CN201228440Y - Horizontal moving device for large steel formwork system - Google Patents

Horizontal moving device for large steel formwork system Download PDF

Info

Publication number
CN201228440Y
CN201228440Y CNU200820040761XU CN200820040761U CN201228440Y CN 201228440 Y CN201228440 Y CN 201228440Y CN U200820040761X U CNU200820040761X U CN U200820040761XU CN 200820040761 U CN200820040761 U CN 200820040761U CN 201228440 Y CN201228440 Y CN 201228440Y
Authority
CN
China
Prior art keywords
adjusting screw
large steel
wheels
moulding plate
rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU200820040761XU
Other languages
Chinese (zh)
Inventor
瞿启忠
卞飞亚
丁春颖
丁海峰
黄晓松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongzhou Construction General Contracting Group Co ltd
Original Assignee
Tongzhou Construction General Contracting Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongzhou Construction General Contracting Group Co ltd filed Critical Tongzhou Construction General Contracting Group Co ltd
Priority to CNU200820040761XU priority Critical patent/CN201228440Y/en
Application granted granted Critical
Publication of CN201228440Y publication Critical patent/CN201228440Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a big steel form system horizontal migration device keeps the infrastructure of original big steel form system unchanged, all installs the wheel on the preceding adjusting screw on the horizontal stiffening rib of big steel form back lower extreme and on the support frame rear portion dead lever. During construction, the front adjusting screw with the wheels rotates downwards to enable the wheels to extend out and be inserted with the fixing bolts, and the rear adjusting screw on the supporting frame rotates upwards to be separated from the ground, so that the large steel formwork supporting system can be pushed (pulled) to an installation place by an operator. And after the ideal position is reached, pulling out the fixing bolt, upwards rotating the front adjusting screw rod with the wheels to enable the wheels to retract, downwards rotating the rear adjusting screw rod on the supporting frame to land, carefully checking the mounting precision of the template, and finishing the template mounting. The system is simple to operate, the construction speed of the concrete wall can be effectively guaranteed, and the construction efficiency of tower crane equipment is greatly improved.

Description

A kind of large steel moulding plate system horizontally moving device
(1) technical field
The utility model is about a kind of large steel moulding plate system horizontally moving device.
(2) background technology
Large steel moulding plate system deadweight in the existing concrete wall construction is bigger, under the situation that does not have the hanging device coordinative construction, manpower can't be moved operation, and its construction is stronger to the dependence of hanging devices such as tower crane, thereby increased the burden of tower crane, influenced the speed of application of whole engineering.
(3) summary of the invention
In order to overcome above-mentioned defective, the utility model provides a kind of operation comparatively simple, effectively guarantees the concrete wall speed of application, significantly improves the large steel moulding plate system horizontally moving device of the efficiency of construction of tower crane equipment.
The technical scheme in the invention for solving the technical problem is: keep the basic boom of original large steel moulding plate system constant, a plurality of wheels are installed on the large steel moulding plate system, 2~4 preceding adjusting screw(rod)s promptly are housed on the horizontal ribs of lower end, the large steel moulding plate back side, wheel all is equipped with in every preceding adjusting screw(rod) lower end, every Pin bracing frame rear portion of large steel moulding plate is welded with fixed bar in addition, and wheel all is equipped with in the fixed bar lower end.During construction the preceding adjusting screw(rod) of belt wheel is rotated down and wheel is stretched out and plugs the appended Fixed latches of screw tip, the back adjusting screw(rod) on the bracing frame is rotated up liftoff, then the large steel moulding plate system can be pushed away (drawing) by the operator to the infield.After waiting to arrive ideal position, take out Fixed latches, the preceding adjusting screw(rod) of belt wheel is rotated up make the wheel indentation, the back adjusting screw(rod) on the bracing frame is rotated down lands, and carefully check the installation accuracy of template, then template installation.Like this between the large steel moulding plate installation period, the task of tower crane be with the handling of large steel moulding plate system to relevant flooring, all the other can be installed voluntarily by the operator.Also help simultaneously the large steel moulding plate system and preceding workman is installed in large steel moulding plate bottom stickup leakproof adhesive tape.
The beneficial effects of the utility model are that the installation that has changed large steel moulding plate system in traditional technology relies on hanging devices such as tower crane fully, can effectively alleviate the burden of tower crane, improve speed of application.
(4) description of drawings
The utility model is described in further detail below in conjunction with drawings and Examples.
Fig. 1 is the three-dimensional view of the utility model embodiment
Among the figure: 1, large steel moulding plate, 2, formwork-support, 3, the vertical ribs of template, 4, the horizontal ribs of template, 5, preceding adjusting screw(rod), 6, the back adjusting screw(rod), 7, fixed bar, 8, wheel, 9, Fixed latches, 10, pin hole
(5) specific embodiment
The specific embodiment: the system handling of large steel moulding plate 1 and bracing frame 2 being made of tower crane is to relevant flooring, preceding adjusting screw(rod) 5 is rotated down wheel 8 is stretched out and plugs the appended Fixed latches 9 of screw tip and advance pin hole 10, general back adjusting screw(rod) 6 rotates up liftoff, and then the large steel moulding plate support system can be pushed away (drawing) by the operator to the infield.After waiting to arrive ideal position, take out Fixed latches 9, and preceding adjusting screw(rod) 5 rotated up make the wheel indentation, will back adjusting screw(rod) 6 be rotated down and land, and carefully check the installation accuracy of template, then template installation.

Claims (3)

1, a kind of large steel moulding plate system horizontally moving device is characterized in that: 2~4 preceding adjusting screw(rod)s are housed on the horizontal ribs of lower end, the large steel moulding plate back side, and preceding adjusting screw(rod) is connected with the ribs spiral, and wheel all is equipped with in every preceding adjusting screw(rod) lower end.
2, large steel moulding plate system horizontally moving device according to claim 1 is characterized in that: preceding adjusting screw(rod) top is all with Fixed latches, and Fixed latches passes pin hole grafting on preceding adjusting screw(rod) top and the vertical ribs in the large steel moulding plate back side.
3, large steel moulding plate system horizontally moving device according to claim 1 is characterized in that: every Pin bracing frame rear portion of large steel moulding plate all is welded with fixed bar, and wheel all is equipped with in the fixed bar lower end.
CNU200820040761XU 2008-07-07 2008-07-07 Horizontal moving device for large steel formwork system Expired - Fee Related CN201228440Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU200820040761XU CN201228440Y (en) 2008-07-07 2008-07-07 Horizontal moving device for large steel formwork system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU200820040761XU CN201228440Y (en) 2008-07-07 2008-07-07 Horizontal moving device for large steel formwork system

Publications (1)

Publication Number Publication Date
CN201228440Y true CN201228440Y (en) 2009-04-29

Family

ID=40633391

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU200820040761XU Expired - Fee Related CN201228440Y (en) 2008-07-07 2008-07-07 Horizontal moving device for large steel formwork system

Country Status (1)

Country Link
CN (1) CN201228440Y (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102653937A (en) * 2012-05-10 2012-09-05 中铁四局集团第一工程有限公司 Concrete construction template bracket for high speed rotary road of automobile test field and construction method
CN105926929A (en) * 2014-10-15 2016-09-07 中铁四局集团有限公司 Concrete pouring construction method for a straight wall
CN106744405A (en) * 2016-11-13 2017-05-31 无锡晟欧船舶设备有限公司 A kind of mobile rubbish hangs
CN109208510A (en) * 2018-09-11 2019-01-15 江苏正交通设施有限公司 A kind of road guard
CN112315735A (en) * 2020-10-27 2021-02-05 宜昌市中心人民医院(三峡大学第一临床医学院、三峡大学附属中心人民医院) Electronic multi-functional rehabilitation training frame of integration

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102653937A (en) * 2012-05-10 2012-09-05 中铁四局集团第一工程有限公司 Concrete construction template bracket for high speed rotary road of automobile test field and construction method
CN102653937B (en) * 2012-05-10 2014-05-07 中铁四局集团第一工程有限公司 Concrete construction template bracket for high speed rotary road of automobile test field and construction method
CN105926929A (en) * 2014-10-15 2016-09-07 中铁四局集团有限公司 Concrete pouring construction method for a straight wall
CN105926929B (en) * 2014-10-15 2018-01-30 中铁四局集团有限公司 A kind of pouring construction method of straight wall concrete
CN106744405A (en) * 2016-11-13 2017-05-31 无锡晟欧船舶设备有限公司 A kind of mobile rubbish hangs
CN109208510A (en) * 2018-09-11 2019-01-15 江苏正交通设施有限公司 A kind of road guard
CN109208510B (en) * 2018-09-11 2021-05-07 江苏正一交通设施有限公司 Road guardrail
CN112315735A (en) * 2020-10-27 2021-02-05 宜昌市中心人民医院(三峡大学第一临床医学院、三峡大学附属中心人民医院) Electronic multi-functional rehabilitation training frame of integration
CN112315735B (en) * 2020-10-27 2023-12-29 宜昌市中心人民医院(三峡大学第一临床医学院、三峡大学附属中心人民医院) Integrated electric multifunctional rehabilitation training frame

Similar Documents

Publication Publication Date Title
CN201228440Y (en) Horizontal moving device for large steel formwork system
CN205527407U (en) Building hoisting machine
CN202090572U (en) Wall plastering machine for decorating building
CN202544854U (en) Lining trolley for subway station
CN202850484U (en) Safety mechanism for building construction climbing template
CN102794724B (en) A kind of tooling device used for locating web plate
CN203175052U (en) Leveler for building floor beam slab construction
CN201221365Y (en) Front cantilever temporary support
CN204040450U (en) A kind of for angle connector in tools type section steel builder's jack
CN204455779U (en) Combined type channel-section steel formwork leverage
CN201962924U (en) Putty scraping machine
CN204283455U (en) Novel thin coal seam filling hydraulic support
CN203514751U (en) Convenient-to-move scaffold for building interior wall construction
CN201447862U (en) Instrumental operating platform used for elevator shaft shear wall shuttering erection
CN201339311Y (en) Turning plate device of hanging rack
CN214739838U (en) Dish knot formula scaffold frame based on BIM
CN110905206A (en) Overhanging discharging platform with drawing type channel and construction method
CN106836807A (en) It is a kind of can quick-assembling and mobile modular rack application method
CN209704074U (en) A kind of building structure strengthening device
CN109518947A (en) A kind of structure corner support construction of fast demountable
CN203145017U (en) Large-sized chute device for pouring mass concrete into deep foundation pit
CN209556361U (en) A kind of eminence overhanging erecting device
CN203160669U (en) Integrated inclined ladder structure used for putting up vertical pedestrian path in scaffold
CN204265249U (en) A kind of transfer crane and portal frame thereof
CN205243097U (en) Building builder's temporary shed

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090429

Termination date: 20170707