CN200988018Y - Paint spray booth of purifying paint mist - Google Patents

Paint spray booth of purifying paint mist Download PDF

Info

Publication number
CN200988018Y
CN200988018Y CN 200620140906 CN200620140906U CN200988018Y CN 200988018 Y CN200988018 Y CN 200988018Y CN 200620140906 CN200620140906 CN 200620140906 CN 200620140906 U CN200620140906 U CN 200620140906U CN 200988018 Y CN200988018 Y CN 200988018Y
Authority
CN
China
Prior art keywords
spray booth
paint spray
room
coating cloud
clean room
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 200620140906
Other languages
Chinese (zh)
Inventor
俞银德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 200620140906 priority Critical patent/CN200988018Y/en
Application granted granted Critical
Publication of CN200988018Y publication Critical patent/CN200988018Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Details Or Accessories Of Spraying Plant Or Apparatus (AREA)

Abstract

Disclosed is a spray painting house to purify paint fog, which comprises a house body device, a water circulation device and a wind engine device, the house device comprises a studio and a top ventilation pipe arranged on the top of the studio, the studio comprises a front painting spray room, a purification room, a paint fog absorption room and an electric engine room, the paint fog absorption room is arranged between the purification room and the electric engine room, the front painting spray room is arranged in the front of the purification room, the paint fog absorption room, and the electric engine room, the paint fog absorption room is connected with the front spray painting room, the purification room and the paint fog absorption room are connected by a centre through hole on a vertical separator between them, the water circulation device comprises a water pump and a water pipe system, the water pipe system comprises a device which generates water curtain in the front painting spray room, the electric engine of the wind engine device is arranged inside the electric engine room, the impeller of the wind engine device is arranged inside the purification room, the paint fog inlet of the wind engine device is the centre through hole on the vertical separator, the paint fog outlet of the wind engine device is arranged inside the purification room, and the inlet of the top ventilation pipe is connected with the purification room. The paint fog purification ratio of the spray painting house to purify paint fog of the utility model reaches above 90%, the structure is simple, the occupied space is very small, and the application prospect is very wide.

Description

A kind of paint spray booth that purifies coating cloud
Technical field
The utility model relates to a kind of paint spray booth, relates in particular to a kind of paint spray booth that can remove coating cloud.
Background technology
Workpiece always has the disperse of part coating cloud around the workpiece and in the preceding paint spray booth when spraying paint, have a strong impact on operator's health, if directly coating cloud is arranged to outdoor, the meeting pollutant atmosphere influences the life of surrounding resident.In order to capture coating cloud effectively, present spraying treating apparatus has fountain, water curtain type etc.The paint spraying apparatus of water curtain type is to be will spray paint and be divided into paint spraying section and coating cloud processing section in the boundary with the water curtain plate.Spray paint air-flow and air enters the coating cloud processing section under the exhaust blower suction, collect through cascade and water smoke flushing, make coating cloud be gathered in tank, two kinds of fluids collide mutually, water smoke and the air that contains coating cloud are fully mixed, thereby realize removing the process of coating cloud, the air after the purified treatment just can be arranged in the air.But the waste gas purification effect that the present disclosed gas purifying equipment that sprays paint has is undesirable, the complex structure that has, cost height.
Summary of the invention
The utility model is in order to solve prior art constructions complexity, the unfavorable problem of clean-up effect, and a kind of paint spray booth of purification coating cloud of simple in structure, good purification is provided.
For addressing the above problem, the paint spray booth of purification coating cloud of the present utility model comprises a room body device, a water circle device and a blower fan apparatus, it is characterized in that, the room body device comprises that an operating room and is installed in the top discharge duct at top, operating room; The operating room comprises a preceding paint spray booth, a clean room, a coating cloud suction chamber and a motor room, the coating cloud suction chamber is between clean room and motor room, preceding paint spray booth in the clean room, coating cloud suction chamber and motor room front, the coating cloud suction chamber communicates with preceding paint spray booth, and the clean room communicates by the central through hole on the longitudinal baffle between them with the coating cloud suction chamber; Water circle device comprises a water pump and a water pipe system, and water pipe system comprises that one produces the device of cascade in preceding paint spray booth; The motor of blower fan apparatus is in motor room, and the impeller of blower fan apparatus is in the clean room, and the coating cloud import of blower fan apparatus is the central through hole on the longitudinal baffle, and the coating cloud outlet of blower fan apparatus is positioned at the clean room; The import of top discharge duct is communicated with the clean room.
The paint spray booth of purification coating cloud of the present utility model, after the coating cloud that produces of spraying paint is handled through the device that produces cascade in preceding paint spray booth, major part lacquer particulate wherein enters in the water, the coating cloud import that the central through hole of clean gas on the longitudinal baffle between coating cloud suction chamber and clean room and the coating cloud suction chamber enters blower fan apparatus, by entering in the clean room after the blower fan apparatus pressurization, discharge duct enters atmosphere through the top, the coating cloud purifying rate reaches more than 90%, and, the paint spray booth of purification spraying of the present utility model is simple in structure, space hold is very little, and application prospect is very wide.
The paint spray booth of purification coating cloud of the present utility model also comprises and has a following feature:
Also comprise paint spray booth, a back, back paint spray booth in the clean room, coating cloud suction chamber and motor room back, the coating cloud suction chamber communicates with the paint spray booth, back, water pipe system also comprise one in back paint spray booth the device of generation cascade.
Water pipe system comprises that also a device and that produces cascade in blast pipe produces cascade in the clean room device and produces the device of cascade in the coating cloud suction chamber; In the middle of the bottom of the longitudinal baffle between coating cloud suction chamber and clean room and the coating cloud suction chamber slot is arranged, the clean room is communicated with coating cloud suction chamber and preceding paint spray booth.
The device that in front paint spray booth and in the rear paint spray booth, produces cascade comprise be installed in respectively in the front paint spray booth and rear paint spray booth inner bottom part frid below a bottom transverse horizontal water inflow pipe, be installed in the front paint spray booth respectively and two inside top wall vertical equity water inlet pipes of inner top both sides, rear paint spray booth, the top board that passes the operating room respectively stretch into front paint spray booth and rear paint spray booth a center of top vertical inlet pipe and below one in the middle of tank and pass respectively the operating room top board a top vertical inlet pipe and below the top in front paint spray booth and rear paint spray booth form a top tank of cascade.
The device that produces cascade in blast pipe comprises and is installed in the blast pipe vertical equity water inlet pipe above the blast pipe upper end open and is installed in a blast pipe porous frid in the blast pipe; The device that produces cascade in the clean room comprises the porous reflection frid that is installed in clean room's internal upper part; The device that in the coating cloud suction chamber, produces cascade comprise the top vertical equity water inlet pipe that is installed in outside the operating room and below a postmedian tank.
The top discharge duct comprises a bent tube section and a straight-tube portion, the straight-tube portion lower end closed, be bearing on the support or on the ground, the straight-tube portion upper end open, the lower ends downward of bent tube section stretches in the straight-tube portion, apart from the straight-tube portion lower end certain distance is arranged, the other end is communicated with the clean room by blast pipe.
Water pipe system also comprises a water inlet manifold, and water inlet manifold is communicated with exit of pump, the horizontal water inlet pipe of bottom transverse, center of top vertical inlet pipe, top vertical inlet pipe, blast pipe vertical equity water inlet pipe and top vertical equity water inlet pipe.
Blower fan apparatus comprises a motor, an impeller, a filter screen and a Blower Housing, the major axis of motor stretches in the clean room by the central through hole on the longitudinal baffle between clean room and the coating cloud suction chamber, impeller is fixedly mounted on the axle head of major axis, filter screen is the cylindrical shape of end sealing, its openend has an outward flange, filter screen is fixed in the Blower Housing by outward flange, and Blower Housing is installed on the central through hole longitudinal baffle on every side of longitudinal baffle, is positioned at the clean room.
In preceding paint spray booth and middle the tank of back in the paint spray booth face the coating cloud suction chamber, its length is wideer slightly than coating cloud suction chamber, and a middle drip water plate is installed on the antetheca of middle tank; The upper surface level of the antetheca of top tank and be lower than the upper surface of other walls, the upper surface that the antetheca of top tank is crossed the right lateral partitions of the left lateral partitions of clean room and motor room forms a downward-sloping top drip water plate, and the length of top tank equals the distance between operating room's left side wallboard and the right wallboard.
Porous reflection frid and blast pipe porous frid are the rectangle frid with a plurality of vertical through hole, have four upright trough rims that make progress.
Description of drawings
Be further described below in conjunction with the paint spray booth of the drawings and specific embodiments purification coating cloud of the present utility model.
Fig. 1 is the right front perspective diagram of first embodiment of the paint spray booth of purification coating cloud of the present utility model, and wherein, discharge duct is in the back, operating room;
Fig. 2 is that the master of the paint spray booth of purification coating cloud shown in Figure 1 looks schematic diagram;
Fig. 3 is the schematic top plan view of the paint spray booth of purification coating cloud shown in Figure 1;
Fig. 4 is the cross-sectional schematic along the A-A line of Fig. 3;
Fig. 5 is the cross-sectional schematic along the B-B line of Fig. 3;
Fig. 6 is the cross-sectional schematic along the C-C line of Fig. 3;
Fig. 7 is the right front perspective diagram of second embodiment of the paint spray booth of purification coating cloud of the present utility model, and wherein, discharge duct is in the left side, operating room;
Fig. 8 is the cross-sectional schematic along the D-D line of Fig. 7.
The specific embodiment
As shown in Figures 1 to 4, the paint spray booth of the purification coating cloud of first embodiment of the utility model comprises a room body device 100, a water circle device 200 and a blower fan apparatus 300.
Room body device 100 comprises the operating room 110 of a base for supporting 101 and a cuboid.The operating room 110 of base for supporting 101 and cuboid can make respectively, then, the operating room 110 of cuboid is fixedly mounted on the base for supporting 101.The operating room 110 of base for supporting 101 and cuboid also can be made into one.
The operating room 110 of cuboid is made of left wallboard 111, one a right wallboard 112, a squab panel 113, a base plate 114, a top board 115 and a front panel 116.Front panel 116 comprises a vertical panel 8 and a bending plate 9.Bending plate 9 comprises the swash plate 10 of front end updip and the frid 11 that upwards is bent to form by swash plate 10 front ends.The end of frid 11 and swash plate 10 have certain interval.As shown in Figure 2, there is a hole at base plate 114 contiguous vertical panels 8 places, are used to install an adjutage 42, and a valve 41 is arranged on the adjutage 42.Top board 115 has a postmedian porous pit plate portion 16.Postmedian porous pit plate portion 16 constitutes a postmedian tank 60 with the two horizontal top risers 18 and the two vertical top risers 19 that are welded on top board 115 upper surfaces.
To shown in Figure 6, room body device 100 comprises that also one is positioned at left longitudinal baffle 12, one right longitudinal baffle 13, one a left lateral partitions 22 and a right lateral partitions 23 of operating room 110 as Fig. 4.Left side longitudinal baffle 12, left lateral partitions 22, the part of left wallboard 111 and the space that a part surrounded of squab panel 113 are a clean room 51.Right longitudinal baffle 13, right lateral partitions 23, the part of right wallboard 112 and the space that a part surrounded of squab panel 113 are a motor room 52.Space between clean room 51 and the motor room 52 is a coating cloud suction chamber 53.The space of clean room 51, coating cloud suction chamber 53 and motor room 52 fronts is a preceding paint spray booth 50.Between the top edge of left side lateral partitions 22 and right lateral partitions 23 and top board 115 lower surfaces certain distance is arranged.Have a large diameter hole 56 in the middle of the left side longitudinal baffle 12, have a small diameter bore 55 in the middle of the right longitudinal baffle 13.Large diameter hole 56 and small diameter bore 55 have same axial line.
Leave top board 115 lower surface certain distances at the top of operating room 110 by being fixedly mounted on tank 32 in the middle of the suspension bracket supporting one on the top board 115, the upper surface level of the antetheca 33 of middle tank 32 and be lower than the upper surface of other walls.Middle tank 32 is positioned at preceding paint spray booth 50 and faces coating cloud suction chamber 53, and its length is wideer slightly than coating cloud suction chamber 53.Drip water plate 34 in the middle of on the antetheca 33 of tank 32, installing one.
The rear surface of being close to top board 115 lower surfaces and left lateral partitions 22 and right lateral partitions 23 at the top of operating room 110 is fixedly mounted on a top tank 35 on the top board 115, the upper surface level of the antetheca of top tank 35 and be lower than the upper surface of other walls.The upper surface that the antetheca of top tank 35 is crossed left lateral partitions 22 and right lateral partitions 23 forms a downward-sloping top drip water plate 36.The length of top tank 35 equals the distance between left wallboard 111 and the right wallboard 112.
Each fixing peace one horizontal slideway 14 of sustained height place on the relative top wall of left lateral partitions 22 and left wallboard 111 is installed porous reflection frid 4 on two horizontal slideways 14, porous reflection frid 4 can horizontal slip on two horizontal slideways 14.Porous reflection frid 4 has four upright trough rims that make progress for the handled rectangle frid with a plurality of vertical through hole in left side.
In the middle of the bottom of left side longitudinal baffle 12 slot 93 is arranged, clean room 51 is communicated with coating cloud suction chamber 53 and preceding paint spray booth 50.
Room body device 100 comprises that also one is installed in the top discharge duct 7 on the top board 115 of operating room 110.Top discharge duct 7 is 110 back in the operating room.Top discharge duct 7 comprises a bent tube section 19 and a straight-tube portion 20.Straight-tube portion 20 lower ends are bearing on the support or directly support on the ground as shown in Figure 1.Straight-tube portion 20 upper end open, sidewall have one 21.The lower end 84 of bent tube section 19 is stretched into downwards in the straight-tube portion 20, apart from the lower end of straight-tube portion 20 certain distance is arranged, and the upper end is communicated with the upwardly extending blast pipe 80 in the hole from the top board 115 of operating room 110.Bent tube section 19 is welded as a whole with straight-tube portion 20.Blast pipe 80 lower ends are communicated with clean room 51, upper end open, installation one blast pipe porous frid 81 above the inner mouth of pipe that is communicated with in the upper end with bent tube section 19.Blast pipe porous frid 81 has four upright trough rims that make progress for having the rectangle frid of a plurality of vertical through hole.A connecting pipe 59 is arranged between the bottom of straight-tube portion 20 and clean room 51.
Water circle device 200 comprises a blast pipe vertical equity water inlet pipe 65 that is installed in 110 outer blast pipe 80 upper end open tops, operating room as shown in Figure 1, be installed in a top vertical equity water inlet pipe 66 of 110 outer postmedian tanks, 60 tops, operating room as shown in Figure 1, be installed in two inside top wall vertical equity water inlet pipes 46 and 48 of 50 inner top both sides, paint spray booth as shown in Figure 2 respectively, be installed in the horizontal water inlet pipe 38 of a bottom transverse below the preceding paint spray booth 50 inner bottom part frids 11 as shown in Figure 4, pass as shown in Figure 4 top board 115 enter preceding paint spray booth 50 middle tank 32 a center of top vertical inlet pipe 61 and pass the top vertical inlet pipe 62 that top board 115 enters top tank 35 as shown in Figure 4.Water circle device 200 also comprises a water inlet manifold 39 and a water pump 90.One end opening of top vertical equity water inlet pipe 65, top vertical equity water inlet pipe 66, the horizontal water inlet pipe 38 of bottom transverse, center of top vertical inlet pipe 61 and top vertical inlet pipe 62, the other end is communicated with water inlet manifold 39.Two inside top wall vertical equity water inlet pipes 36 and 37 are that an end seals the pipe fitting that a side has a plurality of holes, and the other end is connected on the water inlet manifold 39 by pipeline.The horizontal water inlet pipe 38 1 ends sealing of bottom transverse, the other end is communicated with water inlet manifold 39.Have one to discharge the water hole on the horizontal water inlet pipe 38 bottom tube walls of bottom transverse.Water pump 90 outlets are communicated with water inlet manifold 39, and the import of water pump 90 is communicated with an end of an inlet tube, and the other end of inlet tube enters in the preceding paint spray booth 50 from right wallboard 112 bottoms of operating room 110, links to each other with a filter mantle 66.On each water pipe of intaking control valve can be installed.One compensation tank (not shown) can be set, forward automatic water supplement in the paint spray booth 50.
Referring to Fig. 5, blower fan apparatus 300 comprises a motor 63, an impeller 24, a filter screen 25, a Blower Housing 26.Motor 63 is installed in the motor room 52 by a support 27.The major axis 28 of motor 63 stretches out from the small diameter bore 55 in the middle of the right longitudinal baffle 13.Impeller 24 is fixedly mounted on the axle head of major axis 28.Filter screen 25 is the cylindrical shape of end sealing, and its openend has an outward flange, and filter screen 25 is fixed in the Blower Housing 26 by outward flange.Blower Housing 26 is installed on the large diameter hole 56 left longitudinal baffle 12 on every side of left longitudinal baffle 12 by bolt, is positioned at clean room 51.
Respectively open a manhole on left side wallboard 111 and the right wallboard 112, so that dismounting motor 63 and Blower Housing 26.On left side wallboard 111 and the right wallboard 112 manhole door is installed respectively, so that open or close manhole.
The course of work of the paint spray booth of purification coating cloud of the present utility model is as follows:
Inject water in operating room 110, the height of water surpasses the slot 13 of contiguous right wallboard 112 formation in bottom of dividing plate 12, makes the bottom liquid sealing of preceding paint spray booth 50 and coating cloud suction chamber 53 and clean room 51.Starter motor, water circle device 200 and blower fan apparatus 300 runnings, make water be divided into six parts after entering water inlet manifold 39 by filter mantle 66 in 50 bottoms, paint spray booth: first flows into the horizontal water inlet pipe 38 of bottom transverse below the bottom frid 11 that is installed in the preceding paint spray booth 50 in the past, a plurality of orifice flows by the horizontal water inlet pipe of bottom transverse 38 bottoms go out, and form the bottom cascade on the swash plate 10 of the bottom of preceding paint spray booth 50; Second portion flows into two inside top wall vertical equity water inlet pipes 46 and 48, and a plurality of orifice flows by two inside top wall vertical equity water inlet pipes 36 and 37 1 sides go out, and 50 two side forms cascade in the paint spray booth; Third part flows into the blast pipe 80 that is installed in outside the operating room 110 by blast pipe vertical equity water inlet pipe 65, in blast pipe 80, form cascade and water smoke downwards by a plurality of through holes that are installed on the blast pipe porous frid 81 in the blast pipe 80, continuation forms cascade and water smoke downwards by a plurality of through holes on the porous reflection frid 4 that is installed in 51 tops, clean room in clean room 51, the water droplet of falling simultaneously on the porous reflection frid 4 is reflexed in the air by porous reflection frid 4, forms water smoke above porous reflection frid 4; The 4th part flows into the postmedian tank 60 that is installed in outside the operating room 110 by top vertical equity water inlet pipe 66, forms cascade and water smoke downwards by a plurality of through holes on the postmedian porous pit plate portion 16 of top board 115 in coating cloud suction chamber 53; The 5th part is by the middle tank 32 of the preceding paint spray booth 50 of center of top vertical inlet pipe 61 inflows, and the antetheca 33 of crossing tank 32 then flows out, cascade and water smoke in the middle of forming on the middle drip water plate 34 on the antetheca 33 that is installed in tank 32; The 6th part flows into top tank 35 by top vertical inlet pipe 62, and the upper surface of crossing the antetheca 36 of top tank 35 flows on the antetheca 36, forms horizontal cascade and water smoke downwards in preceding paint spray booth 50.
The workpiece of preparing to spray paint is placed in the preceding paint spray booth 50, use spray gun to spray paint to workpiece, the coating cloud with a large amount of lacquer particulates that forms and the preceding paint spray booth 50 interior cascades that spray paint contact with water smoke, then, coating cloud with a small amount of lacquer particulate enters in the coating cloud suction chamber 53, contact with water smoke with the cascade in the coating cloud suction chamber 53, major part lacquer particulate wherein enters in the water, then, the large diameter hole 56 of coating cloud in the middle of left longitudinal baffle 12 that wherein is mixed with water smoke sucks in the Blower Housing 26, after being boosted by the impeller 24 of blower fan apparatus 300, part lacquer particulate wherein is bonded on the filter screen 25, having seldom, the coating cloud of amount lacquer particulate enters clean room 51 through filter screen 25, upwards contact with water smoke with the cascade that below porous reflection frid 4, forms, behind the hole by porous reflection frid 4, contact with water smoke with the cascade that above porous reflection frid 4, forms, lacquer particulate wherein enters in the water, then, coating cloud with trace lacquer particulate enters the bent tube section 19 of top discharge duct 7 by a plurality of holes of the blast pipe porous frid 81 in the blast pipe 80, be flushed to downwards from the lower end 84 of bent tube section 19 on the water surface of straight-tube portion 20 bottoms of top discharge duct 7, lacquer particulate wherein almost all enters in the water, then, clean gas oppositely upwards enters the atmosphere from straight-tube portion 20 upper end open the back.
Porous reflection frid 4, blast pipe porous frid 81, impeller 24, filter screen 25 and filter mantle 66 all can split out cleaning easily.
As shown in Figure 7 and Figure 8, the paint spray booth of the purification coating cloud of second embodiment of the utility model comprise a room body device 100 ', a water circle device a 200 ' and blower fan apparatus 300.
The paint spray booth of the purification coating cloud of second embodiment of the utility model is to increase a paint spray booth and constitute on the basis of the paint spray booth of the purification coating cloud of first embodiment of the utility model.
To shown in Figure 6, the paint spray booth of the purification coating cloud of first embodiment of the utility model has only a preceding paint spray booth 50 as Fig. 1, and top discharge duct 7 is 110 back in the operating room.As shown in Figure 7 and Figure 8, the paint spray booth of the purification coating cloud of second embodiment of the utility model has two preceding paint spray booths, promptly a preceding paint spray booth 50 and paint spray booth 50, a back ', top discharge duct 7 in the operating room 110 ' the left side.Paint spray booth 50 ' and constitute after increasing by one on the basis of operating room 110, operating room 110 ' be.As shown in Figure 8, back paint spray booth 50 ' basic identical with preceding paint spray booth 50 structures has the horizontal water inlet pipe 38 of a bottom transverse, two inside top wall vertical equity water inlet pipes 46 and 48, one a middle tank 32 and a top tank 35.Water circle device 200 ' be that increase is given the pipeline that paint spray booth 50, back ' the interior horizontal water inlet pipe 38 of bottom transverse, middle tank 32 and top tank 35 supplies water and constituted on the basis of water circle device 200.
According to embodiment of the present utility model to being illustrated property of the utility model and nonrestrictive description; but should understand; under the situation that does not break away from relevant protection domain defined by the claims, those skilled in the art can make change and/or revise.

Claims (10)

1, a kind of paint spray booth that purifies coating cloud comprises a room body device, a water circle device and a blower fan apparatus, it is characterized in that, the room body device comprises that an operating room and is installed in the top discharge duct at top, operating room; The operating room comprises a preceding paint spray booth, a clean room, a coating cloud suction chamber and a motor room, the coating cloud suction chamber is between clean room and motor room, preceding paint spray booth in the clean room, coating cloud suction chamber and motor room front, the coating cloud suction chamber communicates with preceding paint spray booth, and the clean room communicates by the central through hole on the longitudinal baffle between them with the coating cloud suction chamber; Water circle device comprises a water pump and a water pipe system, and water pipe system comprises that one produces the device of cascade in preceding paint spray booth; The motor of blower fan apparatus is in motor room, and the impeller of blower fan apparatus is in the clean room, and the coating cloud import of blower fan apparatus is the central through hole on the longitudinal baffle, and the coating cloud outlet of blower fan apparatus is positioned at the clean room; The import of top discharge duct is communicated with the clean room.
2, the paint spray booth of purification coating cloud according to claim 1, it is characterized in that, also comprise paint spray booth, a back, back paint spray booth in the clean room, coating cloud suction chamber and motor room back, the coating cloud suction chamber communicates with the paint spray booth, back, and water pipe system comprises that also one produces the device of cascade in the paint spray booth, back.
3, the paint spray booth of purification coating cloud according to claim 1 and 2 is characterized in that, water pipe system comprises that also a device and that produces cascade in blast pipe produces cascade in the clean room device and produces the device of cascade in the coating cloud suction chamber; In the middle of the bottom of the longitudinal baffle between coating cloud suction chamber and clean room and the coating cloud suction chamber slot is arranged, the clean room is communicated with coating cloud suction chamber and preceding paint spray booth.
4, the paint spray booth of purification coating cloud according to claim 3, it is characterized in that, in preceding paint spray booth and the device that produces cascade in the paint spray booth, back comprise be installed in the preceding paint spray booth respectively and paint spray booth, back inner bottom part frid below the horizontal water inlet pipe of a bottom transverse, be installed in respectively in the preceding paint spray booth and two inside top wall vertical equity water inlet pipes of inner top both sides, paint spray booth, back, the top board that passes the operating room respectively stretches into tank in the middle of the center of top vertical inlet pipe and following of preceding paint spray booth and paint spray booth, back and passes the top vertical inlet pipe of top board of operating room and a top tank of the following top formation cascade in preceding paint spray booth and paint spray booth, back thereof respectively.
5, the paint spray booth of purification coating cloud according to claim 4, it is characterized in that the device that produces cascade in blast pipe comprises and is installed in the blast pipe vertical equity water inlet pipe above the blast pipe upper end open and is installed in a blast pipe porous frid in the blast pipe; The device that produces cascade in the clean room comprises the porous reflection frid that is installed in clean room's internal upper part; The device that in the coating cloud suction chamber, produces cascade comprise the top vertical equity water inlet pipe that is installed in outside the operating room and below a postmedian tank.
6, the paint spray booth of purification coating cloud according to claim 5, it is characterized in that, the top discharge duct comprises a bent tube section and a straight-tube portion, the straight-tube portion lower end closed, be bearing on the support or on the ground, the straight-tube portion upper end open, the lower ends downward of bent tube section stretches in the straight-tube portion, apart from the straight-tube portion lower end certain distance is arranged, the other end is communicated with the clean room by blast pipe.
7, the paint spray booth of purification coating cloud according to claim 6, it is characterized in that, water pipe system also comprises a water inlet manifold, and water inlet manifold is communicated with exit of pump, the horizontal water inlet pipe of bottom transverse, inside top wall vertical equity water inlet pipe, center of top vertical inlet pipe, top vertical inlet pipe, blast pipe vertical equity water inlet pipe and top vertical equity water inlet pipe.
8, the paint spray booth of purification coating cloud according to claim 7, it is characterized in that, blower fan apparatus comprises a motor, an impeller, a filter screen and a Blower Housing, the major axis of motor stretches in the clean room by the central through hole on the longitudinal baffle between clean room and the coating cloud suction chamber, impeller is fixedly mounted on the axle head of major axis, filter screen is the cylindrical shape of end sealing, its openend has an outward flange, filter screen is fixed in the Blower Housing by outward flange, Blower Housing is installed on the central through hole longitudinal baffle on every side of longitudinal baffle, is positioned at the clean room.
9, the paint spray booth of purification coating cloud according to claim 8, it is characterized in that, in preceding paint spray booth and middle the tank of back in the paint spray booth face the coating cloud suction chamber, its length is wideer slightly than coating cloud suction chamber, and a middle drip water plate is installed on the antetheca of middle tank; The upper surface level of the antetheca of top tank and be lower than the upper surface of other walls, the upper surface that the antetheca of top tank is crossed the right lateral partitions of the left lateral partitions of clean room and motor room forms a downward-sloping top drip water plate, and the length of top tank equals the distance between operating room's left side wallboard and the right wallboard.
10, the paint spray booth of purification coating cloud according to claim 9 is characterized in that, porous reflection frid and blast pipe porous frid are the rectangle frid with a plurality of vertical through hole, have four upright trough rims that make progress.
CN 200620140906 2006-12-11 2006-12-11 Paint spray booth of purifying paint mist Expired - Lifetime CN200988018Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200620140906 CN200988018Y (en) 2006-12-11 2006-12-11 Paint spray booth of purifying paint mist

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200620140906 CN200988018Y (en) 2006-12-11 2006-12-11 Paint spray booth of purifying paint mist

Publications (1)

Publication Number Publication Date
CN200988018Y true CN200988018Y (en) 2007-12-12

Family

ID=38939062

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200620140906 Expired - Lifetime CN200988018Y (en) 2006-12-11 2006-12-11 Paint spray booth of purifying paint mist

Country Status (1)

Country Link
CN (1) CN200988018Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100441314C (en) * 2006-12-11 2008-12-10 俞银德 A spray booth for purifying paint mist
CN105597470A (en) * 2015-12-23 2016-05-25 天津赛智科技发展有限公司 Paint mist purifying system
CN117046665A (en) * 2022-05-06 2023-11-14 四川瀚海精密制造有限公司 A spray booth that can self-purify paint slag and paint mist

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100441314C (en) * 2006-12-11 2008-12-10 俞银德 A spray booth for purifying paint mist
CN105597470A (en) * 2015-12-23 2016-05-25 天津赛智科技发展有限公司 Paint mist purifying system
CN117046665A (en) * 2022-05-06 2023-11-14 四川瀚海精密制造有限公司 A spray booth that can self-purify paint slag and paint mist

Similar Documents

Publication Publication Date Title
CN201940322U (en) Eddy paint spray chamber
CN201189432Y (en) Air cleaning device
CN103697550B (en) Air conditioner for painting room of car painting line
CN2394702Y (en) Fume purifying and treating device
CN101020167A (en) Lacquer spraying booth capable of eliminating lacquer mist
CN105526609A (en) Fume exhaust hood used for purifying catering oil fume
CN217220822U (en) Organic waste gas treatment system
CN204115046U (en) A kind of enclosure for purifying kitchen fumes
CN101020166A (en) Lacquer spraying booth capable of eliminating lacquer mist
CN101020168A (en) Lacquer spraying booth capable of eliminating lacquer mist
CN200981045Y (en) Spray-paint house for purifying paint mist
CN209997386U (en) Stainless steel cyclone tower waste gas treatment equipment
CN201154279Y (en) Wet-type smoke removal device
CN2687540Y (en) Oil-fume purifying machine for food and beverage trade
CN103343996B (en) Cooking fume remover
CN106040508A (en) Paint treatment system and method for paint spray booth
CN201120351Y (en) Exhaust gas purifying device for spray painting workshop
CN215784362U (en) Environment-friendly paint spraying cabinet
CN214552214U (en) Novel acid mist purification device for atmospheric pollution treatment
CN108543381A (en) A kind of hedgerow isolation strip air cleaning unit
CN203549949U (en) Oil smoke purifier
CN212596666U (en) Production of quick-drying baking finish door plant is with environmental protection spray booth
CN112158055A (en) Engineering vehicle air conditioning equipment with dust removal humidification function
CN200981046Y (en) Spray-paint house for purifying paint mist
CN2557842Y (en) Cooking fume exhauster for kitchen

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Effective date of abandoning: 20081210

C25 Abandonment of patent right or utility model to avoid double patenting