CN118598037A - A lifting mechanism for building construction machine platform - Google Patents

A lifting mechanism for building construction machine platform Download PDF

Info

Publication number
CN118598037A
CN118598037A CN202410767355.7A CN202410767355A CN118598037A CN 118598037 A CN118598037 A CN 118598037A CN 202410767355 A CN202410767355 A CN 202410767355A CN 118598037 A CN118598037 A CN 118598037A
Authority
CN
China
Prior art keywords
limiting structure
lifting
unit
standard section
support unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202410767355.7A
Other languages
Chinese (zh)
Inventor
张宗军
谭华泰
王琼
余英海
张楠
赵宝军
毛晔
叶红
党朋飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Hailong Construction Technology Co Ltd
China State Construction Hailong Technology Co Ltd
Original Assignee
Guangdong Hailong Construction Technology Co Ltd
China State Construction Hailong Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Hailong Construction Technology Co Ltd, China State Construction Hailong Technology Co Ltd filed Critical Guangdong Hailong Construction Technology Co Ltd
Priority to CN202410767355.7A priority Critical patent/CN118598037A/en
Publication of CN118598037A publication Critical patent/CN118598037A/en
Pending legal-status Critical Current

Links

Classifications

    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B66—HOISTING; LIFTING; HAULING
    • B66F—HOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F11/00—Lifting devices specially adapted for particular uses not otherwise provided for
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B66—HOISTING; LIFTING; HAULING
    • B66F—HOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F13/00—Common constructional features or accessories
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B66—HOISTING; LIFTING; HAULING
    • B66F—HOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F17/00—Safety devices, e.g. for limiting or indicating lifting force

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及造楼机技术领域,尤其涉及一种用于造楼机平台的升降机构。一种用于造楼机平台的升降机构,升降机构包括多节竖向可拆卸连接的标准节组成的钢筋桁架以及套接于标准节上且能够沿钢筋桁架纵向升降的升降装置,升降装置包括位于上部的支撑单元和位于下部的升降单元,支撑单元与造楼机立柱可拆卸连接。升降机构安装在钢筋桁架的最上端、次上端或第三上端的标准节上,并可沿钢筋桁架延伸方向升降,这不仅实现造楼机平台的逐级爬升,也能进行逐级下降。通过控制多个升降机构的同步运动,可以精确控制造楼机平台的升降速度和位置,实现平台的平稳升降,显著提高了施工效率,增强了应对突发事件的能力,保障了施工人员的安全。

The present invention relates to the technical field of building construction machines, and in particular to a lifting mechanism for a building construction machine platform. A lifting mechanism for a building construction machine platform, the lifting mechanism includes a steel truss composed of multiple vertically detachably connected standard sections and a lifting device that is sleeved on the standard sections and can be lifted and lowered along the longitudinal direction of the steel truss, the lifting device includes a support unit located at the top and a lifting unit located at the bottom, and the support unit is detachably connected to the building machine column. The lifting mechanism is installed on the standard section at the top, the second top or the third top of the steel truss, and can be lifted and lowered along the extension direction of the steel truss, which not only realizes the step-by-step climbing of the building construction machine platform, but also can be lowered and lowered step by step. By controlling the synchronous movement of multiple lifting mechanisms, the lifting speed and position of the building construction machine platform can be accurately controlled, and the platform can be lifted and lowered smoothly, which significantly improves the construction efficiency, enhances the ability to respond to emergencies, and ensures the safety of construction personnel.

Description

一种用于造楼机平台的升降机构A lifting mechanism for building construction machine platform

技术领域Technical Field

本发明涉及造楼机技术领域,尤其涉及一种用于造楼机平台的升降机构。The present invention relates to the technical field of building construction machines, and in particular to a lifting mechanism for a platform of a building construction machine.

背景技术Background Art

造楼机是一种专为高层及超高层建筑施工设计的现代化大型机械设备平台,集成了多种先进技术和施工工艺,旨在提高建筑施工的安全性、效率和质量。Building construction machine is a modern large-scale mechanical equipment platform designed specifically for high-rise and super-high-rise building construction. It integrates a variety of advanced technologies and construction processes to improve the safety, efficiency and quality of building construction.

造楼机立柱作为造楼机平台的基础支撑构件,承担着将整个造楼机平台及其负载(包括建筑材料、设备、工器具及作业人员等)的重量安全、稳定地传递至地面或已建成的建筑结构之上。造楼机立柱通常由高强度钢材制成,具有足够的承载能力和良好的抗弯、抗剪性能,以确保在极端工况下仍能保持结构稳定。As the basic supporting member of the building machine platform, the building machine column is responsible for safely and stably transferring the weight of the entire building machine platform and its load (including construction materials, equipment, tools and operators, etc.) to the ground or the built building structure. The building machine column is usually made of high-strength steel, with sufficient load-bearing capacity and good bending and shear resistance to ensure that the structure can remain stable under extreme working conditions.

然而,现有技术下的造楼机只能通过建筑物上的外挂支点支撑,外挂支点常常因选材不当、加工精度不足或长期高负荷运行导致局部应力集中、磨损严重,从而引发支点强度不足的问题。一旦支点发生失效,极可能导致造楼机整体稳定性受损,甚至诱发严重的安全事故。However, the existing building construction machine can only be supported by external fulcrums on the building. The external fulcrums often cause local stress concentration and severe wear due to improper material selection, insufficient processing precision or long-term high-load operation, which leads to insufficient fulcrum strength. Once the fulcrum fails, it is very likely to cause the overall stability of the building construction machine to be damaged, and even induce serious safety accidents.

同时,现有技术下的造楼机只能通过液压油缸以往上顶升方式安装,仅能实现逐级爬升而无法进行逐级下降。当完成某一层的施工任务后,现有的造楼机往往缺乏有效的降层机制,只能通过把液压油缸拆卸并换向安装才能完成下降,费时费力同时安全性无法保证。At the same time, the existing building construction machine can only be installed by lifting up with a hydraulic cylinder, and can only climb up step by step but cannot descend step by step. After completing the construction task of a certain floor, the existing building construction machine often lacks an effective floor lowering mechanism, and can only be lowered by disassembling the hydraulic cylinder and reversing the installation, which is time-consuming and labor-intensive, and safety cannot be guaranteed.

发明内容Summary of the invention

(一)要解决的技术问题1. Technical issues to be resolved

鉴于现有技术的上述缺点、不足,本发明提供用于造楼机平台升降机构,其解决了造楼机平台外挂支点强度不足以及仅能逐级爬升不能逐级下降的技术问题。In view of the above-mentioned shortcomings and deficiencies of the prior art, the present invention provides a lifting mechanism for a building construction machine platform, which solves the technical problems that the external hanging fulcrum of the building construction machine platform is insufficient in strength and can only climb up step by step but not descend step by step.

(二)技术方案(II) Technical solution

为了达到上述目的,本发明采用的主要技术方案包括:In order to achieve the above object, the main technical solutions adopted by the present invention include:

一种用于造楼机平台的升降机构,升降机构包括多节竖向可拆卸连接的标准节组成的钢筋桁架以及套接于标准节上且能够沿钢筋桁架纵向升降的升降装置。The invention discloses a lifting mechanism for a building construction machine platform, comprising a steel bar truss composed of a plurality of vertically detachably connected standard sections and a lifting device which is sleeved on the standard sections and can be lifted and lowered longitudinally along the steel bar truss.

升降装置包括彼此可在第一工作位置、第二工作位置、第三工作位置和第四工作位置之间伸缩连接的支撑单元和升降单元,支撑单元位于升降单元的上方且与造楼机立柱可拆卸连接,支撑单元和升降单元均具有与标准节上的第一限位结构、第二限位结构和第三限位结构可拆卸连接的第四限位结构;同一标准节中,第三限位结构、第二限位结构和第一限位结构高度依次降低。The lifting device includes a supporting unit and a lifting unit which can be telescopically connected to each other between a first working position, a second working position, a third working position and a fourth working position. The supporting unit is located above the lifting unit and is detachably connected to a column of the building construction machine. Both the supporting unit and the lifting unit have a fourth limiting structure which is detachably connected to a first limiting structure, a second limiting structure and a third limiting structure on a standard section. In the same standard section, the heights of the third limiting structure, the second limiting structure and the first limiting structure decrease successively.

支撑单元和升降单元位于第一工作位置时:支撑单元和升降单元的第四限位结构之间的垂直距离为相邻两个标准节中上方标准节的第一限位结构和下方标准节的第二限位结构之间垂直距离;When the support unit and the lifting unit are located at the first working position: the vertical distance between the fourth limiting structures of the support unit and the lifting unit is the vertical distance between the first limiting structure of the upper standard section and the second limiting structure of the lower standard section of two adjacent standard sections;

支撑单元和升降单元位于第二工作位置时:支撑单元和升降单元的第四限位结构之间的垂直距离为相邻两个标准节中第二限位结构之间的垂直距离。When the supporting unit and the lifting unit are located at the second working position: the vertical distance between the fourth limiting structures of the supporting unit and the lifting unit is the vertical distance between the second limiting structures in two adjacent standard sections.

支撑单元和升降单元位于第三工作位置时:支撑单元和升降单元的第四限位结构之间的垂直距离为相邻两个标准节中上方标准节的第二限位结构和下方标准节的第三限位结构之间的垂直距离。When the supporting unit and the lifting unit are located at the third working position: the vertical distance between the fourth limiting structures of the supporting unit and the lifting unit is the vertical distance between the second limiting structure of the upper standard section and the third limiting structure of the lower standard section of two adjacent standard sections.

支撑单元和升降单元位于第四工作位置时:支撑单元和升降单元的第四限位结构之间的垂直距离为三个标准节中两端的标准节上的第二限位结构之间的垂直距离。When the supporting unit and the lifting unit are located at the fourth working position: the vertical distance between the fourth limiting structures of the supporting unit and the lifting unit is the vertical distance between the second limiting structures on the standard sections at both ends of the three standard sections.

进一步的,升降装置具有与标准节安装状态:Furthermore, the lifting device has the following installation state with the standard section:

升降单元和支撑单元处于第一工作位置,升降单元的第四限位结构与钢筋桁架顶部的第二个标准节的第二限位结构连接;解除支撑单元的第四限位结构与钢筋桁架顶部的第一个标准节的第一限位结构连接;The lifting unit and the supporting unit are in the first working position, and the fourth limiting structure of the lifting unit is connected to the second limiting structure of the second standard section at the top of the steel truss; the fourth limiting structure of the supporting unit is disconnected from the first limiting structure of the first standard section at the top of the steel truss;

支撑单元相对于升降单元向上伸出至第四工作位置,将新的标准节置入支撑单元并与原第一个标准节可拆卸拼接,支撑单元的第四限位结构与新的标准节的第二限位结构连接;The support unit extends upward to the fourth working position relative to the lifting unit, a new standard section is placed into the support unit and detachably spliced with the original first standard section, and the fourth limiting structure of the support unit is connected with the second limiting structure of the new standard section;

升降单元相对于支撑单元向上伸出至第三工作位置,升降单元的第四限位结构与原来最顶端的标准节的第三限位结构对齐;The lifting unit extends upward to a third working position relative to the supporting unit, and the fourth limiting structure of the lifting unit is aligned with the third limiting structure of the original topmost standard section;

升降单元相对于支撑单元向下伸出至原来最顶端的标准节的第二限位结构连接,解除支撑单元的第四限位结构与新的标准节的第二限位结构连接;The lifting unit extends downward relative to the supporting unit to connect with the second limiting structure of the original topmost standard section, and releases the connection between the fourth limiting structure of the supporting unit and the second limiting structure of the new standard section;

支撑单元相对于升降单元向下伸出至第一工作位置,支撑单元的第四限位结构与新的标准节的第一限位结构连接。The support unit extends downward to a first working position relative to the lifting unit, and the fourth limiting structure of the support unit is connected to the first limiting structure of the new standard section.

进一步的,升降装置具有与标准节拆卸状态:Furthermore, the lifting device has a disassembled state with a standard section:

升降单元和支撑单元处于第一工作位置,升降单元的第四限位结构与钢筋桁架顶部的第二个标准节的第二限位结构连接,解除支撑单元的第四限位结构与钢筋桁架顶部的标准节的第一限位结构连接;The lifting unit and the supporting unit are in the first working position, the fourth limiting structure of the lifting unit is connected to the second limiting structure of the second standard section at the top of the steel truss, and the fourth limiting structure of the supporting unit is disconnected from the first limiting structure of the standard section at the top of the steel truss;

支撑单元相对于升降单元向上伸出至第二工作位置,支撑单元的第四限位结构与钢筋桁架顶部第一个标准节的第二限位结构连接;The support unit extends upward to a second working position relative to the lifting unit, and the fourth limiting structure of the support unit is connected to the second limiting structure of the first standard section at the top of the steel truss;

解除升降单元的第四限位结构与钢筋桁架顶部的第二个标准节的第二限位结构的连接,移动升降单元向上缩回至第三工作位置;Release the connection between the fourth limiting structure of the lifting unit and the second limiting structure of the second standard section at the top of the steel bar truss, and move the lifting unit upward and retract it to the third working position;

移动升降单元向下伸出至第四工作位置,升降单元的第四限位结构与钢筋桁架顶部的第三个标准节的第二限位结构连接,解除支撑单元的第四限位结构与钢筋桁架顶部第一个标准节的第二限位结构的连接,此时可拆走钢筋桁架顶部第一个标准节;The mobile lifting unit extends downward to the fourth working position, the fourth limiting structure of the lifting unit is connected to the second limiting structure of the third standard section at the top of the steel truss, and the connection between the fourth limiting structure of the support unit and the second limiting structure of the first standard section at the top of the steel truss is released, and the first standard section at the top of the steel truss can be removed;

支撑单元相对于升降单元向下伸出至第一工作位置,支撑单元的第四限位结构与原来第二标准节的第一限位结构连接。The support unit extends downward to a first working position relative to the lifting unit, and the fourth limiting structure of the support unit is connected to the first limiting structure of the original second standard section.

进一步的,升降单元包括底座、升降器和沿升降方向的多个导向杆;Further, the lifting unit includes a base, a lifter, and a plurality of guide rods along the lifting direction;

第四限位结构设于底座;升降器的一端安装在底座上,升降器的另一端能够与支撑单元可拆卸连接或固定连接;The fourth limiting structure is arranged on the base; one end of the lifter is mounted on the base, and the other end of the lifter can be detachably connected or fixedly connected to the support unit;

多个导向杆安装在底座的上端,且位于升降器前后两侧,导向杆贯穿支撑单元边侧,能够引导支撑单元和升降单元彼此沿上下方向伸缩且导向杆与升降器之间有间隙。A plurality of guide rods are installed at the upper end of the base and are located at the front and rear sides of the lifter. The guide rods penetrate the sides of the support unit and can guide the support unit and the lifter to extend and retract in the up and down directions with a gap between the guide rods and the lifter.

底座上设有横向设置的两个第四限位结构;Two fourth limiting structures are arranged horizontally on the base;

升降器位于两个第四限位结构之间,且与两个第四限位结构有间隙;The lifter is located between the two fourth limiting structures and has a gap between the two fourth limiting structures;

进一步的,支撑单元呈倒U形并套在钢筋桁架的顶部外;支撑单元中顶板中部设有挖孔,挖孔位置与造楼机立柱的中心孔相对应;Furthermore, the support unit is in an inverted U shape and is sleeved outside the top of the steel truss; a hole is provided in the middle of the top plate of the support unit, and the position of the hole corresponds to the central hole of the building machine column;

支撑单元中左右两侧的支撑板的外表面上分别设有横向设置贯穿支撑板的两个第四限位结构,第四限位结构能够与标准节限位连接;Two fourth limiting structures are respectively arranged on the outer surfaces of the supporting plates on the left and right sides of the supporting unit and are arranged transversely to penetrate the supporting plates, and the fourth limiting structures can be connected to the standard section limiting structure;

进一步的,底座包括相对设置的两个C型板,C型板的槽口背离标准节方向;C型板的上板前后两侧安装两个垂直于C型板的上板的导向杆,两个导向杆可贯穿支撑单元边侧以实现支撑单元和升降单元纵向导向;Further, the base includes two C-shaped plates arranged opposite to each other, and the notches of the C-shaped plates are away from the standard section direction; two guide rods perpendicular to the upper plate of the C-shaped plate are installed on the front and rear sides of the upper plate of the C-shaped plate, and the two guide rods can pass through the side of the support unit to realize the longitudinal guidance of the support unit and the lifting unit;

C型板固定连接有依次穿透C型板的下板和C型板的上板的升降器,升降器伸缩端的端部与支撑单元固定连接或可拆卸连接;The C-shaped plate is fixedly connected with a lifter which sequentially penetrates the lower plate and the upper plate of the C-shaped plate, and the end of the telescopic end of the lifter is fixedly connected or detachably connected to the support unit;

C型板内设有贯穿C型板的竖直板的两个第四限位结构,第四限位结构能够与标准节限位连接。Two fourth limiting structures are arranged in the C-shaped plate and are vertical plates that penetrate the C-shaped plate. The fourth limiting structures can be connected with the standard section limit.

进一步的,支撑单元中左右两侧的支撑板的底部向外弯折形成凸边,沿着凸边长度方向间隔分布三个竖向的槽孔,边缘的两个槽孔贯穿凸边,中间的槽孔从下表面进入,向上延伸至凸边的内部;Furthermore, the bottoms of the support plates on the left and right sides of the support unit are bent outward to form a convex edge, and three vertical slots are distributed at intervals along the length direction of the convex edge. The two slots on the edge penetrate the convex edge, and the middle slot enters from the lower surface and extends upward to the inside of the convex edge.

边缘的两个槽孔可由两个导向杆贯穿以实现支撑单元与升降单元纵向导向;The two slots on the edge can be penetrated by two guide rods to achieve longitudinal guidance of the support unit and the lifting unit;

中间的槽孔内部与升降器固定连接或可拆卸连接。The interior of the middle slot is fixedly connected or detachably connected to the lifter.

进一步的,支撑单元的内表面和C型板的竖直板靠近钢筋桁架侧表面均安装有多个角钢导向轮组,角钢导向轮组与标准节抵接且可引导支撑单元或C型板沿着标准节延伸方向移动;Furthermore, a plurality of angle steel guide wheel groups are installed on the inner surface of the support unit and the vertical plate of the C-shaped plate near the side surface of the steel truss, and the angle steel guide wheel groups abut against the standard section and can guide the support unit or the C-shaped plate to move along the extension direction of the standard section;

角钢导向轮组包括第一导向轮部件以及与第一导向轮部件铰接的第二导向轮部件,第一导向轮部件安装在支撑板内表面以及C型板的竖板靠近钢筋桁架侧表面,第二导向轮部件可绕与第一导向轮部件铰接的铰接轴顺或逆时针转动90度。The angle steel guide wheel group includes a first guide wheel component and a second guide wheel component hinged to the first guide wheel component. The first guide wheel component is installed on the inner surface of the support plate and the vertical plate of the C-shaped plate close to the side surface of the steel truss. The second guide wheel component can rotate 90 degrees clockwise or counterclockwise around the hinge axis hinged to the first guide wheel component.

进一步的,标准节左右两侧的侧壁上对侧设置两个连接板,每个连接板上开设竖向分布的两列限位结构,限位结构横向设置至少三排;限位结构包括第一限位结构、第二限位结构和第三限位结构;第一限位结构、第二限位结构和第三限位结构与第四限位结构相对应;Furthermore, two connecting plates are arranged on the opposite sides of the side walls on the left and right sides of the standard section, and two rows of limiting structures are arranged vertically on each connecting plate, and at least three rows of limiting structures are arranged horizontally; the limiting structures include a first limiting structure, a second limiting structure and a third limiting structure; the first limiting structure, the second limiting structure and the third limiting structure correspond to the fourth limiting structure;

第一限位结构、第二限位结构和第三限位结构为设置在标准节上的连接孔;The first limiting structure, the second limiting structure and the third limiting structure are connection holes arranged on the standard section;

第四限位结构为螺栓或液压油缸。The fourth limiting structure is a bolt or a hydraulic cylinder.

进一步的,升降机构还包括水泥基筑,水泥基筑固定在基面上,最下端的标准节与水泥基筑固定连接;Furthermore, the lifting mechanism also includes a cement foundation, the cement foundation is fixed on the base surface, and the lowermost standard section is fixedly connected to the cement foundation;

多个水泥基筑在高层建筑的左右两侧均匀分布;Multiple cement foundations are evenly distributed on the left and right sides of the high-rise building;

每一个水泥基筑与每一个带有升降装置的钢筋桁架固定连接。Each cement foundation is fixedly connected to each steel truss with a lifting device.

(三)有益效果(III) Beneficial effects

本发明的有益效果是:本发明的一种用于造楼机平台的升降机构,使用多节竖向可拆卸连接的标准节组成钢筋桁架作为支撑结构替代了传统的外挂支点,标准节之间可拆卸连接,使得支撑结构可以根据施工需要灵活调整高度,避免了外挂支点因选材不当、加工精度不足或长期高负荷运行导致的强度不足问题,增强了整体结构的稳定性和安全性。钢筋桁架结构具有良好的刚度和强度,能够更好地抵抗风荷载、地震荷载等外部作用力,保证了造楼机平台在升降过程中的稳定性。The beneficial effects of the present invention are as follows: the lifting mechanism for the building construction machine platform of the present invention uses a steel truss composed of multiple vertically detachably connected standard sections as a support structure to replace the traditional external support points. The standard sections are detachably connected, so that the support structure can flexibly adjust the height according to construction needs, avoiding the problem of insufficient strength of the external support points due to improper material selection, insufficient processing accuracy or long-term high-load operation, and enhancing the stability and safety of the overall structure. The steel truss structure has good rigidity and strength, can better resist external forces such as wind loads and earthquake loads, and ensures the stability of the building construction machine platform during the lifting process.

升降机构安装在钢筋桁架的最上端、次上端和第三高的标准节上,并可沿钢筋桁架延伸方向升降,这不仅实现造楼机平台的逐级爬升,也能进行逐级下降。通过控制多个升降机构的同步运动,可以精确控制造楼机平台的升降速度和位置,实现平台的平稳升降,显著提高了施工效率,增强了应对突发事件的能力,保障了施工人员的安全。The lifting mechanism is installed on the top, second top and third highest standard section of the steel truss, and can be lifted and lowered along the extension direction of the steel truss, which not only enables the step-by-step climbing of the building machine platform, but also enables the step-by-step descent. By controlling the synchronous movement of multiple lifting mechanisms, the lifting speed and position of the building machine platform can be accurately controlled, achieving smooth lifting and lowering of the platform, significantly improving construction efficiency, enhancing the ability to respond to emergencies, and ensuring the safety of construction workers.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1为本发明的升降机构结构示意图;FIG1 is a schematic diagram of the lifting mechanism structure of the present invention;

图2为升降状态过程中结构示意图;FIG2 is a schematic diagram of the structure during the lifting state;

图3为完成升降状态下结构示意图;FIG3 is a schematic diagram of the structure in the lifting state;

图4为标准节与升降机构和造楼机平台结构布置图;Figure 4 is a diagram showing the layout of the standard section, the lifting mechanism and the platform structure of the building construction machine;

图5为升降机构与造楼机立柱连接处放大图;FIG5 is an enlarged view of the connection between the lifting mechanism and the building construction machine column;

图6为角钢导向轮组结构示意图。Figure 6 is a schematic diagram of the angle steel guide wheel group structure.

【附图标记说明】[Description of Reference Numerals]

1:标准节;2:升降机构;3:造楼机立柱;1: Standard section; 2: Lifting mechanism; 3: Building machine column;

21:支撑单元;22:升降单元;21: support unit; 22: lifting unit;

211:支撑板;212:第四限位结构;213:挖孔;214:凸边;211: support plate; 212: fourth limiting structure; 213: digging hole; 214: convex edge;

221:底座;222:顶升器;223:导向杆;224:角钢导向轮组;221: base; 222: jacking device; 223: guide rod; 224: angle steel guide wheel assembly;

2211:C型板;2211: C-type plate;

2241:第一导向轮部件;2242:第二导向轮部件;2241: first guide wheel component; 2242: second guide wheel component;

具体实施方式DETAILED DESCRIPTION

为了更好的解释本发明,以便于理解,下面结合附图,通过具体实施方式,对本发明作详细描述。其中,本文所提及的“上”、“下”......等方位名词以图2的定向为参照。In order to better explain the present invention and facilitate understanding, the present invention is described in detail below in conjunction with the accompanying drawings through specific embodiments. Wherein, the directional terms such as "upper", "lower", etc. mentioned herein are based on the orientation of Figure 2.

为了更好的理解上述技术方案,下面将参照附图更详细地描述本发明的示例性实施例。虽然附图中显示了本发明的示例性实施例,然而应当理解,可以以各种形式实现本发明而不应被这里阐述的实施例所限制。相反,提供这些实施例是为了能够更清楚、透彻地理解本发明,并且能够将本发明的范围完整的传达给本领域的技术人员。In order to better understand the above technical solution, exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided to enable a clearer and more thorough understanding of the present invention and to fully convey the scope of the present invention to those skilled in the art.

实施例1:Embodiment 1:

参照图2、图3和图4,一种用于造楼机平台的升降机构,升降机构包括多节竖向可拆卸连接的标准节1组成的钢筋桁架以及套接于标准节1上且能够沿钢筋桁架纵向升降的升降装置2。2, 3 and 4, a lifting mechanism for a building construction machine platform is shown, the lifting mechanism comprising a steel truss composed of multiple vertically detachably connected standard sections 1 and a lifting device 2 sleeved on the standard sections 1 and capable of being lifted and lowered longitudinally along the steel truss.

升降装置2包括彼此可在第一工作位置、第二工作位置、第三工作位置和第四工作位置之间伸缩连接的支撑单元21和升降单元22,支撑单元21位于升降单元22的上方且与造楼机立柱3可拆卸连接,支撑单元21和升降单元22均具有与标准节1上的第一限位结构、第二限位结构和第三限位结构可拆卸连接的第四限位结构;同一标准节中,第三限位结构、第二限位结构和第一限位结构高度依次降低。The lifting device 2 includes a support unit 21 and a lifting unit 22 which can be telescopically connected to each other between a first working position, a second working position, a third working position and a fourth working position. The support unit 21 is located above the lifting unit 22 and is detachably connected to the building machine column 3. The support unit 21 and the lifting unit 22 both have a fourth limiting structure which is detachably connected to the first limiting structure, the second limiting structure and the third limiting structure on the standard section 1; in the same standard section, the heights of the third limiting structure, the second limiting structure and the first limiting structure decrease successively.

支撑单元和升降单元位于第一工作位置时:支撑单元21和升降单元22的第四限位结构之间的垂直距离为相邻两个标准节1中上方标准节1的第一限位结构和下方标准节1的第二限位结构之间垂直距离。When the supporting unit and the lifting unit are located at the first working position: the vertical distance between the fourth limiting structures of the supporting unit 21 and the lifting unit 22 is the vertical distance between the first limiting structure of the upper standard section 1 and the second limiting structure of the lower standard section 1 of two adjacent standard sections 1.

支撑单元和升降单元位于第二工作位置时:支撑单元21和升降单元22的第四限位结构之间的垂直距离为相邻两个标准节1中第二限位结构之间的垂直距离。When the supporting unit and the lifting unit are located at the second working position: the vertical distance between the fourth limiting structures of the supporting unit 21 and the lifting unit 22 is the vertical distance between the second limiting structures in two adjacent standard sections 1.

支撑单元和升降单元位于第三工作位置时:支撑单元21和升降单元22的第四限位结构之间的垂直距离为相邻两个标准节1中上方标准节1的第二限位结构和下方标准节1的第三限位结构之间的垂直距离。When the supporting unit and the lifting unit are located at the third working position: the vertical distance between the fourth limiting structures of the supporting unit 21 and the lifting unit 22 is the vertical distance between the second limiting structure of the upper standard section 1 and the third limiting structure of the lower standard section 1 of the two adjacent standard sections 1.

支撑单元和升降单元位于第四工作位置时:支撑单元21和升降单元22的第四限位结构之间的垂直距离为三个标准节1中两端的标准节上的第二限位结构之间的垂直距离。When the supporting unit and the lifting unit are located at the fourth working position: the vertical distance between the fourth limiting structures of the supporting unit 21 and the lifting unit 22 is the vertical distance between the second limiting structures on the standard sections at both ends of the three standard sections 1.

通过将升降装置细分为支撑单元和升降单元,并使它们能够在多个预设的工作位置之间精确伸缩连接,实现了对升降高度的精细化控制。这种设计允许在施工过程中对造楼机平台的位置进行微调,确保了平台在不同高度作业时的精确定位,提高了施工的准确性和安全性。By subdividing the lifting device into a support unit and a lifting unit, and enabling them to be precisely telescopically connected between multiple preset working positions, refined control of the lifting height is achieved. This design allows the position of the building construction machine platform to be fine-tuned during the construction process, ensuring the precise positioning of the platform when operating at different heights, and improving the accuracy and safety of construction.

由于支撑单元和升降单元能够与标准节上的不同限位结构相连接,且这些限位结构在标准节上有规律地分布,使得升降机构能够适应不同高度的调节需求。这种灵活性不仅提升了设备在各种施工条件下的适用性,也简化了维护和调整过程。Since the support unit and lifting unit can be connected to different limit structures on the standard section, and these limit structures are regularly distributed on the standard section, the lifting mechanism can adapt to the adjustment requirements of different heights. This flexibility not only improves the applicability of the equipment under various construction conditions, but also simplifies the maintenance and adjustment process.

通过精心设计的限位结构布局和垂直距离的精确设定,确保了升降过程中结构的稳定对接,减少了不必要的晃动或偏移,提高了整体结构的稳定性。此外,这种设计还有助于分散荷载,减轻对单一连接点的压力,进一步提升了施工安全性。The carefully designed limit structure layout and precise setting of vertical distance ensure the stable docking of the structure during the lifting process, reduce unnecessary shaking or deviation, and improve the stability of the overall structure. In addition, this design also helps to disperse the load, reduce the pressure on a single connection point, and further improve construction safety.

升降装置能够在第一至第四工作位置之间快速切换,意味着造楼机能够更加高效地完成楼层间的爬升与下降动作,无需频繁拆卸和重新组装关键部件,大大缩短了施工周期,提高了工作效率。The lifting device can quickly switch between the first to fourth working positions, which means that the building construction machine can complete the climbing and descending actions between floors more efficiently without the need for frequent disassembly and reassembly of key components, greatly shortening the construction period and improving work efficiency.

参照图2、图3和图4,升降装置2具有与标准节1安装状态:2, 3 and 4, the lifting device 2 has an installation state with the standard section 1:

升降单元22和支撑单元21处于第一工作位置,升降单元22的第四限位结构与钢筋桁架顶部的第二个标准节的第二限位结构连接;解除支撑单元21的第四限位结构与钢筋桁架顶部的第一个标准节1的第一限位结构连接;The lifting unit 22 and the supporting unit 21 are in the first working position, and the fourth limiting structure of the lifting unit 22 is connected to the second limiting structure of the second standard section at the top of the steel truss; the fourth limiting structure of the supporting unit 21 is disconnected from the first limiting structure of the first standard section 1 at the top of the steel truss;

支撑单元21相对于升降单元22向上伸出至第四工作位置,将新的标准节1置入支撑单元21并与原第一个标准节1可拆卸拼接,支撑单元21的第四限位结构与新的标准节1的第二限位结构连接;The support unit 21 extends upward to the fourth working position relative to the lifting unit 22, the new standard section 1 is placed into the support unit 21 and detachably spliced with the original first standard section 1, and the fourth limiting structure of the support unit 21 is connected with the second limiting structure of the new standard section 1;

升降单元22相对于支撑单元21向上伸出至第三工作位置,升降单元22的第四限位结构与原来最顶端的标准节1的第三限位结构对齐;The lifting unit 22 extends upward to a third working position relative to the supporting unit 21, and the fourth limiting structure of the lifting unit 22 is aligned with the third limiting structure of the original topmost standard section 1;

升降单元22相对于支撑单元21向下伸出至原来最顶端的标准节1的第二限位结构连接,解除支撑单元21的第四限位结构与新的标准节1的第二限位结构连接;The lifting unit 22 extends downward relative to the supporting unit 21 to connect with the second limiting structure of the original topmost standard section 1, and releases the connection between the fourth limiting structure of the supporting unit 21 and the second limiting structure of the new standard section 1;

支撑单元21相对于升降单元22向下伸出至第一工作位置,支撑单元21的第四限位结构与新的标准节1的第一限位结构连接。The support unit 21 extends downward to the first working position relative to the lifting unit 22 , and the fourth limiting structure of the support unit 21 is connected to the first limiting structure of the new standard section 1 .

参照图2、图3和图4,升降装置2具有与标准节1拆卸状态。升降单元22和支撑单元21处于第一工作位置,升降单元22的第四限位结构与钢筋桁架顶部的第二个标准节1的第二限位结构连接,解除支撑单元21的第四限位结构与钢筋桁架顶部的标准节1的第一限位结构连接。2, 3 and 4, the lifting device 2 is in a disassembled state from the standard section 1. The lifting unit 22 and the support unit 21 are in the first working position, the fourth limiting structure of the lifting unit 22 is connected to the second limiting structure of the second standard section 1 at the top of the steel truss, and the fourth limiting structure of the support unit 21 is disconnected from the first limiting structure of the standard section 1 at the top of the steel truss.

支撑单元21相对于升降单元22向上伸出至第二工作位置,支撑单元21的第四限位结构与钢筋桁架顶部第一个标准节的第二限位结构连接。The support unit 21 extends upward to the second working position relative to the lifting unit 22, and the fourth limiting structure of the support unit 21 is connected to the second limiting structure of the first standard section at the top of the steel truss.

解除升降单元22的第四限位结构与钢筋桁架顶部的第二个标准节1的第二限位结构的连接,移动升降单元22向上缩回至第三工作位置。The connection between the fourth limiting structure of the lifting unit 22 and the second limiting structure of the second standard section 1 at the top of the steel bar truss is released, and the lifting unit 22 is moved upward and retracted to the third working position.

移动升降单元22向下伸出至第四工作位置,升降单元22的第四限位结构与钢筋桁架顶部的第三个标准节1的第二限位结构连接,解除支撑单元21的第四限位结构与钢筋桁架顶部第一个标准节的第二限位结构的连接,此时可拆走钢筋桁架顶部第一个标准节。The mobile lifting unit 22 extends downward to the fourth working position, and the fourth limiting structure of the lifting unit 22 is connected to the second limiting structure of the third standard section 1 at the top of the steel truss, and the connection between the fourth limiting structure of the support unit 21 and the second limiting structure of the first standard section at the top of the steel truss is released. At this time, the first standard section at the top of the steel truss can be removed.

支撑单元21相对于升降单元22向下伸出至第一工作位置,支撑单元21的第四限位结构与原来第二标准节1的第一限位结构连接。The support unit 21 extends downward to the first working position relative to the lifting unit 22 , and the fourth limiting structure of the support unit 21 is connected to the first limiting structure of the original second standard section 1 .

升降单元22与钢筋桁架限位连接,且支撑支撑单元21向上移动,直至超出钢筋桁架的顶部至少一个标准节1的高度,将新的标准节1置入支撑单元21内部并与现有钢筋桁架可拆卸拼接。升降装置2执行下降操作,升降单元22与第二高标准节1限位连接,且支撑支撑单元21向上运动至与钢筋桁架最上端的标准节有间隙(有间隙方便标准节插入和移出)且与此标准节1限位连接,解除升降单元22与钢筋桁架的限位连接并移动升降单元22至支撑单元21下端;升降单元22下降至第三高标准节1处并与其限位连接,解除支撑单元21的限位连接,移除支撑单元21中标准节1,下降支撑单元21至升降单元22上部。The lifting unit 22 is limitedly connected with the steel truss, and the supporting unit 21 moves upward until it exceeds the height of at least one standard section 1 at the top of the steel truss, and the new standard section 1 is placed inside the supporting unit 21 and detachably spliced with the existing steel truss. The lifting device 2 performs a descending operation, the lifting unit 22 is limitedly connected with the second highest standard section 1, and the supporting unit 21 moves upward until there is a gap with the uppermost standard section of the steel truss (the gap is convenient for inserting and removing the standard section) and is limitedly connected with this standard section 1, the lifting unit 22 is released from the limited connection with the steel truss and the lifting unit 22 is moved to the lower end of the supporting unit 21; the lifting unit 22 descends to the third highest standard section 1 and is limitedly connected with it, the limited connection of the supporting unit 21 is released, the standard section 1 in the supporting unit 21 is removed, and the supporting unit 21 is lowered to the upper part of the lifting unit 22.

通过支撑单元21与升降单元22的协同工作,实现了造楼机平台的自动升降功能,不仅能够逐级爬升,还能逐级下降,极大地提高了施工的灵活性和效率。相较于传统仅能逐级爬升的设备,这种升降机制简化了楼层间转换的复杂度,减少了转换所需的时间和人力成本。Through the coordinated work of the support unit 21 and the lifting unit 22, the automatic lifting function of the building machine platform is realized, which can not only climb up step by step, but also descend step by step, greatly improving the flexibility and efficiency of construction. Compared with traditional equipment that can only climb up step by step, this lifting mechanism simplifies the complexity of switching between floors and reduces the time and labor cost required for switching.

升降装置2通过与钢筋桁架的限位连接,确保了在升降过程中结构的稳定性。特别是在上升和下降操作时,通过精准的定位和限位连接,避免了升降过程中的晃动和偏移,提升了作业安全性。支撑单元与升降单元的相互作用机制,确保了在整个操作过程中的平稳过渡,减少了因设备操作引起的潜在风险。The lifting device 2 ensures the stability of the structure during the lifting process through the limit connection with the steel truss. Especially during the rising and falling operations, the precise positioning and limit connection avoids shaking and deviation during the lifting process, improving the safety of the operation. The interaction mechanism between the support unit and the lifting unit ensures a smooth transition during the entire operation process and reduces the potential risks caused by equipment operation.

升降机构设计中采用的多节竖向可拆卸连接的标准节1组成的钢筋桁架,以及升降装置2的可拆卸连接特性,有利于实现模块化建设。这意味着可以根据不同建筑高度和施工需求,灵活增减标准节数量,既便于运输和安装,也利于现场的快速组装和拆卸,增强了施工的标准化程度,有利于重复利用和降低综合成本。The steel truss composed of multiple vertically detachably connected standard sections 1 and the detachable connection characteristics of the lifting device 2 used in the lifting mechanism design are conducive to modular construction. This means that the number of standard sections can be flexibly increased or decreased according to different building heights and construction requirements, which is convenient for transportation and installation, and also conducive to rapid assembly and disassembly on site, enhancing the standardization of construction, facilitating reuse and reducing overall costs.

钢筋桁架作为一种高度稳定的结构体系,为整个升降机构提供了坚固的支撑框架,能够有效地承受并传递由造楼机平台及其负载产生的巨大重量和施工过程中产生的各种荷载至下部结构,确保了施工安全和结构稳定性。As a highly stable structural system, the steel truss provides a solid support frame for the entire lifting mechanism. It can effectively bear and transfer the huge weight generated by the building machine platform and its load and various loads generated during the construction process to the lower structure, ensuring construction safety and structural stability.

通过钢筋桁架与升降装置的配合,实现了升降机构的平稳上升和下降,避免了传统方法中可能存在的安全隐患,如液压油缸频繁拆装带来的风险,提高了施工过程的整体安全性。钢筋桁架与升降机构的集成设计,尤其是其可拆卸连接和限位连接机制,能够在不依赖外部建筑结构的情况下自成体系,有效替代了传统外挂支点,解决了外挂支点因材料或加工问题导致的局部应力集中和磨损问题,增强了整体结构的可靠性和耐久性。Through the coordination of the steel truss and the lifting device, the lifting mechanism can be smoothly raised and lowered, avoiding the potential safety hazards in traditional methods, such as the risks caused by frequent disassembly and assembly of hydraulic cylinders, and improving the overall safety of the construction process. The integrated design of the steel truss and the lifting mechanism, especially its detachable connection and limit connection mechanism, can form a self-contained system without relying on external building structures, effectively replacing traditional external fulcrums, solving the local stress concentration and wear problems caused by material or processing problems of external fulcrums, and enhancing the reliability and durability of the overall structure.

参照图1和图2,支撑单元21与升降单元22可拆卸连接并可相对运动;升降单元22中的升降器222与支撑单元21可以固定连接。1 and 2 , the support unit 21 and the lifting unit 22 are detachably connected and can move relative to each other; the lifter 222 in the lifting unit 22 can be fixedly connected to the support unit 21 .

支撑单元21一般套接在钢筋桁架最上端的标准节上,升降单元22位于钢筋桁架第二高或第三高的标准节1上。The support unit 21 is generally sleeved on the uppermost standard section of the steel truss, and the lifting unit 22 is located on the second highest or third highest standard section 1 of the steel truss.

支撑单元21与升降单元22均能够与钢筋桁架限位连接,升降单元22为支撑单元21和升降单元22提供升降力,以实现支撑单元21携带造楼机升降。Both the support unit 21 and the lifting unit 22 can be connected to the steel truss in a limiting manner, and the lifting unit 22 provides lifting force for the support unit 21 and the lifting unit 22, so as to realize the lifting of the building construction machine carried by the support unit 21.

通过支撑单元21与钢筋桁架最上端标准节的套接并限位连接,以及升降单元22与钢筋桁架其他标准节的限位连接,确保了整个升降过程中的稳定性和安全性。这种直接与钢筋桁架结构相连的方式,比依赖外挂支点更能均匀分散荷载,减少局部应力集中,降低了施工中结构失稳的风险。The support unit 21 is connected to the uppermost standard section of the steel truss and the lifting unit 22 is connected to the other standard sections of the steel truss to ensure stability and safety during the entire lifting process. This method of directly connecting to the steel truss structure can more evenly distribute the load, reduce local stress concentration, and reduce the risk of structural instability during construction than relying on external support points.

升降单元22不仅为自身提供升降动力,同时也带动支撑单元21升降,这意味着整个造楼机平台的升降操作变得更加统一和高效。这种设计避免了传统方法中升降和支撑结构分离所带来的操作复杂性和时间消耗,提高了施工效率。The lifting unit 22 not only provides lifting power for itself, but also drives the support unit 21 to lift, which means that the lifting operation of the entire building construction machine platform becomes more unified and efficient. This design avoids the operational complexity and time consumption caused by the separation of lifting and supporting structures in traditional methods, and improves construction efficiency.

支撑单元和升降单元都能与钢筋桁架进行限位连接,这一特点确保了在升降过程中设备的精确定位,对于高层建筑施工中对准楼层高度、确保施工完成。此外,这种设计能够适应不同高度和结构变化,提高了设备在多样化的建筑项目中的适应能力。Both the support unit and the lifting unit can be connected to the steel truss in a limited position. This feature ensures the precise positioning of the equipment during the lifting process, which is very useful for aligning the floor height and ensuring the completion of the construction in high-rise building construction. In addition, this design can adapt to different heights and structural changes, improving the adaptability of the equipment in a variety of construction projects.

另外,多个支撑单元21自身是可以支撑造楼机的,但是为了减少支撑单元21的疲劳度,尽量减少支撑单元21自身对造楼机的支撑,改成钢筋桁架来支撑。In addition, the plurality of support units 21 themselves can support the building construction machine, but in order to reduce fatigue of the support units 21, the support of the building construction machine by the support units 21 themselves is reduced as much as possible and replaced with a steel truss for support.

参照图1和图2,升降单元22包括底座221、升降器222和与升降器222平行的两个导向杆223。1 and 2 , the lifting unit 22 includes a base 221 , a lifter 222 , and two guide rods 223 parallel to the lifter 222 .

底座221能够与标准节1限位连接;升降器222的一端安装在底座221上,升降器222的另一端能够与支撑单元21可拆卸连接中间槽孔内设置法兰或者吊环可拆卸连接或固定连接伸缩端直接与中间槽孔焊接,或者取消中间槽孔,升降器222直接与凸边214底部连接,或者升降器222直接直接与凸边214顶部焊接,目的是保证凸边214与C型板可贴靠。The base 221 can be limitedly connected to the standard section 1; one end of the lifter 222 is installed on the base 221, and the other end of the lifter 222 can be detachably connected to the support unit 21. A flange or a lifting ring is set in the middle slot hole for detachable connection or fixed connection. The telescopic end is directly welded to the middle slot hole, or the middle slot hole is cancelled, and the lifter 222 is directly connected to the bottom of the flange 214, or the lifter 222 is directly welded to the top of the flange 214, so as to ensure that the flange 214 can be close to the C-shaped plate.

两个导向杆223安装在底座221的上端,且位于升降器222前后两侧,导向杆223贯穿支撑单元21边侧,能够引导支撑单元21和升降单元22上下升降且导向杆223与升降器222之间有间隙。Two guide rods 223 are installed at the upper end of the base 221 and are located at the front and rear sides of the lifter 222. The guide rods 223 pass through the side of the support unit 21, and can guide the support unit 21 and the lifting unit 22 to move up and down, and there is a gap between the guide rods 223 and the lifter 222.

导向杆223与升降器222的配合使用,通过贯穿支撑单元21边侧槽孔并在升降过程中提供导向,有效增加了升降作业的稳定性和准确性,减少了升降过程中的偏斜风险,提升了整个造楼机平台的作业安全性。通过导向杆的设置,使得升降单元在上下移动时能够自动对准和保持正确的位置,简化了升降操作流程,减少了人工调整的需要,从而提高了施工效率。The guide rod 223 and the lifter 222 are used in conjunction with each other, and by penetrating the slots on the side of the support unit 21 and providing guidance during the lifting process, the stability and accuracy of the lifting operation are effectively increased, the risk of deflection during the lifting process is reduced, and the operating safety of the entire building construction machine platform is improved. By setting the guide rod, the lifting unit can automatically align and maintain the correct position when moving up and down, simplifying the lifting operation process, reducing the need for manual adjustment, and thus improving construction efficiency.

升降器与导向杆之间预留的间隙设计,有助于减少部件间的直接接触与摩擦,降低了长期使用下的磨损程度,相互之间不发生干涉。延长了升降装置的使用寿命,同时也减少了维护成本。The reserved gap design between the lifter and the guide rod helps to reduce direct contact and friction between components, reduce the degree of wear under long-term use, and prevent interference between them. It extends the service life of the lifter and reduces maintenance costs.

升降器222优选为常见的液压油缸,单向和双向的均可,支撑单元21和升降单元22一端与钢筋桁家固定,一端与钢筋桁架分开,通过油缸驱动,实现两者的相对运动。油缸下端可位于C型板内,直接与C型板2211下端固定连接。The lifter 222 is preferably a common hydraulic cylinder, which can be unidirectional or bidirectional. One end of the support unit 21 and the lifter 22 is fixed to the steel truss, and the other end is separated from the steel truss. The relative movement of the two is achieved by the cylinder drive. The lower end of the cylinder can be located in the C-shaped plate and directly fixedly connected to the lower end of the C-shaped plate 2211.

参照图1、图2和图5,底座221上设有横向设置的两个第四限位结构212,第四限位结构212能够与标准节1可限位连接。1 , 2 and 5 , two transversely arranged fourth limiting structures 212 are provided on the base 221 , and the fourth limiting structures 212 can be limitably connected to the standard section 1 .

升降器222位于两个第四限位结构212之间,且与两个第四限位结构212有间隙。The lifter 222 is located between the two fourth limiting structures 212 , and there is a gap between the lifter 222 and the two fourth limiting structures 212 .

第四限位结构212与标准节1限位连接时,升降器222能够支撑支撑单元21向上顶升或能够带动支撑单元21向升降单元22方向靠拢;When the fourth limiting structure 212 is connected to the standard section 1 in a limiting manner, the lifter 222 can support the support unit 21 to lift upward or can drive the support unit 21 to move closer to the lifting unit 22;

第四限位结构212与标准节1解除限位连接时,底座221在升降器222作用下能够向支撑单元21方向靠拢或远离支撑单元21方向移动。When the fourth limiting structure 212 is released from the limiting connection with the standard section 1 , the base 221 can move toward the support unit 21 or away from the support unit 21 under the action of the lifter 222 .

第四限位结构为伸缩油缸,伸长状态时,伸缩端作为定位销插入标准节的定位孔中进行限位连接。The fourth limiting structure is a telescopic oil cylinder. When in the extended state, the telescopic end is inserted into the positioning hole of the standard section as a positioning pin for limiting connection.

第四限位结构212与标准节1的可限位连接设计,确保了升降单元在安装和作业过程中的精确对位与稳固连接,提高了整个升降系统的稳定性和安全性。当限位连接部件锁定时,能够为升降器222提供一个坚固的支撑基点,确保升降动作的平稳与准确,特别是在向上顶升或带动支撑单元21移动。The limitable connection design of the fourth limit structure 212 and the standard section 1 ensures the precise alignment and stable connection of the lifting unit during installation and operation, and improves the stability and safety of the entire lifting system. When the limit connection component is locked, it can provide a solid support base point for the lifter 222, ensuring the smooth and accurate lifting action, especially when lifting upward or driving the support unit 21 to move.

参照图1、图2和图3,支撑单元21呈倒U形并套在钢筋桁架的顶部外。1 , 2 and 3 , the support unit 21 is in an inverted U shape and is sleeved outside the top of the steel bar truss.

支撑单元21中顶板中部设有挖孔213,挖孔213位置与造楼机立柱3的中心孔相对应,实现快速定位。A hole 213 is provided in the middle of the top plate of the support unit 21, and the position of the hole 213 corresponds to the central hole of the building construction machine column 3, so as to realize rapid positioning.

支撑单元21中左右两侧的支撑板211的外表面上分别设有横向设置贯穿支撑板211的两个第四限位结构212,第四限位结构212能够与标准节1限位连接。Two fourth limiting structures 212 are respectively disposed on the outer surfaces of the supporting plates 211 on the left and right sides of the supporting unit 21 and are transversely arranged to penetrate the supporting plates 211 . The fourth limiting structures 212 can be connected to the standard section 1 in a limiting manner.

支撑单元21中第四限位结构212与升降单元中第四限位结构212位于同一竖直平面内。The fourth limiting structure 212 in the supporting unit 21 and the fourth limiting structure 212 in the lifting unit are located in the same vertical plane.

第四限位结构212与标准节1限位连接时,升降器222能够带动升降单元22向支撑单元21方向靠拢或能够支撑升降单元22向远离支撑单元21方向移动。When the fourth limiting structure 212 is connected to the standard section 1 in a limiting manner, the lifter 222 can drive the lifting unit 22 to move toward the supporting unit 21 or can support the lifting unit 22 to move away from the supporting unit 21 .

第四限位结构212与标准节1解除限位连接时,升降器222能够带动述支撑单元21向升降单元22方向靠拢或能够支撑述支撑单元21向远离升降单元22方向移动。When the fourth limiting structure 212 is released from the limiting connection with the standard section 1 , the lifter 222 can drive the support unit 21 to move toward the lifting unit 22 or can support the support unit 21 to move away from the lifting unit 22 .

支撑单元21的倒U形设计及其顶部的挖孔213与造楼机立柱3中心孔的对应设置,确保了支撑单元能够精确对接于立柱上,提高了整个造楼机平台的安装精度和稳定性。这种对接方式简化了安装过程,减少了对准时间,同时增强了结构的承重能力和安全性。The inverted U-shaped design of the support unit 21 and the corresponding arrangement of the hole 213 on the top and the central hole of the building construction machine column 3 ensure that the support unit can be accurately docked on the column, improving the installation accuracy and stability of the entire building construction machine platform. This docking method simplifies the installation process, reduces the alignment time, and enhances the load-bearing capacity and safety of the structure.

支撑单元21上的第四限位结构212与标准节1的可限位连接机制,为升降过程中的运动控制提供了灵活性。通过这些限位部件的锁定与解锁,能够精确控制支撑单元与升降单元22之间的相对位置变化,实现向上爬升、向下移动或水平方向的靠拢与分离,提高了作业的灵活性和效率。The limitable connection mechanism between the fourth limit structure 212 on the support unit 21 and the standard section 1 provides flexibility for motion control during the lifting process. By locking and unlocking these limit components, the relative position change between the support unit and the lifting unit 22 can be accurately controlled to achieve upward climbing, downward movement, or horizontal convergence and separation, thereby improving the flexibility and efficiency of the operation.

上方的第四限位结构212与下方的第四限位结构212位于同一竖线上,这种协同工作的方式增强了整个升降系统的稳定性。当部件处于限位状态时,能够确保支撑单元或升降单元在预定位置稳固不动,即使在承受重载或外界环境变化时也能保持结构的稳固,大大提升了施工安全性。The fourth upper limiting structure 212 and the fourth lower limiting structure 212 are located on the same vertical line, and this collaborative working method enhances the stability of the entire lifting system. When the components are in the limiting state, it can ensure that the support unit or the lifting unit is stable and immovable at the predetermined position, and the structure can be kept stable even when subjected to heavy loads or changes in the external environment, greatly improving construction safety.

参照图1和图2,底座221包括相对设置的两个C型板2211,C型板2211的槽口背离标准节1方向;C型板2211的上板前后两侧安装两个垂直于C型板2211的上板的导向杆223,两个导向杆223可贯穿支撑单元21边侧以实现支撑单元21和升降单元22纵向导向。1 and 2 , the base 221 includes two C-shaped plates 2211 arranged opposite to each other, and the grooves of the C-shaped plates 2211 are away from the direction of the standard section 1; two guide rods 223 perpendicular to the upper plate of the C-shaped plate 2211 are installed on the front and rear sides of the upper plate of the C-shaped plate 2211, and the two guide rods 223 can pass through the sides of the support unit 21 to realize the longitudinal guidance of the support unit 21 and the lifting unit 22.

C型板2211固定连接有依次穿透C型板2211的下板和C型板2211的上板的升降器222,升降器222伸缩端的端部与支撑单元21固定连接或可拆卸连接。升降器222固定端与C型板2211相对固定,因而伸缩端运动时,可带动C型板2211纵向移动。The C-shaped plate 2211 is fixedly connected with a lifter 222 which sequentially penetrates the lower plate and the upper plate of the C-shaped plate 2211, and the end of the telescopic end of the lifter 222 is fixedly connected or detachably connected to the support unit 21. The fixed end of the lifter 222 is relatively fixed to the C-shaped plate 2211, so when the telescopic end moves, the C-shaped plate 2211 can be driven to move longitudinally.

C型板2211内设有贯穿C型板2211的竖直板的两个第四限位结构212,第四限位结构212能够与标准节1限位连接。Two fourth limiting structures 212 are provided in the C-shaped plate 2211 and are vertical plates penetrating the C-shaped plate 2211 . The fourth limiting structures 212 can be connected to the standard section 1 in a limiting manner.

C型板2211的结构设计,特别是其槽口背离标准节方向,为底座提供了额外的稳定性和对标准节的贴合度,同时,垂直安装于C型板上板的导向杆223贯穿支撑单元21边侧,确保了支撑单元和升降单元在上下运动时的精确导向,减少偏摆和晃动,提升了作业的精确度和安全性。The structural design of the C-type plate 2211, especially its notch that deviates from the direction of the standard section, provides the base with additional stability and fit to the standard section. At the same time, the guide rod 223 vertically installed on the upper plate of the C-type plate passes through the side of the support unit 21, ensuring the precise guidance of the support unit and the lifting unit when they move up and down, reducing deflection and shaking, and improving the accuracy and safety of the operation.

参照图1,支撑单元21中左右两侧的支撑板211的底部向外弯折形成凸边214,沿着凸边214长度方向间隔分布三个竖向的槽孔,边缘的两个槽孔贯穿凸边214,中间的槽孔从下表面进入,向上延伸至凸边214的内部。1 , the bottoms of the support plates 211 on the left and right sides of the support unit 21 are bent outward to form a convex edge 214 , and three vertical slots are spaced apart along the length direction of the convex edge 214 . The two slots on the edge penetrate the convex edge 214 , and the middle slot enters from the lower surface and extends upward to the inside of the convex edge 214 .

边缘的两个槽孔可由两个导向杆223贯穿以实现支撑单元21与升降单元22纵向导向。The two slots at the edge can be penetrated by two guide rods 223 to achieve longitudinal guidance of the support unit 21 and the lifting unit 22 .

中间的槽孔内部与升降器222固定连接或可拆卸连接,以实现带动升降单元或支撑单元纵向移动。The interior of the middle slot is fixedly connected or detachably connected to the lifter 222 to drive the lifting unit or the supporting unit to move longitudinally.

支撑板211底部的凸边214设计,通过弯折增加了结构的刚性,尤其在承载重物时能更有效地分散压力,减少变形,从而增强整个支撑单元的稳定性和承载能力。The convex edge 214 at the bottom of the support plate 211 is designed to increase the rigidity of the structure through bending, which can more effectively disperse the pressure and reduce deformation when carrying heavy objects, thereby enhancing the stability and load-bearing capacity of the entire support unit.

边缘的两个槽孔通过导向杆223与升降单元22的导向杆相连,确保了支撑单元在上下升降过程中的精确导向,避免偏移和晃动,提高了升降作业的精度和安全性。这种设计简化了导向机制,使得操作更为顺畅和稳定。The two slots on the edge are connected to the guide rods of the lifting unit 22 through the guide rods 223, ensuring the precise guidance of the support unit during the lifting process, avoiding deviation and shaking, and improving the accuracy and safety of the lifting operation. This design simplifies the guiding mechanism and makes the operation smoother and more stable.

参照图6,支撑单元21的内表面和C型板2211的竖直板靠近钢筋桁架侧表面均安装有多个角钢导向轮组224,角钢导向轮组224与标准节1抵接且可引导支撑单元21或C型板2211沿着标准节1延伸方向移动。6 , a plurality of angle steel guide wheel groups 224 are installed on the inner surface of the support unit 21 and the vertical plate of the C-shaped plate 2211 close to the side surface of the steel truss. The angle steel guide wheel group 224 abuts against the standard section 1 and can guide the support unit 21 or the C-shaped plate 2211 to move along the extension direction of the standard section 1.

角钢导向轮组224包括第一导向轮部件2241以及与第一导向轮部件2241铰接的第二导向轮部件2242,第一导向轮部件2241安装在支撑板211内表面以及C型板2211的竖板靠近钢筋桁架侧表面,第二导向轮部件2242可绕与第一导向轮部件2241铰接的铰接轴顺或逆时针转动90度。The angle steel guide wheel group 224 includes a first guide wheel component 2241 and a second guide wheel component 2242 hinged to the first guide wheel component 2241. The first guide wheel component 2241 is installed on the inner surface of the support plate 211 and the vertical plate of the C-shaped plate 2211 close to the side surface of the steel truss. The second guide wheel component 2242 can rotate 90 degrees clockwise or counterclockwise around the hinge axis hinged to the first guide wheel component 2241.

角钢导向轮组中第一导向轮部件2241以及与第一导向轮部件2241铰接的第二导向轮部件2242可选择万向轮,只要满足在取置标准节时,不发生干涉即可。The first guide wheel component 2241 in the angle steel guide wheel assembly and the second guide wheel component 2242 hinged to the first guide wheel component 2241 can be universal wheels as long as no interference occurs when the standard section is removed and placed.

角钢导向轮组224与标准节1的紧密抵接,有效减小了移动过程中的摩擦和阻力,使得支撑单元21和C型板2211能够沿着钢筋桁架顺畅移动,提高了升降作业的平滑性和位置精度。The close contact between the angle steel guide wheel group 224 and the standard section 1 effectively reduces the friction and resistance during the movement, so that the support unit 21 and the C-shaped plate 2211 can move smoothly along the steel truss, improving the smoothness and positioning accuracy of the lifting operation.

第一导向轮部件2241和可旋转的第二导向轮部件2242相结合,形成了一个灵活的导向系统。第二导向轮部件的90度旋转能力,使得导向轮组能够根据需要调整姿态,避免和标准节发生干涉。The first guide wheel component 2241 and the rotatable second guide wheel component 2242 are combined to form a flexible guide system. The 90-degree rotation capability of the second guide wheel component enables the guide wheel group to adjust its posture as needed to avoid interference with the standard section.

导向轮组的稳定导向和减震作用,减少了在升降作业中因震动或错位引起的意外风险,进一步保障了作业人员的安全和整个施工过程的稳定进行。The stable guiding and shock-absorbing function of the guide wheel group reduces the risk of accidents caused by vibration or misalignment during lifting operations, further ensuring the safety of operators and the stability of the entire construction process.

参照图1-图5,每个连接板上开设竖向分布的两列限位结构,限位结构横向设置至少三排;限位结构包括第一限位结构、第二限位结构和第三限位结构;第一限位结构、第二限位结构和第三限位结构与第四限位结构212相对应。Referring to Figures 1-5, two columns of vertically distributed limiting structures are provided on each connecting plate, and at least three rows of limiting structures are arranged horizontally; the limiting structures include a first limiting structure, a second limiting structure and a third limiting structure; the first limiting structure, the second limiting structure and the third limiting structure correspond to the fourth limiting structure 212.

第一限位结构、第二限位结构和第三限位结构为设置在标准节上的连接孔。连接孔之间沿着纵向均匀分布,每个标准节直接的连接孔不局限于三排,可根据标准节的高度,油缸伸缩及支撑力的大小适应性调整。The first limiting structure, the second limiting structure and the third limiting structure are connection holes set on the standard section. The connection holes are evenly distributed along the longitudinal direction. The connection holes directly on each standard section are not limited to three rows, and can be adaptively adjusted according to the height of the standard section, the extension and contraction of the oil cylinder and the size of the supporting force.

第四限位结构为螺栓或液压油缸。The fourth limiting structure is a bolt or a hydraulic cylinder.

连接孔也可成为定位孔。定位孔的精确对应使得限位连接部件能够牢固地嵌入,确保了整个造楼机平台在升降过程中的结构稳定性。这种紧密连接避免了由于部件错位导致的振动或晃动,提高了作业安全性。由于定位孔是竖向分布且横向多排设置,这意味着可以根据具体的施工高度和结构需求选择不同的孔位进行连接。The connection holes can also be used as positioning holes. The precise correspondence of the positioning holes enables the limit connection components to be firmly embedded, ensuring the structural stability of the entire building construction machine platform during the lifting process. This tight connection avoids vibration or shaking caused by component misalignment and improves operational safety. Since the positioning holes are distributed vertically and arranged in multiple rows horizontally, it means that different hole positions can be selected for connection according to the specific construction height and structural requirements.

参照图4,升降机构还包括水泥基筑,水泥基筑固定在基面上,最下端的标准节1与水泥基筑固定连接。4 , the lifting mechanism further comprises a cement foundation, which is fixed on the base surface, and the lowermost standard section 1 is fixedly connected to the cement foundation.

多个水泥基筑在高层建筑的左右两侧均匀分布。Multiple cement foundations are evenly distributed on the left and right sides of the high-rise building.

每一个水泥基筑与每一个带有升降装置2的钢筋桁架固定连接。Each cement foundation is fixedly connected to each steel truss with a lifting device 2.

泥基筑直接固定在基面上,并与最下端的标准节1牢固连接,形成了一个坚实的基础支撑结构。这种设计显著增强了整个造楼机系统的稳定性,确保在进行高层建筑施工时能够安全承载巨大的垂直荷载和侧向力,如风压、施工荷载等,减少了结构变形的风险。The mud foundation is directly fixed on the base surface and firmly connected to the lowest standard section 1, forming a solid foundation support structure. This design significantly enhances the stability of the entire building machine system, ensuring that it can safely bear huge vertical loads and lateral forces such as wind pressure and construction loads during high-rise building construction, reducing the risk of structural deformation.

多个水泥基筑在高层建筑的左右两侧均匀分布,这一布局策略有助于均匀分散建筑施工过程中产生的巨大压力,避免了局部过载现象,进一步提升了整体结构的稳定性和安全性。同时,均衡的分布也有助于减少地基沉降不均的问题,保护周边建筑和基础设施免受影响。Multiple cement foundations are evenly distributed on the left and right sides of the high-rise building. This layout strategy helps to evenly disperse the huge pressure generated during the construction process, avoid local overload, and further improve the stability and safety of the overall structure. At the same time, the balanced distribution also helps to reduce the problem of uneven foundation settlement and protect surrounding buildings and infrastructure from being affected.

每个水泥基筑都与一个带有升降装置的钢筋桁架固定连接,这意味着每个独立的升降单元可以单独操作,提高了施工的灵活性和效率。在需要进行多点同时施工或者不同区域分步施工时,这种布局可以有效加快施工进度,减少等待时间。Each cement foundation is fixedly connected to a steel truss with a lifting device, which means that each independent lifting unit can be operated separately, improving the flexibility and efficiency of construction. When it is necessary to carry out construction at multiple points at the same time or to carry out construction in different areas in stages, this layout can effectively speed up the construction progress and reduce waiting time.

传统外挂支点的定位依赖于具体户型,每个项目需单独设计支点位置,这不仅耗时耗力,还难以实现规模化生产与施工。而水泥基筑的均匀分布跳过了这一繁琐过程,无需逐一考量每个支点的定位,而是基于建筑总体布局直接规划,大大加速了设计周期,减少了定制化工作量。The positioning of traditional external fulcrums depends on the specific apartment type, and the fulcrum position needs to be designed separately for each project, which is not only time-consuming and labor-intensive, but also difficult to achieve large-scale production and construction. The uniform distribution of cement foundation skips this tedious process. There is no need to consider the positioning of each fulcrum one by one, but it is directly planned based on the overall layout of the building, which greatly speeds up the design cycle and reduces the workload of customization.

造楼机平台的升降机构工作过程原理:The working principle of the lifting mechanism of the building construction machine platform:

起始阶段,造楼机的升降机构安装在由水泥基筑支撑的钢筋桁架基础上,准备进行楼层的上升或下降操作。At the initial stage, the lifting mechanism of the building construction machine is installed on a steel truss foundation supported by a cement foundation, ready to carry out the raising or lowering operation of the floor.

升降机构上升流程(标准节加入):Lifting mechanism rising process (standard section added):

步骤1:起始位置设定;水泥基筑上预先安装了标准节,构成钢筋桁架,升降机构已就位。确保升降单元22和支撑单元21处于第一工作位置。此时,升降单元22的第四限位结构与钢筋桁架顶部第二个标准节的第二限位结构紧密连接。同时,解除支撑单元21与钢筋桁架顶部第一个标准节的第一限位结构的连接,准备进行新标准节的安装。Step 1: Starting position setting; standard sections are pre-installed on the cement foundation to form a steel truss, and the lifting mechanism is in place. Ensure that the lifting unit 22 and the support unit 21 are in the first working position. At this time, the fourth limiting structure of the lifting unit 22 is tightly connected to the second limiting structure of the second standard section at the top of the steel truss. At the same time, the connection between the support unit 21 and the first limiting structure of the first standard section at the top of the steel truss is released, and the new standard section is ready to be installed.

步骤2:提升支撑单元;操作支撑单元21相对于升降单元22向上伸出,直至到达第四工作位置。在此过程中,新的标准节被置入支撑单元21内部,并与原本位于顶部的第一个标准节进行可拆卸式的拼接。接着,调整支撑单元21的第四限位结构与新标准节的第二限位结构连接,确保两者稳固对接。Step 2: Lift the support unit; operate the support unit 21 to extend upward relative to the lifting unit 22 until it reaches the fourth working position. During this process, the new standard section is placed inside the support unit 21 and detachably spliced with the first standard section originally located at the top. Next, adjust the fourth limiting structure of the support unit 21 to connect with the second limiting structure of the new standard section to ensure that the two are firmly connected.

步骤3:升降单元调整至第三工作位置;接下来,升降单元22相对于支撑单元21向上伸出,直至其第四限位结构与之前位于最顶端的标准节的第三限位结构对齐。这一操作为下一步下降做准备,确保后续步骤的平滑过渡。Step 3: The lifting unit is adjusted to the third working position; next, the lifting unit 22 extends upward relative to the support unit 21 until its fourth limit structure is aligned with the third limit structure of the standard section previously located at the top. This operation prepares for the next step of descent and ensures a smooth transition of the subsequent steps.

步骤4:随后,将升降单元22相对于支撑单元21小心地下伸,直到其第四限位结构与原最顶端标准节的第二限位结构重新连接。此时,解除支撑单元21与新标准节第二限位结构的连接,为最后的定位做准备。Step 4: Then, carefully lower the lifting unit 22 relative to the support unit 21 until its fourth limiting structure is reconnected with the second limiting structure of the original topmost standard section. At this time, the connection between the support unit 21 and the second limiting structure of the new standard section is released to prepare for the final positioning.

步骤5:最终定位并锁定;最后,支撑单元21相对于升降单元22向下伸出,回到第一工作位置。在这个位置上,支撑单元21的第四限位结构与新标准节的第一限位结构精准对接并锁定,完成了新标准节的安装。Step 5: Final positioning and locking: Finally, the support unit 21 extends downward relative to the lifting unit 22 and returns to the first working position. At this position, the fourth limiting structure of the support unit 21 is precisely docked and locked with the first limiting structure of the new standard section, completing the installation of the new standard section.

升降机构下降流程(标准节移出):Lifting mechanism lowering process (standard section removed):

步骤1:初始布置;确保升降单元22和支撑单元21处于第一工作位置,其中升降单元22的第四限位结构与钢筋桁架顶部第二个标准节的第二限位结构连接。解除支撑单元21与当前最上方标准节(即准备移除的标准节)的第一限位结构的连接,为移除操作做准备。Step 1: Initial arrangement: Ensure that the lifting unit 22 and the support unit 21 are in the first working position, wherein the fourth limiting structure of the lifting unit 22 is connected to the second limiting structure of the second standard section at the top of the steel truss. Release the connection between the support unit 21 and the first limiting structure of the current topmost standard section (i.e., the standard section to be removed) to prepare for the removal operation.

步骤2:支撑单元调整至第二工作位置;支撑单元21相对于升降单元22向上伸出至第二工作位置,使得支撑单元21的第四限位结构与即将被移除的标准节的第二限位结构相连。此步骤是为了稳定上方结构,为下方操作创造安全条件。Step 2: The support unit is adjusted to the second working position; the support unit 21 extends upward to the second working position relative to the lifting unit 22, so that the fourth limiting structure of the support unit 21 is connected to the second limiting structure of the standard section to be removed. This step is to stabilize the upper structure and create safety conditions for the lower operation.

步骤3:升降单元调整;解除升降单元22的第四限位结构与当前第二标准节(未来将成为顶部标准节)的第二限位结构的连接,然后小心地将升降单元22向上缩回到第三工作位置。Step 3: Adjust the lifting unit; release the connection between the fourth limiting structure of the lifting unit 22 and the second limiting structure of the current second standard section (which will become the top standard section in the future), and then carefully retract the lifting unit 22 upward to the third working position.

步骤4:升降单元22需继续向下伸出至第四工作位置,其第四限位结构与现在成为顶部标准节的第三个标准节的第二限位结构连接。Step 4: The lifting unit 22 needs to continue to extend downward to the fourth working position, and its fourth limiting structure is connected to the second limiting structure of the third standard section which now becomes the top standard section.

步骤5:恢复原位;支撑单元21相对于升降单元22向下伸出至第一工作位置,此时支撑单元21的第四限位结构与新顶部标准节(即原第二个标准节)的第一限位结构重新连接并锁定,确保整个钢筋桁架结构的稳定性和安全性。Step 5: Return to the original position; the support unit 21 extends downward to the first working position relative to the lifting unit 22. At this time, the fourth limiting structure of the support unit 21 is reconnected and locked with the first limiting structure of the new top standard section (i.e., the original second standard section) to ensure the stability and safety of the entire steel truss structure.

在本发明的描述中,需要理解的是,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。在本发明的描述中,“多个”的含义是两个或两个以上,除非另有明确具体的限定。In the description of the present invention, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

在本发明中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连;可以是两个元件内部的连通或两个元件的相互作用关系。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

在本发明中,除非另有明确的规定和限定,第一特征在第二特征“上”或“下”,可以是第一和第二特征直接接触,或第一和第二特征通过中间媒介间接接触。而且,第一特征在第二特征“之上”、“上方”和“上面”,可以是第一特征在第二特征正上方或斜上方,或仅仅表示第一特征水平高度高于第二特征。第一特征在第二特征“之下”、“下方”和“下面”,可以是第一特征在第二特征正下方或斜下方,或仅仅表示第一特征水平高度低于第二特征。In the present invention, unless otherwise clearly specified and limited, when a first feature is “on” or “below” a second feature, it may be that the first and second features are in direct contact, or that the first and second features are in indirect contact through an intermediate medium. Moreover, when a first feature is “above”, “above” or “above” a second feature, it may be that the first feature is directly above or obliquely above the second feature, or it may simply mean that the first feature is higher in level than the second feature. When a first feature is “below”, “below” or “below” a second feature, it may be that the first feature is directly below or obliquely below the second feature, or it may simply mean that the first feature is lower in level than the second feature.

在本说明书的描述中,术语“一个实施例”、“一些实施例”、“实施例”、“示例”、“具体示例”或“一些示例”等的描述,是指结合该实施例或示例描述的具体特征、结构、材料或者特点包含于本发明的至少一个实施例或示例中。在本说明书中,对上述术语的示意性表述不必须针对的是相同的实施例或示例。而且,描述的具体特征、结构、材料或者特点可以在任一个或多个实施例或示例中以合适的方式结合。此外,在不相互矛盾的情况下,本领域的技术人员可以将本说明书中描述的不同实施例或示例以及不同实施例或示例的特征进行结合和组合。In the description of this specification, the description of the terms "one embodiment", "some embodiments", "embodiment", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.

尽管上面已经示出和描述了本发明的实施例,可以理解的是,上述实施例是示例性的,不能理解为对本发明的限制,本领域的普通技术人员在本发明的范围内可以对上述实施例进行改动、修改、替换和变型。Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may alter, modify, replace and modify the above embodiments within the scope of the present invention.

Claims (10)

1.一种用于造楼机平台的升降机构,其特征在于,升降机构包括多节竖向可拆卸连接的标准节组成的钢筋桁架以及套接于标准节上且能够沿钢筋桁架纵向升降的升降装置;升降装置包括彼此可在第一工作位置、第二工作位置、第三工作位置和第四工作位置之间伸缩连接的支撑单元和升降单元,支撑单元位于升降单元的上方且与造楼机立柱可拆卸连接,支撑单元和升降单元均具有与标准节上的第一限位结构、第二限位结构和第三限位结构可拆卸连接的第四限位结构;同一标准节中,第三限位结构、第二限位结构和第一限位结构高度依次降低;位于第一工作位置时:支撑单元和升降单元的第四限位结构之间的垂直距离为相邻两个标准节中上方标准节的第一限位结构和下方标准节的第二限位结构之间垂直距离;位于第二工作位置时:支撑单元和升降单元的第四限位结构之间的垂直距离为相邻两个标准节中第二限位结构之间的垂直距离;位于第三工作位置时:支撑单元和升降单元的第四限位结构之间的垂直距离为相邻两个标准节中上方标准节的第二限位结构和下方标准节的第三限位结构之间的垂直距离;位于第四工作位置时:支撑单元和升降单元的第四限位结构之间的垂直距离为三个标准节中两端的标准节上的第二限位结构之间的垂直距离。1. A lifting mechanism for a building construction machine platform, characterized in that the lifting mechanism comprises a steel truss composed of a plurality of vertically detachably connected standard sections and a lifting device sleeved on the standard sections and capable of being lifted and lowered longitudinally along the steel truss; the lifting device comprises a support unit and a lifting unit which can be telescopically connected to each other between a first working position, a second working position, a third working position and a fourth working position, the support unit is located above the lifting unit and is detachably connected to a column of the building construction machine, the support unit and the lifting unit both have a fourth limiting structure detachably connected to a first limiting structure, a second limiting structure and a third limiting structure on the standard section; in the same standard section, the heights of the third limiting structure, the second limiting structure and the first limiting structure are reduced in sequence; when in the first working position: the support unit The vertical distance between the fourth limiting structures of the support unit and the lifting unit is the vertical distance between the first limiting structure of the upper standard section and the second limiting structure of the lower standard section among two adjacent standard sections; when located at the second working position: the vertical distance between the fourth limiting structures of the support unit and the lifting unit is the vertical distance between the second limiting structures of the two adjacent standard sections; when located at the third working position: the vertical distance between the fourth limiting structures of the support unit and the lifting unit is the vertical distance between the second limiting structure of the upper standard section and the third limiting structure of the lower standard section among two adjacent standard sections; when located at the fourth working position: the vertical distance between the fourth limiting structures of the support unit and the lifting unit is the vertical distance between the second limiting structures on the standard sections at both ends of the three standard sections. 2.根据权利要求1的用于造楼机平台的升降机构,其特征在于,2. The lifting mechanism for a building construction machine platform according to claim 1, characterized in that: 升降装置具有与标准节安装状态:The lifting device has the same installation status as the standard section: 升降单元和支撑单元处于第一工作位置,升降单元的第四限位结构与钢筋桁架顶部的第二个标准节的第二限位结构连接;解除支撑单元的第四限位结构与钢筋桁架顶部的第一个标准节的第一限位结构连接;The lifting unit and the supporting unit are in the first working position, and the fourth limiting structure of the lifting unit is connected to the second limiting structure of the second standard section at the top of the steel truss; the fourth limiting structure of the supporting unit is disconnected from the first limiting structure of the first standard section at the top of the steel truss; 支撑单元相对于升降单元向上伸出至第四工作位置,将新的标准节置入支撑单元并与原第一个标准节可拆卸拼接,支撑单元的第四限位结构与新的标准节的第二限位结构连接;The support unit extends upward to the fourth working position relative to the lifting unit, a new standard section is placed into the support unit and detachably spliced with the original first standard section, and the fourth limiting structure of the support unit is connected with the second limiting structure of the new standard section; 升降单元相对于支撑单元向上伸出至第三工作位置,升降单元的第四限位结构与原来最顶端的标准节的第三限位结构对齐;The lifting unit extends upward to a third working position relative to the supporting unit, and the fourth limiting structure of the lifting unit is aligned with the third limiting structure of the original topmost standard section; 升降单元相对于支撑单元向下伸出至原来最顶端的标准节的第二限位结构连接,解除支撑单元的第四限位结构与新的标准节的第二限位结构连接;The lifting unit extends downward relative to the supporting unit to connect with the second limiting structure of the original topmost standard section, and releases the connection between the fourth limiting structure of the supporting unit and the second limiting structure of the new standard section; 支撑单元相对于升降单元向下伸出至第一工作位置,支撑单元的第四限位结构与新的标准节的第一限位结构连接。The support unit extends downward to a first working position relative to the lifting unit, and the fourth limiting structure of the support unit is connected to the first limiting structure of the new standard section. 3.根据权利要求1的用于造楼机平台的升降机构,其特征在于,3. The lifting mechanism for a building construction machine platform according to claim 1, characterized in that: 升降装置具有与标准节拆卸状态:The lifting device has the following disassembled state: 升降单元和支撑单元处于第一工作位置,升降单元的第四限位结构与钢筋桁架顶部的第二个标准节的第二限位结构连接,解除支撑单元的第四限位结构与钢筋桁架顶部的标准节的第一限位结构连接;The lifting unit and the supporting unit are in the first working position, the fourth limiting structure of the lifting unit is connected to the second limiting structure of the second standard section at the top of the steel truss, and the fourth limiting structure of the supporting unit is disconnected from the first limiting structure of the standard section at the top of the steel truss; 支撑单元相对于升降单元向上伸出至第二工作位置,支撑单元的第四限位结构与钢筋桁架顶部第一个标准节的第二限位结构连接;The support unit extends upward to a second working position relative to the lifting unit, and the fourth limiting structure of the support unit is connected to the second limiting structure of the first standard section at the top of the steel truss; 解除升降单元的第四限位结构与钢筋桁架顶部的第二个标准节的第二限位结构的连接,移动升降单元向上缩回至第三工作位置;Release the connection between the fourth limiting structure of the lifting unit and the second limiting structure of the second standard section at the top of the steel bar truss, and move the lifting unit upward and retract it to the third working position; 移动升降单元向下伸出至第四工作位置,升降单元的第四限位结构与钢筋桁架顶部的第三个标准节的第二限位结构连接,解除支撑单元的第四限位结构与钢筋桁架顶部第一个标准节的第二限位结构的连接,此时可拆走钢筋桁架顶部第一个标准节;The mobile lifting unit extends downward to the fourth working position, the fourth limiting structure of the lifting unit is connected to the second limiting structure of the third standard section at the top of the steel truss, and the connection between the fourth limiting structure of the support unit and the second limiting structure of the first standard section at the top of the steel truss is released, and the first standard section at the top of the steel truss can be removed; 支撑单元相对于升降单元向下伸出至第一工作位置,支撑单元的第四限位结构与原来第二标准节的第一限位结构连接。The support unit extends downward to a first working position relative to the lifting unit, and the fourth limiting structure of the support unit is connected to the first limiting structure of the original second standard section. 4.根据权利要求1的升降机构,其特征在于,4. The lifting mechanism according to claim 1, characterized in that: 升降单元包括底座、升降器和沿升降方向的多个导向杆;The lifting unit includes a base, a lifter and a plurality of guide rods along the lifting direction; 第四限位结构设于底座;升降器的一端安装在底座上,升降器的另一端能够与支撑单元可拆卸连接或固定连接;The fourth limiting structure is arranged on the base; one end of the lifter is mounted on the base, and the other end of the lifter can be detachably connected or fixedly connected to the support unit; 多个导向杆安装在底座的上端,且位于升降器前后两侧,导向杆贯穿支撑单元边侧,能够引导支撑单元和升降单元彼此沿上下方向伸缩且导向杆与升降器之间有间隙。A plurality of guide rods are installed at the upper end of the base and are located at the front and rear sides of the lifter. The guide rods penetrate the sides of the support unit and can guide the support unit and the lifter to extend and retract in the up and down directions with a gap between the guide rods and the lifter. 底座上设有横向设置的两个第四限位结构;Two fourth limiting structures are arranged horizontally on the base; 升降器位于两个第四限位结构之间,且与两个第四限位结构有间隙。The lifter is located between the two fourth limiting structures and has a gap between the two fourth limiting structures. 5.根据权利要求4的升降机构,其特征在于,5. The lifting mechanism according to claim 4, characterized in that: 支撑单元呈倒U形并套在钢筋桁架的顶部外;The support unit is in an inverted U shape and is placed outside the top of the steel truss; 支撑单元中顶板中部设有挖孔,挖孔位置与造楼机立柱的中心孔相对应;A hole is provided in the middle of the top plate of the support unit, and the position of the hole corresponds to the central hole of the building machine column; 支撑单元中左右两侧的支撑板的外表面上分别设有横向设置贯穿支撑板的两个第四限位结构,第四限位结构能够与标准节限位连接。Two fourth limiting structures are respectively arranged on the outer surfaces of the supporting plates on the left and right sides of the supporting unit and are transversely arranged to penetrate the supporting plates. The fourth limiting structures can be connected to the standard section limit. 6.根据权利要求5的升降机构,其特征在于,6. The lifting mechanism according to claim 5, characterized in that: 底座包括相对设置的两个C型板,C型板的槽口背离标准节方向;C型板的上板前后两侧安装两个垂直于C型板的上板的导向杆,两个导向杆可贯穿支撑单元边侧以实现支撑单元和升降单元纵向导向;The base includes two C-shaped plates arranged opposite to each other, and the notches of the C-shaped plates are away from the standard section direction; two guide rods perpendicular to the upper plate of the C-shaped plates are installed on the front and rear sides of the upper plate of the C-shaped plates, and the two guide rods can penetrate the side of the support unit to realize the longitudinal guidance of the support unit and the lifting unit; C型板固定连接有依次穿透C型板的下板和C型板的上板的升降器,升降器伸缩端的端部与支撑单元固定连接或可拆卸连接;The C-shaped plate is fixedly connected with a lifter which sequentially penetrates the lower plate and the upper plate of the C-shaped plate, and the end of the telescopic end of the lifter is fixedly connected or detachably connected to the support unit; C型板内设有贯穿C型板的竖直板的两个第四限位结构,第四限位结构能够与标准节限位连接。Two fourth limiting structures are arranged in the C-shaped plate and are vertical plates that penetrate the C-shaped plate. The fourth limiting structures can be connected with the standard section limit. 7.根据权利要求6的升降机构,其特征在于,7. The lifting mechanism according to claim 6, characterized in that: 支撑单元中左右两侧的支撑板的底部向外弯折形成凸边,沿着凸边长度方向间隔分布三个竖向的槽孔,边缘的两个槽孔贯穿凸边,中间的槽孔从下表面进入,向上延伸至凸边的内部;The bottoms of the support plates on the left and right sides of the support unit are bent outward to form a convex edge, and three vertical slots are distributed at intervals along the length direction of the convex edge. The two slots on the edge penetrate the convex edge, and the middle slot enters from the lower surface and extends upward to the inside of the convex edge; 边缘的两个槽孔可由两个导向杆贯穿以实现支撑单元与升降单元纵向导向;The two slots on the edge can be penetrated by two guide rods to achieve longitudinal guidance of the support unit and the lifting unit; 中间的槽孔内部与升降器固定连接或可拆卸连接。The interior of the middle slot is fixedly connected or detachably connected to the lifter. 8.根据权利要求7的升降机构,其特征在于,8. The lifting mechanism according to claim 7, characterized in that: 支撑单元的内表面和C型板的竖直板靠近钢筋桁架侧表面均安装有多个角钢导向轮组,角钢导向轮组与标准节抵接且可引导支撑单元或C型板沿着标准节延伸方向移动;A plurality of angle steel guide wheel groups are installed on the inner surface of the support unit and the vertical plate of the C-shaped plate close to the side surface of the steel truss. The angle steel guide wheel groups abut against the standard section and can guide the support unit or the C-shaped plate to move along the extension direction of the standard section. 角钢导向轮组包括第一导向轮部件以及与第一导向轮部件铰接的第二导向轮部件,第一导向轮部件安装在支撑板内表面以及C型板的竖板靠近钢筋桁架侧表面,第二导向轮部件可绕与第一导向轮部件铰接的铰接轴顺或逆时针转动90度。The angle steel guide wheel group includes a first guide wheel component and a second guide wheel component hinged to the first guide wheel component. The first guide wheel component is installed on the inner surface of the support plate and the vertical plate of the C-shaped plate close to the side surface of the steel truss. The second guide wheel component can rotate 90 degrees clockwise or counterclockwise around the hinge axis hinged to the first guide wheel component. 9.根据权利要求8的升降机构,其特征在于,9. The lifting mechanism according to claim 8, characterized in that: 标准节左右两侧的侧壁上对侧设置两个连接板,每个连接板上开设竖向分布的两列限位结构,限位结构横向设置至少三排;限位结构包括第一限位结构、第二限位结构和第三限位结构;第一限位结构、第二限位结构和第三限位结构与第四限位结构相对应;Two connecting plates are arranged on the opposite sides of the side walls on the left and right sides of the standard section, and two rows of limiting structures are arranged vertically on each connecting plate, and at least three rows of limiting structures are arranged horizontally; the limiting structures include a first limiting structure, a second limiting structure and a third limiting structure; the first limiting structure, the second limiting structure and the third limiting structure correspond to the fourth limiting structure; 第一限位结构、第二限位结构和第三限位结构为设置在标准节上的连接孔;The first limiting structure, the second limiting structure and the third limiting structure are connection holes arranged on the standard section; 第四限位结构为螺栓或液压油缸。The fourth limiting structure is a bolt or a hydraulic cylinder. 10.根据权利要求1的升降机构,其特征在于,升降机构还包括水泥基筑,水泥基筑固定在基面上,最下端的标准节与水泥基筑固定连接;10. The lifting mechanism according to claim 1, characterized in that the lifting mechanism further comprises a cement foundation, the cement foundation is fixed on the base surface, and the lowermost standard section is fixedly connected to the cement foundation; 多个水泥基筑在高层建筑的左右两侧均匀分布;Multiple cement foundations are evenly distributed on the left and right sides of the high-rise building; 每一个水泥基筑与每一个带有升降装置的钢筋桁架固定连接。Each cement foundation is fixedly connected to each steel truss with a lifting device.
CN202410767355.7A 2024-06-14 2024-06-14 A lifting mechanism for building construction machine platform Pending CN118598037A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202410767355.7A CN118598037A (en) 2024-06-14 2024-06-14 A lifting mechanism for building construction machine platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202410767355.7A CN118598037A (en) 2024-06-14 2024-06-14 A lifting mechanism for building construction machine platform

Publications (1)

Publication Number Publication Date
CN118598037A true CN118598037A (en) 2024-09-06

Family

ID=92565739

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202410767355.7A Pending CN118598037A (en) 2024-06-14 2024-06-14 A lifting mechanism for building construction machine platform

Country Status (1)

Country Link
CN (1) CN118598037A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN120465674A (en) * 2025-07-15 2025-08-12 龙岩市隆顺金属工程有限公司 A detachable steel structure construction operation platform

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN120465674A (en) * 2025-07-15 2025-08-12 龙岩市隆顺金属工程有限公司 A detachable steel structure construction operation platform

Similar Documents

Publication Publication Date Title
CN218712236U (en) External mold device applied to continuous beam construction
CN115467507B (en) A construction hanging basket for the reinforcement of hyperbolic structures and its working method
CN116219896A (en) Prefabricated installation device and construction method for bridge substructure
CN202689495U (en) Self-elevating chimney and water tower construction tower frame
CN117661865A (en) Prefabricated building construction integrated platform and its operating methods
CN115559209A (en) Double-tower-column cable tower construction method
CN220319141U (en) Threading type self-climbing cloth machine
CN120425727A (en) Suspended wall installation system and construction method suitable for fully prefabricated assembled stations
CN115749232A (en) Building machine and building method thereof
CN113215341B (en) Modular mounting structure of large-scale blast furnace top diffusion platform
CN119306117B (en) Positioning hanging device for box girder installation
CN112109037B (en) Special dismounting device for overhauling unit brake of hydropower station and dismounting method thereof
CN222540421U (en) A lifting mechanism for building construction machine platform
CN218969776U (en) Bearing device of outer template for hanging basket
CN115784033B (en) Obliquely attached tower crane and operating method thereof
CN217388477U (en) Tool for motor installation
CN116853964A (en) Tower crane step changing device and tower crane
CN108821082A (en) Mining steel structure derrick
CN115594091A (en) Lifting and lifting device and lifting method for a modular prefabricated house
CN119976672B (en) Lifting device and method for assembling a lifting device
CN224244382U (en) Hanging basket capable of transversely moving and turning
CN218345028U (en) Vertical transportation equipment for small materials
CN213011447U (en) Construction elevator steel platform ballast formula basis
CN223936042U (en) Spandrel girder structure with climbing claws
CN223950591U (en) TBM props boots hoisting accessory in tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination