CN117822453A - Water positioning method for pressure-bearing pontoon of floating bridge - Google Patents

Water positioning method for pressure-bearing pontoon of floating bridge Download PDF

Info

Publication number
CN117822453A
CN117822453A CN202410014642.0A CN202410014642A CN117822453A CN 117822453 A CN117822453 A CN 117822453A CN 202410014642 A CN202410014642 A CN 202410014642A CN 117822453 A CN117822453 A CN 117822453A
Authority
CN
China
Prior art keywords
buoy
steel pipe
platform
pipe piles
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202410014642.0A
Other languages
Chinese (zh)
Other versions
CN117822453B (en
Inventor
汪来发
李业勋
时蓓玲
蒋建荣
徐立新
黎亚舟
王璇
邹赐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Third Harbor Engineering Co Ltd
Original Assignee
CCCC Third Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Third Harbor Engineering Co Ltd filed Critical CCCC Third Harbor Engineering Co Ltd
Priority to CN202410014642.0A priority Critical patent/CN117822453B/en
Publication of CN117822453A publication Critical patent/CN117822453A/en
Application granted granted Critical
Publication of CN117822453B publication Critical patent/CN117822453B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/14Floating bridges, e.g. pontoon bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种浮桥承压浮筒的水上定位方法,包括:步骤一,搭设座底平台和靠泊墩;步骤二,利用拖轮将浮筒拖行至座底平台附近;步骤三,通过座底平台上的四个平台卷扬机和靠泊墩上的靠泊墩卷扬机,完成浮筒的初定位;步骤四,向浮筒内注入压载水,使浮筒下沉;步骤五,将浮筒坐落在座底平台上;步骤六,启动座底平台上的一对纵向千斤顶和两对横向千斤顶,进行浮筒的平面位置的精调;步骤七,在浮筒上依次进行墩身接高工序以及墩身与主梁连接工序后,先利用水泵抽出浮筒内的压载水,使浮筒上浮,再利用拖轮将浮筒连同浮筒上的墩身和主梁一起拖离座底平台的工作区域。本发明能确保浮筒在水中的稳定性,便于后续浮筒与墩身以及墩身与主梁对接。

The invention discloses a method for positioning a floating bridge pressure buoy on water, comprising: step one, setting up a bottom platform and a berthing pier; step two, using a tugboat to drag the buoy to the vicinity of the bottom platform; step three, completing the initial positioning of the buoy through four platform winches on the bottom platform and the berthing pier winches on the berthing pier; step four, injecting ballast water into the buoy to sink the buoy; step five, seating the buoy on the bottom platform; step six, starting a pair of longitudinal jacks and two pairs of transverse jacks on the bottom platform to fine-tune the plane position of the buoy; step seven, after sequentially performing the pier body height connection process and the pier body and main beam connection process on the buoy, first use a water pump to pump out the ballast water in the buoy to float the buoy, and then use a tugboat to drag the buoy together with the pier body and the main beam on the buoy away from the working area of the bottom platform. The invention can ensure the stability of the buoy in water, and facilitate the subsequent docking of the buoy with the pier body and the pier body with the main beam.

Description

一种浮桥承压浮筒的水上定位方法A method for positioning floating bridge pressure buoy on water

技术领域Technical Field

本发明涉及一种浮桥承压浮筒的水上定位方法。The invention relates to a method for positioning a floating bridge pressure buoy on water.

背景技术Background technique

近30年,浮桥开始应用到现代基础设施建设中来,其技术得到快速发展,并逐渐趋于成熟,可以作为现代基础设施的重要组成部分。尽管如此,与包括斜拉桥和悬索桥在内的陆上桥梁相比,目前浮桥的资料还是非常的有限,尤其是浮桥的施工记录、环境条件、耐久性、运行和性能方面的资料。目前,全世界长浮桥的数量非常有限,仅有20座左右。In the past 30 years, floating bridges have been applied to modern infrastructure construction. Their technology has developed rapidly and gradually matured, and can be used as an important part of modern infrastructure. However, compared with land bridges including cable-stayed bridges and suspension bridges, the current data on floating bridges is still very limited, especially the data on construction records, environmental conditions, durability, operation and performance of floating bridges. At present, the number of long floating bridges in the world is very limited, only about 20.

国外已建成的浮桥大多为连续式浮筒结构,这种类型的浮桥下部的方形浮筒首尾连接形成连续式浮体结构,浮筒上部可直接承载车辆交通荷载,也可设置桥墩或框架结构等以提升桥面标高。Most of the floating bridges built abroad are continuous pontoon structures. The square pontoons at the bottom of this type of floating bridge are connected end to end to form a continuous floating structure. The upper part of the pontoons can directly bear vehicle traffic loads, and piers or frame structures can also be set up to increase the bridge deck elevation.

在现有的浮桥施工过程中,一般都是采用拼接式结构,在浮桥单体之间设置有浮桥连接件,浮桥连接件将浮桥单体相互对接,构搭成整体的浮桥结构;由于钢结构的浮桥对接精度要求较高,即水上钢结构的浮筒与墩身对接以及墩身与主梁对接时,对浮筒的定位精度要求高。而浮筒处于漂浮状态,定位难度更大。因此如何确保浮筒在水中的稳定性是一个亟待解决的关键问题。In the existing floating bridge construction process, a splicing structure is generally used. A floating bridge connector is set between the floating bridge units. The floating bridge connector connects the floating bridge units to each other to form an integral floating bridge structure. Since the docking accuracy of the steel structure floating bridge is high, that is, when the floating buoy of the water steel structure is docked with the pier body and the pier body is docked with the main beam, the positioning accuracy of the floating buoy is required to be high. The floating buoy is in a floating state, and the positioning is more difficult. Therefore, how to ensure the stability of the buoy in the water is a key issue that needs to be solved urgently.

发明内容Summary of the invention

本发明的目的在于克服现有技术的缺陷而提供一种浮桥承压浮筒的水上定位方法,它能确保浮筒在水中的稳定性,便于后续浮筒与墩身以及墩身与主梁对接。The purpose of the present invention is to overcome the defects of the prior art and provide a method for positioning the pressure buoy of a floating bridge on water, which can ensure the stability of the buoy in water and facilitate the subsequent docking of the buoy with the pier body and the pier body with the main beam.

本发明的目的是这样实现的:一种浮桥承压浮筒的水上定位方法,包括以下步骤:The object of the present invention is achieved by: a method for positioning a floating bridge pressure buoy on water, comprising the following steps:

步骤一,搭设座底平台和靠泊墩,该座底平台包括打设在海床上的钢管桩、固定在钢管桩顶面上的平台板、安装在平台板上的四根平台限位立柱和平面精调机构;所述钢管桩包括左侧钢管桩、右侧钢管桩和第一排横向钢管桩至第六排横向钢管桩;第一排横向钢管桩和第六排横向钢管桩均由两根钢管桩构成,第二排横向钢管桩至第五排横向钢管桩均由三根钢管桩构成;平台板包括一根固定在左侧钢管桩的顶面和右侧钢管桩的顶面之间的中纵向分配梁、两根一一对应地固定在第二至第五排横向钢管桩的前部和后部的边纵向分配梁、一一对应地固定在第一排横向钢管桩的顶面和第六排横向钢管桩的顶面上的第一短横向分配梁和第二短横向分配梁和一一对应地固定在第二排横向钢管桩的顶面、第三排横向钢管桩的顶面、第四排横向钢管桩的顶面和第五排横向钢管桩的顶面上的第一长横向分配梁至第四长横向分配梁;四根平台限位立柱一一对应地安装在第一长横向分配梁至第四长横向分配梁的后部顶面上,该四根平台限位立柱上各自固定一个靠泊柱工作平台,每个靠泊柱工作平台上各自安装一台平台卷扬机;所述平面精调机构包括一对一一对应地安装在所述中纵向分配梁的两头的纵向千斤顶和两对一一对应地安装在第一短横向分配梁的两头和第二短横向分配梁的两头的横向千斤顶;所述靠泊墩设在座底平台的中纵向分配梁的一端头的旁侧并包括固定在海床上的靠泊墩基础、固定在靠泊墩基础上的靠泊墩立柱和一个安装在靠泊墩立柱上的靠泊墩工作平台,该靠泊墩工作平台上安装有靠泊墩卷扬机;Step one, erect a base platform and a berthing pier, the base platform includes steel pipe piles driven on the seabed, a platform plate fixed on the top surface of the steel pipe piles, four platform limit columns and a plane fine adjustment mechanism installed on the platform plate; the steel pipe piles include left-side steel pipe piles, right-side steel pipe piles and the first row of transverse steel pipe piles to the sixth row of transverse steel pipe piles; the first row of transverse steel pipe piles and the sixth row of transverse steel pipe piles are each composed of two steel pipe piles, and the second row of transverse steel pipe piles to the fifth row of transverse steel pipe piles are each composed of three steel pipe piles; the platform plate includes a middle longitudinal distribution beam fixed between the top surface of the left-side steel pipe pile and the top surface of the right-side steel pipe pile, two side longitudinal distribution beams fixed one-to-one to the front and rear of the second to fifth rows of transverse steel pipe piles, a first short transverse distribution beam and a second short transverse distribution beam fixed one-to-one to the top surface of the first row of transverse steel pipe piles and the top surface of the sixth row of transverse steel pipe piles, and a first short transverse distribution beam fixed one-to-one to the top surface of the second row of transverse steel pipe piles, a third row of transverse steel pipe piles, and a fourth row of transverse steel pipe piles. The first long transverse distribution beam to the fourth long transverse distribution beam on the top surface of the steel pipe pile, the top surface of the fourth row of transverse steel pipe piles and the top surface of the fifth row of transverse steel pipe piles; four platform limit columns are installed one by one on the rear top surface of the first long transverse distribution beam to the fourth long transverse distribution beam, and a berthing column working platform is fixed on each of the four platform limit columns, and each berthing column working platform is respectively installed with a platform winch; the plane fine adjustment mechanism includes a one-to-one corresponding longitudinal jack installed at both ends of the middle longitudinal distribution beam and two pairs of one-to-one corresponding transverse jacks installed at both ends of the first short transverse distribution beam and at both ends of the second short transverse distribution beam; the berthing pier is arranged on the side of one end of the middle longitudinal distribution beam of the bottom platform and includes a berthing pier foundation fixed on the seabed, a berthing pier column fixed on the berthing pier foundation and a berthing pier working platform installed on the berthing pier column, and the berthing pier working platform is installed with a berthing pier winch;

步骤二,将浮筒拖行至座底平台附近,浮筒的顶面上设置四根侧揽绳桩、一根端缆绳桩和抽水注水口;浮筒的顶面中心的底墩身的四个角部各自安装一个棱镜;Step 2: Drag the buoy to the vicinity of the bottom platform, set four side rope piles, one end rope pile and a water pumping and injection port on the top surface of the buoy; install a prism at each of the four corners of the bottom pier body at the center of the top surface of the buoy;

步骤三,先将所述靠泊墩卷扬机的钢丝绳和四个平台卷扬机的钢丝绳一一对应地系在浮筒上的端缆绳桩和四根侧揽绳桩上,接着启动四个平台卷扬机,使浮筒停靠在四根平台限位立柱上,再启动靠泊墩卷扬机,使浮筒的一端紧贴在靠泊墩立柱上,完成浮筒的初定位;Step 3: first, tie the wire rope of the berthing pier winch and the wire ropes of the four platform winches to the end cable pile and the four side rope piles on the buoy one by one, then start the four platform winches to make the buoy dock on the four platform limit columns, and then start the berthing pier winch to make one end of the buoy close to the berthing pier column, thus completing the initial positioning of the buoy;

步骤四,在浮筒上安放水泵,向浮筒内注入压载水,同步放松靠泊墩卷扬机和四个平台卷扬机的钢丝绳,使浮筒下沉;Step 4: Place a water pump on the buoy to inject ballast water into the buoy, and simultaneously loosen the wire ropes of the berthing pier winch and the four platform winches to sink the buoy;

步骤五,在浮筒沉放过程中测量浮筒的标高,并通过测量浮筒内的水深计算注水量,同时测量浮筒的顶标高;当注水量增加,浮筒的顶标高变化量远小于水深变化时,即判定浮筒已坐落在座底平台上,此时停止注水;Step 5: During the sinking process of the buoy, the elevation of the buoy is measured, and the water injection amount is calculated by measuring the water depth in the buoy, and the top elevation of the buoy is measured at the same time; when the water injection amount increases and the change in the top elevation of the buoy is much smaller than the change in the water depth, it is determined that the buoy has sat on the bottom platform, and water injection is stopped at this time;

步骤六,利用全站仪测量浮筒上的底墩身的四个角部的棱镜,判断浮筒的平面位置偏差,启动座底平台上的一对纵向千斤顶和两对横向千斤顶,进行浮筒的平面位置的精调,并利用全站仪同步复测,直至误差满足规范要求,完成浮筒的精确定位;Step 6: Use the total station to measure the prisms at the four corners of the bottom pier on the pontoon to determine the plane position deviation of the pontoon, start a pair of longitudinal jacks and two pairs of transverse jacks on the bottom platform, fine-tune the plane position of the pontoon, and use the total station to re-measure synchronously until the error meets the specification requirements to complete the precise positioning of the pontoon;

步骤七,在浮筒上依次进行墩身接高工序以及墩身与主梁连接工序后,先利用水泵抽出浮筒内的压载水,使浮筒上浮,再将浮筒连同浮筒上的墩身和主梁一起拖离座底平台的工作区域。Step seven, after carrying out the pier body heightening process and the pier body and main beam connection process on the pontoon, first use a water pump to pump out the ballast water in the pontoon to make the pontoon float, and then drag the pontoon together with the pier body and main beam on the pontoon away from the working area of the base platform.

上述的浮桥承压浮筒的水上定位方法,其中,进行步骤一时,每排横向钢管桩之间均设置横向平联,第一排横向钢管桩至第六排横向钢管桩之间设置纵向平联;四根平台限位立柱之间连接横向平联;每根平台限位立柱的后侧均设有斜撑架。The above-mentioned method for positioning the pressure-bearing buoy of a floating bridge in water, wherein, when performing step one, transverse parallel connections are arranged between each row of transverse steel pipe piles, and longitudinal parallel connections are arranged between the first row of transverse steel pipe piles to the sixth row of transverse steel pipe piles; the transverse parallel connections are connected between the four platform limit columns; and a diagonal brace is arranged on the rear side of each platform limit column.

上述的浮桥承压浮筒的水上定位方法,其中,进行步骤一时,所述靠泊墩基础的平面呈直角三角形并包括三根靠泊墩钢管桩和设在三根靠泊墩钢管桩顶面上的靠泊墩基础平台;所述靠泊墩立柱连接在靠近所述中纵向分配梁的一根靠泊墩钢管桩上,该靠泊墩立柱与靠泊墩基础平台之间设置斜撑架。The above-mentioned method for positioning the pressure-bearing buoy of a floating bridge in water, wherein, when performing step one, the plane of the berthing pier foundation is a right-angled triangle and includes three berthing pier steel pipe piles and a berthing pier foundation platform arranged on the top surface of the three berthing pier steel pipe piles; the berthing pier column is connected to a berthing pier steel pipe pile close to the middle longitudinal distribution beam, and a diagonal brace is arranged between the berthing pier column and the berthing pier foundation platform.

上述的浮桥承压浮筒的水上定位方法,其中,进行步骤五时,浮筒内的水深每隔10cm测量一次。In the above-mentioned method for positioning the pressure-bearing buoy of a floating bridge on water, when performing step five, the water depth in the buoy is measured every 10 cm.

本发明的浮桥承压浮筒的水上定位方法具有以下特点:采用在水上搭设座底平台和靠箔墩,并在座底平台和靠箔墩各自设置卷扬机,将浮筒拖到在座底平台的上方,再通过向浮筒内注入压载水,使浮筒坐落在座底平台上,然后通过设在座底平台上的平面精调机构调节浮筒的平面位置,完成浮筒的精确定位。本发明采用的座底平台和靠泊墩不仅给浮筒提供稳定的支撑,同时防止浮筒被水流冲走或漂浮起来,又能避免对浮筒造成伤害或损坏,便于后续浮筒与墩身以及墩身与主梁对接。The method for positioning the pressure-bearing buoy of a floating bridge on water of the present invention has the following characteristics: a bottom platform and a pier are set up on water, and a winch is set on each of the bottom platform and the pier, the buoy is dragged above the bottom platform, and then ballast water is injected into the buoy so that the buoy is seated on the bottom platform, and then the plane position of the buoy is adjusted by a plane fine adjustment mechanism set on the bottom platform to complete the precise positioning of the buoy. The bottom platform and the pier used in the present invention not only provide stable support for the buoy, but also prevent the buoy from being washed away or floating by the water flow, and can also avoid causing harm or damage to the buoy, so as to facilitate the subsequent docking of the buoy with the pier body and the pier body with the main beam.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1是进行本发明的步骤一时搭设的座底平台的平面图;FIG1 is a plan view of a base platform set up when performing step 1 of the present invention;

图2是图1中的A-A向视图;Fig. 2 is a view in the direction of A-A in Fig. 1;

图3是图1中的B-B向视图;Fig. 3 is a B-B view in Fig. 1;

图4是图1中的C-C向视图;Fig. 4 is a C-C view in Fig. 1;

图5是进行本发明的步骤一时搭设的靠泊墩的立面图;FIG5 is an elevation view of a berthing pier erected during step 1 of the present invention;

图6是进行本发明的步骤二时需要定位的浮筒的平面图;FIG6 is a plan view of a buoy that needs to be positioned when performing step 2 of the present invention;

图7是进行本发明的步骤三时的第一种状态图;FIG7 is a first state diagram when performing step three of the present invention;

图8是进行本发明的步骤三时的第二种状态图。FIG. 8 is a second state diagram when performing step three of the present invention.

具体实施方式Detailed ways

下面将结合附图对本发明作进一步说明。The present invention will be further described below in conjunction with the accompanying drawings.

请参阅图1至图8,本发明的浮桥承压浮筒的水上定位方法,包括以下步骤:Referring to FIGS. 1 to 8 , the method for positioning the floating bridge pressure buoy in water of the present invention comprises the following steps:

步骤一,搭设座底平台1和靠泊墩2,该座底平台1A包括打设在海床上的钢管桩、固定在钢管桩顶面上的平台板、安装在平台板上的四根平台限位立柱15和平面精调机构;其中,Step 1: Set up the base platform 1 and the berthing pier 2. The base platform 1A includes steel pipe piles driven on the seabed, a platform plate fixed on the top of the steel pipe piles, four platform limit columns 15 installed on the platform plate, and a plane fine adjustment mechanism; wherein:

钢管桩包括左侧钢管桩13a、右侧钢管桩13b和第一排横向钢管桩至第六排横向钢管桩131~136;第一排横向钢管桩131和第六排横向钢管桩136均由两根钢管桩构成,第二排横向钢管桩132至第五排横向钢管桩135均由三根钢管桩构成;第一排横向钢管桩131至第六排横向钢管桩136之间设置纵向平联;每排横向钢管桩之间均设置横向平联;The steel pipe piles include a left steel pipe pile 13a, a right steel pipe pile 13b and first to sixth rows of transverse steel pipe piles 131-136; the first row of transverse steel pipe piles 131 and the sixth row of transverse steel pipe piles 136 are each composed of two steel pipe piles, and the second row of transverse steel pipe piles 132 to the fifth row of transverse steel pipe piles 135 are each composed of three steel pipe piles; longitudinal parallel connections are arranged between the first row of transverse steel pipe piles 131 to the sixth row of transverse steel pipe piles 136; transverse parallel connections are arranged between each row of transverse steel pipe piles;

平台板包括一根固定在左侧钢管桩的顶面和右侧钢管桩的顶面之间的中纵向分配梁140、两根一一对应地固定在第二排横向钢管桩132至第五排横向钢管桩135的前部和后部的边纵向分配梁141、一一对应地固定在第一排横向钢管桩131的顶面和第六排横向钢管桩136的顶面上的第一短横向分配梁142和第二短横向分配梁143和一一对应地固定在第二排横向钢管桩132的顶面、第三排横向钢管桩133的顶面、第四排横向钢管桩134的顶面和第五排横向钢管桩135的顶面上的第一长横向分配梁144至第四长横向分配梁147;The platform plate includes a middle longitudinal distribution beam 140 fixed between the top surfaces of the left steel pipe piles and the top surfaces of the right steel pipe piles, two side longitudinal distribution beams 141 fixed one-to-one to the front and rear parts of the second row of transverse steel pipe piles 132 to the fifth row of transverse steel pipe piles 135, a first short transverse distribution beam 142 and a second short transverse distribution beam 143 fixed one-to-one to the top surfaces of the first row of transverse steel pipe piles 131 and the sixth row of transverse steel pipe piles 136, and a first long transverse distribution beam 144 to a fourth long transverse distribution beam 147 fixed one-to-one to the top surfaces of the second row of transverse steel pipe piles 132, the third row of transverse steel pipe piles 133, the fourth row of transverse steel pipe piles 134 and the fifth row of transverse steel pipe piles 135;

四根平台限位立柱15一一对应地安装在第一长横向分配梁144至第四长横向分配梁147的后部顶面上,四根平台限位立柱15之间连接横向平联,每根平台限位立柱15的后侧均设有斜撑架;该四根平台限位立柱15上各自固定一个靠泊柱工作平台150,每个靠泊柱工作平台150上各自安装一台平台卷扬机16;Four platform limit columns 15 are installed one by one on the top surfaces of the rear parts of the first long transverse distribution beam 144 to the fourth long transverse distribution beam 147. The four platform limit columns 15 are connected by transverse parallel connection, and a diagonal support frame is provided on the rear side of each platform limit column 15; a berthing column working platform 150 is fixed on each of the four platform limit columns 15, and each berthing column working platform 150 is installed with a platform winch 16;

平面精调机构包括一对一一对应地安装在中纵向分配梁140的两头的纵向千斤顶17和两对一一对应地安装在第一短横向分配梁142的两头和第二短横向分配梁143的两头的横向千斤顶18(见图1至图4);The plane fine adjustment mechanism includes a longitudinal jack 17 installed one-to-one at both ends of the middle longitudinal distribution beam 140 and two pairs of transverse jacks 18 installed one-to-one at both ends of the first short transverse distribution beam 142 and the second short transverse distribution beam 143 (see Figures 1 to 4);

靠泊墩2设在座底平台1的中纵向分配梁140的右端头的旁侧并包括固定在海床上的靠泊墩基础20、固定在靠泊墩基础20上的靠泊墩立柱21和一个安装在靠泊墩立柱21上的靠泊墩工作平台210,该靠泊墩工作平台210上安装有靠泊墩卷扬机22;靠泊墩基础20的平面呈直角三角形并包括三根靠泊墩钢管桩和设在三根靠泊墩钢管桩顶面上的靠泊墩基础平台;靠泊墩立柱21连接在靠近中纵向分配梁140的一根靠泊墩钢管桩上,该靠泊墩立柱21与靠泊墩基础平台之间设置斜撑架(见图1和图5);The berthing pier 2 is arranged beside the right end of the middle longitudinal distribution beam 140 of the bottom platform 1 and comprises a berthing pier foundation 20 fixed on the seabed, a berthing pier column 21 fixed on the berthing pier foundation 20 and a berthing pier working platform 210 installed on the berthing pier column 21, and a berthing pier winch 22 is installed on the berthing pier working platform 210; the berthing pier foundation 20 is in a right triangle plane and comprises three berthing pier steel pipe piles and a berthing pier foundation platform arranged on the top surface of the three berthing pier steel pipe piles; the berthing pier column 21 is connected to a berthing pier steel pipe pile close to the middle longitudinal distribution beam 140, and a diagonal brace is arranged between the berthing pier column 21 and the berthing pier foundation platform (see Figures 1 and 5);

步骤二,利用拖轮将浮筒3拖行至座底平台1附近,浮筒3的顶面上设置一根端缆绳桩31、四根侧揽绳桩32和抽水注水口33;浮筒3的顶面中心的底墩身30的四个角部各自安装一个棱镜34,用于定位测量(见图6);Step 2: Use a tugboat to tow the buoy 3 to the vicinity of the bottom platform 1. An end cable pile 31, four side cable piles 32 and a water pumping and injection port 33 are arranged on the top surface of the buoy 3; a prism 34 is respectively installed at the four corners of the bottom pier 30 at the center of the top surface of the buoy 3 for positioning measurement (see FIG. 6 );

步骤三,先将靠泊墩卷扬机22的钢丝绳和四个平台卷扬机16的钢丝绳一一对应地系在浮筒3上的端缆绳桩31和四根侧揽绳桩32上,接着启动四个平台卷扬机16,使浮筒3停靠在四根平台限位立柱15上(见图7),再启动靠泊墩卷扬机22,使浮筒3的右端紧贴在靠泊墩立柱21上,完成浮筒3的初定位(见图8);Step 3: first, tie the steel wire rope of the berthing pier winch 22 and the steel wire ropes of the four platform winches 16 to the end cable pile 31 and the four side rope piles 32 on the buoy 3 in a one-to-one correspondence, then start the four platform winches 16 to make the buoy 3 dock on the four platform limit columns 15 (see Figure 7), and then start the berthing pier winch 22 to make the right end of the buoy 3 close to the berthing pier column 21, completing the initial positioning of the buoy 3 (see Figure 8);

步骤四,在浮筒3上安放水泵,向浮筒3内注入压载水,同步放松靠泊墩卷扬机22和四个平台卷扬机16的钢丝绳,使浮筒3下沉;Step 4: Place a water pump on the buoy 3, inject ballast water into the buoy 3, and simultaneously loosen the wire ropes of the berthing pier winch 22 and the four platform winches 16 to sink the buoy 3;

步骤五,在浮筒沉放过程中测量浮筒的标高,并通过测量浮筒内的水深计算注水量,浮筒内的水深每隔10cm测量一次,同时测量浮筒的顶标高;当注水量增加,浮筒的顶标高变化量远小于水深变化时,即判定浮筒已坐落在座底平台1上,此时停止注水;Step 5: During the sinking process of the buoy, the elevation of the buoy is measured, and the amount of water injected is calculated by measuring the water depth in the buoy. The water depth in the buoy is measured every 10 cm, and the top elevation of the buoy is measured at the same time. When the amount of water injected increases and the change in the top elevation of the buoy is much smaller than the change in the water depth, it is determined that the buoy has been seated on the bottom platform 1, and water injection is stopped at this time.

步骤六,利用全站仪测量浮筒3上的底墩身30的四个角部的棱镜34,判断浮筒3的平面位置偏差,启动座底平台1上的一对纵向千斤顶17和两对横向千斤顶18,进行浮筒3的平面位置的精调,并利用全站仪同步复测,直至误差满足规范要求,完成浮筒3的精确定位;Step 6: Use the total station to measure the prisms 34 at the four corners of the bottom pier 30 on the pontoon 3, determine the plane position deviation of the pontoon 3, start a pair of longitudinal jacks 17 and two pairs of transverse jacks 18 on the bottom platform 1, fine-tune the plane position of the pontoon 3, and use the total station to synchronously re-measure until the error meets the specification requirements, and complete the precise positioning of the pontoon 3;

步骤七,完成在浮筒3上依次进行墩身接高工序以及墩身与主梁连接工序后,先利用水泵抽出浮筒3内的压载水,使浮筒3上浮,再利用拖轮将浮筒连同浮筒上的墩身和主梁一起拖离座底平台的工作区域。Step seven, after completing the pier body heightening process and the pier body and main beam connection process on the pontoon 3, first use a water pump to pump out the ballast water in the pontoon 3 to make the pontoon 3 float, and then use a tugboat to tow the pontoon together with the pier body and main beam on the pontoon away from the working area of the base platform.

以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变型,因此所有等同的技术方案也应该属于本发明的范畴,应由各权利要求所限定。The above embodiments are only used to illustrate the present invention, rather than to limit the present invention. Those skilled in the relevant technical field may make various changes or modifications without departing from the spirit and scope of the present invention. Therefore, all equivalent technical solutions should also belong to the scope of the present invention and should be defined by the claims.

Claims (4)

1.一种浮桥承压浮筒的水上定位方法,其特征在于,所述定位方法包括以下步骤:1. A method for positioning a floating bridge pressure buoy on water, characterized in that the positioning method comprises the following steps: 步骤一,搭设座底平台和靠泊墩,该座底平台包括打设在海床上的钢管桩、固定在钢管桩顶面上的平台板、安装在平台板上的四根平台限位立柱和平面精调机构;所述钢管桩包括左侧钢管桩、右侧钢管桩和第一排横向钢管桩至第六排横向钢管桩;第一排横向钢管桩和第六排横向钢管桩均由两根钢管桩构成,第二排横向钢管桩至第五排横向钢管桩均由三根钢管桩构成;平台板包括一根固定在左侧钢管桩的顶面和右侧钢管桩的顶面之间的中纵向分配梁、两根一一对应地固定在第二至第五排横向钢管桩的前部和后部的边纵向分配梁、一一对应地固定在第一排横向钢管桩的顶面和第六排横向钢管桩的顶面上的第一短横向分配梁和第二短横向分配梁和一一对应地固定在第二排横向钢管桩的顶面、第三排横向钢管桩的顶面、第四排横向钢管桩的顶面和第五排横向钢管桩的顶面上的第一长横向分配梁至第四长横向分配梁;四根平台限位立柱一一对应地安装在第一长横向分配梁至第四长横向分配梁的后部顶面上,该四根平台限位立柱上各自固定一个靠泊柱工作平台,每个靠泊柱工作平台上各自安装一台平台卷扬机;所述平面精调机构包括一对一一对应地安装在所述中纵向分配梁的两头的纵向千斤顶和两对一一对应地安装在第一短横向分配梁的两头和第二短横向分配梁的两头的横向千斤顶;所述靠泊墩设在座底平台的中纵向分配梁的一端头的旁侧并包括固定在海床上的靠泊墩基础、固定在靠泊墩基础上的靠泊墩立柱和一个安装在靠泊墩立柱上的靠泊墩工作平台,该靠泊墩工作平台上安装有靠泊墩卷扬机;Step one, erect a base platform and a berthing pier, the base platform includes steel pipe piles driven on the seabed, a platform plate fixed on the top surface of the steel pipe piles, four platform limit columns and a plane fine adjustment mechanism installed on the platform plate; the steel pipe piles include left-side steel pipe piles, right-side steel pipe piles and the first row of transverse steel pipe piles to the sixth row of transverse steel pipe piles; the first row of transverse steel pipe piles and the sixth row of transverse steel pipe piles are each composed of two steel pipe piles, and the second row of transverse steel pipe piles to the fifth row of transverse steel pipe piles are each composed of three steel pipe piles; the platform plate includes a middle longitudinal distribution beam fixed between the top surface of the left-side steel pipe pile and the top surface of the right-side steel pipe pile, two side longitudinal distribution beams fixed one-to-one to the front and rear of the second to fifth rows of transverse steel pipe piles, a first short transverse distribution beam and a second short transverse distribution beam fixed one-to-one to the top surface of the first row of transverse steel pipe piles and the top surface of the sixth row of transverse steel pipe piles, and a first short transverse distribution beam fixed one-to-one to the top surface of the second row of transverse steel pipe piles, a third row of transverse steel pipe piles, and a fourth row of transverse steel pipe piles. The first long transverse distribution beam to the fourth long transverse distribution beam on the top surface of the steel pipe pile, the top surface of the fourth row of transverse steel pipe piles and the top surface of the fifth row of transverse steel pipe piles; four platform limit columns are installed one by one on the rear top surface of the first long transverse distribution beam to the fourth long transverse distribution beam, and a berthing column working platform is fixed on each of the four platform limit columns, and each berthing column working platform is respectively installed with a platform winch; the plane fine adjustment mechanism includes a one-to-one corresponding longitudinal jack installed at both ends of the middle longitudinal distribution beam and two pairs of one-to-one corresponding transverse jacks installed at both ends of the first short transverse distribution beam and at both ends of the second short transverse distribution beam; the berthing pier is arranged on the side of one end of the middle longitudinal distribution beam of the bottom platform and includes a berthing pier foundation fixed on the seabed, a berthing pier column fixed on the berthing pier foundation and a berthing pier working platform installed on the berthing pier column, and the berthing pier working platform is installed with a berthing pier winch; 步骤二,将浮筒拖行至座底平台附近,浮筒的顶面上设置四根侧揽绳桩、一根端缆绳桩和抽水注水口;浮筒的顶面中心的底墩身的四个角部各自安装一个棱镜;Step 2: Drag the buoy to the vicinity of the bottom platform, set four side rope piles, one end rope pile and a water pumping and injection port on the top surface of the buoy; install a prism at each of the four corners of the bottom pier body at the center of the top surface of the buoy; 步骤三,先将所述靠泊墩卷扬机的钢丝绳和四个平台卷扬机的钢丝绳一一对应地系在浮筒上的端缆绳桩和四根侧揽绳桩上,接着启动四个平台卷扬机,使浮筒停靠在四根平台限位立柱上,再启动靠泊墩卷扬机,使浮筒的一端紧贴在靠泊墩立柱上,完成浮筒的初定位;Step 3: first, tie the wire rope of the berthing pier winch and the wire ropes of the four platform winches to the end cable pile and the four side rope piles on the buoy one by one, then start the four platform winches to make the buoy dock on the four platform limit columns, and then start the berthing pier winch to make one end of the buoy close to the berthing pier column, thus completing the initial positioning of the buoy; 步骤四,在浮筒上安放水泵,向浮筒内注入压载水,同步放松靠泊墩卷扬机和四个平台卷扬机的钢丝绳,使浮筒下沉;Step 4: Place a water pump on the buoy to inject ballast water into the buoy, and simultaneously loosen the wire ropes of the berthing pier winch and the four platform winches to sink the buoy; 步骤五,在浮筒沉放过程中测量浮筒的标高,并通过测量浮筒内的水深计算注水量,同时测量浮筒的顶标高;当注水量增加,浮筒的顶标高变化量远小于水深变化时,即判定浮筒已坐落在座底平台上,此时停止注水;Step 5: During the sinking process of the buoy, the elevation of the buoy is measured, and the water injection amount is calculated by measuring the water depth in the buoy, and the top elevation of the buoy is measured at the same time; when the water injection amount increases and the change in the top elevation of the buoy is much smaller than the change in the water depth, it is determined that the buoy has sat on the bottom platform, and water injection is stopped at this time; 步骤六,利用全站仪测量浮筒上的底墩身的四个角部的棱镜,判断浮筒的平面位置偏差,启动座底平台上的一对纵向千斤顶和两对横向千斤顶,进行浮筒的平面位置的精调,并利用全站仪同步复测,直至误差满足规范要求,完成浮筒的精确定位;Step 6: Use the total station to measure the prisms at the four corners of the bottom pier on the pontoon to determine the plane position deviation of the pontoon, start a pair of longitudinal jacks and two pairs of transverse jacks on the bottom platform, fine-tune the plane position of the pontoon, and use the total station to re-measure synchronously until the error meets the specification requirements to complete the precise positioning of the pontoon; 步骤七,在浮筒上依次进行墩身接高工序以及墩身与主梁连接工序后,先利用水泵抽出浮筒内的压载水,使浮筒上浮,再将浮筒连同浮筒上的墩身和主梁一起拖离座底平台的工作区域。Step seven, after carrying out the pier body heightening process and the pier body and main beam connection process on the pontoon, first use a water pump to pump out the ballast water in the pontoon to make the pontoon float, and then drag the pontoon together with the pier body and main beam on the pontoon away from the working area of the base platform. 2.根据权利要求1所述的浮桥承压浮筒的水上定位方法,其特征在于,进行步骤一时,每排横向钢管桩之间均设置横向平联,第一排横向钢管桩至第六排横向钢管桩之间设置纵向平联;四根平台限位立柱之间连接横向平联;每根平台限位立柱的后侧均设有斜撑架。2. The method for positioning the pressure-bearing buoy of a floating bridge in water according to claim 1 is characterized in that, when performing step one, transverse parallel connections are arranged between each row of transverse steel pipe piles, and longitudinal parallel connections are arranged between the first row of transverse steel pipe piles to the sixth row of transverse steel pipe piles; the transverse parallel connections are connected between the four platform limit columns; and a diagonal brace is arranged on the rear side of each platform limit column. 3.根据权利要求1所述的浮桥承压浮筒的水上定位方法,其特征在于,进行步骤一时,所述靠泊墩基础的平面呈直角三角形并包括三根靠泊墩钢管桩和设在三根靠泊墩钢管桩顶面上的靠泊墩基础平台;所述靠泊墩立柱连接在靠近所述中纵向分配梁的一根靠泊墩钢管桩上,该靠泊墩立柱与靠泊墩基础平台之间设置斜撑架。3. The method for positioning a floating bridge pressure buoy in water according to claim 1 is characterized in that, when performing step one, the plane of the berthing pier foundation is a right triangle and includes three berthing pier steel pipe piles and a berthing pier foundation platform arranged on the top surface of the three berthing pier steel pipe piles; the berthing pier column is connected to a berthing pier steel pipe pile close to the middle longitudinal distribution beam, and a diagonal brace is arranged between the berthing pier column and the berthing pier foundation platform. 4.根据权利要求1所述的浮桥承压浮筒的水上定位方法,其特征在于,进行步骤五时,浮筒内的水深每隔10cm测量一次。4. The method for positioning a floating bridge pressure buoy in water according to claim 1, characterized in that when performing step 5, the water depth in the buoy is measured every 10 cm.
CN202410014642.0A 2024-01-04 2024-01-04 Water positioning method for pressure-bearing pontoon of floating bridge Active CN117822453B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202410014642.0A CN117822453B (en) 2024-01-04 2024-01-04 Water positioning method for pressure-bearing pontoon of floating bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202410014642.0A CN117822453B (en) 2024-01-04 2024-01-04 Water positioning method for pressure-bearing pontoon of floating bridge

Publications (2)

Publication Number Publication Date
CN117822453A true CN117822453A (en) 2024-04-05
CN117822453B CN117822453B (en) 2025-07-15

Family

ID=90509341

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202410014642.0A Active CN117822453B (en) 2024-01-04 2024-01-04 Water positioning method for pressure-bearing pontoon of floating bridge

Country Status (1)

Country Link
CN (1) CN117822453B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101016079A (en) * 2007-02-12 2007-08-15 孙正维 Offing temporary floating platform convenient for assembling and storing
CN103015364A (en) * 2012-12-18 2013-04-03 刘张雄 Fully-assembled steel-structure wading basic platform
CN112252157A (en) * 2020-10-23 2021-01-22 湖北工业大学 Non-pile suspension construction temporary bridge
CN212714475U (en) * 2020-05-18 2021-03-16 中铁二十五局集团第四工程有限公司 Underwater bridge construction floating bridge
CN112796320A (en) * 2021-02-02 2021-05-14 中铁十五局集团第一工程有限公司 Movable floating platform on water suitable for accurate construction of deep-water pile foundation
CN213358291U (en) * 2020-04-09 2021-06-04 太湖流域管理局水文局(信息中心) Assembled steel construction landing stage
CN116427303A (en) * 2023-03-28 2023-07-14 广东冠粤路桥有限公司 An amphibious light work platform and its installation method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101016079A (en) * 2007-02-12 2007-08-15 孙正维 Offing temporary floating platform convenient for assembling and storing
CN103015364A (en) * 2012-12-18 2013-04-03 刘张雄 Fully-assembled steel-structure wading basic platform
CN213358291U (en) * 2020-04-09 2021-06-04 太湖流域管理局水文局(信息中心) Assembled steel construction landing stage
CN212714475U (en) * 2020-05-18 2021-03-16 中铁二十五局集团第四工程有限公司 Underwater bridge construction floating bridge
CN112252157A (en) * 2020-10-23 2021-01-22 湖北工业大学 Non-pile suspension construction temporary bridge
CN112796320A (en) * 2021-02-02 2021-05-14 中铁十五局集团第一工程有限公司 Movable floating platform on water suitable for accurate construction of deep-water pile foundation
CN116427303A (en) * 2023-03-28 2023-07-14 广东冠粤路桥有限公司 An amphibious light work platform and its installation method

Also Published As

Publication number Publication date
CN117822453B (en) 2025-07-15

Similar Documents

Publication Publication Date Title
CN100579862C (en) Method and apparatus for launching a ship transversely built on the ground
CN110374008A (en) A method of the erection of cable-stayed bridge steel truss is carried out in marine environment
CN216640288U (en) Tower-passing sliding platform for steel box girder of cable-stayed bridge
CN110055895B (en) Economical and practical steel trestle construction method
CN117802869B (en) A floating push-up assembly method for a floating bridge
CN116163215B (en) Large-section pushing installation method for anchor steel beam in upper cross sea
JP4574273B2 (en) Water structure and its construction method
CN108612049A (en) A kind of bank-protection works construction uses the construction method of Integral Steel sliding-mode structure
CN118029416B (en) Transfer construction method for oversized anti-collision pouring jacket cofferdam
CN117802871B (en) A construction process for an integral floating bridge
CN205046483U (en) A portable construction platform for bridge foundation construction
CN111622091B (en) Stress test method for prefabricated bridge pier
CN212426769U (en) Temporary river channel section support for hoisting steel box girder of upper-span steel structure bridge
CN117779763A (en) A construction platform and construction method for supporting piles of large-span trestle bridges
CN205742125U (en) A kind of work platform for boring
CN117822453A (en) Water positioning method for pressure-bearing pontoon of floating bridge
CN111980049A (en) Foundation device and construction method of deep riverbed mast-type quay crane
CN222948903U (en) High pile wharf steel structure
CN106759089A (en) Simple mudflat wharf based on waste tires and construction method thereof
CN206562592U (en) Simple mudflat wharf based on waste tires
CN102493363A (en) Quick construction method for segment No.0 of continuous beam
CN117802870B (en) Integral water hoisting and assembling method for floating bridge
CN217781787U (en) Device is demolishd to bridge flotation tank steel construction support on water
CN118029268B (en) Hoisting and assembling method for fixed support of floating bridge
CN214687185U (en) Pre-tensioning method double-T-beam assembled prestressed pipe pile tensioning pedestal

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant