CN118704502A - A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building - Google Patents

A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building Download PDF

Info

Publication number
CN118704502A
CN118704502A CN202411105887.0A CN202411105887A CN118704502A CN 118704502 A CN118704502 A CN 118704502A CN 202411105887 A CN202411105887 A CN 202411105887A CN 118704502 A CN118704502 A CN 118704502A
Authority
CN
China
Prior art keywords
well
construction
water
pipe
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202411105887.0A
Other languages
Chinese (zh)
Inventor
钟汰涌
汪洋
张劲松
张恒瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Construction Investment Group Co ltd
Original Assignee
Guizhou Construction Investment Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Construction Investment Group Co ltd filed Critical Guizhou Construction Investment Group Co ltd
Priority to CN202411105887.0A priority Critical patent/CN118704502A/en
Publication of CN118704502A publication Critical patent/CN118704502A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a method for dewatering a deep foundation pit pipe well close to an existing building sand-containing layer, which is characterized by comprising the following steps of; comprises the following steps of; preparing construction, determining a pipe well layout scheme, entering equipment, measuring and paying off, performing foundation pit bracing construction and completing the pipe well construction. The invention effectively ensures the safety of surrounding buildings, ensures that the filter pipe of the pipe well is not blocked in the dewatering process, completes the well sealing of the pressure-bearing and dewatering well once, and prevents the sand flowing phenomenon of the silt stratum.

Description

一种紧邻既有建筑物含流砂层深基坑管井降水施工方法A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building

技术领域Technical Field

一种紧邻既有建筑物含流砂层深基坑管井降水施工方法A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building

技术领域Technical Field

本发明属于建筑技术领域,具体来说涉及一种紧邻既有建筑物含流砂层深基坑管井降水施工方法。The invention belongs to the technical field of construction, and in particular relates to a pipe well dewatering construction method for a deep foundation pit containing a quicksand layer adjacent to an existing building.

背景技术Background Art

随着城市化进程加快,城市用地日益紧张。在既有建筑周边进行基坑开挖并支护已成为基坑施工新常态。含流砂层的地层地区广泛分布,在该地层进行基坑开挖极易引起坑内涌水涌砂、紧邻既有建筑沉降的施工难题。现有技术主要通过灵活选择降水方法和开挖方式解决上述问题,方法缺乏普适性,且忽视了含流砂层地层中砂性土颗粒对降水井的淤堵。With the acceleration of urbanization, urban land is becoming increasingly scarce. Excavating and supporting foundation pits around existing buildings has become the new normal for foundation pit construction. Strata containing quicksand layers are widely distributed, and excavating foundation pits in such strata is very likely to cause construction difficulties such as water and sand gushing in the pit and settlement of existing buildings adjacent to the pit. The existing technology mainly solves the above problems by flexibly selecting precipitation methods and excavation methods. The methods lack universality and ignore the clogging of precipitation wells by sandy soil particles in strata containing quicksand layers.

发明内容Summary of the invention

本发明的目的在于克服上述缺点而提供一种有效保证周边建筑安全,保证降水过程中管井滤管不淤堵,使承压降水井封井一次完成,防止粉砂地层流砂现象发生的紧邻既有建筑物含流砂层深基坑管井降水施工工法。The purpose of the present invention is to overcome the above-mentioned shortcomings and provide a method for effectively ensuring the safety of surrounding buildings, ensuring that the filter pipes of the pipe wells are not blocked during the precipitation process, so that the pressure precipitation wells can be sealed at one time, and preventing the occurrence of sand flow in the silt sand stratum, and preventing the occurrence of sand flow in the silt sand stratum. Deep foundation pit pipe well precipitation construction method containing quicksand layers adjacent to existing buildings.

本发明的目的及解决其主要技术问题是采用以下技术方案来实现的:The purpose of the present invention and the solution of its main technical problems are achieved by adopting the following technical solutions:

本发明的一种紧邻既有建筑物含流砂层深基坑管井降水施工方法,其特征在于;包括以下步骤;The invention discloses a method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building, which is characterized by comprising the following steps:

1)施工准备;1) Construction preparation;

结合工程地质条件、工程地质勘察报告、工程所在地水文气候条件以及待建工程周边建筑、地下电缆管线情况,根据施工总体安排对施工现场进行三通一平,确保施工现场降水施工所需的各种道路、水电管线具备条件,施工人员、施工机具、施工物资的准备工作;Combined with the engineering geological conditions, engineering geological survey reports, hydrological and climatic conditions of the project site, and the surrounding buildings and underground cable pipelines of the project to be built, the construction site shall be leveled according to the overall construction arrangement to ensure that the various roads, water and electricity pipelines required for the construction site are ready, and the construction personnel, construction machinery and materials shall be prepared;

2)确定管井布设方案;2) Determine the layout plan of the tube wells;

根据工程地质勘察报告结合基坑开挖深度选择降水方式;Select the dewatering method based on the engineering geological survey report and the excavation depth of the foundation pit;

3)设备进场;3) Equipment entering the site;

截水帷幕施工机械有三轴搅拌机及配套设备,组成隔断墙的密排钻孔灌注桩使用的有旋挖钻机及配套设备;The construction machinery for the water-blocking curtain includes a three-axis mixer and its supporting equipment, and the closely spaced bored piles that make up the partition wall include a rotary drilling rig and its supporting equipment;

4)测量放线;4) Measurement and layout;

根据提供的测量控制点,通过作图计算确定井点位置。在井位点挖小土坑,深度为300mm-500mm,井点点位与设计点位偏差不大于 50mm;According to the provided measurement control points, the well point location is determined by drawing and calculating. A small pit is dug at the well point with a depth of 300mm-500mm. The deviation between the well point location and the designed location should not exceed 50mm.

5)基坑围护施工;5) Foundation pit support construction;

基坑围护施工包括截水帷幕施工和隔断墙施工,其中;截水帷幕施工采用三轴搅拌桩作为截水帷幕,桩位放样,桩机就位,检验、调平钻机,正循环钻进至设计深度,打开高压注浆泵,反循环边喷浆边提升至设计桩面以上 0.5m,重复搅拌下钻,反循环提钻至桩顶地表后提出地面,成桩结束,下一循环水泥搅拌桩施工,桩机就位对中、调平、校正垂直度,保证机身与地面夹角为 90°,确保桩垂直度误差在 1.0%以内,所需泥浆根据设计要求配置,泥浆应充分搅拌保证均匀,制成泥浆的 pH、粘度、含砂率参数指标符合设计要求,待冷却水循环正常后启动搅拌机,放松起重机钢丝绳,使搅拌机沿导向架切土搅拌下沉,下沉速度由电机的电流监测表控制,当遇到硬土层下沉较慢时,冲水以利于钻进,搅拌机下沉至设计深度后开启灰浆泵,出口压力保持在 0.4Mpa-0.6MPa,使水泥浆连续喷入,搅拌机旋喷速度控制在0.4-0.60m/min,当提升至设计标高时,宜停止提升并搅拌数秒,以保证桩头均匀密实,为使喷入土中的水泥浆与土体充分搅拌,重复搅拌下沉直至设计要求深度,然后搅拌提升,并沿桩体在下部上下 1.0m范围内复喷,施工完毕后;The foundation pit retaining construction includes the construction of water-cutting curtain and partition wall. The water-cutting curtain construction uses three-axis mixing piles as the water-cutting curtain, the pile position is marked, the pile driver is in place, the drilling rig is inspected and leveled, the positive cycle drills to the designed depth, the high-pressure grouting pump is turned on, the reverse cycle is lifted while spraying grout to 0.5m above the designed pile surface, the mixing is repeated, the reverse cycle is lifted to the surface of the pile top and then raised to the ground, the pile is completed, the next cycle of cement mixing pile construction, the pile driver is in place, centered, leveled, and corrected for verticality, ensuring that the angle between the machine body and the ground is 90°, and the verticality error of the pile is ensured to be within 1.0%. The required mud is configured according to the design requirements, the mud should be fully stirred to ensure uniformity, and the mud is made The pH, viscosity and sand content parameters meet the design requirements. After the cooling water circulation is normal, start the mixer, loosen the crane wire rope, and let the mixer cut the soil and mix it along the guide frame. The sinking speed is controlled by the motor's current monitoring meter. When encountering a hard soil layer and sinking slowly, flush water to facilitate drilling. After the mixer sinks to the designed depth, turn on the mortar pump, and keep the outlet pressure at 0.4Mpa-0.6MPa to spray cement slurry continuously. The mixer's rotary spraying speed is controlled at 0.4-0.60m/min. When it is lifted to the designed elevation, it is advisable to stop lifting and stirring for a few seconds to ensure that the pile head is evenly compacted. In order to fully mix the cement slurry sprayed into the soil with the soil, repeat the stirring and sinking until the required design depth, then stir and lift, and spray again along the pile body within 1.0m above and below. After the construction is completed;

其中;隔断墙施工是向集料斗中注入适量清水,开启灰浆泵,清洗管道中的残积水泥浆,同时清除钻头粘附土,搅拌桩水泥含量质量比不得小于土重15%-20%;搅拌桩采用 P.O. 42.5 普通硅酸盐水泥,水灰比为 1﹕0.5;压浆提升速度控制在0.3-0.5m/min;桩身垂直度偏差不得超过 1.0%,桩位偏差不得大于 50mm;桩体压浆要求一气呵成、不得中断,每根桩宜装浆一次并喷搅完成;要求连续施工,桩搭接穿插交叉施工,相邻两桩施工间隔不得超过 12h;如超过,应采取在两桩中部加桩补救;施工过程因故停浆,宜将搅拌机下沉至停浆点下 500mm,恢复供浆后再搅拌提升,拌时采用三喷三搅施工工艺;Among them; the construction of partition wall is to inject a proper amount of clean water into the aggregate hopper, turn on the mortar pump, clean the residual cement slurry in the pipeline, and remove the soil adhering to the drill bit. The cement content of the mixing pile shall not be less than 15%-20% of the soil weight; the mixing pile adopts P.O. 42.5 ordinary silicate cement, and the water-cement ratio is 1:0.5; the grouting lifting speed is controlled at 0.3-0.5m/min; the verticality deviation of the pile body shall not exceed 1.0%, and the pile position deviation shall not exceed 50mm; the grouting of the pile body is required to be completed in one go and shall not be interrupted. Each pile should be filled with grout once and sprayed and mixed; continuous construction is required, and the piles are overlapped and cross-constructed. The interval between the construction of two adjacent piles shall not exceed 12h; if it exceeds, a pile should be added in the middle of the two piles to remedy the situation; if the grouting is stopped for some reason during the construction process, the mixer should be sunk to 500mm below the grouting stop point, and the grouting and lifting should be resumed after the grouting is restored. The three-spraying and three-mixing construction process should be adopted during mixing;

6)管井施工;6) Pipe well construction;

管井施工包括钻孔、清孔、回填井底砂垫层、滤管段放淤堵、下井管并回填滤料、调试与试抽水、正式抽水、封井;Pipe well construction includes drilling, hole cleaning, backfilling the well bottom sand cushion, declogging the filter pipe section, lowering the well pipe and backfilling the filter material, debugging and test pumping, formal pumping, and well sealing;

A.钻孔;钻机移动至井点位,调整钻机,保证钻机平衡、牢固,钻井过程中不发生偏移、倾斜;A. Drilling: Move the drilling rig to the well site and adjust the drilling rig to ensure that it is balanced and firm, and does not deviate or tilt during the drilling process;

B.清孔;成孔完成后应及时清孔,清孔时采用足够长度的软胶管插入井底进行注水清孔,直至流出清水为止,应逐孔进行清洗,避免出现死井;B. Hole cleaning: After the hole is completed, it should be cleaned in time. When cleaning the hole, a soft rubber hose of sufficient length is inserted into the bottom of the well to inject water to clean the hole until clean water flows out. The hole should be cleaned one by one to avoid dead wells;

C.回填井底砂垫层;清孔完成后回填井底砂垫层,回填滤料、砂垫层厚度应满足要求;C. Backfill the sand cushion layer at the bottom of the well; after the hole is cleaned, backfill the sand cushion layer at the bottom of the well. The thickness of the backfill filter material and sand cushion layer should meet the requirements;

D.管段防淤堵;针对含流砂层层地质情况,井点管安管前应先对滤管段进行处理,在滤管段外侧包裹粗、细两层纤维的针刺非织造土工织物即土工布;D. Anti-clogging of pipe sections: In view of the geological conditions of quicksand layers, the filter pipe section should be treated before the well point pipe is installed, and the outer side of the filter pipe section should be wrapped with a needle-punched non-woven geotextile with two layers of coarse and fine fibers, i.e., geotextile;

E.下井管并回填滤料;把组装好的滤管通过吊车起吊至清孔后的管井孔内,井管固定好后下放滤料;E. Lower the well pipe and backfill the filter material; lift the assembled filter pipe by crane to the well hole after the hole is cleaned, and lower the filter material after the well pipe is fixed;

F.调试与试抽水;在正式抽水前必须试抽,以检查抽水设备运转是否正常,在基坑中心设置观测井点,调试与试抽水完成后正式抽水;F. Debugging and trial pumping: Before formal pumping, trial pumping must be carried out to check whether the pumping equipment is operating normally. An observation well point is set up in the center of the foundation pit. After debugging and trial pumping are completed, formal pumping will be carried out;

G.正式抽水;调试与试抽水完成后抽水;G. Formal pumping: pumping after commissioning and trial pumping are completed;

H封井;根据管井所处位置,封井分为正常封井和基坑承压降水井封底,结构底板施工完成,基坑内施工完成的部分满足主体结构抗浮要求;基坑降水井井内稳定水位位于基坑面以下 2m-3m,基坑承压降水井封底,保持承压降水井水位处于静止状态,采用优质黏土对承压降水井填充,填充高度应比滤管高出2m-3m,待黏土完全沉淀稳定,用水泵将水抽出,用水位计测量承压水渗透情况,将含砂率小的黏土、水泥按体积比 1﹕1 充分混合后加水拌合制成球状,对承压降水井填充,填充高度约 2m,用水位计检测承压水渗透情况;向承压降水井填入瓜子片和砂的拌合物,砂石拌合物的回填高度应在基坑底板以上 2m,用钢筋将注浆管与井口固定后开始注浆,使水泥浆通过瓜子片的空隙渗入井管缝隙;到达水泥浆的初凝时间后,割除井管至底板面以下 0.5m;观测 2h-4h,若井管内有少量水溢出,使用快干水泥对井管封闭;若井管内无水溢出且封闭效果满足要求,焊接钢板封闭井口;将承压降水井预留的基坑混凝土底板周边凿毛,垃圾清理完成后绑扎钢筋进行二次混凝土浇筑。H. Well sealing; according to the location of the pipe well, well sealing is divided into normal well sealing and bottom sealing of foundation pit pressure dewatering well, the structural bottom plate construction is completed, and the completed part in the foundation pit meets the anti-floating requirements of the main structure; the stable water level in the foundation pit dewatering well is 2m-3m below the foundation pit surface, the bottom of the foundation pit pressure dewatering well is sealed, and the water level of the pressure dewatering well is kept in a static state. The pressure dewatering well is filled with high-quality clay, and the filling height should be 2m-3m higher than the filter tube. After the clay is completely settled and stabilized, the water is pumped out with a water pump, and the pressure water penetration is measured with a water level meter. Clay and cement with a low sand content are fully mixed in a volume ratio of 1:1, and then water is added to mix them into balls, which are filled in the pressure dewatering well. The filling height is about 2m, and the pressure water penetration is detected with a water level meter; a mixture of melon seeds and sand is filled into the pressure dewatering well, and the backfill height of the sand and gravel mixture should be above the foundation pit bottom plate. 2m, fix the grouting pipe to the wellhead with steel bars and start grouting, so that the cement slurry penetrates into the gaps of the well pipe through the gaps of the melon seed slices; after the initial setting time of the cement slurry is reached, cut the well pipe to 0.5m below the bottom plate surface; observe for 2h-4h, if a small amount of water overflows from the well pipe, use quick-drying cement to seal the well pipe; if there is no water overflow from the well pipe and the sealing effect meets the requirements, weld the steel plate to seal the wellhead; roughen the periphery of the concrete bottom plate of the foundation pit reserved for the pressure-bearing dewatering well, and after the garbage is cleaned up, tie the steel bars for secondary concrete pouring.

步骤1)中所述的三通一平是水通、电通、道路通和场地平整。The three connections and one leveling mentioned in step 1) are water connection, electricity connection, road connection and site leveling.

步骤2)中所述的降水方式是明排水、管井降水。The precipitation method described in step 2) is open drainage and pipe well precipitation.

步骤5)中所述的三喷三搅是‌将桩机定位在预定的施工位置,‌接着,‌通过钻杆下沉到预定的深度,‌在达到设计深度后,‌边搅拌边提升钻杆,‌同时喷浆,‌提升后,‌再次下沉到设计深度,‌再次边搅拌边提升钻杆,‌进行喷浆,‌完成上述步骤后,‌停止喷浆。The three-spraying and three-mixing described in step 5) is to position the pile driver at the predetermined construction position, then, sink the drill rod to the predetermined depth, after reaching the designed depth, lift the drill rod while stirring, and spray grout at the same time, after lifting, sink to the designed depth again, lift the drill rod while stirring again, and spray grout, after completing the above steps, stop spraying.

本发明与现有技术相比,具有明显的有益效果;从以上技术方案可知:通过管井降水是用水泵排除土体中的水分,减小或消除土体中的动水压力,提高基坑稳定性,此外,由于渗流向下,在动水压力作用下,管井降水可使坑底土层趋于密实。采用管井降水降低地下水位,可使施工人员在无水、干燥的环境下进行土方开挖和基础施工,不仅可避免涌水、涌砂、冒泥、翻浆,而且有效防止粉砂地层流砂现象的发生。高压旋喷桩、搅拌桩等截水帷幕施工时,由于含流砂层层渗透系数大,层内地下水动水压力大、水流速度快,导致水泥浆尚未硬化形成强度即被地下水冲散,不能完全隔断坑内外的地下水联系,造成紧邻既有建筑沉降。通过在紧邻既有建筑和基坑支护结构之间设置隔断墙(密排钻孔灌注桩),在隔断墙与基坑围护结构间双液注浆(硅酸盐水泥、水玻璃),可在建筑与基坑之间形成有效防护,隔断坑内外地下水联系,有效减小基坑降水对紧邻既有建筑的影响,防止建筑沉降。在管井滤管段上包裹粗细维度不同的 2 层针刺非织造土工织物(土工布)可有效防止粉砂造成的滤管段淤堵。外层 8D 维度的针刺非织造土工织物对粉砂进行第一层阻隔,内侧 6D 维度的针刺非织造土工织物对粉砂进行二次阻隔。D(旦尼尔)是密度单位,用于衡量纤维细度,指9000m 长的纤维在公定回潮率时的质量克数。8D 维度的针刺非织造土工织物由 8D 纤维制成,9000m 长的 8D 纤维在公定回潮率时的质量克数为 8g。粉砂颗粒粒径不一,粒径较大的颗粒由外层 8D 维度的针刺非织造土工织物阻挡。粒径适中的颗粒通过外层土工织物后,由内层 6D 维度的针刺非织造土工织物阻挡。粒径较小的颗粒通过两层非织造土工织物进入井管,不会造成淤堵。含流砂层层渗透系数大,引起承压降水井井管内地下水补给较快。管井抽水停止后,井内水位快速上升。井口水泥砂浆溶解于水中不能硬化,严重减慢施工进度,降低施工质量。本工法采用粘土拌合水泥制成球状,对承压降水井进行填充,可阻止井管内地下水上升,为顺利封井创造有利条件。总之;本发明有效保证周边建筑安全,保证降水过程中管井滤管不淤堵,可使承压降水井封井一次完成,防止粉砂地层流砂现象发生。Compared with the prior art, the present invention has obvious beneficial effects. It can be seen from the above technical scheme that the pipe well dewatering is to remove the moisture in the soil with a water pump, reduce or eliminate the dynamic water pressure in the soil, and improve the stability of the foundation pit. In addition, due to the downward seepage, under the action of dynamic water pressure, the pipe well dewatering can make the soil layer at the bottom of the pit tend to be dense. The use of pipe well dewatering to lower the groundwater level allows construction personnel to carry out earthwork excavation and foundation construction in a waterless and dry environment, which can not only avoid water gushing, sand gushing, mud bubbling, and slurry overflow, but also effectively prevent the occurrence of sand flow in silt sand formations. When constructing water-cutting curtains such as high-pressure jet grouting piles and mixing piles, due to the large permeability coefficient of the layer containing quicksand, the dynamic water pressure of the groundwater in the layer is large, and the water flow speed is fast, resulting in the cement slurry being dispersed by groundwater before it hardens and forms strength, and the groundwater connection inside and outside the pit cannot be completely cut off, causing the settlement of the existing buildings adjacent to it. By setting up partition walls (closely spaced bored piles) between the existing buildings and the foundation pit support structure, and double-liquid grouting (Portland cement, water glass) between the partition walls and the foundation pit retaining structure, effective protection can be formed between the building and the foundation pit, isolating the groundwater connection inside and outside the pit, effectively reducing the impact of foundation pit precipitation on the existing buildings adjacent to it, and preventing building settlement. Wrapping the filter pipe section of the pipe well with two layers of needle-punched nonwoven geotextiles (geotextiles) of different coarse and fine dimensions can effectively prevent the filter pipe section from being blocked by silt sand. The outer 8D needle-punched nonwoven geotextile provides the first layer of barrier for silt sand, and the inner 6D needle-punched nonwoven geotextile provides the second layer of barrier for silt sand. D (denier) is a unit of density used to measure fiber fineness, referring to the mass of 9000m long fiber at the standard moisture regain. The 8D needle-punched nonwoven geotextile is made of 8D fiber. The mass of 9000m long 8D fiber at the standard regain is 8g. The particle size of silt particles varies. The larger particles are blocked by the outer 8D needle-punched nonwoven geotextile. After the particles with moderate particle size pass through the outer geotextile, they are blocked by the inner 6D needle-punched nonwoven geotextile. The particles with smaller particle size enter the well pipe through two layers of nonwoven geotextile without causing clogging. The permeability coefficient of the layer containing quicksand is large, which causes the groundwater to be replenished faster in the well pipe of the pressure dewatering well. After the well pumping stops, the water level in the well rises rapidly. The cement mortar at the wellhead dissolves in water and cannot harden, which seriously slows down the construction progress and reduces the construction quality. This method uses clay mixed with cement to make balls to fill the pressure dewatering well, which can prevent the groundwater in the well pipe from rising and create favorable conditions for the smooth sealing of the well. In conclusion, the present invention effectively ensures the safety of surrounding buildings and ensures that the filter pipes of the pipe wells are not blocked during the precipitation process, and can seal the pressure precipitation wells in one go to prevent the occurrence of sand flow in silt sand formations.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1是本发明的工艺流程图;Figure 1 is a process flow chart of the present invention;

图2是本发明的管井降水原理示意图;Fig. 2 is a schematic diagram of the principle of water reduction in a tube well of the present invention;

图3是本发明的防淤堵示意图a;FIG3 is a schematic diagram a of the anti-clogging method of the present invention;

图4是本发明的防淤堵示意图b;FIG4 is a schematic diagram b of the anti-clogging method of the present invention;

图5是本发明的加固示意图;FIG5 is a schematic diagram of reinforcement of the present invention;

图6是本发明的管井剖面图;Fig. 6 is a cross-sectional view of a tube well of the present invention;

图7是本发明的承压降水井封井示意图。FIG. 7 is a schematic diagram of sealing a pressure dewatering well according to the present invention.

具体实施方式DETAILED DESCRIPTION

以下结合附图及较佳实施例,对依据本发明的具体实施方式、结构、特征及其功效,详细说明如后。The specific implementation methods, structures, features and functions of the present invention are described in detail below in conjunction with the accompanying drawings and preferred embodiments.

实施例1Example 1

一种紧邻既有建筑物含流砂层深基坑管井降水施工方法,其特征在于;包括以下步骤;A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building, characterized by comprising the following steps:

1)施工准备1) Construction preparation

结合工程地质条件、工程地质勘察报告、工程所在地水文气候条件以及待建工程周边建筑、地下电缆管线等情况,根据施工总体安排对施工现场进行“三通一平”,同时开展施工队伍的招标工作,确保施工现场降水施工所需的各种道路、水电管线具备条件。确定好施工队伍后,结合施工队伍的意见编制施工方案,并要求施工队伍按照报批获准后的施工方案做好施工人员、施工机具、施工物资等的准备工作。施工前相关技术人员应编制安全技术交底,对施工作业人员书面交底,并签字留底。Combined with the engineering geological conditions, engineering geological survey reports, hydrological and climatic conditions of the project site, and surrounding buildings and underground cables and pipelines of the project to be built, the construction site is "three connections and one leveling" according to the overall construction arrangement, and the construction team is invited to bid to ensure that the various roads, water and electricity pipelines required for the construction site precipitation construction are available. After the construction team is determined, a construction plan is prepared in combination with the opinions of the construction team, and the construction team is required to prepare construction personnel, construction machinery and tools, construction materials, etc. in accordance with the construction plan after approval. Before construction, relevant technical personnel should prepare safety technical disclosures, give written disclosures to construction workers, and sign and keep a record.

2)确定管井布设方案2) Determine the layout plan of the pipe well

根据工程地质勘察报告结合基坑开挖深度选择降水方式。管井降水适用于以下情况:对于渗透系数大于10-4cm/s,地下水丰富的砂土、砂质粉土、粉土与碎石土等土层,用明排水易造成土颗粒大量流失,用轻型井点难以满足降水要求,采用管井降水。管井一般沿基坑周围离边坡上缘 0.5m-1.5m 呈环形布置;当基坑深度较窄,在一侧呈直线形布置;当为面积不大的独立基坑时,采取点式布置。井中心距基坑边缘的距离,依据所用钻机的钻孔方法而定;管井的最大埋设深度达 10m,间距为 10m-50m,降水深度达5m。Select the dewatering method according to the engineering geological survey report and the excavation depth of the foundation pit. Pipe well dewatering is suitable for the following situations: For soil layers with a permeability coefficient greater than 10-4cm/s and abundant groundwater, such as sandy soil, sandy silt, silt and gravel soil, open drainage is prone to cause a large amount of soil particles to be lost, and it is difficult to meet the dewatering requirements with light well points. Pipe well dewatering is adopted. Pipe wells are generally arranged in a ring around the foundation pit 0.5m-1.5m away from the upper edge of the slope; when the foundation pit is narrow, it is arranged in a straight line on one side; when it is an independent foundation pit with a small area, a point arrangement is adopted. The distance from the center of the well to the edge of the foundation pit depends on the drilling method of the drilling rig used; the maximum burial depth of the pipe well is 10m, the spacing is 10m-50m, and the dewatering depth is 5m.

3)设备进场3) Equipment arrival

截水帷幕施工机械有三轴搅拌机及配套设备。组成隔断墙的密排钻孔灌注桩使用的有旋挖钻机及配套设备,管井降水设备主要包括井管和抽水设备等。抽水设备为真空抽水泵。真空抽水泵配套的有配电箱电缆以及备用的柴油发电机。成井设备有回旋钻机及配套设备,辅助使用有汽车吊、运输车、全站仪、经纬仪。The construction machinery for water-blocking curtains includes three-axis mixers and supporting equipment. The densely-packed bored piles that make up the partition wall use rotary drilling rigs and supporting equipment. The pipe well dewatering equipment mainly includes well pipes and pumping equipment. The pumping equipment is a vacuum pump. The vacuum pump is equipped with a distribution box cable and a spare diesel generator. The well-forming equipment includes a rotary drilling rig and supporting equipment, and auxiliary equipment includes a truck crane, a transport vehicle, a total station, and a theodolite.

4)测量放线4) Measurement and layout

根据提供的测量控制点,通过作图计算确定井点位置。在井位点挖小土坑,深度为300mm-500mm。井点点位与设计点位偏差不得大于 50mm。According to the provided measurement control points, the well point location is determined by drawing and calculating. A small pit is dug at the well point location with a depth of 300mm-500mm. The deviation between the well point location and the designed location shall not exceed 50mm.

)截水帷幕施工) Water cut-off curtain construction

与双轴搅拌桩相比,三轴搅拌桩施工速度快、搅拌均匀、无泥浆、成品质量好,因此采用三轴搅拌桩作为截水帷幕,截水帷幕的施工工艺流程为:桩位放样、桩机就位、检验、调平钻机、正循环钻进至设计深度、打开高压注浆泵、反循环边喷浆边提升至设计桩面以上0.5m、重复搅拌下钻、反循环提钻至桩顶地表后提出地面、成桩结束、下一循环水泥搅拌桩施工。Compared with double-axis mixing piles, three-axis mixing piles have fast construction speed, uniform mixing, no mud, and good finished product quality. Therefore, three-axis mixing piles are used as water-cutting curtains. The construction process of water-cutting curtains is as follows: pile position layout, pile driver positioning, inspection, leveling of drilling rigs, positive cycle drilling to the designed depth, turning on the high-pressure grouting pump, reverse circulation while spraying and lifting to 0.5m above the designed pile surface, repeated mixing and drilling, reverse circulation lifting the drill to the surface of the pile top and then lifting it out of the ground, the pile is completed, and the next cycle of cement mixing piles is constructed.

A桩机就位:桩机就位后检查钻杆长度、钻头直径,然后对中、调平、校正垂直度,保证机身与地面夹角为 90°,确保桩垂直度误差在 1.0%以内。A. Pile driver in place: After the pile driver is in place, check the drill rod length and drill bit diameter, then center, level and correct the verticality to ensure that the angle between the machine body and the ground is 90° and that the pile verticality error is within 1.0%.

制备泥浆:所需泥浆根据设计要求配置,泥浆应充分搅拌保证均匀。制成泥浆的pH、粘度、含砂率等参数指标符合设计要求。Preparation of mud: The required mud is prepared according to the design requirements, and the mud should be fully stirred to ensure uniformity. The pH, viscosity, sand content and other parameters of the prepared mud meet the design requirements.

搅拌下沉:待冷却水循环正常后启动搅拌机,放松起重机钢丝绳,使搅拌机沿导向架切土搅拌下沉,下沉速度由电机的电流监测表控制。预拌时不宜冲水;当遇到硬土层下沉较慢时,冲水以利于钻进。Stirring and sinking: After the cooling water circulation is normal, start the mixer, loosen the crane wire rope, and let the mixer cut the soil and sink along the guide frame. The sinking speed is controlled by the motor's current monitoring meter. It is not advisable to flush water during pre-mixing; when encountering a hard soil layer and the sinking is slow, flush water to facilitate drilling.

搅拌提升:搅拌机下沉至设计深度后开启灰浆泵,出口压力保持在 0.4Mpa-0.6MPa,使水泥浆连续喷入。搅拌机旋喷速度控制在 0.5m/min 左右。当提升至设计标高时,宜停止提升并搅拌数秒,以保证桩头均匀密实。Mixing and lifting: After the mixer sinks to the designed depth, start the mortar pump and keep the outlet pressure at 0.4Mpa-0.6MPa to spray cement slurry continuously. The mixer's rotary spraying speed is controlled at about 0.5m/min. When it is lifted to the designed elevation, it is advisable to stop lifting and stir for a few seconds to ensure that the pile head is evenly compacted.

重复搅拌下沉与提升:为使喷入土中的水泥浆与土体充分搅拌,重复搅拌下沉直至设计要求深度。然后搅拌提升,并沿桩体在下部上下 1.0m范围内复喷。施工完毕后,向集料斗中注入适量清水,开启灰浆泵,清洗管道中的残积水泥浆,同时清除钻头粘附土。Repeated mixing, sinking and lifting: In order to fully mix the cement slurry sprayed into the soil with the soil, repeatedly stir and sink until the required depth. Then stir and lift, and spray again within 1.0m above and below the pile body. After the construction is completed, inject an appropriate amount of clean water into the aggregate hopper, turn on the mortar pump, clean the residual cement slurry in the pipeline, and remove the soil adhering to the drill bit.

其中;搅拌桩水泥含量不得小于土重的 12%(质量比),根据经验建议将水泥用量调整至15%-20%;搅拌桩采用 P. O. 42.5 普通硅酸盐水泥,水灰比为 1﹕0.5;压浆提升速度控制在 0.5m/min 以内;桩身垂直度偏差不得超过 1.0%,桩位偏差不得大于 50mm;桩体压浆要求一气呵成、不得中断,每根桩宜装浆一次并喷搅完成;要求连续施工,桩搭接穿插交叉施工,相邻两桩施工间隔不得超过 12h;如超过,应采取在两桩中部加桩补救;施工过程因故停浆,宜将搅拌机下沉至停浆点下 500mm,恢复供浆后再搅拌提升,拌时采用“三喷三搅”施工工艺;搅拌头翼片的枚数、宽度与搅拌轴的垂直夹角、搅拌头的回转数、提升速度相匹配, 确保加固深度范围内土体的搅拌次数满足设计要求,支护结构施工;钻孔灌注桩适用性强、振动小、噪音低,因此采用钻孔灌注桩作为支护结构。The cement content of the mixing pile shall not be less than 12% of the soil weight (mass ratio). According to experience, it is recommended to adjust the cement dosage to 15%-20%. The mixing pile adopts P.O. 42.5 ordinary silicate cement with a water-cement ratio of 1:0.5. The grouting and lifting speed is controlled within 0.5m/min. The verticality deviation of the pile body shall not exceed 1.0%, and the pile position deviation shall not be greater than 50mm. The grouting of the pile body is required to be completed in one go without interruption. Each pile should be filled with grout once and sprayed. Continuous construction is required, and the piles are overlapped and cross-constructed. The construction interval between two adjacent piles shall not exceed 12h. If exceeded, a pile should be added in the middle of the two piles to remedy the situation. If the grouting is stopped for some reason during the construction process, the mixer should be sunk to 500mm below the grouting stop point, and the grouting and lifting should be resumed after the grouting is restored. The "three spraying and three mixing" construction process should be adopted during mixing. The number and width of the blades of the mixing head should match the vertical angle of the mixing shaft, the number of rotations of the mixing head, and the lifting speed. Ensure that the mixing times of the soil within the reinforcement depth range meet the design requirements and the support structure is constructed; bored cast-in-place piles have strong applicability, small vibration and low noise, so bored cast-in-place piles are used as the support structure.

其中;钻孔灌注桩施工过程中成孔孔径、垂直度须满足要求;下放钢筋笼时须注意钢筋笼不要碰撞到孔壁,钢筋笼就位后固定牢固;清孔后的沉渣厚度要满足要求,清孔后及时进行水下混凝土的浇筑工作;因故超过 4h 不能浇筑水下混凝土时应重新进行清孔;浇筑水下混凝土时,混凝土的质量、粗骨料的粒径、混凝土的坍落度等技术指标应满足要求;混凝土浇筑过程中要严格控制导管的拔出速度,严禁导管拔出泥浆面;初灌时导管埋深0.5m-1m,正常灌注时导管埋深2m-6m;混凝土浇筑后的高度要超出设计标高 0.5m-1m;须特别注意含流砂层地层对成桩质量的影响。Among them; the hole diameter and verticality of the bored pile construction process must meet the requirements; when lowering the steel cage, care must be taken not to let the steel cage collide with the hole wall, and the steel cage must be firmly fixed in place; the thickness of the sediment after cleaning the hole must meet the requirements, and underwater concrete pouring must be carried out in time after cleaning the hole; if for some reason underwater concrete cannot be poured for more than 4 hours, the hole should be cleaned again; when pouring underwater concrete, technical indicators such as the quality of concrete, the particle size of coarse aggregate, and the slump of concrete should meet the requirements; during the concrete pouring process, the speed of pulling out the catheter must be strictly controlled, and it is strictly forbidden to pull the catheter out of the mud surface; the catheter is buried 0.5m-1m deep during initial pouring, and 2m-6m deep during normal pouring; the height after concrete pouring must exceed the design elevation by 0.5m-1m; special attention must be paid to the impact of the quicksand layer on the quality of the pile.

6)隔断墙施工6) Partition wall construction

为防止降水影响范围内紧邻既有建筑的沉降,在基坑支护结构与紧邻既有建筑间设置隔断墙,隔断墙的深度比基坑围护结构深度深 2m 以上,隔断墙采用密排钻孔灌注桩。双液注浆施工,隔断墙施工完成后,在隔断墙与基坑支护结构中间双液注浆。双液浆由水泥浆与水玻璃掺合而成。水泥浆由硅酸盐水泥和水组成, 水泥浆和水玻璃组成的掺合物初凝时间为0.5min-1.5min。掺合物中硅酸盐水泥、水、水玻璃的比例为 1﹕0.5﹕0.05。用制成的双液浆在隔断墙与基坑支护结构之间进行注浆加固,根据紧邻既有建筑的距离决定注浆为一排或多排。In order to prevent the settlement of the existing buildings adjacent to the foundation pit within the influence range of precipitation, a partition wall is set between the foundation pit support structure and the adjacent existing building. The depth of the partition wall is more than 2m deeper than the depth of the foundation pit retaining structure, and the partition wall adopts densely arranged bored piles. Double liquid grouting construction: after the construction of the partition wall is completed, double liquid grouting is performed between the partition wall and the foundation pit support structure. Double liquid grout is made of cement slurry and water glass. Cement slurry is composed of silicate cement and water. The initial setting time of the mixture composed of cement slurry and water glass is 0.5min-1.5min. The ratio of silicate cement, water and water glass in the mixture is 1:0.5:0.05. The prepared double liquid slurry is used for grouting reinforcement between the partition wall and the foundation pit support structure. The grouting is determined to be one row or more rows according to the distance to the adjacent existing building.

其中;双液注浆施工过程中采用地质钻机从地面垂直钻孔,成孔速度快、可靠性高、垂直度易控制,可查清漏水、待加固区地层,可知该钻孔与即将处理的漏点是否连通,在钻进过程中查明是否有掏空 现象;针对不同地层采取不同注浆参数,提高注浆加固的均一性,确保注浆效果;Among them; During the double-liquid grouting construction process, a geological drill is used to drill vertically from the ground. The hole-making speed is fast, the reliability is high, and the verticality is easy to control. It can be used to find out the leakage and the stratum in the area to be reinforced. It can be known whether the borehole is connected to the leakage point to be treated, and whether there is hollowing phenomenon during the drilling process; different grouting parameters are adopted for different strata to improve the uniformity of grouting reinforcement and ensure the grouting effect;

采取适当的浆液比,控制注浆压力指标,保证注浆效果,控制地表隆起,注浆完成后,随基坑降水开挖的进行,对紧邻既有建筑进行沉降观测,如沉降变化超出预计范围应在隔断墙与基坑支护结构间增加双液注浆量。Adopt appropriate slurry ratio, control grouting pressure index, ensure grouting effect, and control surface uplift. After grouting is completed, as the foundation pit dewatering and excavation proceed, conduct settlement observations on adjacent existing buildings. If the settlement change exceeds the expected range, increase the double-liquid grouting volume between the partition wall and the foundation pit support structure.

7)钻孔7) Drilling

钻机移动至井点位,调整钻机,保证钻机平衡、牢固,钻井过程中不发生偏移、倾斜。管井孔采用泥浆护壁成孔,孔口设置护筒以防孔口塌方,并在一侧设排泥沟、泥浆池。成孔后保证井点管距坑壁不小于 1.0m-1.5m(若距离过小易漏气),成孔后井点间距为 0.8m-1.6m。井点管的入土深度应根据降水深度及储水层所在位置决定,但必须将滤管埋入含水层内,并且比基坑(沟、槽)底深0.9m-1.2m。井点管的埋置深度应计算确定。降水井井点间距约为10m-15m。管井钻孔完成后应检查孔口直径、管井垂直度,保证成孔后井点管可顺利插至孔底。井点管与孔壁应留有回填滤料间隙。成孔后检查孔内泥浆性能,保证不塌孔、缩径。Move the drilling rig to the well point, adjust the drilling rig, ensure that the drilling rig is balanced and firm, and there is no deviation or tilt during the drilling process. The tube well hole is drilled with mud wall protection, and a casing is set at the hole mouth to prevent the hole mouth from collapsing. A mud drainage ditch and a mud pool are set on one side. After drilling, ensure that the distance between the well point pipe and the pit wall is not less than 1.0m-1.5m (if the distance is too small, it is easy to leak), and the spacing between the well points after drilling is 0.8m-1.6m. The depth of the well point pipe buried in the ground should be determined according to the precipitation depth and the location of the aquifer, but the filter pipe must be buried in the aquifer and 0.9m-1.2m deeper than the bottom of the foundation pit (ditch, trench). The burial depth of the well point pipe should be calculated and determined. The spacing between the precipitation well points is about 10m-15m. After the tube well is drilled, the hole diameter and the verticality of the tube well should be checked to ensure that the well point pipe can be smoothly inserted to the bottom of the hole after drilling. There should be a gap between the well point pipe and the hole wall for backfilling filter material. After drilling, check the mud properties in the hole to ensure that there is no hole collapse or diameter shrinkage.

8)清孔8) Cleaning holes

成孔完成后应及时清孔,清孔时采用足够长度的软胶管插入井底进行注水清孔,直至流出清水为止。应逐孔进行清洗,避免出现死井。After the hole is completed, it should be cleaned in time. When cleaning the hole, a soft rubber hose of sufficient length is inserted into the bottom of the well to inject water to clean the hole until clear water flows out. Cleaning should be carried out hole by hole to avoid dead wells.

9)回填井底砂垫层9) Backfill the sand cushion at the bottom of the well

清孔完成后回填井底砂垫层,回填滤料、砂垫层厚度应满足要求。After the hole is cleaned, the sand cushion layer at the bottom of the well should be backfilled. The thickness of the backfill filter material and sand cushion layer should meet the requirements.

10)滤管段防淤堵10) Anti-clogging of filter tube section

针对含流砂层层地质情况,井点管安管前应先对滤管段进行处理,在滤管段外侧包裹粗、细两层纤维的针刺非织造土工织物(土工布)。其中,外侧粗纤维针刺非织造土工织物由 8D 纤维制成,内侧细纤维针刺非织造土工织物由 6D 纤维制成。两层不同粗细维度的针刺非织造土工织物应分开绑扎。内层 6D 维度的针刺非织造土工织物绑扎牢固后,再进行外侧 8D 维度针刺非织造土工织物的绑扎。两层不同粗细维度针刺非织造土工织物之间的接缝不能重叠, 接缝上下应错开 500mm 以上。In view of the geological conditions of the quicksand layer, the filter pipe section should be treated before the well point pipe is installed, and the outer side of the filter pipe section should be wrapped with two layers of coarse and fine fiber needle-punched nonwoven geotextiles (geotextiles). Among them, the outer coarse fiber needle-punched nonwoven geotextile is made of 8D fiber, and the inner fine fiber needle-punched nonwoven geotextile is made of 6D fiber. The two layers of needle-punched nonwoven geotextiles of different coarse and fine dimensions should be tied separately. After the inner layer of 6D dimensional needle-punched nonwoven geotextile is tied firmly, the outer layer of 8D dimensional needle-punched nonwoven geotextile should be tied. The seams between the two layers of needle-punched nonwoven geotextiles of different coarse and fine dimensions cannot overlap, and the seams should be staggered by more than 500mm.

11)下井管并回填滤料11) Lower the well pipe and backfill the filter material

把组装好的滤管通过吊车起吊至清孔后的管井孔内。吊装时防止滤管碰撞井壁。井点管的垂直度应满足要求,保证井点管中心与井口中心重合,井点管与井壁间距均匀,满足下放滤料的要求。井点管分节下放时,每节之间应有固定措施(节与节之间采用 3-4 根长度为100mm 的竹条或木方通过钢丝绑扎固定),防止上、下节错位。井点管多为金属管、无砂混凝土管、PVC 管,井点管下端有开孔的滤管段,滤管段长度一般为 1m。滤管段与井点管及井点管与井点管之间采用软管连接,连接要牢固并经过试验,保证不漏气。集水总管一般为 PVC 管,标高应尽量接近地下水位线,在安装时沿抽水水流方向保持 0.25%-0.5%的上仰坡度。井管拼装就位后,井管要高出地面 500mm 以上并加盖,防止雨水或泥水进入井管。井管固定好后下放滤料,所选滤料应有良好的渗水、透水性,具体要求如下:Lift the assembled filter pipe by crane into the wellbore after the hole is cleaned. Prevent the filter pipe from colliding with the well wall during lifting. The verticality of the well point pipe should meet the requirements, ensure that the center of the well point pipe coincides with the center of the wellhead, and the spacing between the well point pipe and the well wall is uniform, meeting the requirements for lowering the filter material. When the well point pipe is lowered in sections, there should be fixing measures between each section (3-4 bamboo strips or wooden squares with a length of 100mm are used between the sections and fixed by steel wire binding) to prevent the upper and lower sections from being misaligned. Well point pipes are mostly metal pipes, sandless concrete pipes, and PVC pipes. There is a filter pipe section with an opening at the bottom of the well point pipe, and the length of the filter pipe section is generally 1m. The filter pipe section and the well point pipe and the well point pipes are connected by hoses. The connection must be firm and tested to ensure that there is no air leakage. The main water collection pipe is generally a PVC pipe, and the elevation should be as close to the groundwater level as possible. During installation, the upward slope should be maintained at 0.25%-0.5% along the direction of the pumping water flow. After the well pipe is assembled in place, the well pipe should be more than 500mm above the ground and covered to prevent rainwater or muddy water from entering the well pipe. After the well pipe is fixed, the filter material is placed down. The selected filter material should have good water seepage and permeability. The specific requirements are as follows:

A.砂石必须采用粗砂,直径 2mm-4mm;A. The sand and gravel must be coarse sand with a diameter of 2mm-4mm;

B.滤管应放置在井孔中间,砂石滤层的厚度应到原地面,以提高透水性,并防止土粒渗入滤管堵塞滤管网眼;填砂厚度要均匀,速度要快,将泥浆挤出井孔;填料应用铁锹下料, 以防下料不均匀或冲击井壁;填砂过程不得中断,以防孔壁塌土;B. The filter tube should be placed in the middle of the wellbore, and the thickness of the sand and gravel filter layer should reach the original ground to improve water permeability and prevent soil particles from penetrating into the filter tube and blocking the filter mesh; the sand filling thickness should be uniform and the speed should be fast to squeeze the mud out of the wellbore; the filler should be placed with a shovel to prevent uneven placement or impact on the wellbore wall; the sand filling process should not be interrupted to prevent the hole wall from collapsing;

C.砂石滤层的填充高度至少要超过滤管顶以上 1000mm-1800mm,一般应填至原地下水位线以上,以保证土层水流上下畅通。C. The filling height of the sand and gravel filter layer must be at least 1000mm-1800mm above the top of the filter pipe, and should generally be filled above the original groundwater level to ensure smooth flow of water in the soil layer.

12)调试与试抽水12) Debugging and trial pumping

检查集水总管与井点管连接胶管的各个接头在试抽水时是否漏气。若漏气应重新连接或用油腻子堵塞,并重新拧紧法兰盘螺栓和胶管铅丝,直至不漏气为止。在正式抽水前必须试抽,以检查抽水设备运转是否正常,管路是否存在漏气现象。在水泵进水管上安装真空表, 在水泵出水管上安装压力表。为观测降水深度是否达到要求的降水深度,在基坑中心设置观测井点,以便于通过观测井点水位, 描绘降水曲线。试抽时,应检查整个管网的真空度。真空度应达到 550mmHg(73.33kPa)方可抽水。观察出水量大小以及出水水质情况,出现连续水质浑浊应调查原因,查明原因并处理完成后方可继续试抽水。试抽水合格后方可正式抽水。Check whether the joints of the hose connecting the water collecting main pipe and the well point pipe are leaking during the test pumping. If there is a leak, reconnect or plug it with putty, and re-tighten the flange bolts and hose lead wire until there is no leak. Before formal pumping, a test pumping must be carried out to check whether the pumping equipment is operating normally and whether there is any leakage in the pipeline. Install a vacuum gauge on the water pump inlet pipe and a pressure gauge on the water pump outlet pipe. In order to observe whether the precipitation depth reaches the required precipitation depth, an observation well point is set at the center of the foundation pit so that the precipitation curve can be drawn by observing the water level at the well point. During the test pumping, the vacuum degree of the entire pipe network should be checked. The vacuum degree should reach 550mmHg (73.33kPa) before pumping. Observe the amount of water discharged and the quality of the water discharged. If the water quality is continuously turbid, the cause should be investigated. After the cause is found out and handled, the test pumping can be continued. Formal pumping can be carried out only after the test pumping is qualified.

13)正式抽水13) Formal pumping

正式抽水过程中应不间断地记录抽水速度、出水量以及水质情况。发现问题应及时处理。持续抽水以保证地下水降至基坑底部以下 0.5m。正式抽水过程中须注意:During the formal pumping process, the pumping speed, water output and water quality should be recorded continuously. If any problems are found, they should be dealt with promptly. Pumping should be continued to ensure that the groundwater level drops to 0.5m below the bottom of the foundation pit. During the formal pumping process, attention should be paid to the following:

A.保证抽水期间不停电;A. Ensure power outage during pumping;

B.经常进行检查,出水规律应“先大后小,先浊后清”;B. Check regularly, the water discharge pattern should be "large first then small, turbid first then clear";

C.经常检查和调节离心泵的出水阀门以控制出水量,当地下水位降至要求水位后,减少出水阀门的出水量,尽量使抽吸与排水保持均匀;C. Check and adjust the outlet valve of the centrifugal pump frequently to control the water output. When the groundwater level drops to the required level, reduce the water output of the outlet valve to keep the suction and drainage as even as possible;

D.冬季施工应做好集水总管保温,防止受冻;D. During winter construction, the main water collection pipe should be well insulated to prevent freezing;

E.基坑周围上部应挖好截水沟,防止雨水流入基坑。E. A drainage ditch should be dug around the upper part of the foundation pit to prevent rainwater from flowing into the foundation pit.

14)封井14) Sealing the well

根据管井所处位置,封井分为正常封井和基坑承压降水井封底。正常井口的封井达到下列要求后可进行封井作业:According to the location of the pipe well, well sealing is divided into normal well sealing and bottom sealing of foundation pit pressure dewatering well. The well sealing operation can be carried out after the normal wellhead sealing meets the following requirements:

A.结构底板施工完成;A. Construction of the structural base plate is completed;

B.基坑内施工完成的部分满足主体结构抗浮要求;B. The completed part of the foundation pit meets the anti-floating requirements of the main structure;

C.基坑降水井井内稳定水位位于基坑面以下 2m-3m,基坑承压降水井封底步骤如下:C. The stable water level in the foundation pit dewatering well is 2m-3m below the foundation pit surface. The steps for sealing the bottom of the foundation pit pressure dewatering well are as follows:

D.保持承压降水井水位处于静止状态,采用优质黏土对承压降水井填充,填充高度应比滤管高出 2m-3m;待黏土完全沉淀稳定,用水泵将水抽出,用水位计测量承压水渗透情况;D. Keep the water level of the pressure well static, fill it with high-quality clay, and the filling height should be 2m-3m higher than the filter tube; after the clay is completely settled and stabilized, use a water pump to pump out the water, and measure the pressure water penetration with a water level meter;

E.将含砂率小的黏土、水泥按体积比 1﹕1 充分混合后加水拌合制成球状,对承压降水井填充,填充高度约 2m,用水位计检测承压水渗透情况;向承压降水井填入瓜子片和砂的拌合物,砂石拌合物的回填高度应在基坑底板以上 2m;用钢筋将注浆管与井口固定后开始注浆,使水泥浆通过瓜子片的空隙渗入井管缝隙;到达水泥浆的初凝时间后,割除井管至底板面以下 0.5m;观测 2h-4h,若井管内有少量水溢出,使用快干水泥对井管封闭;若井管内无水溢出且封闭效果满足要求,焊接钢板封闭井口;将承压降水井预留的基坑混凝土底板周边凿毛,垃圾清理完成后绑扎钢筋进行二次混凝土浇筑,施工完成。E. Mix clay and cement with a low sand content in a volume ratio of 1:1, add water and mix to form a ball, fill it into the pressure dewatering well, the filling height is about 2m, and use a water level meter to detect the penetration of pressure water; fill the pressure dewatering well with a mixture of melon seed slices and sand, and the backfill height of the sand and gravel mixture should be 2m above the bottom plate of the foundation pit; fix the grouting pipe to the wellhead with steel bars and start grouting, so that the cement slurry penetrates into the gap of the well pipe through the gap of the melon seed slices; after the initial setting time of the cement slurry is reached, cut the well pipe to 0.5m below the bottom plate surface; observe for 2h-4h, if a small amount of water overflows from the well pipe, use quick-drying cement to seal the well pipe; if there is no water overflowing from the well pipe and the sealing effect meets the requirements, weld the steel plate to seal the wellhead; roughen the periphery of the concrete bottom plate of the foundation pit reserved for the pressure dewatering well, tie the steel bars after the garbage is cleaned up, and then pour the secondary concrete, and the construction is completed.

以上所述,仅是本发明的较佳实施例而已,并非对本发明作任何形式上的限制,任何未脱离本发明技术方案内容,依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化与修饰,均仍属于本发明技术方案的范围内。The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any simple modification, equivalent change and modification made to the above embodiment according to the technical essence of the present invention without departing from the technical solution of the present invention still falls within the scope of the technical solution of the present invention.

Claims (4)

1. A method for dewatering construction of a deep foundation pit pipe well close to an existing building sand-containing layer is characterized by comprising the following steps of; comprises the following steps of;
1) Preparing construction;
Combining engineering geological conditions, engineering geological survey reports, hydrologic climate conditions of the engineering location and conditions of surrounding buildings and underground cable pipelines of the engineering to be built, carrying out three-way leveling on a construction site according to the overall arrangement of the construction, and ensuring that various roads and water and electricity pipelines required by precipitation construction on the construction site have conditions, and preparing work of constructors, construction machines and construction materials;
2) Determining a tubing well layout scheme;
Selecting a precipitation mode according to the engineering geological investigation report and the excavation depth of the foundation pit;
3) Entering the equipment;
The water curtain construction machine is provided with a triaxial stirrer and matched equipment, and a rotary drilling rig and matched equipment for forming the close-packed bored pile of the partition wall are arranged;
4) Measuring and paying off;
Determining the position of a well point through drawing calculation according to the provided measurement control points, digging a small soil pit at the well point, wherein the depth is 300-500 mm, and the deviation between the well point position and the design point position is not more than 50mm;
5) Performing foundation pit enclosure construction;
The foundation pit enclosure construction comprises water interception curtain construction and partition wall construction, wherein; the construction of the water interception curtain adopts a triaxial mixing pile as the water interception curtain, the pile position is lofted, a pile machine is in place, a testing and leveling drilling machine is used for forward circulation drilling to the designed depth, a high-pressure grouting pump is started, reverse circulation is performed while grouting is performed, lifting is performed to 0.5m above the designed pile surface, repeated stirring is performed, the reverse circulation is performed, the ground is lifted after the drilling is performed to the surface of the pile top, the pile forming is finished, the next circulation cement mixing pile is constructed, the pile machine is in place for centering, leveling and correcting verticality, the included angle between the machine body and the ground is ensured to be 90 degrees, the pile verticality error is ensured to be within 1.0 percent, the required slurry is configured according to the design requirement, the slurry is sufficiently stirred and ensured to be uniform, the parameter indexes of pH, viscosity and sand content of the prepared slurry are in accordance with the design requirement, the stirring machine is started after the cooling water circulation is normal, loosening a steel wire rope of a crane to enable a stirrer to cut soil along a guide frame, stir and sink, wherein the sinking speed is controlled by a current monitoring meter of a motor, when a hard soil layer is sunk slowly, flushing can be performed to facilitate drilling, a mortar pump is started after the stirrer is sunk to a designed depth, the outlet pressure is kept at 0.4Mpa-0.6Mpa, cement paste is continuously sprayed, the rotary spraying speed of the stirrer is controlled to be 0.4-0.60m/min, when the stirring is lifted to a designed elevation, lifting is stopped and stirring is performed for a plurality of seconds to ensure that a pile head is uniformly compact, and in order to enable cement paste sprayed into the soil and the soil body to be fully stirred, stirring and sinking are repeated until the designed required depth, stirring and lifting are performed again within a range of 1.0m along the lower part of the pile body, and after construction is finished;
Wherein; the partition wall construction is to inject a proper amount of clear water into the collection hopper, start the mortar pump, clean the residual cement slurry in the pipeline, and simultaneously clean the drill bit adhesion soil, wherein the cement content mass ratio of the stirring pile is not less than 15% -20% of the soil; the stirring pile adopts P.O. 42.5 ordinary Portland cement, and the water-cement ratio is 1:0.5; the grouting lifting speed is controlled to be 0.3-0.5m/min; the deviation of the perpendicularity of the pile body is not more than 1.0%, and the deviation of the pile position is not more than 50mm; the grouting requirement of the pile body is finished at one time without interruption, and each pile is preferably filled with slurry once and sprayed and stirred; continuous construction is required, pile lap joint is inserted and crossed, and the construction interval between two adjacent piles is not more than 12 hours; if the pile number exceeds the preset value, pile adding and remedying are adopted in the middle of the two piles; stopping slurry according to reasons in the construction process, sinking the stirrer to 500mm below the slurry stopping point, and stirring and lifting after slurry supply is recovered, wherein a three-spraying and three-stirring construction process is adopted during stirring;
6) Constructing a pipe well;
the construction of the pipe well comprises drilling, hole cleaning, backfilling of a sand cushion layer at the bottom of the well, dredging and plugging of a filter pipe section, well casing and backfilling of filter materials, debugging and trial pumping, formal pumping and Feng Jing;
A. drilling holes; the drilling machine moves to the well point position, the drilling machine is adjusted, the drilling machine is balanced and firm, and no deviation and inclination occur in the drilling process;
B. clearing holes; after the hole forming is finished, cleaning holes in time, and inserting a soft rubber pipe with enough length into the bottom of the well to fill water to clean the holes until clean water flows out, wherein holes are cleaned one by one to avoid dead well;
C. Backfilling a sand cushion layer at the bottom of the well; backfilling a sand cushion layer at the bottom of the well after the hole cleaning is completed, the thickness of the backfill filter material and the sand cushion layer should meet the requirement;
D. The pipe section is prevented from being blocked; aiming at the geological condition of the layer containing the flowing sand, the filter pipe section is treated before the well point pipe is installed, and the outer side of the filter pipe section is wrapped with a thick layer and a thin layer of fiber to form a needled non-woven geotextile, namely geotextile;
E. Setting the well pipe and backfilling filter materials; hoisting the assembled filter tube into the tube well hole after hole cleaning by a crane, and lowering filter materials after the well tube is fixed;
F. Debugging and water pumping trial; the test pumping is needed before the formal pumping to check whether the pumping equipment operates normally, an observation well point is arranged in the center of the foundation pit, and the positive pumping is performed after the debugging and test pumping are completed;
G. formally pumping water; pumping water after debugging and water trial pumping are completed;
H, sealing the well; according to the position of the pipe well, the well sealing is divided into normal well sealing and bottom sealing of the foundation pit pressure-bearing dewatering well, the construction of the structural bottom plate is completed, and the completed part in the foundation pit meets the anti-floating requirement of the main structure; the stable water level in the pit dewatering well is 2m-3m below the pit surface, the bottom of the pit pressure-bearing dewatering well is sealed, the water level of the pressure-bearing dewatering well is kept in a static state, high-quality clay is adopted to fill the pressure-bearing dewatering well, the filling height is 2m-3m higher than that of a filter tube, when the clay is completely settled and stable, water is pumped out by a water pump, the pressure-bearing water permeation condition is measured by a water level meter, clay and cement with small sand content are fully mixed according to the volume ratio of 1:1, then water is added and mixed into a sphere shape, the pressure-bearing dewatering well is filled, the filling height is about 2m, and the pressure-bearing water permeation condition is detected by the water level meter; filling the pressure-bearing dewatering well with a mixture of melon seed pieces and sand, wherein the backfilling height of the sand-stone mixture is 2m above the foundation pit bottom plate, fixing the grouting pipe with a wellhead by using steel bars, and grouting to enable cement slurry to permeate into a well pipe gap through gaps of the melon seed pieces; after the initial setting time of the cement paste is reached, the well pipe is cut off to be 0.5m below the bottom plate surface; observing for 2-4 hours, and sealing the well pipe by using quick-setting cement if a small amount of water overflows in the well pipe; if no water overflows in the well pipe and the sealing effect meets the requirement, welding a steel plate to seal the wellhead; and roughening the periphery of a foundation pit concrete bottom plate reserved by the pressure-bearing dewatering well, binding reinforcing steel bars after garbage cleaning is completed, and performing secondary concrete pouring.
2. The method for dewatering a deep foundation pit pipe well immediately adjacent to an existing building sand-containing layer according to claim 1, wherein the three-way level in step 1) is water-through, electric-through, road-through and field-leveling.
3. The method for dewatering a deep foundation pit pipe well immediately adjacent to an existing building sand-containing layer according to claim 1, wherein the dewatering mode in the step 2) is open drainage and pipe well dewatering.
4. The method of dewatering construction of a deep foundation pit pipe well immediately adjacent to a sand-flowing layer of an existing building according to claim 1, wherein in the step 5), three-spraying three stirring is ‌ to position a pile driver at a predetermined construction position, ‌ then ‌ is sunk to a predetermined depth through a drill pipe, after ‌ reaches a design depth, ‌ is lifted while stirring the drill pipe, ‌ is sprayed with slurry at the same time, ‌ is lifted, ‌ is sunk to the design depth again, ‌ is lifted while stirring the drill pipe again, ‌ is sprayed with slurry, and ‌ is completed, and then ‌ is stopped.
CN202411105887.0A 2024-08-13 2024-08-13 A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building Pending CN118704502A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202411105887.0A CN118704502A (en) 2024-08-13 2024-08-13 A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202411105887.0A CN118704502A (en) 2024-08-13 2024-08-13 A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building

Publications (1)

Publication Number Publication Date
CN118704502A true CN118704502A (en) 2024-09-27

Family

ID=92811277

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202411105887.0A Pending CN118704502A (en) 2024-08-13 2024-08-13 A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building

Country Status (1)

Country Link
CN (1) CN118704502A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN119411574A (en) * 2025-01-07 2025-02-11 山东大学 A solidified soft soil bearing layer FRP-steel honeycomb web photovoltaic pile foundation and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN119411574A (en) * 2025-01-07 2025-02-11 山东大学 A solidified soft soil bearing layer FRP-steel honeycomb web photovoltaic pile foundation and construction method

Similar Documents

Publication Publication Date Title
WO2022096024A1 (en) Construction method for super-long small-diameter hole bored pile
CN103993603B (en) A kind of anchor pole churning back cover deep foundation ditch reversed construction method without dewatering operation
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN108797598A (en) The construction technology of pre-loaded support struts in a kind of deep basal pit
CN108560541A (en) A kind of full casing follow-up scar drilling construction method of churning driven
LU500273B1 (en) New comprehensive dewatering and drainage method and drainage device for mudstone subway station
CN112502139A (en) Construction method for excavation of deep pit by three-axis stirring pile curtain water stop and rotary digging cast-in-place pile support
CN110984221A (en) Construction method for reinforcing end socket at initial end of air shaft and guide wall structure
CN113089655A (en) Construction method in three-pipe rotary spraying pile pit in flowing water environment
CN111851546A (en) A construction method for closed dewatering of dredging wells in deep foundation pit construction
CN111560958A (en) Construction method of water-rich deep foundation pit in silty clay stratum
CN112144559B (en) Well construction method in high-water-rich loess sand pebble stratum pressure-variable pipe well
CN118704502A (en) A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building
CN211898541U (en) Guide wall structure for reinforced structure of air shaft initial end head
CN112176947A (en) Bank protection construction method for concave bank line of sludge layer foundation
CN113846695B (en) Reverse construction method basement construction method
CN113266362B (en) A construction method of pipe jacking and cover excavation crossing existing dense anchor cable area
CN114250801A (en) Pipe well and light well point combined dewatering construction method
CN216920368U (en) A large-scale circular foundation pit three-axis stirring pile support structure
CN205224019U (en) Stake of reinforcing bar fiber cement soil
CN112523272B (en) Anti-floating blind ditch for strongly weathered rock stratum and construction method thereof
CN115748786A (en) Drainage sinking construction method for pipe-jacking circular open caisson
CN116220027A (en) BIM auxiliary reinforced pile and non-reinforced pile engaged pile construction method
CN113585237B (en) Ground connecting wall joint and construction method of ground connecting wall
CN221256734U (en) Push pipe receiving well

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination