CN119664385A - In-situ disassembly method for broken stratum water delivery tunnel open type TBM shield - Google Patents

In-situ disassembly method for broken stratum water delivery tunnel open type TBM shield Download PDF

Info

Publication number
CN119664385A
CN119664385A CN202411789947.5A CN202411789947A CN119664385A CN 119664385 A CN119664385 A CN 119664385A CN 202411789947 A CN202411789947 A CN 202411789947A CN 119664385 A CN119664385 A CN 119664385A
Authority
CN
China
Prior art keywords
shield
tbm
grouting
tunnel
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202411789947.5A
Other languages
Chinese (zh)
Inventor
李东锋
李伟伟
赵铭坤
李兆宇
方涛
毕晨
张健
申玉西
张磊
沙世全
王忠朋
王明星
李小龙
张涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 3 Co Ltd
Original Assignee
Sinohydro Bureau 3 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 3 Co Ltd filed Critical Sinohydro Bureau 3 Co Ltd
Priority to CN202411789947.5A priority Critical patent/CN119664385A/en
Publication of CN119664385A publication Critical patent/CN119664385A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses an in-situ disassembly method of an open TBM (Tunnel boring machine) stay shield of a stratum water conveyance tunnel, which comprises the steps of firstly collapsing cavities at the top of a shield and grouting and reinforcing broken surrounding rocks, secondly integrally welding the shield, thirdly installing a TBM host and a crane span region lifting facility, fourthly installing a supporting lifting facility after TBM and disassembling supporting equipment after TBM, fifthly, disassembling a main beam and a rear support of the TBM host, sixthly, disassembling a main drive and a cutter head of the TBM host, and seventhly, grouting and reinforcing the cutter head and the top region of the shield. The invention adopts the section steel to integrally weld the top, side and bottom shields before disassembling the machine, the shields are not disassembled during disassembling the machine, the shields are reserved as permanent supporting bodies, and then a plurality of hoisting equipment are matched, so that the in-situ safe and efficient disassembling of the machine in a TBM hole is realized, the stability of surrounding rocks of the hole is fully ensured, the construction risk is greatly reduced, and the construction safety and the construction progress are effectively ensured.

Description

In-situ disassembly method for broken stratum water delivery tunnel open type TBM shield
Technical Field
The invention belongs to the technical field of tunnel construction, and particularly relates to an in-situ disassembly method for an open TBM (Tunnel boring machine) reserved shield of a ground stratum water delivery tunnel.
Background
At present, the TBM method is widely applied in a water delivery tunnel, due to the particularity of TBM equipment, a belt is usually disconnected after a TBM finishes a main tunnel tunneling task by a TBM in-tunnel dismantling machine, a main machine is dismantled for a certain distance to excavate a chamber, after the excavation of the chamber is completed, an electric hoist is arranged at the top of the dismantling chamber, equipment such as a winch and a jack is utilized to dismantle main machine parts, and after a matched trolley is separated section by section, the main machine parts are disassembled and dismantled in situ. The mode requires that the section and the space of the disassembled hole are large enough, the construction difficulty is large, and the construction period is long. When the TBM is extremely broken and can not form a dismantling chamber due to surrounding rock in TBM tunneling, and the TBM reaches the scrapping standard, the shield is blocked, and the forced dismantling machine by adopting the traditional method can face extremely great construction risks.
Disclosure of Invention
Aiming at the defects in the prior art, the invention provides an in-situ disassembly method for the open TBM shield of the broken stratum water delivery tunnel, which adopts section steel to integrally weld the top shield, the side shield and the bottom shield before disassembly, and the shields are not disassembled when the machine is disassembled, but are reserved as permanent supporting bodies, and are matched with various hoisting equipment, so that the in-situ safe and efficient disassembly in the TBM tunnel is realized, the stability of surrounding rocks of the tunnel is fully ensured, the construction risk is greatly reduced, the construction safety and the construction progress are effectively ensured, good engineering effects are obtained, and the method has a stronger reference effect on similar engineering.
In order to solve the technical problems, the technical scheme adopted by the invention is that the method for detaching the open TBM shield in situ of the broken stratum water delivery tunnel is characterized by comprising the following steps:
Step one, cavity collapse backfilling at the top of a shield and grouting reinforcement on broken surrounding rocks, wherein the process is as follows:
Step 101, spraying, mixing and backfilling a cavity collapsed at the top of a shield, drilling a plurality of first grouting anchors at the tail part of the shield by using a hand drill, arranging the first grouting anchors along the circumferential direction of a tunnel, and arranging the first grouting anchors at the top of the shield;
102, after grouting reinforcement is completed, connecting a steel arch at the tail of the shield by using steel bars and section steel, and sealing the steel arch at the tail of the shield which is not sealed by sprayed concrete;
Welding the joints of the side shields and the top shields by using a connecting steel plate, and welding the top shields, the side shields and the top shields and the side shields and the bottom shields by using connecting steel bars to form a surrounding rock steel support body;
The method comprises the steps of installing a TBM host and a crane span structure region lifting facility, namely, arranging two groups of lifting anchor points on the tops of tunnels corresponding to the TBM host and the crane span structure region, wherein each group of lifting anchor points are uniformly distributed along the extending direction of the tunnels;
step four, installing supporting hoisting facilities after TBM and dismantling supporting equipment after TBM, wherein the process is as follows:
Step 401, simultaneously, two groups of fixed hanging point groups are arranged on the top of a tunnel corresponding to a TBM rear supporting area in a beating mode, wherein each group of fixed hanging point groups are uniformly distributed along the circumferential direction of the tunnel;
Step 402, welding lifting lugs on a frame structure of the TBM rear supporting equipment and installing guide chains;
step 403, after the TBM post-supporting equipment is removed, removing the TBM post-supporting frame structure and transporting out of the tunnel by utilizing a TBM post-supporting lifting facility in sequence;
And fifthly, removing a main beam and a rear support of the TBM host, wherein the process is as follows:
step 501, arranging a plurality of support columns at the bottom of a main beam, wherein the support columns are distributed along the extending direction of the main beam;
Step 502, adjusting the length of the steel wire rope, and removing the main push cylinder and the supporting shoe and transporting out of the hole after the main beam and the rear support are tensioned by using a hoisting chain block;
Step 503, dismantling a connecting bolt between the rear support and the main beam II, detaching the rear support, turning over, placing the rear support at the bottom of the tunnel, and dividing and dismembering the rear support in the tunnel and then sequentially transporting the rear support out of the tunnel, wherein the main beam comprises the main beam I and the main beam II;
step 504, disassembling the saddle, sequentially transporting the saddle out of the hole, and finally disassembling and dismembering the main beam II and the main beam I, and sequentially transporting the saddle out of the hole;
Step six, dismantling a main drive and a cutter head of a TBM host, namely cutting and dismembering the steel structure and a motor reducer at the upper part of the main drive in sequence from top to bottom by adopting a sequence from top to bottom, and transferring dismantled parts to the outside of a transport hole on a scooter by utilizing a lifting frame;
And seventhly, grouting and reinforcing the top areas of the cutterhead and the shield, wherein a plurality of groups of grouting hole groups are drilled at the tops of the cutterhead and the shield, the grouting hole groups are distributed in a quincuncial shape, each grouting hole group comprises a plurality of grouting holes, the grouting holes are distributed along the circumferential direction of the tunnel, a second grouting anchor rod is inserted into each grouting hole, cement grouting is carried out by the aid of the second grouting anchor rod, grouting and reinforcing are carried out on the broken surrounding rock areas at the tops of the cutterhead and the shield, and disassembling and machine is completed.
The method for in-situ disassembly of the open TBM shield of the stratum-breaking water-conveying tunnel is characterized in that in the step 101, the circumferential distance between two adjacent first grouting anchors is 0.5-1 m, the length of each first grouting anchor is 2.0-6.0 m, the inclination angle of each first grouting anchor is 10-45 degrees, the first grouting anchors incline forwards along the extending direction of the tunnel, the included angle between the first grouting anchors on two sides is 120-150 degrees, and when cement slurry is injected by the first grouting anchors, the grouting pressure is not more than 3MPa.
The method for in-situ disassembly of the open TBM shield of the broken stratum water delivery tunnel is characterized in that in the third step, derailment prevention steel plates are arranged at two ends of the first track beam.
The method for in-situ disassembly of the open TBM shield of the ground stratum water conveyance tunnel is characterized in that in the third step, the first track beam is installed at the top of the tunnel through a plurality of first installation pieces, the plurality of first installation pieces are uniformly distributed along the extending direction of the first track beam, four installation holes are formed in each lifting anchor point, and each first installation piece comprises a first installation plate arranged at the lifting anchor point, a first fixed anchor rod arranged between the first installation plate and the installation holes, and a rib plate arranged on the first installation plate and far away from one side of the first fixed anchor rod.
The method for in-situ detaching the shield of the open TBM of the stratum conveying tunnel is characterized in that in step 401, the fixed hanging point groups comprise four fixed hanging point groups distributed along the circumferential direction of the tunnel, the chain blocks are installed at the top of the tunnel through second installation pieces, the number of the second installation pieces is equal to that of the chain blocks and corresponds to that of the chain blocks one by one, each second installation piece comprises a second installation plate arranged at the fixed hanging point, a second fixed anchor rod arranged between the second installation plate and the fixed hanging point, and two installation anchor rods which are arranged on the second installation plate and are uniformly distributed on one side far away from the second fixed anchor rod, one ends of the two installation anchor rods are fixed on the second installation plate, and the chain blocks are installed between the other ends of the two installation anchor rods.
The method for in-situ disassembly of the open TBM shield of the ground stratum water conveyance tunnel is characterized in that in the step six, the hoisting frame is a portal hoisting frame, the hoisting frame comprises a plurality of hoisting frame bodies, the hoisting frame bodies are distributed along the extending direction of the tunnel, a second track beam is arranged among the hoisting frame bodies, the hoisting frame comprises a hoisting cross beam which is horizontally arranged and a supporting vertical beam which is vertically arranged at the bottom of the hoisting cross beam, the hoisting cross beam is connected with the supporting vertical beam through bolts, an inclined support is obliquely arranged between the hoisting cross beam and the supporting vertical beam, and the second track beam is distributed at the bottom of the hoisting cross beam.
The in-situ disassembly method for the open TBM retaining shield of the stratum water conveyance tunnel is characterized in that in the seventh step, an included angle between grouting holes on two sides is 180 degrees, the length of a second grouting anchor rod is 3.5m, the tail of the second grouting anchor rod is welded with a shield, and the distance between two adjacent grouting hole groups is 1.25-1.5 m.
The invention has the advantages that the top, side and bottom shields are integrally welded by adopting the section steel before disassembling the machine, the shields are not disassembled when the machine is disassembled, but are reserved as permanent support bodies, and then the permanent support bodies are matched with various hoisting equipment, so that the in-situ safe and efficient machine disassembling in the TBM hole is realized, the stability of surrounding rocks of the hole is fully ensured, the construction risk is greatly reduced, the construction safety and the construction progress are effectively ensured, good engineering effect is achieved, and the construction method has a stronger reference effect on similar engineering.
The technical scheme of the invention is further described in detail through the drawings and the embodiments.
Drawings
Fig. 1 is a schematic diagram of the placement of a first grouting anchor in a tunnel according to the present invention.
Fig. 2 is a schematic view of the construction state of the whole welding of the shield of the present invention.
Fig. 3 is a schematic view of the installation position of the first rail beam according to the present invention.
FIG. 4 is a schematic view of the installation position of the supporting lifting device in the tunnel after TBM according to the present invention.
Fig. 5 is a schematic view of the construction state of the invention with the main beam and rear support of the TBM main machine removed.
Fig. 6 is a schematic structural view of the lifting frame body of the present invention.
Fig. 7 is a schematic view of the construction state of the motor reducer and the steel structure of the main drive upper part of the TBM main machine removed in the present invention.
Fig. 8 is a schematic view of the construction state of the main drive middle lower part of the TBM host and the cutter head middle lower part of the TBM host removed.
Fig. 9 is a flow chart of the method of the present invention.
Reference numerals illustrate:
1-shield, 2-first grouting anchor rod, 3-tunnel;
4-connecting steel plates, 5-side shields and 6-top shields;
7-a bottom shield, 9-a first track beam;
10-a first mounting plate, 11-a first fixed anchor rod, 12-a rib plate;
13, a chain block, 14, a second mounting plate and 15, a second fixed anchor rod;
16-installing anchor rods, 17-main beams and 18-supporting columns;
19-a main pushing oil cylinder, 20-a supporting shoe and 21-a main beam II;
22-rear support, 23-main beam I, 24-main drive;
25-cutterhead, 26-second track beam, 27-hoisting cross beam;
28-supporting vertical beams, 29-inclined supports and 31-connecting section steel;
32-working platform.
Detailed Description
The method for in-situ disassembly of the open TBM shield of the broken stratum water delivery tunnel as shown in figures 1 to 9 comprises the following steps:
Step one, cavity collapse backfilling at the top of a shield and grouting reinforcement on broken surrounding rocks, wherein the process is as follows:
Step 101, spraying, mixing and backfilling a cavity collapsed at the top of a shield 1 before disassembling, drilling a plurality of first grouting anchors 2 at the tail of the shield 1 by using a hand drill, arranging the first grouting anchors 2 along the circumferential direction of a tunnel 3, uniformly distributing the first grouting anchors 2 at the top of the shield 1, injecting cement paste into the tops of the shield 1 and a cutterhead by using the first grouting anchors 2, and grouting and reinforcing broken surrounding rocks at the tops of the shield 1 and the cutterhead;
102, after grouting reinforcement is completed, connecting a steel arch at the tail part of the shield 1 by using steel bars and section steel, and sealing the steel arch at the tail part of the shield 1 which is not sealed by sprayed concrete;
Welding the whole shield, namely connecting joints of the side shield 5 and the top shield 6 by using a connecting steel plate 4, and welding the joints among the top shields 6, the side shield 5 and the top shield 6 and the joints between the side shield 5 and the bottom shield 7 by using a connecting section steel 31 to form a surrounding rock steel support body;
The method comprises the steps of installing a TBM host and a crane span structure region lifting facility, namely, arranging two groups of lifting anchor points on the tops of tunnels corresponding to the TBM host and the crane span structure region, wherein each group of lifting anchor points are uniformly distributed along the extending direction of the tunnel 3, installing a first track beam 9 by utilizing the lifting anchor points, and installing a lifting chain block on the first track beam 9 to finish the installation of the TBM host and the crane span structure region lifting facility;
step four, installing supporting hoisting facilities after TBM and dismantling supporting equipment after TBM, wherein the process is as follows:
Step 401, two groups of fixed hanging point groups are arranged on the top of a tunnel corresponding to the TBM rear supporting area, and each group of fixed hanging point groups is uniformly distributed along the circumferential direction of the tunnel 3;
Step 402, welding lifting lugs on a frame structure of the TBM rear supporting equipment and installing guide chains;
step 403, after the TBM post-supporting equipment is removed, removing the TBM post-supporting frame structure and transporting out of the tunnel by utilizing a TBM post-supporting lifting facility in sequence;
And fifthly, removing a main beam and a rear support of the TBM host, wherein the process is as follows:
Step 501, arranging a plurality of support columns 18 at the bottom of a main beam 17, wherein the support columns 18 are distributed along the extending direction of the main beam 17, and the top of the main beam 17 is connected with a hoisting chain block pulley by using a steel wire rope;
Step 502, adjusting the length of the steel wire rope, tensioning the main beam 17 and the rear support 22 by using a hoisting chain block, removing the main push cylinder 19 and the support shoe 20, and transporting out of a hole;
Step 503, removing connecting bolts between the rear support 22 and the main beam II 21, detaching and turning the rear support 22, and then placing the rear support 22 at the bottom of the tunnel 3, and dividing and dismembering the rear support 22 in the tunnel 3 and then sequentially transporting the rear support 22 out of the tunnel;
Step 504, disassembling the saddle, sequentially transporting the saddle out of the hole, and finally disassembling and dismembering the main beam II 21 and the main beam I23, and sequentially transporting the saddle out of the hole;
Step six, dismantling the main drive and the cutterhead of the TBM host, namely cutting and dismembering the steel structure and the motor reducer at the upper part of the main drive 24 in sequence from top to bottom by adopting a sequence from top to bottom, and transferring dismantled parts to the outside of a transport hole on a plate vehicle by utilizing a lifting frame;
and seventh, grouting reinforcement is carried out on the top areas of the cutterhead and the shield, namely a plurality of groups of grouting hole groups are drilled on the tops of the cutterhead 25 and the shield 1, the grouting hole groups are distributed in a quincuncial shape, each grouting hole group comprises a plurality of grouting holes, the grouting holes are distributed along the circumferential direction of the tunnel 3, a second grouting anchor rod is inserted into each grouting hole, cement grouting is carried out by utilizing the second grouting anchor rod, grouting reinforcement is carried out on the top broken surrounding rock areas of the cutterhead 25 and the shield 1, and disassembly is completed.
The invention initiates a method for detaching the shield in situ, integrally welds the top shield, the side shield and the bottom shield by adopting the section steel before detaching the shield, and reserves the shield as a permanent support body instead of detaching the shield, and then cooperates with various hoisting equipment to realize safe and efficient detachment of the shield in situ in the TBM hole, fully ensures the stability of surrounding rocks of the hole, greatly reduces construction risk, effectively ensures construction safety and construction progress, obtains good engineering effect and has stronger reference function on similar engineering.
In step 102, the steel arch without concrete spraying is a steel arch with a top arch within a range of 150-270 degrees, and M35 mortar with a thickness of 20cm can be sprayed for sealing.
In the second step, after the surrounding rock steel support body is formed, a guide seat, an oil cylinder, a pipeline and the like in the shield 1 need to be dismantled to be used as a working space for cutting main driving.
In the third step, the first track beam 9 is made of HW175 section steel, two track beams are arranged on the top of the tunnel in a fitting mode, the distance between the two track beams is 1.8m, and the length of each track beam is 36m.
In step 401, the design bearing capacity of a single fixed lifting point is 5t, and the lifting point test detection is the same as that of the host dismounting lifting facility. 8 6t chain blocks are arranged on the fixed lifting points and serve as lifting equipment, the chain blocks are mainly used for lifting the rear supporting upper equipment and the steel structure, when the rear supporting lower equipment is dismounted, lifting lugs or track beams are welded on the rear supporting frame structure, and a chain block or a manual block is arranged for lifting the lower equipment.
In step 402, when the lower equipment matched with the rear is dismantled, lifting lugs or track beams can be welded on the frame structure matched with the rear, and a chain block or a manual hoist is installed to hoist the lower equipment.
In step three and step 401, in the process of installing the TBM host and the bridge area lifting device and installing the TBM post-supporting lifting device, in order to ensure the subsequent normal use of the TBM host and the bridge area lifting device and the TBM post-supporting lifting device, the TBM host and the bridge area lifting device and the TBM post-supporting lifting device need to be installed and tested in the installation process, so that the TBM host and the bridge area lifting device and the TBM post-supporting lifting device can be simultaneously carried out in the installation process, and the installation and test processes can also be repeatedly carried out.
In the fourth step, the fifth step and the sixth step, when the main beam and the rear support of the TBM host machine, and the main drive of the TBM host machine and the dismantling of the cutterhead are sequentially carried out according to the construction sequence, and when the TBM rear supporting equipment is dismantled, the main beam and the rear support of the TBM host machine in the fifth step can be dismantled simultaneously, so that the dismantling time is further saved, and the dismantling efficiency is improved.
In the sixth step, when the upper part of the main drive 24 is removed, the motor speed reducer, the gear and the bearing, the top steel structure of the rear end of the main drive, the top steel structure of the front end of the main drive, the adapter steel structure, the cutter head connecting bolt, the bearing, the motor speed reducer, the gear and the bearing are removed in sequence, and the removed parts are sequentially transferred to the outside of the transport hole on the scooter by using the hoisting frame, and when the cutter head 25 and the rest part of the main drive 24 are removed subsequently, the top steel structure of the cutter head, the middle and upper parts of the main drive, the middle and lower parts of the cutter head and the bottoms of the cutter head 25 and the main drive 24 are removed sequentially.
In the sixth step, the electric and hydraulic components in the shield are to be removed before the cutterhead and the main driving base are removed. Removing the side shield oil cylinder and the wedge oil cylinder, removing the wedge base to enlarge the working space, and removing the bottom connecting pin shaft. And after the cutterhead and the main driving base are dismembered into small blocks in situ, the cutterhead and the main driving base are hoisted and transported out of the tunnel.
And step seven, after the disassembly work is finished, steel structures such as rib plates of the lining section and the like are cut off from the inner side of the shield, and secondary lining and consolidation grouting are performed in time if necessary.
In the process of dismantling the TBM rear supporting equipment, as the steel structure size of the TBM rear supporting connecting bridge is 5.5m wide by 3.9m high, the steel structure size of the spraying mixing bridge is 5.5m wide by 3.8m high, and the steel structure size of the trolley is 5.0m wide by 3.6m high, when the rear supporting steel structure adopts integral transportation, when the wind belt distributed along the line and the belt slag discharging system are dismantled, the belt slag discharging system is not dismantled, the power supply and drainage pipes and the transformer are not dismantled, the illumination along the line is powered off, the illumination, the drainage pump station, the water tank and the like are not required to be dismantled, the air is stopped for a long time, the risk of crushing the wind belt due to water seepage of the hole wall exists, the rear supporting and the main machine are synchronously dismantled once ventilation is stopped, harmful gas generated in the electric welding operation cannot be discharged, meanwhile, the temperature of the working face is increased, and constructors are required to be completely evacuated. In consideration of the above factors, after the rear matched steel structure is decomposed, the steel structure connecting bolts are disassembled and decomposed or are planed at the welding seam to be decomposed and transported out of the hole.
In the fourth step, in the process of removing the supporting equipment after TBM, the main hole continuous belt conveyor, the support hole fixed belt conveyor, the hole external slag-turning belt conveyor and the power supply system are required to be removed synchronously. The dismantling of the belt conveyor system mainly comprises dismantling of an out-hole slag-turning belt conveyor, a support hole fixing belt conveyor and a main hole continuous belt system, wherein the process is as follows.
Main hole continuous belt conveyor dismantling
The belt is removed, namely the total length of the main hole belt is about 36km, and the belt is wound up by a winding machine and then is conveyed out of the hole. After the TBM is stopped and has the condition of dismantling the belt conveyor, the belt is pulled out from the position of the head part of the belt bin to be cut off, 2 belt coiling machines are placed at the head part of the belt bin, the belt is firstly coiled to the former belt coiling machine by utilizing the common driving of the former belt coiling machine and the driving motor, and after the belt is coiled into a large coil of 540 meters, the belt is conveniently transported out of a tunnel, and then the belt is divided into two coils of 270m by utilizing the latter belt coiling machine, so that the requirement of transporting the large coil of 540m can not be met due to the small supporting tunnel transportation space.
And (3) dismantling the belt conveyor support, namely dismantling the belt conveyor support from inside to outside after the winding of the main hole continuous belt is completed. A simple belt conveyor support dismantling working platform is installed on an internal combustion locomotive, and the belt conveyor support, a carrier roller, a chain and the like are dismantled manually.
And the middle relay driving station is dismantled, namely, after the belt on the main hole continuous belt is received into the middle driving relay station, the middle driving relay station system of the belt conveyor is dismantled. And welding lifting lugs on the steel arch centering which is arranged in the middle driving relay station area, installing a chain block, and dismantling the middle driving relay station.
And (3) dismantling the main drive and the belt bin, namely dismantling the belt bin and the main drive station system which are arranged at the intersection section of the main hole after the main hole continuous belt is completely rolled. The main driving station and the belt bin are to be dismantled by manually matching with a 25t gantry crane and a 25t automobile crane which are arranged on the intersecting section of the main tunnel.
Removing support hole fixing belt conveyor and hole outer slag transferring belt conveyor
And (3) dismantling the belt, namely enabling the total length of the supporting hole belt to be about 5.2km, wherein the belt winding mode is consistent with the main hole continuous belt winding mode. Considering that the gradient of the support hole is larger, the lower belt is easy to slide down in the belt winding process, and the upper belt and the lower belt are required to be wound separately in order to ensure construction safety. Before the belt is wound, the upper belt is fixed at the tensioning station by adopting a fixing clamp, the lower belt is fixed section by section, and after the belt is fixed, the belt is cut off from the tail parts of the tensioning platform of the hole belt conveyor and the supporting hole belt return station respectively. And after the belt is cut off, the upper belt is wound by adopting the same method as the main hole continuous belt, after the upper belt is wound to the hole tensioning platform, the rest upper belt and the lower belt connector are subjected to butt joint vulcanization, and then the lower belt winding is completed. When the belt is wound, the belt is prevented from sliding downwards, the belt is fixed by the fixing clamp before cutting off after one roll of belt is wound, and the belt can be cut off after the belt is fixed.
And (3) dismantling the belt conveyor support, namely after the winding of the support hole belt is completed, starting to dismantle the belt conveyor support. The simple belt conveyor support dismantling working platform is installed on the forklift, and the belt conveyor support, the carrier roller, the chain and the like are dismantled manually.
And after the winding of the supporting hole belt is completed, the supporting hole belt driving station, the tensioning device, the outer truss of the hole, the slag transferring belt machine and the like are dismounted, and the structure is dismounted by adopting manual cooperation with a 25t automobile crane.
And finally, dismantling the power supply system, wherein the TBM power supply system dismantling task is to arrange 120 kV high-voltage cable with the length of about 20.4km on the right side of the wall of the hole in the hole entering direction and dismantle 120 kV high-voltage switch cabinet arranged at the intersection section of the main hole. After the TBM stops tunneling and has the power supply system dismantling condition, the power supply is firstly cut off, and the high-voltage cables are sequentially wound up from inside to outside and are transported out of the tunnel. When the 20kV high-voltage cable is wound, the high-voltage cable reel is placed on a scooter towed by an internal combustion locomotive, and the cable is wound by one reel manually. The 20kV high-voltage switch cabinet is disassembled by manually matching with a 25t automobile crane.
In this embodiment, in step 101, the circumferential distance between two adjacent first grouting anchors 2 is 0.5 m-1 m, the length of the first grouting anchor 2 is 2.0 m-6.0 m, the inclination angle of the first grouting anchor 2 is 10 ° to 45 °, the first grouting anchor 2 is inclined forward along the extending direction of the tunnel 3, the included angle between the first grouting anchors 2 at two sides is 120 ° to 150 °, and when cement slurry is injected by using the first grouting anchors 2, the grouting pressure is not more than 3MPa.
In the third embodiment, in the step three, derailment prevention steel plates are disposed at two ends of the first track beam 9.
In the third embodiment, the first track beam 9 is installed at the top of the tunnel 3 through a plurality of first installation members, the plurality of first installation members are uniformly distributed along the extending direction of the first track beam 9, four installation holes are formed in each lifting anchor point, and each first installation member comprises a first installation plate 10 arranged at the lifting anchor point, a first fixing anchor rod 11 arranged between the first installation plate 10 and the installation holes, and a rib plate 12 arranged on the first installation plate 10 and distributed on one side far from the first fixing anchor rod 11.
When in actual use, the upper end of the first track beam 9 is welded with the first fixed anchor rod 11 and the first mounting plate 10, one side of the first mounting plate 10 is welded with the first fixed anchor rod 11, the other side is additionally provided with the rib plate 12, and the two ends of the first track beam 9 are welded with derailment-preventing steel plates with the thickness of 16mm as plugs to prevent the lifting chain block pulley from derailing. 210 t chain block pulleys are arranged on each guide rail and used for hoisting and turning over each structural member. The diameter of the first fixed anchor rod 11 is phi 22, the cement cartridge/common mortar anchor rod with L=2.5m, the anchor rod is of a screw steel HRB400 level, the total length of the anchor rod is 2.5m, the exposed 0.5m, the rock-entering anchoring length is more than or equal to 2m, and the longitudinal arrangement interval of the anchor rod is 2m. And after the lifting appliance is installed and qualified through quality detection and dynamic and static load tests, the host machine is removed in sequence.
In this embodiment, in step 401, the fixed hanging point group includes four fixed hanging point groups distributed along the circumferential direction of the tunnel 3, the chain blocks 13 are mounted on the top of the tunnel 3 through second mounting pieces, the number of the second mounting pieces is equal to that of the chain blocks 13 and corresponds to that of the chain blocks one by one, each second mounting piece includes a second mounting plate 14 disposed at the fixed hanging point, a second fixing anchor 15 disposed between the second mounting plate 14 and the fixed hanging point, and two mounting anchors 16 disposed on the second mounting plate 14 and uniformly distributed on one side far from the second fixing anchor 15, one ends of the two mounting anchors 16 are fixed on the second mounting plate 14, and the chain blocks 13 are mounted between the other ends of the two mounting anchors 16.
In the sixth embodiment, the lifting frame is a door-shaped lifting frame, the lifting frame comprises a plurality of lifting frame bodies, the lifting frame bodies are distributed along the extending direction of the tunnel 3, a second track beam 26 is arranged among the lifting frame bodies, the lifting frame comprises a lifting cross beam 27 horizontally arranged and a supporting vertical beam 28 vertically arranged at the bottom of the lifting cross beam 27, the lifting cross beam 27 is connected with the supporting vertical beam 28 through bolts, an inclined support 29 is obliquely arranged between the lifting cross beam 27 and the supporting vertical beam 28, and the second track beam 26 is distributed at the bottom of the lifting cross beam 27.
As shown in fig. 6, a plurality of working platforms 32 are also horizontally disposed on the supporting vertical beams 28.
In the embodiment, in the seventh step, the included angle between the grouting holes at two sides is 180 degrees, the length of the second grouting anchor rod is 3.5m, the tail of the second grouting anchor rod is welded with the shield 1, and the distance between two adjacent grouting hole groups is 1.25 m-1.5 m.
The foregoing description is only a preferred embodiment of the present invention, and is not intended to limit the present invention, and any simple modification, variation and equivalent structural changes made to the above embodiment according to the technical substance of the present invention still fall within the scope of the technical solution of the present invention.

Claims (7)

1.一种破碎地层输水隧洞敞开式TBM留盾原位拆机方法,其特征在于,该方法包括以下步骤:1. A method for dismantling an open-type TBM in a broken stratum water delivery tunnel with shield left in situ, characterized in that the method comprises the following steps: 步骤一、护盾顶部塌腔回填并对破碎围岩注浆加固,过程如下:Step 1: Backfill the collapsed cavity at the top of the shield and reinforce the broken surrounding rock with grouting. The process is as follows: 步骤101、拆机前先对护盾(1)顶部塌腔进行喷混回填;然后利用手风钻在护盾(1)尾部钻设多个第一注浆锚杆(2),多个所述第一注浆锚杆(2)沿隧道(3)的周向方向布设,且多个所述第一注浆锚杆(2)均布设在所述护盾(1)的顶部;利用第一注浆锚杆(2)向护盾(1)和刀盘的顶部注入水泥浆,对护盾(1)和刀盘顶部的破碎围岩进行注浆加固;Step 101: Before dismantling the machine, the collapsed cavity at the top of the shield (1) is backfilled with spray mix; then, a plurality of first grouting anchor rods (2) are drilled at the tail of the shield (1) using a hand drill, and the plurality of first grouting anchor rods (2) are arranged along the circumferential direction of the tunnel (3), and the plurality of first grouting anchor rods (2) are all arranged at the top of the shield (1); cement slurry is injected into the top of the shield (1) and the cutter head using the first grouting anchor rods (2), and the broken surrounding rock at the top of the shield (1) and the cutter head is reinforced by grouting; 步骤102、待注浆加固完成后,利用钢筋和型钢连接护盾(1)尾部的钢拱架,并对护盾(1)尾部未喷射混凝土封闭的钢拱架进行喷射混凝土封闭;Step 102, after the grouting reinforcement is completed, the steel arch frame at the rear of the shield (1) is connected with steel bars and steel sections, and the steel arch frame at the rear of the shield (1) that is not sealed with sprayed concrete is sealed with sprayed concrete; 步骤二、护盾整体焊接:先利用连接钢板(4)将侧护盾(5)和顶护盾(6)的接缝处连接;再利用连接型钢(31)将顶护盾(6)之间、侧护盾(5)和顶护盾(6)之间、以及侧护盾(5)和底护盾(7)之间焊接连接,形成围岩钢支撑体;Step 2: Welding the shield as a whole: first, use the connecting steel plate (4) to connect the joints of the side shields (5) and the top shield (6); then use the connecting steel (31) to weld the top shields (6), the side shields (5) and the top shield (6), and the side shields (5) and the bottom shield (7) to form a surrounding rock steel support body; 步骤三、TBM主机及桥架区域起吊设施安装:在TBM主机及桥架区域对应的隧洞顶部打设两组起吊锚点,每组所述起吊锚点均沿所述隧道(3)的延伸方向均匀布设;利用所述起吊锚点安装第一轨道梁(9),并在第一轨道梁(9)上安装起吊手拉葫芦滑车,完成TBM主机及桥架区域起吊设施的安装;Step 3: Installation of lifting facilities in the TBM mainframe and bridge area: two groups of lifting anchor points are set on the top of the tunnel corresponding to the TBM mainframe and bridge area, and each group of lifting anchor points is evenly arranged along the extension direction of the tunnel (3); the first track beam (9) is installed using the lifting anchor points, and a lifting hand chain hoist pulley is installed on the first track beam (9), thereby completing the installation of the lifting facilities in the TBM mainframe and bridge area; 步骤四、TBM后配套起吊设施安装与TBM后配套设备拆除,过程如下:Step 4: Installation of TBM rear supporting lifting facilities and removal of TBM rear supporting equipment. The process is as follows: 步骤401、同时在TBM后配套区域对应的隧洞顶部打设两组固定吊点组,每组所述固定吊点组均沿所述隧道(3)的周向方向均匀布设;在所述固定吊点组上安装多个手拉葫芦(13),完成TBM后配套区域起吊设施的安装;安装完成后依次进行TBM后配套上层设备的拆除并运出洞外;Step 401: simultaneously, two groups of fixed lifting point groups are set on the top of the tunnel corresponding to the TBM rear supporting area, and each group of the fixed lifting point groups is evenly arranged along the circumferential direction of the tunnel (3); a plurality of hand chain hoists (13) are installed on the fixed lifting point groups to complete the installation of the lifting facilities in the TBM rear supporting area; after the installation is completed, the TBM rear supporting upper equipment is dismantled in sequence and transported out of the tunnel; 步骤402、在TBM后配套设备的框架结构上焊接吊耳并安装导链;安装完成后进行TBM后配套下层设备的拆除并运出洞外;Step 402, welding the lifting lugs on the frame structure of the TBM rear supporting equipment and installing the guide chain; after the installation is completed, dismantling the TBM rear supporting lower equipment and transporting it out of the cave; 步骤403、TBM后配套设备拆除完成后,利用TBM后配套起吊设施依次将TBM后配套框架结构拆除并运出洞外;Step 403: After the TBM rear supporting equipment is dismantled, the TBM rear supporting frame structure is dismantled and transported out of the tunnel in sequence using the TBM rear supporting lifting facilities; 步骤五、拆除TBM主机的主梁和后支撑,过程如下:Step 5: Remove the main beam and rear support of the TBM mainframe. The process is as follows: 步骤501、在主梁(17)的底部设置多个支撑柱(18),多个所述支撑柱(18)沿所述主梁(17)的延伸方向布设;主梁(17)的顶部利用钢丝绳和起吊手拉葫芦滑车连接;Step 501: a plurality of support columns (18) are arranged at the bottom of the main beam (17), and the plurality of support columns (18) are arranged along the extension direction of the main beam (17); the top of the main beam (17) is connected with a steel wire rope and a lifting hand chain hoist pulley; 步骤502、调节所述钢丝绳的长度,利用起吊手拉葫芦将主梁(17)和后支撑(22)拉紧后,拆除主推油缸(19)和撑靴(20)并运出洞外;Step 502, adjusting the length of the steel wire rope, tightening the main beam (17) and the rear support (22) using a lifting hand chain hoist, removing the main push cylinder (19) and the support shoe (20) and transporting them out of the cave; 步骤503、拆除后支撑(22)和主梁二(21)之间的连接螺栓,将后支撑(22)卸下翻转后放置在隧道(3)的底部,在隧道(3)内将后支撑(22)分割肢解后依次运出洞外;其中,所述主梁(17)包括主梁一(23)和主梁二(21);Step 503, remove the connecting bolts between the rear support (22) and the second main beam (21), remove the rear support (22), turn it over and place it at the bottom of the tunnel (3), cut and dismember the rear support (22) in the tunnel (3) and transport them out of the tunnel in sequence; wherein the main beam (17) includes the first main beam (23) and the second main beam (21); 步骤504、将鞍架分解拆除并依次运出洞外,最后将主梁二(21)和主梁一(23)拆卸肢解后依次运出洞外;Step 504, disassemble and remove the saddle frame and transport them out of the cave in sequence, and finally disassemble and dismember the second main beam (21) and the first main beam (23) and transport them out of the cave in sequence; 步骤六、拆除TBM主机的主驱动和刀盘:先采用由后向前、由上至下的顺序依次对主驱动(24)上部的钢结构和电机减速机进行切割肢解拆除,并利用吊装架将拆除的部件依次转运至板车上运出洞外;然后采用由上至下、由后向前的顺序依次对刀盘(25)和主驱动(24)剩余部分进行切割并利用吊装架将切割后的部件依次转运至板车上运出洞外;Step 6: Dismantle the main drive and cutterhead of the TBM main machine: First, cut and dismantle the steel structure and motor reducer on the upper part of the main drive (24) in order from back to front and from top to bottom, and use a hoisting frame to transfer the removed parts to a cart and transport them out of the hole; then, cut the remaining parts of the cutterhead (25) and the main drive (24) in order from top to bottom and from back to front, and use a hoisting frame to transfer the cut parts to a cart and transport them out of the hole; 步骤七、对刀盘和护盾的顶部区域进行注浆加固:在刀盘(25)和护盾(1)的顶部钻设多组注浆孔组,多组所述注浆孔组呈梅花型布设,每组所述注浆孔组均包括多个注浆孔,多个所述注浆孔沿所述隧道(3)的周向方向布设;在所述注浆孔内插入第二注浆锚杆,并利用第二注浆锚杆进行水泥注浆,将刀盘(25)和护盾(1)的顶部破碎围岩区域进行注浆加固,完成拆机。Step 7: Grouting reinforcement of the top area of the cutter disc and the shield: Drill multiple groups of grouting holes on the top of the cutter disc (25) and the shield (1), the multiple groups of grouting holes are arranged in a plum blossom shape, each group of the grouting holes includes multiple grouting holes, and the multiple grouting holes are arranged along the circumferential direction of the tunnel (3); insert a second grouting anchor rod into the grouting hole, and use the second grouting anchor rod to perform cement grouting to grout the top broken surrounding rock area of the cutter disc (25) and the shield (1), and complete the dismantling of the machine. 2.根据权利要求1所述的一种破碎地层输水隧洞敞开式TBM留盾原位拆机方法,其特征在于:步骤101中,相邻两个所述第一注浆锚杆(2)之间的环向间距为0.5m~1m,所述第一注浆锚杆(2)的长度为2.0m~6.0m,所述第一注浆锚杆(2)的倾斜角度为10°~45°,且所述第一注浆锚杆(2)沿隧道(3)的延伸方向向前倾斜;位于两侧的所述第一注浆锚杆(2)之间的夹角为120°~150°;利用第一注浆锚杆(2)注入水泥浆时,注浆压力不大于3MPa。2. The method for in-situ dismantling of an open-type TBM with shield in a broken stratum water conveyance tunnel according to claim 1, characterized in that: in step 101, the circumferential spacing between two adjacent first grouting anchor rods (2) is 0.5m-1m, the length of the first grouting anchor rod (2) is 2.0m-6.0m, the inclination angle of the first grouting anchor rod (2) is 10°-45°, and the first grouting anchor rod (2) is inclined forward along the extension direction of the tunnel (3); the angle between the first grouting anchor rods (2) on both sides is 120°-150°; when cement slurry is injected using the first grouting anchor rod (2), the grouting pressure is not greater than 3MPa. 3.根据权利要求1所述的一种破碎地层输水隧洞敞开式TBM留盾原位拆机方法,其特征在于:步骤三中,所述第一轨道梁(9)的两端均设置有防脱轨钢板。3. The method for in-situ dismantling of an open-type TBM with shield in a broken stratum water conveyance tunnel according to claim 1, characterized in that: in step 3, both ends of the first track beam (9) are provided with anti-derailment steel plates. 4.根据权利要求3所述的一种破碎地层输水隧洞敞开式TBM留盾原位拆机方法,其特征在于:步骤三中,所述第一轨道梁(9)通过多个第一安装件安装在隧道(3)的顶部,多个所述第一安装件沿所述第一轨道梁(9)的延伸方向均匀布设;每个所述起吊锚点上均打设有四个安装孔,所述第一安装件包括设置在所述起吊锚点处的第一安装板(10)、设置在所述第一安装板(10)和所述安装孔之间的第一固定锚杆(11)、以及设置在所述第一安装板(10)上且布设在远离所述第一固定锚杆(11)一侧的筋板(12)。4. The method for in-situ dismantling of an open-type TBM with shield retained in a broken stratum water conveyance tunnel according to claim 3, characterized in that: in step 3, the first track beam (9) is installed on the top of the tunnel (3) through a plurality of first mounting parts, and the plurality of first mounting parts are evenly arranged along the extension direction of the first track beam (9); four mounting holes are drilled on each of the lifting anchor points, and the first mounting parts include a first mounting plate (10) arranged at the lifting anchor point, a first fixing anchor rod (11) arranged between the first mounting plate (10) and the mounting hole, and a rib plate (12) arranged on the first mounting plate (10) and arranged on a side away from the first fixing anchor rod (11). 5.根据权利要求1所述的一种破碎地层输水隧洞敞开式TBM留盾原位拆机方法,其特征在于:步骤401中,所述固定吊点组包括四个沿所述隧道(3)的周向方向布设的所述固定吊点组;所述手拉葫芦(13)通过第二安装件安装在隧道(3)的顶部,所述第二安装件的数量和所述手拉葫芦(13)的数量相等且一一对应;所述第二安装件均包括设置在所述固定吊点的第二安装板(14)、设置在所述第二安装板(14)和所述固定吊点之间的第二固定锚杆(15)、以及两个均设置在所述第二安装板(14)上且均布设在远离所述第二固定锚杆(15)一侧的安装锚杆(16);两个所述安装锚杆(16)的一端固定在所述第二安装板(14)上,两个所述安装锚杆(16)的另一端之间安装手拉葫芦(13)。5. The method for in-situ dismantling of an open-type TBM with shield retained in a broken stratum water conveyance tunnel according to claim 1, characterized in that: in step 401, the fixed lifting point group includes four fixed lifting point groups arranged along the circumferential direction of the tunnel (3); the hand chain hoist (13) is installed on the top of the tunnel (3) through a second mounting member, and the number of the second mounting members is equal to the number of the hand chain hoists (13) and corresponds one to one; the second mounting members each include a second mounting plate (14) arranged at the fixed lifting point, a second fixed anchor rod (15) arranged between the second mounting plate (14) and the fixed lifting point, and two mounting anchor rods (16) both arranged on the second mounting plate (14) and arranged on a side away from the second fixed anchor rod (15); one end of the two mounting anchor rods (16) is fixed on the second mounting plate (14), and the hand chain hoist (13) is installed between the other ends of the two mounting anchor rods (16). 6.根据权利要求1所述的一种破碎地层输水隧洞敞开式TBM留盾原位拆机方法,其特征在于:步骤六中,所述吊装架为门字形吊装架,所述吊装架包括多个吊装架体,多个所述吊装架体沿所述隧道(3)的延伸方向布设,多个所述吊装架体之间设置有第二轨道梁(26);所述吊装架包括水平设置的吊装横梁(27)和竖向设置在所述吊装横梁(27)底部的支撑竖梁(28),所述吊装横梁(27)和所述支撑竖梁(28)之间通过螺栓连接,所述吊装横梁(27)和所述支撑竖梁(28)之间斜向设置有斜支撑(29);所述第二轨道梁(26)布设在所述吊装横梁(27)的底部。6. The method for in-situ dismantling of an open-type TBM with shield retained in a broken stratum water conveyance tunnel according to claim 1, characterized in that: in step 6, the hoisting frame is a gate-shaped hoisting frame, the hoisting frame comprises a plurality of hoisting frame bodies, the plurality of hoisting frame bodies are arranged along the extension direction of the tunnel (3), and a second track beam (26) is arranged between the plurality of hoisting frame bodies; the hoisting frame comprises a horizontally arranged hoisting cross beam (27) and a supporting vertical beam (28) vertically arranged at the bottom of the hoisting cross beam (27), the hoisting cross beam (27) and the supporting vertical beam (28) are connected by bolts, and an oblique support (29) is obliquely arranged between the hoisting cross beam (27) and the supporting vertical beam (28); the second track beam (26) is arranged at the bottom of the hoisting cross beam (27). 7.根据权利要求1所述的一种破碎地层输水隧洞敞开式TBM留盾原位拆机方法,其特征在于:步骤七中,位于两侧的所述注浆孔之间的夹角为180°;所述第二注浆锚杆的长度为3.5m,且所述第二注浆锚杆的尾部和护盾(1)焊接连接;相邻两组所述注浆孔组之间的间距为1.25m~1.5m。7. The method for in-situ dismantling of an open-type TBM with shield retained in a broken stratum water conveyance tunnel according to claim 1, characterized in that: in step 7, the angle between the grouting holes on both sides is 180°; the length of the second grouting anchor is 3.5m, and the tail of the second grouting anchor is welded to the shield (1); the spacing between two adjacent groups of grouting holes is 1.25m~1.5m.
CN202411789947.5A 2024-12-06 2024-12-06 In-situ disassembly method for broken stratum water delivery tunnel open type TBM shield Pending CN119664385A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202411789947.5A CN119664385A (en) 2024-12-06 2024-12-06 In-situ disassembly method for broken stratum water delivery tunnel open type TBM shield

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202411789947.5A CN119664385A (en) 2024-12-06 2024-12-06 In-situ disassembly method for broken stratum water delivery tunnel open type TBM shield

Publications (1)

Publication Number Publication Date
CN119664385A true CN119664385A (en) 2025-03-21

Family

ID=94994196

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202411789947.5A Pending CN119664385A (en) 2024-12-06 2024-12-06 In-situ disassembly method for broken stratum water delivery tunnel open type TBM shield

Country Status (1)

Country Link
CN (1) CN119664385A (en)

Similar Documents

Publication Publication Date Title
CN106698207B (en) The construction method of shield machine is disassembled in hole
CN109441459B (en) Earth pressure balance type shield split starting side unearthing construction method
CN110056362B (en) Shield receiving and lateral translation hoisting method in air duct of underground excavation station
CN110748349B (en) A double-split starting method for a double-track tunnel shield with small clearance
CN110145317B (en) Shield tunneling machine station-crossing construction method
CN114109415A (en) Construction method for disassembling tunnel of shield machine of non-expanding excavation chamber
CN111472797B (en) Implementation method for detaching TBM in hole
CN113446020B (en) Hole-expansion-free type in-hole disassembly method for open TBM host
CN110778320A (en) Synchronous excavation supporting construction method for three-step inverted arch of weak surrounding rock tunnel
CN110094214B (en) Construction method of secondary lining movable support system for shallow-buried underground excavation tunnel
CN111255469A (en) Modular disassembly construction method in closed narrow space of shield machine
CN112031791B (en) Disassembling method of shield machine in limited space
CN112796783B (en) A Construction Method for Segment Demolition in Underground Excavation Tunnels with Shield Tunneling in Advance
CN213269891U (en) Shield constructs quick-witted dismounting device
JP7236506B2 (en) Top-down Pipe Propulsion Construction Vertical Shaft Launching Device in Shield Tunnel and Construction Method Therefor
CN105970992B (en) Large section high inclination-angle tunnel type pile foundation construction process
CN213775382U (en) Split starting belt conveyor of shield machine
CN119664385A (en) In-situ disassembly method for broken stratum water delivery tunnel open type TBM shield
CN111946351B (en) Rapid excavation method for contact channel of hard rock stratum of rail transit
CN114033398A (en) Construction method for returning of low gravity center dragging method shield back matching trolley tunnel
CN210977480U (en) Double-split originating station structure of small-clear-distance double-line tunnel shield
CN113605905B (en) Construction method for nondestructive disassembly of shield machine in tunnel
CN112963015A (en) Tunnel dismantling construction method in collinear connection with existing subway line below
CN115163090B (en) Shield originating construction method, originating device and installation method thereof
CN116427942A (en) Nuclear power station drainage tunnel shield oblique starting method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination