Multi-layer steel corridor hovering assembly device and implementation method
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a multi-layer steel gallery hovering assembly device and an implementation method.
Background
The steel gallery structure is an important part for connecting different building spaces in the modern building field, and becomes a part of urban building landscape by virtue of the unique design concept and practicality. When designing the steel vestibule, need consider its light and firm combination, steel is because of its high strength and light characteristics for the vestibule also can keep graceful form under the great span, possesses good plasticity simultaneously in order to adapt to different design demands. In the past, the air corridor is often constructed by adopting an integral lifting process. However, as building functions and structures become more complex, the construction process of once assembling and then integrally lifting the traditional steel corridor has the problem of difficult implementation. In engineering practice, in order to reduce the steel corridor and assemble the degree of difficulty, can adopt to assemble the local floor steel corridor and wholly promote certain height earlier afterwards, assemble bottom again.
The assembly mode has the following problems that when an upper steel corridor hovers, a lower steel corridor is assembled and hoisted, the visual and physical interference of the upper assembled steel corridor is caused, and the construction efficiency is low, the potential safety hazard is large and the like; with the suspension of the upper steel corridor, the steel ropes are deformed differently, so that the upper steel corridor and the lower steel corridor are difficult to assemble due to the deflection of the positions when being butted; because the steel cable overlength, it is very difficult to adjust upper steel vestibule through the shrink of steel cable, and the precision is lower, and current upper steel vestibule adjusts the structure and need fix the side in both sides building, and fixed position's determination receives building structure restriction.
Disclosure of Invention
In view of the above, the invention aims to provide a multi-layer steel gallery hovering assembly device and an implementation method thereof, which are flexible to install, high in positioning accuracy and high in safety.
In order to achieve the above purpose, the present invention provides the following technical solutions:
The utility model provides a multilayer steel corridor hovers and assembles device, includes four suspension hangers, the two liang of top of fixing at both sides building of suspension hanger, the suspension hanger stretches out the steel cable of suspending usefulness, the tip of steel cable is fixed with the grip slipper, the lower extreme side of upper steel corridor is held to the grip slipper; the lower end of the clamping seat is fixedly provided with a support column, and the end part of the support column is provided with a support seat; the utility model also comprises a butt joint base table, the butt joint base table comprises a plurality of straight rails arranged on the ground and an operation table slidingly arranged on the straight rails, a plurality of support rods are arranged on the operation table, the lower steel corridor is built by the support rods, the lower steel corridor is in a vertical butt joint state, four steel cylinders are also arranged on the operation table, the top end of the steel cylinder is vertically and slidably provided with a jacking column, a hydraulic cylinder is further arranged in the steel cylinder, the jacking column is pushed by the hydraulic cylinder to vertically move, four steel cylinders are respectively and correspondingly positioned below the clamping seat, the jacking column comprises a lower column and an upper column, and synchronous rods are sequentially connected between the four lower columns; the lower column top is equipped with the oil pocket, go up the post lower extreme and slide and locate in the oil pocket, an adjusting cylinder is seted up to the oil pocket, an adjusting cylinder threaded connection has an adjusting post, rotates the adjusting post, through the oil pressure fine setting the length of jack-up post, it is equipped with the support to go up the post top the pedestal of supporting seat.
Further, the end part of the support column is provided with a ball head, the support seat is provided with a ball groove, and the ball head is rotatably arranged in the ball groove.
The device further comprises a translation part and a passive part, wherein the passive part comprises a fixing clamp seat used for being fixed at the lower edge of the side surface of the upper steel gallery, and the fixing clamp seat extends to the outer transverse rod; the translation portion is in including removing the locomotive that sets up on the synchronizing bar, be equipped with telescoping device on the locomotive, telescoping device's tip is equipped with the montant that upwards extends, the horizontal pole tip is equipped with and supplies montant male through-hole, when butt joint upper steel vestibule and lower floor steel vestibule, the montant inserts the through-hole.
Further, the cross rod is rotatably provided with a cross shaft, the cross shaft is rotatably provided with a swivel base, the rotating shaft of the cross shaft is perpendicular to the outer side face of the upper steel corridor, the rotating shaft of the swivel base is perpendicular to the rotating shaft of the cross shaft, and the through hole is formed in the swivel base.
Further, the clamping seat comprises a seat body and a T-shaped table fixedly arranged on the side face of the seat body, a plurality of threaded columns are respectively extended from the two sides and the top side of the T-shaped table, clamping blocks are respectively arranged on the two sides and the top side of the T-shaped table, the clamping blocks are slidably arranged on the threaded columns, nuts are connected to the threaded columns in a threaded mode, and a baffle plate arranged on the outer side of an upper layer steel corridor is arranged on the T-shaped table.
Further, the bottom surface of supporting seat is the disc structure, the pedestal top surface inwards is equipped with the counter bore that the internal diameter is greater than the supporting seat external diameter.
An implementation method of a multi-layer steel corridor hovering assembly device comprises the following steps:
S1, installing hanging frames at hanging positions at the top ends of buildings on two sides, lowering steel ropes, and clamping the side surfaces of the lower ends of the upper-layer steel corridor through clamping seats of the steel ropes, wherein four steel ropes are respectively hung at four ends of the upper-layer steel corridor to enable the upper-layer steel corridor to be hung;
S2, recovering the steel ropes, and suspending the upper steel gallery to a high-altitude position;
s3, arranging a straight rail and an operation table on the straight rail, and placing the operation table outside the upper steel corridor;
s4, installing a supporting rod on the operation table, and building a lower steel corridor through the supporting rod, so that the lower steel corridor is in a vertical butt joint state with the upper steel corridor;
s5, moving the whole operation table to enable the lower steel corridor to move below the upper steel corridor;
s6, moving down the upper layer steel corridor to enable the four-end supporting seats to be in butt joint with the pedestal;
S7, inserting the vertical rods into the through holes, and aligning the upper steel corridor with the lower steel corridor by moving the translation part;
S8, lifting the steel rope, rotating the adjusting column, adjusting the supporting height of the synchronizing rod, and finely adjusting the vertical alignment degree of the upper steel corridor and the lower steel corridor through the cooperation of the steel rope and the adjusting cylinder;
s9, pushing the jacking column to move through the hydraulic cylinder, so that the upper steel corridor is spliced with the lower steel corridor.
The invention has the beneficial effects that:
The invention is used for hanging and splicing the upper layer and the lower layer of the steel corridor, the steel ropes extend out through the four hanging brackets, and the two ends of the bottom sides of the two outer sides of the upper layer steel corridor are clamped through the clamping seats at the end parts of the steel ropes, so that the upper layer steel corridor is stably hung, wherein each clamping seat is provided with a support post and a supporting seat, the lower layer steel corridor moves to the lower side of the upper layer steel corridor along with a straight rail after an operation table is built through supporting rods with different lengths, and the movable operation table is arranged, so that the lower layer steel corridor is positioned outside the lower range of the upper layer steel corridor when being built, the falling potential safety hazard of the upper layer steel corridor is avoided, the visual and physical interference of the upper layer steel corridor is removed, and the construction efficiency of the upper layer steel corridor and the lower layer steel corridor can be synchronously built, so that the construction efficiency of the steel corridor is improved; after the construction of the upper steel gallery and the lower steel gallery is completed, the operation table moves below the upper steel gallery, so that the next steel gallery leveling can be performed; through setting up the jack-prop of steel cylinder and support grip slipper, before vertical concatenation two-layer steel vestibule, carry out the fine setting of splice position to upper steel vestibule, specific fine setting mode is: one of the steel ropes is hung for bearing force, so that the supporting seat is far away from the support of the pedestal, the adjusting column is rotated, the length of the jacking column is adjusted through the change of oil pressure, after the adjustment is finished, the supporting seat is placed on the pedestal, the deflection of the upper steel corridor caused by hanging can be adjusted and removed through the adjustment of four supporting points, and in the subsequent splicing, the four jacking columns are simultaneously lowered along with the retraction of the hydraulic cylinder, so that the upper steel corridor is accurately spliced with the lower steel corridor; after the structure is supported by the supporting points, the upper steel corridor is supported by the four steel cylinders, and compared with direct steel rope suspension splicing, the steel corridor can be prevented from shaking during splicing, and the splicing difficulty and potential safety hazard of the steel corridor are reduced; the hydraulic fine adjustment structure of the jacking column is arranged on the steel cylinder, so that the two-side buildings cannot be interfered, the flexibility is strong, and the butting accuracy is high.
Additional advantages, objects, and features of the invention will be set forth in part in the description which follows and in part will become apparent to those having ordinary skill in the art upon examination of the following or may be learned from practice of the invention. The objects and other advantages of the invention may be realized and obtained by means of the instrumentalities and combinations particularly pointed out in the specification.
Drawings
In order to make the objects, technical solutions and advantageous effects of the present invention more clear, the present invention provides the following drawings for description:
FIG. 1 is a schematic view of an overall hover re-modulation device according to an embodiment of the present invention;
FIG. 2 is a schematic diagram of a detail at A of FIG. 1;
FIG. 3 is a schematic diagram of a detail at B of FIG. 1;
FIG. 4 is a cross-sectional view of an embodiment of the present invention taken through a top post and steel cylinder;
FIG. 5 is a cross-sectional view of a T-shaped stage in accordance with an embodiment of the present invention;
The figures are marked as follows: 1. an upper steel gallery; 2. a lower steel gallery; 3. a suspension bracket; 31. a steel rope; 4. a clamping seat; 41. a support post; 42. a support base; 421. a ball groove; 43. a base; 44. a T-shaped table; 45. a threaded column; 46. clamping blocks; 47. a nut; 48. a baffle; 49. ball head; 5. docking a base table; 51. a straight rail; 52. an operation table; 53. a support rod; 54. a steel cylinder; 55. a top column; 551. loading a column; 552. a lower column; 553. an oil chamber; 554. an adjustment cylinder; 555. an adjusting column; 556. a pedestal; 5561. countersink; 56. a hydraulic cylinder; 57. a synchronizing lever; 6. a translation section; 61. a moving vehicle; 62. a telescoping device; 63. a vertical rod; 7. a passive part; 71. a fixing clamp seat; 72. a cross bar; 73. a horizontal axis; 74. rotating base; 741. and a through hole.
Detailed Description
As shown in fig. 1-5, the invention discloses a multi-layer steel gallery hovering assembly device and an implementation method, the multi-layer steel gallery hovering assembly device comprises four suspension brackets 3, wherein the suspension brackets 3 are fixed at the top ends of buildings at two sides in pairs, the suspension brackets 3 extend out of steel ropes 31 for suspension through an electric winding device, clamping seats 4 are fixed at the end parts of the steel ropes 31, the clamping seats 4 are clamped on the side surfaces of the lower end of an upper layer steel gallery 1, and the upper layer steel gallery 1 is horizontally and stably suspended through the clamping of the four clamping seats 4, as shown in fig. 2, a support column 41 is fixedly arranged at the lower end of the clamping seats 4, and supporting seats 42 are arranged at the end parts of the support columns 41; the device also comprises a butt joint base table 5, wherein the butt joint base table 5 comprises a plurality of straight rails 51 arranged on the ground and an operation table 52 slidably arranged on the straight rails 51, and the operation table 52 can move in a traction way through a traction machine and other equipment; the operation table 52 is provided with a plurality of support rods 53, the lower steel corridor 2 is built through the plurality of support rods 53, the lower steel corridor 2 is in a vertical butt joint state, the length of the support rods 53 is selected according to the bottom structure of the lower steel corridor 2, the operation table 52 is also provided with four steel cylinders 54, as shown in fig. 4, the top ends of the steel cylinders 54 are vertically and slidably provided with jacking columns 55, the steel cylinders 54 are internally provided with hydraulic cylinders 56, the jacking columns 55 are pushed to vertically move by the hydraulic cylinders 56, the four steel cylinders 54 are respectively correspondingly positioned below the clamping seat 4, the jacking columns 55 comprise lower columns 552 and upper columns 551, and synchronous rods 57 are sequentially connected between the four lower columns 552; the top of the lower column 552 is provided with an oil cavity 553, the lower end of the upper column 551 is slidably arranged in the oil cavity 553, the oil cavity 553 is provided with an adjusting cylinder 554, the adjusting cylinder 554 is in threaded connection with an adjusting column 555, the adjusting column 555 is rotated, the length of the jacking column 55 is finely adjusted through oil pressure, and the top of the upper column 551 is provided with a pedestal 556 for supporting the supporting seat 42.
The device is used for hanging and splicing upper and lower layers of a multi-layer steel corridor, steel ropes 31 are stretched out through four hanging frames 3, two ends of the bottom sides of two outer sides of the upper layer steel corridor 1 are clamped through clamping seats 4 at the end parts of the steel ropes 31, so that the upper layer steel corridor 1 is stably hung, wherein each clamping seat 4 is provided with a support column 41 and a support seat 42, after an operation table 52 is built through support rods 53 with different lengths, the lower layer steel corridor 2 moves below the upper layer steel corridor 1 along with a straight rail 51, and by arranging a movable operation table 52, the lower layer steel corridor 2 is located outside the lower range of the upper layer steel corridor 1 during building, so that potential safety hazards of falling of the upper layer steel corridor 1 are avoided, visual and physical interference of the upper layer steel corridor 1 are also removed, building of the upper layer steel corridor 1 and the lower layer steel corridor 2 can be synchronously carried out, and the construction efficiency of the steel corridor is improved; after the construction of the upper steel gallery 1 and the lower steel gallery 2 is completed, the operation table 52 is moved below the upper steel gallery 1, so that the next steel gallery leveling can be performed; through setting up the jack-up post 55 of steel cylinder 54 and support grip slipper 4, before vertical concatenation two-layer steel vestibule, carry out the fine setting of splice position to upper steel vestibule 1, specific fine setting mode is: one of the steel ropes 31 is suspended and stressed, so that the supporting seat 42 is far away from the support of the pedestal 556, the adjusting column 555 is rotated, the length of the jacking column 55 is adjusted through the change of oil pressure, after the adjustment is finished, the supporting seat 42 is placed on the pedestal 556, the deflection adjustment of the upper steel corridor 1 caused by suspension can be removed through the adjustment of four supporting points, and in the subsequent splicing, the four jacking columns 55 are simultaneously lowered along with the retraction of the hydraulic cylinder 56, so that the upper steel corridor 1 is accurately spliced with the lower steel corridor 2; after the structure is supported by the supporting points, the upper steel corridor 1 is supported by the four steel cylinders 54, compared with the direct steel rope 31 which is used for hanging and splicing, the steel corridor can be prevented from swinging during splicing, and the splicing difficulty and the potential safety hazard of the steel corridor are reduced; the hydraulic fine adjustment structure of the top column 55 is arranged on the steel cylinder 54, so that the hydraulic fine adjustment structure cannot interfere with buildings on two sides, and is high in flexibility and high in butting accuracy.
In a further aspect, as shown in fig. 2 and 4, a ball head 49 is disposed at an end of the pillar 41, a ball groove 421 is formed on the supporting seat 42, and the ball head 49 is rotatably disposed in the ball groove 421.
After the clamping seat 4 is clamped on the side face of the steel corridor, the bottom face of the supporting seat 42 is not absolutely parallel to the pedestal 556 due to the special-shaped structure of the steel corridor and the clamping structural factors, so that the supporting seat 42 bottom face deflection caused by deflection generated by clamping of the clamping seat 4 and the steel corridor is neutralized by arranging the ball structure, the surface-to-surface contact and stress uniformity of the supporting seat 42 and the pedestal 556 are ensured, and the supporting is stable after the leveling of the upper steel corridor 1 is ensured.
In a further aspect, as shown in fig. 3, the device further comprises a translation part 6 and a passive part 7, wherein the passive part 7 comprises a fixing clamping seat 71 for fixing the lower edge of the side surface of the upper steel gallery 1, and the fixing clamping seat 71 extends a cross rod 72 outwards; the translation portion 6 is including removing the mobile carriage 61 that sets up on the synchronizing bar 57, and the mobile carriage 61 is easy the movable structure of synchronizing bar 57 can select motor driven rack and pinion meshing structure, be equipped with telescoping device 62 on the mobile carriage 61, equipment such as telescoping device 62 can select telescopic cylinder, the tip of telescoping device 62 is equipped with the montant 63 that upwards extends, the horizontal pole 72 tip is equipped with and supplies montant 63 male through-hole 741, when docking upper steel vestibule 1 and lower floor's steel vestibule 2, montant 63 inserts through-hole 741.
In this structure, through the telescopic action of moving car 61 along synchronizing bar 57 removal and telescoping device 62, make the montant 63 of telescoping device 62 tip at the arbitrary removal of horizontal direction, embolia through-hole 741 through montant 63, montant 63 can drive the fixed holder 71 that is connected with upper steel vestibule 1 and remove, make upper steel vestibule 1 horizontal migration, through translation of translation portion 6, realize upper steel vestibule 1 in the regulation of hanging butt joint lower floor steel vestibule 2 horizontal position, replace manual traction, avoid the rocking scheduling problem of steel vestibule.
In a further scheme, as shown in fig. 3, a transverse shaft 73 is rotatably arranged on the transverse rod 72, a rotating seat 74 is rotatably arranged on the transverse shaft 73, a rotating shaft of the transverse shaft 73 is perpendicular to the outer side surface of the upper steel gallery 1, a rotating shaft of the rotating seat 74 is perpendicular to a rotating shaft of the transverse shaft 73, and the through hole 741 is formed in the rotating seat 74.
In this structure, through setting up biax revolution mechanic, make montant 63 can vertically pass through hole 741, avoid because of the fixed holder 71 centre gripping when steel vestibule side, because of the error that the structure centre gripping produced, lead to montant 63 and the problem that through hole 741 can not directly penetrate to this structure can not produce to rock after vertical penetrating through hole 741, and fixed holder 71 only receives the removal traction of montant 63.
In a further scheme, as shown in fig. 5, the clamping seat 4 includes a seat body 43 and a T-shaped table 44 fixedly arranged on the side surface of the seat body 43, two sides and a top side of the T-shaped table 44 respectively extend a plurality of threaded columns 45, two sides and a top side of the T-shaped table 44 are respectively provided with clamping blocks 46, the clamping blocks 46 are slidably arranged on the threaded columns 45, nuts 47 are connected to the threaded columns 45 in a threaded manner, and the T-shaped table 44 is provided with a baffle 48 which is blocked on the outer side of the upper steel gallery 1.
The structure is provided with two clamping blocks 46 which are horizontally clamped and vertically clamped respectively, and the clamping seat 4 can be clamped at the bottom end crossing position of any steel beam of the steel corridor of the steel frame structure by matching with the baffle plate 48, and rotation and translation relative to the steel corridor can not be generated, so that a pre-fixing condition is provided for subsequent positioning and supporting.
In a further aspect, as shown in fig. 2, the bottom surface of the supporting seat 42 has a disc structure, and the top surface of the pedestal 556 is provided with a counter bore 5561 having an inner diameter greater than the outer diameter of the supporting seat 42. By providing the counterbore 5561, the support base 42 can be displaced along the plane of the pedestal 556 within a certain range within the counterbore 5561 and is blocked by the edge of the counterbore 5561, thereby avoiding support failure caused by the support base 42 falling from the pedestal 556.
Through the structure, the invention provides an implementation method of the multi-layer steel gallery hovering assembly device, which comprises the following steps:
S1, installing hanging frames 3 at hanging positions at the top ends of buildings on two sides, lowering steel ropes 31, clamping the side surfaces of the lower ends of the upper-layer steel corridor 1 through clamping seats 4 of the steel ropes 31, and respectively hanging four steel ropes 31 at four ends of the upper-layer steel corridor 1 to enable the upper-layer steel corridor 1 to be hung;
s2, recovering the steel ropes 31, and suspending the upper steel gallery 1 to a high-altitude position;
s3, arranging a straight rail 51 and an operation table 52 on the straight rail 51, and placing the operation table 52 outside the upper steel gallery 1;
S4, installing a supporting rod 53 on the operating platform 52, supporting and building the lower steel corridor 2 through the supporting rod 53, so that the lower steel corridor 2 is in a vertical butt joint state with the upper steel corridor 1;
S5, moving the whole operation table 52 to enable the lower steel corridor 2 to move below the upper steel corridor 1;
s6, moving down the upper layer steel corridor 1 to enable the four-end supporting seats 42 to be in butt joint with the pedestal 556;
S7, inserting the vertical rods 63 into the through holes 741, and enabling the upper steel corridor 1 to be aligned with the lower steel corridor 2 by moving the translation part 6;
S8, lifting the steel rope 31, rotating the adjusting column 555, adjusting the supporting height of the synchronizing rod 57, and finely adjusting the vertical alignment degree of the upper steel gallery 1 and the lower steel gallery 2 through the cooperation of the steel rope 31 and the adjusting cylinder 554;
and S9, pushing the top column 55 to move through the hydraulic cylinder 56, so that the upper steel corridor 1 and the lower steel corridor 2 are spliced.
Finally, it is noted that the above-mentioned preferred embodiments are only intended to illustrate rather than limit the invention, and that, although the invention has been described in detail by means of the above-mentioned preferred embodiments, it will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the scope of the invention as defined by the appended claims.