CN1676782A - Expansion hanging pile connecting end plate fastener and prefab - Google Patents
Expansion hanging pile connecting end plate fastener and prefab Download PDFInfo
- Publication number
- CN1676782A CN1676782A CN 200510069891 CN200510069891A CN1676782A CN 1676782 A CN1676782 A CN 1676782A CN 200510069891 CN200510069891 CN 200510069891 CN 200510069891 A CN200510069891 A CN 200510069891A CN 1676782 A CN1676782 A CN 1676782A
- Authority
- CN
- China
- Prior art keywords
- nut
- expansion hanging
- screw
- prefabricated component
- end plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The invention relates to tubular interface, the pre-make part, which is made of pre-make part's interface and the connection instruction between the pre-make parts as well as the facture of the pre-make part. The inflation hang-connection stake end-board interface comprises hang-connection screw cap, inflation hang-connection screw and inflation pin. The plug-connection screw cap connects reelingly to the screw part of the inflation hang-connection screw. When face-to-face connection, the inflation hang-connection bulgy stage of the screw inflation hang-connects to the inner of inflation hang-connection screw cap and hang-connects to the bulgy stage which in the cavity of the hang-connection screw cap by the role of pin. The pre-make part which is made of inflation hang-connection stake end-board interface has the hang-connection screw caps inserted in both the two ends. In the pre-make part, there are many items of the portrait reinforcing steel bar whose two ends clip to the steel cap of the hang-connection screw caps respectively. The inflation hang-connection screw is used to the face-to-face connection between the pre-make parts.
Description
Technical field:
The present invention relates to a kind of pile tube connects button, precast plate and connects that button, bridge pier connect button, bridge connects button and electric pole interface and prefabricated component thereof, and adopt pile tube to connect button, precast plate to connect button, bridge pier and connect button, bridge and connect the syndeton between being connected between being connected between being connected between pile tube that button and electric pole interface constitutes and pile tube and pile tube, precast plate and precast plate, bridge pier and bridge pier, electric pole preform rod and preform rod and the preparation method of prefabricated component, the genus prefabricated component connects to be detained and prefabricated component manufacturing field.
Background technology:
Notice of authorization CN2495685Y, title " concrete tubular pile snap joint ", this joint comprises respectively with last, stake is plugged into and is held two affixed end plates, connecting pin, offer screwed hole in the end plate of last stake, connecting pin one end is threaded and can cooperates with the screwed hole of last stake end plate, the other end is square, and both sides have to stagger closes tooth, the end plate below of following stake is embedded with connector box, between two ends of connector box and two pin plates compression spring is housed, the square hole that one end of connecting pin band engaging tooth can pass down on the end plate of stake inserts between two pin plates, on it engaging tooth can be meshing with each other with the tooth of pin plate one side.Its weak point: the one, because following end plate only depends on 6 connector boxs, last stake only depends on volume less than the termination of connector box and the concrete setting in the pile tube together, and can't be connected as a single entity with the longitudinal reinforcement in the pile tube, can't constitute overall structure with the cage of reinforcement in the pile tube, it connects suitable intensity initiative and reliability can't guarantee at all, particularly when connector box and termination are subjected to external impacts, its connector box produces with concrete inevitably with the termination and separates, can't guarantee to go up stake and following reliable the butt joint, this is present present technique field one of insurmountable technical barrier so far; The 2nd, the compression spring in the connector box in the pile crown plate up and down, after pile tube in depth touches underground water down, produce corrosion inevitably, As time goes on the elasticity of its compression spring will progressively disappear, the pile extension fracture takes place at last inevitably, seriously have influence on the safety factor and the safety of the building of building, this not only exists in the docking of the pile tube of this structure and pile tube, and in the docking of the pile tube of other tube pile structure and pile tube, seriously exist, be the present technique field so far still unsolved technical barrier two; The 3rd, when prefabricated, can't solve up and down pile crown plate and concrete and between the crackle that produced and the spillage phenomenon that caused of pile crown plate up and down, therefore reduced concrete intensity, easily pile breaking phenomenon taken place, this be the present technique field so far still unsolved technical barrier three; The 4th, the skirtboard that had of pile crown plate up and down, the circumferential reinforcement that pilespacing head plate place preceding 5~6 is enclosed can't be put and be welded on the longitudinal reinforcement, therefore the length that the reinforcing bar longitudinal extension is produced when haling longitudinal reinforcement, make before the pile crown plate place on several meters to tens of meters the longitudinal reinforcement acyclic at all to reinforcing bar, prefabricated pile tube, fragmentation takes place in its one inevitably, gently then influence piling quality, heavy then cause piling failure, this is that present present technique field is wanted to solve, but so far four of still unsolved technical barrier; The 5th, can't solve some longitudinal reinforcement longitudinal extension uniformity in the pile tube, can't realize that standardization hales the purpose of reinforcing bar, the bad aftereffect that is produced is: can't guarantee pile tube intensity, can't guarantee the uniformity of some pile tube inherent qualities, be that present present technique field is wanted to solve, but so far five of still unsolved technical barrier; The 6th, cost expense height, the fabricating cost of every block of pile crown plate up to 300 yuan about, increased construction costs widely.
Summary of the invention:
Purpose of design: avoid the weak point in the background technology, designing a kind of one is to guarantee that the steel hoop on the pile tube skeleton not only can be around to pile tube skeleton two ends, and can guarantee that its point is welded on the longitudinal reinforcement of skeleton, guarantee the uniformity of pile tube intensity, the fracture of fundamentally avoiding pile tube is with broken; The 2nd, fundamentally solve some longitudinal reinforcement longitudinal extension uniformity in the pile tube, reinforcing bar is haled in the realization standardization, guarantees the uniformity of industrialized mass production pile tube inherent quality; The 4th, guaranteeing to reduce the cost of production of pile tube (bridge prefabrication plate, electric pole precast body etc.) widely under the pile tube butt joint reliable quality prerequisite.
Design scheme: in order to realize purpose of design of the present invention, the present invention adopts the expansion hanging principle to force the expansion hanging screw moment formation expansion hanging between the pile tube that needs pile extension to dock.On structure design: 1, the design that articulates nut is one of feature of the present invention, and its major function is: the one, and articulate the screw thread in the nut and the screw section of expansion hanging screw and spin, work to hale reinforcing bar, pile extension; The 2nd, have a reinforced hole at the bottom of the cap of nut, the periphery of reinforced hole is reinforcing bar heading Ka Tai, this reinforcing bar heading card platform can be stuck in the reinforcing bar heading that will connect firmly and articulate in the nut.Its major function is: the one, hale the longitudinal reinforcement in the pile tube; The 2nd, be prefabricated component with prefabricated component between (being connected between being connected between pile tube and pile tube, between precast plate and precast plate, bridge pier and bridge pier, electric pole preform rod with between preform rod) when docking, in the expansion hanging screw boss of expansion hanging section insert articulate in the nut lumen and under the effect of the pin that expands with the chamber in inner convex platform form to articulate and combine; Haling longitudinal reinforcement is meant: after articulating the longitudinal reinforcement that nut is through pile tube, heading is upset at the two ends of its longitudinal reinforcement, the heading at its two ends is connected on the reinforcing bar heading Ka Tai that articulates nut firmly, fixedly articulate an end of nut, the other end with hale screw and spin after, hale screw and can realize haling the purpose that longitudinal reinforcement extends; 2, the design of expansion hanging screw is two of a feature of the present invention, its major function is: the one, and the expansion hanging section in the expansion hanging screw is after the insertion by force of the pin that is subjected to expanding, and its expansion hanging section expands in articulating the nut chamber and the expansion hanging boss of expansion hanging paragraph header portion can expand in articulating the nut chamber, articulate with inner convex platform formation in the chamber; The 2nd, the screw section in the expansion hanging screw with articulate nut and spin after, and the expansion hanging section can be docked with articulating nut realization plug-in type expansion hanging in moment, thereby docking with mode moment of expansion hanging between pile tube and pile tube can be finished.
Technical scheme 1: expansion hanging formula pile extension end plate is buckled, 2 or a plurality of nut (2) that articulates are distributed in and articulate the screw section that nut (3) is screwed in expansion hanging screw (4) on the end plate (15), during butt joint, the expansion hanging boss (9) of expansion hanging screw (4) articulates in the expansion hanging nut (2) and with the inner convex platform that articulates nut chamber (11) (8) under the effect of the pin (10) that expands.
Technical scheme 2: buckle the prefabricated component that constitutes by expansion hanging formula pile extension end plate, prefabricated component (12) two ends be built-in with respectively have an end plate (15) articulate nut (2), the heading (14) at some longitudinal reinforcements (13) two ends is connected to respectively on the reinforcing bar heading Ka Tai (5) that articulates in the nut (2) in the prefabricated component (12), and expansion hanging screw (4) is used for docking between prefabricated component and prefabricated component.
Technical scheme 3: buckle the prefabricated component that constitutes and the docking structure between prefabricated component by expansion hanging formula pile extension end plate, the end of two prefabricated components that dock is equipped with several that have end plate respectively and articulates nut, the screw section of expansion hanging screw is screwed in the screw thread that articulates nut, the expansion hanging section of expansion hanging screw insert articulate articulate in the nut in the nut chamber and with its expansion hanging, finish docking between prefabricated component and prefabricated component.
Technical scheme 4: buckle the preparation method of making prefabricated component by expansion hanging formula pile extension end plate, the heading of some longitudinal reinforcements is stuck in the heading Ka Tai that articulates nut that has end plate and goes up and put it in the shaping mould in the reinforcing cage, hale simultaneously prefabricated component die cavity one end articulate nut to the power that sets, force some reinforcing bars to extend to the length that sets synchronously after, centrifugal casting or vibration foundry goods, promptly get and have the prefabricated component that articulates nut structure, the expansion hanging screw is used for docking between prefabricated component and prefabricated component.
The present invention compares with background technology, and the one, the defective that the pipe pile reinforcing bar skeleton that does not fundamentally exist background technology to exist separates with pile tube end plate two; The 2nd, the pile extension phenomenon of rupture takes place when fundamentally avoiding present all pile tubes and pile tube pile extension or behind the pile extension, guaranteed the safety factor and the safety of piling quality, fundamentally guaranteed building, particularly the reliability of high-rise building foundation quality; The 3rd, the application is not owing to exist up and down pile crown plate, therefore do not have the crackle that produced between pile crown end plate and the concrete and the spillage phenomenon that caused of pile crown plate up and down, guaranteed pile tube globality and intensity, eliminated the pile breaking phenomenon of background technology existence; The 4th, because the skirtboard that the application does not exist pile crown plate up and down to be had, therefore can make circumferential reinforcement spot weld the longitudinal reinforcement two ends, do not exist to leak to weld and punctuate, when haling longitudinal reinforcement, steel hoop on the longitudinal reinforcement can extend with the extension of longitudinal reinforcement synchronously, guaranteed the uniformity and the globality of pipe pile reinforcing bar skeleton quality, has fundamentally solved piling that background technology exists when stressed, its pile tube fragmentation, the fracture defective; The 5th, the expansion hanging boss combines with articulating articulating of nut inner chamber inner convex platform formation in the expansion hanging screw, has guaranteed the reliable connection between pile tube and pile tube; The 6th, solve the problem that some longitudinal reinforcements in the pile tube can't the standardization longitudinal extension, realized the uniformity of pile tube intensity, pile tube inherent quality; The 6th, reduced the cost of production of pile tube widely, only remove one of tubular pile head end plate, only domestic annual demand is saved about 30 yuan of cost for every more than 100,000,000, can produce unexpected economic benefit and social benefit every year for saving RMB more than 3,000,000,000 yuan; The 7th, start made between pile tube and pile tube, the novel docking structure between precast plate and precast plate, between bridge pier and bridge pier, between electric pole preform rod and preform rod.
Description of drawings:
Fig. 1 is the structural representation that expansion hanging formula pile extension end plate is buckled.
Fig. 2 is the structural representation that articulates nut.
Fig. 3 is the main TV structure schematic diagram of expansion hanging screw.
Fig. 4 is the structural representation that expands and sell.
Fig. 5 is the plan structure schematic diagram of expansion hanging section in the expansion hanging screw.
Fig. 6 is the structural representation of pile tube.
Fig. 7 is that expansion hanging formula pile extension end plate is buckled the pile tube of formation and the docking structure schematic diagram between pile tube or bridge pier and bridge pier or electric pole and electric pole.
The specific embodiment:
Embodiment 1: with reference to accompanying drawing 1~5.Expansion hanging formula pile extension end plate is buckled, 2 or a plurality of nut 2 that articulates are distributed on the end plate 15, articulate the screw section that nut 2 is screwed in expansion hanging screw 4, during butt joint, the expansion hanging boss 9 of expansion hanging screw 4 articulates in the expansion hanging nut 2 and with the inner convex platform 8 that articulates nut chamber 11 under the effect of the pin 10 that expands, and sees accompanying drawing 1.Articulating nut 2 adopts metal (as steel, stainless steel, alloy steel etc.) or nonmetals (as plastics, synthetic plastic, pottery etc.) by existing casting or injection moulding or ceramic sintering or machining technique making, the center that articulates at the bottom of the cap of nut 2 has reinforced hole 1, and the periphery of reinforced hole 1 is a reinforcing bar heading card platform 5, articulates that the cap mouth of nut 2 is inboard to be screw thread 3.Articulate screw thread 3 in the nut 2 for haling screw thread, accompanying drawing 2; Expansion hanging screw 4 adopts metal (as steel, stainless steel, alloy steel etc.) or nonmetals (as plastics, synthetic plastic etc.) by existing casting or injection moulding or machining technique making, expansion hanging screw 4 is by the pin 10 that expands, expansion hanging section 6 and screw section 7 constitute, expansion hanging section 6 and screw section 7 are overall structure, the expansion hanging head of expansion hanging screw be boss structure and with articulate nut 2 chambeies 11 inner convex platforms 8 and articulate, hanging 9 moments of boss for the ease of the expansion in the expansion hanging screw 4 inserts in the expansion chamber 11 that articulates in the nut, the expansion of expansion hanging screw 4 is hung the arm of angle that connects of the end of boss and outwell a circle, see accompanying drawing 3.Articulate nut 2, expansion hanging screw 4, expand and sell 10 employing metals or nonmetals making; Metal material is meant all kinds of steel and alloy thereof, and nonmetals are batch plastics, resin, nylon, pottery and synthetic materials thereof etc.
Embodiment 2: with reference to accompanying drawing 6.On the basis of embodiment 1, buckle the prefabricated component (pipe shape, square pipe pile etc.) that constitutes by expansion hanging formula pile extension end plate, buckle the prefabricated component that constitutes by expansion hanging formula pile extension end plate, prefabricated component 12 two ends be built-in with respectively have an end plate 15 articulate nut 2, the heading 14 at some longitudinal reinforcement 13 two ends is connected to respectively on the reinforcing bar heading card platform 5 that articulates in the nut 2 in the prefabricated component 12, and expansion hanging screw 4 is used for docking between prefabricated component and prefabricated component.(this expansion hanging screw 4 is when pile tube docks with pile tube, and the screw section of its expansion hanging screw is screwed in and articulates in the nut 2; When pile tube does not dock with pile tube, its expansion hanging screw 4 with articulate nut 2 and separate, keeping separately).
Embodiment 3: with reference to accompanying drawing 7.On the basis of embodiment 1 and 2, the end of two prefabricated components that dock is equipped with several that have end plate respectively and articulates nut, the screw section of expansion hanging screw is screwed in the screw thread that articulates nut, the expansion hanging section of expansion hanging screw insert articulate articulate in the nut in the nut chamber and with its expansion hanging, finish docking between prefabricated component and prefabricated component.
Embodiment 4: with reference to accompanying drawing 7.On the basis of embodiment 1 and 2, buckle between the prefabricated component and prefabricated component that constitutes the docking structure of (between bridge board and bridge board, between electric pole and electric pole or the like) by expansion hanging formula pile extension end plate, the end of two prefabricated components that dock is equipped with several that have end plate respectively and articulates nut, the screw section of expansion hanging screw is screwed in the screw thread that articulates nut, the expansion hanging section of expansion hanging screw, insertion articulate articulate in the nut in the nut chamber and with its expansion hanging, finish docking between prefabricated component and prefabricated component.
Embodiment 5: buckled the preparation method of making prefabricated component by expansion hanging formula pile extension end plate, buckle the preparation method of making prefabricated component by expansion hanging formula pile extension end plate, the heading of some longitudinal reinforcements is stuck in the heading Ka Tai that articulates nut that has end plate and goes up and put it in the shaping mould in the reinforcing cage, that hales prefabricated component die cavity one end simultaneously articulates nut to the power that sets, after forcing some reinforcing bars to extend to the length that sets synchronously, centrifugal casting or vibration foundry goods, promptly get and have the prefabricated component that articulates nut structure, the expansion hanging screw is used for docking between prefabricated component and prefabricated component.
What need understand is: though the foregoing description is to the present invention's detailed explanation of contrasting; but these embodiment are just illustrative to the present invention; rather than limitation of the present invention, any innovation and creation that do not exceed in the connotation of the present invention all fall within the scope of protection of the present invention.
Claims (8)
1, a kind of expansion hanging formula pile extension end plate is buckled, it is characterized in that: 2 or a plurality of nut (2) that articulates are distributed in and articulate the screw section that nut (3) is screwed in expansion hanging screw (4) on the end plate (15), during butt joint, the expansion hanging boss (9) of expansion hanging screw (4) articulates in the expansion hanging nut (2) and with the inner convex platform that articulates nut chamber (11) (8) under the effect of the pin (10) that expands.
2, expansion hanging formula pile extension end plate according to claim 1 is buckled, it is characterized in that: the center that articulates at the bottom of the cap of nut (2) has reinforced hole (1), the periphery of reinforced hole (1) is reinforcing bar heading Ka Tai (5), and the cap mouth inboard that articulates nut (2) is screw thread (3).
3, expansion hanging formula pile extension end plate according to claim 2 is buckled, and it is characterized in that: articulate screw thread (3) in the nut (2) for haling screw thread.
4, expansion hanging formula pile extension end plate according to claim 1 is buckled, it is characterized in that: expansion hanging screw (4) is made of expand pin (10), expansion hanging section (6) and screw section (7), expansion hanging section (6) and screw section (7) are overall structure, the expansion hanging head of expansion hanging screw be boss structure and with articulate nut (2) chamber (11) inner convex platform (8) and articulate.
5, a kind ofly buckle the prefabricated component that constitutes by expansion hanging formula pile extension end plate, it is characterized in that: prefabricated component (12) two ends be built-in with respectively have an end plate (15) articulate nut (2), the heading (14) at some longitudinal reinforcements (13) two ends is connected to respectively on the reinforcing bar heading Ka Tai (5) that articulates in the nut (2) in the prefabricated component (12), and expansion hanging screw (4) is used for docking between prefabricated component and prefabricated component.
6, a kind ofly buckle the prefabricated component that constitutes and the docking structure between prefabricated component by expansion hanging formula pile extension end plate, it is characterized in that: the end of two prefabricated components that dock is equipped with several that have end plate respectively and articulates nut, the screw section of expansion hanging screw is screwed in the screw thread that articulates nut, the expansion hanging section of expansion hanging screw insert articulate articulate in the nut in the nut chamber and with its expansion hanging, finish docking between prefabricated component and prefabricated component.
7, a kind of preparation method of making prefabricated component of buckleing by expansion hanging formula pile extension end plate, it is characterized in that: the heading of some longitudinal reinforcements is stuck in the heading Ka Tai that articulates nut that has end plate and goes up and put it in the shaping mould in the reinforcing cage, hale simultaneously prefabricated component die cavity one end articulate nut to the power that sets, force some reinforcing bars to extend to the length that sets synchronously after, centrifugal casting or vibration foundry goods, promptly get and have the prefabricated component that articulates nut structure, the expansion hanging screw is used for docking between prefabricated component and prefabricated component.
8, according to claim 7ly buckle the pile extension method of making pile tube, it is characterized in that: the equal in length of some longitudinal reinforcements by expansion hanging formula pile extension end plate; Circumferential reinforcement welds or is bundled on the longitudinal reinforcement; Articulating nut draws the quantity of nut to equate with the top.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2005100698917A CN100408766C (en) | 2005-05-17 | 2005-05-17 | Expansion hanging pile connecting end plate fastener and prefab |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2005100698917A CN100408766C (en) | 2005-05-17 | 2005-05-17 | Expansion hanging pile connecting end plate fastener and prefab |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1676782A true CN1676782A (en) | 2005-10-05 |
CN100408766C CN100408766C (en) | 2008-08-06 |
Family
ID=35049502
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2005100698917A Expired - Fee Related CN100408766C (en) | 2005-05-17 | 2005-05-17 | Expansion hanging pile connecting end plate fastener and prefab |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100408766C (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104989716A (en) * | 2015-06-25 | 2015-10-21 | 周兆弟 | Connecting nut for connecting piece |
CN105002986A (en) * | 2015-06-25 | 2015-10-28 | 周兆弟 | Clamping matching type connecting element |
CN105040825A (en) * | 2015-07-07 | 2015-11-11 | 钟智谦 | Connecting structure and connecting method |
CN105040688A (en) * | 2015-06-25 | 2015-11-11 | 周兆弟 | Inserting head for connecting piece |
CN105040689A (en) * | 2015-06-25 | 2015-11-11 | 周兆弟 | Multi-column clamping connecting piece |
CN105155673A (en) * | 2015-06-25 | 2015-12-16 | 周兆弟 | Clamping connecting structure for connecting prefabricated members |
CN108951852A (en) * | 2018-10-16 | 2018-12-07 | 上海大禺预制构件有限公司 | A kind of prefabricated column |
CN114482030A (en) * | 2021-10-28 | 2022-05-13 | 广州市建筑集团有限公司 | Mechanical tooth rapid pile splicing device and method for PHC tubular pile |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02213513A (en) * | 1989-02-13 | 1990-08-24 | Taisei Corp | Method of coupling existing concrete pile |
CN2403821Y (en) * | 2000-01-12 | 2000-11-01 | 钟肇鸿 | Fast connector for steel reinforced concrete precast pile |
CN2495685Y (en) * | 2001-08-01 | 2002-06-19 | 钟肇鸿 | Quick-action joint for prestressed concrete piles |
CN1603523A (en) * | 2004-11-16 | 2005-04-06 | 周兆弟 | Upper screw lower connecting pile fastener and precast member |
CN2795282Y (en) * | 2005-05-17 | 2006-07-12 | 周兆弟 | Expansion hanging type pile extension end plate and prefabricated member |
-
2005
- 2005-05-17 CN CNB2005100698917A patent/CN100408766C/en not_active Expired - Fee Related
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104989716A (en) * | 2015-06-25 | 2015-10-21 | 周兆弟 | Connecting nut for connecting piece |
CN105002986A (en) * | 2015-06-25 | 2015-10-28 | 周兆弟 | Clamping matching type connecting element |
CN105040688A (en) * | 2015-06-25 | 2015-11-11 | 周兆弟 | Inserting head for connecting piece |
CN105040689A (en) * | 2015-06-25 | 2015-11-11 | 周兆弟 | Multi-column clamping connecting piece |
CN105155673A (en) * | 2015-06-25 | 2015-12-16 | 周兆弟 | Clamping connecting structure for connecting prefabricated members |
CN105002986B (en) * | 2015-06-25 | 2017-03-08 | 周兆弟 | Clamping engagement formula connector |
CN104989716B (en) * | 2015-06-25 | 2018-05-15 | 周兆弟 | Attaching nut for connector |
CN105155673B (en) * | 2015-06-25 | 2018-09-14 | 周兆弟 | Plug-in connection structure for prefabricated components connection |
CN105040825A (en) * | 2015-07-07 | 2015-11-11 | 钟智谦 | Connecting structure and connecting method |
CN108951852A (en) * | 2018-10-16 | 2018-12-07 | 上海大禺预制构件有限公司 | A kind of prefabricated column |
CN114482030A (en) * | 2021-10-28 | 2022-05-13 | 广州市建筑集团有限公司 | Mechanical tooth rapid pile splicing device and method for PHC tubular pile |
CN114482030B (en) * | 2021-10-28 | 2024-04-12 | 广州市建筑集团有限公司 | Mechanical tooth rapid pile extension device and pile extension method for PHC pipe pile |
Also Published As
Publication number | Publication date |
---|---|
CN100408766C (en) | 2008-08-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100348803C (en) | Pile connecting buckle and its prefabricated unit | |
CN1676782A (en) | Expansion hanging pile connecting end plate fastener and prefab | |
CN1603523A (en) | Upper screw lower connecting pile fastener and precast member | |
CN2795296Y (en) | Expansion hanging type pile extension buckle and prefabricated member | |
CN1676781A (en) | Expansion hanging pile connecting fastener and prefab | |
CN2861281Y (en) | Elastic meshing body pile connecting fastener and prefab | |
CN1676771A (en) | Double-end inserting elastic meshing body pile connecting end plate and prefab | |
CN2795284Y (en) | Top screw bottom lift expansion engaged body pile extension end plate and prefabricated member | |
CN2890173Y (en) | Splicing type pile-splicing buckle and precast products | |
CN1676766A (en) | Expansion meshing body pile-connecting end plate and prefab | |
CN2795282Y (en) | Expansion hanging type pile extension end plate and prefabricated member | |
CN1676775A (en) | Elastic meshing body pile connecting fastener and prefab | |
CN200946273Y (en) | Plugging-in type pipe-connecting fastener | |
CN2795285Y (en) | Expansion engaged body pile extension end plate and prefabricated member | |
CN1676764A (en) | Upper-screw-lower-top expansion meshing body pile-connecting fastener and prefab | |
CN2795286Y (en) | Expansion engaged body pile extension buckle and fabricated member | |
CN2795283Y (en) | Top screw bottom lift expansion engaged body pile extension buckle and prefabricated member | |
CN200964590Y (en) | Plugging-in type pipe connection fastener and preform | |
CN1676778A (en) | Double-end expansion hanging pile connecting fastener and prefab | |
CN1676774A (en) | Eleastic expansion meshing body pile connecting end plate and prefab | |
CN100445474C (en) | Expansion meshing body pile-connecting fastener and prefab | |
CN2795289Y (en) | Double head insert expansion engaged body pile extension end plate and prefabricated member | |
CN100445472C (en) | Upper-screw-lower-top expansion meshing body pile-connecting end plate and prefab | |
CN201033871Y (en) | Elastic expanding joggle joint pile end plate, precast member and butt-jointing structure between the members | |
CN2795293Y (en) | Double head expansion pile extension end plate buckle and prefabricated member |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20080806 Termination date: 20170517 |