CN118619129A - Tower crane installation and disassembly methods - Google Patents

Tower crane installation and disassembly methods Download PDF

Info

Publication number
CN118619129A
CN118619129A CN202411097203.7A CN202411097203A CN118619129A CN 118619129 A CN118619129 A CN 118619129A CN 202411097203 A CN202411097203 A CN 202411097203A CN 118619129 A CN118619129 A CN 118619129A
Authority
CN
China
Prior art keywords
tower crane
installation
disassembly
safety
jacking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202411097203.7A
Other languages
Chinese (zh)
Inventor
苏永柱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202411097203.7A priority Critical patent/CN118619129A/en
Publication of CN118619129A publication Critical patent/CN118619129A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/16Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes with jibs supported by columns, e.g. towers having their lower end mounted for slewing movements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/26Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
    • B66C23/28Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels
    • B66C23/283Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels with frameworks composed of assembled elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Transportation (AREA)
  • Jib Cranes (AREA)

Abstract

本发明公开了一种塔式起重机安装及拆卸方法,安装流程为:确定基础施工方案→砼基础施工及验收→设置动力源→清点零部件、构件→按步骤安装塔机基本构件→顶升加节到允许自由高度→锚固加节→安装到所需高度→接地电阻、垂直度测量→整机调试;拆卸流程为:查看拆卸现场、检查塔机各部件、准备拆卸工具材料→编制具体拆卸方案→下达拆卸工作任务单→降塔→拆除附墙装置→降到允许的最小高度→用汽车吊拆卸各构件总成→清单零部件、构件→构件运输出场→分类堆放。本发明的方法中通过对塔机安、拆过程中的诸多技术要点进行详细的阐述说明,使用过程中严格按照上述技术要点进行操作,按照正规作业程序施工,可以很好地控制安全风险,避免发生安全事故。

The invention discloses a tower crane installation and disassembly method, the installation process is: determine the foundation construction plan → concrete foundation construction and acceptance → set the power source → check the parts and components → install the basic components of the tower crane in steps → lift and add sections to the allowed free height → anchor and add sections → install to the required height → measure ground resistance and verticality → debug the whole machine; the disassembly process is: check the disassembly site, check the various parts of the tower crane, prepare disassembly tools and materials → compile a specific disassembly plan → issue a disassembly work task list → lower the tower → remove the wall attachment device → lower to the minimum allowed height → use a truck crane to disassemble the assembly of various components → check the parts and components → transport the components out of the site → classify and stack. In the method of the invention, many technical points in the installation and disassembly process of the tower crane are explained in detail, and the operation is strictly carried out in accordance with the above technical points during use, and the construction is carried out according to the regular operation procedures, so that the safety risks can be well controlled and the safety accidents can be avoided.

Description

塔式起重机安装及拆卸方法Tower crane installation and disassembly methods

技术领域Technical Field

本发明涉及一种塔式起重机安装及拆卸方法,属于建筑施工方法技术领域。The invention relates to a tower crane installation and disassembly method, belonging to the technical field of building construction methods.

背景技术Background Art

塔式起重机简称塔机,亦称塔吊,为动臂装在高耸塔身上部的旋转起重机。其作业空间大,主要用于房屋建筑施工中物料的垂直和水平输送及建筑构件的安装。由金属结构、工作机构和电气系统三部分组成。金属结构包括塔身、动臂和底座等。工作机构有起升、变幅、回转和行走四部分。电气系统包括电动机、控制器、配电柜、连接线路、信号及照明装置等。Tower crane is also called tower crane, which is a rotating crane with a boom mounted on the top of a tall tower. It has a large working space and is mainly used for vertical and horizontal transportation of materials and installation of building components in house construction. It consists of three parts: metal structure, working mechanism and electrical system. The metal structure includes the tower body, boom and base. The working mechanism has four parts: lifting, luffing, rotation and travel. The electrical system includes motors, controllers, distribution cabinets, connecting lines, signals and lighting devices, etc.

虽然塔机在安、拆、使用过程中存在较大的安全风险,如果能很好的把握安、拆、使用过程中的几个安全要点,按照正规作业程序施工,就可以很好的控制安全风险。Although there are great safety risks in the installation, dismantling and use of tower cranes, if you can grasp several safety points in the installation, dismantling and use process well and follow the regular operating procedures, you can control the safety risks well.

发明内容Summary of the invention

本发明的目的在于,提供一种塔式起重机安装及拆卸方法。通过该方法可以降低塔机在安、拆过程中存在的安全风险。The object of the present invention is to provide a tower crane installation and disassembly method, by which the safety risks existing in the installation and disassembly process of the tower crane can be reduced.

本发明的技术方案:塔式起重机安装及拆卸方法,塔机安装流程为:确定基础施工方案→砼基础施工及验收→设置动力源→清点零部件、构件→按步骤安装塔机基本构件→顶升加节到允许自由高度→锚固加节→安装到所需高度→接地电阻、垂直度测量→整机调试;塔机拆卸流程为:查看拆卸现场、检查塔机各部件、准备拆卸工具材料→编制具体拆卸方案→下达拆卸工作任务单→降塔→拆除附墙装置→降到允许的最小高度→用汽车吊拆卸各构件总成→清单零部件、构件→构件运输出场→分类堆放。The technical solution of the present invention is a tower crane installation and disassembly method, the tower crane installation process is: determine the foundation construction plan → concrete foundation construction and acceptance → set the power source → count the parts and components → install the basic components of the tower crane in steps → lift and add sections to the allowed free height → anchor and add sections → install to the required height → measure ground resistance and verticality → debug the whole machine; the tower crane disassembly process is: check the disassembly site, check the various parts of the tower crane, prepare disassembly tools and materials → prepare a specific disassembly plan → issue a disassembly work task list → lower the tower → remove the wall-mounted device → lower to the allowed minimum height → use a truck crane to disassemble the component assemblies → list the parts and components → transport the components to the site → classify and stack them.

前述的塔式起重机安装及拆卸方法中,塔机安拆前技术检查要点:In the above tower crane installation and disassembly methods, the technical inspection points before tower crane installation and disassembly are as follows:

1)在安拆作业开始前,应进行一次全面检查;1) Before installation and disassembly work begins, a comprehensive inspection should be carried out;

2)检查设备基础是否符合技术要求,水平度误差小于1/500,将地脚螺栓或设备基础节进行抄平并调整至允许范围以内;2) Check whether the equipment foundation meets the technical requirements and the horizontal error is less than 1/500, and level the anchor bolts or equipment foundation sections and adjust them to within the allowable range;

3)对设备各机构、部位、结构焊缝、重要部位螺栓、销轴、卷扬机构和钢丝绳、吊钩、吊具、安全限位装置以及电气设备、线路进行仔细检查,发现问题应立即解决;3) Carefully inspect all mechanisms, parts, structural welds, bolts at important parts, pins, hoisting mechanisms and wire ropes, hooks, slings, safety limit devices, electrical equipment and lines of the equipment, and solve any problems found immediately;

4)检查塔机顶升液压系统的液压缸和油管、顶升套架结构、导向轮、顶升块及止动器;4) Check the hydraulic cylinder and oil pipe of the tower crane jacking hydraulic system, the jacking frame structure, the guide wheel, the jacking block and the stopper;

5)检查塔机起升系统钢丝绳、制动装置,确认无误后方可使用;5) Check the wire rope and brake device of the tower crane hoisting system and use them only after confirming that they are correct;

6)对安装人员所使用的工具、安全带、安全帽进行全面检查,不合格者立即更换;6) Conduct a comprehensive inspection of the tools, safety belts and helmets used by the installers, and replace those that fail to meet the standards immediately;

7)检查安拆作业中使用的辅助机械,技术要求能保证安拆作业需要;7) Check the auxiliary machinery used in the installation and disassembly operations, and ensure that the technical requirements can meet the needs of the installation and disassembly operations;

8)检查安拆现场有关情况,电源、运输道路、作业场地是否已具备安拆作业条件;8) Check the installation and dismantling site conditions and whether the power supply, transportation roads and work sites are ready for installation and dismantling;

9)检查安全监督岗的设置及安全措施的贯彻落实是否已符合要求。9) Check whether the establishment of safety supervision posts and the implementation of safety measures meet the requirements.

前述的塔式起重机安装及拆卸方法中,自升式塔式起重机的顶升加节,应符合下列要求:In the above-mentioned tower crane installation and disassembly methods, the jacking and sectioning of the self-erecting tower crane shall meet the following requirements:

1)顶升系统必须完好;1) The lifting system must be intact;

2)结构件必须完好;2) Structural parts must be intact;

3)顶升前,塔式起重机下支座与顶升套架应可靠连接;3) Before lifting, the lower support of the tower crane and the lifting frame should be reliably connected;

4)顶升前,应确保顶升横梁搁置正确;4) Before lifting, ensure that the lifting beam is placed correctly;

5)顶升前,应将塔式起重机配平;顶升过程中,应确保塔式起重机的平衡;5) Before lifting, the tower crane should be leveled; during the lifting process, the balance of the tower crane should be ensured;

6)顶升加节的顺序,应符合产品说明书的规定;6) The order of lifting and adding sections should comply with the provisions of the product manual;

7)顶升过程中,不应进行起升、回转、变幅操作;7) During the lifting process, lifting, rotation and luffing operations should not be performed;

8)顶升结束后,应将标准节与回转下支座可靠连接;8) After the lifting is completed, the standard section should be reliably connected to the lower slewing support;

9)塔式起重机加节后需进行附着的,应按照先装附着装置、后顶升加节的顺序进行,附着装置的位置和支撑点的强度应符合要求。9) If a tower crane needs to be attached after adding sections, the sequence should be to install the attachment device first and then lift and add sections. The position of the attachment device and the strength of the supporting points should meet the requirements.

前述的塔式起重机安装及拆卸方法中,安拆作业中的安全技术控制要求:In the above tower crane installation and disassembly methods, the safety technical control requirements during installation and disassembly operations are:

1)设备安拆作业应在白天进行,如需加快进度,可在具备良好照明条件的夜间做一些简单拼装工作,不得在大风、浓雾和雨雪天气进行;1) Equipment installation and disassembly should be carried out during the day. If the progress needs to be accelerated, some simple assembly work can be done at night with good lighting conditions. It should not be carried out in strong winds, dense fog, rain or snow;

2)在安拆作业过程中,必须保持现场的整洁和秩序,不得堆存杂物以免妨碍作业并影响安全,设备金属结构下面必须垫放木枋,防止损坏结构或造成结构变形;2) During the installation and dismantling process, the site must be kept clean and orderly. No debris should be piled up to avoid hindering the operation and affecting safety. Wooden beams must be placed under the metal structure of the equipment to prevent damage to the structure or deformation of the structure;

3)安拆架设用的钢丝绳及其固定必须符合标准和满足安拆上的要求;3) The steel wire rope used for installation and its fixing must comply with the standards and meet the installation requirements;

4)在进行逐件组拼或部件安装之前,必须对部件各部分的完好情况、连接情况和钢丝绳穿绕情况、电气线路进行全面检查;4) Before assembling or installing each part piece by piece, the integrity, connection, wire rope threading and electrical circuits of each part must be fully inspected;

5)在安拆塔机起重臂和平衡臂时,要始终保持起重机的平衡,不允许只安拆一个起重臂就中断作业;5) When installing and disassembling the tower crane boom and balance arm, the crane must always be kept balanced. It is not allowed to interrupt the operation by installing and disassembling only one boom;

6)在安拆作业过程中,如突然发生停电、机械故障、天气骤变情况不能继续作业,或作业时间已到需要停休时,必须使设备已安装的部位达到稳定状态并已锁固牢靠,所有结构件已连接牢固,经过检查确认妥善后,方可停止作业;6) During the installation and disassembly process, if there is a sudden power outage, mechanical failure, sudden weather change and the operation cannot be continued, or the operation time has reached and it needs to be stopped, the installed parts of the equipment must be stabilized and locked securely, all structural parts must be firmly connected, and the operation can only be stopped after inspection and confirmation;

7)安拆时应使用规定的螺栓、销轴连接件,并要有可靠的防松或保护装置,螺栓紧固时应符合规定的预紧力;7) When installing or disassembling, the specified bolts and pin connectors should be used, and reliable anti-loosening or protective devices should be provided. When tightening the bolts, the specified pre-tightening force should be met;

8)安拆作业的程序、辅助设备、索具、工具,均应遵照该机使用说明书中的规定。8) The procedures, auxiliary equipment, rigging and tools for installation and disassembly operations shall comply with the provisions in the machine's instruction manual.

前述的塔式起重机安装及拆卸方法中,标准节、回转平台安装完毕后应重点检查:In the above-mentioned tower crane installation and disassembly methods, the following should be checked after the standard section and slewing platform are installed:

1)标准节的型号及安装位置是否符合原厂说明书的安装规定,标准节和基础节螺栓的预紧力应符合技术规定;1) Whether the model and installation position of the standard section conform to the installation regulations of the original manufacturer's manual, and the preload force of the bolts of the standard section and foundation section shall conform to the technical regulations;

2)驾驶室和回转支承之间连接应牢固可靠;2) The connection between the cab and the slewing bearing should be firm and reliable;

3)最高附着点下塔身轴线对支承面垂直度应≤相应高度的2/1000,独立状态或附着状态下最高附着点以上塔身轴线对支承面垂直度应≤4/1000。3) The verticality of the tower axis to the supporting surface below the highest attachment point should be ≤ 2/1000 of the corresponding height. The verticality of the tower axis above the highest attachment point to the supporting surface in the independent or attached state should be ≤ 4/1000.

前述的塔式起重机安装及拆卸方法中,塔机平衡臂、起重臂、平衡重、制动装置及各类安全限位装置安装完毕后应重点检查:In the above tower crane installation and disassembly methods, the tower crane balance arm, lifting arm, counterweight, brake device and various safety limit devices should be checked after installation:

1)平衡臂、起重臂和塔身之间连接是否紧固可靠,连接销轴应无窜动,紧固符合技术要求;1) Whether the connection between the balance arm, the boom and the tower body is tight and reliable, the connecting pin should not move, and the tightness meets the technical requirements;

2)平衡臂、起重臂各节之间连接是否紧固可靠,紧固应符合技术规定;2) Whether the connection between the balance arm and the crane arm is tight and reliable, and the tightness should comply with technical regulations;

3)护栏、护圈等安全装置是否齐全,牢固可靠;3) Whether the safety devices such as guardrails and guard rings are complete, firm and reliable;

4)平衡臂拉杆安装是否正确,受力均匀,连接紧固应符合技术规定;4) Whether the balance arm tie rod is installed correctly, the force is evenly distributed, and the connection and tightening meet the technical requirements;

5)平衡重的重量、安装位置和固定情况是否符合技术规定;5) Whether the weight, installation position and fixing of the counterweight meet the technical requirements;

6)检测驾驶室供电电压,其值应为380v±5%;6) Check the cab power supply voltage, the value should be 380v±5%;

7)对起升、变幅、回转工作机构进行试运转,应平稳无异响,制动灵敏可靠;7) Test run the lifting, luffing and slewing working mechanisms, which should be stable and without abnormal noise, and the braking should be sensitive and reliable;

8)试验各类安全限位保护装置,动作应灵敏可靠。8) Test various safety limit protection devices, and the operation should be sensitive and reliable.

前述的塔式起重机安装及拆卸方法中,开口销检查:In the above tower crane installation and disassembly methods, the split pin inspection:

1)起重臂及平衡臂的拉杆销轴的开口销必须在吊装前进行一次全面检查,以防漏装或开口销未打开现象;1) The cotter pins of the tie rod pin shafts of the crane arm and the balance arm must be fully inspected before lifting to prevent missing installation or cotter pins not opening;

2)检查起重臂、平衡臂、塔帽连接处销轴的开口销尺寸、大小是否符合要求;2) Check whether the size and size of the cotter pins at the connection between the boom, balance arm and tower cap meet the requirements;

3)检查开口销安装的位置是否符合要求。3) Check whether the installation position of the cotter pin meets the requirements.

前述的塔式起重机安装及拆卸方法中,整机安装完毕后的技术检验:In the above tower crane installation and disassembly methods, the technical inspection after the whole machine is installed is:

对各个工作机构进行检验和调整,要求各机构动作正确、平稳、无异响,制动灵敏可靠;Inspect and adjust each working mechanism, requiring that each mechanism operates correctly, smoothly, without abnormal noise, and that the brakes are sensitive and reliable;

检验整机钢结构应安装正确,无变形、开焊、裂痕,检查所有连接点的紧固情况,螺栓、销轴牢固可靠,紧固符合技术规定;Check that the steel structure of the whole machine is installed correctly without deformation, open welding or cracks. Check the tightness of all connection points. The bolts and pins are firm and reliable, and the tightness meets the technical requirements.

对各安全保护装置进行检验和调整,要求限位动作准确、灵敏、可靠;Inspect and adjust each safety protection device, requiring the limit action to be accurate, sensitive and reliable;

1)起升机构超高限位,要求吊钩至起重臂之间的安全距离≥800cm;1) The lifting mechanism has an over-height limit, requiring the safety distance between the hook and the boom to be ≥800cm;

2)小车变幅的前后限位,要求起重小车限位停车位置,最外端距轨道终端止挡的距离≥20-30cm;2) The front and rear limits of the trolley's amplitude change require that the distance between the outermost end of the trolley and the track terminal stop be ≥20-30cm;

3)对力矩保护装置进行校验,力矩保护精度误差≤5%;3) Check the torque protection device, and the torque protection accuracy error shall be ≤5%;

经过以上阶段及整机检验后,填写设备安装自检记录。After the above stages and the inspection of the whole machine, fill in the equipment installation self-inspection record.

本发明的有益效果:与现有技术相比,本发明的方法中通过对塔机安、拆过程中的诸多技术要点进行详细的阐述说明,使用过程中严格按照上述技术要点进行操作,按照正规作业程序施工,就可以很好地控制安全风险,避免发生安全事故。Beneficial effects of the present invention: Compared with the prior art, the method of the present invention explains in detail many technical points in the installation and dismantling process of the tower crane. During use, the operation is strictly carried out in accordance with the above technical points and the construction is carried out according to the regular operating procedures, which can well control the safety risks and avoid safety accidents.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1为塔机的安装工艺流程图;Fig. 1 is a flow chart of the installation process of the tower crane;

图2为塔机的拆卸工艺流程图。Figure 2 is a process flow chart of tower crane disassembly.

具体实施方式DETAILED DESCRIPTION

下面结合附图和实施例对本发明作进一步的说明,但并不作为对本发明限制的依据。The present invention is further described below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the present invention.

本发明的实施例:塔式起重机安装及拆卸方法,塔机安装流程为:确定基础施工方案→砼基础施工及验收→设置动力源→清点零部件、构件→按步骤安装塔机基本构件→顶升加节到允许自由高度→锚固加节→安装到所需高度→接地电阻、垂直度测量→整机调试;塔机拆卸流程为:查看拆卸现场、检查塔机各部件、准备拆卸工具材料→编制具体拆卸方案→下达拆卸工作任务单→降塔→拆除附墙装置→降到允许的最小高度→用汽车吊拆卸各构件总成→清单零部件、构件→构件运输出场→分类堆放。The embodiment of the present invention is a tower crane installation and disassembly method, the tower crane installation process is: determine the foundation construction plan → concrete foundation construction and acceptance → set the power source → count the parts and components → install the basic components of the tower crane in steps → lift and add sections to the allowed free height → anchor and add sections → install to the required height → measure ground resistance and verticality → debug the whole machine; the tower crane disassembly process is: check the disassembly site, check the various parts of the tower crane, prepare disassembly tools and materials → prepare a specific disassembly plan → issue a disassembly work task list → lower the tower → remove the wall-mounted device → lower to the minimum allowed height → use a truck crane to disassemble the component assemblies → check the parts and components → transport the components to the site → classify and stack them.

塔机安拆顺序:按其使用说明书要求进行,若遇特殊情况,需由使用、安拆单位根据现场情况制定专项方案及措施。The order of tower crane installation and disassembly: follow the requirements of its instruction manual. In case of special circumstances, the user and installation units must formulate special plans and measures based on the on-site conditions.

1)在安拆作业开始前,应进行一次全面检查,以防止由于疏忽而存在隐患,确保安全作业。1) Before installation and disassembly work begins, a comprehensive inspection should be carried out to prevent hidden dangers due to negligence and ensure safe operation.

2)检查设备基础是否符合技术要求。水平度误差小于1/500,将地脚螺栓或设备基础节进行抄平并调整至允许范围以内。2) Check whether the equipment foundation meets the technical requirements. The horizontal error is less than 1/500, and the anchor bolts or equipment foundation sections are leveled and adjusted to within the allowable range.

3)对设备各机构、部位、结构焊缝、重要部位螺栓、销轴、卷扬机构和钢丝绳、吊钩、吊具、安全限位装置以及电气设备、线路等进行仔细检查,发现问题应立即解决。3) Carefully inspect all mechanisms, parts, structural welds, bolts in important parts, pins, winch mechanisms and wire ropes, hooks, slings, safety limit devices, electrical equipment, lines, etc. of the equipment, and solve any problems found immediately.

4)检查塔机顶升液压系统的液压缸和油管、顶升套架结构、导向轮、顶升块及止动器等。4) Check the hydraulic cylinder and oil pipe of the tower crane's jacking hydraulic system, the jacking frame structure, guide wheels, jacking blocks and stoppers, etc.

5)检查塔机起升系统钢丝绳、制动装置等,确认无误后方可使用。5) Check the wire rope, brake device, etc. of the tower crane hoisting system and use it only after confirming that they are correct.

6)对安装人员所使用的工具、安全带、安全帽等进行全面检查,不合格者立即更换。6) Conduct a comprehensive inspection of the tools, safety belts, safety helmets, etc. used by the installers, and replace any that fail to meet the standards immediately.

7)检查安拆作业中使用的辅助机械,如起重机、运输汽车等必须性能良好,技术要求能保证安拆作业需要。7) Check that the auxiliary machinery used in the installation and dismantling operations, such as cranes, transport vehicles, etc., must have good performance and the technical requirements can meet the needs of the installation and dismantling operations.

8)检查安拆现场有关情况,如电源、运输道路、作业场地等是否已具备安拆作业条件。8) Check the installation and dismantling site conditions, such as whether the power supply, transportation roads, work sites, etc. are ready for installation and dismantling.

9)安全监督岗的设置及安全措施的贯彻落实已符合要求。9) The establishment of safety supervision posts and the implementation of safety measures have met the requirements.

安装作业,应根据专项施工方案要求实施。安装作业人员应分工明确、职责清楚。安装前应对安装作业人员进行安全技术交底,交底人和被交底人双方应在交底书上签字,专职安全员应监督整个交底过程。Installation work should be carried out according to the requirements of the special construction plan. The installation workers should have clear division of labor and responsibilities. Before installation, the installation workers should be given safety and technical explanations. Both the person giving the explanation and the person being explained should sign the explanation book, and the full-time safety officer should supervise the entire explanation process.

安装辅助设备就位后,应对其机械和安全性能进行检验,合格后方可作业。实际应用中,经常发现因安装辅助设备自身安全性能出现故障而发生塔式起重机安全事故,所以要对安装辅助设备的机械性能进行检查,合格后方可使用。After the auxiliary equipment is installed in place, its mechanical and safety performance should be inspected and it can only be used after it passes the inspection. In actual applications, it is often found that tower crane safety accidents occur due to failure of the safety performance of the auxiliary equipment itself, so the mechanical performance of the auxiliary equipment should be inspected and it can only be used after it passes the inspection.

安装作业中应统一指挥,明确指挥信号。当视线受阻、距离过远时,应采用对讲机或多级指挥。During the installation work, unified command and clear command signals should be implemented. When the line of sight is blocked or the distance is too far, intercom or multi-level command should be used.

自升式塔式起重机的顶升加节,应符合下列要求:The lifting section of a self-erecting tower crane shall meet the following requirements:

1)顶升系统必须完好;1) The lifting system must be intact;

2)结构件必须完好;2) Structural parts must be intact;

3)顶升前,塔式起重机下支座与顶升套架应可靠连接;3) Before lifting, the lower support of the tower crane and the lifting frame should be reliably connected;

4)顶升前,应确保顶升横梁搁置正确;4) Before lifting, ensure that the lifting beam is placed correctly;

5)顶升前,应将塔式起重机配平;顶升过程中,应确保塔式起重机的平衡;5) Before lifting, the tower crane should be leveled; during the lifting process, the balance of the tower crane should be ensured;

6)顶升加节的顺序,应符合产品说明书的规定;6) The order of lifting and adding sections should comply with the provisions of the product manual;

7)顶升过程中,不应进行起升、回转、变幅等操作;7) During the lifting process, lifting, rotation, and luffing operations should not be performed;

8)顶升结束后,应将标准节与回转下支座可靠连接;8) After the lifting is completed, the standard section should be reliably connected to the lower slewing support;

9)塔式起重机加节后需进行附着的,应按照先装附着装置、后顶升加节的顺序进行,附着装置的位置和支撑点的强度应符合要求。9) If a tower crane needs to be attached after adding sections, the sequence should be to install the attachment device first and then lift and add sections. The position of the attachment device and the strength of the supporting points should meet the requirements.

塔式起重机的独立高度、悬臂高度应符合产品说明书的要求。The independent height and cantilever height of the tower crane should comply with the requirements of the product manual.

雨雪、浓雾天严禁进行安装作业。安装时塔式起重机最大高度处的风速应符合产品说明书的要求,且风速不得超过12m/s。Installation work is strictly prohibited in rainy, snowy and foggy days. The wind speed at the maximum height of the tower crane during installation should meet the requirements of the product manual and should not exceed 12m/s.

塔式起重机不宜在夜间进行安装作业;特殊情况下,必须在夜间进行塔式起重机安装和拆卸作业时,应保证提供足够的照明。It is not advisable to install tower cranes at night; in special circumstances, when tower crane installation and disassembly operations must be carried out at night, sufficient lighting should be provided.

特殊情况,当安装作业不能连续进行时,必须将已安装的部位固定牢靠并达到安全状态,经检查确认无隐患后,方可停止作业。In special circumstances, when the installation work cannot be carried out continuously, the installed parts must be securely fixed and in a safe state, and the work can only be stopped after inspection and confirmation that there are no hidden dangers.

电气设备应按产品说明书的要求进行安装,安装所用的电源线路应符合现行行业标准《施工现场临时用电安全技术规范》JGJ46的要求。Electrical equipment should be installed according to the requirements of the product manual, and the power lines used for installation should comply with the requirements of the current industry standard "Technical Specifications for Temporary Electricity Safety at Construction Sites" JGJ46.

塔式起重机的安全装置必须齐全,并应按程序进行调试合格。The safety devices of tower cranes must be complete and should be debugged and qualified according to the procedures.

联接件及其防松防脱件应符合规定要求,严禁用其他代用品代用。联接件及其防松防脱件应使用力矩扳手或专用工具紧固联接螺栓,使预紧力矩达到规定要求。The connection parts and their anti-loosening and anti-dropping parts shall meet the specified requirements, and it is strictly forbidden to use other substitutes. The connection parts and their anti-loosening and anti-dropping parts shall use torque wrenches or special tools to tighten the connection bolts so that the pre-tightening torque meets the specified requirements.

1)设备安拆作业应在白天进行,如需加快进度,可在具备良好照明条件的夜间做一些简单拼装工作,不得在大风、浓雾和雨雪天气进行。1) Equipment installation and disassembly should be carried out during the day. If the progress needs to be accelerated, some simple assembly work can be done at night with good lighting conditions. It should not be carried out in strong winds, dense fog, rain or snow.

2)在安拆作业过程中,必须保持现场的整洁和秩序,不得堆存杂物以免妨碍作业并影响安全。设备金属结构下面必须垫放木枋,防止损坏结构或造成结构变形。2) During the installation and disassembly process, the site must be kept clean and orderly, and no debris should be piled up to avoid hindering the work and affecting safety. Wooden beams must be placed under the metal structure of the equipment to prevent damage to the structure or deformation of the structure.

3)安拆架设用的钢丝绳及其固定必须符合标准和满足安拆上的要求。3) The steel wire rope used for installation and its fixing must comply with the standards and meet the installation requirements.

4)在进行逐件组拼或部件安装之前,必须对部件各部分的完好情况、连接情况和钢丝绳穿绕情况、电气线路等进行全面检查。4) Before assembling or installing components piece by piece, a comprehensive inspection must be carried out on the integrity of each component, the connection condition, the wire rope threading condition, the electrical circuits, etc.

5)在安拆塔机起重臂和平衡臂时,要始终保持起重机的平衡,不允许只安拆一个起重臂(或平衡臂)就中断作业。5) When installing or disassembling the tower crane's boom and counter-arm, the crane must always be kept balanced. It is not allowed to interrupt the operation just to install or disassemble one boom (or counter-arm).

6)在安拆作业过程中,如突然发生停电、机械故障、天气骤变等情况不能继续作业,或作业时间已到需要停休时,必须使设备已安装的部位达到稳定状态并已锁固牢靠,所有结构件已连接牢固,经过检查确认妥善后,方可停止作业。6) During the installation and disassembly process, if there is a sudden power outage, mechanical failure, sudden weather change, etc. and the operation cannot continue, or the operation time has reached and a break is required, the installed part of the equipment must be stabilized and securely locked, all structural parts must be firmly connected, and the operation can only be stopped after inspection and confirmation that it is proper.

7)安拆时应使用规定的螺栓、销轴等连接件,并要有可靠的防松或保护装置。螺栓紧固时应符合规定的预紧力。钢丝绳安装应严格执行GB5972-2006《起重机械用钢丝绳检验和报废实用规范》。7) When installing and disassembling, the specified bolts, pins and other connectors should be used, and reliable anti-loosening or protective devices should be provided. The bolts should be tightened with the specified preload. The installation of wire ropes should strictly follow GB5972-2006 "Practical Specifications for Inspection and Retirement of Wire Ropes for Hoisting Machinery".

8)安拆作业的程序、辅助设备、索具、工具等,均应遵照该机使用说明书中的规定。8) The installation and disassembly procedures, auxiliary equipment, rigging, tools, etc. should comply with the provisions of the machine's instruction manual.

应检查设备基础表面平整度、混凝土强度、预埋件位置、排水沟设置等,均应符合要求。The surface flatness of the equipment foundation, concrete strength, position of embedded parts, drainage ditch settings, etc. should be checked and all should meet the requirements.

基础节的安装位置(包括水平和垂直偏差)在允许范围内,螺栓齐全,紧固符合规定。The installation position of the foundation section (including horizontal and vertical deviations) is within the allowable range, the bolts are complete, and the tightening complies with regulations.

1)标准节的型号(指有加强节)及安装位置是否符合原厂说明书的安装规定,标准节和基础节螺栓的预紧力应符合技术规定。1) Whether the model of the standard section (referring to the reinforced section) and the installation position comply with the installation regulations of the original manufacturer's instructions, and the preload force of the standard section and foundation section bolts should comply with the technical regulations.

2)驾驶室和回转支承之间连接应牢固可靠。2) The connection between the cab and the slewing bearing should be firm and reliable.

3)最高附着点下塔身轴线对支承面垂直度不得大于相应高度的2/1000,独立状态或附着状态下最高附着点以上塔身轴线对支承面垂直度不得大于4/1000。3) The verticality of the tower axis to the supporting surface below the highest attachment point shall not be greater than 2/1000 of the corresponding height; the verticality of the tower axis above the highest attachment point to the supporting surface in the independent or attached state shall not be greater than 4/1000.

1)平衡臂、起重臂和塔身之间连接是否紧固可靠,连接销轴应无窜动,紧固符合技术要求。1) Whether the connection between the balance arm, the lifting arm and the tower body is tight and reliable, the connecting pin shaft should not move, and the tightness meets the technical requirements.

2)平衡臂、起重臂各节之间连接是否紧固可靠,紧固应符合技术规定。2) Whether the connections between the balance arm and the lifting arm are tight and reliable, the tightness should comply with technical regulations.

3)护栏、护圈等安全装置是否齐全,牢固可靠。3) Whether guardrails, guard rings and other safety devices are complete, firm and reliable.

4)平衡臂拉杆安装是否正确,受力均匀,连接紧固应符合技术规定。4) Check whether the balance arm tie rod is installed correctly, the force is evenly distributed, and the connection is tight in accordance with technical regulations.

5)平衡重的重量、安装位置和固定情况是否符合技术规定。5) Whether the weight, installation position and fixation of the counterweight comply with the technical regulations.

6)检测驾驶室供电电压,其值应为380v±5%。6) Check the cab power supply voltage, the value should be 380v±5%.

7)对起升、变幅、回转等工作机构进行试运转,应平稳无异响,制动灵敏可靠。7) Test run the lifting, boom lengthening, slewing and other working mechanisms, which should be smooth and noise-free, and the braking should be sensitive and reliable.

8)试验各类安全限位保护装置,动作应灵敏可靠。8) Test various safety limit protection devices, and the operation should be sensitive and reliable.

1)起重臂及平衡臂的拉杆销轴的开口销必须在吊装前进行一次全面检查,以防漏装或开口销未打开等现象。1) The cotter pins of the tie rod pin shafts of the crane arm and the balance arm must be fully inspected before lifting to prevent missing installation or cotter pins not opening.

2)检查起重臂、平衡臂、塔帽等连接处销轴的开口销尺寸、大小是否符合要求。2) Check whether the size and dimensions of the cotter pins at the joints of the crane arm, balance arm, tower cap, etc. meet the requirements.

3)检查开口销安装的位置是否符合要求。3) Check whether the installation position of the cotter pin meets the requirements.

对各个工作机构进行检验和调整,要求各机构动作正确、平稳、无异响,制动灵敏可靠。Inspect and adjust each working mechanism, requiring it to operate correctly, smoothly, without abnormal noise, and have sensitive and reliable braking.

检验整机钢结构应安装正确,无变形、开焊、裂痕等。检查所有连接点的紧固情况,螺栓、销轴牢固可靠,紧固符合技术规定。Check that the steel structure of the whole machine is installed correctly without deformation, open welding, cracks, etc. Check the tightness of all connection points, and that the bolts and pins are firm and reliable, and the tightness meets the technical regulations.

对各安全保护装置进行检验和调整,要求限位动作准确、灵敏、可靠。Inspect and adjust each safety protection device, requiring the limit action to be accurate, sensitive and reliable.

1)起升机构超高限位,要求吊钩至起重臂(或起重小车)之间的安全距离不小于800cm。1) The lifting mechanism has an over-height limit, requiring the safe distance between the hook and the crane arm (or crane trolley) to be no less than 800cm.

2)小车变幅的前后限位,要求起重小车限位停车位置,最外端距轨道终端止挡的距离不小于20-30cm。2) The front and rear limits of the trolley's amplitude change require that the distance between the outermost end of the lifting trolley and the terminal stop of the track should be no less than 20-30cm.

3)对力矩保护装置进行校验,力矩保护精度误差不大于5%。3) Check the torque protection device and the torque protection accuracy error shall not exceed 5%.

经过以上阶段及整机检验后,填写设备安装自检记录。After the above stages and the inspection of the whole machine, fill in the equipment installation self-inspection record.

塔机在安拆过程中重大危险源主要包括以下几个方面内容:The major hazards of tower cranes during installation and dismantling mainly include the following aspects:

1)设备倾覆;1) Equipment overturning;

2)触电危险;2) Danger of electric shock;

3)物体打击;3) Object strike;

4)高空坠落等。4) Falling from a height, etc.

针对塔机在安拆过程中的重大危险源,编制安全技术措施。Formulate safety technical measures to address major hazards during the installation and dismantling of tower cranes.

完善设备安全管理制度,做到层层落实把关,职责到人。Improve the equipment safety management system, ensure that controls are implemented at every level and that responsibilities are assigned to individuals.

安拆操作司机必须持有效证件上岗,严格遵守《塔机安全技术操作规程》,严禁违章操作,并做好安全技术交底,作业前召开安全技术交底会,做好书面记录。Installation and disassembly operators must hold valid certificates to work, strictly abide by the "Safety Technical Operation Regulations for Tower Cranes", strictly prohibit illegal operations, and conduct safety and technical briefings. A safety and technical briefing meeting must be held before operations, and written records must be kept.

建立操作司机、指挥、安拆、维保等人员岗位职责,做到分工明确,职责清楚。Establish job responsibilities for operators, commanders, installers, maintenance personnel, etc., to ensure clear division of labor and responsibilities.

塔机安装完毕(或拆除前),现场技术人员组织主车司机对设备关键部位进行一次检查,发现问题及时纠正整改。After the tower crane is installed (or before it is dismantled), on-site technicians organize the main vehicle driver to inspect the key parts of the equipment and correct any problems found in a timely manner.

起重作业人员必须了解起重吊装工作的一些基本知识,掌握起重吊装作业的基本技能,配备必需的联络工具,如对讲机等。Lifting operators must understand some basic knowledge of lifting and hoisting work, master the basic skills of lifting and hoisting operations, and be equipped with necessary communication tools, such as walkie-talkies.

塔机作业区域内高压线、供电电压降的安全处理措施:Safety measures for high-voltage lines and power supply voltage drops in the tower crane operation area:

1)对影响安拆施工的高压线,应改变高压线布置,或者采取措施用绝缘橡胶管包裹高压线。1) For high-voltage lines that affect installation and removal, the layout of the high-voltage lines should be changed, or measures should be taken to wrap the high-voltage lines with insulating rubber tubes.

2)设备安装完毕,必须对其接地电阻进行测量,一般要求接地电阻<5欧姆;主电路和控制电路的对地绝缘电阻不应小于0.5MΩ。2) After the equipment is installed, its grounding resistance must be measured. Generally, the grounding resistance is required to be <5 ohms; the insulation resistance of the main circuit and control circuit to ground should not be less than 0.5MΩ.

3)塔机在安拆及运行过程中,避免在磁场的作用下撞上高压线。3) During the installation and operation of the tower crane, avoid colliding with high-voltage lines under the influence of the magnetic field.

4)当安装高度超过100m时,应在中间位置设置二次供电线路,或者增大输电电缆的截面积,减小电压降和电流损失。4) When the installation height exceeds 100m, a secondary power supply line should be set in the middle position, or the cross-sectional area of the transmission cable should be increased to reduce voltage drop and current loss.

按照说明书所附的有关电气原理图将线路接通。Connect the circuit according to the relevant electrical schematic diagram attached to the instruction manual.

经认真检查确认无误后方可进行空载下的运转。Operation under no-load condition can only be carried out after careful inspection and confirmation.

按要求调整好高度限位器、变幅限制器及回转限制器,使其灵敏可靠。Adjust the height limiter, amplitude limiter and slew limiter as required to make them sensitive and reliable.

调整重量限制器及力矩限制器,调试完毕,操作司机不得随意变动。Adjust the weight limiter and torque limiter. After debugging, the operator shall not change them at will.

塔式起重机拆卸作业宜连续进行;当遇特殊情况,拆卸作业不能继续时,应采取措施保证塔式起重机处于安全状态。The dismantling operation of tower cranes should be carried out continuously; when special circumstances occur and the dismantling operation cannot continue, measures should be taken to ensure that the tower crane is in a safe state.

当用于拆卸作业的辅助起重设备设置在建筑物上时,应明确设置位置、锚固方法,并应对辅助起重设备的安全性及建筑物的承载能力等进行验算。When auxiliary lifting equipment used for dismantling operations is set on a building, the setting location and anchoring method should be clearly specified, and the safety of the auxiliary lifting equipment and the bearing capacity of the building should be verified.

拆卸前应检查下列项目:主要结构件、连接件、电气系统、起升机构、回转机构、变幅机构、顶升机构等。发现隐患应采取措施,解决后方可进行拆卸作业。Before disassembly, the following items should be checked: main structural parts, connectors, electrical system, lifting mechanism, slewing mechanism, luffing mechanism, jacking mechanism, etc. If hidden dangers are found, measures should be taken and disassembly can only be carried out after they are resolved.

附着式塔式起重机应明确附着装置的拆卸顺序和方法。For attached tower cranes, the sequence and method of disassembly of the attachment device should be clearly stated.

自升式塔式起重机每次降节前,应检查顶升系统和附着装置的联接等,确认完好后方可进行作业。Before lowering a self-erecting tower crane each time, the connections between the jacking system and the attachment device should be checked, and operations can only be carried out after confirming that they are in good condition.

拆卸时应先降节、后拆除附着装置。塔式起重机的自由端高度应符合规定要求。When disassembling, the section should be lowered first and then the attachment device should be removed. The free end height of the tower crane should meet the specified requirements.

拆卸完毕后,为塔式起重机拆卸作业而设置的所有设施应拆除,清理场地上作业时所用的吊索具、工具等各种零配件和杂物。After the dismantling is completed, all facilities set up for the tower crane dismantling operation should be removed, and the slings, tools and other spare parts and debris used in the operation on the site should be cleared.

Claims (8)

1. The method for installing and dismantling the tower crane is characterized in that: the installation flow of the tower crane is as follows: determining a foundation construction scheme, constructing a concrete foundation, checking and accepting, setting a power source, checking parts and components, installing basic components of a tower crane according to steps, jacking a joint to a permissible free height, anchoring the joint, installing the joint to a required height, measuring grounding resistance and verticality, and debugging the whole machine; the disassembly flow of the tower crane is as follows: checking a disassembly field, checking all parts of a tower crane, preparing disassembly tool materials, compiling a specific disassembly scheme, issuing a disassembly work order, lowering a tower, dismantling a wall attaching device, lowering the minimum allowable height, disassembling all component assemblies by using an automobile crane, listing parts and components, transporting the components out of a field, and stacking the components in a classified mode.
2. The tower crane installation and removal method according to claim 1, wherein: technical inspection key points before installing and detaching the tower crane:
1) Before the start of the mounting and dismounting operation, a comprehensive inspection should be performed;
2) Checking whether the equipment foundation meets the technical requirement or not, leveling the foundation bolts or the equipment foundation sections until the levelness error is less than 1/500, and adjusting the foundation bolts or the equipment foundation sections to be within an allowable range;
3) Carefully inspecting all mechanisms, parts, structural welding lines, important part bolts, pin shafts, hoisting mechanisms, steel wire ropes, lifting hooks, lifting slings, safety limiting devices, electrical equipment and circuits of the equipment, and immediately solving the found problems;
4) Checking a hydraulic cylinder, an oil pipe, a jacking sleeve frame structure, a guide wheel, a jacking block and a stopper of a jacking hydraulic system of the tower crane;
5) Checking a steel wire rope and a braking device of a lifting system of the tower crane, the back of the confirmation is usable without error;
6) The tool, the safety belt and the safety helmet used by the installer are comprehensively checked, and the unqualified person is immediately replaced;
7) Checking auxiliary machinery used in the mounting and dismounting operation, wherein the technical requirement can ensure the requirement of the mounting and dismounting operation;
8) Checking whether the safety commutation field has the safety and disassembly operation conditions or not;
9) Checking whether the setting of the safety supervision post and implementation of the safety measures meet the requirements.
3. The tower crane installation and removal method according to claim 1, wherein: the jacking section of the self-elevating tower crane meets the following requirements:
1) The jacking system must be intact;
2) The structural member must be intact;
3) Before jacking, the lower support of the tower crane is reliably connected with the jacking sleeve frame;
4) Before jacking, the jacking cross beam is ensured to be placed correctly;
5) Before jacking, balancing the tower crane; in the jacking process, the balance of the tower crane is ensured;
6) The sequence of jacking and adding the sections accords with the specification of the product specification;
7) In the jacking process, lifting, turning and amplitude changing operations are not required;
8) After the jacking is finished, the standard joint is reliably connected with the rotary lower support;
9) The tower crane needs to be attached after the joint is added, the attachment device is firstly attached, then the joint is lifted, and the position of the attachment device and the strength of the supporting point meet the requirements.
4. The tower crane installation and removal method according to claim 1, wherein: safety technical control requirements in the mounting and dismounting operation are as follows:
1) The equipment mounting and dismounting operation should be carried out in daytime, if the progress needs to be quickened, some simple assembly operations can be carried out at night with good lighting conditions, and the equipment mounting and dismounting operation cannot be carried out in windy, heavy fog and rainy and snowy weather;
2) In the process of mounting and dismounting operation, the field must be kept clean and orderly, sundries must not be piled up to avoid interference to operation and influence safety, and wood beams must be padded under the metal structure of the equipment to prevent damage to the structure or deformation of the structure;
3) The steel wire rope for mounting and dismounting and the fixing thereof are required to meet the standard and meet the requirements of mounting and dismounting;
4) Before assembling or installing the components piece by piece, the complete inspection of the complete condition, connection condition and wire rope threading condition of each part of the components and the electric circuit is required;
5) When the crane boom and the balance arm of the tower crane are dismounted, the balance of the crane is always kept, and only one crane boom is not allowed to be dismounted, so that the operation is interrupted;
6) In the process of installing and dismantling operation, if power failure, mechanical failure and weather sudden change occur suddenly, the operation cannot be continued, or when the operation time reaches the stop-and-break requirement, the installed part of the equipment must be in a stable state and firmly locked, all structural members are firmly connected, and after checking and confirming that the structural members are good, the operation can be stopped;
7) The bolt and the pin shaft connector are required to be used in mounting and dismounting, and a reliable anti-loosening or protecting device is required, and the bolt is required to meet the preset pretightening force in fastening;
8) The procedures, auxiliary equipment, rigging and tools for the mounting and dismounting operation should be in accordance with the specifications of the machine.
5. The tower crane installation and removal method according to claim 1, wherein: after the standard section and the rotary platform are installed, the important inspection is carried out:
1) Whether the model and the installation position of the standard joint accord with the installation specification of the original factory specification or not, and the pretightening force of bolts of the standard joint and the foundation joint accord with the technical specification;
2) The connection between the cab and the slewing bearing should be firm and reliable;
3) The verticality of the axis of the tower body below the highest attachment point to the supporting surface is less than or equal to 2/1000 of the corresponding height, and the verticality of the axis of the tower body above the highest attachment point in an independent state or an attachment state to the supporting surface is less than or equal to 4/1000.
6. The tower crane installation and removal method according to claim 1, wherein: the balance arm, the crane arm, the balance weight, the braking device and various safety limiting devices of the tower crane should be mainly checked after being installed:
1) Whether the connection among the balance arm, the lifting arm and the tower body is reliable or not, the connecting pin shaft should not have play, and the fastening meets the technical requirements;
2) Whether the connection between each section of the balance arm and each section of the crane arm is reliable or not, and the fastening should meet the technical specification;
3) Safety devices such as guardrails, guard rings and the like are complete, firm and reliable;
4) Whether the balance arm pull rod is installed correctly or not, the stress is even, and the connection and the fastening should meet the technical specification;
5) Whether the weight, the installation position and the fixing condition of the balancing weight accord with technical regulations or not;
6) Detecting the power supply voltage of a cab, wherein the value of the power supply voltage is 380 v+/-5%;
7) Test operation is carried out on the lifting, luffing and rotating working mechanisms, so that the lifting, luffing and rotating working mechanisms are stable, have no abnormal sound, and are sensitive and reliable in braking;
8) Various safety limit protection devices are tested, and the action is sensitive and reliable.
7. The tower crane installation and removal method according to claim 1, wherein: cotter pin inspection:
1) The cotter pins of the pull rod pin shafts of the lifting arm and the balance arm must be comprehensively checked once before hoisting so as to prevent neglected loading or the cotter pins from being opened;
2) Checking whether the size and the dimension of the cotter pin of the pin shaft at the joint of the lifting arm, the balance arm and the tower cap meet the requirements;
3) Checking whether the installation position of the cotter pin meets the requirement.
8. The tower crane installation and removal method according to claim 1, wherein: technical inspection after the whole machine is installed:
each working mechanism is checked and adjusted, so that each mechanism is required to act correctly, stably and without abnormal sound, and the braking is sensitive and reliable;
The steel structure of the whole machine is checked to be correctly installed, deformation, welding and cracks are avoided, the fastening condition of all connection points is checked, the bolts and the pin shafts are firm and reliable, and the fastening meets the technical specifications;
each safety protection device is checked and adjusted, and the limiting action is required to be accurate, sensitive and reliable;
1) The lifting mechanism is ultrahigh in limit, and the safety distance between the lifting hook and the lifting arm is required to be more than or equal to 800cm;
2) The trolley is limited in the front and back of amplitude variation, the trolley is required to be limited in stopping position, and the distance between the outermost end and a rail terminal stop is more than or equal to 20-30cm;
3) Checking the moment protection device, wherein the moment protection precision error is less than or equal to 5%;
after the above stage and the whole machine inspection, the equipment installation self-checking record is filled in.
CN202411097203.7A 2024-08-12 2024-08-12 Tower crane installation and disassembly methods Pending CN118619129A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202411097203.7A CN118619129A (en) 2024-08-12 2024-08-12 Tower crane installation and disassembly methods

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202411097203.7A CN118619129A (en) 2024-08-12 2024-08-12 Tower crane installation and disassembly methods

Publications (1)

Publication Number Publication Date
CN118619129A true CN118619129A (en) 2024-09-10

Family

ID=92606834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202411097203.7A Pending CN118619129A (en) 2024-08-12 2024-08-12 Tower crane installation and disassembly methods

Country Status (1)

Country Link
CN (1) CN118619129A (en)

Similar Documents

Publication Publication Date Title
CN103982045B (en) A kind of roofing latticed shell structure is encorbelmented construction method of installation without support
CN104631839A (en) Construction method for integrally lifting super-high, super-heavy, large-span space corridor
CN111636693A (en) A BIM-based steel grid installation and construction method
LU506578B1 (en) Construction method of large-span steel structure workshop main body engineering
CN106812670B (en) The construction method for hanging of large-scale wind electricity equipment under Mountain Conditions
CN109235903A (en) Steel structure modularization construction method
CN117449209A (en) A bridge steel structure installation and construction closing method
CN112978561B (en) Hoisting construction method of shield machine under 220kV high-voltage line
CN105275251A (en) Railway existing line overhead line system hard crossbeam erection method
CN111395848A (en) Mast type steel structure and inhaul cable installation construction method
CN110104568B (en) A self-inspection evaluation method for tower crane installation
CN118619129A (en) Tower crane installation and disassembly methods
CN212532065U (en) A gantry crane that can be used in different height difference sites
CN113896089B (en) Construction method of oversized blast furnace
CN111792540A (en) Full reverse construction method for hanging movable electric hoist on main structure beam slab
CN117905285A (en) Construction method of high-rise building steel structure and building material hoisting mechanism thereof
CN112249915A (en) Large bridge crane hoisting method for closed occasions of factory buildings
CN117735416A (en) Combined hoisting method for blast furnace shaft frame
CN211848999U (en) Bilateral balanced draw gear of steel structure frame bridge
CN102041784B (en) Horizontal rotation construction technology of oversized, overweight and special-shaped construction member through multipoint hoisting and horizontal rotation hanger
CN115352984A (en) Safe Construction Method for Track Transportation in Inclined Shaft
CN120622329A (en) Mounting and dismounting and hoisting method for oversized bridge crane
CN121894557A (en) Construction method of tower crane
CN117738473A (en) Installation and construction method of steel rib column
CN113931076B (en) Prefabricated installation construction method for bridge deck plate of gradient section of steel plate composite beam bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication