CN200976471Y - 直流双极垂直排列“f”形输电线路系列铁塔 - Google Patents

直流双极垂直排列“f”形输电线路系列铁塔 Download PDF

Info

Publication number
CN200976471Y
CN200976471Y CN 200520102214 CN200520102214U CN200976471Y CN 200976471 Y CN200976471 Y CN 200976471Y CN 200520102214 CN200520102214 CN 200520102214 CN 200520102214 U CN200520102214 U CN 200520102214U CN 200976471 Y CN200976471 Y CN 200976471Y
Authority
CN
China
Prior art keywords
tower
polar
transmission line
arm
insulator string
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200520102214
Other languages
English (en)
Inventor
应建国
朱天浩
陈稼苗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid DC Project Construction Co., Ltd.
Zhejiang Electric Power Design Institute
Original Assignee
Zhejiang Electric Power Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Electric Power Design Institute filed Critical Zhejiang Electric Power Design Institute
Priority to CN 200520102214 priority Critical patent/CN200976471Y/zh
Application granted granted Critical
Publication of CN200976471Y publication Critical patent/CN200976471Y/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

直流双极垂直排列“F”形输电线路系列铁塔,包括直线塔(A)、直线转角塔(B)和耐张转角塔(C)三种塔型,其技术要点是将直流输电线路两极导线由水平布置改为垂直布置。前二种塔型上层为地线横担,下面两层依次为上极导线横担和下极导线横担,极导线通过“V”型绝缘子串与铁塔相连接;第三种塔型不设置极导线横担,极导线通过耐张绝缘子串直接挂于塔窗身部挂点上,挂点上下布置并适当错开,分别位于塔窗身部两侧,同时在极导线挂点上方同一侧分别设置跳线支架。本系列塔型可使极导线水平投影距离减至1.8米左右,有效减小线路走廊宽度,节约工程建设投资,尤其适用于经济发达、建筑密集的平原地区。

Description

直流双极垂直排列“F”形输电线路系列铁塔
技术领域
本实用新型涉及一种直流输电线路铁塔。
背景技术
为满足我国强大的电力输送要求,电力部门目前采用输送能力较500kV交流输电方式更大的±500kV直流输电方式。±500kV直流输电线路采取的是将双极导线水平对称布置的一种结构,如图1所示。这种结构受力对称,但占用线路走廊过宽,线路走廊本身宽度加两极水平投影5米范围内的建筑物必须拆迁,造成了线路建设投资大和政策处理困难的局面。
发明内容
现有的双极导线水平对称布置的±500kV直流输电线路由于占用走廊过多过宽而导致投资大、拆迁困难等方面的矛盾日益突出。缩小线路走廊宽度、提高单位走廊宽度的输电能力是国家电力部门致力解决的一个课题。本实用新型克服了现有技术中的缺点,为直流输电线路设计了一种新颖的结构,以解决线路走廊过宽问题。
本实用新型技术是一种将两极导线由水平布置改为垂直布置的一种塔型,如图2、图3、图4所示,共有三种塔型形式,一种叫直线塔(A),一种叫直线转角塔(B),还有一种叫耐张转角塔(C),其中前二种直线塔型上层为地线横担,下二层为极导线横担,极导线与铁塔通过“V”布置的绝缘子串相连接,外型如“F”形,第三种耐张转角塔极导线和地线直接挂在塔身上,联接点适当错开,两横担为耐张塔极导线的跳线用。
由图2、图3、图4可见,这种塔型极导线的水平投影距离从常规两极水平布置的15米以上减少到1.8米左右,有效减小了线路走廊宽度,在经济发达的平原建筑特密集地区,可大大减少拆迁建筑物的数量。而且,采用这种塔型设计,不仅能减少拆房量,减轻政策处理的难度,还能节省大量的土地和工程建设投资。
附图说明
图1为直流双极水平排列输电线路铁塔的结构示意图;
图2、图3、图4为直流双极垂直排列“F”形输电线路系列铁塔的结构示意图,其中:
图2为直线塔的结构示意图;
图3为直线转角塔的结构示意图;
图4为耐张转角塔的结构示意图。
具体实施方式
下面结合附图和具体实施方式对本实用新型作进一步详细描述:
1、直线塔
直线塔(图2)由塔头、塔身(6)和塔腿(7)组成,其中塔头部分包括左地线横担(1)、右地线横担(2)、上极导线横担(3)、下极导线横担(4)和塔窗身部(5)。直线塔是典型的偏心受力结构,两极导线横担分上下两层,均布置于塔身一侧。上下两极导线通过等长V型绝缘子串(8)分别悬挂于上下极导线横担(3)和(4)上。上极导线横担(3)短,下极导线横担(4)长。由于两极导线均偏于塔身一侧,因此左右地线横担长度不一样,左地线横担(1)短,右地线横担(2)长。
2、直线转角塔
直线转角塔(图3)由塔头、塔身(6)和塔腿(7)组成,其中塔头部分包括外角侧地线横担(1)、内角侧地线横担(2)、上极导线横担(3)、下极导线横担(4)和塔窗身部(5)。直线转角塔是典型的偏心受力结构,两极导线横担分上下两层,均布置于塔身内角侧。
直线转角塔适用于10度以内的线路转角,两极导线通过不等长V型绝缘子串(8)与铁塔连接,V型绝缘子串(8)两连接点分别位于横担头部和横担与塔身连接处。上极导线横担(3)短,下极导线横担(4)长。
由于两极导线均偏于塔身内角侧,因此两侧地线横担长度不一样,外角侧地线横担(1)短,内角侧地线横担(2)长。
3、耐张转角塔
耐张转角塔(图4)与常规的直流双极水平排列输电线路铁塔相比,取消了极导线横担,上下两极导线通过耐张绝缘子串分别挂于塔窗身部挂点(9)和(10)上,结构布置非常紧凑。
耐张转角塔由塔头、塔身(6)和塔腿(7)组成,其中塔头部分包括上极导线挂点(9)、下极导线挂点(10)、上极导线跳线支架(11)、下极导线跳线支架(12)和塔窗身部(5)。上极导线挂点(9)和下极导线挂点(10)分别位于塔窗身部两侧。极导线跳线支架设置于极导线挂点上方,与相应的挂点位于塔窗身部同一侧,即挂点(9)和跳线支架(11)对应、挂点(10)和跳线支架(12)对应。

Claims (4)

1、一种直流双极垂直排列“F”形输电线路直线塔,其特征是:直流输电线路两极导线垂直布置,位于地线横担下层,分上下两层,依次为上极导线横担(3)和下极导线横担(4),极导线通过“V”型绝缘子串(8)与铁塔相连接。
2、如权利要求1所述的直流双极垂直排列“F”形输电线路直线塔,其特征是,所述“V”型绝缘子串(8)为等长“V”型绝缘子串。
3、如权利要求1所述的直流双极垂直排列“F”形输电线路直线塔,其特征是,所述“V”型绝缘子串(8)为不等长“V”型绝缘子串。
4、一种直流双极垂直排列“F”形输电线路耐张转角塔,其特征是:直流输电线路两极导线分上下两层垂直布置,不设置极导线横担,极导线通过耐张绝缘子串直接挂于塔窗身部挂点(9)和(10),挂点(9)和(10)上下布置并适当错开,分别位于塔窗身部两侧,同时在极导线挂点上方同一侧分别设置跳线支架(11)和(12),即挂点(9)和跳线支架(11)对应,挂点(10)和跳线支架(12)对应。
CN 200520102214 2005-05-16 2005-05-16 直流双极垂直排列“f”形输电线路系列铁塔 Expired - Fee Related CN200976471Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200520102214 CN200976471Y (zh) 2005-05-16 2005-05-16 直流双极垂直排列“f”形输电线路系列铁塔

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200520102214 CN200976471Y (zh) 2005-05-16 2005-05-16 直流双极垂直排列“f”形输电线路系列铁塔

Publications (1)

Publication Number Publication Date
CN200976471Y true CN200976471Y (zh) 2007-11-14

Family

ID=38902751

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200520102214 Expired - Fee Related CN200976471Y (zh) 2005-05-16 2005-05-16 直流双极垂直排列“f”形输电线路系列铁塔

Country Status (1)

Country Link
CN (1) CN200976471Y (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101672124B (zh) * 2009-09-25 2011-06-15 国网电力科学研究院 一种复合材料杆塔
CN102287070A (zh) * 2011-06-29 2011-12-21 浙江省电力设计院 一种z型边坡塔
CN102508964A (zh) * 2011-11-03 2012-06-20 国网电力科学研究院 直流输电线路地面合成电场计算方法
CN102852370A (zh) * 2012-10-10 2013-01-02 北京玻钢院复合材料有限公司 一种高压输电线路杆塔用的复合材料组合式横担
CN105449616A (zh) * 2015-12-31 2016-03-30 国网浙江奉化市供电公司 一种双回路架空线路改造装置
CN105781215A (zh) * 2016-04-29 2016-07-20 邹平县供电公司 一种基于输电施工系统可均匀沉降的输电线路铁塔装置

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101672124B (zh) * 2009-09-25 2011-06-15 国网电力科学研究院 一种复合材料杆塔
CN102287070A (zh) * 2011-06-29 2011-12-21 浙江省电力设计院 一种z型边坡塔
CN102287070B (zh) * 2011-06-29 2013-04-03 浙江省电力设计院 一种z型边坡塔
CN102508964A (zh) * 2011-11-03 2012-06-20 国网电力科学研究院 直流输电线路地面合成电场计算方法
CN102852370A (zh) * 2012-10-10 2013-01-02 北京玻钢院复合材料有限公司 一种高压输电线路杆塔用的复合材料组合式横担
CN105449616A (zh) * 2015-12-31 2016-03-30 国网浙江奉化市供电公司 一种双回路架空线路改造装置
CN105781215A (zh) * 2016-04-29 2016-07-20 邹平县供电公司 一种基于输电施工系统可均匀沉降的输电线路铁塔装置
CN105781215B (zh) * 2016-04-29 2017-12-22 邹平县供电公司 一种基于输电施工系统可均匀沉降的输电线路铁塔装置

Similar Documents

Publication Publication Date Title
CN200976471Y (zh) 直流双极垂直排列“f”形输电线路系列铁塔
CN103362343A (zh) 一种同塔六回路杆塔
CN206673533U (zh) 一种新型高压输电线路转角杆安装结构
CN203352105U (zh) 一种导线排列方式转换杆
CN201332249Y (zh) 同塔三回输电线路酒杯形直线塔
CN202721351U (zh) 一种220千伏hgis配电装置的双层出线结构
CN203260976U (zh) 电缆终端塔
CN208479112U (zh) 一种用于已建单回耐张塔的电缆引下专用杆
CN201821070U (zh) 双回紧凑型输电线路跳线为水平绕跳的转角塔
CN204691375U (zh) 一种220kV四回路电缆终端窄基钢管塔
CN206722513U (zh) 一种架空输电线路复合材料穿心直线塔
CN206220619U (zh) 一种单回架空输电线路电缆t接引下耐张塔
CN206302128U (zh) 一种悬索拉线塔绝缘子串
CN115313278A (zh) 一种直线杆塔
CN108005458A (zh) 双回路单开断π型铁塔
CN204928052U (zh) 一种杆式垂直排列紧凑型输电线路
CN201332250Y (zh) 同塔三回输电线路猫头形直线塔
CN204402131U (zh) 一种新型输电线路铁塔结构
CN203589482U (zh) 一种750kV悬吊管母线进出线结构
CN205283055U (zh) 一种110kV架空线路
CN221031765U (zh) 一种220kV双回矮型电缆终端杆
CN214697175U (zh) 一种分体式钻越用高压输电线路铁塔
CN211647529U (zh) 双回路杆塔
CN220247776U (zh) 四分裂导线用220kV水平排列耐张矩形根开低穿塔
CN211597956U (zh) 一种66kV双回输电线路直线耐张分歧铁塔

Legal Events

Date Code Title Description
C57 Notification of unclear or unknown address
DD01 Delivery of document by public notice

Addressee: Wang Jun

Document name: Correction notice

C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20081121

Address after: No. 69, false Hill Road, Gongshu District, Zhejiang, Hangzhou: 310014

Co-patentee after: State Grid DC Project Construction Co., Ltd.

Patentee after: Zhejiang Electric Power Design Institute

Address before: No. 69, false Hill Road, Gongshu District, Zhejiang, Hangzhou: 310014

Patentee before: Zhejiang Electric Power Design Institute

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20071114

Termination date: 20140516