Disclosure of Invention
The application provides a construction method for accurately controlling settlement of an ultra-shallow soil-covered ultra-large-diameter shield tunnel, which can realize cooperative control of anti-floating and settlement of a tunnel structure.
In order to achieve the above purpose, the application adopts the following technical scheme:
The application provides a construction method for accurately controlling settlement of an ultra-shallow earthing ultra-large diameter shield tunnel, which comprises the following steps:
Constructing waterproof curtains along two sides of a tunnel design axis, and constructing club-footed piles in the waterproof curtains on each side, wherein the club-footed piles are distributed at intervals along the length direction of the waterproof curtains;
in a central area of a tunnel surrounded by the waterproof curtain, the soil body is integrally reinforced based on the triaxial mixing piles;
After the construction of the pedestal pile is completed, constructing a longitudinal beam and an anti-floating plate to form a door-type anti-floating structure, and synchronously embedding a ground grouting pipeline on the anti-floating plate under the condition of the construction of the anti-floating plate, wherein the longitudinal beam is arranged along the length direction of a tunnel;
Injecting slurry into the periphery of the tunnel segment in the process that the shield is pushed to the target construction section along the tunnel design axis;
under the condition that the shield passes through the target construction section, grouting liquid is pressed into a gap between the anti-floating plate and the tunnel segment through a ground grouting pipeline, so that tunnel construction is completed.
In some possible implementations, the waterproof curtain is constructed by a triaxial stirring pile process, the pile body bottom of the waterproof curtain extends to a target stratum below the tunnel bottom plate, and the horizontal distance between the waterproof curtains on two sides is larger than the horizontal width of the tunnel design outline.
In some possible implementation modes, the reinforcing range of the triaxial mixing pile to the soil body in the central area of the tunnel is that the horizontal direction covers a preset area extending to the left and right sides of the design contour line of the tunnel, the vertical direction is from the bottom surface of the anti-floating plate to a preset depth below the bottom plate of the tunnel, and the reinforced soil body and the waterproof curtains on the two sides form an integrated structure.
In some possible implementations, the bottom of the longitudinal beam is fixedly connected with the pile top of the club-footed pile through embedded bars, and the top of the longitudinal beam is integrally poured with the bottom surface of the anti-floating plate.
In some possible implementations, the ground grouting pipeline penetrates the anti-floating plate along a direction perpendicular to the anti-floating plate, an opening of a first port of the ground grouting pipeline faces to the top of the tunnel segment, and an opening of a second port of the ground grouting pipeline forms a grouting hole at the top of the anti-floating plate.
In some possible implementations, before grouting the slurry into the gap between the anti-floating plate and the tunnel segment through the ground grouting pipeline, the method further includes:
and determining the grouting sequence and single grouting amount of the grouting liquid based on the gap position and the volume between the anti-floating plate and the tunnel segment.
In some possible implementations, after grouting the slurry into the gap between the anti-floating plate and the tunnel segment through the ground grouting pipeline, the method further includes:
And verifying the gap filling effect, and performing secondary grouting through a ground grouting pipeline under the condition that an unfilled and filled region exists.
In some possible implementations, the method includes:
and under the condition that the pile spacing of the adjacent club-footed piles is smaller than a preset spacing threshold, adopting a pile jump construction mode.
In some possible implementations, the slurry is a dual slurry, mixed from cement slurry and water glass based on a predetermined ratio.
In some possible implementations, a reinforcing mesh is preset around the grouting holes of the ground grouting pipeline.
According to the technical scheme, the application has at least the following beneficial effects:
According to the application, by constructing waterproof curtains along two sides of a tunnel design axis and constructing bottom-expanding piles which are arranged at intervals in the waterproof curtains on each side, an effective underground water blocking system and a reliable anti-floating foundation are established, the soil body is integrally reinforced based on triaxial stirring piles in a central area of the tunnel surrounded by the waterproof curtains, the stratum stability and uniformity in the shield tunneling process are improved, after the bottom-expanding piles are constructed, longitudinal beams and anti-floating plates are constructed, a gate-type anti-floating structure is formed, ground grouting pipelines are synchronously embedded in the anti-floating plates under the condition of the construction of the anti-floating plates, a synergistic permanent anti-floating system is formed, an innovative process of ground pre-embedding and ground grouting is realized, slurry is timely injected into the periphery of a tunnel segment in the process of pushing the shield to a target construction segment along the tunnel design axis, floating and stratum settlement of the tunnel are restrained, and slurry is pressed into gaps between the anti-floating plates and the tunnel segment through the ground grouting pipelines under the condition that the shield passes through the target construction segment, so that the tunnel construction of the structure is completed, and hidden danger of the structure is thoroughly eliminated, and the long-term stability of the floating structure is ensured. The whole construction method forms a systematic sedimentation control system and realizes the cooperative control of anti-floating and sedimentation of the tunnel structure.
It should be appreciated that the description of technical features, aspects, benefits or similar language in the present application does not imply that all of the features and advantages may be realized with any single embodiment. Conversely, it should be understood that the description of features or advantages is intended to include, in at least one embodiment, the particular features, aspects, or advantages. Therefore, the description of technical features, technical solutions or advantageous effects in this specification does not necessarily refer to the same embodiment. Furthermore, the technical features, technical solutions and advantageous effects described in the present embodiment may also be combined in any appropriate manner. Those of skill in the art will appreciate that an embodiment may be implemented without one or more particular features, aspects, or benefits of a particular embodiment. In other embodiments, additional features and advantages may be recognized in certain embodiments that may not be present in all embodiments.
Detailed Description
The terms "first," "second," and "third," and the like, in the description and in the drawings, are used for distinguishing between different objects and not necessarily for describing a sequential or chronological order.
In embodiments of the application, words such as "exemplary" or "such as" are used to mean serving as an example, instance, or illustration. Any embodiment or design described herein as "exemplary" or "e.g." in an embodiment should not be taken as preferred or advantageous over other embodiments or designs. Rather, the use of words such as "exemplary" or "such as" is intended to present related concepts in a concrete fashion.
In view of the above, the embodiment of the application provides a construction method for accurately controlling settlement of an ultra-shallow soil-covered ultra-large-diameter shield tunnel, and in order to make the technical scheme of the application clearer and easier to understand, an application scene of the technical scheme of the application is described below with reference to the accompanying drawings. Fig. 1 is a schematic diagram of an application scenario provided in an embodiment of the present application.
In the application scene, firstly constructing waterproof curtains along two sides of a tunnel design axis, wherein the waterproof curtains are continuous seepage-proof structures and are used for blocking seepage of external groundwater to a tunnel area, avoiding construction influenced by excessive buoyancy of groundwater or seepage of strata, constructing foundation piles at intervals in the range of each waterproof curtain, expanding the bottoms of the foundation piles, enhancing the uplift resistance of pile bodies, providing stable vertical support for a subsequent anti-floating structure, simultaneously, integrally reinforcing the soil body in the central area of the tunnel surrounded by the waterproof curtains by using triaxial stirring piles to improve the compactness and bearing capacity of soil bodies around the tunnel, reducing stratum settlement during shield propulsion, constructing longitudinal beams and anti-floating plates at the top of the pile, arranging the longitudinal beams along the length direction of the tunnel, connecting the foundation piles at the same side, enabling the anti-floating plates to span over the tunnel, fixing the foundation piles at the two sides through the longitudinal beams, covering the tunnel area like a door frame, synchronously embedding ground grouting pipelines when the whole is constructed, providing for subsequent filling gaps, simultaneously, filling the grouting gaps towards the periphery of the tunnel segment along the axis of the tunnel segment, namely, controlling the grouting gaps between the foundation piles and the ground grouting layers when the tunnel segment is filled with the grouting pile, and the foundation pile is further prevented from being filled into the ground by the foundation pile, and the anti-floating pile is prevented from being filled into the gap between the ground, and the foundation pile.
In order to make the technical scheme of the application clearer and easier to understand, the method for accurately controlling the settlement of the ultra-shallow soil-covering ultra-large-diameter shield tunnel is introduced by combining the application scenes. As shown in FIG. 2, the method is a flow chart of a construction method for accurately controlling settlement of an ultra-shallow soil-covered ultra-large-diameter shield tunnel. The construction method for accurately controlling the settlement of the ultra-shallow earthing ultra-large diameter shield tunnel comprises the following steps:
S201, constructing waterproof curtains along two sides of a tunnel design axis, and constructing club-footed piles in the waterproof curtains on each side, wherein the club-footed piles are distributed at intervals along the length direction of the waterproof curtains.
Optionally, the waterproof curtain is constructed by adopting a triaxial stirring pile process, the bottom of the pile body of the waterproof curtain extends to a target stratum below the tunnel bottom plate, and the horizontal distance between the waterproof curtains on two sides is larger than the horizontal width of the tunnel design outline. And under the condition that the pile spacing of the adjacent club-footed piles is smaller than a preset spacing threshold, adopting a pile jump construction mode.
The tunnel design axis refers to the central line path of the tunnel in the horizontal and vertical directions, namely the theoretical position line of the tunnel design, and is a main reference for determining the trend and the position of the tunnel.
The waterproof curtain is an underground continuous wall formed by cement-soil mixing piles and the like, and mainly aims to block the flow path of underground water and prevent the underground water from penetrating into an excavation area.
The club-footed pile is a pile foundation, the diameter of the bottom of the club-footed pile is larger than that of the pile body (similar to an enlarged head), and the bearing capacity and the pulling resistance of the pile can be improved.
The length direction is the direction of extension along the tunnel axis, i.e. the longitudinal direction.
Spaced arrangement means that the driven piles are not continuous but are arranged at a certain pitch.
The triaxial stirring pile process is a foundation treatment method, and is characterized in that three drill rods are simultaneously rotated and sprayed with slurry to be mixed with soil to form a continuous cylindrical cement soil pile, and the continuous cylindrical cement soil pile is commonly used for forming a waterproof curtain or reinforcing a foundation.
The pile body of the waterproof curtain extends to the target stratum below the tunnel bottom plate, and the pile body of the waterproof curtain not only penetrates through the depth of the tunnel bottom plate, but also continues to extend downwards to reach a certain depth required by stable stratum or design, such as soil body extending to 3 meters below the tunnel bottom plate.
The tunnel design profile refers to the outline dimension of a tunnel section (such as a circular section), and is a theoretical boundary for determining the size of the tunnel section.
The horizontal distance is the transverse distance between the central lines of the waterproof curtains on two sides, and is generally larger than the width of the outline of the tunnel so as to ensure the integral protection of the tunnel.
Pile spacing refers to the distance between the center points of the same side underreamed piles.
The preset spacing threshold is the minimum allowable pile spacing preset in engineering design, and construction interference or soil damage caused by too close piles is prevented.
The pile jump construction mode is that when the pile distance is smaller, one pile is firstly constructed, and after the piles are solidified, the middle pile is constructed, so that the problem that the adjacent pile holes are extruded or collapsed during simultaneous construction is avoided.
The construction method comprises the steps of firstly constructing waterproof curtains along two sides of a tunnel design axis for blocking groundwater seepage of the periphery of a tunnel section before construction of accurate control of settlement of an ultra-shallow soil-covered ultra-large-diameter shield tunnel, and then constructing pedestal piles at certain intervals on the inner side of each waterproof curtain on each side to serve as key vertical bearing components of a portal anti-floating structure. The waterproof curtain is generally constructed by adopting a triaxial stirring pile process, the depth of the pile bottom of the waterproof curtain is required to extend to a stable stratum below a tunnel bottom plate, and the horizontal distance between the two side curtains is required to be larger than the width of a tunnel design outline so as to form an effective groundwater isolation and soil protection range. If the distance between adjacent club-footed piles is too small, pile jumping construction mode is adopted to sequentially carry out so as to avoid mutual interference and soil disturbance in the construction process, and therefore pile forming quality and safety and stability of the integral structure are ensured.
S202, integrally reinforcing soil based on triaxial mixing piles in a central area of a tunnel surrounded by the waterproof curtain.
Optionally, the reinforcing range of the triaxial mixing pile to the soil body in the central area of the tunnel is that the horizontal direction covers the preset area extending to the left and right sides of the design contour line of the tunnel, the vertical direction is from the bottom surface of the anti-floating plate to the preset depth below the bottom plate of the tunnel, and the reinforced soil body and the waterproof curtains on the two sides form an integrated structure.
The central area of the tunnel surrounded by the waterproof curtains is an inner area surrounded by the waterproof curtains at two sides of the tunnel, and is a construction range where the tunnel main body is located.
The triaxial mixing pile is a foundation treatment method for forming cylindrical continuous reinforcement by simultaneously rotating and spraying curing agent (usually cement slurry) through three coaxial drill rods and fully mixing with foundation soil.
The integral reinforcement refers to uniform and omnibearing strength improvement and stability improvement of soil body by adopting pile bodies which are continuously, fully distributed or staggered.
The reinforcement range refers to the spatial area where the soil body is treated by adopting the stirring piles.
The preset area is the reinforcement width determined according to engineering design requirements, such as 5 meters around the outline of the tunnel body.
The anti-floating plate is a reinforced concrete plate which is arranged above the tunnel and covers the section of the tunnel, and resists the lifting action of the buoyancy of the groundwater to the tunnel through the self weight and the connection with the lower structure.
The bottom surface of the anti-floating plate is the bottom elevation of the upper horizontal anti-floating plate in the door-type anti-floating structure.
The tunnel floor is the bottommost portion of the tunnel structure and is commonly referred to as the bottom end of a segment or lining.
The preset depth is a lower limit of reinforcement depth specified in the design, such as 3 meters below the tunnel floor.
The integrated structure is that the reinforced soil body and the waterproof curtains on two sides are tightly combined in mechanics and space to form a continuous and synergistic whole.
For example, after the construction of waterproof curtains on two sides of a tunnel is completed, the soil body of the central area of the tunnel formed by enclosing the curtains needs to be integrally reinforced. The reinforcement adopts a triaxial stirring pile process, the reinforcement range covers a certain width (for example, 5 meters each) extending to the left and right sides of the tunnel design contour line in the horizontal direction, and the reinforcement range is raised from the bottom surface elevation of the upper anti-floating plate to a certain depth (for example, 3 meters) below the tunnel bottom plate in the vertical direction. Through the reinforcement treatment, the bearing capacity and uniformity of the shield tunneling cross-region soil body are obviously improved, the reinforcement soil body and the waterproof curtains on the two sides form a continuous and cooperatively stressed integral structure, and reliable foundation guarantee is provided for the subsequent shield tunneling and long-term stability of the tunnel structure.
S203, after the pedestal pile construction is completed, constructing a longitudinal beam and an anti-floating plate to form a door type anti-floating structure, and synchronously embedding a ground grouting pipeline on the anti-floating plate under the condition of the anti-floating plate construction.
Optionally, the stringers are arranged along the length direction of the tunnel. Reinforcing steel bar meshes are preset around grouting holes of the ground grouting pipeline.
The bottom of the longitudinal beam is fixedly connected with the pile top of the club-footed pile through embedded bars, and the top of the longitudinal beam and the bottom surface of the anti-floating plate are poured into a whole.
The ground grouting pipeline penetrates through the anti-floating plate along the direction perpendicular to the anti-floating plate, the opening of the first port of the ground grouting pipeline faces to the top of the tunnel segment, and the opening of the second port of the ground grouting pipeline forms a grouting hole at the top of the anti-floating plate.
The longitudinal beams are reinforced concrete beams arranged along the length direction of the tunnel, play a role in transverse connection and load transmission in the portal anti-floating structure, are connected with pile tops of the pedestal piles and form an integral frame with the upper anti-floating plate.
The door-type anti-floating structure is an integral stress system consisting of an anti-floating plate, a longitudinal beam and a club-footed pile, is shaped like a door-type structure, and can effectively resist buoyancy on a tunnel for a long time.
The bottom of the longitudinal beam is fixedly connected with the pile top of the club-footed pile, the top of the longitudinal beam is fixedly connected with the bottom surface of the anti-floating plate, so that the club-footed pile, the longitudinal beam and the anti-floating plate form a stressed integrated portal frame, a ground grouting pipeline penetrates through the anti-floating plate, and a plurality of rows of grouting holes are preset at the top of the anti-floating plate.
The anti-floating plates are horizontally covered on the top of the reinforced soil body and the club-footed pile, the horizontal projection range of the anti-floating plates exceeds the left side and the right side of the tunnel design contour line, the multiple rows of grouting holes are distributed at intervals along the length direction of the tunnel, and the horizontal distribution range of each row of grouting holes covers the top projection area of the tunnel segment.
The pre-buried ground grouting pipeline refers to a grouting pipeline system which is pre-installed and fixed in the anti-floating plate before pouring the anti-floating plate concrete and is used for grouting operation through the ground in the later period.
The grouting holes are the openings of the grouting pipeline and are divided into two types, one type is an injection hole positioned at the top of the anti-floating plate, and the other type is a grouting hole positioned at the bottom of the anti-floating plate and facing the tunnel segment.
The reinforcing steel bar net is an encrypted reinforcing steel bar net sheet arranged around the grouting holes and is used for enhancing the local compressive strength of concrete and preventing cracking.
The embedded bars are the bars which extend from the pile tops of the club-footed piles in advance and are used for being connected with the bars at the bottoms of the longitudinal beams, so that the reliable force transmission between the piles and the beams is ensured.
The pouring into a whole means that the longitudinal beam and the anti-floating plate adopt a construction mode of integral continuous pouring, so that the longitudinal beam and the anti-floating plate form a seamless connection reinforced concrete whole.
The top of the tunnel segment is the outer surface of the upper half part of the prefabricated segment ring of the shield tunnel, and is a target area which needs to be filled by grouting.
The direction vertical to the anti-floating plate is an arrangement mode that the grouting pipeline vertically passes through the thickness direction of the anti-floating plate, namely, the pipeline and the plane of the anti-floating plate form an angle of 90 degrees.
Illustratively, after the construction of the pedestal pile is completed, the upper construction stage of the portal anti-floating structure is entered. Firstly, constructing a longitudinal beam along the length direction of a tunnel, firmly connecting the bottom of the longitudinal beam with the pile top of a pedestal pile through embedded bars to form a reliable vertical force transmission node, and then, integrally casting an anti-floating plate at the top of the longitudinal beam to form a seamless connection reinforced concrete whole of the longitudinal beam and the anti-floating plate, thereby forming a complete 'door' -shaped anti-floating structure system.
Meanwhile, in the process of carrying out anti-floating plate construction, the ground grouting pipeline is synchronously embedded. The ground grouting pipeline consists of a plurality of grouting pipes which vertically penetrate through the anti-floating plate, wherein a first port (a lower end opening) of each grouting pipe faces to a grouting space reserved at the top of a tunnel segment, a second port (an upper end opening) of each grouting pipe forms a grouting hole at the top of the anti-floating plate, reinforcing steel bar meshes are arranged at the periphery of an orifice in order to enhance the local bearing capacity of concrete around the grouting holes, and a direct channel is provided for implementing ground grouting after a follow-up shield passes through the embedded ground grouting pipeline, so that filling and reinforcement of a gap at the top of the tunnel can be completed through the ground without the need of the tunnel from the inside, and the accurate control of ground embedding and ground grouting is realized.
S204, injecting slurry into the periphery of the tunnel segment in the process that the shield is pushed to the target construction section along the tunnel design axis.
The slurry is double slurry, and is formed by mixing cement slurry and water glass based on a preset proportion.
The tunnel segment is an annular supporting structure formed by splicing the inner sides of tunnel excavation outlines in the shield pushing process, the outer ring surface of the tunnel segment is attached to the soil body reinforced by the triaxial mixing piles, and a preset gap is reserved between the top of the tunnel segment and the bottom surface of the anti-floating plate.
Optionally, before grouting the slurry into the gap between the anti-floating plate and the tunnel segment through the ground grouting pipeline, the grouting device further comprises:
and determining the grouting sequence and single grouting amount of the grouting liquid based on the gap position and the volume between the anti-floating plate and the tunnel segment.
After grouting liquid is pressed to the clearance between the anti-floating plate and the tunnel segment through the ground grouting pipeline, the grouting device further comprises:
And verifying the gap filling effect, and performing secondary grouting through a ground grouting pipeline under the condition that an unfilled and filled region exists.
The shield is a large-scale machine for tunnel construction, soil is cut through a cutter disc at the front end, and prefabricated segments are assembled at the rear part to form tunnel lining construction equipment.
The target construction section refers to a specific tunnel section in which shield tunneling is being performed, and generally corresponds to a section in which portal anti-floating structure construction and ground pretreatment have been completed.
The periphery of the tunnel segment refers to an annular gap formed between the outer surface of the prefabricated reinforced concrete segment and surrounding soil after the prefabricated reinforced concrete segment is installed.
The double-liquid slurry is a grouting material formed by mixing two liquids (usually cement slurry and water glass) with different components according to a certain proportion, and is characterized by being capable of being quickly solidified after mixing, and playing a role in timely filling and reinforcing.
The cement slurry is formed by mixing cement and water according to a certain proportion, and is a basic component of grouting materials.
The water glass is aqueous solution of sodium silicate, is used as a coagulant of double-liquid slurry, and can obviously accelerate the setting time after being mixed with cement slurry.
The preset proportion is the mixing proportion of cement paste and water glass preset according to engineering requirements and geological conditions, and can be determined through experiments.
The gap between the anti-floating plate and the tunnel segment is a space which possibly exists between the top of the tunnel segment and the bottom surface of the upper anti-floating plate after the tunnel segment is assembled, and is a main filling area for ground grouting.
The grouting sequence is a sequence of grouting operation on a plurality of grouting holes, and is usually carried out from one end to the other end or from the middle to the two ends.
The single grouting amount is the volume of the slurry injected through one grouting hole at a time, and needs to be reasonably controlled according to the gap volume and the grouting pressure.
The gap filling effect verification is to check whether the gap is completely filled with the slurry through methods such as geophysical prospecting (such as geological radar) or drilling sampling after grouting is completed.
Unfilled filled areas are void or non-dense areas that remain after grouting, often requiring additional grouting.
The secondary grouting is performed for the unfilled and filled area after the primary grouting is completed, so as to ensure that the gap is completely compact.
By way of example, in the process of pushing the shield along the tunnel design axis, double slurry is synchronously injected into the annular gap around the tunnel segment, and the slurry is formed by mixing cement slurry and water glass according to a preset proportion, so that the soil around the tunnel can be quickly solidified, and the floating and later sedimentation of the tunnel are restrained.
After the shield passes through, before top grouting is performed by utilizing the pre-buried ground grouting pipeline, a reasonable grouting sequence (such as grouting from one end to the other end or from interval jump holes) is formulated according to the position distribution and total volume of gaps between the anti-floating plate and the tunnel pipe pieces, and single grouting amount of each grouting hole is determined, so that uniform and efficient filling is realized.
After the primary grouting is finished, the gap filling effect is verified (such as geological radar scanning is adopted), if the unfilled and full area is found, secondary supplementary grouting is carried out through a ground grouting pipeline until the gap is completely filled and compacted by the slurry, soil loosening and cavity hidden danger are thoroughly eliminated, and long-term stability of the tunnel structure is ensured.
S205, under the condition that the shield passes through the target construction section, grouting liquid is injected into a gap between the anti-floating plate and the tunnel segment through a ground grouting pipeline, so that tunnel construction is completed.
The shield passing through the target construction section means that the shield tunneling machine has completed propelling construction in a specific tunnel section, segment assembly is completed, and the section has the condition of subsequent treatment.
The grouting liquid is injected into the target gap through the grouting pipeline by grouting equipment at a certain pressure, so that the grouting liquid is fully filled and permeated into the soil gap.
The tunnel construction refers to the whole process from excavation, support to final structure formation of tunnel engineering, and comprises the working of shield tunneling, segment assembly, grouting reinforcement, anti-floating structure construction and other stages.
By way of example, when the shield tunneling machine completes tunneling in the target construction section and the tunnel segment is assembled in place, grouting pipelines on the ground, which are buried in the anti-floating plate in advance, are utilized to inject slurry (such as superfine cement slurry) with specific proportion into the gap between the anti-floating plate and the top of the tunnel segment, the gap is fully filled with the slurry through pressure and the slurry permeates into surrounding soil, and through grouting filling, not only the hidden trouble of the gap between structures can be eliminated, but also the soil can be effectively compacted, the stability of the whole structure is enhanced, long-term safe use of the tunnel under the ultra-shallow earthing condition is ensured, and the final completion of the tunnel construction of the segment is marked.
Based on the above, the construction method for accurately controlling the settlement of the ultra-shallow soil super-large diameter shield tunnel is characterized in that water-stop curtains are constructed along two sides of a tunnel design axis, and under-reaping piles distributed at intervals are constructed in the water-stop curtains on each side, an effective groundwater blocking system and a reliable anti-floating foundation are established, soil mass is integrally reinforced based on triaxial stirring piles in a central area of the tunnel surrounded by the water-stop curtains, the stability and uniformity of stratum in the tunneling process of the shield are improved, longitudinal beams and anti-floating plates are constructed after the construction of the under-reaping piles are completed, a gate anti-floating structure is formed, and under the condition of the construction of the anti-floating plates, ground grouting pipelines are synchronously embedded in the anti-floating plates, a synergistic permanent anti-floating system is formed, an innovative process of ground pre-burying and ground grouting is realized, slurry is injected into the periphery of a target construction section of the tunnel in time, the tail clearance of the tunnel is filled in the process of advancing the shield along the tunnel design axis, the floating of the tunnel and the settlement of the stratum is restrained, under the condition that the shield passes through the target construction section of the tunnel, the ground grouting pipelines are used for grouting the ground grouting pipelines between the anti-floating plates and the pipe, the floating structure is completely eliminated, and the hidden trouble of the structure is eliminated. The whole construction method forms a systematic sedimentation control system and realizes the cooperative control of anti-floating and sedimentation of the tunnel structure.
The descriptions of the processes or structures corresponding to the drawings have emphasis, and the descriptions of other processes or structures may be referred to for the parts of a certain process or structure that are not described in detail.
The foregoing is merely illustrative of specific embodiments of the present application, and the scope of the present application is not limited thereto, but any changes or substitutions within the technical scope of the present application should be covered by the scope of the present application.