Construction method of post-cast strip top plate support-free template system
Technical Field
The invention belongs to the technical field of house construction, and particularly relates to a construction method of a post-cast strip roof support-free template system.
Background
The post-cast strip is a concrete strip reserved at corresponding positions of a foundation slab, a wall and a beam according to design or construction specification requirements in order to prevent harmful cracks possibly generated by uneven self shrinkage or uneven settlement of a reinforced concrete structure in building construction. The traditional post-pouring strip template supporting system adopts a steel pipe frame template, a bowl buckle frame template and a reinforced concrete column to independently support, a main template form takes a bottom floor as a support, double-row scaffolds are arranged on two sides of a post-pouring strip in the construction of the supporting system, and the double-row scaffolds and the full-hall scaffolds are kept in a disconnected state so as to prevent mutual interference when the scaffolds are removed.
In addition, the traditional post-pouring belt supporting system is adopted, the construction process of completing concrete pouring in the post-pouring belt and maintaining for 28 days is carried out, the service time of turnover materials such as a steel pipe support frame and a template is greatly occupied, the supporting materials are seriously accumulated, the renting cost is too high, the secondary lapping and disassembling are needed, the potential safety hazard of the structural system is greatly increased, in conclusion, how to improve the post-pouring belt supporting system, the erection of a supporting frame body is avoided, the turnover rate of the frame body material is improved, the passing condition is improved, the utilization of construction space is improved, the comprehensive expansion of a working face is facilitated, the convenience is provided for the cross construction of other processes nearby the post-pouring belt, and the technical problem of the need of solving is solved by relevant construction technicians.
Disclosure of Invention
The invention aims to provide a construction method of a post-cast strip top plate support-free formwork system, which is characterized in that a steel bar sleeve pre-embedded in a truss plate is used for connecting the post-cast strip top plate support-free formwork system and an upper pre-embedded draw hook through a tie bar for welding, so that oblique pulling force is provided for a cantilever plate, in addition, after the hoisting work of a precast slab is completed, bolt sleeves are pre-embedded at two sides of the post-cast strip truss plate, the bottom formwork position is adjusted, bolts penetrate through a rigid supporting plate and the pre-embedded bolt sleeves in a superposed truss, and fastening is performed through the rigid supporting plate.
In order to solve the technical problems, the invention is realized by the following technical scheme:
The invention relates to a construction method of a post-cast strip top plate support-free template system, which comprises the following steps of;
Step one: the drag hook is embedded into the concrete beams at the two sides of the post-pouring belt;
step two: a bottom template, a bolt sleeve, a superimposed sheet truss, bolts and a rigid support plate enter;
step three: paving a superimposed sheet truss in the length direction of the post-pouring belt;
step four: binding steel bars on two side plates of the post-pouring belt;
Step five: post-pouring two-side superimposed sheet trusses and concrete pouring;
step six: welding the drawknot tendon and connecting the drawknot tendon with the upper draw hook and the lower draw hook;
step seven: after the concrete plates at two sides of the post-pouring belt reach the requirement of removing the mould, removing the bottom mould plate;
Step eight: binding post-pouring strip internal joint steel bars;
step nine: the bolt die hanging device is installed, and the position of the bolt is adjusted to be fastened;
Step ten: pouring post-pouring belt concrete;
Step eleven: and the template is supported and removed obliquely upwards.
In the construction method of the post-pouring strip top plate support-free template system, firstly, the pre-embedded position of a lower drag hook in a concrete beam is accurately measured and marked according to a construction drawing, drilling is carried out at the marked position by using drilling equipment, the aperture and depth are ensured to meet the design requirements, the pre-fabricated lower drag hook is installed in the drilled hole, and special anchoring glue or bar planting glue is used for fixing, so that the verticality and the firmness of the lower drag hook are ensured, and the lower drag hook is effectively connected with a tie bar in the subsequent step;
in the second step, the required materials such as a bottom template, a bolt sleeve, a superimposed sheet truss, bolts, a rigid supporting plate and the like are prepared in advance, and the materials meet design specifications and quality standards, and are inspected through appearance inspection, dimension measurement and performance test so as to ensure construction quality.
Further, in the third step, the laminated truss plates are adopted to replace wood templates, the plate ribs are embedded into reinforced concrete structures on two sides of the post-pouring belt, the assembled laminated truss is paved in sequence in the length direction of the post-pouring belt, and in the paving process, tools such as a level meter and a laser range finder are used to ensure the level and alignment of the truss, so that the plate has a certain bearing capacity.
Further, in the construction method of the post-cast strip top plate support-free template system, in the process of formwork supporting of the superimposed sheet truss, a bolt sleeve, a steel bar sleeve and a drag hook are embedded in the post-cast strip top plate support-free template system, the steel bar sleeve is 60 x 37mm in specification and is used for connecting a tension steel bar (the steel bar grade adopts HRB 400) with the diameter of 25mm, the embedded steel bar adopts a hook form with the tail end of 90 degrees according to requirements of concrete structural design Specification B50010-2010 (2015 edition), and the anchoring length of the tension steel bar is calculated according to anchoring conditions and is not smaller than 200mm.
In the fifth and sixth steps, when concrete is poured at the post-pouring zone, firstly, a reinforcing steel bar sleeve pre-embedded in a truss of the laminated slab is connected with a tie bar at the upper part, the appearance quality of a joint is checked, the joint is not more than 2 buckles, no gaps exist between the reinforcing steel bars and the connecting sleeve, then, the tie bar and a drag hook pre-embedded in a beam column node and the truss of the laminated slab are welded in double-sided manner, the welding length is not more than 10d, the included angle between the cable-stayed tie bar and a concrete floor slab is 45 degrees, the tie bar and the upper pre-embedded drag hook are welded and connected (the double-sided welding is 10d, the welding seam is even and full, the problem of no welding slag air hole is solved), and the like is solved by connecting the reinforcing steel bar sleeves pre-embedded under the truss of the laminated slab, so that a special diagonal bracing design structure (triangle geometry invariable structure) is formed, the stress supporting system is stable, the length of a safe cantilever plate is generally not more than 4m, when the horizontal direction of the cantilever plate is not more than 4m, a sleeve is arranged every 2m in the vertical direction of the post-pouring zone and every 2m in the beam column node direction, the cantilever slab is more beneficial to the expansion of the tie bar and the additional pre-bar is arranged on the pre-poured slab, and the stability is better;
the construction flow of the fifth and sixth steps is as follows;
(1) The method comprises the steps that a bolt sleeve is embedded before the production of a superimposed sheet truss, after hoisting of precast slabs on two sides of a post-cast strip is completed, the position of a lower bottom die is adjusted, a rigid supporting plate and a bottom die plate are manufactured by adopting steel materials with Q235, phi 20 is selected as the bolt specification, a groove is formed in the middle of the rigid supporting plate to embed the bottom die plate, rectangular horizontal cavities are formed in the middle of the rigid supporting plate to adapt to fixing of the bolts, and when the embedded bolt sleeve deviates in the horizontal direction, positioning and mounting can be carried out in the length direction;
(2) The rigid supporting plate is arranged below the bottom template and used for embedding and fixing the complete bottom die so that the post-pouring belt part can be better completely sealed;
(3) And the bolts penetrate through the rectangular hole cavities below the rigid support plates and are fastened with the bolt sleeves pre-buried in the superimposed sheet truss.
In the seventh step, whether the concrete slab meets the strength requirement of the form removal is determined through test or experience judgment, the compressive strength test of the same-condition maintenance test block is usually required, after the concrete slab meets the form removal requirement, the bottom formwork is carefully removed by using a special tool, the damage to the concrete is avoided, and the safety is required to be paid attention to in the removal process, so that the accidental falling of the formwork is prevented.
In the construction method of the post-cast strip top plate support-free template system, in the eighth step, in the post-cast strip, impurities such as floating paste, loose aggregate and the like are removed from a joint area, so that the joint area is clean and tidy, and steel bar binding is carried out in the cleaned joint area, and in the binding process, the position of the steel bar is ensured to be accurate, and the binding is firm, so that an effective force transmission structure is formed during subsequent concrete pouring;
And step nine, installing the prepared bolt die hanging device at a designated position, ensuring firm and reliable connection between the bolt die hanging device and surrounding structures, adjusting the position of the bolt according to actual needs, enabling the bolt die hanging device to meet construction requirements, fastening the bolt by using tools such as a spanner, and ensuring stability and safety of the die hanging device.
In the step ten, proper concrete mixing ratio is selected, preparation work before pouring is carried out, pump pipe arrangement, personnel division and the like are carried out, and concrete pouring is carried out on the post-pouring belt by adopting a pumping mode. In the pouring process, the slump and filling speed of concrete are strictly controlled, and the pouring uniformity and compactness are ensured.
In the eleventh step, through structural stability analysis and field inspection, whether the template and the inclined upper support can be removed is judged, factors such as concrete strength and structural stability are analyzed, and after the removal conditions are met, the template and the inclined upper support are safely and orderly removed according to a preset sequence and method. During the dismantling process, the safety protection of operators is needed to be paid attention to, and the members are prevented from falling to hurt people.
The invention has the following beneficial effects:
1. the invention has the advantages of convenient disassembly and assembly, high bearing capacity of the supporting structure system, turnover and repeated use of the supporting structure materials, improvement of the utilization rate of resources by recycling, reduction of serious accumulation of materials such as steel pipe scaffold, templates and the like, reduction of the cost of daily maintenance, and accordance with the requirements of civilized construction, green construction and efficient construction.
2. According to the invention, the upper embedded draw hooks and the lower embedded draw hooks are connected by the welding tie bars to serve as an inclined support, the superimposed sheet truss serves as a support-free formwork system of the bottom die, the included angle between the inclined tie bars and the concrete floor slab is 45 degrees, and an inclined pull rod design structure (triangle geometry unchanged structure) is formed, so that the problem of concrete forming quality at two sides of the post-pouring strip is solved, and the problems of concrete deformation, cracks and sinking caused by collision of construction operation on the support structure can be reduced.
3. The post-pouring belt of the bolt hanging die is convenient to support for the bottom die, avoids the workload caused by installing the template and supporting at the lower floor, can effectively solve the problem that the frame occupies a construction channel in the traditional post-pouring belt construction process, is convenient for the comprehensive expansion of a working face, saves the use of steel pipe materials, is formed at one time in the installation process, has no virtual support, has relatively stable structural form, is convenient to detach and install, has high turnover rate in use, and has more general applicability.
4. According to the invention, the middle part of the rigid support plate is provided with the groove for embedding and fixing the bottom template, and the rectangular horizontal hole cavity is formed for adapting to different bolts to fix the bottom template, so that the positioning and the installation in the length direction can be performed when the horizontal deviation of the embedded bolt sleeve occurs, the template device is easier to install on site, and the controllability of construction quality is greatly improved.
Of course, it is not necessary for any one product to practice the invention to achieve all of the advantages set forth above at the same time.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings that are needed for the description of the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and that other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
FIG. 1 is a construction process flow diagram of a post-cast strip top plate support-free formwork system of the present invention;
FIG. 2 is a schematic view of a rigid support plate of the present invention;
FIG. 3 is a schematic diagram of a post-cast strip top plate support-free formwork system of the present invention.
In the drawings, the list of components represented by the various numbers is as follows:
1. Tie the steel bar, 2, upper pre-buried drag hook; 3. a drag hook is embedded in the lower part; 4. a reinforcing bar sleeve; 5. a bolt sleeve; 6. superimposed sheet truss; 7. a bottom template; 8. a bolt; 9. a rigid support plate.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Referring to fig. 1-3, the invention discloses a post-cast strip top plate support-free template system construction method, which comprises the following steps of;
Step one: the drag hook is embedded into the concrete beams at the two sides of the post-pouring belt;
step two: a bottom template, a bolt sleeve, a superimposed sheet truss, bolts and a rigid support plate enter;
step three: paving a superimposed sheet truss in the length direction of the post-pouring belt;
step four: binding steel bars on two side plates of the post-pouring belt;
Step five: post-pouring two-side superimposed sheet trusses and concrete pouring;
step six: welding the drawknot tendon and connecting the drawknot tendon with the upper draw hook and the lower draw hook;
step seven: after the concrete plates at two sides of the post-pouring belt reach the requirement of removing the mould, removing the bottom mould plate;
Step eight: binding post-pouring strip internal joint steel bars;
step nine: the bolt die hanging device is installed, and the position of the bolt is adjusted to be fastened;
Step ten: pouring post-pouring belt concrete;
Step eleven: and the template is supported and removed obliquely upwards.
In the construction method of the post-cast strip top plate support-free template system, firstly, accurately measuring and marking the pre-embedded position of a lower draw hook in a concrete beam according to a construction drawing, drilling holes at the marked positions by using drilling equipment to ensure that the aperture and depth meet design requirements, installing the prefabricated lower draw hook in the drilled holes, and fixing the prefabricated lower draw hook by using special anchoring glue or bar planting glue to ensure the perpendicularity and firmness of the lower draw hook so as to be effectively connected with a drawknot bar in the subsequent step;
in the second step, the required materials such as a bottom template, a bolt sleeve, a superimposed sheet truss, bolts, a rigid supporting plate and the like are prepared in advance, and the materials meet design specifications and quality standards, and are inspected through appearance inspection, dimension measurement and performance test so as to ensure construction quality.
In the third step, the truss plates of the superposed plates are adopted to replace wood templates, the plate ribs are embedded into reinforced concrete structures on two sides of the post-pouring belt, the assembled truss plates of the superposed plates are paved in sequence in the length direction of the post-pouring belt, and in the paving process, tools such as a level meter, a laser range finder and the like are used to ensure the level and alignment of the truss plates, so that the plates have certain bearing capacity.
In the formwork supporting process of the superimposed sheet truss, a bolt sleeve, a steel bar sleeve and a drag hook are embedded in the post-cast strip top plate support-free formwork system, the steel bar sleeve is 60 x 37mm in specification and is used for connecting tension steel bars (HRB 400 is adopted for the steel bar grade) with the diameter of 25mm, the embedded steel bars are in a hook form with 90-degree hooks at the tail ends according to requirements of concrete structural design Specification B50010-2010 (2015), and the anchoring length of the tension steel bars is calculated according to anchoring conditions and is not less than 200mm.
In the fifth and sixth steps, when pouring concrete at the post-pouring zone, firstly, connecting a reinforcing steel bar sleeve pre-embedded in a truss of the laminated slab with an upper tie bar, checking the appearance quality of a joint, wherein the exposure is not more than 2 buckles, no gaps exist between the reinforcing steel bars and the connecting sleeve, then welding the tie bar with a drag hook pre-embedded in a beam-column joint and the truss of the laminated slab in a double-sided manner, the welding length is not less than 10d, the included angle between the cable-stayed tie bar and a concrete floor slab is 45 degrees, the tie bar is welded with an upper pre-embedded drag hook and a lower pre-embedded drag hook (the double-sided welding is 10d, the welding seam is even and full, the problem of no welding slag air holes and the like) and is connected through the reinforcing steel bar sleeve pre-embedded below the truss of the laminated slab, so as to form a special diagonal tension rod design structure (triangle geometry invariable structure), therefore, the stress support system is stable, the length of a safe cantilever plate is generally not more than 4m, when the horizontal span of the cantilever plate is more than 4m, each 2m of the sleeve is embedded in the vertical direction along the post-pouring zone, and the girder joint direction is more than 2m, the drag hook is embedded in the direction, so that the stress stability of the post-pouring zone is more beneficial to be increased;
the construction flow of the fifth and sixth steps is as follows;
(1) The method comprises the steps that a bolt sleeve is embedded before the production of a superimposed sheet truss, after hoisting of precast slabs on two sides of a post-cast strip is completed, the position of a lower bottom die is adjusted, a rigid supporting plate and a bottom die plate are manufactured by adopting steel materials with Q235, phi 20 is selected as the bolt specification, a groove is formed in the middle of the rigid supporting plate to embed the bottom die plate, rectangular horizontal cavities are formed in the middle of the rigid supporting plate to adapt to fixing of the bolts, and when the embedded bolt sleeve deviates in the horizontal direction, positioning and mounting can be carried out in the length direction;
(2) The rigid supporting plate is arranged below the bottom template and used for embedding and fixing the complete bottom die so that the post-pouring belt part can be better completely sealed;
(3) And the bolts penetrate through the rectangular hole cavities below the rigid support plates and are fastened with the bolt sleeves pre-buried in the superimposed sheet truss.
In the seventh step, whether the concrete slab meets the strength requirement of form removal is determined through test or experience judgment, the compressive strength test of the same-condition maintenance test block is usually required, after the concrete slab meets the form removal requirement, a special tool is adopted to carefully remove the bottom formwork, so that the damage to the concrete is avoided, the safety is required to be paid attention to in the removal process, and the accidental falling of the formwork is prevented.
In the construction method of the post-cast strip top plate support-free template system, cleaning a joint area in a post-cast strip, removing impurities such as floating paste, loose aggregate and the like, ensuring the cleanness and the neatness of the joint area, binding reinforcing steel bars in the cleaned joint area, and ensuring accurate positions and firm binding of the reinforcing steel bars in the binding process so as to form an effective force transfer structure in the subsequent concrete pouring process;
And step nine, installing the prepared bolt die hanging device at a designated position, ensuring firm and reliable connection between the bolt die hanging device and surrounding structures, adjusting the position of the bolt according to actual needs, enabling the bolt die hanging device to meet construction requirements, fastening the bolt by using tools such as a spanner, and ensuring stability and safety of the die hanging device.
In the step ten, proper concrete mixing ratio is selected, preparation work before pouring is carried out, pump pipe arrangement, personnel division and the like are carried out, and concrete pouring is carried out on the post-pouring belt by adopting a pumping mode. In the pouring process, the slump and filling speed of concrete are strictly controlled, and the pouring uniformity and compactness are ensured.
In the eleventh step, through structural stability analysis and field inspection, whether the template and the inclined upper support can be removed is judged, factors such as concrete strength, structural stability and the like are analyzed, and after the removal conditions are met, the template and the inclined upper support are safely and orderly removed according to a preset sequence and method. During the dismantling process, the safety protection of operators is needed to be paid attention to, and the members are prevented from falling to hurt people.
In the description of the present specification, the descriptions of the terms "one embodiment," "example," "specific example," and the like, mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the present invention. In this specification, schematic representations of the above terms do not necessarily refer to the same embodiments or examples. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The preferred embodiments of the invention disclosed above are intended only to assist in the explanation of the invention. The preferred embodiments are not exhaustive or to limit the invention to the precise form disclosed. Obviously, many modifications and variations are possible in light of the above teaching. The embodiments were chosen and described in order to best explain the principles of the invention and the practical application, to thereby enable others skilled in the art to best understand and utilize the invention. The invention is limited only by the claims and the full scope and equivalents thereof.