CN119041700A - Reusable combined type assembled building dowel bar fixing die - Google Patents

Reusable combined type assembled building dowel bar fixing die Download PDF

Info

Publication number
CN119041700A
CN119041700A CN202411314029.7A CN202411314029A CN119041700A CN 119041700 A CN119041700 A CN 119041700A CN 202411314029 A CN202411314029 A CN 202411314029A CN 119041700 A CN119041700 A CN 119041700A
Authority
CN
China
Prior art keywords
nut
fixing
outer side
reusable
dowel bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202411314029.7A
Other languages
Chinese (zh)
Inventor
薛晨
吴华伟
阙凡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN202411314029.7A priority Critical patent/CN119041700A/en
Publication of CN119041700A publication Critical patent/CN119041700A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • E04G21/122Machines for joining reinforcing bars
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1841Means for positioning building parts or elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本发明提供一种可重复使用的组合式装配式建筑插筋固定模具,属于建筑施工技术领域,包括固定骨架,所述固定骨架的顶部螺栓安装有若干个底座,所述底座的顶部固定安装有连接柱。本发明通过调节件、连接件可以调节施工平台的高度和水平度,从而控制浇筑混凝土的厚度,同时施工平台的中部为空心设置便于后期浇筑混凝土和预留套管插筋的夹紧工作,通过安装组件的设置,可以将施工平台牢固的安装在调节件的顶部,通过移动调节垫片控制滑杆的位置,通过将第三螺母安装在滑杆的螺纹部可以对滑杆进行固定,然后滑动移动支板,将安装件安装在安装槽内部进行定位,达到随意调节插筋位置的目的。

The present invention provides a reusable combined assembled building dowel fixing mold, which belongs to the field of building construction technology, and includes a fixed frame, wherein the top bolts of the fixed frame are installed with a plurality of bases, and the top of the base is fixedly installed with a connecting column. The present invention can adjust the height and levelness of the construction platform through adjusting parts and connecting parts, so as to control the thickness of the poured concrete. At the same time, the middle part of the construction platform is hollow, which is convenient for the later pouring of concrete and the clamping of the reserved sleeve dowel. Through the setting of the installation component, the construction platform can be firmly installed on the top of the adjusting part, and the position of the slide rod can be controlled by moving the adjusting gasket. The slide rod can be fixed by installing the third nut on the threaded part of the slide rod, and then the support plate is slid and moved, and the installation part is installed in the installation groove for positioning, so as to achieve the purpose of freely adjusting the dowel position.

Description

Reusable combined type assembled building dowel bar fixing die
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a reusable combined type assembled building dowel bar fixing die.
Background
The dowel bar is used for binding longitudinal bars of a column in a foundation before concrete pouring, and mainly aims to solve the problems that the column, a shear wall and the like are added between floors, if the number of similar components is not arranged on the foundation layer or the lower layer or the number of reinforcing bars on the upper layer is more than that of the lower layer, reserved reinforcing bars are required to be arranged on the lower layer and extend into the upper layer to overlap with the similar components on the upper layer, the dowel bar is called as the dowel bar, the dowel bar is mainly used for places such as the foundation, the column, the wall and the like, and is an important technology in building construction.
The fixed mould of dowel usually carries out the customization processing according to the demand, and the setting element can't take out, needs excision to it, can't be applied to next project after the construction, leads to the suitability lower, causes the material extravagant easily, and because dowel lacks suitable fixed establishment, leads to the inner circle of fixed section of thick bamboo to be greater than the reinforcing bar diameter, then makes the reinforcing bar appear the skew easily when the location, influences the accuracy of location.
Disclosure of Invention
The invention aims to provide a reusable combined type assembled building dowel bar fixing die, and aims to solve the problems in the background technology.
In order to achieve the above purpose, the present invention provides the following technical solutions:
the utility model provides a repeatedly usable's assembled building dowel fixed mould of combination, includes fixed skeleton, a plurality of base is installed to fixed skeleton's top bolt, the top fixed mounting of base has the spliced pole, be provided with the strengthening rib between base and the spliced pole.
As a preferable scheme of the invention, an adjusting piece is fixedly arranged at the top of the connecting column, a connecting piece is arranged on an outer side bolt of the adjusting piece, and a construction platform is arranged at the top of the adjusting piece.
As a preferable scheme of the invention, a mounting assembly is arranged between the adjusting piece and the construction platform, the mounting assembly comprises a rubber gasket, a first nut, first inclined plane saw teeth, a second nut, second inclined plane saw teeth and internal threads, the rubber gasket is arranged on the outer side of the adjusting piece, the first nut is arranged on the outer side of the adjusting piece and is positioned at the top of the rubber gasket, and the first inclined plane saw teeth are arranged at the top of the first nut.
As a preferable mode of the invention, the second nut is arranged at the top of the first nut, the second inclined plane saw teeth are arranged at the bottom of the second nut, and the internal thread is arranged inside the first nut and the second nut.
As a preferable scheme of the invention, a supporting seat is fixedly arranged at the top of the construction platform, a sliding rail is arranged in the supporting seat, and an adjusting gasket is arranged on the outer side of the sliding rail.
As a preferable scheme of the invention, two threaded holes are formed in the adjusting gasket, a sliding rod is arranged in the threaded holes, threaded parts are arranged at two ends of the sliding rod, and a second nut is arranged on the outer side of the threaded parts.
As a preferable scheme of the invention, the outer side of the sliding rod is slidably provided with the movable support plate, the movable support plate and the inside of the sliding rod are provided with the mounting grooves, the inside of the mounting grooves is provided with the mounting piece, the inside of the movable support plate is provided with the dowel bars, the position of the sliding rod is controlled by the movable adjusting gasket, the sliding rod can be fixed by mounting the second nut on the threaded part of the sliding rod, then the movable support plate is slidably moved, and the mounting piece is mounted in the mounting grooves for positioning, so that the purpose of randomly adjusting the dowel bar position is achieved, and the use of workers is facilitated.
As a preferable scheme of the invention, the top of the movable support plate is provided with a fixing mechanism, the fixing mechanism comprises a fixing cylinder, a through groove, a vertical nail, an inner rubber ring, an outer rubber ring, a throat hoop and a fixing lock head, the fixing cylinder is fixedly arranged at the top of the movable support plate, and the through groove is formed in the fixing cylinder.
As a preferable scheme of the invention, a plurality of vertical nails are fixedly arranged at the top of the fixed cylinder, the inner rubber ring is fixedly arranged at the inner side of the vertical nails, and the outer rubber ring is fixedly arranged at the outer side of the vertical nails.
As a preferable scheme of the invention, the hose clamp is arranged on the outer side of the outer rubber ring, the fixed lock head is arranged on the outer side of the hose clamp, and the inner rubber ring is tightly attached to the surface of the dowel bar through the cooperation of the hose clamp and the fixed lock head, so that the hose clamp is fixed, and the construction quality problem caused by deflection can not occur even when concrete is poured.
Compared with the prior art, the invention has the beneficial effects that:
according to the invention, the height and the levelness of the construction platform can be adjusted through the adjusting piece and the connecting piece, so that the thickness of the poured concrete is controlled, meanwhile, the middle part of the construction platform is hollow, so that the clamping work of the post-poured concrete and the reserved sleeve dowel bars is facilitated, the construction platform can be firmly installed at the top of the adjusting piece through the arrangement of the installation assembly, the position of the sliding rod is controlled through the moving adjusting gasket, the sliding rod can be fixed through installing the third nut on the threaded part of the sliding rod, then the supporting plate is moved in a sliding manner, the installation piece is installed in the installation groove for positioning, the purpose of randomly adjusting the dowel bar position is achieved, the use by workers is facilitated, the inner rubber ring is tightly attached to the surface of the dowel bars through the arrangement of the fixing mechanism and the cooperation of the throat hoops and the fixing locking heads, and the construction quality problem caused by deflection cannot occur even when the concrete is poured.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings that are needed in the description of the embodiments will be briefly described below, it being obvious that the drawings in the following description are only some embodiments of the present invention, and that other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art. Wherein:
FIG. 1 is a schematic view of the overall structure of a reusable modular building dowel bar fixing mold;
FIG. 2 is a schematic view of the overall structure of a reusable modular building dowel bar fixing mold;
FIG. 3 is an enlarged view of the structure at A in FIG. 1 of a reusable modular building dowel bar fixing mold;
FIG. 4 is a schematic illustration of a reusable modular building dowel bar fixing mold mounting assembly;
FIG. 5 is a schematic view of a partial mechanism in a reusable modular building dowel bar fixing mold;
FIG. 6 is an enlarged view of the structure at B in FIG. 5 of a reusable modular building dowel bar fixing mold;
FIG. 7 is an enlarged view of the structure at C in FIG. 5 of a reusable modular building dowel bar fixing mold;
FIG. 8 is a schematic view of a fixing mechanism in a reusable modular building dowel bar fixing mold;
fig. 9 is a schematic view of a fixing mechanism in a reusable modular building dowel bar fixing mold.
1, A fixed framework, 2, a base, 3, a connecting column, 4, a reinforcing rib, 5, an adjusting piece, 6, a connecting piece, 7, a construction platform, 8, a mounting assembly, 801, a rubber gasket, 802, a first nut, 803, a first inclined sawtooth, 804, a second nut, 805, a second inclined sawtooth, 806, an internal thread, 9, a supporting seat, 10, a sliding rail, 11, an adjusting gasket, 12, a threaded hole, 13, a sliding rod, 14, a threaded part, 15, a third nut, 16, a movable supporting plate, 17, a mounting groove, 18, a mounting piece, 19, a dowel bar, 20, a fixing mechanism, 2001, a fixing cylinder, 2002, a through groove, 2003, a vertical nail, 2004, an inner rubber ring, 2005, an outer rubber ring, 2006, a throat hoop, 2007, and a fixed lock head.
Detailed Description
In order that the above-recited objects, features and advantages of the present invention will become more readily apparent, a more particular description of the invention will be rendered by reference to specific embodiments thereof which are illustrated in the appended drawings.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention, but the present invention may be practiced in other ways other than those described, and persons skilled in the art will readily appreciate that the present invention is not limited to the specific embodiments disclosed below.
Further, reference herein to "one embodiment" or "an embodiment" means that a particular feature, structure, or characteristic can be included in at least one implementation of the invention. The appearances of the phrase "in one embodiment" in various places in the specification are not necessarily all referring to the same embodiment, nor are separate or alternative embodiments mutually exclusive of other embodiments.
Example 1
Referring to fig. 1-9, in accordance with an embodiment of the present invention, there is provided an embedded rotisserie comprising,
The fixed skeleton 1, a plurality of base 2 is installed to the top bolt of fixed skeleton 1, the top fixed mounting of base 2 has spliced pole 3, be provided with strengthening rib 4 between base 2 and the spliced pole 3, the top fixed mounting of spliced pole 3 has regulating part 5, connecting part 6 is installed to the outside bolt of regulating part 5, construction platform 7 is installed at the top of regulating part 5, install installation component 8 between regulating part 5 and the construction platform 7, installation component 8 includes rubber packing ring 801, first nut 802, first inclined plane sawtooth 803, second nut 804, second inclined plane sawtooth 805 and internal thread 806, rubber packing ring 801 installs in the outside of regulating part 5, first nut 803 is installed in the outside of regulating part 5 and is located the top of rubber packing ring 801, first inclined plane sawtooth 803 sets up at the top of first nut 802, the top of first nut 802 is installed to second nut 804, second inclined plane sawtooth 805 sets up the bottom of second nut 804, internal thread 806 sets up the inside at first nut 802 and second nut 804.
As shown in fig. 1 to 4, the height and levelness of the construction platform 7 can be adjusted through the adjusting member 5 and the connecting member 6, so as to control the thickness of the poured concrete, meanwhile, the middle part of the construction platform 7 is hollow, so that the clamping work of the poured concrete and the reserved sleeve dowel 19 in the later stage is facilitated, the first nut 802 and the second nut 804 are installed on the outer side of the adjusting member 5 through the arrangement of the installation component 8, and the first inclined plane saw tooth 803 and the second inclined plane saw tooth 805 are mutually locked, so that the loosening of the device can be prevented.
Example 2
Referring to fig. 5-9, this embodiment is based on the previous embodiment, which is a second embodiment of the present invention.
In this embodiment, the supporting seat 9 is fixedly installed on the top of the construction platform 7, the sliding rail 10 is provided in the supporting seat 9, the adjusting gasket 11 is provided on the outer side of the sliding rail 10, two threaded holes 12 are provided in the adjusting gasket 11, the sliding rod 13 is installed in the threaded holes 12, threaded portions 14 are provided at two ends of the sliding rod 13, a third nut 15 is installed on the outer side of the threaded portions 14, the movable support plate 16 is slidably installed on the outer side of the sliding rod 13, the movable support plate 16 and the sliding rod 13 are internally provided with the mounting groove 17, the mounting piece 18 is installed in the mounting groove 17, the dowel 19 is provided in the movable support plate 16, the fixing mechanism 20 is provided on the top of the movable support plate 16, the fixing mechanism 20 comprises a fixing cylinder 2001, a through groove 2002, a stud 2003, an inner rubber ring 2004, an outer rubber ring 2005, a throat hoop 2006 and a fixing lock 2007, the fixing cylinder 2001 is fixedly installed on the top of the fixing cylinder 2001, the inner side of the inner rubber ring 2004 is fixedly installed on the inner side of the mounting groove 17, the fixing hoop is fixedly installed on the outer side of the throat hoop 2005, and the fixing lock 2007 is fixedly installed on the outer side of the throat 2005.
As shown in fig. 5 to 9, the position of the slide bar 13 is controlled by moving the adjusting washer 11, the slide bar 13 can be fixed by installing the third nut 15 on the threaded part 14 of the slide bar 13, then the support plate 16 is moved in a sliding manner, the installation piece 18 is installed in the installation groove 17 to be positioned, so that the position of the dowel bar 19 is determined, the dowel bar 19 is placed in the fixing cylinder 2001, the outer rubber ring 2005 is locked by the throat hoop 2006 and the fixing lock 2007, the inner rubber ring 2004 is tightly attached to the surface of the dowel bar 19, the dowel bar is fixed, the dowel bar 19 is prevented from displacement when concrete is poured, and the normal operation of building construction is ensured.
When the concrete pouring device is used, firstly, the base 2 is installed on the fixed framework 1, the strength of the base 2 can be improved through the reinforcing ribs 4, the height and the levelness of the construction platform 7 can be adjusted through the adjusting piece 5 and the connecting piece 6, so that the thickness of poured concrete is controlled, meanwhile, the middle part of the construction platform 7 is hollow, the clamping work of the concrete pouring at the later stage and the reserved sleeve dowel 19 is convenient, the first nut 802 and the second nut 804 are installed on the outer side of the adjusting piece 5 through the installation of the installation component 8, the first inclined plane sawtooth 803 and the second inclined plane sawtooth 805 are mutually locked, the device can be prevented from loosening, the construction platform 7 can be firmly installed on the top of the adjusting piece 5, the position of the slide rod 13 can be controlled through the moving adjusting gasket 11, the slide rod 13 can be fixed through the threaded part 14 of the third nut 15, then the support plate 16 is moved in a sliding mode, the installation piece 18 is installed inside the installation groove 17 to be positioned, therefore, the dowel 19 is well positioned, the dowel 19 is placed into the fixed cylinder 2001, the locking head 2007 is ensured, the dowel is tightly attached to the dowel 19 through the throat 2006 and the fixed rubber ring 2005, and the normal construction is guaranteed, and the concrete is prevented from moving on the dowel 19 when the dowel 19 is tightly and the surface of the concrete is normally poured.
In sum, the height and the levelness of the construction platform 7 can be adjusted through the adjusting piece 5 and the connecting piece 6, thereby the thickness of the poured concrete is controlled, the middle part of the construction platform 7 is hollow, the later pouring concrete and the clamping work of the reserved sleeve dowel 19 are convenient, the construction platform 7 can be firmly installed at the top of the adjusting piece 5 through the arrangement of the installation component 8, the position of the sliding rod 13 is controlled through the moving adjusting gasket 11, the sliding rod 13 can be fixed through the threaded part 14 of the third nut 15 installed at the sliding rod 13, then the supporting plate 16 is slidingly moved, the installation piece 18 is installed in the installation groove 17 for positioning, the purpose of randomly adjusting the position of the dowel 19 is achieved, the use of workers is facilitated, the inner rubber ring 2004 is tightly attached to the surface of the dowel 19 through the cooperation of the throat hoop and the fixed lock head 20, and the construction quality problem caused by offset cannot occur even when the concrete is poured.
It is important to note that the construction and arrangement of the application as shown in the various exemplary embodiments is illustrative only. Although only a few embodiments have been described in detail in this disclosure, those skilled in the art who review this disclosure will readily appreciate that many modifications are possible (e.g., variations in sizes, dimensions, structures, shapes and proportions of the various elements, values of parameters (e.g., temperature, pressure, etc.), mounting arrangements, use of materials, colors, orientations, etc.) without materially departing from the novel teachings and advantages of the subject matter described in this application. For example, elements shown as integrally formed may be constructed of multiple parts or elements, the position of elements may be reversed or otherwise varied, and the nature or number of discrete elements or positions may be altered or varied. Accordingly, all such modifications are intended to be included within the scope of present application. The order or sequence of any process or method steps may be varied or re-sequenced according to alternative embodiments. In the claims, any means-plus-function clause is intended to cover the structures described herein as performing the recited function and not only structural equivalents but also equivalent structures. Other substitutions, modifications, changes and omissions may be made in the design, operating conditions and arrangement of the exemplary embodiments without departing from the scope of the present applications. Therefore, the application is not limited to the specific embodiments, but extends to various modifications that nevertheless fall within the scope of the appended claims.
Furthermore, in order to provide a concise description of the exemplary embodiments, all features of an actual implementation may not be described (i.e., those not associated with the best mode presently contemplated for carrying out the invention, or those not associated with practicing the invention).
It should be appreciated that in the development of any such actual implementation, numerous implementation-specific decisions may be made in any engineering or design project. Such a development effort might be complex and time consuming, but would nevertheless be a routine undertaking of design, fabrication, and manufacture for those of ordinary skill having the benefit of this disclosure.
It should be noted that the above embodiments are only for illustrating the technical solution of the present invention and not for limiting the same, and although the present invention has been described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that the technical solution of the present invention may be modified or substituted without departing from the spirit and scope of the technical solution of the present invention, which is intended to be covered in the scope of the claims of the present invention.

Claims (10)

1. The reusable combined type assembled building dowel bar fixing die is characterized by comprising a fixing framework (1), wherein a plurality of bases (2) are installed on top bolts of the fixing framework (1), connecting columns (3) are fixedly installed on the tops of the bases (2), and reinforcing ribs (4) are arranged between the bases (2) and the connecting columns (3).
2. The reusable combined type assembled building dowel bar fixing die disclosed in claim 1 is characterized in that an adjusting piece (5) is fixedly arranged at the top of the connecting column (3), a connecting piece (6) is arranged on an outer side bolt of the adjusting piece (5), and a construction platform (7) is arranged at the top of the adjusting piece (5).
3. The reusable modular building dowel fixing die set forth in claim 2, wherein a mounting assembly (8) is mounted between the adjusting piece (5) and the construction platform (7), the mounting assembly (8) comprises a rubber gasket (801), a first nut (802), first inclined plane saw teeth (803), a second nut (804), second inclined plane saw teeth (805) and internal threads (806), the rubber gasket (801) is mounted on the outer side of the adjusting piece (5), the first nut (802) is mounted on the outer side of the adjusting piece (5) and located on the top of the rubber gasket (801), and the first inclined plane saw teeth (803) are arranged on the top of the first nut (802).
4. A reusable modular building dowel fixing mold as set forth in claim 3, wherein the second nut (804) is mounted on top of the first nut (802), the second beveled serrations (805) are provided on the bottom of the second nut (804), and the internal threads (806) are provided inside the first nut (802) and the second nut (804).
5. The reusable combined type assembled building dowel bar fixing die disclosed in claim 2 is characterized in that a supporting seat (9) is fixedly arranged at the top of the construction platform (7), a sliding rail (10) is arranged in the supporting seat (9), and an adjusting gasket (11) is arranged on the outer side of the sliding rail (10).
6. The reusable combined type assembled building dowel bar fixing die disclosed in claim 5 is characterized in that two threaded holes (12) are formed in the adjusting gasket (11), a sliding rod (13) is mounted in the threaded holes (12), threaded portions (14) are arranged at two ends of the sliding rod (13), and a third nut (15) is mounted on the outer side of the threaded portions (14).
7. The reusable combined type assembled building dowel bar fixing die disclosed in claim 6, wherein the outer side of the sliding rod (13) is provided with a movable support plate (16), the movable support plate (16) and the sliding rod (13) are internally provided with mounting grooves (17), the mounting grooves (17) are internally provided with mounting pieces (18), and the movable support plate (16) is internally provided with dowel bars (19).
8. The reusable combined type assembled building dowel bar fixing die disclosed in claim 7, wherein the top of the movable support plate (16) is provided with a fixing mechanism (20), the fixing mechanism (20) comprises a fixing barrel (2001), a through groove (2002), a vertical nail (2003), an inner rubber ring (2004), an outer rubber ring (2005), a throat hoop (2006) and a fixing lock head (2007), the fixing barrel (2001) is fixedly arranged at the top of the movable support plate (16), and the through groove (2002) is formed in the fixing barrel (2001).
9. The reusable modular building dowel bar fixing mold of claim 8, wherein the plurality of vertical nails (2003) are fixedly mounted on the top of the fixing cylinder (2001), the inner rubber ring (2004) is fixedly mounted on the inner side of the vertical nails (2003), and the outer rubber ring (2005) is fixedly mounted on the outer side of the vertical nails (2003).
10. The reusable modular building dowel fixing mold of claim 8, wherein the throat hoop (2006) is mounted on the outer side of the outer rubber ring (2005), and the fixing lock (2007) is mounted on the outer side of the throat hoop (2006).
CN202411314029.7A 2024-09-20 2024-09-20 Reusable combined type assembled building dowel bar fixing die Pending CN119041700A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202411314029.7A CN119041700A (en) 2024-09-20 2024-09-20 Reusable combined type assembled building dowel bar fixing die

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202411314029.7A CN119041700A (en) 2024-09-20 2024-09-20 Reusable combined type assembled building dowel bar fixing die

Publications (1)

Publication Number Publication Date
CN119041700A true CN119041700A (en) 2024-11-29

Family

ID=93575771

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202411314029.7A Pending CN119041700A (en) 2024-09-20 2024-09-20 Reusable combined type assembled building dowel bar fixing die

Country Status (1)

Country Link
CN (1) CN119041700A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424636A (en) * 2019-07-29 2019-11-08 中国十七冶集团有限公司 Assembled architecture conversion layer reserves casing joint bar positioning device and construction method
CN212671017U (en) * 2020-06-16 2021-03-09 中建一局集团第三建筑有限公司 Assembled construction is with vertical reinforcing bar positioning die that can have enough to meet need
CN113187796A (en) * 2021-05-24 2021-07-30 王健康 Bolt and nut fastener with anti-loosening and anti-falling functions
CN214925589U (en) * 2021-05-24 2021-11-30 沈阳欣荣基建筑工程有限公司 Be used for prefabricated building PC wall conversion layer to reserve joint bar positioner

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424636A (en) * 2019-07-29 2019-11-08 中国十七冶集团有限公司 Assembled architecture conversion layer reserves casing joint bar positioning device and construction method
CN212671017U (en) * 2020-06-16 2021-03-09 中建一局集团第三建筑有限公司 Assembled construction is with vertical reinforcing bar positioning die that can have enough to meet need
CN113187796A (en) * 2021-05-24 2021-07-30 王健康 Bolt and nut fastener with anti-loosening and anti-falling functions
CN214925589U (en) * 2021-05-24 2021-11-30 沈阳欣荣基建筑工程有限公司 Be used for prefabricated building PC wall conversion layer to reserve joint bar positioner

Similar Documents

Publication Publication Date Title
US8069624B1 (en) Pocketformer assembly for a post-tension anchor system
US6837473B2 (en) Method and apparatus for erecting forms for concrete pours
KR20170100829A (en) Top of the spacing member dies
CN108000702B (en) Bidirectional pretensioning prestressed concrete track slab die and application thereof
CN119041700A (en) Reusable combined type assembled building dowel bar fixing die
CN115288042B (en) A reinforcement device and construction method for external prestressed precise tensioning
KR101739126B1 (en) Method for Forming Top-down-typed Underground Strucutre
CN118952449B (en) A tensioning device for reducing prestress loss and a method for preparing a concrete component
JP5105551B2 (en) Column rebar assembling jig, column rebar assembling jig set, and method for manufacturing reinforced concrete column
CN114045750B (en) Construction method of high pier column tie beam
CN210342689U (en) Slotted wood formwork for pool wall
CN222101453U (en) A sample frame structure for concrete construction of the connecting beam of the water intake tower
CN112576029A (en) Cast-in-place stand column in civil construction and construction method thereof
CN113494156A (en) Wall body steel reinforcement fossil fragments and strutting arrangement thereof
CN223689297U (en) Independent column beam node template
CN115680199B (en) Controller for thickness of reinforced concrete floor slab and thickness of reinforced protection layer
US20240328109A1 (en) Radial bolt corrugated pipe mold and assembly for cementitious foundations, and method for stabilization
KR102516806B1 (en) A spacer device for concrete form having rail type frame
JPH0692643B2 (en) Construction method of structure and its equipment
CN222847562U (en) Reinforcing wall column and wall fixing structure
CN220790786U (en) Leveling mechanism and steel structure embedded steel plate leveling bracket
JP4344626B2 (en) Pressure plate construction method
CN117266542B (en) SPCS prefabricated wall body component lower opening shutoff shaping template
CN222949462U (en) A curved template reinforcement
KR101034462B1 (en) Insulation fixture of aluminum formwork with improved structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination