CN201140783Y - Composed scaffold - Google Patents

Composed scaffold Download PDF

Info

Publication number
CN201140783Y
CN201140783Y CNU2007200776450U CN200720077645U CN201140783Y CN 201140783 Y CN201140783 Y CN 201140783Y CN U2007200776450 U CNU2007200776450 U CN U2007200776450U CN 200720077645 U CN200720077645 U CN 200720077645U CN 201140783 Y CN201140783 Y CN 201140783Y
Authority
CN
China
Prior art keywords
scaffold
strap
chuck
bar
assembly
Prior art date
Application number
CNU2007200776450U
Other languages
Chinese (zh)
Inventor
聂家平
朱越成
Original Assignee
上海外高桥造船有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 上海外高桥造船有限公司 filed Critical 上海外高桥造船有限公司
Priority to CNU2007200776450U priority Critical patent/CN201140783Y/en
Application granted granted Critical
Publication of CN201140783Y publication Critical patent/CN201140783Y/en

Links

Abstract

A combined type scaffold comprises a chuck which is hung on the upper edge of cabin walls, a connecting strip which is connected with the chuck and is pressed on the cabin wall, and a plurality of cross rods which are connected with the connecting strip. The utility model can increase the installation and detachment speed of the scaffold, reduces labor and material resources, and reduces cost and increase efficiency. When the scaffold is applied in the building process of each ship, the scaffold can bring long-term economic benefits.

Description

Assembly scaffold

Technical field

The utility model relates to boats and ships scaffold parts, particularly relates to a kind of assembly scaffold that carries out construction operation on vertical bulkhead of segmentation or the straight outside plate that is installed in.

Background technology

In the shipbuilding field, the needed scaffold of on vertical bulkhead of segmentation or straight outside plate, constructing, domestic extensive employing pipe pin hand form.Though this form is simple, shortcoming also clearly: poor stability, pipe is too much, outward appearance is not attractive in appearance.

The utility model content

The purpose of this utility model provides that a kind of intensity is good, Stability Analysis of Structures, easy accessibility, be convenient to the assembly scaffold of construction operation.

The purpose of this utility model is achieved through the following technical solutions:

A kind of assembly scaffold, its characteristics are that it comprises that one hangs over the chuck of bulkhead upper edge, one be connected with this chuck be resisted against connecting strap on this bulkhead and some and this connecting strap bonded assembly cross bar.

Wherein, this chuck and this connecting strap top all are provided with some cooresponding holes, and this chuck is connected by the bolt that passes this corresponding aperture with this connecting strap.

Wherein, also be provided with a wire rope hole that is used for fixing usefulness on this chuck.

Wherein, this connecting strap is provided with some equally spaced holes, and an end of this cross bar also is provided with the cooresponding cross bar hole in hole on some and this connecting strap, and this connecting strap is connected by the bolt that passes this corresponding aperture with this cross bar.

Wherein, this cross bar is provided with a socket that is used to insert railing post away from an end of this cross bar hole.

Wherein, this socket is a steel pipe.

Positive progressive effect of the present utility model is: improve the Assembly ﹠Disassembly speed of scaffold, reduce manpower and materials, cost-cutting is raised the efficiency; When in the manufacture process that is applied to every ship-related products, more can bring long-term economic benefit.

Description of drawings

Fig. 1 is the structural representation of the utility model preferred embodiment.

Fig. 2 is the structural representation of chuck in the utility model preferred embodiment.

Fig. 3 is the structural representation of connecting strap in the utility model preferred embodiment.

Fig. 4 is the structural representation of cross bar in the utility model preferred embodiment.

Fig. 5 is the enforcement constitution diagram of the utility model preferred embodiment.

The specific embodiment

Provide the utility model preferred embodiment below in conjunction with accompanying drawing, to describe the technical solution of the utility model in detail.

Be depicted as constructional drawing of the present utility model as Fig. 1-4.Assembly scaffold of the present utility model comprises: chuck 1, connecting strap 2, cross bar 3.Chuck 1 adopts the steel plate of δ 12, makes the shape of hook.Chuck 1 is used for assembly scaffold is hung over the upper edge place of vertical wall 4 and the weight of bearing whole scaffold.Have the collet bore 11 of 2 Φ 22mm on the chuck 1, be used for chuck 1 and connecting strap 2 are connected by bolt, have the wire rope hole 12 of 1 Φ 30mm on the chuck 1 in addition, this hole can be used to assembly scaffold be carried out better fixing by steel rope.

Connecting strap 2 adopts the band steel of 10*80*2134, and length is 2134mm.Have the connection cylindrical void 21 of 17 Φ 22mm on the band steel by constant spacing, the effect in these holes is to use bolt to connect miscellaneous part (as chuck 1, cross bar 3 and other connecting straps 2), and can regulate the height of scaffold by the position that changes point of connection.

Cross bar 3 adopts the angle steel of Φ 75*75*8 to make.One end of cross bar 3 has the cross bar hole 31 of 2 Φ 22mm, is used for being connected with connecting strap 2 by bolt, and the hot rolled seamless steel tube 32 of one section Φ 42*4 of other end welding, length is 120mm, is used for doing the socket of protection railing column 5.When railing post 5 is connected with steel pipe 32, only needs that steel pipe 32 is inserted in the bottom of railing post 5 and get final product, the bottom of railing post 5 is the welded pipees that adopt Φ 33.5, and the space is very little between the socket, can not produce big becoming flexible.Cross bar 3 is used for lay foot plank 6.

During combination, with chuck 1 and connecting strap 2, connecting strap 2 and cross bar 3,2 connecting straps 2 connect the junction bolt by the hole of 2 Φ 22mm up and down.

It more than is exactly the structure of single assembly scaffold.During practical application, as shown in Figure 5, realize the installation of scaffold by several assembly scaffolds.During installation,, determine required assembly scaffold number, after on the ground assembly scaffold being made up, assembly scaffold is hung over the upper edge of vertical wall by certain interval at first according to the length of vertical wall; Secondly, foot plank 6 is laid on same one deck cross bar 3 of two adjacent assembly scaffolds, and fixes with pricking the silk colligation; Then, the steel pipe 32 with railing post 5 inserts on the cross bar 3 installs protection railing 7.By this kind mode, the assembly scaffold that all are adjacent all lays foot plank 6 and installs protection railing 7.So just finished the installation of scaffold.Also very convenient during dismounting, remove earlier protection railing 7 and foot plank 6, assembly scaffold is hung to dismantle behind the vertical wall again and get final product.

The utility model is not limited to above embodiment, only is to be casehistory such as above data, and concrete numerical value is decided on actual conditions.

Claims (6)

1, a kind of assembly scaffold is characterized in that, it comprises that one hangs over the chuck of bulkhead upper edge, one be connected with this chuck be resisted against connecting strap on this bulkhead and some and this connecting strap bonded assembly cross bar.
2, assembly scaffold according to claim 1 is characterized in that, this chuck and this connecting strap top all are provided with some cooresponding holes, and this chuck is connected by the bolt that passes this corresponding aperture with this connecting strap.
3, assembly scaffold according to claim 2 is characterized in that, also is provided with a wire rope hole that is used for fixing usefulness on this chuck.
4, assembly scaffold according to claim 3, it is characterized in that, this connecting strap is provided with some equally spaced holes, and an end of this cross bar also is provided with the cooresponding cross bar hole in hole on some and this connecting strap, and this connecting strap is connected by the bolt that passes this corresponding aperture with this cross bar.
5, assembly scaffold according to claim 4 is characterized in that, this cross bar is provided with a socket that is used to insert railing post away from an end of this cross bar hole.
6, assembly scaffold according to claim 5 is characterized in that, this socket is a steel pipe.
CNU2007200776450U 2007-12-28 2007-12-28 Composed scaffold CN201140783Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200776450U CN201140783Y (en) 2007-12-28 2007-12-28 Composed scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200776450U CN201140783Y (en) 2007-12-28 2007-12-28 Composed scaffold

Publications (1)

Publication Number Publication Date
CN201140783Y true CN201140783Y (en) 2008-10-29

Family

ID=40068497

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200776450U CN201140783Y (en) 2007-12-28 2007-12-28 Composed scaffold

Country Status (1)

Country Link
CN (1) CN201140783Y (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102145739A (en) * 2011-03-14 2011-08-10 沪东中华造船(集团)有限公司 Scaffold suitable for cargo hold area
CN101380993B (en) * 2008-10-24 2012-05-30 沪东中华造船(集团)有限公司 Detachable welding hanging bar for welding large-sized vertical joint
CN102785766A (en) * 2012-09-03 2012-11-21 广东中远船务工程有限公司 Novel scaffold fixture combination for ships
CN101844612B (en) * 2009-03-24 2013-04-24 上海外高桥造船有限公司 Fabricated scaffold and using method thereof
CN105000153A (en) * 2015-06-25 2015-10-28 上海外高桥造船有限公司 Scaffold horse and scaffold building method
CN106335605A (en) * 2016-10-17 2017-01-18 上海江南长兴造船有限责任公司 Method for erecting scaffold handrails for top of hatch coaming
CN107434009A (en) * 2017-08-28 2017-12-05 上海江南长兴造船有限责任公司 A kind of scaffold building method based on structural perforate
CN109398644A (en) * 2018-11-06 2019-03-01 南通中远海运川崎船舶工程有限公司 A kind of disassembling method of foot hand equipment peculiar to vessel

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101380993B (en) * 2008-10-24 2012-05-30 沪东中华造船(集团)有限公司 Detachable welding hanging bar for welding large-sized vertical joint
CN101844612B (en) * 2009-03-24 2013-04-24 上海外高桥造船有限公司 Fabricated scaffold and using method thereof
CN102145739A (en) * 2011-03-14 2011-08-10 沪东中华造船(集团)有限公司 Scaffold suitable for cargo hold area
CN102785766A (en) * 2012-09-03 2012-11-21 广东中远船务工程有限公司 Novel scaffold fixture combination for ships
CN102785766B (en) * 2012-09-03 2016-01-20 广东中远船务工程有限公司 New Marine scaffold tooling combination
CN105000153A (en) * 2015-06-25 2015-10-28 上海外高桥造船有限公司 Scaffold horse and scaffold building method
CN105000153B (en) * 2015-06-25 2018-05-04 上海外高桥造船有限公司 Foot hand horse and the method for scaffold building
CN106335605A (en) * 2016-10-17 2017-01-18 上海江南长兴造船有限责任公司 Method for erecting scaffold handrails for top of hatch coaming
CN107434009A (en) * 2017-08-28 2017-12-05 上海江南长兴造船有限责任公司 A kind of scaffold building method based on structural perforate
CN107434009B (en) * 2017-08-28 2019-06-18 上海江南长兴造船有限责任公司 A kind of scaffold building method based on structural aperture
CN109398644A (en) * 2018-11-06 2019-03-01 南通中远海运川崎船舶工程有限公司 A kind of disassembling method of foot hand equipment peculiar to vessel

Similar Documents

Publication Publication Date Title
CN102979304B (en) Construction method of double shear wall formworks at deformation joint of high-rise building
CN103243817B (en) A kind of assembled beam-column attachment means
CN104453197B (en) High Large Cantilever concrete structural steel shape supports platform
CN104196222B (en) The suspension scaffold of tools type section steel builder's jack
CN102031866A (en) Removal-free thermal insulation decorative template and mounting method thereof
CN202469251U (en) Combined support hanger
CN101858057B (en) Method for rapidly mounting reinforced concrete crash barrier steel form
CN204386134U (en) The attached mould scaffold of a kind of concrete cylindrical hoop
CN203403661U (en) Detachable triangular support
CN102454218B (en) Tube-in-tube structure for reinforced concrete core tubes and integrally-assembled space steel grids
CN104110086A (en) Suspended dome and plane prestress combined structure, tensioning tool and construction method
CN203462764U (en) Large cantilever promotion counter-force frame
CN201521101U (en) Safety scaffold
CN203080911U (en) Inner formwork for concrete walls at deformation joint
CN201546436U (en) Platform for construction of high-altitude suspension structures
CN202416184U (en) Construction device for formwork for longitudinal wet joint of box girder
CN103352563A (en) Self plate-bearing type steel bar mesh support combined template and construction method thereof
CN201598820U (en) Single point suspension external hanging bracket
CN102425306A (en) Construction method of steel reinforced truss floor decking plate and steel reinforced truss floor decking plate
CN207419520U (en) Piping lane construction template component
CN101736893A (en) Overhanging type scaffold supporting system
CN203514309U (en) Steel strand anchorage device base
CN103104092A (en) Support composite structure of beam and slab
CN105350759A (en) Suspended scaffold
CN201546435U (en) Bolted stayed cantilever scaffold

Legal Events

Date Code Title Description
GR01 Patent grant
C14 Grant of patent or utility model
TR01 Transfer of patent right

Effective date of registration: 20100611

Address after: 201913 No. 2468 Jiangnan Road, Changxin Township, Chongming County, Shanghai, Changxin

Patentee after: Shanghai Jiangnan Changxing Shipbuilding Co., Ltd.

Address before: 200137 Shanghai city Pudong New Area Zhouhai Road No. 3001

Patentee before: Shanghai Waigaoqiao Shipbuilding Co., Ltd.

COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 200137 NO.3001, ZHOUHAI ROAD, PUDONG NEW AREA, SHANGHAI CITY TO: 201913 NO.2468, CHANGXING JIANGNAN AVENUE, CHANGXING TOWNSHIP, CHONGMING COUNTY, SHANGHAI CITY

ASS Succession or assignment of patent right

Owner name: SHANGHAI JIANGNAN CHANGXING SHIPBUILDING CO., LTD.

Free format text: FORMER OWNER: SHANGHAI WAIGAOQIAO SHIPBUILDING CO., LTD.

Effective date: 20100611

C41 Transfer of patent application or patent right or utility model
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081029

Termination date: 20161228

CF01 Termination of patent right due to non-payment of annual fee