CN1290792A - Construction equipment for in-site pouring concrete pile - Google Patents

Construction equipment for in-site pouring concrete pile Download PDF

Info

Publication number
CN1290792A
CN1290792A CN 00120876 CN00120876A CN1290792A CN 1290792 A CN1290792 A CN 1290792A CN 00120876 CN00120876 CN 00120876 CN 00120876 A CN00120876 A CN 00120876A CN 1290792 A CN1290792 A CN 1290792A
Authority
CN
China
Prior art keywords
mentioned
casing
vibrator
guide frame
equipment according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 00120876
Other languages
Chinese (zh)
Other versions
CN1112486C (en
Inventor
王继忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING PUISSANT GEOTECHNICAL ENGINEERING Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=4588453&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CN1290792(A) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Individual filed Critical Individual
Priority to CN 00120876 priority Critical patent/CN1112486C/en
Publication of CN1290792A publication Critical patent/CN1290792A/en
Application granted granted Critical
Publication of CN1112486C publication Critical patent/CN1112486C/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The construction equipment of the present invention can pouring high quality concrete pile in various geological conditions. It includes bottom base, vertical frame on the front part of the base supported by an inclined support on the base, hoist fixed on the base, pulley on the top of the frame and weight hung by rope extending from the hoist and wound through the pulley. By means of the motion of the weight through one protecting cylinder, the bottom of pile hole is tamped. The equipment also includes one vibrator applying vibrating force to the protecting cylinder.

Description

The construction equipment of in-site pouring concrete pile
The present invention relates to the basic field in the civil engineering, particularly relate to the construction equipment of in-site pouring concrete pile.
In the past, for the construction of in-site pouring concrete pile, include hammering pore-forming perfusion, promptly at first with the mode of pipe casing is squeezed in the ground, inserted reinforced material to bottom, stake hole afterwards, form bearing course at pile end by hammering, promote casing then on one side, on one side concrete perfusion.The shortcoming of above-mentioned prior art is running into some soil body, and during such as silt, the soil body is bigger to the frictional force of casing external surface, thereby be difficult to this casing is sunk to prescribed depth, when running in addition, produce sometimes and suck the hammer phenomenon than the pan soil body, promptly hammer into shape be driven into its bottom along casing after, this hammer inserts in the soil body of casing bottom, produce vacuum and be difficult to extract,, increase trouble also can for construction even hammer body is extracted, such as the loss of wire rope, incur loss through delay the duration.In addition, in the construction of pile concrete, when pouring into pile concrete promoting casing, concrete is closely knit inadequately, can't guarantee the quality of pile concrete.In a word, above-mentioned existing construction equipment can not adapt to the condition of various foundation soil bodies, can not successfully carry out the construction of stake.
The object of the present invention is to provide a kind of construction equipment of in-site pouring concrete pile, it can make the construction of stake carry out smoothly, can adapt to various geological conditionss, guarantees the construction quality of stake.
The construction equipment of in-site pouring concrete pile of the present invention comprises the chassis, the perpendicular direction of the front end edge on this chassis is provided with guide frame, this guide frame is supported on the chassis by the inclination support unit, on the chassis, be fixed with main winch, top at guide frame is provided with pulley mechanism, the rope that stretches out from above-mentioned main winch is walked around above-mentioned pulley mechanism and suspended in midair weight, this weight is done elevating movement in casing inside, can realize that this equipment also comprises the vibrator that can apply vibration force to above-mentioned casing to the ramming of stake hole bottom.
In the construction equipment of above-mentioned in-site pouring concrete pile, also be provided with the casing detent mechanism, it is used to make casing align piles position, and it is crooked to prevent that casing from producing.
In the construction equipment of above-mentioned in-site pouring concrete pile, above-mentioned vibrator comprises motor, and this motor drives eccentric block by gear drive and produces vibration.
In the construction equipment of above-mentioned in-site pouring concrete pile, above-mentioned vibrator comprises motor, this motor drives eccentric block and produce vibration.
In above-mentioned construction equipment at above-mentioned in-site pouring concrete pile, above-mentioned vibrator comprises can make weight along the hole of passing up and down, the rope that maybe can make the suspention weight is along the hole of passing up and down, both sides in this hole are provided with a motor respectively symmetrically, its power is at 7.5~15 kilowatts, and each motor drives eccentric block by gear drive and produces vibration.
In the construction equipment of above-mentioned in-site pouring concrete pile, the both sides of above-mentioned vibrator comprise the guide that this vibrator is moved up and down on the inboard edge of above-mentioned guide frame, such as roller.
In the construction equipment of above-mentioned in-site pouring concrete pile, above-mentioned vibrator is fixed in the casing top.
In the construction equipment of above-mentioned in-site pouring concrete pile, above-mentioned vibrator hangs on the top of above-mentioned guide frame by another rope of walking around the pulley mechanism that is arranged on the guide frame, so that when needs vibrate, above-mentioned vibrator is hung in the top of above-mentioned casing and this casing is applied vibration force, the other end of this another rope is wound on the secondary hoist engine that is fixed on the chassis.
In the construction equipment of above-mentioned in-site pouring concrete pile, above-mentioned vibrator is arranged in the vertical rod of above-mentioned guide frame.
In the construction equipment of above-mentioned in-site pouring concrete pile, above-mentioned casing detent mechanism comprises the casing location-plate of the front portion, bottom that is arranged at above-mentioned guide frame, its two ends are fixed with the fluid pressure type supporting leg that is fixed on the chassis respectively, offer the hole that casing is passed on this location-plate.
The advantage of the construction equipment of in-site pouring concrete pile of the present invention is hammering mode and mode of vibration combined, promptly casing is sunk to prescribed depth in the ground with vibration force and these two kinds of power of hammer force, for the softer soil body, only rely on mode of vibration that casing is sunk in the ground, and for some soil layer, such as than the pan soil body, only rely on the hammering mode that casing is sunk in the stratum, when running into powder soil horizon, in sinking to the process of casing, casing is applied vibration force, overcome the frictional force of casing external surface, and overcome end resistance by the hammering mode, because the effect of hammering is arranged in this process, so need not very big vibrational energy overcomes end resistance, on the other hand, because the effect of vibration, in the hammering process, can between the hammer body of stake end and the soil body, not produce vacuum, can not produce and suck the hammer phenomenon, consequently, the electric load of the motor in the vibrator is less, can not increase very big construction cost, vibrate lessly in addition, promptly vibrating noise is less, thereby can construct in densely populated area.In addition, in the concrete process of perfusion pile body, when promoting casing, casing is vibrated, can concrete vibrating is closely knit, voids and pits can not appear, and need not to insert vibrating spear in addition and vibrate, simplified construction, and the quality of stake is improved.
Below in conjunction with accompanying drawing, the embodiment of the construction equipment of in-site pouring concrete pile of the present invention is specifically described.
Fig. 1 is the elevation of construction equipment of the in-site pouring concrete pile of one embodiment of the present of invention;
Fig. 2 is the side view of above-mentioned construction equipment;
Fig. 3 is the partial enlarged drawing of the casing detent mechanism in the above-mentioned construction equipment;
As illustrated in fig. 1 and 2, construction equipment as the in-site pouring concrete pile of embodiments of the invention comprises chassis 7, this chassis 7 is anterior along vertically being provided with guide frame C, 7 rear portion is fixed with and puts formula main winch 3 soon on the chassis in addition, these main winch 3 back are provided with electrical control cubicles 16 and ballast pouring weight 6, main winch 3 the place aheads are provided with secondary hoist engine 4, between guide frame C and chassis 7, be connected with inclination cramp bar 2, above-mentioned guide frame C is the gate-type structure, the crossbeam 20 that it comprises two vertical poles 21 and is positioned at vertical pole 21 tops, vertical pole 21 is telescopic, it comprises the below, in this hollow stem 1 of hollow stem 1 that diameter is thicker and insertion, the bar 18 that diameter is thinner, be fixed with head pulley 8 and auxiliary pulley 15 on the crossbeam 20, the wire rope 28 that stretches out from main winch 3 is walked around this pulley 8 and is connected with elongated hammer 9 end faces, this hammer is done elevating movement in casing 13, two wire rope 22 that stretch out from secondary hoist engine 4 pass through auxiliary pulley 15, A suspends in midair with vibrator, so that realize the oscilaltion of a vibrator A, this vibrator A can be by the guide of both sides, chimeric such as roller with the guide rail that is arranged in the vertical rod 1, thereby can be along moving up and down, vibrator A can adopt multiple known type, such as adopting following form, the intermediate portion has the hole, this hole can make hammer pass through, bilateral symmetry ground in the hole is provided with the motor that is respectively arranged with 1 7.5 kilowatts, and each motor can drive a corresponding eccentric block by gear drive separately.The arranged outside on above-mentioned chassis 7 has a plurality of vertical support mechanism 14, and such as the fluid pressure type supporting leg, the bottom surface on chassis 7 is provided with rotating disk 27, and this rotating disk 27 is supported on hydraulic moving mechanism system 5.
As shown in Figure 3, the construction equipment of the in-site pouring concrete pile of embodiments of the invention also comprises casing detent mechanism B, it comprises location-plate 19, the pars intermedia of this location-plate 19 offers the hole of passing for casing 13, the two ends of location-plate 19 are fixed with fluid pressure type supporting leg 10 respectively, 10,10 fens other top portion of this fluid pressure type supporting leg are not fixed on the chassis 7.

Claims (10)

1. the construction equipment of an in-site pouring concrete pile, it comprises the chassis, the perpendicular direction of the front end edge on this chassis is provided with guide frame, this guide frame is supported on the chassis by the inclination support unit, on the chassis, be fixed with main winch, top at guide frame is provided with pulley mechanism, the rope that stretches out from above-mentioned main winch is walked around above-mentioned pulley mechanism and suspended in midair weight, this weight is done elevating movement in casing inside, can realize that this equipment also comprises the vibrator that can apply vibration force to above-mentioned casing to the ramming of stake hole bottom.
2. equipment according to claim 1 is characterized in that also being provided with the casing detent mechanism, and it is used to make casing align piles position, and it is crooked to prevent that casing from producing.
3. equipment according to claim 1 is characterized in that above-mentioned vibrator comprises motor, and this motor drives eccentric block by gear drive and produces vibration.
4. equipment according to claim 1 is characterized in that above-mentioned vibrator comprises motor, this motor drives eccentric block and produce vibration.
5. equipment according to claim 1, it is characterized in that above-mentioned vibrator comprises the hole that the weight edge is passed up and down, the rope that maybe can make the suspention weight is along the hole of passing up and down, both sides in this hole are provided with a motor respectively symmetrically, its power is at 7.5~15 kilowatts, and each motor drives eccentric block by gear drive and produces vibration.
6. equipment according to claim 1 is characterized in that the both sides of above-mentioned vibrator comprise the guide that this vibrator is moved up and down on the inboard edge of above-mentioned guide frame, and this guide is a roller.
7. equipment according to claim 1 is characterized in that above-mentioned vibrator is fixed in the casing top.
8. equipment according to claim 1, it is characterized in that above-mentioned vibrator hangs on the top of above-mentioned guide frame by another rope of walking around the pulley mechanism that is arranged on the guide frame, so that when needs vibrate, above-mentioned vibrator is hung in the top of above-mentioned casing and this casing is applied vibration force, the other end of this another rope is wound on the secondary hoist engine that is fixed on the chassis.
9. equipment according to claim 1 is characterized in that above-mentioned vibrator is arranged in the vertical rod of above-mentioned guide frame.
10. equipment according to claim 2, it is characterized in that the casing detent mechanism comprises the casing location-plate of the front portion, bottom that is arranged at above-mentioned guide frame, its two ends are fixed with the fluid pressure type supporting leg that is fixed on the chassis respectively, offer the hole that casing is passed on this location-plate.
CN 00120876 2000-08-04 2000-08-04 Construction equipment for in-site pouring concrete pile Expired - Lifetime CN1112486C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 00120876 CN1112486C (en) 2000-08-04 2000-08-04 Construction equipment for in-site pouring concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 00120876 CN1112486C (en) 2000-08-04 2000-08-04 Construction equipment for in-site pouring concrete pile

Publications (2)

Publication Number Publication Date
CN1290792A true CN1290792A (en) 2001-04-11
CN1112486C CN1112486C (en) 2003-06-25

Family

ID=4588453

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 00120876 Expired - Lifetime CN1112486C (en) 2000-08-04 2000-08-04 Construction equipment for in-site pouring concrete pile

Country Status (1)

Country Link
CN (1) CN1112486C (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101831908A (en) * 2010-05-11 2010-09-15 武汉华威建筑桩工机械有限责任公司 Large-diameter ultra-deep static-pressure single tube immersing ramming grouting pile construction process and device
CN103821147A (en) * 2014-01-11 2014-05-28 石午江 Multifunctional mechanical hammering hole forming machine
CN104314078A (en) * 2014-11-05 2015-01-28 王继忠 Concrete pile construction equipment and construction method thereof
CN105264144A (en) * 2013-04-19 2016-01-20 弗拉克图姆2012公司 A hammering device and a method for operating a hammering device
CN106149480A (en) * 2016-08-24 2016-11-23 中铁四局集团建筑工程有限公司 It is applicable to the straight thread stake machine without hydraulic thick sand bed geology and construction method
CN108678381A (en) * 2018-06-29 2018-10-19 衡阳泰源商砼有限公司 A kind of concrete vibration stick

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101831908A (en) * 2010-05-11 2010-09-15 武汉华威建筑桩工机械有限责任公司 Large-diameter ultra-deep static-pressure single tube immersing ramming grouting pile construction process and device
CN105264144A (en) * 2013-04-19 2016-01-20 弗拉克图姆2012公司 A hammering device and a method for operating a hammering device
CN103821147A (en) * 2014-01-11 2014-05-28 石午江 Multifunctional mechanical hammering hole forming machine
CN104314078A (en) * 2014-11-05 2015-01-28 王继忠 Concrete pile construction equipment and construction method thereof
CN106149480A (en) * 2016-08-24 2016-11-23 中铁四局集团建筑工程有限公司 It is applicable to the straight thread stake machine without hydraulic thick sand bed geology and construction method
CN106149480B (en) * 2016-08-24 2018-12-28 中铁四局集团建筑工程有限公司 Straight rib line stake machine and construction method suitable for no hydraulic thick sand bed geology
CN108678381A (en) * 2018-06-29 2018-10-19 衡阳泰源商砼有限公司 A kind of concrete vibration stick

Also Published As

Publication number Publication date
CN1112486C (en) 2003-06-25

Similar Documents

Publication Publication Date Title
CN207332754U (en) Electric pole is digged pit upright bar integrated apparatus
CN107338781A (en) A kind of compacting pile construction device and its construction method
CN1112486C (en) Construction equipment for in-site pouring concrete pile
EP0560867B1 (en) Method for manufacturing a tubular foundation in the ground
CN211395670U (en) Piling device for building construction
CN110359447B (en) Pipe column
CN107461145A (en) A kind of construction piling equipment
CN210459189U (en) Novel BNT carrier pile and construction equipment thereof
CN207277312U (en) A kind of compacting pile construction device
CN1093582C (en) Construction method of in-situ pouring concrete pile and adopted construction equipment
CN211948416U (en) Immersed tube pile extruding machine
CN117231131A (en) Micro-hole cast-in-place pile drilling equipment and rapid drilling construction method
CN103866763B (en) Method for making pile by performing pile pressure irrigation through immersed tube and special device and application
RU2097489C1 (en) Process of placing concrete into cast-in-place piles and installation for its implementation
CN105840109A (en) Multifunctional rotary drilling machine movable assembling mechanism assembly
CN112012199A (en) A new type of BNT carrier pile and its construction equipment construction method
CN1070563C (en) Construction equipment of concrete pile with tamper diffusion head at bottom
CN219137675U (en) Static pressure stake machine
CN2354993Y (en) Apparatus for cast-in-situ concrete piles
CN217923563U (en) Soil pile pressing machine
CN106149480B (en) Straight rib line stake machine and construction method suitable for no hydraulic thick sand bed geology
CN218843091U (en) Fixing mechanism of compaction equipment
CN117605023B (en) Bored pile construction device and construction method thereof
KR101005359B1 (en) Depth Drilling Rig
CN210975789U (en) Low clearance pile machine for squeezing and expanding broken stone

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: BEIJING PUISSANT GEOTECHNICAL ENGINEERING CO., LTD.

Assignor: Wang Jizhong

Contract record no.: 2011110000108

Denomination of invention: Construction equipment for in-site pouring concrete pile

Granted publication date: 20030625

License type: Exclusive License

Open date: 20010411

Record date: 20110718

C56 Change in the name or address of the patentee
CP02 Change in the address of a patent holder

Address after: 102218 Beijing city Changping District East Town Taiping home building No. 31 Beijing possente Geotechnical Engineering Co. Ltd.

Patentee after: Wang Jizhong

Address before: 061001 Yang Qiuxin, Department of economics and trade, Hebei Engineering and Technical College, 70 West Central Middle Road, Hebei, Cangzhou

Patentee before: Wang Jizhong

ASS Succession or assignment of patent right

Owner name: BEIJING PUISSANT GEOTECHNICAL ENGINEERING CO., LTD

Free format text: FORMER OWNER: WANG JIZHONG

Effective date: 20150104

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150104

Address after: 102218, Beijing, Changping District East small town Taiping homes, building 31

Patentee after: BEIJING PUISSANT GEOTECHNICAL ENGINEERING CO., LTD.

Address before: 102218 Beijing city Changping District East Town Taiping home building No. 31 Beijing possente Geotechnical Engineering Co. Ltd.

Patentee before: Wang Jizhong

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20030625