Overhead crane for overhead line
Technical Field
The invention relates to the technical field of overhead line equipment, in particular to a crane for overhead line.
Background
Overhead power cables refer to power cables that are to be secured to towers for the transmission of electrical energy.
The line engineering construction of overhead power transmission cable includes: foundation construction of a pole tower, assembly construction of the pole tower, wiring construction, grounding engineering construction and the like.
During the construction of the overhead lines, the overhead lines are influenced by terrains, landforms and line channels, and need to cross facilities such as houses, highways, railways, wharfs, bridges, existing distribution lines and the like.
When the crossing operation is carried out, the crossed distribution lines are required to be subjected to power failure treatment, and rail traffic such as highways, railways and the like is blocked, so that great inconvenience is brought to the production and life of people, and construction equipment capable of being quickly transferred is required to be developed, so that the influence on the production and life of people is reduced.
For this, in the patent with publication number CN112209314a, a "self-walking type rapid crossing and hoisting integrated machine" is disclosed, see fig. 23, the patent includes a chassis 01, a walking system 02 is additionally installed on the chassis 01, a revolving support 03 is installed on the chassis 01, a revolving platform 04 is installed on the revolving support 03, a boom 05 and an amplitude-variable oil cylinder 06 are installed on the revolving platform 04, the amplitude-variable oil cylinder 06 is used for adjusting the angle of the boom 05, a crossing frame assembly 07 and a lifting hook 08 are installed at the top end of the boom 05, and a ladder 09 is installed at the back of the boom 05. At the job site, constructor can climb to the top of the suspension arm 05 through the ladder 09, the operation of the crossing type power transmission cable is completed, and after construction is completed, the traveling system 02 can drive the whole equipment to transfer rapidly.
However, in the above patent, the span structure assembly is supported by only one boom, so that the stability of the span structure assembly is reduced, and the position of the erected power cable cannot be horizontally moved along the span structure assembly, so that the position of the power cable is inconvenient to adjust, and the flexibility of the overhead cable is reduced.
Therefore, how to improve the stability of the crossing frame assembly and the flexibility of the wiring is a technical problem to be solved at present.
Disclosure of Invention
The invention aims at the defects in the prior art, and provides the crane for the overhead wire, which can improve the stability of a crossing frame assembly and improve the flexibility of the overhead wire.
In order to achieve the above purpose, the present invention provides the following technical solutions:
a crane for overhead line comprises a tractor, a suspension arm adjusting device and a crossing frame assembly,
The suspension arm comprises a first suspension arm and a second suspension arm which are both arranged on the tractor,
The suspension arm adjusting device comprises a first adjusting device and a second adjusting device, the first adjusting device is used for adjusting the angle of the first suspension arm, the second adjusting device is used for adjusting the angle of the second suspension arm,
The crossing frame assembly comprises a first platform and a second platform, the first platform is arranged at the top end of the first suspension arm, the second platform is arranged at the top end of the second suspension arm,
The bottom of first platform is equipped with first track, and the bottom of second platform is equipped with the second track, is equipped with third track and interfacing apparatus on the second track, and interfacing apparatus is used for driving third track and first track butt joint, and after third track and first track butt joint, first track and second track and third track amalgamation become the hoist and mount track, are equipped with the locomotive on the hoist and mount track, and the bottom of locomotive is equipped with the overhead line construction coaster.
Further, a third adjusting device is arranged on the upper portion of the first suspension arm and used for adjusting the angle of the first platform, a fourth adjusting device is arranged on the upper portion of the second suspension arm and used for adjusting the angle of the second platform.
Further, the top surface of the first track is provided with a first plane and a second plane, the first plane is higher than the second plane,
The top surface of the second track is provided with a guide rail, the top surface of the second track is flush with the second plane, the top surface of the guide rail is flush with the first plane,
The top surface of the third track is flush with the first plane, a guide hole is formed in the third track, the guide rail is in sliding fit with the guide hole, and the bottom of the third track is in sliding fit with the second plane and the top surface of the second track.
Further, be equipped with the butt joint hole on the second track, the width of butt joint hole is greater than the width of guiding hole is equipped with the butt joint seat in the butt joint hole, the top of butt joint seat with third orbital bottom is connected, and the orbital bottom of second is equipped with interfacing apparatus, interfacing apparatus includes the rodless cylinder, and the top of the piston of rodless cylinder is connected with the bottom of butt joint seat.
Further, the mobile car includes the removal casing, is equipped with the movable motor in the removal casing, is equipped with the turbine on the output shaft of movable motor, and the top cooperation of turbine is provided with the worm, and the both ends of worm run through the removal casing, and the both ends and the removal casing rotation of worm are connected, and the both ends that the worm worn out the removal casing all are equipped with the removal wheel, move the wheel walking and be in first plane the orbital top surface of third the top surface of guide rail.
Further, the side surface of the first track, the side surface of the second track and the side surface of the third track are flush,
The side part of the movable shell is provided with a guide shaft, the guide shaft is provided with a guide wheel, the guide wheel is attached to the side surface of the first rail, the side surface of the second rail and the side surface of the third rail for rolling,
The first track is equipped with first spacing telescopic link in being close to the orbital one end of second, and the second track is equipped with the spacing telescopic link of second in being close to orbital one end of first, and the spacing telescopic link of first spacing telescopic link after the extension and the spacing telescopic link of second after the extension all are used for preventing the leading wheel removal.
Further, a first railing is arranged on the first platform, a second railing is arranged on the second platform,
The first platform is provided with a first rotating shaft at one end close to the second platform, the first rotating shaft transversely penetrates through the first railing, the first rotating shaft is provided with a first baffle and a gear, the first platform is provided with a through hole, the lower part of the gear is exposed from the through hole, the top surface of the third track is provided with a rack, the rack is meshed with the lower part of the gear,
The first rotating shaft is provided with a ratchet wheel at the end part penetrating through the first railing, the side part of the first platform is provided with a pawl, the lower end of the pawl is rotationally connected with the side part of the first platform, the upper end of the pawl is connected with the side part of the first platform through a reset elastic piece, the reset elastic piece is used for resetting the pawl after anticlockwise swinging, the side part of the first platform is also provided with an abutting telescopic rod, the extending abutting telescopic rod is used for abutting against the side wall of the pawl to prevent the pawl from rotating clockwise,
When the third track slides on the second plane to be close to the first plane, the rack drives the gear to rotate clockwise, the gear drives the first rotating shaft to rotate clockwise, the first rotating shaft drives the ratchet wheel and the first baffle to rotate clockwise,
When the third rail is abutted to the vertical transition surface between the first plane and the second plane, the third rail is abutted to the first rail, the first baffle plate is turned to a horizontal state, and the first baffle plate in the horizontal state is overlapped on the second platform.
Further, the second platform is provided with a second rotating shaft and a hollow seat at one end close to the first platform, the second rotating shaft is rotationally connected with the second platform, the upper part of the second rotating shaft is provided with a second baffle, the lower part of the second rotating shaft is provided with a spiral groove, the inside of the hollow seat is provided with a pressing block and a pressing elastic piece, the pressing block is vertically and slidingly matched with the inside of the hollow seat, the pressing elastic piece is used for lifting the pressing block upwards, the side wall of the hollow seat is provided with a first opening and a second opening, one side of the pressing block exposed from the first opening is provided with a pressing rod, the pressing rod is matched with the first baffle, one side of the pressing block exposed from the second opening is provided with a pin rod, the pin rod is matched with the spiral groove,
When the first baffle rotates clockwise, the first baffle gradually presses the pressing rod, the pressing rod drives the pressing block to overcome the elastic force of the pressing elastic piece to move downwards, the pressing block drives the pin rod to move downwards, the pin rod pushes the lower groove wall of the spiral groove, the second rotating shaft drives the second baffle to rotate, and the second baffle gradually rotates to the upper side part of the first baffle.
Further, a first electromagnetic chuck is arranged on the first railing, a second electromagnetic chuck is arranged on the second railing,
When the first baffle plate rotates to a vertical state, the first baffle plate shields one end of the first platform, which is close to the second platform, the first electromagnetic chuck attracts the first baffle plate,
When the second baffle shields one end of the second platform, which is close to the first platform, the second electromagnetic chuck attracts the second baffle.
Further, the device also comprises a control module, the abutting telescopic rod, the first electromagnetic chuck and the second electromagnetic chuck are all electrically connected with the control module,
When the control module receives the docking command, the docking device drives the third rail to dock towards the first rail, the first electromagnetic chuck and the second electromagnetic chuck are powered off, the abutting telescopic rod is extended to abut against the side part of the pawl,
When the control module receives a command for releasing the butt joint, the butt joint device drives the third rail to leave the first rail, the first electromagnetic chuck and the second electromagnetic chuck are electrified, and the side part of the pawl is shortened and left by the butt joint telescopic rod.
Compared with the prior art, the invention has the beneficial effects that:
1. according to the invention, when the butt joint device drives the third rail to butt joint with the first rail, the second rail and the third rail are connected, the first platform and the second platform are also connected, at the moment, the crossing frame assembly comprising the first platform and the second platform can be jointly supported by the first suspension arm and the second suspension arm, so that the stability of the crossing frame assembly is improved, and the trolley can drive the overhead line construction trolley to walk along the first rail, the second rail and the third rail, so that the position of the power transmission cable is adjusted, and the flexibility of overhead line is improved.
2. Through setting up first plane and second plane on first track, set up the guide rail on the second track, set up the guiding hole on the third track, can let first orbital first plane, the top surface of guide rail, the orbital top surface parallel and level of third for the locomotive can be on first track, guide rail, third track steady transition, guarantee the normal walking of locomotive.
3. By using a rodless cylinder to drive the third rail to move, the occupied space can be saved compared with the use of a rod cylinder, so that the structure is more compact.
4. Through letting the first orbital side of leading wheel laminating parallel and level, the orbital side of second, the orbital side of third roll, can prevent that the locomotive from taking place the collision in the vertical direction of walking direction, improved the walking stability of locomotive.
5. Through setting up first spacing telescopic link and the spacing telescopic link of second, can prevent that the leading wheel from breaking away from first track or second track when docking track and first track do not dock, prevent that the locomotive from falling, improved the safety in utilization.
6. Through setting up first pivot, gear, first baffle, rack, can be when the butt joint of butt joint device drive third track and first track, drive the first baffle of closing state and open for first platform is opened, need not the constructor and opens first baffle by hand, not only reduces intensity of labour, still improves and opens efficiency.
7. When the first baffle is opened, because the first baffle can overlap on the second platform, so the first baffle can play the effect of linking first platform and second platform except that the effect of closing first platform, the first baffle can also play, allows constructor walk through first platform and second platform on the first baffle. On one hand, the risk of walking between the first platform and the second platform by constructors is reduced, and the safety is improved; in the second aspect, other plate bodies are not required to be used for connecting the first platform and the second platform temporarily, so that the connection efficiency is improved.
8. Through setting up ratchet, pawl, can prevent that the third track from accidentally leaving first track, guarantee third track and the reliability of first track butt joint, guarantee first baffle is opened and overlap joint reliability on the second platform.
9. Through setting up second pivot, second baffle, hollow seat, pressing the briquetting, pressing the elastic component, pressing pole, round pin pole, can open at the in-process that first baffle opened, drive second baffle for the second platform is opened, need not the workman and opens the second baffle by hand, is favorable to further reducing intensity of labour, further improves and opens efficiency.
10. After the second baffle is opened, the second baffle can be located the top lateral part of first baffle for the second baffle not only can play the effect of closing the second platform, and the second baffle can also play the effect of railing, makes constructor walk when on first baffle, can support the stable health of second baffle, has improved the security.
11. Through setting up first electromagnet and second electromagnet, can stabilize the closed condition of first baffle and second baffle, further improve the security.
Drawings
FIG. 1 is a split perspective view of a first rail, a second rail, a third rail, and a docking device;
FIG. 2 is an assembled perspective view of the first rail, the second rail, the third rail, and the docking device;
FIG. 3 is an assembled top view of the first rail, second rail, third rail, and docking mechanism;
FIG. 4 is an assembled front view of the first rail, the second rail, the third rail, and the docking mechanism;
FIG. 5 is an assembled perspective view of the first platform, the second platform, the first rail, the second rail, the third rail, and the docking device;
FIG. 6 is an assembled perspective view II of the first platform, the second platform, the first rail, the second rail, the third rail, and the docking device;
FIG. 7 is an assembled front view of the first platform, second platform, first rail, second rail, third rail, docking mechanism;
FIG. 8 is an enlarged view of a portion of FIG. 7 at A;
FIG. 9 is an assembled front view of the second spindle, hollow seat, pressing block, pressing spring, pressing lever, and pin;
FIG. 10 is an assembled perspective view I of the second spindle, hollow seat, pressing block, pressing elastic member, pressing lever, and pin lever;
FIG. 11 is an assembled perspective view II of the second spindle, hollow seat, pressing block, pressing elastic member, pressing lever and pin lever;
FIG. 12 is an assembled perspective view III of the second spindle, hollow seat, pressing block, pressing elastic member, pressing lever, and pin lever;
FIG. 13 is a perspective view of the mobile cart with the mobile housing removed;
FIG. 14 is a perspective view of the mobile cart;
FIG. 15 is a front view of the mobile cart;
FIG. 16 is a right side view of the mobile cart;
FIG. 17 is an assembled perspective view of the mobile cart, first platform, second platform, first rail, second rail, third rail, docking device;
Fig. 18 is a front view of the traveling carriage provided with the electric hoist;
FIG. 19 is an assembled front view of the carriage, electric block, overhead working truck, first platform, second platform, first rail, second rail, third rail, and docking mechanism;
FIG. 20 is a schematic view of a construction of a jack for overhead lines;
FIG. 21 is a control schematic diagram I;
FIG. 22 is a second control schematic;
Fig. 23 is a schematic diagram of a structure of the background art.
In the figure:
01-chassis, 02-running system, 03-slewing support, 04-slewing table, 05-boom, 06-luffing cylinder, 07-span frame assembly, 08-lifting hook, 09-ladder,
1-A tractor of the type comprising a tractor,
21-A first boom arm, which is arranged on the first boom,
22-A second boom arm, the second boom arm,
31-A first hydraulic cylinder,
32-A second hydraulic cylinder,
41-First platform, 411-first railing, 412-first electromagnetic chuck, 413-first rotating shaft, 414-first baffle, 415-gear, 416-through hole, 417-ratchet, 418-pawl, 419-reset elastic piece, 4110-abutting telescopic rod,
42-Second platform, 421-second railing, 422-second electromagnetic chuck, 423-second rotating shaft, 4231-spiral groove, 424-second baffle, 425-hollow seat, 4251-first opening, 4252-second opening, 426-pressing block, 427-pressing elastic piece, 428-pressing rod, 429-pin rod,
51-A third hydraulic cylinder,
52-A fourth hydraulic cylinder,
61-First track, 611-first plane, 612-second plane, 613-vertical transition plane, 614-first limit telescopic rod,
62-A second track, 621-a guide rail, 622-a butt joint hole, 623-a butt joint seat, 624-a second limit telescopic rod,
63-Third rail, 631-pilot hole, 632-rack,
7-Rodless cylinder, 71-piston,
8-Moving vehicle, 81-moving shell, 82-moving motor, 83-turbine, 84-worm, 85-moving wheel, 86-guiding axle, 87-guiding wheel, 88-electric hoist,
9-Stringing construction pulleys.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and fully with reference to the accompanying drawings, in which it is evident that the embodiments described are some, but not all embodiments of the invention. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Example 1:
referring to fig. 20, a crane for overhead lines comprises a tractor 1, a boom adjusting device, a crossing frame assembly.
Referring to fig. 20, the boom includes a first boom 21 and a second boom 22.
The boom adjusting device comprises a first adjusting device and a second adjusting device. The first adjusting means is used for adjusting the angle of the first boom 21 and the second adjusting means is used for adjusting the angle of the second boom 22.
Referring to fig. 20, in the present embodiment 1, the first adjusting device includes a first hydraulic cylinder 31, the bottom of the first boom 21 is rotatably connected with the tractor 1, the bottom of the first hydraulic cylinder 31 is rotatably connected with the tractor 1, and the piston rod of the first hydraulic cylinder 31 is rotatably connected with the lower portion of the first boom 21. When the piston rod of the first hydraulic cylinder 31 is extended, the first boom 21 swings in a direction away from the second boom 22; when the piston rod of the first hydraulic cylinder 31 is retracted, the first boom 21 swings in a direction approaching the second boom 22. The angle of the first boom 21 can be adjusted by the telescopic action of the piston rod of the first hydraulic cylinder 31.
Referring to fig. 20, in the present embodiment 1, the second adjusting device includes a second hydraulic cylinder 32, the bottom of the second boom 22 is rotatably connected to the tractor 1, the bottom of the second hydraulic cylinder 32 is rotatably connected to the tractor 1, and the piston rod of the second hydraulic cylinder 32 is rotatably connected to the lower portion of the second boom 22. When the piston rod of the second hydraulic cylinder 32 is extended, the second boom 22 swings in a direction away from the first boom 21; when the piston rod of the second hydraulic cylinder 32 is retracted, the second boom 22 swings in a direction approaching the first boom 21. The angle of the second boom 22 can be adjusted by the telescopic action of the piston rod of the second hydraulic cylinder 32.
Referring to fig. 20, a ladder 09 is mounted to the back of the first boom 21 and the back of the second boom 22 for ease of climbing by the constructor.
Referring to fig. 20, the crossing carriage assembly includes a first platform 41 and a second platform 42. The first platform 41 is rotatably mounted to the top end of the first boom 21, and the second platform 42 is rotatably mounted to the top end of the second boom 22.
The upper part of the first boom 21 is provided with a third adjusting device for adjusting the angle of the first platform 41, and the upper part of the second boom 22 is provided with a fourth adjusting device for adjusting the angle of the second platform 42.
Referring to fig. 20, in the present embodiment 1, the third adjusting means includes a third hydraulic cylinder 51, the bottom of the third hydraulic cylinder 51 is rotatably connected to the upper portion of the first boom 21, and the piston rod of the third hydraulic cylinder 51 is rotatably connected to the bottom of the first platform 41. When the piston rod of the third hydraulic cylinder 51 is extended, the first platform 41 swings upward; when the piston rod of the third hydraulic cylinder 51 is retracted, the first platform 41 swings downward. The angle of the first platform 41 can be adjusted by the telescopic action of the piston rod of the third hydraulic cylinder 51.
Referring to fig. 20, in the present embodiment 1, the fourth adjusting means includes a fourth hydraulic cylinder 52, the bottom of the fourth hydraulic cylinder 52 is rotatably connected to the upper portion of the second boom 22, and the piston rod of the fourth hydraulic cylinder 52 is rotatably connected to the bottom of the second platform 42. When the piston rod of the fourth hydraulic cylinder 52 is extended, the second platform 42 swings upward; when the piston rod of the fourth hydraulic cylinder 52 is retracted, the second platform 42 swings downward. The angle of the second platform 42 can be adjusted by the telescopic action of the piston rod of the fourth hydraulic cylinder 52.
Referring to fig. 1 to 7, a first rail 61 is installed at the bottom of the first platform 41, a second rail 62 is installed at the bottom of the second platform 42, a third rail 63 and a docking device are installed on the second rail 62, the docking device is used for driving the third rail 63 to dock with the first rail 61, when the third rail 63 is docked with the first rail 61, the second rail 62 and the third rail 63 are spliced into a hoisting rail, a trolley 8 is installed on the hoisting rail, and a trolley construction trolley 9 is installed at the bottom of the trolley 8.
Referring to fig. 1, in embodiment 1, the top surface of the first rail 61 is provided with a first plane 611 and a second plane 612, the first plane 611 is higher than the second plane 612, and a vertical transition surface 613 is provided between the first plane 611 and the second plane 612. A guide rail 621 is mounted on the top surface of the second rail 62. The third rail 63 is provided with a guide hole 631, and the guide rail 621 is slidably engaged with the guide hole 631. Referring to fig. 2, the top surfaces of the first plane 611 and the third rail 63 and the top surface of the guide rail 621 are flush, the second plane 612 and the top surface of the second rail 62 are flush, and the bottom of the third rail 63 is in sliding engagement with the second plane 612 and the top surface of the second rail 62.
Referring to fig. 1, in embodiment 1, the second rail 62 is provided with a docking hole 622, a docking seat 623 is provided in the docking hole 622, and the width of the docking hole 622 is larger than the width of the guide hole 631. Since the width of the docking hole 622 is greater than the width of the guide hole 631, the width of the docking hole 622 is greater than the width of the guide rail 621 positioned in the guide hole 631, the guide rail 621 cannot completely separate the third rail 63 and the docking station 623 so that the bottom of the third rail 63 and the top of the docking station 623 can be assembled together. Further, in the present embodiment 1, the docking device includes a rodless cylinder 7, the rodless cylinder 7 is installed at the bottom of the second rail 62, and the top of the piston 71 of the rodless cylinder 7 is fixedly connected with the bottom of the docking station 623. After the rodless cylinder 7 is started, the piston 71 of the rodless cylinder 7 can drive the third rail 63 to move through the butt joint seat 623.
Referring to fig. 13-17, in this embodiment 1, the mobile cart 8 includes a mobile housing 81, a mobile motor 82 is installed in the mobile housing 81, a turbine 83 is installed on an output shaft of the mobile motor 82, a worm 84 is cooperatively provided above the turbine 83, two ends of the worm 84 penetrate through the mobile housing 81, two ends of the worm 84 are rotatably connected with the mobile housing 81 through bearings, two ends of the worm 84 penetrating out of the mobile housing 81 are all installed with mobile wheels 85, and the mobile wheels 85 travel on the first plane 611, the top surface of the third rail 63, and the top surface of the guide rail 621.
In order to prevent the moving wheel 85 from slipping, friction stripes are arranged on the first plane 611, the top surface of the third rail 63 and the top surface of the guide rail 621, and the friction stripes can increase the friction resistance when the moving wheel 85 walks, reduce the slipping probability and ensure the effectiveness of the walking movement of the moving wheel 85.
Referring to fig. 18 and 19, in the present embodiment 1, an electric block 88 is provided between the bottom of the traveling carriage 8 and the overhead working truck 9, the electric block 88 being mounted on the bottom of the traveling carriage 8, the electric block 88 being used to hoist the overhead working truck 9.
The working principle of this embodiment 1 is as follows:
Firstly, a power transmission cable to be erected passes through a wire-erecting construction pulley 9, so that the wire-erecting construction pulley 9 can be used as a fulcrum for traction of the power transmission cable; then the first suspension arm 21 is driven to be lifted by the first adjusting device, and the second suspension arm 22 is driven to be lifted by the second adjusting device; the first platform 41 is then adjusted to the horizontal by the third adjusting means, and the second platform 42 is adjusted to the horizontal by the fourth adjusting means; then the third rail 63 is driven to be in butt joint with the first rail 61 by a butt joint device, so that the first rail 61, the second rail 62 and the third rail 63 are spliced into a hoisting rail; finally, the moving vehicle 8 is driven to drive the overhead line construction pulley 9 to walk along the hoisting track, and the position of the power transmission cable is adjusted.
From the above working principle, this embodiment 1 has the following effects:
First, in embodiment 1, when the docking device drives the third rail 63 to dock with the first rail 61, not only the first rail 61, the second rail 62 and the third rail 63 are engaged, but also the first platform 41 and the second platform 42 are engaged, at this time, the span structure assembly including the first platform 41 and the second platform 42 can be supported by the first boom 21 and the second boom 22 together, stability of the span structure assembly is improved, and the trolley 8 can drive the trolley 9 to walk along the first rail 61, the second rail 62 and the third rail 63, so that the position of the power cable can be adjusted, and flexibility of the overhead line is improved.
Second, through setting up first plane 611 and second plane 612 on first track 61, set up guide rail 621 on second track 62, set up guiding hole 631 on third track 63, can let the first plane 611 of first track 61, the top surface of guide rail 621, the top surface parallel and level of third track 63 for mobile car 8 can be on first track 61, guide rail 621, the steady transition of third track 63, guarantee mobile car 8's normal walking.
Third, by driving the third rail 63 to move using the rodless cylinder 7, the occupied space can be saved as compared with using a rod cylinder, so that the structure is more compact.
Example 2:
This example 2 is a further improvement over example 1:
Referring to fig. 2 and 3, the side of the first rail 61, the side of the second rail 62, and the side of the third rail 63 are flush.
Referring to fig. 15 and 17, a guide shaft 86 is mounted at a side of the moving housing 81, and a guide wheel 87 is rotatably coupled to the guide shaft 86. The guide wheel 87 rolls on the side of the first rail 61, the side of the second rail 62, and the side of the third rail 63.
Referring to fig. 1, the first rail 61 is provided with a first limit telescopic rod 614 at an end close to the second rail 62, the second rail 62 is provided with a second limit telescopic rod 624 at an end close to the first rail 61, and the first limit telescopic rod 614 and the second limit telescopic rod 624 are used for preventing the guide wheel 87 from moving. In this embodiment 1, the first limiting telescopic rod 614 and the second limiting telescopic rod 624 may each be a telescopic device such as a hydraulic cylinder or an air cylinder.
The working principle of this embodiment 2 is as follows:
(1) When the third rail 63 is not docked with the first rail 61, the first limit telescoping rod 614 and the second limit telescoping rod 624 are in an extended state. If the mobile vehicle 8 is located on the first rail 61, the extended first limit telescopic rod 614 can block the guide wheel 87 from leaving the first rail 61, so that the mobile vehicle 8 is prevented from falling. If the mobile vehicle 8 is located on the second rail 62, the extended second limit telescopic rod 624 can block the guide wheel 87 from leaving the second rail 62 and the third rail 63, so that the mobile vehicle 8 is prevented from falling.
(2) When the third rail 63 is docked in place with the first rail 61, the first limit telescoping rod 614 and the second limit telescoping rod 624 are in a shortened state. At this time, the mobile vehicle 8 can travel among the first rail 61, the second rail 62, and the third rail 63.
(3) To facilitate the determination of whether to dock, a normally open travel switch is mounted on the vertical transition surface 613 between the first plane 611 and the second plane 612. Referring to fig. 21, the normally open travel switch, the first limit telescoping rod 614, and the second limit telescoping rod 624 are all electrically connected to the control module. When the third rail 63 abuts against the vertical transition surface 613, the third rail 63 and the first rail 61 are abutted in place, and the normally open travel switch is pressed by the third rail 63, and after receiving a signal from the normally open travel switch, the control module controls the first limit telescopic rod 614 and the second limit telescopic rod 624 to be shortened. When not aligned, the normally open travel switch is not depressed by the third rail 63 and the control module controls the first and second limit telescoping rods 614, 624 to extend.
From the above working principle, this embodiment 2 has the following effects:
First, by rolling the side surface of the first rail 61, the side surface of the second rail 62, and the side surface of the third rail 63, which are flush with each other, the guide wheels 87 can be prevented from colliding with each other in the direction perpendicular to the traveling direction of the traveling vehicle 8, and the traveling stability of the traveling vehicle 8 can be improved.
Second, by providing the first limit telescopic link 614 and the second limit telescopic link 624, when the docking rail is not docked with the first rail 61, the guide wheels 87 are prevented from being separated from the first rail 61 or the second rail 62, the mobile car 8 is prevented from falling, and the use safety is improved.
Example 3:
This example 3 is a further improvement over example 1 or example 2:
Referring to fig. 5, the first platform 41 has a first rail 411 mounted thereon, and the second platform 42 has a second rail 421 mounted thereon. The first rail 411 is provided with a first electromagnetic chuck 412, and the second rail 421 is provided with a second electromagnetic chuck 422.
Referring to fig. 5 and 8, the first platform 41 is provided with a first rotation shaft 413 at an end near the second platform 42. The first rotary shaft 413 transversely penetrates the first column 411, and the first rotary shaft 413 is rotatably connected with the first column 411 through a bearing. The first baffle 414 and the gear 415 are mounted on the first rotary shaft 413, the first platform 41 is provided with a through hole 416, the lower portion of the gear 415 is exposed from the through hole 416, the rack 632 is mounted on the top surface of the third rail 63, and the rack 632 is meshed with the lower portion of the gear 415.
Referring to fig. 8, a first rotary shaft 413 is provided with a ratchet 417 at an end penetrating the first rail 411. The side of the first platform 41 is provided with a pawl 418, the lower end of the pawl 418 is rotatably connected with the side of the first platform 41, and the upper end of the pawl 418 is connected with the side of the first platform 41 through a return elastic member 419, in this embodiment 3, the return elastic member 419 may use a spring, and the return elastic member 419 is used for returning the pawl 418 after counterclockwise swinging. The side portion of the first platform 41 is further provided with an abutting telescopic rod 4110, the extended abutting telescopic rod 4110 is used for abutting against the side wall of the pawl 418 to prevent the pawl 418 from rotating clockwise, the shortened abutting telescopic rod 4110 does not prevent the pawl 418 from swinging clockwise, and in this embodiment 3, the abutting telescopic rod 4110 can adopt telescopic devices such as a hydraulic cylinder or an air cylinder.
Referring to fig. 5-7 and 9-12, the second platform 42 is provided with a second rotating shaft 423 and a hollow seat 425 at one end near the first platform 41, the second rotating shaft 423 is rotatably connected with the second platform 42, and the hollow seat 425 is fixedly mounted on the second platform 42. The second baffle 424 is installed at the upper part of the second rotating shaft 423, and the spiral groove 4231 is provided at the lower part of the second rotating shaft 423. The hollow seat 425 is internally provided with a pressing block 426 and a pressing elastic member 427, the pressing block 426 is vertically slidably fitted with the inside of the hollow seat 425, and in this embodiment 3, the pressing elastic member 427 may employ a spring, and the pressing elastic member 427 is used for lifting the pressing block 426 upward. The side wall of the hollow seat 425 is provided with a first opening 4251 and a second opening 4252, a pressing rod 428 is arranged on one side of the pressing block 426 exposed from the first opening 4251, the pressing rod 428 is matched with the first baffle 414, a pin rod 429 is arranged on one side of the pressing block 426 exposed from the second opening 4252, and the pin rod 429 is matched with the spiral groove 4231.
Referring to fig. 22, embodiment 3 further includes a control module. The docking device, the abutting telescopic rod 4110, the first electromagnetic chuck 412 and the second electromagnetic chuck 422 are all electrically connected with the control module. The control module is also electrically connected with an operation panel, the operation panel is used for sending a docking command or a command for releasing docking to the control module, the operation panel can be arranged on the tractor 1, and in addition, the operation panel can also send the command in a mode of a remote control panel and the like.
The working principle of this embodiment 3 is as follows:
(1) When the docking operation is needed:
When the control module receives the docking command, the control module controls the docking device to drive the third rail 63 to dock to the first rail 61, and at the same time, the control module controls the first electromagnetic chuck 412 and the second electromagnetic chuck 422 to be powered off, and the abutting telescopic rod 4110 stretches and abuts against the side part of the pawl 418.
When the third rail 63 is docked to the first rail 61, the third rail 63 slides on the second plane 612 of the first rail 61 to approach the first plane 611, the third rail 63 drives the rack 632 to move together, the rack 632 drives the gear 415 to rotate clockwise, the gear 415 drives the first rotating shaft 413 to rotate clockwise, and the first rotating shaft 413 drives the ratchet 417 and the first shutter 414 to rotate clockwise.
When the ratchet 417 rotates clockwise, the ratchet teeth on the ratchet 417 push the upper end of the pawl 418 against the elastic force of the return elastic member 419, so that the pawl 418 swings counterclockwise from the vertical state, and the pawl 418 does not interfere with the clockwise rotation of the ratchet 417. Each time one ratchet passes over the pawl 418, the pawl 418 is reset to the vertical state by the elastic force of the reset elastic member 419, and the abutting telescopic rod 4110 can prevent the pawl 418 from rotating clockwise from the vertical state, so that the first rotating shaft 413 can be prevented from rotating anticlockwise during the abutting operation.
When the first baffle 414 rotates clockwise, the first baffle 414 gradually presses the pressing rod 428, the pressing rod 428 drives the pressing block 426 to move downwards against the elastic force of the pressing elastic piece 427, the pressing block 426 drives the pin rod 429 to move downwards, the pin rod 429 pushes the lower groove wall of the spiral groove 4231, the second rotating shaft 423 drives the second baffle 424 to rotate, and the second baffle 424 gradually opens the second platform 42.
When the third rail 63 abuts against the vertical transition surface 613 between the first plane 611 and the second plane 612, the third rail 63 abuts against the first rail 61, the first barrier 414 is turned to the horizontal state, the first barrier 414 in the horizontal state is overlapped on the second platform 42, and the second barrier 424 is also turned to the upper side of the first barrier 414. At this time, the worker can walk between the first platform 41 and the second platform 42.
(2) When the undocking operation is needed:
when the control module receives a command for releasing the docking, the control module controls the docking device to drive the third rail 63 to leave the first rail 61, and at the same time, the control module controls the first electromagnetic chuck 412 and the second electromagnetic chuck 422 to be electrified, and the abutting telescopic rod 4110 is shortened to leave the side part of the pawl 418.
When the third rail 63 leaves the first rail 61, the third rail 63 slides on the second plane 612 of the first rail 61 away from the first plane 611, the third rail 63 drives the rack 632 to move together, the rack 632 drives the gear 415 to rotate counterclockwise, the gear 415 drives the first rotating shaft 413 to rotate counterclockwise, and the first rotating shaft 413 drives the ratchet 417 and the first shutter 414 to rotate counterclockwise.
When the ratchet 417 rotates counterclockwise, the ratchet teeth of the ratchet 417 toggle the upper end of the pawl 418, so that the pawl 418 swings clockwise from the vertical posture. In this process, since the abutting telescoping rod 4110 has been shortened, the abutting telescoping rod 4110 does not interfere with the rotation of the pawl 418 from the vertical state in the clockwise direction.
When the first baffle 414 rotates anticlockwise, the first baffle 414 leaves the second platform 42, the first baffle 414 also leaves the pressing rod 428, and the pressing rod 428 and the pin rod 429 are driven to move upwards and reset by the pressing rod 426 due to the elastic force of the pressing elastic piece 427, the pressing rod 428 after moving upwards and resetting can wait for the first baffle 414 to be pressed downwards again, the pin rod 429 after moving upwards and resetting pushes the upper groove wall of the spiral groove 4231, so that the second rotating shaft 423 drives the second baffle 424 to rotate reversely, and the second baffle 424 gradually closes the second platform 42.
When the first baffle 414 rotates counterclockwise to the vertical state, the first baffle 414 shields an end of the first platform 41 near the second platform 42, that is, the first platform 41 is closed by the first baffle 414, and the first electromagnetic chuck 412 attracts the first baffle 414. When the second shutter 424 shields the end of the second platform 42 near the first platform 41, the second platform 42 is closed by the second shutter 424, and the second electromagnetic chuck 422 attracts the second shutter 424.
From the above working principle, this embodiment 3 has the following effects:
First, through setting up first pivot 413, gear 415, first baffle 414, rack 632, can be when interfacing apparatus drive third track 63 and first track 61 dock, drive the first baffle 414 of closed state and open for first platform 41 opens, need not the constructor and opens first baffle 414 by hand, not only reduces intensity of labour, still improves and opens efficiency.
Second, when the first flap 414 is opened, because the first flap 414 can overlap the second platform 42, the first flap 414 can function to engage the first and second platforms 41, 42 in addition to closing the first platform 41, allowing a constructor to walk on the first flap 414 through the first and second platforms 41, 42. On the one hand, the risk of the constructor walking between the first platform 41 and the second platform 42 is reduced, and the safety is improved; in the second aspect, the first platform 41 and the second platform 42 are joined without using other plates temporarily, so that the joining efficiency is improved.
Third, by providing the ratchet 417 and the pawl 418, the third rail 63 can be prevented from accidentally leaving the first rail 61, the reliability of the abutting joint of the third rail 63 and the first rail 61 is ensured, and the reliability of the opening of the first baffle 414 and the overlapping joint on the second platform 42 is ensured.
Fourth, through setting up second pivot 423, second baffle 424, hollow seat 425, pressing block 426, pressing elastic element 427, pressing rod 428, round pin pole 429, can open at the in-process that first baffle 414 opened, drive second baffle 424 for second platform 42 opens, need not the workman and opens second baffle 424 by hand, is favorable to further reducing intensity of labour, further improves and opens efficiency.
Fifth, after the second baffle 424 is opened, the second baffle 424 can be located on the upper side portion of the first baffle 414, so that the second baffle 424 can not only play a role in closing the second platform 42, but also play a role in railing, so that when a constructor walks on the first baffle 414, the constructor can support the second baffle 424 to stabilize the body, and safety is improved.
Sixth, by providing the first electromagnetic chuck 412 and the second electromagnetic chuck 422, the closed state of the first shutter 414 and the second shutter 424 can be stabilized, and the safety can be further improved.
Example 4:
this example 4 is a further improvement over example 1:
The tractor 1 is provided with a first slewing bearing and a second slewing bearing. The first boom 21 and the first adjusting device are mounted on a first slewing bearing, and the second boom 22 and the second adjusting device are mounted on a second slewing bearing. The first slewing bearing is used for adjusting the horizontal deflection angle of the first suspension arm 21, and the second slewing bearing is used for adjusting the horizontal deflection angle of the second suspension arm 22. By adjusting the horizontal deflection angle of the first boom 21 and the second boom 22, it is possible to allow the first boom 21 and the second boom 22 to be displaced laterally on the tractor 1 for easy transport. The first slewing bearing and the second slewing bearing are both in the prior art.
It will be apparent to those skilled in the art that various modifications and variations can be made to the present invention without departing from the spirit or scope of the invention. Thus, it is intended that the present invention also include such modifications and alterations insofar as they come within the scope of the appended claims or the equivalents thereof.