CN201241712Y - Primary support structure of large deformation formation tunnel - Google Patents

Primary support structure of large deformation formation tunnel Download PDF

Info

Publication number
CN201241712Y
CN201241712Y CNU2008200300453U CN200820030045U CN201241712Y CN 201241712 Y CN201241712 Y CN 201241712Y CN U2008200300453 U CNU2008200300453 U CN U2008200300453U CN 200820030045 U CN200820030045 U CN 200820030045U CN 201241712 Y CN201241712 Y CN 201241712Y
Authority
CN
China
Prior art keywords
tunnel
deformation
layer
large deformation
support structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2008200300453U
Other languages
Chinese (zh)
Inventor
刘培硕
梁文灏
李国良
刘赪
张剑
杨国柱
张旭珍
贾元霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CNU2008200300453U priority Critical patent/CN201241712Y/en
Application granted granted Critical
Publication of CN201241712Y publication Critical patent/CN201241712Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a large-deformation layer tunnel primary support structure, belonging to the railway tunnel primary support structure technical field. The underground constructions such as tunnel and the like pass the soft rock fracture zone of complex stress conditions, and after excavating tunnel, the stress is released and the tunnel will occur bulking deformation, and is easy to occur large deformation, having large deformation amount, high deformation speed and long lasting time, while the surrounding rock has large area extruding into limitations, therefore, the support is fractured or damaged seriously, and is even instable to bring collapse accidents and high disposal difficulty. The large-deformation layer tunnel primary support structure adopts two-layer support, combining rigidity and flexibility, which is composed of a two-layer sprayed concrete, a system grouting anchor pile, a reinforcing mesh, a steel frame, a locking anchor cable and the like. The structure can effectively inhibit primary large deformation to prevent collapse and can fully release the stress of surrounding rock, to prevent long-time large force on the permanent structure, thereby confirming the structure of safety and reliability.

Description

Large deformation formation tunnel preliminary bracing structure
Technical field
The utility model belongs to railway tunnel preliminary bracing structure field, relates to large deformation formation tunnel preliminary bracing structure.
Background technology
Underground constructions such as tunnel are by the soft rock zone of fracture location of geostatic stress state complex, behind the tunnel excavation, owing to broken bulging deformation takes place stress release, large deformation takes place easily, be characterized in that deflection is big, rate of strain fast, the duration is very long, the country rock large tracts of land is extruded fouling of clearance gauge, and supporting cracking or breakage are very serious, even unstability causes cave-in accident, and intractability is big.
The tunnel preliminary bracing is main force structure, and is most important to guaranteeing the safety during the constructing tunnel, simultaneously, also is main permanent force structure, must accomplish economical rationality, safe and reliable.
Summary of the invention
The purpose of this utility model is to provide a kind of tempers toughness with gentleness, anti-allow in conjunction with and the large deformation formation tunnel preliminary bracing structure of economic and reliable.
For achieving the above object, the technical solution adopted in the utility model is:
Large deformation formation tunnel preliminary bracing structure, its special character is: described large deformation formation tunnel preliminary bracing structure comprises double-layer injection concrete, system's grouting anchor pile, steel mesh reinforcement, steelframe, lock pin anchor cable; The surface in described tunnel is provided with one deck sprayed mortar, the system that radially is provided with grouting anchor pile in the tunnel, on system's grouting anchor pile, the surface of tunnel concrete is provided with steel mesh reinforcement, steelframe, end at system's grouting anchor pile is provided with lock pin anchor cable, and the external surface of its supporting and protection structure is a structure for second layer concrete.
The utility model is with respect to prior art, and its advantage is as follows:
This structure has fully been studied the origin cause of formation and the deformation mechanism of large deformation, tunnel preliminary bracing structure tempers toughness with gentleness, anti-ly allow combination, adopt combining structures such as double-layer injection concrete, system's grouting anchor pile, steel mesh reinforcement, steelframe, lock pin anchor cable, effectively inhibition initial stage excessive deformation is avoided landslide, fully discharge surrouding rock stress simultaneously, avoid permanent structure long-term stressed excessive, guarantee that structural safety is reliable.
Description of drawings
Fig. 1 is a structural section structure chart of the present utility model.
The specific embodiment
Referring to Fig. 1, the utility model large deformation formation tunnel preliminary bracing structure is characterized in that: described large deformation formation tunnel preliminary bracing structure comprises double-layer injection concrete 1, system's grouting anchor pile 2, steel mesh reinforcement 3, steelframe 4, lock pin anchor cable 5; The surface in described tunnel is provided with one deck sprayed mortar 1, the system that radially is provided with grouting anchor pile 2 in the tunnel, on system's grouting anchor pile 2, the surface of tunnel concrete is provided with steel mesh reinforcement 3, steelframe 4, end at system's grouting anchor pile 2 is provided with lock pin anchor cable 5, and the external surface of its supporting and protection structure is a structure for second layer concrete.
This structure is summed up the practical experience that large deformation is handled in domestic and international tunnel, adopt double-deck supporting, temper toughness with gentleness, partly form by double-layer injection concrete 1, system's grouting anchor pile 2, steel mesh reinforcement 3, steelframe 4, lock pin anchor cable 5 etc. respectively, can effectively control tunnel deformation, guarantee construction and structural safety.
Benching tunnelling method is adopted in the integrating tunnel construction, whole section is divided into arch, second section, bottom three parts to be applied successively, order is first pneumatically placed concrete → install system's grouting anchor pile → layings steel mesh reinforcement → set up steelframe → installations lock pin anchor cable → answer pneumatically placed concrete → reinforcement spray to establish concrete, wherein sprayed mortar divides and carries out for three times, spray just and multiple spray are one deck structure, and it is second layer structure that concrete is established in the reinforcement spray.
This structure has fully been studied the origin cause of formation and the deformation mechanism of large deformation, tunnel preliminary bracing structure tempers toughness with gentleness, anti-ly allow combination, adopt combining structures such as double-layer injection concrete, system's grouting anchor pile, steel mesh reinforcement, steelframe, lock pin anchor cable, effectively inhibition initial stage excessive deformation is avoided landslide, fully discharge surrouding rock stress simultaneously, avoid permanent structure long-term stressed excessive, guarantee that structural safety is reliable.

Claims (1)

1, large deformation formation tunnel preliminary bracing structure is characterized in that: described large deformation formation tunnel preliminary bracing structure comprises double-layer injection concrete (1), system's grouting anchor pile (2), steel mesh reinforcement (3), steelframe (4), lock pin anchor cable (5); The surface in described tunnel is provided with one deck sprayed mortar (1), the system that radially is provided with grouting anchor pile (2) in the tunnel, on system's grouting anchor pile (2), the surface of tunnel concrete is provided with steel mesh reinforcement (3), steelframe (4), end at system's grouting anchor pile (2) is provided with lock pin anchor cable (5), and the external surface of its supporting and protection structure is a structure for second layer concrete.
CNU2008200300453U 2008-08-22 2008-08-22 Primary support structure of large deformation formation tunnel Expired - Fee Related CN201241712Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008200300453U CN201241712Y (en) 2008-08-22 2008-08-22 Primary support structure of large deformation formation tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008200300453U CN201241712Y (en) 2008-08-22 2008-08-22 Primary support structure of large deformation formation tunnel

Publications (1)

Publication Number Publication Date
CN201241712Y true CN201241712Y (en) 2009-05-20

Family

ID=40715009

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008200300453U Expired - Fee Related CN201241712Y (en) 2008-08-22 2008-08-22 Primary support structure of large deformation formation tunnel

Country Status (1)

Country Link
CN (1) CN201241712Y (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103032080A (en) * 2012-12-21 2013-04-10 江苏建筑职业技术学院 Support method of weak and broken surrounding rock tunnel
CN103244146A (en) * 2013-05-14 2013-08-14 中铁二十一局集团第四工程有限公司 Construction method for steel frame connection in tunnel anchor-plate retaining
CN103244147A (en) * 2013-05-14 2013-08-14 中铁二十一局集团第四工程有限公司 Construction method for locking anchor tubes of tunnel anchor-plate retaining steel frames
CN103527219A (en) * 2013-10-18 2014-01-22 四川省交通运输厅公路规划勘察设计研究院 Tunnel supporting structure used for large deformation stratum and construction method of tunnel supporting structure
CN103939112A (en) * 2014-05-07 2014-07-23 中铁第一勘察设计院集团有限公司 Down-cross cheuch tunnel double-layer forepoling structure
CN105298524A (en) * 2015-09-14 2016-02-03 中铁二十五局集团第四工程有限公司 Deformation reinforcing method of karst cave tunnel initial support
CN107503779A (en) * 2017-08-01 2017-12-22 中铁十局集团有限公司 A kind of extrusion pressing type Support System in Soft Rock Tunnels prestress anchorage cable group supporting construction and construction technology
CN108661664A (en) * 2018-04-04 2018-10-16 中交第三公路工程局有限公司 A kind of tunnel crushed zone construction method and combination supporting device
CN109184753A (en) * 2018-09-28 2019-01-11 中国电建集团成都勘测设计研究院有限公司 The processing method of limit is invaded for deformation after Tunnel
CN114352358A (en) * 2021-12-28 2022-04-15 中南大学 Dynamic grading control method and system for large deformation of high-ground-stress deep-buried soft rock tunnel

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103032080A (en) * 2012-12-21 2013-04-10 江苏建筑职业技术学院 Support method of weak and broken surrounding rock tunnel
CN103244146A (en) * 2013-05-14 2013-08-14 中铁二十一局集团第四工程有限公司 Construction method for steel frame connection in tunnel anchor-plate retaining
CN103244147A (en) * 2013-05-14 2013-08-14 中铁二十一局集团第四工程有限公司 Construction method for locking anchor tubes of tunnel anchor-plate retaining steel frames
CN103244147B (en) * 2013-05-14 2014-12-17 中铁二十一局集团第四工程有限公司 Construction method for locking anchor tubes of tunnel anchor-plate retaining steel frames
CN103527219B (en) * 2013-10-18 2016-03-16 四川省交通运输厅公路规划勘察设计研究院 For the construction of the tunnel support structure on large deformation stratum
CN103527219A (en) * 2013-10-18 2014-01-22 四川省交通运输厅公路规划勘察设计研究院 Tunnel supporting structure used for large deformation stratum and construction method of tunnel supporting structure
CN103939112A (en) * 2014-05-07 2014-07-23 中铁第一勘察设计院集团有限公司 Down-cross cheuch tunnel double-layer forepoling structure
CN105298524A (en) * 2015-09-14 2016-02-03 中铁二十五局集团第四工程有限公司 Deformation reinforcing method of karst cave tunnel initial support
CN107503779A (en) * 2017-08-01 2017-12-22 中铁十局集团有限公司 A kind of extrusion pressing type Support System in Soft Rock Tunnels prestress anchorage cable group supporting construction and construction technology
CN107503779B (en) * 2017-08-01 2024-04-02 中铁十一局集团有限公司 Extrusion type weak surrounding rock tunnel prestressed anchor cable group supporting structure and construction process
CN108661664A (en) * 2018-04-04 2018-10-16 中交第三公路工程局有限公司 A kind of tunnel crushed zone construction method and combination supporting device
CN109184753A (en) * 2018-09-28 2019-01-11 中国电建集团成都勘测设计研究院有限公司 The processing method of limit is invaded for deformation after Tunnel
CN114352358A (en) * 2021-12-28 2022-04-15 中南大学 Dynamic grading control method and system for large deformation of high-ground-stress deep-buried soft rock tunnel
CN114352358B (en) * 2021-12-28 2022-12-02 中南大学 Dynamic grading control method and system for large deformation of high-ground-stress deep-buried soft rock tunnel

Similar Documents

Publication Publication Date Title
CN201241712Y (en) Primary support structure of large deformation formation tunnel
JP7125550B2 (en) SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH
CN202140098U (en) Large soft rock deformation tunnel supporting structure based on controllable deformation release
CN102937030B (en) Bolting-grouting integrated support method for zonal disintegration of deep roadway surrounding rock
CN103527219B (en) For the construction of the tunnel support structure on large deformation stratum
CN203296780U (en) Supporting and protecting lining device used for preventing surrounding rock from large deformation in underground cavern construction
CN102996149B (en) Support method for bolt-grouting composite crushing dynamic-pressure roadway soft rock roof by high-pre-stressed anchor cable
CN103775092B (en) Tunnels in Shallow Buried tunneling remaining core soil in advance improvement CRD construction
CN101967984B (en) Deep well tunnel cable anchor rigid-flexible coupling support and surrounding rock overall reinforced support method
CN203515604U (en) Tunnel Support structure for schist layer in deformation
CN102337903B (en) Method of active coupling support in time and space for control of minimum deformation of surrounding rock of deep well roadway
CN203452799U (en) Corrugated steel tunnel supporting structure
CN101769154A (en) Excavation supporting method for tunnel construction
CN102650212B (en) Construction method for protecting partition wall in double-arch tunnel through temporary support of middle pilot tunnel
CN101338678A (en) Supporting arch hidden digging top-down construction method
CN101539021B (en) Road tunnel excavation method
CN108518229A (en) Large deformation weak broken wall rock outsized section tunnel excavation supporting structure and construction method
CN103032080A (en) Support method of weak and broken surrounding rock tunnel
CN208236427U (en) Large deformation weak broken wall rock outsized section tunnel excavation supporting structure
CN110230497A (en) A kind of positive barrel double -side approach construction method in threaded list road
CN104453948A (en) Vertical prestress steel pipe supporting structure for large-section subsurface tunnel and construction process
CN102606173B (en) Construction method for treating tunnel deformation segment and accelerating tunneling
CN104120739A (en) Multi-pilot tunnel excavation one-off arching construction method
CN204436407U (en) The structure that the pre-Geological disaster prevention of the double-deck preliminary bracing of a kind of big cross section Support System in Soft Rock Tunnels occurs
CN105386779A (en) Arch column method for building large-scale underground structure in shallow buried rock stratums

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090520

Termination date: 20170822