CN118579664A - Large diameter shield machine hoisting and lowering assembly construction method and auxiliary hoisting device - Google Patents
Large diameter shield machine hoisting and lowering assembly construction method and auxiliary hoisting device Download PDFInfo
- Publication number
- CN118579664A CN118579664A CN202410896106.8A CN202410896106A CN118579664A CN 118579664 A CN118579664 A CN 118579664A CN 202410896106 A CN202410896106 A CN 202410896106A CN 118579664 A CN118579664 A CN 118579664A
- Authority
- CN
- China
- Prior art keywords
- shield
- well
- block
- main
- hook
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 32
- 238000000034 method Methods 0.000 claims abstract description 32
- 229910000831 Steel Inorganic materials 0.000 claims description 9
- 239000010959 steel Substances 0.000 claims description 9
- 230000007246 mechanism Effects 0.000 claims description 8
- 238000009412 basement excavation Methods 0.000 claims description 5
- 238000009434 installation Methods 0.000 claims description 5
- 230000009471 action Effects 0.000 claims description 3
- 238000003466 welding Methods 0.000 claims 2
- 230000008569 process Effects 0.000 abstract description 12
- 238000010586 diagram Methods 0.000 description 25
- 238000012986 modification Methods 0.000 description 5
- 230000004048 modification Effects 0.000 description 5
- 101100233916 Saccharomyces cerevisiae (strain ATCC 204508 / S288c) KAR5 gene Proteins 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000003139 buffering effect Effects 0.000 description 1
- 238000009933 burial Methods 0.000 description 1
- 238000009407 construction method and process Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/06—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for minimising or preventing longitudinal or transverse swinging of loads
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C15/00—Safety gear
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本发明涉及地下工程盾构施工技术领域,公开了一种大直径盾构机吊装下井组装施工方法及辅助起吊装置。旨在解决现有技术中组装耗时,效率低,时间成本高;会出现返工的情况的技术问题。本发明在盾构机吊装之前,准备吊装设备,并在吊装设备的行走区域内铺设路基、以承载吊装设备自重和吊装重量,所述吊装设备包括400t和/或300t履带吊。本发明确保各分体部件精确吊装定位与牢固连接,降低施工风险,减少不必要的返工;通过优化吊装下井和组装工序与步骤,可以降低组装的难度,提高组装的效率和准确性,从而减少施工时间,提高整体施工效率。
The present invention relates to the technical field of shield construction in underground engineering, and discloses a method for assembling a large-diameter shield machine by hoisting it down a well and an auxiliary hoisting device. It aims to solve the technical problems in the prior art that the assembly is time-consuming, inefficient, and time-costly; and rework may occur. Before the shield machine is hoisted, the present invention prepares hoisting equipment and lays a roadbed in the walking area of the hoisting equipment to bear the deadweight and hoisting weight of the hoisting equipment. The hoisting equipment includes a 400t and/or 300t crawler crane. The present invention ensures that each split component is accurately hoisted, positioned, and firmly connected, reduces construction risks, and reduces unnecessary rework; by optimizing the hoisting down a well and assembly processes and steps, the difficulty of assembly can be reduced, and the efficiency and accuracy of assembly can be improved, thereby reducing construction time and improving overall construction efficiency.
Description
技术领域Technical Field
本发明涉及地下工程盾构施工技术领域,尤其涉及一种大直径盾构机吊装下井组装施工方法及辅助起吊装置。The invention relates to the technical field of underground engineering shield construction, and in particular to a method for assembling a large-diameter shield machine by hoisting it down a shaft and an auxiliary hoisting device.
背景技术Background Art
大直径盾构机吊装下井的施工方法在当前的城市轨道交通建设中扮演着重要角色,但也面临着诸多挑战和问题。盾构机在隧洞施工中具有高自动化程度、节省人力、施工速度快等特点,特别适用于隧洞洞线较长、埋深较大的情况。在吊装下井过程中,需要考虑场地小、组装困难、地下管线复杂、浅覆土始发等问题。场地小、组装困难等问题使得大直径盾构机的吊装下井成为一项技术难题。The construction method of hoisting and lowering a large-diameter shield machine into the shaft plays an important role in the current urban rail transit construction, but it also faces many challenges and problems. The shield machine has the characteristics of high automation, labor saving, and fast construction speed in tunnel construction. It is particularly suitable for tunnels with long tunnel lines and deep burials. In the process of hoisting and lowering into the shaft, it is necessary to consider problems such as small site, difficult assembly, complex underground pipelines, and shallow cover. Problems such as small site and difficult assembly make the hoisting and lowering of large-diameter shield machines a technical problem.
在已经公开的文献中,中国专利申请号202310177024 .3的名为盾构机吊组装方法的专利中公开了一种吊机组装方法,该方法主要包括如下步骤:(1)开设工作井;(2)布设卷扬机及滑移轨道;(3)下放反力架底部构件及始发台;(4)吊装临时导台;(5)管片输送小车吊装;(6)-(17)盾体及后配套设备于主井口及副井口对应下井(18)盾体前移;(19)安装中间箱涵及边轨;(20)安装反力架顶部(21)安装负环管片,盾构机调试。本公开的盾构机吊组装方法具有吊装效率高、吊装工期短等优点。In the published literature, a patent entitled "Shield machine crane assembly method" with Chinese patent application number 202310177024.3 discloses a crane assembly method, which mainly includes the following steps: (1) opening a working shaft; (2) laying a winch and a sliding track; (3) lowering the bottom component of the reaction frame and the starting platform; (4) hoisting a temporary guide platform; (5) hoisting the segment conveying trolley; (6)-(17) lowering the shield body and the rear supporting equipment to the main wellhead and the auxiliary wellhead respectively; (18) moving the shield body forward; (19) installing the intermediate box culvert and the side rail; (20) installing the top of the reaction frame; (21) installing the negative ring segment, and debugging the shield machine. The shield machine crane assembly method disclosed in the present invention has the advantages of high hoisting efficiency and short hoisting period.
但是,在常年一线的工作中,申请人认为,现阶段的技术还存在如下不足之处,具体表现在:1组装耗时,效率低,时间成本高;2,偶尔会出现返工的情况。However, in the long-term front-line work, the applicant believes that the current technology still has the following shortcomings, specifically: 1. Assembly is time-consuming, inefficient, and has high time costs; 2. Rework occasionally occurs.
发明内容Summary of the invention
鉴于以上技术问题,本公开提供了一种大直径盾构机吊装下井组装施工方法及辅助起吊装置,解决了现有技术中组装耗时,效率低,时间成本高;会出现返工的情况的技术问题。In view of the above technical problems, the present invention provides a large-diameter shield machine hoisting and lowering shaft assembly construction method and an auxiliary lifting device, which solves the technical problems of time-consuming assembly, low efficiency, high time cost and rework in the prior art.
本发明研究大直径盾构机吊装下井的施工方法,形成一整套成熟有序的详细工序,有利于解决现场实际组装问题,确保各分体部件精确吊装定位与牢固连接,降低施工风险,减少不必要的返工;通过优化吊装下井和组装工序与步骤,可以降低组装的难度,提高组装的效率和准确性,从而减少施工时间,提高整体施工效率。The present invention studies the construction method of hoisting and lowering a large-diameter shield machine into a well, and forms a complete set of mature and orderly detailed processes, which is conducive to solving actual assembly problems on site, ensuring the accurate hoisting and positioning and firm connection of each split component, reducing construction risks, and reducing unnecessary rework; by optimizing the hoisting and lowering and assembly processes and steps, the difficulty of assembly can be reduced, and the efficiency and accuracy of assembly can be improved, thereby reducing construction time and improving overall construction efficiency.
本发明适用于盾构法隧道施工大直径盾构机设备的吊装下井组装施工工序与步骤。结合大直径盾构机吊装下井的施工特点、技术要求以及现场实际情况,提出了一套详细的吊运组装方法,严格按照施工方法和工序进行作业,可以确保盾构机的安装质量和隧道的施工质量。The present invention is applicable to the construction process and steps of hoisting and lowering a large-diameter shield machine equipment into a well for shield tunnel construction. Combining the construction characteristics, technical requirements and actual conditions of hoisting and lowering a large-diameter shield machine into a well, a detailed hoisting and assembly method is proposed. The operation is carried out strictly in accordance with the construction method and process, which can ensure the installation quality of the shield machine and the construction quality of the tunnel.
根据本公开的一个方面,提供一种大直径盾构机吊装下井组装施工方法及辅助起吊装置,在盾构机吊装之前,准备吊装设备,并在吊装设备的行走区域内铺设路基、以承载吊装设备自重和吊装重量,所述吊装设备包括400t和/或300t履带吊,其特征在于,包括如下步骤:According to one aspect of the present disclosure, a method for assembling a large-diameter shield machine by hoisting it down a shaft and an auxiliary hoisting device are provided. Before the shield machine is hoisted, hoisting equipment is prepared, and a roadbed is laid in the walking area of the hoisting equipment to bear the deadweight of the hoisting equipment and the hoisting weight. The hoisting equipment includes a 400t and/or 300t crawler crane, and is characterized in that the method includes the following steps:
1 搭建井下平台及叉车下井:在竖井后方搭建作业平台用于行走运输,并用履带吊将叉车放于作业平台上方、以运输船底板部件;1. Build an underground platform and lower a forklift into the shaft: Build an operating platform behind the shaft for walking and transportation, and use a crawler crane to place a forklift on the operating platform to transport the bottom plate parts;
2 船底板与喂片机下井:a.船底板下井:将船底板分为若干节,通过履带吊的主钩依次将每节船底板下吊至隧道内,并用叉车将每节船底板呈直线式铺设;b.喂片机吊装下井:首先将喂片机拆解分成多块,然后使用履带吊依序将喂片机分块下井后,在船底板上组装喂片机;2 Lowering of the ship bottom plate and the film feeder into the well: a. Lowering of the ship bottom plate into the well: Divide the ship bottom plate into several sections, and use the main hook of the crawler crane to lower each section of the ship bottom plate into the tunnel in turn, and use a forklift to lay each section of the ship bottom plate in a straight line; b. Lifting and lowering the film feeder into the well: First, disassemble the film feeder into several pieces, and then use the crawler crane to lower the film feeder into the well in sections in order, and then assemble the film feeder on the ship bottom plate;
3搭建车轮平台和轨道:在竖井内搭建一号台车车轮平台,并在一号台车车轮平台上搭建一号台车车轮轨道,所述一号台车车轮轨道的高度与船底板高度相同;3. Build the wheel platform and track: Build the No. 1 trolley wheel platform in the shaft, and build the No. 1 trolley wheel track on the No. 1 trolley wheel platform, the height of the No. 1 trolley wheel track being the same as the height of the ship bottom plate;
4 一号台车车轮下井:通过履带吊将多个一号台车车轮吊至一号台车车轮平台上,并安装固定;4 Lowering the wheels of the No. 1 trolley into the well: Use a crawler crane to lift multiple wheels of the No. 1 trolley onto the wheel platform of the No. 1 trolley and install and fix them;
5 一号台车分块下井:将一号台车分为下部前段、下部后段、中部前段、中部后段、上部前段、上部后段六个部分;依次通过履带吊主钩和副钩同时起吊每个部分下井后,并在井内进行组装一号台车,5. The No. 1 trolley is lowered into the well in sections: the No. 1 trolley is divided into six parts: the lower front section, the lower rear section, the middle front section, the middle rear section, the upper front section, and the upper rear section; each part is lifted into the well by the main hook and the auxiliary hook of the crawler crane, and the No. 1 trolley is assembled in the well.
6连接平台下井:通过履带吊将连接平台吊装下井,连接平台下井后和一号台车进行连接,安装固定销轴,在一号台车顶部和连接平台之间通过手拉葫芦以固定连接平台;6 Connecting platform lowered into the well: The connecting platform is hoisted into the well by a crawler crane, connected to the No. 1 trolley after lowering into the well, and the fixing pin is installed. A hand chain hoist is used to fix the connecting platform between the top of the No. 1 trolley and the connecting platform;
7 第一部分盾构机吊装下井:将盾构机分为8块;依次吊装下井盾体分块5、盾体分块6、盾体分块4;7 The first part: hoisting and lowering the shield machine into the well: the shield machine is divided into 8 blocks; shield block 5, shield block 6, and shield block 4 are hoisted and lowered into the well in sequence;
8 驱动组件下井:履带吊主钩使用钢丝绳挂在驱动部翻身架主吊耳上,主、副钩同时起吊,将驱动部整体入井安装到前盾上;8 Driving unit lowered into the well: The crawler crane main hook is hung on the main lifting lug of the driving unit turning frame with a wire rope, the main and auxiliary hooks are lifted at the same time, and the driving unit is lowered into the well as a whole and installed on the front shield;
所述钢丝绳包括至少两条,所述钢丝绳尺寸为φ90mmX10mThe steel wire ropes include at least two, and the size of the steel wire ropes is φ90mmX10m
9 纵梁下井:履带吊主钩与副钩配合做起钩变幅动作直至纵梁直立,将纵梁翻身90°,调整纵梁与地面距离在0.2~0.5m,然后拆除翻身吊耳上的钢丝绳、卸扣;9 Lowering the longitudinal beam into the well: The crawler crane main hook and auxiliary hook cooperate to perform the hook-lifting and luffing action until the longitudinal beam is upright, turn the longitudinal beam over 90 degrees, adjust the distance between the longitudinal beam and the ground to 0.2-0.5m, and then remove the wire rope and shackle on the turning lifting ear;
10 第二部分盾构机吊装下井:依次吊装下井盾体分块3、盾体分块7、盾体分块2、盾体分块8、盾体分块1;10 The second part is to hoist the shield machine down into the well: hoist the shield block 3, shield block 7, shield block 2, shield block 8, and shield block 1 into the well in sequence;
11 刀盘下井:刀盘下井前,在地面上拼装并焊接刀盘,完成后,400t主履带吊主钩挂在刀盘主吊耳及翻身吊耳上,300t履带吊主钩挂在刀盘副吊耳;两台吊机同步提升刀盘,在离地面2m主吊耳提升,副吊耳下降,在刀盘整体翻身90°后,调整刀盘与地面距离在0.2~0.5m,然后拆除副吊耳上的钢丝绳、卸扣;11 Cutterhead lowering: Before the cutterhead is lowered into the well, the cutterhead is assembled and welded on the ground. After completion, the main hook of the 400t main crawler crane is hung on the main lifting eye and the turning lifting eye of the cutterhead, and the main hook of the 300t crawler crane is hung on the auxiliary lifting eye of the cutterhead. The two cranes lift the cutterhead synchronously. When the main lifting eye is lifted 2m from the ground, the auxiliary lifting eye is lowered. After the cutterhead is turned over 90° as a whole, the distance between the cutterhead and the ground is adjusted to 0.2-0.5m, and then the wire rope and shackle on the auxiliary lifting eye are removed;
12 前盾切口环下井安装:刀盘安装完成后,安装盾体分块1上的切口环,主、副钩同时起吊,将盾体分块1切口环入井;切口环与盾体分块1之间通过骑缝座定位连接,安装骑缝销,焊接连接切口环与盾体分块1;12 Installation of the front shield cutout ring downhole: After the cutterhead is installed, install the cutout ring on the shield block 1, lift the main and auxiliary hooks at the same time, and lower the cutout ring of the shield block 1 into the well; the cutout ring and the shield block 1 are positioned and connected through the saddle seat, and the saddle pin is installed, and the cutout ring and the shield block 1 are welded and connected;
13 后盾下分块下井:主履带吊主、副钩同时起吊后盾前段下分块4;13 Lowering of the back shield block: The main crawler crane main and auxiliary hooks simultaneously lift the front lower back shield block 4;
14 拼装机和托梁下井:主履带吊主钩继续缓慢起吊,副钩配合作起钩变幅等动作直至整个拼装机立起来;在拼装机翻身90°后,调整其与地面距离,一般保持在0.2~0.5m,然后拆除翻身吊耳上的钢丝绳、卸扣;14 Assembler and joist lowered into the well: the main hook of the crawler crane continues to lift slowly, and the auxiliary hook cooperates with the hook lifting and luffing until the entire assembler stands up; after the assembler turns over 90°, adjust its distance from the ground, generally keeping it at 0.2-0.5m, and then remove the wire rope and shackle on the turning lifting ear;
托梁预先通过胎架支起,确保胎架稳定。拼装机装入托梁上,直至移动到托梁左端最大位置;然后使用工艺卡板固定拼装机与托梁,施焊固定;The joist is supported by the frame in advance to ensure the stability of the frame. The assembly machine is installed on the joist until it moves to the maximum position on the left end of the joist; then the assembly machine and the joist are fixed with a process pallet and welded;
15 后盾左、右分块下井:主履带吊主钩挂在后盾左分块2外侧的主吊耳上,副钩挂在后盾左分块2内侧的翻身吊耳上。主、副钩同时起吊;15 Lowering the left and right blocks of the rear shield: The main hook of the main crawler crane is hung on the main lifting lug on the outside of the left block 2 of the rear shield, and the auxiliary hook is hung on the turning lifting lug on the inside of the left block 2 of the rear shield. The main and auxiliary hooks are lifted at the same time;
16 后盾上分块1下井:主履带吊主钩挂在后盾上分块外侧主吊耳上,副钩使用一对φ52mmX10m钢丝绳挂在后盾上分块的外侧主吊耳上,检查无误后,主、副钩同时起吊入井。16 Lowering the upper block 1 of the rear shield into the well: the main hook of the main crawler crane is hung on the main lifting lug outside the upper block of the rear shield, and the auxiliary hook is hung on the main lifting lug outside the upper block of the rear shield using a pair of φ52mmX10m wire ropes. After checking that everything is correct, the main and auxiliary hooks are lifted into the well at the same time.
所述步骤(5)中在井内组装一号台车包括如下步骤:The step (5) of assembling the No. 1 trolley in the well comprises the following steps:
a.下部前段吊装下井,并安装到一号台车车轮轨道上,然后对一号台车车轮施作溜车防护,以防止台车发生滑动;a. The lower front section is hoisted down the well and installed on the wheel track of the No. 1 trolley. Then the wheels of the No. 1 trolley are protected from slipping to prevent the trolley from sliding;
b.下部后段吊装下井,并与下部前段进行对接,对接处使用螺栓固定连接;b. The lower rear section is hoisted down into the well and connected with the lower front section, and the connection is fixed with bolts;
c.中部前段下井并安装到下部前段结构上,中部前段与下部前段对接处通过定位销和螺栓连接固定;c. The middle front section is lowered into the well and installed on the lower front section structure. The middle front section and the lower front section are connected and fixed at the joint by positioning pins and bolts;
d.中部后段吊装下井,并与中部前段及下部后段进行对接,对接处使用螺栓固定连接;d. The middle rear section is hoisted down into the well and connected with the middle front section and the lower rear section. Bolts are used to fix the connection at the connection points;
e.上部前段吊装下井,并安装到中部前段结构上,上部前段与中部前段通过定位销和螺栓连接固定;e. The upper front section is hoisted down the well and installed on the middle front section structure. The upper front section and the middle front section are connected and fixed by positioning pins and bolts;
f.上部后段吊装下井,并与上部前段及中部后段进行对接,对接处使用螺栓固定连接。f. The upper rear section is hoisted into the well and connected with the upper front section and the middle rear section. The connection is fixed with bolts.
所述步骤7中第一部分盾构机吊装下井还包括如下步骤:The first part of the shield machine hoisting down the well in step 7 also includes the following steps:
7.1 盾体分块5下井:使用400t履带吊主、副钩同时起吊,在离地面2m时,主钩提升,副钩下降,盾体分块5翻身90°,并调整盾体分块5与地面距离为0.2~0.5m,然后拆除翻身吊耳上的钢丝绳、卸扣,盾体分块5的定位位置为盾体分块5切口环前端对应洞门位置;7.1 Lowering shield block 5 into the well: Use the main and auxiliary hooks of a 400t crawler crane to lift it simultaneously. When it is 2m above the ground, the main hook is lifted and the auxiliary hook is lowered. The shield block 5 is turned over 90° and the distance between the shield block 5 and the ground is adjusted to 0.2-0.5m. Then remove the wire rope and shackle on the turning lifting ear. The positioning position of the shield block 5 is the front end of the cut ring of the shield block 5 corresponding to the tunnel door position.
7.2 盾体分块6和盾体分块4下井:将履带吊主钩挂在盾体分块6外侧主吊耳上,副钩挂在盾体分块4的外侧主吊耳上,主、副钩同时起吊,实现盾体分块6和分块4入井7.2 Lowering shield block 6 and shield block 4 into the well: Hang the main hook of the crawler crane on the main lifting lug outside shield block 6, and hang the auxiliary hook on the main lifting lug outside shield block 4. Lift the main and auxiliary hooks at the same time to lower shield block 6 and block 4 into the well.
所述步骤10中第二部分盾构机吊装下井还包括如下步骤:The second part of the shield machine hoisting down the well in step 10 also includes the following steps:
10.1盾体分块3、盾体分块7下井:履带吊主钩挂在盾体分块3外侧主吊耳上,副钩挂在盾体分块3的外侧主吊耳上,同时起吊,在底部架设始发基座,并在始发基座上用胎架及千斤顶进行支撑,以防止盾体分块侧滑,10.1 Shield block 3 and shield block 7 are lowered into the well: the main hook of the crawler crane is hung on the main lifting lug outside the shield block 3, and the auxiliary hook is hung on the main lifting lug outside the shield block 3. They are lifted at the same time, and the starting base is set up at the bottom, and the starting base is supported by a tire frame and a jack to prevent the shield block from sliding sideways.
10.2 盾体分块2、盾体分块8下井:履带吊主、副钩同时起吊,将盾体分块2、盾体分块8入井;10.2 Lowering shield block 2 and shield block 8 into the well: The main and auxiliary hooks of the crawler crane are lifted simultaneously to lower shield block 2 and shield block 8 into the well;
10.3 盾体分块1下井:履带吊主钩挂在盾体分块1外侧主吊耳上,履带吊副钩挂在盾体分块1的外侧主吊耳上,主、副钩同时起吊,将盾体分块1入井。10.3 Lowering shield block 1 into the well: The main hook of the crawler crane is hung on the main lifting lug outside the shield block 1, and the auxiliary hook of the crawler crane is hung on the main lifting lug outside the shield block 1. The main and auxiliary hooks are lifted at the same time to lower the shield block 1 into the well.
所述履带吊的两条履下铺设10块路基板,所述基板的方向沿掘进方向设计。Ten roadbed plates are laid under the two crawlers of the crawler crane, and the direction of the plate is designed along the excavation direction.
所述基板的底部设有带动其抬升的升降装置。A lifting device is provided at the bottom of the base plate to drive the base plate to lift up.
一种辅助起吊装置,使用上述的大直径盾构机吊装下井组装施工方法,包括吊钩,所述吊钩下方设有滑轮,吊装钢缆穿过所述滑轮,所述滑轮包括内轮和外轮,所述内轮和外轮之间安装有y字形垫圈,所述垫圈中空,气管连接其内外,所述气管的另一端连接气源,所述气管上连接阀门。An auxiliary lifting device is used in the above-mentioned large-diameter shield machine lifting and lowering into the well for assembly construction, comprising a hook, a pulley is provided under the hook, the lifting steel cable passes through the pulley, the pulley comprises an inner wheel and an outer wheel, a Y-shaped gasket is installed between the inner wheel and the outer wheel, the gasket is hollow, an air pipe connects the inside and the outside, the other end of the air pipe is connected to the air source, and a valve is connected to the air pipe.
所述y字形垫圈旁设有辅助定位环。An auxiliary positioning ring is arranged beside the Y-shaped gasket.
所述升降装置包括升降机构和磁吸块,所述升降机构的端部和所述磁吸块间电磁吸引。The lifting device comprises a lifting mechanism and a magnetic attraction block, and an end of the lifting mechanism and the magnetic attraction block are electromagnetically attracted to each other.
本发明的有益效果在于:The beneficial effects of the present invention are:
1.本发明研究大直径盾构机吊装下井的施工方法,形成一整套成熟有序的详细工序,有利于解决现场实际组装问题,确保各分体部件精确吊装定位与牢固连接,降低施工风险,减少不必要的返工;通过优化吊装下井和组装工序与步骤,可以降低组装的难度,提高组装的效率和准确性,从而减少施工时间,提高整体施工效率。本发明结合大直径盾构机吊装下井的施工特点、技术要求以及现场实际情况,提出了一套详细的吊运组装方法,严格按照施工方法和工序进行作业,可以确保盾构机的安装质量和隧道的施工质量。1. The present invention studies the construction method of hoisting and lowering a large-diameter shield machine into a well, and forms a complete set of mature and orderly detailed procedures, which is conducive to solving the actual assembly problems on site, ensuring the accurate hoisting and positioning of each split component and a firm connection, reducing construction risks, and reducing unnecessary rework; by optimizing the hoisting and lowering and assembly procedures and steps, the difficulty of assembly can be reduced, and the efficiency and accuracy of assembly can be improved, thereby reducing construction time and improving overall construction efficiency. The present invention combines the construction characteristics, technical requirements and actual on-site conditions of hoisting and lowering a large-diameter shield machine into a well, and proposes a set of detailed hoisting and assembly methods. Operations are carried out strictly in accordance with the construction methods and procedures, which can ensure the installation quality of the shield machine and the construction quality of the tunnel.
2.通过将盾构机拆分成多个分块,采用分步吊装的方式,显著提高了吊装效率和安全性。允许在有限的竖井空间内精确控制每个组件的下井过程,减少了空间占用,同时降低了单次吊装的重量,使得吊装作业更易于管理和控制。2. By splitting the shield machine into multiple blocks and adopting a step-by-step lifting method, the lifting efficiency and safety are significantly improved. It allows the lowering process of each component to be accurately controlled within the limited shaft space, reducing space occupancy and reducing the weight of a single lift, making the lifting operation easier to manage and control.
3.通过定位销、螺栓固定连接等确保了各个部件能够精确对接,提高了组装的精确性和稳定性。盾体分块的吊装通过翻身、精确对位、固定等步骤,确保了盾构机主体结构的准确拼接,为后续的掘进作业奠定了坚实的基础。3. The precise connection of each component is ensured by means of positioning pins and bolts, which improves the accuracy and stability of assembly. The shield blocks are hoisted through turning over, precise alignment, and fixation, ensuring the accurate splicing of the main structure of the shield machine, laying a solid foundation for subsequent excavation operations.
4.辅助起吊装置采用了独特的y字形垫圈设计,配合气压控制,能够有效缓冲吊装过程中的冲击力,保护吊装设备和盾构机组件不受损伤。同时,通过辅助定位环进一步提升了吊装的精准度。4. The auxiliary lifting device adopts a unique Y-shaped gasket design, which, combined with air pressure control, can effectively buffer the impact force during the lifting process and protect the lifting equipment and shield machine components from damage. At the same time, the auxiliary positioning ring further improves the lifting accuracy.
5.履带吊下方铺设的路基板及升降装置,分散了荷载,保证了地面承载力,通过可调节的升降功能,适应了不同阶段施工的需求,确保了施工场地的安全与稳定。5. The roadbed and lifting device laid under the crawler crane disperse the load and ensure the ground bearing capacity. Through the adjustable lifting function, it adapts to the needs of construction at different stages and ensures the safety and stability of the construction site.
6.通过搭建作业平台、叉车下井、一号台车及其轨道的安装,构建了一个高效的地下物流和组装结构,极大提升了盾构机各部件在竖井内部的转运和组装效率,减少了人工搬运的劳动强度和安全风险。6. By building an operating platform, lowering a forklift into the shaft, and installing the No. 1 trolley and its tracks, an efficient underground logistics and assembly structure was constructed, which greatly improved the efficiency of the transportation and assembly of various components of the shield machine inside the shaft and reduced the labor intensity and safety risks of manual handling.
7.采用400t和/或300t履带吊,结合主、副钩的协同作业,吊装能力强大,作业灵活性高,确保完成吊装下井组装过程。7. Use 400t and/or 300t crawler cranes, combined with the coordinated operation of the main and auxiliary hooks, with strong lifting capacity and high operational flexibility to ensure the completion of the lifting and assembly process downhole.
8.基板的设计,便于适应该设计条件下的负载。8. The design of the base plate is convenient for adapting to the load under the design conditions.
9.本申请还设计了一套辅助起吊的定位装置,在该定位装置的帮助下,可以实现进一步的准确定位。9. The present application also designs a set of auxiliary lifting positioning devices, with the help of which further accurate positioning can be achieved.
10.y字形垫圈的设计便于实现滑轮的锁死,可以有效防止吊装结构的摇晃失稳,有效提高吊装效率。10. The design of the Y-shaped washer facilitates the locking of the pulley, which can effectively prevent the shaking and instability of the lifting structure and effectively improve the lifting efficiency.
11.升降装置可以有效对运输线路的高度进行调整,尤其是可以有效调整途径设备的重心平衡,灵活性高提高运输效率。11. The lifting device can effectively adjust the height of the transport route, especially it can effectively adjust the center of gravity balance of the equipment on the route, and its high flexibility improves the transport efficiency.
12.辅助定位环提高设备的稳定性。12. Auxiliary positioning ring improves the stability of the equipment.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
图1为大直径盾构机吊装下井组装施工方法流程图;Figure 1 is a flow chart of the large diameter shield machine hoisting and lowering into the well assembly construction method;
图2是滑轮的剖视图;Fig. 2 is a cross-sectional view of the pulley;
图3是升降装置的结构示意图;FIG3 is a schematic structural diagram of a lifting device;
图4为井下平台结构示意图;Figure 4 is a schematic diagram of the downhole platform structure;
图5为船底板结构示意图;Figure 5 is a schematic diagram of the bottom plate structure;
图6为一号台车车轮平台结构示意图;FIG6 is a schematic diagram of the structure of the wheel platform of the No. 1 trolley;
图7为一号台车车轮结构示意图;Figure 7 is a schematic diagram of the wheel structure of the No. 1 trolley;
图8为一号台车下部前段结构示意图;FIG8 is a schematic diagram of the front structure of the lower part of the No. 1 trolley;
图9为一号台车下部后段结构示意图;FIG9 is a schematic diagram of the structure of the lower rear section of the No. 1 trolley;
图10为一号台车中部前段结构示意图;Figure 10 is a schematic diagram of the structure of the front section of the middle part of the No. 1 trolley;
图11为一号台车中部后段结构示意图;Figure 11 is a schematic diagram of the structure of the middle rear section of the No. 1 trolley;
图12为一号台车上部前段结构示意图;FIG12 is a schematic diagram of the upper front section structure of the No. 1 trolley;
图13为一号台车上部后段结构示意图;FIG13 is a schematic diagram of the upper rear section structure of the No. 1 trolley;
图14为连接平台结构示意图;FIG14 is a schematic diagram of the connection platform structure;
图15为盾体分块5结构示意图;FIG15 is a schematic diagram of the structure of the shield body block 5;
图16为盾体分块6、4结构示意图;Figure 16 is a schematic diagram of the structure of shield body blocks 6 and 4;
图17为驱动组件结构示意图;FIG17 is a schematic diagram of the structure of a drive assembly;
图18为纵梁结构示意图;Figure 18 is a schematic diagram of the longitudinal beam structure;
图19为盾体分块3、7结构示意图;Figure 19 is a schematic diagram of the structure of shield body blocks 3 and 7;
图20为盾体分块2、8结构示意图;Figure 20 is a schematic diagram of the structure of shield body blocks 2 and 8;
图21为盾体分块1结构示意图;Figure 21 is a schematic diagram of the structure of the shield body block 1;
图22为刀盘结构示意图;Figure 22 is a schematic diagram of the cutter disc structure;
图23为前盾切口环结构示意图;Figure 23 is a schematic diagram of the front shield cutout ring structure;
图24为后盾下分块4结构示意图;Figure 24 is a schematic diagram of the structure of the backing lower sub-block 4;
图25为拼装机和托梁结构示意图;Fig. 25 is a schematic diagram of the assembly machine and the joist structure;
图26为后盾分块2、3结构示意图;Figure 26 is a schematic diagram of the structure of backing blocks 2 and 3;
图27为后盾分块1结构示意图;Figure 27 is a schematic diagram of the structure of the backing block 1;
图中各部件名称:1、内轮;2、y字形垫圈;3、气管;4、外轮;5、辅助定位环;6、路基板;7、磁吸块;8、升降机构;9、叉车;10、井下平台;11、船底板;12、一号台车车轮平台;13、一号台车车轮;14、一号台车下部前段;15、一号台车下部后段;16、一号台车中部前段;17、一号台车中部后段;18、一号台车上部前段;19、一号台车上部后段;20、连接平台;21、盾体分块5;22、盾体分块6;23、盾体分块4;24、驱动组件;25、纵梁;26盾体分块3;27、盾体分块7;28、盾体分块2;29、盾体分块8;30、盾体分块1;31、刀盘;32前盾切口环;33、后盾下分块4;34、拼装机;35、托梁;36、后盾分块2;37、后盾分块3;38、后盾分块1。The names of the components in the figure are: 1. Inner wheel; 2. Y-shaped gasket; 3. Air pipe; 4. Outer wheel; 5. Auxiliary positioning ring; 6. Road base plate; 7. Magnetic block; 8. Lifting mechanism; 9. Forklift; 10. Underground platform; 11. Bottom plate; 12. No. 1 trolley wheel platform; 13. No. 1 trolley wheel; 14. No. 1 trolley lower front section; 15. No. 1 trolley lower rear section; 16. No. 1 trolley middle front section; 17. No. 1 trolley middle rear section; 18. No. 1 trolley upper front section; 19. The upper rear section of the trolley; 20, connecting platform; 21, shield block 5; 22, shield block 6; 23, shield block 4; 24, drive assembly; 25, longitudinal beam; 26 shield block 3; 27, shield block 7; 28, shield block 2; 29, shield block 8; 30, shield block 1; 31, cutter head; 32 front shield cutting ring; 33, rear shield lower block 4; 34, assembler; 35, support beam; 36, rear shield block 2; 37, rear shield block 3; 38, rear shield block 1.
具体实施方式DETAILED DESCRIPTION
以下结合附图对本发明的优选实施例进行说明,应当理解,此处所描述的优选实施例仅用于说明和解释本发明,并不用于限定本发明。The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.
实施例1Example 1
本例公开一种大直径盾构机吊装下井组装施工方法及辅助起吊装置,参见图1至27,This example discloses a method for assembling a large-diameter shield machine by hoisting it down a shaft and an auxiliary hoisting device, see FIGS. 1 to 27 ,
在盾构机吊装之前,准备吊装设备,并在吊装设备的行走区域内铺设路基、以承载吊装设备自重和吊装重量,所述吊装设备包括400t和/或300t履带吊,其特征在于,包括如下步骤:Before hoisting the shield machine, prepare the hoisting equipment and lay the roadbed in the walking area of the hoisting equipment to bear the deadweight of the hoisting equipment and the hoisting weight. The hoisting equipment includes a 400t and/or 300t crawler crane, which is characterized by comprising the following steps:
1 搭建井下平台及叉车下井:在竖井后方搭建作业平台用于行走运输,并用履带吊将叉车放于作业平台上方、以运输船底板部件;1. Build an underground platform and lower a forklift into the shaft: Build an operating platform behind the shaft for walking and transportation, and use a crawler crane to place a forklift on the operating platform to transport the bottom plate parts;
2 船底板与喂片机下井:a.船底板下井:将船底板分为若干节,通过履带吊的主钩依次将每节船底板下吊至隧道内,并用叉车将每节船底板呈直线式铺设;b.喂片机吊装下井:首先将喂片机拆解分成多块,然后使用履带吊依序将喂片机分块下井后,在船底板上组装喂片机;2 Lowering of the ship bottom plate and the film feeder into the well: a. Lowering of the ship bottom plate into the well: Divide the ship bottom plate into several sections, and use the main hook of the crawler crane to lower each section of the ship bottom plate into the tunnel in turn, and use a forklift to lay each section of the ship bottom plate in a straight line; b. Lifting and lowering the film feeder into the well: First, disassemble the film feeder into several pieces, and then use the crawler crane to lower the film feeder into the well in sections in order, and then assemble the film feeder on the ship bottom plate;
3搭建车轮平台和轨道:在竖井内搭建一号台车车轮平台,并在一号台车车轮平台上搭建一号台车车轮轨道,所述一号台车车轮轨道的高度与船底板高度相同;3. Build the wheel platform and track: Build the No. 1 trolley wheel platform in the shaft, and build the No. 1 trolley wheel track on the No. 1 trolley wheel platform, the height of the No. 1 trolley wheel track being the same as the height of the ship bottom plate;
4 一号台车车轮下井:通过履带吊将多个一号台车车轮吊至一号台车车轮平台上,并安装固定;4 Lowering the wheels of the No. 1 trolley into the well: Use a crawler crane to lift multiple wheels of the No. 1 trolley onto the wheel platform of the No. 1 trolley and install and fix them;
5 一号台车分块下井:将一号台车分为下部前段、下部后段、中部前段、中部后段、上部前段、上部后段六个部分;依次通过履带吊主钩和副钩同时起吊每个部分下井后,并在井内进行组装一号台车,5. The No. 1 trolley is lowered into the well in sections: the No. 1 trolley is divided into six parts: the lower front section, the lower rear section, the middle front section, the middle rear section, the upper front section, and the upper rear section; each part is lifted into the well by the main hook and the auxiliary hook of the crawler crane, and the No. 1 trolley is assembled in the well.
6连接平台下井:通过履带吊将连接平台吊装下井,连接平台下井后和一号台车进行连接,安装固定销轴,在一号台车顶部和连接平台之间通过手拉葫芦以固定连接平台;6 Connecting platform lowered into the well: The connecting platform is hoisted into the well by a crawler crane, connected to the No. 1 trolley after lowering into the well, and the fixing pin is installed. A hand chain hoist is used to fix the connecting platform between the top of the No. 1 trolley and the connecting platform;
7 第一部分盾构机吊装下井:将盾构机分为8块;依次吊装下井盾体分块5、盾体分块6、盾体分块4;7 The first part: hoisting and lowering the shield machine into the well: the shield machine is divided into 8 blocks; shield block 5, shield block 6, and shield block 4 are hoisted and lowered into the well in sequence;
8 驱动组件下井:履带吊主钩使用钢丝绳挂在驱动部翻身架主吊耳上,主、副钩同时起吊,将驱动部整体入井安装到前盾上;8 Driving unit lowered into the well: The crawler crane main hook is hung on the main lifting lug of the driving unit turning frame with a wire rope, the main and auxiliary hooks are lifted at the same time, and the driving unit is lowered into the well as a whole and installed on the front shield;
所述钢丝绳包括至少两条,所述钢丝绳尺寸为φ90mmX10mThe steel wire ropes include at least two, and the size of the steel wire ropes is φ90mmX10m
9 纵梁下井:履带吊主钩与副钩配合做起钩变幅动作直至纵梁直立,将纵梁翻身90°,调整纵梁与地面距离在0.2~0.5m,然后拆除翻身吊耳上的钢丝绳、卸扣;9 Lowering the longitudinal beam into the well: The crawler crane main hook and auxiliary hook cooperate to perform the hook-lifting and luffing action until the longitudinal beam is upright, turn the longitudinal beam over 90 degrees, adjust the distance between the longitudinal beam and the ground to 0.2-0.5m, and then remove the wire rope and shackle on the turning lifting ear;
10 第二部分盾构机吊装下井:依次吊装下井盾体分块3、盾体分块7、盾体分块2、盾体分块8、盾体分块1;10 The second part is hoisting the shield machine down the shaft: hoisting the shield block 3, shield block 7, shield block 2, shield block 8, and shield block 1 down the shaft in sequence;
11 刀盘下井:刀盘下井前,在地面上拼装并焊接刀盘,完成后,400t主履带吊主钩挂在刀盘主吊耳及翻身吊耳上,300t履带吊主钩挂在刀盘副吊耳;两台吊机同步提升刀盘,在离地面2m主吊耳提升,副吊耳下降,在刀盘整体翻身90°后,调整刀盘与地面距离在0.2~0.5m,然后拆除副吊耳上的钢丝绳、卸扣;11 Cutterhead lowering: Before the cutterhead is lowered into the well, the cutterhead is assembled and welded on the ground. After completion, the main hook of the 400t main crawler crane is hung on the main lifting eye and the turning lifting eye of the cutterhead, and the main hook of the 300t crawler crane is hung on the auxiliary lifting eye of the cutterhead. The two cranes lift the cutterhead synchronously. When the main lifting eye is lifted 2m from the ground, the auxiliary lifting eye is lowered. After the cutterhead is turned over 90° as a whole, the distance between the cutterhead and the ground is adjusted to 0.2-0.5m, and then the wire rope and shackle on the auxiliary lifting eye are removed;
12 前盾切口环下井安装:刀盘安装完成后,安装盾体分块1上的切口环,主、副钩同时起吊,将盾体分块1切口环入井;切口环与盾体分块1之间通过骑缝座定位连接,安装骑缝销,焊接连接切口环与盾体分块1;12 Installation of the front shield cutout ring downhole: After the cutterhead is installed, install the cutout ring on the shield block 1, lift the main and auxiliary hooks at the same time, and lower the cutout ring of the shield block 1 into the well; the cutout ring and the shield block 1 are positioned and connected through the saddle seat, and the saddle pin is installed, and the cutout ring and the shield block 1 are welded and connected;
13 后盾下分块下井:主履带吊主、副钩同时起吊后盾前段下分块4;13 Lowering of the back shield block: The main crawler crane main and auxiliary hooks simultaneously lift the front lower back shield block 4;
14 拼装机和托梁下井:主履带吊主钩继续缓慢起吊,副钩配合作起钩变幅等动作直至整个拼装机立起来;在拼装机翻身90°后,调整其与地面距离,一般保持在0.2~0.5m,然后拆除翻身吊耳上的钢丝绳、卸扣;14 Assembler and joist lowered into the well: the main hook of the crawler crane continues to lift slowly, and the auxiliary hook cooperates with the hook lifting and luffing until the entire assembler stands up; after the assembler turns over 90°, adjust its distance from the ground, generally keeping it at 0.2-0.5m, and then remove the wire rope and shackle on the turning lifting ear;
托梁预先通过胎架支起,确保胎架稳定。拼装机装入托梁上,直至移动到托梁左端最大位置;然后使用工艺卡板固定拼装机与托梁,施焊固定;The joist is supported by the frame in advance to ensure the stability of the frame. The assembly machine is installed on the joist until it moves to the maximum position on the left end of the joist; then the assembly machine and the joist are fixed with a process pallet and welded;
15 后盾左、右分块下井:主履带吊主钩挂在后盾左分块2外侧的主吊耳上,副钩挂在后盾左分块2内侧的翻身吊耳上。主、副钩同时起吊;15 Lowering the left and right blocks of the rear shield: The main hook of the main crawler crane is hung on the main lifting lug on the outside of the left block 2 of the rear shield, and the auxiliary hook is hung on the turning lifting lug on the inside of the left block 2 of the rear shield. The main and auxiliary hooks are lifted at the same time;
16 后盾上分块1下井:主履带吊主钩挂在后盾上分块外侧主吊耳上,副钩使用一对φ52mmX10m钢丝绳挂在后盾上分块的外侧主吊耳上,检查无误后,主、副钩同时起吊入井。16 Lowering the upper block 1 of the rear shield into the well: the main hook of the main crawler crane is hung on the main lifting lug outside the upper block of the rear shield, and the auxiliary hook is hung on the main lifting lug outside the upper block of the rear shield using a pair of φ52mmX10m wire ropes. After checking that everything is correct, the main and auxiliary hooks are lifted into the well at the same time.
所述步骤(5)中在井内组装一号台车包括如下步骤:The step (5) of assembling the No. 1 trolley in the well comprises the following steps:
a.下部前段吊装下井,并安装到一号台车车轮轨道上,然后对一号台车车轮施作溜车防护,以防止台车发生滑动;a. The lower front section is hoisted down the well and installed on the wheel track of the No. 1 trolley. Then the wheels of the No. 1 trolley are protected from slipping to prevent the trolley from sliding;
b.下部后段吊装下井,并与下部前段进行对接,对接处使用螺栓固定连接;b. The lower rear section is hoisted down into the well and connected with the lower front section, and the connection is fixed with bolts;
c.中部前段下井并安装到下部前段结构上,中部前段与下部前段对接处通过定位销和螺栓连接固定;c. The middle front section is lowered into the well and installed on the lower front section structure. The middle front section and the lower front section are connected and fixed at the joint by positioning pins and bolts;
d.中部后段吊装下井,并与中部前段及下部后段进行对接,对接处使用螺栓固定连接;d. The middle rear section is hoisted down into the well and connected with the middle front section and the lower rear section. Bolts are used to fix the connection at the connection points;
e.上部前段吊装下井,并安装到中部前段结构上,上部前段与中部前段通过定位销和螺栓连接固定;e. The upper front section is hoisted down the well and installed on the middle front section structure. The upper front section and the middle front section are connected and fixed by positioning pins and bolts;
f.上部后段吊装下井,并与上部前段及中部后段进行对接,对接处使用螺栓固定连接。f. The upper rear section is hoisted into the well and connected with the upper front section and the middle rear section. The connection is fixed with bolts.
所述步骤7中第一部分盾构机吊装下井还包括如下步骤:The first part of the shield machine hoisting down the well in step 7 also includes the following steps:
7.1 盾体分块5下井:使用400t履带吊主、副钩同时起吊,在离地面2m时,主钩提升,副钩下降,盾体分块5翻身90°,并调整盾体分块5与地面距离为0.2~0.5m,然后拆除翻身吊耳上的钢丝绳、卸扣,盾体分块5的定位位置为盾体分块5切口环前端对应洞门位置;7.1 Lowering shield block 5 into the well: Use the main and auxiliary hooks of a 400t crawler crane to lift it simultaneously. When it is 2m above the ground, the main hook is lifted and the auxiliary hook is lowered. The shield block 5 is turned over 90° and the distance between the shield block 5 and the ground is adjusted to 0.2-0.5m. Then remove the wire rope and shackle on the turning lifting ear. The positioning position of the shield block 5 is the front end of the cut ring of the shield block 5 corresponding to the tunnel door position.
7.2 盾体分块6和盾体分块4下井:将履带吊主钩挂在盾体分块6外侧主吊耳上,副钩挂在盾体分块4的外侧主吊耳上,主、副钩同时起吊,实现盾体分块6和分块4入井7.2 Lowering shield block 6 and shield block 4 into the well: Hang the main hook of the crawler crane on the main lifting lug outside shield block 6, and hang the auxiliary hook on the main lifting lug outside shield block 4. Lift the main and auxiliary hooks at the same time to lower shield block 6 and block 4 into the well.
所述步骤10中第二部分盾构机吊装下井还包括如下步骤:The second part of the shield machine hoisting down the well in step 10 also includes the following steps:
10.1 盾体分块3、盾体分块7下井:履带吊主钩挂在盾体分块3外侧主吊耳上,副钩挂在盾体分块3的外侧主吊耳上,同时起吊,在底部架设始发基座,并在始发基座上用胎架及千斤顶进行支撑,以防止盾体分块侧滑,10.1 Shield block 3 and shield block 7 are lowered into the well: the main hook of the crawler crane is hung on the main lifting lug outside the shield block 3, and the auxiliary hook is hung on the main lifting lug outside the shield block 3. They are lifted at the same time, and the starting base is set up at the bottom, and the starting base is supported by a tire frame and a jack to prevent the shield block from sliding sideways.
10.2 盾体分块2、盾体分块8下井:履带吊主、副钩同时起吊,将盾体分块2、盾体分块8入井;10.2 Lowering shield block 2 and shield block 8 into the well: The main and auxiliary hooks of the crawler crane are lifted simultaneously to lower shield block 2 and shield block 8 into the well;
10.3 盾体分块1下井:履带吊主钩挂在盾体分块1外侧主吊耳上,履带吊副钩挂在盾体分块1的外侧主吊耳上,主、副钩同时起吊,将盾体分块1入井。10.3 Lowering shield block 1 into the well: The main hook of the crawler crane is hung on the main lifting lug outside the shield block 1, and the auxiliary hook of the crawler crane is hung on the main lifting lug outside the shield block 1. The main and auxiliary hooks are lifted at the same time to lower the shield block 1 into the well.
履带吊的两条履下铺设10块路基板6,路基板6的方向沿掘进方向设计。Ten roadbed plates 6 are laid under the two crawlers of the crawler crane, and the direction of the roadbed plates 6 is designed along the excavation direction.
基板的底部设有带动其抬升的升降装置。A lifting device is arranged at the bottom of the base plate to lift it.
一种辅助起吊装置,使用上述的大直径盾构机吊装下井组装施工方法,包括吊钩,吊钩下方设有滑轮,吊装钢缆穿过滑轮,滑轮包括内轮1和外轮4,内轮1和外轮4之间安装有y字形垫圈2,y字形垫圈2中空连接气管3一端,气管3的另一端连接气源,气管3上设置阀门。An auxiliary lifting device is used for the above-mentioned large-diameter shield machine lifting and lowering into the well assembly construction method, comprising a hook, a pulley is arranged under the hook, the lifting steel cable passes through the pulley, the pulley comprises an inner wheel 1 and an outer wheel 4, a Y-shaped washer 2 is installed between the inner wheel 1 and the outer wheel 4, the Y-shaped washer 2 is hollow and connected to one end of an air pipe 3, the other end of the air pipe 3 is connected to an air source, and a valve is arranged on the air pipe 3.
y字形垫圈2旁设有辅助定位环5。An auxiliary positioning ring 5 is provided beside the Y-shaped gasket 2 .
升降装置包括升降机构8和磁吸块7,升降机构8的端部和磁吸块7间电磁吸引。The lifting device comprises a lifting mechanism 8 and a magnetic attraction block 7 , and electromagnetic attraction is generated between the end of the lifting mechanism 8 and the magnetic attraction block 7 .
辅助起吊装置在工作过程中,首先,在履带吊的两条履带下方沿掘进方向铺设路基板,以提供稳定的支撑,确保履带吊在作业时的稳定性,通过升降机构8控制磁吸块7的垂直移动,路基板6不同的抬升高度,适应不同位置的吊装需求。吊钩通过滑轮连接钢缆,滑轮间安装的y字形垫圈2作为结构支撑,并通过连接气管3与气源相连。气管3上的阀门用于控制气压,以调节y字形垫圈2内部的压力,y字形垫圈2发挥缓冲作用,减少起吊过程中的振动和冲击,确保在吊装过程中的稳定性,辅助定位环5用于进一步精确调整y字形垫圈2的位置。During the operation of the auxiliary lifting device, first, a roadbed is laid under the two crawlers of the crawler crane along the excavation direction to provide stable support and ensure the stability of the crawler crane during operation. The vertical movement of the magnetic block 7 is controlled by the lifting mechanism 8, and the roadbed 6 has different lifting heights to meet the lifting requirements of different positions. The hook is connected to the steel cable through a pulley. The Y-shaped washer 2 installed between the pulleys serves as a structural support and is connected to the air source through a connecting air pipe 3. The valve on the air pipe 3 is used to control the air pressure to adjust the pressure inside the Y-shaped washer 2. The Y-shaped washer 2 plays a buffering role to reduce vibration and impact during the lifting process and ensure stability during the lifting process. The auxiliary positioning ring 5 is used to further accurately adjust the position of the Y-shaped washer 2.
尽管已描述了本发明的一些优选实施例,但本领域内的技术人员一旦得知了基本创造性概念,则可对这些实施例作出另外的变更和修改。所以,所附权利要求意欲解释为包括优选实施例以及落入本发明范围的所有变更和修改。Although some preferred embodiments of the present invention have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present invention.
显然,本领域的技术人员可以对本发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本申请权利要求及其等同技术的范围之内,则本发明也意图包含这些改动和变型在内。Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of this application and their equivalents, the present invention is also intended to include these modifications and variations.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202410896106.8A CN118579664A (en) | 2024-07-05 | 2024-07-05 | Large diameter shield machine hoisting and lowering assembly construction method and auxiliary hoisting device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202410896106.8A CN118579664A (en) | 2024-07-05 | 2024-07-05 | Large diameter shield machine hoisting and lowering assembly construction method and auxiliary hoisting device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN118579664A true CN118579664A (en) | 2024-09-03 |
Family
ID=92524818
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202410896106.8A Pending CN118579664A (en) | 2024-07-05 | 2024-07-05 | Large diameter shield machine hoisting and lowering assembly construction method and auxiliary hoisting device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN118579664A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN119409072A (en) * | 2025-01-06 | 2025-02-11 | 中铁九局集团第四工程有限公司 | A method for hoisting a narrow shaft shield machine |
-
2024
- 2024-07-05 CN CN202410896106.8A patent/CN118579664A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN119409072A (en) * | 2025-01-06 | 2025-02-11 | 中铁九局集团第四工程有限公司 | A method for hoisting a narrow shaft shield machine |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111794754B (en) | Pipe piece assembled derrick and construction method thereof | |
CN103726421B (en) | Height and span adjustable track paver for metro construction | |
CN110552703B (en) | Duct piece mounting system applied to shaft construction | |
JP4264470B2 (en) | Bridge girder member erection method and erection device | |
CN118579664A (en) | Large diameter shield machine hoisting and lowering assembly construction method and auxiliary hoisting device | |
CN114542153B (en) | A mining hydraulic support installation and removal device and installation and removal method | |
CN110645004B (en) | Method for turning shield machine trolley in negative two layers of operated station | |
CN113818478B (en) | Overweight prefabricated pipe gallery installation system and construction method thereof | |
CN213169974U (en) | Horizontal transportation and translation tool for large equipment in factory building | |
CN116281606A (en) | Shield tunneling machine hanging assembling method | |
CN108396749B (en) | Installation system and installation method of steel support in foundation pit | |
JP4346194B2 (en) | Carriage and equipment for installing concrete blocks on slopes | |
CN203684019U (en) | Height and span adjustable track laying machine for subway construction | |
CN114135325A (en) | Equipment and method for assembling tunnel inner arch steel structure | |
CN212712395U (en) | Split mounting type hanger rail portal frame for subway tunnel scattered-laying frame rail construction | |
JP4489872B2 (en) | Bridge erection method and apparatus | |
CN118728422A (en) | A method for installing a template trolley for a high-altitude TBM rock burst tunnel | |
CN112938773A (en) | Installation method and installation system of underground engineering segment and installation crane | |
CN114622919B (en) | A construction method for shield machine splitting down the shaft and assembling through the station | |
CN114893221A (en) | Tunnel primary support steel arch mounting device and mounting method thereof | |
CN114481724A (en) | Transport track quick dismantling system for shield construction | |
CN214780349U (en) | Installation system and installation crane for underground engineering segments | |
CN212687392U (en) | Cable crane hoisting device for bridge erection | |
CN2520321Y (en) | Wellhead apparatus hoisting device and special transport frame | |
CN220828258U (en) | Segment descending transportation device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |