CN201024903Y - An artesian well tower - Google Patents

An artesian well tower Download PDF

Info

Publication number
CN201024903Y
CN201024903Y CNU2006201284675U CN200620128467U CN201024903Y CN 201024903 Y CN201024903 Y CN 201024903Y CN U2006201284675 U CNU2006201284675 U CN U2006201284675U CN 200620128467 U CN200620128467 U CN 200620128467U CN 201024903 Y CN201024903 Y CN 201024903Y
Authority
CN
China
Prior art keywords
derrick
tower
boring tower
boring
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2006201284675U
Other languages
Chinese (zh)
Inventor
靳益民
高淑芳
宋秋峰
孔祥旺
张西坤
刘凤荣
宋小娟
朱彩华
芦广杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BORING MACHINERY PLANT HEBEI CONSTRUCTION PROSPECTING INST Co Ltd
Original Assignee
BORING MACHINERY PLANT HEBEI CONSTRUCTION PROSPECTING INST Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BORING MACHINERY PLANT HEBEI CONSTRUCTION PROSPECTING INST Co Ltd filed Critical BORING MACHINERY PLANT HEBEI CONSTRUCTION PROSPECTING INST Co Ltd
Priority to CNU2006201284675U priority Critical patent/CN201024903Y/en
Application granted granted Critical
Publication of CN201024903Y publication Critical patent/CN201024903Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a boring tower which is used for boring deep well, comprising a well rack, an overhead crane, a racking platform, a vertical tube platform, a work ladder and a base seat. The well rack is provided with four main tower posts. The left side, the right side and the back side of the well rack are integrated into a whole through the four main tower posts. The upper segment of the front side of the well rack is connected with a truss, while the lower segment takes a front opening structure. The cross section of the lower segment of the well rack takes an open n-shaped space structure so that the drill rod and the vertical root can pass through. A herringbone-shaped lifting rack which is used for lifting and laying the well rack horizontally is arranged between the base seat positioned at the back of the well rack and the well rack. The utility model has the advantages that the n-shaped structure formed by the four main tower posts increases the operation space inside the well boring tower and increase the stability of the boring tower; and the top segment of the boring tower is made into a closed space frame structure, and the four sides of the structure is connected with a truss, thereby increasing the stability of the whole device. Besides, the whole boring tower is designed into a truss structure with five segments, which is convenient for mounting and demounting and is also convenient for transporting.

Description

A kind of boring tower
Technical field
The utility model relates to a kind of a kind of boring tower that drills for oil and use when well or other deep-well.
Background technology
The A font structure derrick that the boring tower of the at present general usefulness that drills for oil all is made up of three king-posts.The latter half of headframe has only two faces to be provided with drag link and the diagonal member that connects king-post, and syndeton is not very stable.Spatial content is smaller in the boring tower that other three king-posts are formed, tower, deposits the limited amount of drilling rod, and boring tower is generally overall structure, install and transportation very inconvenient.
Summary of the invention
The technical problems to be solved in the utility model provides that a kind of Stability Analysis of Structures, spatial content are big, the boring tower of easy accessibility.
The technical scheme in the invention for solving the above technical problem is:
Comprise derrick, overhead traveling crane, quadruple board platform, standpipe platform, working stand, man-like shelf, base, the king-tower post of derrick has four, and left and right, back three of derrick connect as one four king-tower posts by truss.This derrick is the open front formula, and cross section is a not enclosure space structure of ∏ type.Be provided with on the base at derrick rear and between the derrick and rise and set level the herringbone hoisting rack that derrick is used.
Further improvement of the utility model is: the epimere in the derrick front also has truss to connect, and hypomere is that three of open front formulas are by the truss syndeton.
Further improvement of the utility model is: the derrick main body is divided into five sections, and every section trussed construction is identical, and each drag link, diagonal member are little flexibility depression bar.Connected by four bearing pins between each section, each junction also is provided with the attached plate of strengthening usefulness.
The herringbone hoisting rack that derrick rear and base rear are provided with is the device that derrick telescoping is used, couple together by the two-dimensional person cabinet frame of four bearing pins by cross bearer two monolithics, crossbeam adopts major diameter tubing, every side two connecting pins distance is big, simultaneously crossbeam center line and the cantilevered wheels dead in line that is contained on the herringbone hoisting rack, effectively balance the torsional moment that produces in the process that hoists.The man-like shelf foreleg is made up of two i iron, and leg centre position, front and back adds connecting rod and connects, the strut stability of leg before and after having improved.Cross bearer is provided with the third wheel of belt length axle, is used for changing the direction of winch drum to the wire rope of overhead traveling crane.Derrick hoists and finishes, and is locked by U-bolt and derrick body, and man-like shelf just constitutes derrick hypomere ingredient.
Further improvement of the utility model is: the shaped steel size of the bottom joint of the king-tower post of boring tower is greater than the shaped steel size of other joint, thereby the center of gravity of whole derrick is reduced, and strengthens resistance to overturning.
3.6 ° of whole rig front gradients, 0.8 ° of the unidirectional gradient in side, the derrick rigidity of section is nonlinear change, makes whole derrick when satisfying applying working condition to greatest extent, have enough intensity and stability, and it is minimum that material consumption is reduced to.
Further improvement of the utility model is: the boring tower rope sheave that hoists adopts shift sleeve structure.
Further improvement of the utility model is: base branch foreground and backstage two parts are carriers of whole rig and derrick; The foreground comprises several parts such as foreground base, thribble platform, table beam, winch beam, end straining beam, basis for the rig equipment, thribble beam, table beam, winch beam are the heavy in section welding I beam, be connected with the left and right sides base on foreground by upper and lower twice bearing pin respectively, its underpart connects whole foreground by several end straining beams as a whole, makes base have good steadiness when work; The backstage is the base of drilling rig power plant and transmission device thereof; AM/BAM is connected by eight bearing pins, and this structure makes rig have integral rigidity and stability preferably.When rig finishes displacement in boring, needn't just can carry out integral translation by derrick lowering.
The technological progress that the utility model is obtained is:
With four king-tower posts boring tower is made the structure that the cross section is the ∏ type, increased the working space in the boring tower, also increased the stability of boring tower; Whole boring tower is arranged to five sections trussed construction, easy disassembling, also convenient transportation.The epimere of boring tower is made the enclosure space frame construction that the four sides has truss to connect, and has strengthened resistance to overturning.Connection between each section of boring tower is to be connected the bearing pin connection with four by strengthening attached plate connection, and contact area connects increase greatly than the bearing pin of A type tower, thereby has improved the resistance to overturning and the supporting capacity of derrick.Four king-tower posts leave derrick plane section centre of form axle farthest, give full play to the effect of material.
For guaranteeing that derrick has big rigidity at place near the ground, on the first segment tower leg, adopt heavy one-level shaped steel, thereby the supporting capacity of whole derrick is improved.
Derrick hoists and uses man-like shelf both sides third wheel central axis and be connected the crossbeam central lines, has eliminated the bad moment of torsion that produces in the process that hoists.The whole pull-up of the derrick that derrick adopts equipment of itself to connect on ground or put down, it is convenient and reliable to rise and fall.
The boring tower rope sheave that hoists adopts the sliding sleeve form, improves dependability, reduces cost.
Description of drawings
Fig. 1 is a structural representation of the present utility model; Fig. 2 is a side structure schematic diagram of the present utility model.
Wherein: 1, base, 2, derrick, 3, quadruple board platform, 4, overhead traveling crane, 5, the back diagonal member, 6, the side diagonal member, 7, drag link, 8, the herringbone hoisting rack, 9, the standpipe platform.
The specific embodiment
Below in conjunction with accompanying drawing the utility model is done explanation in further detail.
Embodiment as shown in Figure 1 and Figure 2 as can be known, it comprises derrick 2, overhead traveling crane 4, quadruple board platform 3, standpipe platform 9, working stand, herringbone hoisting rack 8, base 1, the king-tower post of derrick 2 has four, left and right, back three of derrick 2 connect as one four king-tower posts by truss, and these truss comprise the drag link 7 on back diagonal member 5, side diagonal member 6 and three faces.Epimere in derrick 2 fronts also has truss to connect, hypomere then for three of open front formulas by the truss syndeton.The cross section of these derrick 2 hypomeres is a not enclosure space structure of ∏ type, passes through for drilling rod, thribble.
It is five sections that derrick 2 main bodys of the present utility model are divided into, and every section trussed construction is identical, and each drag link, diagonal member are little flexibility depression bar.Connected by four bearing pins between each section, each junction also is provided with the attached plate of strengthening usefulness.Be provided with herringbone hoisting rack 8 between derrick 2 rears and the base 1, herringbone hoisting rack 8 is to hoist or set level the device that derrick is used, couple together by the two-dimensional person cabinet frame of four bearing pins by cross bearer two monolithics, crossbeam adopts major diameter tubing, every side two connecting pins distance is big, simultaneously crossbeam center line and the cantilevered wheels dead in line that is contained on the herringbone hoisting rack 8, the torsional moment that hoists and produce in the process with the balance boring tower.Herringbone hoisting rack 8 forelegs are made up of two i iron, and leg centre position, front and back adds connecting rod and connects, with the strut stability of leg before and after improving.Cross bearer is provided with the third wheel of belt length axle, is used for changing the direction of winch drum to the wire rope of overhead traveling crane.Derrick hoists and finishes, and is locked by U-bolt and derrick body, and herringbone hoisting rack 8 just constitutes derrick hypomere ingredient.Boring tower bottom one saves the shaped steel size of the shaped steel size of king-tower post greater than other joint, thereby the center of gravity of whole derrick is reduced, and strengthens resistance to overturning.
3.6 ° of whole rig front gradients, 0.8 ° of the unidirectional gradient in side, the derrick rigidity of section is nonlinear change, makes whole derrick when satisfying applying working condition to greatest extent, have enough intensity and stability, and it is minimum that material consumption is reduced to.
The boring tower rope sheave that hoists adopts shift sleeve structure.
1 fen foreground of base and backstage two parts are carriers of whole rig and derrick; The foreground comprises several parts such as foreground base, thribble platform, table beam, winch beam, end straining beam, basis for the rig equipment, thribble beam, table beam, winch beam are the heavy in section welding I beam, be connected with the left and right sides base on foreground by upper and lower twice bearing pin respectively, its underpart connects whole foreground by several end straining beams as a whole, makes base have good steadiness when work; The backstage is the base of drilling rig power plant and transmission device thereof; AM/BAM is connected by eight bearing pins, and this structure makes rig have integral rigidity and stability preferably.When rig finishes displacement in boring, needn't just can carry out integral translation by derrick lowering.

Claims (6)

1. a boring tower comprises derrick, overhead traveling crane, quadruple board platform, standpipe platform, working stand, base, it is characterized in that: the king-tower post of derrick has four, and left and right, back three of derrick connect as one four king-tower posts by truss; Be provided with on the base at derrick rear and between the derrick and rise and set level the herringbone hoisting rack that derrick is used.
2. a kind of boring tower according to claim 1 is characterized in that the epimere of described derrick front also has truss to connect.
3. a kind of boring tower according to claim 1 is characterized in that described derrick is divided into five sections, has bearing pin to connect between each section, and each junction also is provided with attached plate.
4. a kind of boring tower according to claim 1 is characterized in that the size of the shaped steel size of the bottom joint of described king-tower post greater than the shaped steel of other joint.
5. a kind of boring tower according to claim 1 is characterized in that the described boring tower rope sheave that hoists adopts shift sleeve structure.
6. a kind of boring tower according to claim 1, it is characterized in that described base branch foreground and backstage two parts, the foreground comprises foreground base, thribble platform, table beam, winch beam, end straining beam, thribble beam, table beam, winch beam are connected with the left and right sides base on foreground by upper and lower twice bearing pin respectively, and its underpart connects whole foreground as a whole by several end straining beams; The backstage is the base of drilling rig power plant and transmission device thereof; AM/BAM is connected by eight bearing pins.
CNU2006201284675U 2006-12-21 2006-12-21 An artesian well tower Expired - Fee Related CN201024903Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2006201284675U CN201024903Y (en) 2006-12-21 2006-12-21 An artesian well tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2006201284675U CN201024903Y (en) 2006-12-21 2006-12-21 An artesian well tower

Publications (1)

Publication Number Publication Date
CN201024903Y true CN201024903Y (en) 2008-02-20

Family

ID=39098759

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2006201284675U Expired - Fee Related CN201024903Y (en) 2006-12-21 2006-12-21 An artesian well tower

Country Status (1)

Country Link
CN (1) CN201024903Y (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102140891A (en) * 2011-03-18 2011-08-03 衡阳中地装备探矿工程机械有限公司 Variable-position overhead crane drill tower
CN102490865A (en) * 2011-12-01 2012-06-13 大连中远船务工程有限公司 Module graduation tower of deep-sea drilling ship
CN104343393A (en) * 2013-08-09 2015-02-11 中国石油天然气集团公司 A-shaped drilling rig derrick with double racking platforms for construction
CN104343394A (en) * 2013-08-09 2015-02-11 中国石油天然气集团公司 Front opening type drilling rig derrick with double racking platforms for construction
CN105484683A (en) * 2016-01-22 2016-04-13 中石化石油工程机械有限公司第四机械厂 Automatic discharge device for drill strings
CN106078195A (en) * 2016-06-27 2016-11-09 宝鸡石油机械有限责任公司 The assemble method of case block formula base

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102140891A (en) * 2011-03-18 2011-08-03 衡阳中地装备探矿工程机械有限公司 Variable-position overhead crane drill tower
CN102140891B (en) * 2011-03-18 2013-04-24 衡阳中地装备探矿工程机械有限公司 Variable-position overhead crane drill tower
CN102490865A (en) * 2011-12-01 2012-06-13 大连中远船务工程有限公司 Module graduation tower of deep-sea drilling ship
CN104343393A (en) * 2013-08-09 2015-02-11 中国石油天然气集团公司 A-shaped drilling rig derrick with double racking platforms for construction
CN104343394A (en) * 2013-08-09 2015-02-11 中国石油天然气集团公司 Front opening type drilling rig derrick with double racking platforms for construction
CN104343393B (en) * 2013-08-09 2017-02-15 中国石油天然气集团公司 A-shaped drilling rig derrick with double racking platforms for construction
CN105484683A (en) * 2016-01-22 2016-04-13 中石化石油工程机械有限公司第四机械厂 Automatic discharge device for drill strings
CN106078195A (en) * 2016-06-27 2016-11-09 宝鸡石油机械有限责任公司 The assemble method of case block formula base
CN106078195B (en) * 2016-06-27 2018-07-06 宝鸡石油机械有限责任公司 The assemble method of case block formula pedestal

Similar Documents

Publication Publication Date Title
CN201024903Y (en) An artesian well tower
CN203403418U (en) Steel casing double-layer guide frame structure
CN107447678A (en) A kind of erection crane of the two-way positioning of energy
CN103510864B (en) One kind three saves hydraulically extensible suit derrick
CN202064840U (en) Four-drill column drill derrick
CN202296907U (en) Suspension arm balanced movable arm tower crane capable of luffing based on steel rope traction
CN102303821A (en) Luffing tower crane with balanced type suspension arm based on traction luffing of steel rope
CN204625045U (en) A kind of steel structure hoisting door shaped stent formula hanging apparatus
CN207362709U (en) A kind of erection crane of the two-way positioning of energy
CN204152426U (en) A kind of quick removal of home rig of hydraulic cylinder raising
CN105822132A (en) Unit type assembly and erection method of extra-high-voltage power transmission iron pylon
CN101016827A (en) 18 m hydraulic pressure rise and fall retractable drill tower
CN201133219Y (en) Sea derrick for drilling and repairing
CN102691479A (en) Slipping luffing mechanism for crossbeam of horizontal directional drilling machine
CN207863871U (en) A kind of derrick for repairing equipment for petroleum drilling
CN205973410U (en) Special cross hanging beam structure of reactor core shell hoist and mount
CN2863755Y (en) Levelling device for overhead working truck platform draw-in rod
CN206941414U (en) The Bridge Erector of the whole two-way erection in hole on a kind of asymmetric framing prefabricated case beam beam of achievable large-tonnage
CN201420239Y (en) Hydraulic locking mechanism
CN106677713B (en) Reinforce drilling machine
CN203531759U (en) Three-section hydraulic telescopic headframe
CN202924633U (en) Cargo boom pull rod and tower crane comprising cargo boom pull rod
CN201013249Y (en) Novel oil-well rig lifting foundation
CN201292775Y (en) Oil rig derrick
US2889898A (en) Combination oil well derrick and tilting construction boom

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee