CN119412079B - A method for oblique top selection of tunnels with uniform cross-section - Google Patents

A method for oblique top selection of tunnels with uniform cross-section Download PDF

Info

Publication number
CN119412079B
CN119412079B CN202510011979.0A CN202510011979A CN119412079B CN 119412079 B CN119412079 B CN 119412079B CN 202510011979 A CN202510011979 A CN 202510011979A CN 119412079 B CN119412079 B CN 119412079B
Authority
CN
China
Prior art keywords
support
arch
section
steel
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202510011979.0A
Other languages
Chinese (zh)
Other versions
CN119412079A (en
Inventor
刘世纲
邵春
王伟岩
徐宾宾
杨润来
余漾
徐远鹏
邱朋
王建军
张晓华
代浩
王晓姝
郭文静
陈浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
No 3 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
No 3 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, No 3 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN202510011979.0A priority Critical patent/CN119412079B/en
Publication of CN119412079A publication Critical patent/CN119412079A/en
Application granted granted Critical
Publication of CN119412079B publication Critical patent/CN119412079B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明涉及建筑施工领域,具体涉及一种等截面隧道斜交挑顶方法。等截面隧道相交位置采用异型拱架,每榀异形拱架根据与线路相交不同的角度,其结构形式均不同,同时通过斜撑和门架的设置保证斜交位置的结构稳定。本发明作为斜交等截面隧道挑顶支护结构,有效解决了等截面隧道斜交位置初期支护施工的问题,提高了施工质量,降低了施工安全风险。

The present invention relates to the field of building construction, and specifically to a method for obliquely crossing and top-lifting a tunnel of equal cross-section. Special-shaped arch frames are used at the intersection of equal-section tunnels, and each special-shaped arch frame has a different structural form according to the different angles of intersection with the line. At the same time, the structural stability of the oblique intersection position is ensured by the arrangement of diagonal braces and portal frames. As a top-lifting support structure for oblique equal-section tunnels, the present invention effectively solves the problem of initial support construction at the oblique intersection position of equal-section tunnels, improves construction quality, and reduces construction safety risks.

Description

Oblique crossing roof picking method for constant-section tunnel
Technical Field
The invention relates to the field of building construction, in particular to a method for obliquely crossing and jacking a tunnel with a uniform section.
Background
In the railway tunnel construction process, when tunnels with the same cross section are inclined, because the cross sections are the same, the stress structure at the inclined position is complex, deformation and collapse are easy to occur, the site construction needs cannot be met, the potential safety quality hazards of the construction are large, meanwhile, serious economic loss is easy to cause, and the potential hazards are buried for the subsequent railway operation traffic safety. The existing construction method is to finish excavation supporting according to the outline of an originally designed constant section tunnel, then perform expansion excavation treatment at the intersection position of two constant section tunnels to finish structure conversion, and the method needs to destroy the steel support at the vault position. However, the stress on the vault is concentrated, and once the steel support at the vault is broken, the situation of structural instability and tunnel collapse is very easy to occur.
Disclosure of Invention
The invention provides a method for obliquely jacking a uniform-section tunnel, which aims to solve the problem of construction of the oblique crossing position of the uniform-section tunnel, and provides a design of a supporting structure system of the oblique crossing jacking of the uniform-section tunnel.
The technical scheme adopted by the invention for realizing the purpose is that the invention provides a method for obliquely picking the top of a tunnel with a uniform cross section, which comprises the following steps:
Step 1, before two sections of inclined positions of a tunnel with equal cross section are excavated, surrounding rocks in the range of steps on a tunnel I with equal cross section are provided with advanced measures and grouting reinforcement treatment, and advanced supports are arranged above the surrounding rocks;
Step 2, after the advanced support construction is completed, tunnel excavation is carried out, concrete preliminary spraying is carried out after an upper step is excavated, and the upper step preliminary support is completed, wherein the method comprises four units, namely an upper step arch foot steel support, an upper step arch waist steel support, an upper step arch crown steel support and an upper step temporary vertical support steel support;
Step 3, suspending operation after finishing the primary support of the two arches of the upper step, starting diagonal bracing reinforcement construction, and reinforcing the load bearing capacity of the primary support right angle part of the upper step;
Step4, after the construction of the upper step is completed for the primary support of 6 arch frames, starting the construction of the lower step and completing the corresponding primary support construction, wherein the construction comprises two units of a lower step arch foot steel support and a lower step temporary vertical support steel support, and then synchronously propelling the upper step and the lower step;
step 5, excavating an inverted arch after the primary support of the lower step is completed by 3 arch frames, arranging the inverted arch only in the section at the diagonal position, and sealing the section steel arch frames into a ring by adopting the section steel arch frames when single excavation is not more than a threshold value;
Step 6, after the primary support of the inclined position paragraph is finished, the upper step and the lower step synchronously continue to construct forward for 10m according to the normal section and then pause operation, so that the lower step is ensured to be 10m away from the inclined position;
Step 7, a portal frame at an oblique position is constructed, wherein the portal frame consists of a vertical beam and a cross beam, the vertical beam and the cross beam are both composed of I-steel, the cross beam consists of 3 units, the vertical beam consists of 2 units, the vertical beam and the cross beam are connected through bolts, and the diagonal bracing of a tunnel I with a peer-to-peer section is required to be dismantled during portal frame construction;
step 8, after the portal frame is constructed, constructing an arc-shaped arch frame in the portal frame, wherein the upper part of the arc-shaped arch frame is provided with oblique I-steel which is connected with the portal frame in a welding mode;
Step 9, after the arc-shaped arch frame finishes supporting, tunneling of the equal-section tunnel II at the diagonal position is started, when the arch frame is arranged at intervals due to unequal distances between the left side and the right side, non-equidistant arrangement is adopted, and the temporary vertical supporting steel support of the upper step and the temporary vertical supporting steel support of the lower step of the initial supporting of the equal-section tunnel I in the range of the gate frame are required to be dismantled before tunneling;
and 10, strengthening monitoring measurement in the construction process, ensuring that the accumulated deformation of the primary support is not more than a threshold value, and ensuring that the deformation rate after the primary support is closed into a ring is not more than the threshold value, namely performing waterproof structure construction, and timely following subsequent lining construction.
The primary support comprises a section steel arch frame, longitudinal connecting steel bars, foot locking anchor pipes, system anchor rods, a steel bar net and sprayed concrete.
In the step 2, mechanical milling construction is adopted for tunnel excavation.
In the step 4, the left side and the right side of the lower step are excavated by stepping, and the stepping distance is 2 arch frames.
In the step 5, the threshold value of the single excavation distance of the inverted arch is 3m.
In the step 7, the portal frame adopts double-spliced I-steel.
In the step 9, the primary support arch frame of the constant-section tunnel I in the portal frame range is a vertical unit part of the special-shaped arch frame, namely an upper step temporary vertical support steel support and a lower step temporary vertical support steel support.
In the step 9, the primary support of the section is adjusted, the distance between the short side arches is 0.5m, and the distance between the long side arches is 1m.
Aiming at the construction of the tunnel diagonal position with the same section, the invention solves the problem of stable structure by adopting the measures of mechanical milling excavation, special-shaped arch support, temporary reinforcement of diagonal braces, reinforcement of double-spliced I20I-shaped steel portal frames, reinforcement of arc-shaped arch frames and the like, and displays that the accumulated maximum deformation sedimentation value is 2.4cm and the accumulated maximum deformation convergence value is 1.9cm according to the monitoring and measuring result, thereby ensuring the structural safety and reducing the construction safety risk.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for the description of the embodiments will be briefly described below, and it is obvious that the drawings described below are only some embodiments of the present invention, and other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
FIG. 1 is a schematic flow chart of the method for obliquely picking the top of the tunnel with the uniform section.
FIG. 2 is a schematic illustration of a cross-sectional tunnel of the present invention;
FIG. 3 is a schematic illustration of a cross section of a constant section tunnel I of the present invention;
FIG. 4 is a schematic diagram of a cross section of a constant section tunnel II according to the present invention;
In the figure, 1-advance support, 2A-upper step arch steel support, 2B-upper step arch steel support, 2C-upper step arch steel support, 2D-upper step temporary vertical support steel support, 3-upper step, 4-lower step, 5A-lower step arch steel support, 5B-lower step temporary vertical support steel support, 6-inverted arch, 7-foot locking anchor pipe, 8-cross beam, 9-diagonal support, 10-vertical beam and 11-arc arch.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
For the purpose of facilitating an understanding of the embodiments of the invention, reference will now be made to the drawings of several specific embodiments, examples of which are illustrated in the accompanying drawings and are not intended to limit the embodiments of the invention.
Example 1
As shown in fig. 1, a process flow diagram of a medium-section tunnel diagonal roof picking method in one embodiment includes:
step 1, before two sections of inclined positions of a tunnel with equal cross section are excavated, surrounding rocks in the range of a step 3 on a tunnel I with equal cross section are provided with advanced measures and grouting reinforcement treatment, and advanced supports 1 are arranged above the surrounding rocks;
Step 2, after the construction of the advanced support 1 is completed, tunnel excavation is carried out, concrete preliminary spraying is carried out after an upper step 3 is excavated, and the upper step preliminary support is completed, wherein the four units of an upper step arch foot steel support 2A, an upper step arch waist steel support 2B, an upper step arch crown steel support 2C and an upper step temporary vertical support steel support 2D are included;
Step 3, suspending operation after finishing the primary support of the two arch frames of the upper step 3, starting to carry out diagonal bracing 9 reinforcement construction, and reinforcing the load bearing capacity of the primary support right angle part of the upper step 3;
step 4, after the construction of the upper step 3 completes the primary support of 6 arch frames, starting the construction of the lower step 4 and completing the corresponding primary support construction, wherein the construction comprises two units of a lower step arch foot steel support 5A and a lower step temporary vertical support steel support 5B, and then synchronously propelling the upper step and the lower step;
step 5, excavating an inverted arch 6 after the primary support of the lower step 4 is completed by 3 arch frames, arranging the inverted arch 6 only on the section at the diagonal position, and sealing the section steel arch frames into a ring by adopting the section steel arch frames when single excavation is not more than a threshold value;
step 6, after the primary support of the inclined position section is completed, the upper step 3 and the lower step 4 synchronously continue to construct forward for 10m according to the normal section and then pause operation, so that the lower step is ensured to be 10m away from the inclined position;
Step 7, a portal frame at an oblique position is constructed, the portal frame is composed of a vertical beam 10 and a cross beam 8, the vertical beam 10 and the cross beam 8 are both composed of I-steel, the cross beam 8 is composed of 3 units, the vertical beam 10 is composed of 2 units, the vertical beam 10 and the cross beam 8 are connected through bolts, and the diagonal bracing 9 of a tunnel I with a peer-to-peer section is required to be dismantled during portal frame construction;
step 8, after the portal frame is constructed, constructing an arc-shaped arch frame 11 in the portal frame, wherein the upper part of the arc-shaped arch frame is provided with oblique I-steel which is connected with the portal frame in a welding mode;
Step 9, after the arc-shaped arch 11 finishes supporting, tunneling of the equal-section tunnel II at the diagonal position is started, when the distance between the left side and the right side of the adjusting section is set, non-equidistant setting is adopted until the adjustment is finished, and the upper step temporary vertical supporting steel support 2D and the lower step temporary vertical supporting steel support 5B of the initial supporting of the equal-section tunnel I in the range of the gate frame are required to be dismantled before tunneling;
and 10, strengthening monitoring measurement in the construction process, ensuring that the accumulated deformation of the primary support is not more than a threshold value, and ensuring that the deformation rate after the primary support is closed into a ring is not more than the threshold value, namely performing waterproof structure construction, and timely following subsequent lining construction.
The primary support comprises a section steel arch frame, longitudinal connecting steel bars, foot locking anchor pipes, system anchor rods, a steel bar net and sprayed concrete.
The portal adopts double-spliced I-steel, namely the flange plates are welded into a whole by adopting the same I-steel.
And the initial support arch frame of the constant-section tunnel I in the portal frame dismantling range is an upper step temporary vertical support steel support 2D and a lower step temporary vertical support steel support 5B part of the initial support of the constant-section tunnel I.
The arches of the constant-section tunnel II are arranged in a non-equidistant mode, namely, the distance between the short side arches of the adjusting section is 0.5m, and the distance between the long side arches is 1m.
The invention solves the problem of stable structure by adopting the measures of mechanical milling excavation, special-shaped arch support, temporary reinforcement of diagonal braces, reinforcement of double-spliced I20I-shaped steel portal frames, reinforcement of arc-shaped arch frames and the like aiming at the construction of the diagonal positions of tunnels with the same section, ensures the structural safety according to the monitoring and measuring results, and reduces the construction safety risk.
The following describes an application scenario of the present invention, fig. 2 is a schematic view of a diagonal plane of a tunnel with a uniform section of the present invention, fig. 3 is a schematic view of a cross section I of a tunnel with a uniform section of the present invention, and fig. 4 is a schematic view of a cross section II of a tunnel with a uniform section of the present invention, which specifically comprises the following steps:
Step 1, setting a phi 60mm advanced middle pipe shed, 9 m/root, with a lap joint length of 3m and a pipe shed circumferential spacing of 50cm in the range of a step 3 on a equal section tunnel I before the two equal section tunnels are excavated in the oblique crossing position paragraphs, controlling the external inserting angle of the pipe shed to be 1-3 degrees, and excavating after drilling and verifying grouting effects;
Step 2, excavating by adopting a two-step reserved core soil milling excavation method, wherein the excavation distance is not more than 2 arch frames distance in each cycle, after the upper step 3 is excavated, the upper step is closed by adopting sprayed concrete with the thickness of 5cm, the upper step is reinforced and supported by adopting I18 steel arch frames, the spacing is 0.8M, the method comprises four units of an upper step arch foot steel support 2A, an upper step arch waist steel support 2B, an upper step arch foot steel support 2C and an upper step temporary vertical support steel support 2D, all the units are connected by adopting M27 high-strength bolts, the arch frames are reinforced and connected by adopting phi 22mm screw steel bars, meanwhile, the construction and grouting reinforcement of a locking foot anchor pipe are enhanced, and the locking foot is a phi 42mm steel flower pipe with the length of 4M/root;
Step 3, suspending operation after finishing the primary support of the two arches of the upper step 3, starting diagonal bracing reinforcement construction, wherein the diagonal bracing is an I18-shaped steel arch, and reinforcing the load bearing capacity of the primary support right-angle part of the upper step 3;
Step 4, after the construction of the upper step 3 completes the primary support of 6 arch frames, starting the construction of the lower step 4 and completing the corresponding primary support construction, wherein the construction comprises a lower step arch foot steel support 5A and a lower step temporary vertical support steel support 5B, then synchronously propelling the upper step and the lower step, wherein the footage of the lower step is not more than 2 arch frames in each cycle, and the arch feet of the upper step are strictly forbidden to be suspended;
step 5, excavating an inverted arch after the primary support of the lower step 4 is completed by 3 arch frames, wherein the inverted arch frames are connected with the arch frames of the lower step 4 by bolts, and the inverted arch6 is arranged only in a section at an oblique crossing position, and the single excavation is not more than 3m;
Step 6, after the primary support passport of the diagonal position paragraph is finished, the upper step 3 and the lower step 4 synchronously continue to be constructed forward for 10m according to the normal section and then pause operation, so that the position of the lower step away from the diagonal position is ensured to be 10m;
Step 7, before tunneling a tunnel II with the same cross section, constructing a portal frame at an oblique crossing position, wherein the portal frame consists of a vertical beam 10 and a cross beam 8, the vertical beam 10 and the cross beam 8 are both composed of I20I-steel, the cross beam 8 consists of 3 units, the vertical beam 10 consists of 2 units, the vertical beam 10 and the cross beam 8 are connected by bolts, and when the portal frame is constructed, the oblique support of the tunnel I with the same cross section is required to be dismantled, and in the dismantling process, the protection of a connected arch frame is paid attention;
Step 8, after the construction of the portal frame is completed, constructing an arc-shaped arch frame 11 in the portal frame, wherein the upper part of the arc-shaped arch frame 11 is provided with oblique I-steel which is connected with the portal frame, and the connection mode of the position is welding;
And 9, after the arc-shaped arch 11 finishes supporting, tunneling of the equal-section tunnel II at the diagonal position is started, the section is adjusted, the arch spacing of the short sides is 0.5m, the arch spacing of the long sides is 1m, and the upper step temporary vertical supporting steel support 2D and the lower step temporary vertical supporting steel support 5B of the initial supporting of the equal-section tunnel I in the door frame range are required to be dismantled before tunneling, and mechanical dismantling is adopted for dismantling.
The foregoing disclosure is illustrative of the present invention and is not to be construed as limiting the scope of the invention, which is defined by the appended claims.

Claims (3)

1.一种等截面隧道斜交挑顶方法,其特征是,等截面隧道相交位置采用异型拱架,每榀异形拱架根据与线路相交不同的角度,其结构形式均不同,同时通过斜撑和门架的设置保证斜交位置的结构稳定,具体包括以下步骤:1. A method for obliquely crossing the top of a tunnel with a uniform cross section, characterized in that a special-shaped arch frame is used at the intersection of the tunnels with a uniform cross section, and each special-shaped arch frame has a different structural form according to the different angles of intersection with the line, and the structural stability of the oblique intersection position is ensured by the arrangement of diagonal braces and portal frames, and specifically comprises the following steps: 步骤1,两个等截面隧道斜交位置段落开挖前,对等截面隧道I上台阶(3)范围内的围岩设置超前措施并注浆加固处理,在所述围岩上方设置超前支护(1);具体的:对等截面隧道I上台阶(3)范围内设置φ60mm超前中管棚,9m/根,搭接长度为3m,管棚环向间距50cm,管棚外插角控制在1°至3°,施工完成后,钻孔验证注浆效果后再进行开挖;Step 1: Before excavating the oblique intersection section of two equal-section tunnels, advance measures are set for the surrounding rock within the upper step (3) of the equal-section tunnel I and grouting reinforcement treatment is carried out, and an advance support (1) is set above the surrounding rock; specifically: a φ60mm advance middle pipe shed is set within the upper step (3) of the equal-section tunnel I, 9m/root, lap length of 3m, annular spacing of 50cm, and the external insertion angle of the pipe shed is controlled at 1° to 3°. After the construction is completed, drilling is performed to verify the grouting effect before excavation; 步骤2,所述超前支护(1)施工完成后,进行隧道开挖,开挖上台阶(3)后进行混凝土初喷,完成上台阶初期支护,包含:上台阶拱脚钢支撑(2A)、上台阶拱腰钢支撑(2B)、上台阶拱顶钢支撑(2C)以及上台阶临时竖撑钢支撑(2D)四个单元;具体的:开挖采用两台阶预留核心土加铣挖法施工,每循环开挖距离不大于2榀拱架距离,上台阶3开挖完成后,及时采用5cm厚的喷射混凝土完成封闭,上台阶采用I18型钢拱架加强支护,间距0.8m,各单元之间采用M27高强螺栓连接,拱架之间采用φ22mm螺纹钢筋加强连接,同时加强锁脚锚管施工并注浆加固,锁脚为φ42mm钢花管,长度4m/根;Step 2, after the construction of the advanced support (1) is completed, the tunnel is excavated, and after the upper step (3) is excavated, the concrete is initially sprayed to complete the initial support of the upper step, which includes: the upper step arch foot steel support (2A), the upper step arch waist steel support (2B), the upper step arch top steel support (2C) and the upper step temporary vertical support steel support (2D) four units; specifically: the excavation adopts the two-step reserved core soil plus milling excavation method, and the excavation distance of each cycle is not more than the distance of 2 arch frames. After the excavation of the upper step 3 is completed, 5 cm thick sprayed concrete is used in time to complete the closure. The upper step adopts I18 steel arch frame to strengthen the support, with a spacing of 0.8m. M27 high-strength bolts are used to connect the units, and φ22mm threaded steel bars are used to strengthen the connection between the arch frames. At the same time, the construction of the locking foot anchor pipe is strengthened and grouting is reinforced. The locking foot is a φ42mm steel flower pipe with a length of 4m/root; 步骤3,完成上台阶(3)的初期支护两榀拱架后暂停作业,开始进行斜撑(9)加固施工,斜撑(9)为I18型钢拱架,加强上台阶(3)的初期支护直角部位的承受荷载能力;Step 3, after completing the initial support of the upper step (3) with two arch frames, suspend the operation and start the reinforcement construction of the diagonal brace (9), the diagonal brace (9) is an I18 steel arch frame, which strengthens the load bearing capacity of the right-angled part of the initial support of the upper step (3); 步骤4,上台阶(3)施工完成6榀拱架距离的初期支护之后,开始下台阶(4)施工并完成相应初期支护施工,包含:下台阶拱脚钢支撑(5A)和下台阶临时竖撑钢支撑(5B)两个单元,然后同步推进上、下台阶;所述下台阶左右两侧要错步开挖,错步距离不大于2榀拱架,上台阶拱脚严禁悬空;Step 4, after the upper step (3) is constructed to complete the initial support of 6 arch frames, the lower step (4) is constructed and the corresponding initial support construction is completed, including: two units: the lower step arch foot steel support (5A) and the lower step temporary vertical support steel support (5B), and then the upper and lower steps are promoted synchronously; the left and right sides of the lower step should be staggered for excavation, and the staggered distance should not be greater than 2 arch frames, and the upper step arch foot is strictly prohibited from being suspended in the air; 步骤5,下台阶(4)初期支护完成3榀拱架之后,开挖仰拱(6),仅斜交位置段落设置仰拱(6),且单次开挖不大于3m阈值,采用型钢拱架封闭成环;Step 5, after the initial support of the lower step (4) is completed with three arch frames, the inverted arch (6) is excavated, and the inverted arch (6) is set only in the oblique position section, and the single excavation is not greater than the threshold of 3m, and the steel arch frame is used to close the ring; 步骤6,斜交位置段落的初期支护完成后,上台阶(3)和下台阶(4)按正常断面同步继续往前施工10m后暂停作业,保证下台阶离斜交位置为10m;Step 6: After the initial support of the oblique intersection section is completed, the upper step (3) and the lower step (4) are synchronously constructed according to the normal section for 10m and then suspended to ensure that the lower step is 10m away from the oblique intersection; 步骤7,施作斜交位置的门架,门架施工时需要对等截面隧道I的斜撑(9)进行拆除;Step 7, constructing a portal frame at an oblique position. When constructing the portal frame, the oblique support (9) of the equal-section tunnel I needs to be removed; 步骤8,门架施作完成后,施工门架内的弧形拱架(11),弧形拱架上部设置斜向工字钢同门架连接,连接方式采用焊接;Step 8, after the construction of the portal frame is completed, an arc-shaped arch frame (11) is constructed inside the portal frame, and an oblique I-beam is arranged on the upper part of the arc-shaped arch frame to be connected with the portal frame, and the connection method is welding; 步骤9,弧形拱架(11)完成支护后,开始斜交位置等截面隧道II的掘进,调整段落由于左右侧距离不等,拱架间距设置时,采用非等距离设置,直至调整完成,掘进前对门架范围的等截面隧道I的初期支护下台阶临时竖撑钢支撑(5B)、上台阶临时竖撑钢支撑(2D)进行拆除;所述门架范围的等截面隧道I的初期支护拱架是异型拱架的竖直单元部分,即上台阶临时竖撑钢支撑(2D)和下台阶临时竖撑钢支撑(5B);所述调整段落初期支护,短边拱架间距为0.5m,长边拱架间距为1m;Step 9, after the arc-shaped arch frame (11) completes the support, the excavation of the equal-section tunnel II at the oblique position begins. Due to the unequal distances between the left and right sides of the adjustment section, the arch frame spacing is set with a non-equidistant setting until the adjustment is completed. Before excavation, the initial support lower step temporary vertical support steel support (5B) and upper step temporary vertical support steel support (2D) of the equal-section tunnel I within the gantry range are removed; the initial support arch frame of the equal-section tunnel I within the gantry range is the vertical unit part of the special-shaped arch frame, namely the upper step temporary vertical support steel support (2D) and the lower step temporary vertical support steel support (5B); the initial support of the adjustment section, the short side arch frame spacing is 0.5m, and the long side arch frame spacing is 1m; 步骤10,施工过程中加强监控量测,确保初期支护累计变形量不大于阈值,以及封闭成环以后变形速率不大于阈值,即进行防水结构施工,及时跟进后续的衬砌施工。Step 10: Strengthen monitoring and measurement during the construction process to ensure that the cumulative deformation of the initial support is not greater than the threshold, and the deformation rate after the ring is closed is not greater than the threshold, that is, to carry out waterproof structure construction and follow up the subsequent lining construction in a timely manner. 2.根据权利要求1所述的一种等截面隧道斜交挑顶方法,其特征是,所述初期支护包括:型钢拱架、纵向连接钢筋、锁脚锚管、系统锚杆、钢筋网和喷射混凝土。2. A method for oblique top-lifting of a tunnel of equal cross-section according to claim 1, characterized in that the initial support includes: a steel arch frame, longitudinal connecting steel bars, locking anchor pipes, system anchor rods, steel mesh and shotcrete. 3.根据权利要求1所述的一种等截面隧道斜交挑顶方法,其特征是,所述步骤7中,所述门架由竖梁(10)和横梁(8)组成,竖梁(10)和横梁(8)均采用工字钢组成,横梁(8)由3个单元组成,竖梁(10)由2个单元组成,竖梁(10)和横梁(8)之间采用螺栓连接。3. A method for oblique top-lifting of a tunnel of equal cross-section according to claim 1, characterized in that, in step 7, the portal frame is composed of a vertical beam (10) and a horizontal beam (8), both the vertical beam (10) and the horizontal beam (8) are made of I-beams, the horizontal beam (8) is composed of 3 units, the vertical beam (10) is composed of 2 units, and the vertical beam (10) and the horizontal beam (8) are connected by bolts.
CN202510011979.0A 2025-01-06 2025-01-06 A method for oblique top selection of tunnels with uniform cross-section Active CN119412079B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202510011979.0A CN119412079B (en) 2025-01-06 2025-01-06 A method for oblique top selection of tunnels with uniform cross-section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202510011979.0A CN119412079B (en) 2025-01-06 2025-01-06 A method for oblique top selection of tunnels with uniform cross-section

Publications (2)

Publication Number Publication Date
CN119412079A CN119412079A (en) 2025-02-11
CN119412079B true CN119412079B (en) 2025-05-16

Family

ID=94460255

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202510011979.0A Active CN119412079B (en) 2025-01-06 2025-01-06 A method for oblique top selection of tunnels with uniform cross-section

Country Status (1)

Country Link
CN (1) CN119412079B (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN216974878U (en) * 2022-01-26 2022-07-15 四川路桥华东建设有限责任公司 Landslide accumulation body tunnel top-picking composite reinforcing ring
CN115717536A (en) * 2022-11-22 2023-02-28 中铁十二局集团有限公司 Inclined shaft forward-hole-entering and top-raising construction method for large-section tunnel in weak water-rich stratum

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195432A (en) * 2013-03-08 2013-07-10 中铁二十二局集团第一工程有限公司 Weak surrounding rock, tunnel intersection and arc-shaped pilot tunnel construction method
CN207647521U (en) * 2017-11-03 2018-07-24 中铁四局集团有限公司 Rock matter super large section tunnel inclined shaft changes positive cave and faces supporting construction system forever
CN110230507A (en) * 2019-05-27 2019-09-13 中建交通建设集团有限公司四川分公司 A kind of cabinet frame caunches engineering method
CN112431599B (en) * 2020-10-20 2022-10-28 中铁十九局集团第五工程有限公司 Tunnel excavation method for upper soft and lower hard stratum
CN117145496A (en) * 2023-08-09 2023-12-01 广西交通设计集团有限公司 Construction method for transferring transverse tunnel to positive tunnel of large-section weak surrounding rock tunnel
CN118640020A (en) * 2024-06-03 2024-09-13 中铁广州工程局集团有限公司 A construction method for fast top lifting of large-span and small-angle inclined shafts

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN216974878U (en) * 2022-01-26 2022-07-15 四川路桥华东建设有限责任公司 Landslide accumulation body tunnel top-picking composite reinforcing ring
CN115717536A (en) * 2022-11-22 2023-02-28 中铁十二局集团有限公司 Inclined shaft forward-hole-entering and top-raising construction method for large-section tunnel in weak water-rich stratum

Also Published As

Publication number Publication date
CN119412079A (en) 2025-02-11

Similar Documents

Publication Publication Date Title
CN104847374B (en) Large-deformation tunnel in soft rock support system and its construction method
CN102587922B (en) A construction method for arc-guided roof lifting in oblique inclined shafts in soft and broken rock formations
CN112228082B (en) A tunnel collapse treatment method for combined grouting of pipe shed and advanced small conduit
WO2021120991A1 (en) Method for reconstructing shield tunnel for mining construction
CN110821513B (en) Construction method for performing advanced grouting and supporting on tunnel local collapse
CN111779510B (en) Primary support invasion limit arch changing method for high liquid limit red clay surrounding rock tunnel
CN205063959U (en) Tunnel support structure suitable for upper soft and lower hard strata
CN109812270B (en) A support structure for a tunnel passing through a water-rich filled cave and a construction method thereof
CN110541721A (en) Support system and construction method for fully weathered surrounding rock tunnel in water-rich quicksand stratum
CN108412519A (en) The slight large deformation single-track tunnel suspension device of highlands soft rock and construction method
CN103277118A (en) Joint steel frame supporting system for excavating auxiliary tunnel on main-tunnel arch wall and construction method of joint steel frame supporting system
CN104975861A (en) Non-disturbance type supporting structure used for tunnel vault collapsed cavity processing
CN106567718A (en) A construction method for the replacement of pull-trough support in single-arch super-large-span subway stations in composite strata
CN108035733A (en) Partial excavation method for combined vertical supports of rock mass and super-large section tunnel steel frame rock wall
CN111365017B (en) Construction method of underground intercommunication tunnel
CN110700841A (en) Double-side-wall guide pit type excavation method for tunnel excavation
CN113107520A (en) Construction method for excavation and conversion process of inclined shaft and main tunnel of tunnel
CN105134258B (en) Multi-step pipe shed locking foot construction method for completely weathered VI-level surrounding rock tunnel
CN112814686A (en) Construction method for transverse expanding excavation conversion when tunnel section suddenly changes into large-span section
CN112922635A (en) Hydraulic tunnel excavation supporting structure and construction method
CN114412504B (en) Soft rock tunnel multi-layer arch frame primary support method
CN211448697U (en) Single-line tunnel supporting device for soft rock slight large deformation in plateau area
CN215057408U (en) Reinforcing device for intersection of inclined shaft and main tunnel of highway tunnel
CN108071402A (en) The micro- step construction method of loess tunnel
CN119412079B (en) A method for oblique top selection of tunnels with uniform cross-section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant