CN121138961A - Multifunctional integrated anchor cable construction equipment and construction methods - Google Patents

Multifunctional integrated anchor cable construction equipment and construction methods

Info

Publication number
CN121138961A
CN121138961A CN202511546520.7A CN202511546520A CN121138961A CN 121138961 A CN121138961 A CN 121138961A CN 202511546520 A CN202511546520 A CN 202511546520A CN 121138961 A CN121138961 A CN 121138961A
Authority
CN
China
Prior art keywords
anchor cable
arm
drill
assembly
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202511546520.7A
Other languages
Chinese (zh)
Inventor
张海涛
徐涛
张文涛
刘建亮
欧阳新池
张延辉
宋效凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Heavy Industry Group Co Ltd
China Railway Construction Corp Ltd CRCC
Original Assignee
China Railway Construction Heavy Industry Group Co Ltd
China Railway Construction Corp Ltd CRCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Heavy Industry Group Co Ltd, China Railway Construction Corp Ltd CRCC filed Critical China Railway Construction Heavy Industry Group Co Ltd
Priority to CN202511546520.7A priority Critical patent/CN121138961A/en
Publication of CN121138961A publication Critical patent/CN121138961A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明涉及隧道施工技术领域,尤其公开一种多功能集成的锚索施工设备及施工方法。多功能集成的锚索施工设备中,折叠式钻臂总成用于在隧洞内进行钻孔施工;折叠式锚索臂总成包括工作臂机构、送索机构和送药机构,工作臂机构能够沿水平面做回转运动和沿竖直面做俯仰运动,送索机构设置于工作臂机构远离履带式底盘的一端,送索机构用于将锚索输送至钻孔内,送药机构用于将锚固剂输送至钻孔内;注浆总成用于将砂浆注入至钻孔内。本发明通过一台设备便可实现隧洞内钻孔、锚固、注浆功能的集成,可以在空间有限的隧洞内高效施工,减少人力物力,降低安全隐患,降低了作业人员的劳动强度,有效地提高了施工效率。

This invention relates to the field of tunnel construction technology, and in particular discloses a multifunctional integrated anchor cable construction equipment and method. The multifunctional integrated anchor cable construction equipment includes a folding drill arm assembly for drilling operations within a tunnel. The folding anchor cable arm assembly comprises a working arm mechanism, a cable feeding mechanism, and a grouting mechanism. The working arm mechanism is capable of rotation in the horizontal plane and pitching in the vertical plane. The cable feeding mechanism is located at the end of the working arm mechanism furthest from the tracked chassis and is used to deliver the anchor cable into the borehole. The grouting mechanism is used to deliver the anchoring agent into the borehole. A grouting assembly is used to inject grout into the borehole. This invention integrates drilling, anchoring, and grouting functions within a tunnel using a single device, enabling efficient construction in tunnels with limited space, reducing manpower and material resources, minimizing safety hazards, reducing the labor intensity of workers, and effectively improving construction efficiency.

Description

Multifunctional integrated anchor cable construction equipment and construction method
Technical Field
The invention relates to the technical field of tunnel construction, in particular to multifunctional integrated anchor cable construction equipment and a construction method.
Background
The anchor cable trolley is key equipment for drilling, grouting and anchor cable installation in tunnel construction, and the performance of the anchor cable trolley directly influences the construction efficiency and quality. Along with the development of tunnel engineering to deep and complex geological conditions, higher requirements are put forward on the integration, automation and adaptability of the anchor cable trolley.
At present, the anchor cable support is used in the fields of foundation pits, side slopes, bridges, coal mines and the like, the construction mode adopts a traditional simple drilling machine to drill holes, the other steps of cable feeding, tensioning and the like are manually completed, the anchor cable is manually installed, and the defects of long construction period, high potential safety hazard, high labor intensity, low efficiency and the like exist. With the development of society, mechanical tunnel construction instead of manual work will be a necessary trend of future development.
However, in the application process, when drilling, anchor cable and grouting are performed, the drill jumbo and the anchor cable jumbo are matched with each other to realize the whole-process construction, and the problems of low efficiency and the like are solved. These problems limit the further development of drilling, anchoring and injection machines.
Therefore, it is necessary to provide a new multifunctional integrated anchor line construction equipment to solve the above technical problems.
Disclosure of Invention
The invention mainly aims to provide multifunctional integrated anchor cable construction equipment and a construction method, and aims to solve the problem of low construction efficiency of an existing anchor cable trolley.
The multifunctional integrated anchor cable construction equipment is characterized by comprising a crawler-type chassis, a foldable drill arm assembly, a foldable anchor cable arm assembly and a grouting assembly, wherein the crawler-type chassis can walk along the ground, the foldable drill arm assembly is arranged on the crawler-type chassis and is used for drilling construction in a tunnel, the foldable anchor cable arm assembly comprises a working arm mechanism, a cable conveying mechanism and a drug conveying mechanism, the working arm mechanism is arranged on the crawler-type chassis, the working arm mechanism can perform rotary motion along a horizontal plane and pitching motion along a vertical plane, the cable conveying mechanism is arranged at one end, far away from the crawler-type chassis, of the working arm mechanism, the cable conveying mechanism is used for conveying anchor cables into a drilling hole, the drug conveying mechanism is arranged on the cable conveying mechanism and is used for conveying anchoring agents into the drilling hole, the grouting assembly is arranged on the crawler-type chassis, and the grouting assembly is used for injecting mortar into the drilling hole.
The working arm mechanism comprises a working arm rotary table, a first working arm, a first telescopic arm, an L-shaped rotary seat, a hanging basket, a first lifting piece and a second lifting piece, wherein the working arm rotary table is arranged on the crawler-type chassis and can rotate around a vertical shaft, the first working arm is hinged between the working arm rotary table and the first telescopic arm, the first end of the first telescopic arm is hinged with the first working arm, the second end of the first telescopic arm is hinged with the L-shaped rotary seat, the first telescopic arm can stretch in the length direction, the L-shaped rotary seat can rotate around the axial direction of the first telescopic arm, the hanging basket is arranged on the L-shaped rotary seat, the first lifting piece is hinged between the working arm rotary table and the first working arm, the first lifting piece can drive the first working arm to do pitching motion along a vertical plane, and the second lifting piece is hinged between the first working arm and the first telescopic arm can drive the first lifting piece to do pitching motion along the vertical plane.
Optionally, the cable feeding mechanism comprises an anchor cable arm guide rail, a hydraulic shear, a first power head and two anchor cable conveying wheels, wherein the anchor cable arm guide rail is arranged on the L-shaped rotary seat, the hydraulic shear is arranged on the anchor cable arm guide rail and is used for shearing an anchor cable, the first power head is arranged on the anchor cable arm guide rail in a sliding manner, the first power head can clamp the anchor cable and drive the anchor cable to move along the anchor cable arm guide rail or rotate along the axis direction of the anchor cable, the two anchor cable conveying wheels are arranged on the anchor cable arm guide rail at intervals, the anchor cable sequentially extends to the first power head through the two anchor cable conveying wheels, and the anchor cable conveying wheels are used for conveying the anchor cable
Optionally, the medicine delivery mechanism comprises a rotating assembly, a medicine delivery pipe and an air compressor, wherein the rotating assembly is arranged at one end of the anchor cable arm guide rail, which is far away from the first telescopic arm, the medicine delivery pipe is connected with the output end of the rotating assembly, the rotating assembly can drive the medicine delivery pipe to rotate between a butting position and an avoiding position, the medicine delivery pipe is used for delivering anchoring agent, the air compressor is communicated with the medicine delivery pipe, and the air compressor can blow the anchoring agent in the medicine delivery pipe into a drill hole.
Optionally, the folding anchor cable arm assembly further comprises a tee structure, a jacking pipe and two jacking pipe conveying wheels, wherein the tee structure is provided with an output end and two input ends, the output end is connected with the input end of the first power head, one input end is used for an anchor cable to pass through, the other input end is used for the jacking pipe to pass through, the two jacking pipe conveying wheels are arranged on the anchor cable arm guide rail at intervals, the jacking pipe conveying wheels and the anchor cable conveying wheels are arranged in a vertically staggered mode, the jacking pipe sequentially passes through the two jacking pipe conveying wheels and extends into the input end, and the jacking pipe conveying wheels can drive the jacking pipe to pass through the first power head and extend into a drilling hole so as to push an anchoring piece into the bottom of the drilling hole.
Optionally, the folding anchor rope assembly still includes fine setting mechanism, fine setting mechanism includes lateral shifting subassembly, vertical movement subassembly and mechanical tongs, the lateral shifting subassembly set up in the anchor rope arm guide rail is kept away from the one end of first flexible arm, vertical movement subassembly set up in on the lateral shifting subassembly, lateral shifting mechanism can drive vertical movement subassembly moves along the horizontal direction of perpendicular to drilling axis, mechanical tongs set up in on the vertical movement subassembly, vertical movement subassembly can drive mechanical tongs moves along vertical direction, mechanical tongs are used for pressing from both sides tight anchor rope.
The foldable drill boom assembly comprises a drill boom mechanism, a propelling beam base and a propelling rod adding mechanism, wherein the drill boom mechanism is arranged on the crawler-type chassis and can perform rotary motion along a horizontal plane and pitching motion along a vertical plane, the propelling beam base is hinged with one end, far away from the crawler-type chassis, of the drill boom mechanism, the propelling rod adding mechanism is arranged on the propelling beam base and is used for performing drilling construction in a tunnel.
The drill arm mechanism comprises a drill arm rotary table, a second working arm, a second telescopic arm, a third lifting piece and a fourth lifting piece, wherein the drill arm rotary table is arranged on the crawler chassis, the second working arm rotary table can rotate around a vertical shaft, the second working arm is hinged between the drill arm rotary table and the second telescopic arm, the first end of the second telescopic arm is hinged with the second working arm, the second end of the second telescopic arm is connected with the pushing beam base, the second telescopic arm can stretch along the length direction, the third lifting piece is hinged between the drill arm rotary table and the second working arm, the third lifting piece can drive the second working arm to do pitching motion along a vertical plane, the fourth lifting piece is hinged between the second working arm and the second telescopic arm, and the fourth lifting piece can drive the second telescopic arm to do pitching motion along the vertical plane.
The pushing and rod adding mechanism comprises a drill boom guide rail, a drill clamping device, a second power head, a center oil cylinder and a rod adding assembly, wherein the drill boom guide rail is arranged on the pushing beam base, the drill clamping device is arranged at one end, close to a drill hole, of the drill boom guide rail and used for supporting a drill rod, the second power head is arranged on the drill boom guide rail in a sliding mode, the output end of the second power head is connected with the drill rod and used for providing impact force for the drill rod, the center oil cylinder is arranged on the drill boom guide rail, the output end of the center oil cylinder is formed into a conical portion used for being abutted with the surface of a tunnel, the center oil cylinder can be lengthened or shortened to be close to or far away from the surface of the tunnel, and the rod adding assembly is used for replacing the drill rod.
Optionally, the grouting assembly comprises a stirrer, a grouting pump and a grouting pipeline, wherein the stirrer is used for stirring the slurry, the grouting pump is connected between the stirrer and the grouting pipeline, and the grouting pump can convey the slurry in the stirrer into a drilling hole through the grouting pipeline.
Optionally, the multifunctional integrated anchor cable construction equipment further comprises an anchor cable reel, a rotary driving piece and a turnover driving piece, wherein the bottom of the anchor cable reel is rotatably connected with the crawler-type chassis through a pin shaft, the anchor cable reel is provided with an anchor cable reel which is rotatably arranged on the anchor cable reel, the rotary driving piece is arranged on the crawler-type chassis and is connected with a central shaft of the anchor cable reel, the rotary driving piece can drive the anchor cable reel to rotate so as to convey the anchor cable, the turnover driving piece is hinged between the anchor cable reel and the crawler-type chassis, and the turnover driving piece can drive the anchor cable reel to move between a horizontal position and a vertical position.
In addition, the invention also provides a construction method of the multifunctional integrated anchor cable construction equipment, which adopts the multifunctional integrated anchor cable construction equipment as set forth in any one of claims 1 to 10 to carry out construction, and is characterized by comprising the following steps of
S1, excavating in a tunnel by adopting a three-step method to form an upper step, a middle step and a lower step;
S2, advancing the multifunctional integrated anchor cable construction equipment to a middle step;
S3, controlling multifunctional integrated anchor cable construction equipment to carry out drilling construction and anchor cable construction on the surface of the tunnel;
S4, installing steel belts, backing plates and anchorage devices, and tensioning anchor cables;
s5, grouting the inside of the drilled hole by adopting a grouting assembly.
Optionally, the S3 includes:
S3.1, drilling construction is carried out on the surface of a right tunnel of the centering step by adopting a folding drill boom assembly;
s3.2, adopting a folding drill arm assembly to sequentially drill the top tunnel surface of the upper step and the right tunnel surface of the upper step;
S3.3, drilling construction is carried out on the left side tunnel surface of the upper step by adopting a folding drill boom assembly, and simultaneously, anchor rope construction is carried out on the top and the right side tunnel surface of the upper step in sequence by adopting a folding anchor rope boom assembly;
S3.4, drilling construction is carried out on the left side tunnel surface of the centering step by adopting a folding drill boom assembly, and meanwhile, anchor rope construction is carried out on the left side tunnel surface of the upper step by adopting a folding anchor rope boom assembly;
S3.5, drilling construction is carried out on the left side and the right side tunnel surfaces of the lower step by adopting a folding drill boom assembly, and meanwhile, anchor rope construction is carried out on the left side of the centering step by adopting a folding anchor rope boom assembly;
s3.6, carrying out anchor rope construction on the left side tunnel surface and the right side tunnel surface of the lower step by adopting a folding anchor rope arm assembly;
s3.7, carrying out anchor rope construction on the surface of the tunnel at the top of the lower step by adopting a folding anchor rope arm assembly.
According to the technical scheme, the folding drill boom assembly can finish drilling construction in a tunnel, the folding anchor cable boom can convey the anchor cable and the anchoring agent into the drilling through the cable conveying mechanism and the drug conveying mechanism respectively under the cooperation of the working boom mechanism, and mortar is injected into the drilling through the grouting assembly, so that the integration of drilling, anchoring and grouting functions in the tunnel can be realized through only one device, efficient construction in the tunnel with limited space can be realized, manpower and material resources are reduced, potential safety hazard is reduced, labor intensity of operators is reduced, and construction efficiency is effectively improved.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings that are required in the embodiments or the description of the prior art will be briefly described, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and other drawings may be obtained according to the structures shown in these drawings without inventive effort for a person skilled in the art.
Fig. 1 is a schematic structural view of a multifunctional integrated anchor line construction apparatus according to an embodiment of the present invention;
Fig. 2 is a schematic structural view of a folding anchor arm assembly according to an embodiment of the present invention;
FIG. 3 is a schematic view of a drug delivery mechanism in a docked position according to an embodiment of the present invention;
FIG. 4 is a schematic diagram of a drug delivery mechanism in an avoidance position according to an embodiment of the present invention;
FIG. 5 is a schematic view of a folding boom assembly according to an embodiment of the present invention;
fig. 6 is a schematic structural view of the multifunctional integrated anchor line construction equipment in a folded state according to an embodiment of the present invention;
FIG. 7 is a schematic illustration of the construction of an anchor rope reel in accordance with an embodiment of the present invention when the anchor rope reel is replaced;
FIG. 8 is a schematic view of the crawler chassis in an embodiment of the present invention;
Fig. 9 is a construction schematic diagram of a multifunctional integrated anchor line construction apparatus in an embodiment of the present invention.
Reference numerals illustrate:
1. Crawler chassis, 1.1, fuel tank, 1.2, hydraulic radiator, 1.3, landing leg, 1.4, cab, 1.5, water pump, 1.6, air compressor, 1.7, tool cabinet, 1.8, hydraulic oil tank, 1.9, electric cabinet, 1.10, anchor cable arm base, 1.11, boom base, 2, folding boom assembly, 2.1, boom mechanism, 2.1.1, boom swivel, 2.1.2, second working arm, 2.1.3, second telescopic arm, 2.1.4, third lifting member, 2.1.5, fourth lifting member, 2.2, pushing beam base, 2.3, pushing beam adding mechanism, 2.3.1, boom guide, 2.3.2, drill boom holder, 2.3.3, second power head, 2.3.4, oil cylinder, 2.3.5, a rod adding assembly, 3, a folding anchor cable arm assembly, 3.1, a working arm mechanism, 3.1.1, a working arm rotary table, 3.1.2, a first working arm, 3.1.3, a first telescopic arm, 3.1.4, an L-shaped rotary seat, 3.1.5, a hanging basket, 3.1.6, a first lifting piece, 3.1.7, a second lifting piece, 3.2, a cable feeding mechanism, 3.2.1, an anchor cable arm guide rail, 3.2.2, a hydraulic shear, 3.2.3, a first power head, 3.2.4, an anchor cable conveying wheel, 3.3, a drug feeding mechanism, 3.3.1, a rotary assembly, 3.3.2, a drug feeding pipe, 3.4, a tee joint structure, 3.5, a drug conveying wheel, a 3.6, a fine tuning mechanism, 4, a grouting assembly, 5, a reel, 6 and a power mechanism.
The achievement of the objects, functional features and advantages of the present invention will be further described with reference to the accompanying drawings, in conjunction with the embodiments.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and fully with reference to the accompanying drawings, in which it is evident that the embodiments described are only some, but not all embodiments of the invention. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
It should be noted that all directional indicators (such as up, down, left, right, front, and rear are used in the embodiments of the present invention) are merely for explaining the relative positional relationship, movement conditions, and the like between the components in a certain specific posture (as shown in the drawings), and if the specific posture is changed, the directional indicators are changed accordingly.
Furthermore, descriptions such as those referred to as "first," "second," and the like, are provided for descriptive purposes only and are not to be construed as indicating or implying a relative importance or implying an order of magnitude of the indicated technical features in the present disclosure. Thus, a feature defining "a first" or "a second" may explicitly or implicitly include at least one such feature. In the description of the present invention, the meaning of "plurality" means at least two, for example, two, three, etc., unless specifically defined otherwise.
In the present invention, unless explicitly specified and limited otherwise, the terms "connected," "fixed," and the like are to be construed broadly, and for example, "fixed" may be fixedly connected, detachably connected, or integrally formed, mechanically connected, electrically connected, directly connected, indirectly connected via an intervening medium, or in communication between two elements or in an interaction relationship between two elements, unless otherwise explicitly specified. The specific meaning of the above terms in the present invention can be understood by those of ordinary skill in the art according to the specific circumstances.
In addition, the technical solutions of the embodiments of the present invention may be combined with each other, but it is necessary to be based on the fact that those skilled in the art can implement the technical solutions, and when the technical solutions are contradictory or cannot be implemented, the combination of the technical solutions should be considered as not existing, and not falling within the scope of protection claimed by the present invention.
The invention provides multifunctional integrated anchor cable construction equipment and a construction method, and aims to solve the problem of low construction efficiency of an existing anchor cable trolley.
Example 1
Referring to fig. 1 to 4, the multifunctional integrated anchor cable construction equipment comprises a crawler chassis 1, a folding drill boom assembly 2, a folding anchor cable arm assembly 3 and a grouting assembly 4, wherein the crawler chassis 1 can walk along the ground, the folding drill boom assembly 2 is arranged on the crawler chassis 1 and is used for drilling construction in a tunnel, the folding anchor cable arm assembly 3 comprises a working arm mechanism 3.1, a cable conveying mechanism 3.2 and a drug conveying mechanism 3.3, the working arm mechanism 3.1 is arranged on the crawler chassis 1, the working arm mechanism 3.1 can perform rotary motion along the horizontal plane and perform pitching motion along the vertical plane, the cable conveying mechanism 3.2 is arranged at one end, far away from the crawler chassis 1, of the working arm mechanism 3.1, the cable conveying mechanism 3.2 is used for conveying anchor cables into a borehole, the drug conveying mechanism 3.3 is arranged on the cable conveying mechanism 3.2, the drug conveying mechanism 3.3 is used for conveying anchoring agents into the borehole, the grouting assembly 4 is arranged on the crawler chassis 1 and the grouting assembly 4 is used for injecting mortar into the borehole. In this embodiment, the drilling construction in the tunnel can be accomplished to foldable boom assembly 2, and folding anchor rope arm can be respectively through sending rope mechanism 3.2 and sending medicine mechanism 3.3 to the drilling under the cooperation of work arm mechanism 3.1 in, the rethread slip casting assembly 4 is with the mortar injection to the drilling in, thereby just can realize the integration of drilling in the tunnel through an equipment, anchor, slip casting function, can be in the limited efficient construction in tunnel of space, reduce manpower and materials, reduce the potential safety hazard, reduced operating personnel's intensity of labour, improved the efficiency of construction effectively. The multifunctional integrated anchor cable construction equipment is suitable for excavating tunnels by a three-step method, is used for constructing a whole vehicle from a middle step, follows the principle of going up and down, going on two sides and going in the middle, and can effectively control stratum displacement.
The working arm mechanism 3.1 comprises a working arm revolving platform 3.1.1, a first working arm 3.1.2, a first telescopic arm 3.1.3, an L-shaped revolving seat 3.1.4, a hanging basket 3.1.5, a first lifting piece 3.1.6 and a second lifting piece 3.1.7, wherein the working arm revolving platform 3.1.1 is arranged on the crawler chassis 1, the working arm revolving platform 3.1.1 can rotate around a vertical shaft, the first working arm 3.1.2 is hinged between the working arm revolving platform 3.1.1.1 and the first telescopic arm 3.1.3, a first end of the first telescopic arm 3.1.3 is hinged with the first working arm 3.1.2, a second end of the first telescopic arm 3.1.3 is hinged with the L-shaped revolving seat 3.1.4, the first telescopic arm 3.1.3 can be telescopic in a length direction, the L-shaped revolving seat 3.1.4 can rotate around the axis direction of the first telescopic arm 3.1.3, the hanging basket 3.1.1.2 is arranged on the first lifting piece 3.1.1.5, the first lifting piece 3.1.1.1 can be hinged with the first lifting piece 3.1.1.3, and the first lifting piece 3.1.1.3 can be driven to move vertically, and the first lifting piece 3.1.1.1.3.1.3 can be hinged with the first lifting piece 3.1.1.1.4, and the second lifting piece can be hinged with the first lifting piece 3.1.1.1.1.3.1.3.3, and the second lifting piece can be driven vertically, the first lifting piece 1.1.1.1.1.3.3, the first lifting piece can be hinged with the first lifting piece 1.1.1.1.5 can and the first lifting piece can and the first lifting piece 3.5 can be.
In the embodiment, a folding anchor cable arm assembly 3 is arranged at the left front end of the crawler chassis 1 and is used for carrying out operations such as cable feeding, grouting, anchor cable tensioning and the like in a tunnel. The anchor cable arm base 1.10 is arranged on the right front side of the crawler chassis 1, the anchor cable arm rotary table is connected with the anchor cable arm base 1.10 and can rotate around the shaft on the anchor cable arm base 1.10, the rotation of the folding anchor cable arm assembly 3 can be realized through the anchor cable arm rotary table, and the construction requirements of multiple angles and multiple working conditions can be realized in the tunnel. Preferably, the first working arm 3.1.2 is connected to the anchor rope arm revolving platform through a pin shaft, and the first lifting oil cylinder is connected to the front end of the first working arm 3.1.2 and the anchor rope arm revolving platform. The lifting and falling procedures of the first working arm 3.1.2 are completed through the extension and retraction of the first lifting oil cylinder, the front end of the first working arm 3.1.2 is connected with the first telescopic arm 3.1.3 through a pin shaft, and the second lifting oil cylinder is connected with the front end of the first telescopic arm 3.1.3 and the front end of the first working arm 3.1.2. The lifting and falling procedures of the first telescopic arm 3.1.3 are completed through the extension and retraction of the second lifting oil cylinder, preferably, the first telescopic arm 3.1.3 has a front-back telescopic function so as to move the cable conveying mechanism 3.2 to the vicinity of an operation hole, the operation range is enlarged, the hanging basket 3.1.5 assembly is connected with the front end of the first telescopic arm 3.1.3 through a rotating device, an operator can complete corresponding operation contents in the hanging basket 3.1.5 assembly, and the cable conveying mechanism 3.2 is connected to the left side of the hanging basket 3.1.5 assembly through the rotating device.
The cable conveying mechanism 3.2 comprises an anchor cable arm guide rail 3.2.1, a hydraulic shear 3.2.2, a first power head 3.2.3 and two anchor cable conveying wheels 3.2.4, wherein the anchor cable arm guide rail 3.2.1 is arranged on the L-shaped rotary seat 3.1.4, the hydraulic shear 3.2.2 is arranged on the anchor cable arm guide rail 3.2.1 and is used for cutting off an anchor cable, the first power head 3.2.3 is arranged on the anchor cable arm guide rail 3.2.1 in a sliding manner, the first power head 3.2.3 can clamp the anchor cable and drive the anchor cable to move along the anchor cable arm guide rail 3.2.1 or rotate along the axis direction of the anchor cable, the two anchor cable conveying wheels 3.2.4 are arranged on the anchor cable arm guide rail 3.2.1 at intervals, the anchor cable sequentially extends to the first power head 3.2.3 through the two anchor cable conveying wheels 3.2.4, and the anchor cable conveying wheels 3.2.4 are used for conveying the anchor cable. The first power head 3.2.3 is arranged on the anchor cable arm guide rail 3.2.1, the first power head 3.2.3 can slide back and forth along the anchor cable arm guide rail 3.2.1 to push an anchor cable into a hole, and the hydraulic shear 3.2.2 and the anchor cable conveying wheel 3.2.4 are fixed on a base at the rear side of the anchor cable arm guide rail 3.2.1. During the construction of the anchor cable, the anchor cable is respectively abutted against the two anchor cable conveying wheels 3.2.4, the pushing of the anchor cable is realized under the action of friction force of the anchor cable conveying wheels 3.2.4, the first power head 3.2.3 moves forwards along the anchor cable arm guide rail 3.2.1, the first power head 3.2.3 resets after the anchor cable enters the hole, the hydraulic shear 3.2.2 shears the anchor cable after the anchor cable enters the hole for a corresponding length, the first power head 3.2.3 clamps the anchor cable and rotates, and the oil cylinder controls the first power head 3.2.3 to advance, so that anchoring agents in a drilled hole are stirred, the anchoring effect is guaranteed, and the construction quality is improved.
Further, the medicine feeding mechanism 3.3 comprises a rotating assembly 3.3.1, a medicine feeding pipe 3.3.2 and an air compressor 1.6, the rotating assembly 3.3.1 is arranged at one end of the anchor rope arm guide rail 3.2.1, which is far away from the first telescopic arm 3.1.3, the medicine feeding pipe 3.3.2 is connected with the output end of the rotating assembly 3.3.1, the rotating assembly 3.3.1 can drive the medicine feeding pipe 3.3.2 to rotate between a butt joint position and an avoidance position, the medicine feeding pipe 3.3.2 is used for conveying anchoring agent, the air compressor 1.6 is communicated with the medicine feeding pipe 3.3.2, and the air compressor 1.6 can blow the anchoring agent in the medicine feeding pipe 3.3.2 into a drill hole. In the embodiment, the rotating assembly 3.3.1 is arranged at the left side of the front end of the anchor cable arm guide rail 3.2.1, the anchoring agent is a resin anchoring agent, the drug delivery mechanism 3.3 is fixed at the left front end of the anchor cable arm guide rail 3.2.1 and is used for delivering the anchoring agent into a hole, and the air compressor 1.6 is used for providing proper air pressure for the drug delivery tube 3.3.2 to blow the anchoring agent into the hole bottom, and the rotating assembly 3.3.1 is used for rotating the drug delivery tube 3.3.2 to an avoiding position after the injection of the anchoring agent is completed so as to avoid interference with subsequent anchor cable construction.
Still further, folding anchor rope assembly still includes fine-tuning 3.6, fine-tuning 3.6 includes transverse movement subassembly, vertical movement subassembly and mechanical tongs, transverse movement subassembly sets up in anchor rope arm guide rail 3.2.1 keeps away from the one end of first flexible arm 3.1.3, vertical movement subassembly sets up on transverse movement subassembly, transverse movement mechanism can drive vertical movement subassembly and remove along the horizontal direction of perpendicular to drilling axis, mechanical tongs sets up on vertical movement subassembly, vertical movement subassembly can drive mechanical tongs and remove along vertical direction, mechanical tongs are used for pressing from both sides tight anchor rope. In this embodiment, transverse movement subassembly sets up in anchor rope arm guide rail 3.2.1 front end right side, and the anchor rope can be accurate hand-hole under fine setting mechanism 3.6's control action, specifically snatchs the anchor rope through the mechanical tongs, and the regulation in anchor rope perpendicular to hole face within range is realized in the removal of rethread transverse movement subassembly and vertical movement subassembly, accurate propelling movement anchor rope hand-hole.
Referring to fig. 5, the foldable drill boom assembly 2 comprises a drill boom mechanism 2.1, a pushing beam base 2.2 and a pushing rod adding mechanism 2.3, wherein the drill boom mechanism 2.1 is arranged on the crawler chassis 1, the drill boom mechanism 2.1 can perform rotary motion along a horizontal plane and pitch motion along a vertical plane, the pushing beam base 2.2 is hinged with one end, far away from the crawler chassis 1, of the drill boom mechanism 2.1, the pushing rod adding mechanism 2.3 is arranged on the pushing beam base 2.2, and the pushing rod adding mechanism 2.3 is used for performing drilling construction in a tunnel.
The drill boom mechanism 2.1 comprises a drill boom revolving platform 2.1.1, a second working arm 2.1.2, a second telescopic boom 2.1.3, a third lifting piece 2.1.4 and a fourth lifting piece 2.1.5, wherein the drill boom revolving platform 2.1.1 is arranged on the crawler chassis 1, the second working arm 2.1.2 revolving platform can rotate around a vertical shaft, the second working arm 2.1.2 is hinged between the drill boom revolving platform 2.1.1 and the second telescopic boom 2.1.3, a first end of the second telescopic boom 2.1.3 is hinged with the second working arm 2.1.2, a second end of the second telescopic boom 2.1.3 is connected with the pushing beam base 2.2, the second telescopic boom 2.1.3 can extend and retract along the length direction, the third lifting piece 2.1.4 is hinged between the drill boom revolving platform 2.1.1 and the second working arm 2.1.2, the third lifting piece 2.1.4 can drive the second working arm 2.1.1.3 to move vertically along the second lifting surface, and the second lifting piece 2.1.3 can drive the second lifting piece to move vertically along the second lifting surface of the second lifting arm 2.1.3.5. The drill boom revolving platform 2.1.1 can rotate around the shaft on the drill boom base 1.11, the rotation of the folding drill boom assembly 2 can be realized through the drill boom revolving platform 2.1.1, and the construction requirements of multiple angles and multiple working conditions can be realized in a tunnel. Preferably, the second working arm 2.1.2 is connected to the drill boom base 1.11 through the drill boom revolving platform 2.1.1, the third lifting cylinder is connected to the front end of the second working arm 2.1.2 and the drill boom revolving platform 2.1.1, during the anchor cable construction, the lifting and dropping procedures of the second working arm 2.1.2 are completed through the extension and retraction of the third lifting cylinder, the front end of the second working arm 2.1.2 is connected with the second telescopic arm 2.1.3 through a pin shaft, and the fourth lifting cylinder is connected to the front end of the second telescopic arm 2.1.3 and the front end of the second working arm 2.1.2. During the construction of the anchor cable, the lifting and retraction of the second telescopic arm 2.1.3 are completed through the extension and retraction of the fourth lifting oil cylinder, and the working procedure of falling back is completed, preferably, the second telescopic arm 2.1.3 can realize front-back telescopic operation so as to move the pushing and rod adding mechanism 2.3 to the vicinity of a drilling hole, and the working range is enlarged.
Referring to fig. 6, the folding anchor cable arm assembly 3 and the folding drill arm assembly 2 are mounted on the crawler chassis 1, and the turning radius of the whole vehicle is reduced by folding the rotation of the first working arm 3.1.2 and the second working arm 2.1.2, so that the whole vehicle can walk in a narrow and complex tunnel.
In this embodiment, the pushing and rod adding mechanism 2.3 includes a drill arm guide rail 2.3.1, a drill holder 2.3.2, a second power head 2.3.3, a tip cylinder 2.3.4 and a rod adding component 2.3.5, the drill arm guide rail 2.3.1 is arranged on the pushing beam base 2.2, the drill holder 2.3.2 is arranged at one end of the drill arm guide rail 2.3.1 close to a drill hole, the drill holder 2.3.2 is used for supporting a drill rod, the second power head 2.3.3 is slidably arranged on the drill arm guide rail 2.3.1, an output end of the second power head 2.3.3 is connected with the drill rod and used for providing impact force for the drill rod, the tip cylinder 2.3.4 is arranged on the drill arm guide rail 2.3.1, an output end of the tip cylinder 2.3.4 is formed into a conical part used for being abutted against a hole surface, the tip cylinder 2.3.4 can be lengthened or shortened to be close to or far away from the hole surface, and the rod adding component 2.3.5 is used for replacing a tunnel. The drill rod feeding mechanism is fixed at the left side of the drill arm guide rail 2.3.1, and a high-capacity rod warehouse is arranged in the drill rod feeding mechanism, so that the frequency of manual rod feeding can be reduced, the drill rod clamping device 2.3.2 is fixed at the front end of the drill arm guide rail 2.3.1, and a drill rod in a hole is clamped in the drilling process, so that the drill rod is prevented from sliding in the drilling process, and the drilling stability is ensured;
Further, a second power head 2.3.3 is arranged on the drill boom guide rail 2.3.1, the second power head 2.3.3 can slide back and forth along the guide rail, the second power head 2.3.3 can provide power for the drilling machine, and the impact function of the second power head 2.3.3 can be opened when needed. The guide sleeve is arranged at the position of the second power head 2.3.3 to ensure accurate butt joint of the connecting rod, the center oil cylinder 2.3.4 is fixed at the rear of the drill boom guide rail 2.3.1, and under the action of the center oil cylinder 2.3.4, the pushing mechanism can be stabilized according to different construction working conditions, and the drilling stability of an upper step is improved.
In the embodiment, when the anchor cable trolley is used for implementing a drilling process, the whole vehicle is driven to a middle step for construction, the positions of the second working arm 2.1.2 and the second telescopic arm 2.1.3 are adjusted under the action of the third lifting oil cylinder and the fourth lifting oil cylinder, so that the propelling mechanism is aligned with corresponding drilling points, then the center oil cylinder 2.3.4 is stretched out, the center oil cylinder 2.3.4 can select stretching length according to actual working conditions, the stability of the propelling rod adding mechanism 2.3 is increased when the step drilling process is carried out, so that the drilling stability is increased, then the rod adding mechanism is used for adding rods, the drill rod is supported by the drill holder 2.3.2, and the second power head 2.3.3 moves forwards along the drill arm guide rail 2.3.1 for drilling operation.
In this embodiment, the grouting assembly 4 includes a stirrer, a grouting pump and a grouting pipeline, the stirrer is used for stirring the slurry, the grouting pump is connected between the stirrer and the grouting pipeline, and the grouting pump can convey the slurry in the stirrer into the drill hole through the grouting pipeline. The grouting assembly 4 is arranged at the left front part of the crawler chassis 1, so that the grouting stroke can be shortened, and the slurry is prevented from being solidified and blocked in the slurry conveying pipe. During construction, the stirred slurry is conveyed into the grouting pump by the stirrer, the grouting pump provides power, the slurry enters the grouting pipeline through the grouting pump and is conveyed into the anchor cable hole through the grouting pipeline, and therefore grouting function is achieved.
Referring to fig. 7, the multifunctional integrated anchor cable construction equipment further comprises an anchor cable reel 5, a rotary driving piece and a turnover driving piece, wherein the bottom of the anchor cable reel 5 is rotatably connected with the crawler-type chassis 1 through a pin shaft, the anchor cable reel 5 is provided with an anchor cable reel which is rotatably arranged, the rotary driving piece is arranged on the crawler-type chassis 1 and is connected with a central shaft of the anchor cable reel, the rotary driving piece can drive the anchor cable reel to rotate so as to convey an anchor cable, the turnover driving piece is hinged between the anchor cable reel 5 and the crawler-type chassis 1, and the turnover driving piece can drive the anchor cable reel 5 to move between a horizontal position and a vertical position. The rotary driving piece can drive the anchor cable roll to rotate so as to realize automatic conveying of the anchor cable, the lower part of the anchor cable reel 5 is rotationally connected with the crawler chassis 1 through a pin shaft, and the overturning function of the anchor cable reel 5 is realized through the overturning driving piece. When the installation procedure of the anchor rope reel is carried out, the anchor rope reel 5 is turned to be horizontal under the action of the turning driving piece, and then the anchor rope reel is placed in the anchor rope reel 5 through the lifting appliance, so that the replacement of the anchor rope reel is realized, and the normal operation is ensured.
Referring to fig. 8, a crawler chassis 1 is used for walking in a tunnel with limited space and has all-terrain trafficability; the crawler chassis 1 is provided with a fuel tank 1.1, a hydraulic radiator 1.2, supporting legs 1.3, a cab 1.4, a water pump 1.5, an air compressor 1.6, a tool cabinet 1.7, a hydraulic oil tank 1.8, an electric control cabinet 1.9, a power mechanism 6, an anchor cable arm base 1.10 and a drill arm base 1.11, wherein the fuel tank 1.1 and the hydraulic radiator 1.2 are positioned at the left side of the crawler chassis 1, the cab 1.4, the water pump 1.5, the air compressor 1.6 and the tool cabinet 1.7 are positioned at the right side of the crawler chassis 1, the fuel tank 1.1, the hydraulic radiator 1.2, the water pump 1.5 and the air compressor 1.6 are used for heat preservation and heat dissipation of equipment, and the cab 1.4 is at a certain height from the ground; two groups of supporting legs 1.3 are arranged on the front side and the rear side below the crawler chassis 1, the supporting legs 1.3 are of palm type structures, the freedom degree of unfolding and lifting is achieved, the supporting legs 1.3 support the ground during operation, but the crawler cannot be separated from the ground, a hydraulic oil tank 1.8 is located in the middle of the crawler chassis 1 and used for providing hydraulic pressure, an electric control cabinet 1.9 is located on the front side of the crawler chassis 1 and used for providing electric power, a power mechanism 6 is used for providing travelling power for the crawler chassis 1, an anchor cable arm base 1.10 is arranged on the right front side of the crawler chassis 1, and the folding anchor cable arm assembly 3 is connected with the crawler chassis 1 through the anchor cable arm base 1.10.
Example 2
The difference from the embodiment 1 is that, referring to fig. 3 and 4 in combination, the folding anchor cable arm assembly 3 further comprises a tee structure 3.4, a jacking pipe and two jacking pipe conveying wheels 3.5, the tee structure 3.4 is provided with an output end and two input ends, the output end is connected with the input end of the first power head 3.2.3, one input end is used for the anchor cable to pass through, the other input end is used for the jacking pipe to pass through, the two jacking pipe conveying wheels 3.5 are arranged on the anchor cable arm guide rail 3.2.1 at intervals, the jacking pipe conveying wheels 3.5 and the anchor cable conveying wheels 3.2.4 are arranged in a staggered mode, the jacking pipe sequentially passes through the two jacking pipe conveying wheels 3.5 and extends into the input end, and the jacking pipe conveying wheels 3.5 can drive the jacking pipe to pass through the first power head 3.2.3 and extend into a drilling hole so as to push the anchor into the bottom of the drilling hole.
Example 3
Referring to fig. 9, a construction method of a multifunctional integrated anchor line construction apparatus, which performs construction using the multifunctional integrated anchor line construction apparatus as described above, includes
S1, excavating in a tunnel by adopting a three-step method to form an upper step, a middle step and a lower step;
S2, advancing the multifunctional integrated anchor cable construction equipment to a middle step, and in the embodiment, performing a site preparation stage to complete water and electricity access.
S3, controlling multifunctional integrated anchor cable construction equipment to carry out drilling construction and anchor cable construction on the surface of the tunnel;
S3 comprises the following steps:
s3.1, drilling construction is carried out on the surface of a right tunnel of the centering step by adopting the folding drill boom assembly 2;
s3.2, adopting a folding drill arm assembly 2 to sequentially drill the top tunnel surface of the upper step and the right tunnel surface of the upper step, and adopting a folding anchor cable arm assembly 3 to perform anchor cable construction on the right tunnel surface of the middle step;
S3.3, drilling construction is carried out on the left side tunnel surface of the upper step by adopting the folding drill boom assembly 2, and simultaneously, anchor rope construction is carried out on the top and the right side tunnel surface of the upper step in sequence by adopting the folding anchor rope boom assembly 3;
s3.4, drilling construction is carried out on the left side tunnel surface of the centering step by adopting the folding drill boom assembly 2, and meanwhile, anchor rope construction is carried out on the left side tunnel surface of the upper step by adopting the folding anchor rope boom assembly 3;
S3.5, drilling construction is carried out on the left side and the right side tunnel surfaces of the lower step by adopting the folding drill boom assembly 2, and meanwhile, anchor rope construction is carried out on the left side of the centering step by adopting the folding anchor rope boom assembly 3;
S3.6, carrying out anchor rope construction on the left side tunnel surface and the right side tunnel surface of the lower step by adopting a folding anchor rope arm assembly 3;
In the embodiment, the step S3.6 also comprises the steps of mechanically excavating forwards, reserving core soil and circularly constructing according to the steps S3.1-S3.6.
S4, installing steel belts, backing plates and anchorage devices, and tensioning anchor cables;
s5, grouting the inside of the drilled hole by adopting a grouting assembly.
The construction method of the embodiment can ensure that the folding anchor cable arm assembly 3 and the folding drill arm assembly 2 can be in a working state, improve the utilization rate of the two arms and the overall construction efficiency, ensure that the two arms cannot interfere, and ensure that operators standing in the hanging basket 3.1.5 are far away from the folding drill arm assembly 2 when the two arms are constructed separately and ensure the safety of the operators.
The construction method of the multifunctional integrated anchor cable construction equipment comprises the multifunctional integrated anchor cable construction equipment, so that the multifunctional integrated anchor cable construction equipment construction method has all the beneficial effects of the multifunctional integrated anchor cable construction equipment and is not described in detail herein.
The foregoing description is only of the preferred embodiments of the present invention and is not intended to limit the scope of the invention, and all equivalent structural changes made by the description of the present invention and the accompanying drawings or direct/indirect application in other related technical fields are included in the scope of the invention.

Claims (13)

1. The multifunctional integrated anchor cable construction equipment is characterized by comprising a crawler-type chassis (1), a folding drill arm assembly (2), a folding anchor cable arm assembly (3) and a grouting assembly (4), wherein the crawler-type chassis (1) can walk along the ground, the folding drill arm assembly (2) is arranged on the crawler-type chassis (1) and is used for carrying out drilling construction in a tunnel, the folding anchor cable arm assembly (3) comprises a working arm mechanism (3.1), a cable conveying mechanism (3.2) and a drug conveying mechanism (3.3), the working arm mechanism (3.1) is arranged on the crawler-type chassis (1), the working arm mechanism (3.1) can do rotary motion along the horizontal plane and pitching motion along the vertical plane, the cable conveying mechanism (3.2) is arranged at one end of the working arm mechanism (3.1) far away from the crawler-type chassis (1), the cable conveying mechanism (3.2) is used for conveying anchor cables into a borehole, the drug conveying mechanism (3.3) is arranged on the crawler-type anchor mechanism (3.1) and is used for conveying the grouting assembly (4) into the borehole.
2. The multi-functional integrated anchor cable construction equipment according to claim 1, wherein the working arm mechanism (3.1) comprises a working arm rotary table (3.1.1), a first working arm (3.1.2), a first telescopic arm (3.1.3), an L-shaped rotary table (3.1.4), a hanging basket (3.1.5), a first lifting piece (3.1.6) and a second lifting piece (3.1.7), the working arm rotary table (3.1.1) is arranged on the crawler chassis (1), the working arm rotary table (3.1.1) can rotate around a vertical shaft, the first working arm (3.1.2) is hinged between the working arm rotary table (3.1.1) and the first telescopic arm (3.1.3), a first end of the first telescopic arm (3.1.3) is hinged with the first working arm (3.1.2), a second end of the first telescopic arm (3.1.2) is hinged with the first working arm (3.1.2), the first telescopic arm (3.1.1.1.1) can be hinged with the first telescopic arm (3.1.3) and the first telescopic arm (3.1.3) can rotate around the first telescopic arm (3.1.1.3) and the first telescopic arm (3.1.3) along the L-shaped rotary table (3.1.4) and the first telescopic arm (3.1.1.3) can rotate around the first telescopic arm (3.1.1.3) and the first telescopic arm (3.4), the first lifting piece (3.1.6) can drive the first working arm (3.1.2) to do pitching motion along a vertical plane, the second lifting piece (3.1.7) is hinged between the first working arm (3.1.2) and the first telescopic arm (3.1.3), and the second lifting piece (3.1.7) can drive the first telescopic arm (3.1.3) to do pitching motion along the vertical plane.
3. The multifunctional integrated anchor cable construction equipment according to claim 2, wherein the cable conveying mechanism (3.2) comprises an anchor cable arm guide rail (3.2.1), a hydraulic shear (3.2.2), a first power head (3.2.3) and two anchor cable conveying wheels (3.2.4), the anchor cable arm guide rail (3.2.1) is arranged on the L-shaped rotary seat (3.1.4), the hydraulic shear (3.2.2) is arranged on the anchor cable arm guide rail (3.2.1) and used for cutting off an anchor cable, the first power head (3.2.3) is arranged on the anchor cable arm guide rail (3.2.1) in a sliding mode, the first power head (3.2.3) can clamp the anchor cable and drive the anchor cable to move along the anchor cable arm guide rail (3.2.1) or rotate along the axis direction of the anchor cable, and the two anchor cable conveying wheels (3.2.4) are arranged on the arm guide rail (3.2.1) at intervals and sequentially extend from the first power head (3.2.3) to the second power head (3.2.3) and are used for conveying the anchor cable.
4. A multifunctional integrated anchor cable construction equipment according to claim 3, characterized in that the drug delivery mechanism (3.3) comprises a rotating component (3.3.1), a drug delivery pipe (3.3.2) and an air compressor (1.6), the rotating component (3.3.1) is arranged at one end of the anchor cable arm guide rail (3.2.1) far away from the first telescopic arm (3.1.3), the drug delivery pipe (3.3.2) is connected with the output end of the rotating component (3.3.1), the rotating component (3.3.1) can drive the drug delivery pipe (3.3.2) to rotate between a butt joint position and an avoidance position, the drug delivery pipe (3.3.2) is used for delivering anchoring agent, the air compressor (1.6) is communicated with the drug delivery pipe (3.3.2), and the air compressor (1.6) can blow the anchoring agent in the drill hole in the drug delivery pipe (3.3.2).
5. The multifunctional integrated anchor cable construction equipment according to claim 4, wherein the folding anchor cable arm assembly (3) further comprises a tee structure (3.4), a jacking pipe and two jacking pipe conveying wheels (3.5), the tee structure (3.4) is provided with an output end and two input ends, the output end is connected with the input end of the first power head (3.2.3), one input end is used for the anchor cable to pass through, the other input end is used for the jacking pipe to pass through, the two jacking pipe conveying wheels (3.5) are arranged on the anchor cable arm guide rail (3.2.1) at intervals, the jacking pipe conveying wheels (3.5) and the anchor cable conveying wheels (3.2.4) are arranged in a vertically staggered mode, the jacking pipe sequentially passes through the two jacking pipe conveying wheels (3.5) and extends into the input end, and the jacking pipe conveying wheels (3.5) can drive the jacking pipe to pass through the first power head (3.2.3) and extend into a drilling hole to push an anchor to the bottom of the drilling hole.
6. The multifunctional integrated anchor cable construction equipment according to claim 5, wherein the folding anchor cable assembly further comprises a fine adjustment mechanism (3.6), the fine adjustment mechanism (3.6) comprises a transverse movement assembly, a vertical movement assembly and a mechanical gripper, the transverse movement assembly is arranged at one end of the anchor cable arm guide rail (3.2.1) far away from the first telescopic arm (3.1.3), the vertical movement assembly is arranged on the transverse movement assembly, the transverse movement mechanism can drive the vertical movement assembly to move along a horizontal direction perpendicular to a drilling axis, the mechanical gripper is arranged on the vertical movement assembly, the vertical movement assembly can drive the mechanical gripper to move along a vertical direction, and the mechanical gripper is used for clamping an anchor cable.
7. The multifunctional integrated anchor cable construction equipment according to claim 6, wherein the foldable drill boom assembly (2) comprises a drill boom mechanism (2.1), a propelling beam base (2.2) and a propelling rod adding mechanism (2.3), the drill boom mechanism (2.1) is arranged on the crawler-type chassis (1), the drill boom mechanism (2.1) can perform rotary motion along a horizontal plane and pitch motion along a vertical plane, the propelling beam base (2.2) is hinged with one end, far away from the crawler-type chassis (1), of the drill boom mechanism (2.1), the propelling rod adding mechanism (2.3) is arranged on the propelling beam base (2.2), and the propelling rod adding mechanism (2.3) is used for performing drilling construction in a tunnel.
8. The multifunctional integrated anchor cable construction equipment according to claim 7, wherein the drill arm mechanism (2.1) comprises a drill arm rotary table (2.1.1), a second working arm (2.1.2), a second telescopic arm (2.1.3), a third lifting member (2.1.4) and a fourth lifting member (2.1.5), the drill arm rotary table (2.1.1) is arranged on the crawler chassis (1), the second working arm (2.1.2) rotary table can rotate around a vertical shaft, the second working arm (2.1.2) is hinged between the drill arm rotary table (2.1.1) and the second telescopic arm (2.1.3), a first end of the second telescopic arm (2.1.3) is hinged with the second working arm (2.1.2), a second end of the second telescopic arm is connected with the propelling beam base (2.2), the second working arm (2.1.2) can move along the vertical shaft along the second lifting member (2.1.1.3), and the second telescopic arm (2.1.3) can move along the vertical shaft along the second lifting member (2.1.2.1.3).
9. The multi-functional integrated anchor line construction equipment according to claim 8, wherein the pushing and rod adding mechanism (2.3) comprises a drill arm guide rail (2.3.1), a drill bit holder (2.3.2), a second power head (2.3.3), a tip oil cylinder (2.3.4) and a rod adding component (2.3.5), the drill arm guide rail (2.3.1) is arranged on the pushing beam base (2.2), the drill bit holder (2.3.2) is arranged at one end, close to a drill hole, of the drill arm guide rail (2.3.1), the drill bit holder (2.3.2) is used for supporting a drill rod, the second power head (2.3.3) is slidably arranged on the drill arm guide rail (2.3.1), an output end of the second power head (2.3.3) is connected with the drill rod for providing impact force for the drill rod, the oil cylinder (2.3.4) is arranged on the arm guide rail (2.3.1), the tip end of the drill rod is close to the drill rod (2.3.4) or the tip end of the drill rod can be replaced by a conical part (2.4) close to the drill rod component (2.4).
10. The multifunctional integrated anchor line construction equipment according to any one of claims 1 to 7, characterized in that the grouting assembly (4) comprises a stirrer for stirring the slurry, a grouting pump connected between the stirrer and the grouting pipeline, and a grouting pipeline through which the grouting pump can convey the slurry in the stirrer into the borehole.
11. The multifunctional integrated anchor cable construction equipment according to any one of claims 1 to 7, further comprising an anchor cable reel (5), a rotary driving piece and a turnover driving piece, wherein the bottom of the anchor cable reel (5) is rotatably connected with the crawler-type chassis (1) through a pin shaft, an anchor cable reel which is rotatably arranged is arranged on the anchor cable reel (5), the rotary driving piece is arranged on the crawler-type chassis (1) and is connected with a central shaft of the anchor cable reel, the rotary driving piece can drive the anchor cable reel to rotate so as to convey an anchor cable, the turnover driving piece is hinged between the anchor cable reel (5) and the crawler-type chassis (1), and the turnover driving piece can drive the anchor cable (5) to move between a horizontal position and a vertical position.
12. A multifunctional integrated anchor cable construction equipment and construction method, constructed by the multifunctional integrated anchor cable construction equipment according to any one of claims 1 to 10, comprising:
S1, excavating in a tunnel by adopting a three-step method to form an upper step, a middle step and a lower step;
S2, advancing the multifunctional integrated anchor cable construction equipment to a middle step;
S3, controlling multifunctional integrated anchor cable construction equipment to carry out drilling construction and anchor cable construction on the surface of the tunnel;
S4, installing steel belts, backing plates and anchorage devices, and tensioning anchor cables;
s5, grouting the inside of the drilled hole by adopting a grouting assembly.
13. The multi-functional integrated cable construction equipment construction method of claim 12, wherein S3 comprises:
s3.1, drilling construction is carried out on the surface of a right tunnel of the centering step by adopting a folding drill boom assembly (2);
S3.2, adopting a folding drill arm assembly (2) to sequentially drill the top tunnel surface of the upper step and the right tunnel surface of the upper step, and adopting a folding anchor cable arm assembly (3) to anchor the right tunnel surface of the middle step;
S3.3, drilling construction is carried out on the left side tunnel surface of the upper step by adopting a folding drill boom assembly (2), and simultaneously, anchor rope construction is carried out on the top and the right side tunnel surface of the upper step in sequence by adopting a folding anchor rope boom assembly (3);
s3.4, drilling construction is carried out on the left side tunnel surface of the centering step by adopting a folding drill boom assembly (2), and meanwhile, anchor rope construction is carried out on the left side tunnel surface of the upper step by adopting a folding anchor rope boom assembly (3);
s3.5, drilling construction is carried out on the left side and the right side tunnel surfaces of the lower step by adopting a folding drill boom assembly (2), and meanwhile, anchor rope construction is carried out on the left side of the centering step by adopting a folding anchor rope boom assembly (3);
S3.6, carrying out anchor rope construction on the left side tunnel surface and the right side tunnel surface of the lower step by adopting the folding anchor rope arm assembly (3).
CN202511546520.7A 2025-10-28 2025-10-28 Multifunctional integrated anchor cable construction equipment and construction methods Pending CN121138961A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202511546520.7A CN121138961A (en) 2025-10-28 2025-10-28 Multifunctional integrated anchor cable construction equipment and construction methods

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202511546520.7A CN121138961A (en) 2025-10-28 2025-10-28 Multifunctional integrated anchor cable construction equipment and construction methods

Publications (1)

Publication Number Publication Date
CN121138961A true CN121138961A (en) 2025-12-16

Family

ID=97990429

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202511546520.7A Pending CN121138961A (en) 2025-10-28 2025-10-28 Multifunctional integrated anchor cable construction equipment and construction methods

Country Status (1)

Country Link
CN (1) CN121138961A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207420600U (en) * 2017-10-17 2018-05-29 廊坊景隆重工机械有限公司 A kind of Mine anchorage cable trolley
CN110630285A (en) * 2019-10-08 2019-12-31 甘肃恒路交通勘察设计院有限公司 Anchor cable-steel frame support and construction method for large-section soft rock tunnel
CN112696200A (en) * 2020-12-22 2021-04-23 中铁五局集团成都工程有限责任公司 Soft rock large-section tunnel micro-step excavation method
CN115749595A (en) * 2022-11-11 2023-03-07 中国铁建重工集团股份有限公司 Anchor cable trolley and using method thereof
CN219492310U (en) * 2023-04-21 2023-08-08 中铁工程装备集团有限公司 Arch, anchor and spray integrated operation trolley
CN118257617A (en) * 2024-05-06 2024-06-28 江西鑫通机械制造有限公司 Multifunctional anchor cable trolley
CN118582220A (en) * 2023-03-03 2024-09-03 双鸭山金德工贸有限责任公司 A drilling and anchoring automatic integrated machine for coal mines
CN118836029A (en) * 2024-08-23 2024-10-25 长沙科达智能装备股份有限公司 Drilling and grouting anchor cable trolley device and application method
CN119712127A (en) * 2025-02-25 2025-03-28 中铁五局集团电务工程有限责任公司 An excavation method for soft surrounding rock tunnel construction based on real-time monitoring

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207420600U (en) * 2017-10-17 2018-05-29 廊坊景隆重工机械有限公司 A kind of Mine anchorage cable trolley
CN110630285A (en) * 2019-10-08 2019-12-31 甘肃恒路交通勘察设计院有限公司 Anchor cable-steel frame support and construction method for large-section soft rock tunnel
CN112696200A (en) * 2020-12-22 2021-04-23 中铁五局集团成都工程有限责任公司 Soft rock large-section tunnel micro-step excavation method
CN115749595A (en) * 2022-11-11 2023-03-07 中国铁建重工集团股份有限公司 Anchor cable trolley and using method thereof
CN118582220A (en) * 2023-03-03 2024-09-03 双鸭山金德工贸有限责任公司 A drilling and anchoring automatic integrated machine for coal mines
CN219492310U (en) * 2023-04-21 2023-08-08 中铁工程装备集团有限公司 Arch, anchor and spray integrated operation trolley
CN118257617A (en) * 2024-05-06 2024-06-28 江西鑫通机械制造有限公司 Multifunctional anchor cable trolley
CN118836029A (en) * 2024-08-23 2024-10-25 长沙科达智能装备股份有限公司 Drilling and grouting anchor cable trolley device and application method
CN119712127A (en) * 2025-02-25 2025-03-28 中铁五局集团电务工程有限责任公司 An excavation method for soft surrounding rock tunnel construction based on real-time monitoring

Similar Documents

Publication Publication Date Title
CN107842311B (en) Multifunctional tunnel rock drilling and arch erecting integrated machine
US3645343A (en) Rotary drilling machine
CN112096281B (en) Drilling, pile splicing and pile planting all-in-one machine and construction method thereof
CN109630013B (en) A hydraulic rock drilling rig
CN113833486B (en) Multifunctional cantilever type tunnel boring machine
CN113339030A (en) High slope drilling, injecting and anchoring function integrated anchoring equipment
CN113898362B (en) A cantilever anchor mining machine and anchor support method
CN106245985B (en) Hydraulic utility pole truck
CN213478215U (en) A equipment that is used for digging in undercut tunnel to establish slip casting hole
CN114233355A (en) A kind of fast support equipment for excavation roadway and its working method
CN113250193A (en) Construction equipment based on synchronous drilling and precast pile splicing and construction method thereof
CN115749595A (en) Anchor cable trolley and using method thereof
CN120119888A (en) A gantry-type integrated operation workstation that can adapt to different underground cavern sections
CN215211021U (en) Construction equipment based on synchronous drilling and precast pile splicing
CN120465958A (en) Multi-mode non-explosive excavation integrated equipment based on ultra-high pressure hydraulic cutting
CN108119174B (en) Combined drilling boom for drilling holes and locking anchor rods and rock drilling vehicle with same
CN117432430A (en) Method and equipment for tunneling drilled hard rock tunnel
CN115773140A (en) Tunnel double-arm multi-row automatic jumbolter and using method thereof
CN114673518A (en) Tunneling, anchoring and supporting integrated machine and roadway anchoring and supporting construction method
CN110206086B (en) Excavating loader with jumbolter
RU2695196C2 (en) Installation for drilling of rock and method of side installation in predetermined position of drilling device
CN119163089A (en) Tunnel excavation equipment
CN212803057U (en) Hydraulic jumbolter
CN215170115U (en) An efficient anchor drilling rig
CN210104836U (en) Excavation type loader with jumbolter

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination