CN117803140A - A kind of stadium curved special-shaped metal roof and construction method - Google Patents

A kind of stadium curved special-shaped metal roof and construction method Download PDF

Info

Publication number
CN117803140A
CN117803140A CN202311760258.7A CN202311760258A CN117803140A CN 117803140 A CN117803140 A CN 117803140A CN 202311760258 A CN202311760258 A CN 202311760258A CN 117803140 A CN117803140 A CN 117803140A
Authority
CN
China
Prior art keywords
roof
unit
purlin
keel
stadium
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311760258.7A
Other languages
Chinese (zh)
Inventor
刘朝阳
周玉琦
朱彦航
安振
宋少卿
郭学亚
张健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN202311760258.7A priority Critical patent/CN117803140A/en
Publication of CN117803140A publication Critical patent/CN117803140A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D3/00Roof covering by making use of flat or curved slabs or stiff sheets
    • E04D3/02Roof covering by making use of flat or curved slabs or stiff sheets of plane slabs, slates, or sheets, or in which the cross-section is unimportant
    • E04D3/16Roof covering by making use of flat or curved slabs or stiff sheets of plane slabs, slates, or sheets, or in which the cross-section is unimportant of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/04Roof drainage; Drainage fittings in flat roofs, balconies or the like
    • E04D13/064Gutters
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/16Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure
    • E04D13/1687Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure the insulating material having provisions for roof drainage
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D3/00Roof covering by making use of flat or curved slabs or stiff sheets
    • E04D3/36Connecting; Fastening
    • E04D3/3605Connecting; Fastening of roof covering supported directly by the roof structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

本发明提出一种体育场曲面异形金属屋面,包括多个沿体育场周向设置的屋面单体,所述屋面单体上设置有天沟单元,所述屋面单体包括呈异形曲面的型材屋面单元、耐力板屋面单元、穿孔铝单板屋面单元,所述屋面单体的屋檐处设置有内檐口收边单元;一种体育场曲面异形金属屋面的施工方法,包括步骤S1‑S18。屋面与体育场的主体钢结构可调整连接有檩条、檩托、龙骨,可以适应异性曲面,使屋面安装更加简便和灵活,根据模型对现有耐力板板材和型材龙骨的曲率和贴合度进行分析,基于BIM信息化模型,坐标定位提取,定制软件导出三维坐标,生成现场安装控制坐标,采用BIM信息化模型协同化深化设计、所有构件进行预下料加工,提高加工精度,缩短工期。

The invention proposes a curved special-shaped metal roof for a stadium, which includes a plurality of roof units arranged along the circumference of the stadium. The roof units are provided with gutter units. The roof units include profile roof units with special-shaped curved surfaces. Endurance board roofing units and perforated aluminum veneer roofing units, the eaves of the roofing units are provided with inner eaves edge closing units; a construction method for a stadium curved special-shaped metal roof, including steps S1-S18. The roof and the main steel structure of the stadium are adjustable and connected with purlins, purlin supports and keels, which can adapt to heterogeneous curved surfaces, making the roof installation easier and more flexible. The curvature and fit of the existing endurance boards and profile keels were analyzed based on the model. , based on the BIM information model, coordinate positioning extraction, customized software to export three-dimensional coordinates, generate on-site installation control coordinates, use the BIM information model to collaboratively deepen the design, and pre-cut all components to improve processing accuracy and shorten the construction period.

Description

一种体育场曲面异形金属屋面及施工方法A kind of stadium curved special-shaped metal roof and construction method

技术领域Technical field

本发明属于屋面搭建的技术领域,具体是一种体育场曲面异形金属屋面及施工方法。The invention belongs to the technical field of roof construction, and in particular to a curved special-shaped metal roof of a stadium and a construction method thereof.

背景技术Background technique

体育场通常具有复杂的曲面形状,这要求屋顶或覆盖物必须适应这些异性曲面。金属屋面是一种常见的屋顶类型,因为它们具有耐久性、美观性和抗腐蚀性等优点。然而,将金属屋面安装在异性曲面上是一项挑战性的任务,需要考虑以下技术问题:Stadiums often have complex curved shapes, which requires that the roof or covering must adapt to these heterogeneous curves. Metal roofs are a common roof type because of their durability, aesthetics, and resistance to corrosion. However, installing metal roofs on heterogeneous curved surfaces is a challenging task, and the following technical issues need to be considered:

1、曲面适应性:异性曲面可能具有多个坡度和角度,传统的金属屋面安装方法可能无法适应这些曲线,导致安装问题和可能的漏水;1. Curved surface adaptability: Heterosexual curved surfaces may have multiple slopes and angles, and traditional metal roof installation methods may not be able to adapt to these curves, resulting in installation problems and possible water leakage;

2、结构支撑:为了确保金属屋面的稳固安装,必须考虑曲面下的支撑结构,以及如何调整和定制支撑以适应曲面;2. Structural support: To ensure a stable installation of the metal roof, it is necessary to consider the support structure under the curved surface and how to adjust and customize the support to accommodate the curved surface;

3、防水和密封:曲面金属屋面的接缝和连接点需要特别关注,以确保水密性,避免雨水渗透。3. Waterproofing and sealing: The seams and connection points of curved metal roofs require special attention to ensure water tightness and avoid rainwater penetration.

目前,已有现有技术用于在异形曲面上安装金属屋面,传统的方法是将金属板在现场进行手工加工,以适应曲面形状,但是存在以下问题:At present, there are existing technologies for installing metal roofs on special-shaped curved surfaces. The traditional method is to manually process the metal plates on site to adapt to the shape of the curved surfaces, but there are the following problems:

1、无法保证屋面的整体造型与外形平滑过渡,拟合建筑效果,对表皮分格线及龙骨的流畅性效果较差。多数只能远距离观看,无法使用无人机进行近距离拍摄;1. It is impossible to ensure a smooth transition of the overall shape and appearance of the roof and to match the architectural effect. It has a poor effect on the smoothness of the skin's grid lines and keels. Most can only be viewed from a distance, and drones cannot be used for close-up photography;

2、型材屋面及穿孔铝单板完成面的整体效果、板面整体的平整度、细部分隔的尺寸的平直度存在错缝大小不一的情况,耐力板的分隔尺寸,造型拟合无法保证平滑过渡,由于屋面造型主要是由檩条来控制的,故檩条安装是整个屋面系统安装的基础,其安装的精度将直接影响整个屋面系统的质量,安装精度难以控制;2. The overall effect of the finished surface of the profile roof and perforated aluminum veneer, the overall flatness of the board surface, and the straightness of the size of the detailed partitions are different in size. The partition size and shape fitting of the endurance board cannot be guaranteed. Smooth transition. Since the roof shape is mainly controlled by purlins, purlin installation is the basis for the installation of the entire roof system. The accuracy of its installation will directly affect the quality of the entire roof system, and the installation accuracy is difficult to control;

3、双曲屋面多呈波浪造型,不穿孔铝单板的面板规格种类多,穿孔铝单板穿孔率不同,穿孔样式不统一,加工尺寸多样,出具加工图工作量大,加工速度慢;3. Hyperbolic roofs mostly have a wavy shape, and there are many types of panel specifications for non-perforated aluminum veneers. Perforated aluminum veneers have different perforation rates, non-uniform perforation styles, and various processing sizes. The workload of issuing processing drawings is large and the processing speed is slow;

4、屋面的防水与密封性能得不到保障;4. The waterproof and sealing performance of the roof cannot be guaranteed;

5、穿孔底板为反吊安装,作业人员需要在檩条下班进行安装,屋面底板长度较长,无法使用高空作业车进行安装;屋面高度较高,屋面最高点标高+49.3000m,机械无法进行施工。5. The perforated floor is installed with reverse hanging, and the operators need to install it when the purlins are off duty. The roof floor is too long and cannot be installed with an aerial work vehicle. The roof is very high, and the highest point of the roof is above +49.3000m, so machinery cannot carry out the construction.

因此,如何有效提高体育场屋面的安装效率、质量,保证屋面良好的防水与密封性,提高使用耐久性是亟待解决的技术问题。Therefore, how to effectively improve the installation efficiency and quality of the stadium roof, ensure good waterproofing and sealing of the roof, and improve the durability are technical issues that need to be solved urgently.

发明内容Contents of the invention

针对上述背景技术中的不足,本发明提出一种体育场曲面异形金属屋面及施工方法,解决了体育场屋面的安装效率低、质量差,屋面防水与密封性差的问题。In view of the deficiencies in the above background technology, the present invention proposes a stadium curved special-shaped metal roof and a construction method, which solves the problems of low installation efficiency, poor quality, and poor waterproofing and sealing of the stadium roof.

本申请的技术方案为:The technical solution of this application is:

一种体育场曲面异形金属屋面,包括多个沿体育场周向设置的屋面单体,所述屋面单体上设置有天沟单元,所述屋面单体包括呈异形曲面的型材屋面单元、耐力板屋面单元、穿孔铝单板屋面单元,所述屋面单体的屋檐处设置有内檐口收边单元。A stadium curved special-shaped metal roof, including a plurality of roofing units arranged along the circumference of the stadium. The roofing units are provided with gutter units. The roofing units include profile roofing units with special-shaped curved surfaces and endurance board roofs. unit, a perforated aluminum single plate roof unit, and an inner eaves edge closing unit is provided at the eaves of the roof unit.

进一步地,所述型材屋面单元的下端与所述穿孔铝单板屋面单元的上端相连,所述耐力板屋面单元连接于所述耐力板屋面单元与所述型材屋面单元的左侧或右侧。Further, the lower end of the profile roof unit is connected to the upper end of the perforated aluminum veneer roof unit, and the endurance board roof unit is connected to the left or right side of the endurance board roof unit and the profile roof unit.

进一步地,所述天沟单元包括设置于所述型材屋面单元上的内天沟与外天沟,所述型材屋面单元与穿孔铝单板屋面单元上设置有导水槽,所述内天沟与所述外天沟沿所述屋面单体横向设置,所述导水槽沿所述屋面单体纵向设置。Further, the gutter unit includes an inner gutter and an outer gutter provided on the profile roof unit. The profile roof unit and the perforated aluminum veneer roof unit are provided with water conduits, and the inner gutter and The outer gutter is arranged transversely along the roof unit, and the water guide groove is arranged longitudinally along the roof unit.

进一步地,所述内天沟设置于所述型材屋面单元的屋檐处,所述内檐口收边单元设置于所述内天沟的外部,所述内檐口收边单元包括相连的内檐口龙骨、内檐口铝单板,所述内檐口龙骨与主体钢结构、所述内天沟连接。Further, the inner gutter is arranged at the eaves of the profile roof unit, and the inner eaves edge unit is arranged outside the inner gutter. The inner eaves edge unit includes connected inner eaves keels, Inner cornice aluminum single plate, the inner cornice keel is connected to the main steel structure and the inner gutter.

进一步地,所述型材屋面单元的安装步骤如下:S201:安装檩托一、檩条一;S202:安装铝单板檩托;S203:安装穿孔压型底板;S204:铺设无纺布;S205:铺设吸音棉;S206:安装支撑压型钢板;S207:铺设隔汽膜;S208:铺设岩棉;S209:铺设TPO柔性防水卷材;S2010:安装铝单板主龙骨一;S2011:安装铝单板次龙骨一;S2012:安装铝单板。Further, the installation steps of the profile roof unit are as follows: S201: Install purlin support one and purlin one; S202: Install aluminum veneer purlin support; S203: Install perforated profiled bottom plate; S204: Lay non-woven fabric; S205: Lay Sound-absorbing cotton; S206: Install the supporting profiled steel plate; S207: Lay the vapor barrier film; S208: Lay the rock wool; S209: Lay the TPO flexible waterproof membrane; S2010: Install the aluminum veneer main keel one; S2011: Install the aluminum veneer second Keel 1; S2012: Installation of aluminum veneer.

进一步地,所述耐力板屋面单元的安装步骤如下:S301:安装檩托二、檩条二、龙骨二;S302:安装耐力板;S303:安装压板、扣盖。Further, the installation steps of the endurance board roof unit are as follows: S301: Install the second purlin support, the second purlin, and the second keel; S302: Install the endurance board; S303: Install the pressure plate and buckle cover.

进一步地,所述穿孔铝单板屋面单元的安装步骤如下:S401:安装檩托三、檩条三;S402:安装铝单板龙骨三;S403:安装穿孔铝单板。Further, the installation steps of the perforated aluminum veneer roof unit are as follows: S401: Install purlin support 3 and purlin 3; S402: Install aluminum veneer keel 3; S403: Install perforated aluminum veneer.

一种体育场曲面异形金属屋面的施工方法,包括以下步骤:S1:根据设计图纸使用3D建模软件深化主体钢结构、屋面表皮模型,在模型中进行屋面龙骨建模,设计审核确认后,工厂根据龙骨模型进行预加工、预拼装试验; S2:使用3D扫描技术进行安装点位扫描,对主体钢结构及屋面龙骨点位进行复核,将复核有偏差的点位再次导入模型进行调整;S3:根据最终模型出图,完成各部分的材料加工; S4:内天沟、外天沟、内檐口的龙骨均在地面预拼装,待主体钢结构完成,进行吊装;S5:根据提供的测量基准点、基准线、水准点进行复核,按屋面布置图、主体结构轴线、标高进行全面的测量放线;S6:主体钢结构未提升部分在吊装前先在地面完成屋面檩托的安装工作,主体钢结构已提升部分采用屋面定位进行安装;S7:将型材屋面单元、耐力板屋面单元、穿孔铝单板屋面单元中的主檩条分别与屋面连接、次檩条与主檩条连接;S8:将型材屋面单元中的穿孔压型底板安装在屋面与主檩条之间; S9:在主檩条与次檩条的上部设置行走通道;S10:在穿孔压型底板上铺设无纺布、吸音绵;S11:在主檩条与龙骨之间安装支撑压型钢板;S12:支撑压型钢板上依次铺设隔汽膜、岩棉、TPO柔性防水卷材;S13:在屋面设置临时材料堆放平台,将型材屋面单元、耐力板屋面单元、穿孔铝单板屋面单元中的龙骨均与屋面檩托连接;S14:在已安装好的龙骨上划出中心线,将预制铝单板依据编号图的位置,进行安装;S15:安装耐力板屋面单元中的耐力板;S16:内檐口收边单元的龙骨在地面拼装成单元,吊装到屋面进行连接;S17:在施工过程中,用全站仪对每块预制铝单板的三维坐标放样,在龙骨上标记,要求每块预制铝单板的四个角点与三维坐标放样点重合、与模型中的三维坐标点一致; S18:内天沟与外天沟的龙骨采用地面拼装,再吊至屋面进行连接。A construction method for a stadium curved special-shaped metal roof, including the following steps: S1: Use 3D modeling software to deepen the main steel structure and roof skin model according to the design drawings, and perform roof keel modeling in the model. After the design is reviewed and confirmed, the factory will The keel model undergoes pre-processing and pre-assembly testing; S2: Use 3D scanning technology to scan the installation points, review the main steel structure and roof keel points, and import the deviated points into the model again for adjustment; S3: According to The final model is drawn and the material processing of each part is completed; S4: The keels of the inner gutter, outer gutter, and inner cornice are all pre-assembled on the ground, and they are hoisted after the main steel structure is completed; S5: According to the measurement reference points provided, The reference lines and level points shall be reviewed, and comprehensive measurement and setting-out shall be carried out according to the roof layout plan, main structure axis and elevation; S6: The unlifted part of the main steel structure shall first complete the installation of the roof purlins on the ground before hoisting. The main steel structure The lifted part is installed using roof positioning; S7: Connect the main purlins in the profile roof unit, endurance board roof unit, and perforated aluminum veneer roof unit to the roof, and connect the secondary purlins to the main purlin; S8: Connect the profile roof unit The perforated profiled bottom plate is installed between the roof and the main purlin; S9: Set a walking channel on the upper part of the main purlin and the secondary purlin; S10: Lay non-woven fabrics and sound-absorbing cotton on the perforated profiled bottom plate; S11: Place the main purlin and the secondary purlin Install supporting profiled steel plates between the keels; S12: Lay vapor barrier membrane, rock wool, and TPO flexible waterproofing membranes on the supporting profiled steel plates in sequence; S13: Set up a temporary material storage platform on the roof, and combine the profile roofing units and endurance board roofing units. , The keels in the perforated aluminum veneer roof unit are all connected to the roof purlins; S14: Draw the center line on the installed keel, and install the prefabricated aluminum veneer according to the position of the numbered diagram; S15: Install the endurance board Durable panels in the roof unit; S16: The keels of the inner cornice edge unit are assembled into units on the ground and hoisted to the roof for connection; S17: During the construction process, a total station is used to stake out the three-dimensional coordinates of each prefabricated aluminum single panel , mark on the keel, requiring that the four corner points of each prefabricated aluminum veneer coincide with the three-dimensional coordinate stakeout points and be consistent with the three-dimensional coordinate points in the model; S18: The keels of the inner gutter and the outer gutter are assembled on the ground, and then Lift to the roof for connection.

进一步地,采用三点坐标控制法进行安装,提高安装精度。Furthermore, a three-point coordinate control method is used for installation to improve installation accuracy.

进一步地,所述穿孔压型底板、所述支撑压型钢板在与相邻板材交接时均进行斜切处理,保证搭接处的连接效果。Furthermore, the perforated profiled bottom plate and the support profiled steel plate are all beveled when they are connected with adjacent plates to ensure the connection effect at the overlap.

本发明具体的有益效果包括:Specific beneficial effects of the present invention include:

1、本发明中屋面与体育场的主体钢结构可调整连接有檩条、檩托、龙骨,可以适应异性曲面,使屋面安装更加简便和灵活,在模型上的节点位置进行龙骨的建模工作,安装过程中采用三点坐标控制的方式进行安装,确保安装精度,保证龙骨的流畅性;1. In the present invention, the main steel structure of the roof and the stadium can be adjusted and connected with purlins, purlin supports and keels, which can adapt to heterogeneous curved surfaces, making the roof installation easier and more flexible. The keels are modeled at the node positions on the model and installed. During the installation process, three-point coordinate control is used to ensure installation accuracy and smoothness of the keel;

3、本发明使用3D扫描技术进行安装点位扫描,将点位导入到3d模型内,与模型龙骨进行分析;3. The present invention uses 3D scanning technology to scan the installation points, import the points into the 3D model, and analyze them with the model keel;

4、本发明根据模型对现有耐力板板材和型材龙骨的曲率和贴合度进行分析,明确板材哪些需要热成型哪些需要现场冷弯,对模型进行分析,铝型材为双向弯曲造型,需要对铝型材进行热加工处理,通过模具加工出和耐力板相吻合的造型,确保耐力板和铝型材紧密贴合,起到防水效果;4. The present invention analyzes the curvature and fit of existing endurance boards and profile keels based on the model, and clarifies which plates need to be hot-formed and which need to be cold-bent on site. The model is analyzed. The aluminum profile is a two-way bending shape and needs to be bent. The aluminum profile is heat-processed, and the mold is used to process the shape that matches the endurance board to ensure that the endurance board and aluminum profile are closely adhered to achieve a waterproof effect;

5、本发明采用三维激光扫描仪对项目现场进行逆向,保证天幕与建筑结构的精准定位,为减少项目实施二次拆改成本;5. This invention uses a three-dimensional laser scanner to perform reverse engineering on the project site to ensure the precise positioning of the canopy and the building structure, in order to reduce the cost of secondary demolition and renovation of the project;

6、本发明建立建筑最终外表皮模型,确定屋面、天沟、内檐口的空间位置与主体钢结构的相对位置关系,通过建筑施工图提供的外轮廓断面,结合钢结构壳体模型进行排水分析,对局部区域微调,优化设置天沟,降低渗漏隐患,通过模型计算天沟伸缩缝位置,计算因温度变化产出的应力,防止局部位置应力集中,造成焊缝拉裂,确保流水顺畅性;6. The present invention establishes the final exterior skin model of the building, determines the relative positional relationship between the spatial position of the roof, gutter, and inner cornice and the main steel structure, and performs drainage analysis based on the outer contour section provided by the building construction drawing and combined with the steel structure shell model. , fine-tune local areas, optimize the setting of gutters, and reduce the risk of leakage. Calculate the location of gutter expansion joints through the model, calculate the stress due to temperature changes, prevent stress concentration in local locations and cause weld cracks, and ensure smooth water flow. ;

7、本发明基于BIM信息化模型,坐标定位提取,定制软件导出三维坐标,生成现场安装控制坐标,采用BIM信息化模型协同化深化设计、所有构件进行预下料加工,提高加工精度,缩短工期,验算最不利荷载作用下紧固件抗拔力,保证屋面系统受力性能满足要求;7. This invention is based on the BIM information model, coordinate positioning extraction, customized software to derive three-dimensional coordinates, and generate on-site installation control coordinates. The BIM information model is used to collaboratively deepen the design, and all components are pre-cut and processed to improve processing accuracy and shorten the construction period. , check and calculate the pull-out force of fasteners under the most unfavorable load to ensure that the stress performance of the roof system meets the requirements;

8、本发明中地面预拼装加工操作空间充足,可节约大量人力,且方便对构件室外加工制作精度以及接口能够满足现场的安装需要以及满足规范设计要求进行检查,最大程度地把问题留在地面,及时解决,而不是在现场安装时才发现构件的加工精度问题,影响工期,减少现场安装时的错误调整时间,为工程的整体进度和质量保证创造条件;8. The ground pre-assembly processing operation space in the present invention is sufficient, which can save a lot of manpower, and facilitates inspection of the outdoor processing and manufacturing accuracy of components and the ability of interfaces to meet on-site installation needs and standard design requirements, thus leaving problems on the ground to the greatest extent possible. , solve it in time, instead of only discovering the processing accuracy problem of components during on-site installation, which will affect the construction period, reduce the error adjustment time during on-site installation, and create conditions for the overall progress and quality assurance of the project;

9、本发明最大限度的降低了发生安全事故的可能性。9. The present invention minimizes the possibility of safety accidents.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

为了更清楚地说明本发明实施例,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to explain the embodiments of the present invention more clearly, the drawings needed to be used in the description of the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present invention. For ordinary people in the art, For technical personnel, other drawings can also be obtained based on these drawings without exerting creative work.

图1为本发明整体示意图;Fig. 1 is an overall schematic diagram of the present invention;

图2为本发明中屋面单体示意图1;Figure 2 is a schematic diagram 1 of the roof unit in the present invention;

图3为本发明中屋面单体示意图2;FIG3 is a schematic diagram 2 of a roof unit in the present invention;

图4为本发明中导水槽示意图;Figure 4 is a schematic diagram of the water conduit in the present invention;

图5为测量布控示意图;Figure 5 is a schematic diagram of measurement deployment and control;

图6为内檐口收边单元俯视图;Figure 6 is a top view of the inner cornice edge closing unit;

图7为内檐口收边单元侧视图;Fig. 7 is a side view of the inner cornice edge trimming unit;

图8为铝单板龙骨安装定位平面示意图;Figure 8 is a schematic diagram of the installation and positioning plane of the aluminum veneer keel;

图9a为型材屋面单元、耐力板屋面单元檩条布置图;Figure 9a shows the purlin layout of profile roof units and endurance board roof units;

图9b为穿孔铝单板屋面单元、耐力板屋面单元檩条布置图;Figure 9b shows the purlin layout of the perforated aluminum veneer roof unit and endurance board roof unit;

图10为铝单板独立单元分区示意图;Figure 10 is a schematic diagram of the independent unit partitioning of aluminum veneer;

图11为型材屋面单元中主檩条、次檩条连接示意图;Figure 11 is a schematic diagram of the connection between the main purlins and secondary purlins in the profile roof unit;

图12为耐力板屋面单元中檩托、檩条连接示意图;Figure 12 is a schematic diagram of the connection between purlin supports and purlins in the endurance board roof unit;

图13为穿孔铝单板屋面单元中檩条连接示意图;Figure 13 is a schematic diagram of purlin connections in perforated aluminum veneer roof units;

图14a为屋面底板分区布置示意图1;Figure 14a is a schematic diagram 1 of the partition layout of the roof bottom plate;

图14b为屋面底板分区布置示意图2;Figure 14b is a schematic diagram 2 of the partition arrangement of the roof bottom plate;

图15为屋面底板安装节点示意图;Figure 15 is a schematic diagram of the installation node of the roof base plate;

图16为行走通道示意图;Figure 16 is a schematic diagram of the walking channel;

图17为型材屋面单元的安装步骤1示意图;FIG17 is a schematic diagram of step 1 of installing the profile roof unit;

图18为型材屋面单元的安装步骤2示意图;Figure 18 is a schematic diagram of the installation step 2 of the profile roof unit;

图19为型材屋面单元的安装步骤3示意图;Figure 19 is a schematic diagram of installation step 3 of the profile roof unit;

图20为型材屋面单元的安装步骤4示意图;Figure 20 is a schematic diagram of installation step 4 of the profile roof unit;

图21为型材屋面单元的安装步骤5示意图;Figure 21 is a schematic diagram of installation step 5 of the profile roof unit;

图22为型材屋面单元的安装步骤6示意图;Figure 22 is a schematic diagram of installation step 6 of the profile roof unit;

图23为型材屋面单元的安装步骤7示意图;FIG23 is a schematic diagram of step 7 of installing the profile roof unit;

图24为型材屋面单元的安装步骤8示意图;Figure 24 is a schematic diagram of the installation step 8 of the profile roof unit;

图25为型材屋面单元的安装步骤9示意图;Figure 25 is a schematic diagram of installation step 9 of the profile roof unit;

图26为型材屋面单元的安装步骤10示意图;Figure 26 is a schematic diagram of the installation step 10 of the profile roof unit;

图27为型材屋面单元的安装步骤11示意图;FIG27 is a schematic diagram of the installation step 11 of the profile roof unit;

图28为型材屋面单元的安装步骤12示意图;Figure 28 is a schematic diagram of the installation step 12 of the profile roof unit;

图29为耐力板屋面单元的安装步骤1示意图;Figure 29 is a schematic diagram of the installation step 1 of the endurance board roof unit;

图30为耐力板屋面单元的安装步骤2示意图;Figure 30 is a schematic diagram of the installation step 2 of the endurance board roof unit;

图31为耐力板屋面单元的安装步骤3示意图;Figure 31 is a schematic diagram of the installation step 3 of the endurance board roof unit;

图32为穿孔铝单板屋面单元的安装步骤1示意图;Figure 32 is a schematic diagram of the installation step 1 of the perforated aluminum veneer roof unit;

图33为穿孔铝单板屋面单元的安装步骤2示意图;Figure 33 is a schematic diagram of the installation step 2 of the perforated aluminum veneer roof unit;

图34为穿孔铝单板屋面单元的安装步骤3示意图。FIG. 34 is a schematic diagram of installation step 3 of the perforated aluminum veneer roof unit.

附图标号说明:Explanation of reference numbers:

1、屋面单体;2、型材屋面单元;3、耐力板屋面单元;4、穿孔铝单板屋面单元;5、内檐口收边单元;6、内天沟;7、外天沟;8、导水槽;9、内檐口龙骨;10、内檐口铝单板;11、行走通道;15、檩托一;16、檩条一;17、檩托;18、穿孔压型底板;19、无纺布;20、吸音棉;21、支撑压型钢板;22、隔汽膜;23、岩棉;24、TPO;25、主龙骨一;26、次龙骨一;27、铝单板;31、檩托二;32、檩条二;33、龙骨二;34、耐力板;35、压板;36、扣盖;41、檩托三;42、檩条三;43、龙骨三;44、穿孔铝单板。1. Roofing unit; 2. Profile roofing unit; 3. Durable panel roofing unit; 4. Perforated aluminum veneer roofing unit; 5. Inner cornice edge unit; 6. Inner gutter; 7. External gutter; 8. Guidance channel; 9. Inner cornice keel; 10. Inner cornice aluminum veneer; 11. Walking channel; 15. One purlin support; 16. One purlin support; 17. Purlin support; 18. Perforated profiled bottom plate; 19. Non-woven fabric ; 20. Sound-absorbing cotton; 21. Support profiled steel plate; 22. Steam barrier film; 23. Rock wool; 24. TPO; 25. Main keel one; 26. Secondary keel one; 27. Aluminum veneer; 31. Purlin support Two; 32, purlin two; 33, keel two; 34, endurance board; 35, pressure plate; 36, buckle cover; 41, purlin support three; 42, purlin three; 43, keel three; 44, perforated aluminum veneer.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有付出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without exerting creative efforts fall within the scope of protection of the present invention.

一种体育场曲面异形金属屋面,如图1、图2所示,包括多个沿体育场周向设置的屋面单体1,所述屋面单体1上设置有天沟单元,所述屋面单体1包括呈异形曲面的型材屋面单元2、耐力板屋面单元3、穿孔铝单板屋面单元4,所述屋面单体1的屋檐处设置有内檐口收边单元。A stadium curved special-shaped metal roof, as shown in Figures 1 and 2, includes a plurality of roofing units 1 arranged along the circumference of the stadium. Gutter units are provided on the roofing units 1. The roofing units 1 It includes a profile roof unit 2 with a special-shaped curved surface, a durable board roof unit 3, and a perforated aluminum veneer roof unit 4. The roof unit 1 is provided with an inner eaves edge unit at the eaves.

在上述实施方式的基础上,如图3所示,所述型材屋面单元2的下端与所述穿孔铝单板屋面单元4的上端相连,所述耐力板屋面单元3连接于所述耐力板屋面单元3与所述型材屋面单元2的左侧或右侧。Based on the above embodiment, as shown in Figure 3, the lower end of the profile roof unit 2 is connected to the upper end of the perforated aluminum veneer roof unit 4, and the endurance panel roof unit 3 is connected to the left or right side of the endurance panel roof unit 3 and the profile roof unit 2.

在上述实施方式的基础上,如图3、图4所示,所述天沟单元包括设置于所述型材屋面单元2上的内天沟6与外天沟7,所述型材屋面单元2与穿孔铝单板屋面单元4上设置有导水槽8,所述内天沟6与所述外天沟7沿所述屋面单体1横向设置,所述导水槽8沿所述屋面单体1纵向设置。Based on the above embodiments, as shown in Figures 3 and 4, the gutter unit includes an inner gutter 6 and an outer gutter 7 provided on the profile roof unit 2. The profile roof unit 2 and The perforated aluminum veneer roof unit 4 is provided with a water conduit 8. The inner gutter 6 and the outer gutter 7 are arranged transversely along the roof unit 1, and the water conduit 8 is longitudinally along the roof unit 1. set up.

具体地,内天沟与外天沟使用的是3mm不锈钢天沟,材质奥氏316,体育场各区域不锈钢天沟的截面高度不同,但均为U型截面形式。屋面不锈钢天沟采用工程分段折弯成型,现场焊接组装的形式进行加工。Specifically, the inner and outer gutters use 3mm stainless steel gutters, made of Austenitic 316. The cross-section heights of the stainless steel gutters in various areas of the stadium are different, but they are all U-shaped cross-sections. The stainless steel roof gutter is processed by engineering segmented bending and on-site welding and assembly.

在上述实施方式的基础上,如图6、图7所示,所述内天沟6设置于所述型材屋面单元2的屋檐处,所述内檐口收边单元5设置于所述内天沟6的外部,所述内檐口收边单元5包括相连的内檐口龙骨9、内檐口铝单板10,所述内檐口龙骨9与主体钢结构、所述内天沟6连接。On the basis of the above embodiment, as shown in Figures 6 and 7, the inner gutter 6 is disposed at the eaves of the profile roof unit 2, and the inner eaves edge closing unit 5 is disposed at the inner gutter. 6, the inner cornice edge unit 5 includes a connected inner cornice keel 9 and an inner cornice aluminum single plate 10. The inner cornice keel 9 is connected to the main steel structure and the inner gutter 6.

具体地,体育场主体钢结构为桁架结构,整体造型基本为圆形,直径约270m,主要由18个面积构造相同的屋面单体组成。屋面为双曲弧形不规则屋面,其中屋面内外天沟之间坡度在15%~25%之间,外天沟以外屋面坡度大于45%,屋面最大坡度近乎于90°。Specifically, the main steel structure of the stadium is a truss structure. The overall shape is basically circular with a diameter of about 270m. It is mainly composed of 18 roofing units with the same area and structure. The roof is a hyperbolic arc-shaped irregular roof. The slope between the inner and outer gutter of the roof is between 15% and 25%. The slope of the roof outside the outer gutter is greater than 45%. The maximum slope of the roof is close to 90°.

具体地,型材屋面单元2位置,上部装饰铝单板为平与单曲铝单板,板缝为明缝设计,且装饰铝单板为波浪造型,在铝单板表面有导水槽,雨水顺着装饰铝单板板缝和导水槽位置,进入到单层TPO卷材屋面上部,顺着TPO卷材流入屋面内外不锈钢天沟,通过雨水管排出。体育场耐力板屋面系统,上部为双曲耐力板,雨水顺着耐力板板面,进入到屋面内外天沟,通过雨水管进行排出。Specifically, at the 2 position of the profile roof unit, the upper decorative aluminum veneer is a flat or single-shaped aluminum veneer, the seams of the panels are designed with open seams, and the decorative aluminum veneer is in a wavy shape. There are water channels on the surface of the aluminum veneer so that rainwater can flow smoothly. Follow the seams of the decorative aluminum veneer and the water guide channel, enter the top of the single-layer TPO membrane roof, flow along the TPO membrane into the stainless steel gutters inside and outside the roof, and drain out through the rainwater pipe. The upper part of the stadium endurance board roofing system is a double-curved endurance board. Rainwater flows along the surface of the endurance board, enters the internal and external gutters of the roof, and is discharged through rainwater pipes.

在上述实施方式的基础上,所述型材屋面单元2的安装步骤如下:S201:如图17所示,安装檩托一15、檩条一16;S202:如图18所示,安装铝单板檩托17;S203:如图19所示,安装穿孔压型底板18;S204:如图20所示,铺设无纺布19;S205:如图21所示,铺设吸音棉20;S206:如图22所示,安装支撑压型钢板21;S207:如图23所示,铺设隔汽膜22;S208:如图24所示,铺设岩棉23;S209:如图25所示,铺设TPO柔性防水卷材24;S2010:如图26所示,安装铝单板主龙骨一25;S2011:如图28所示,安装铝单板次龙骨一26;S2012:如图28所示,安装铝单板27。On the basis of the above embodiment, the installation steps of the profile roof unit 2 are as follows: S201: As shown in Figure 17, install the purlin support 15 and the purlin 16; S202: As shown in Figure 18, install the aluminum single plate purlin Support 17; S203: As shown in Figure 19, install the perforated bottom plate 18; S204: As shown in Figure 20, lay the non-woven fabric 19; S205: As shown in Figure 21, lay the sound-absorbing cotton 20; S206: As shown in Figure 22 As shown, install the supporting profiled steel plate 21; S207: As shown in Figure 23, lay the vapor barrier membrane 22; S208: As shown in Figure 24, lay the rock wool 23; S209: As shown in Figure 25, lay the TPO flexible waterproof roll Material 24; S2010: As shown in Figure 26, install the aluminum veneer main keel 125; S2011: As shown in Figure 28, install the aluminum veneer secondary keel 126; S2012: As shown in Figure 28, install the aluminum veneer 27 .

在上述实施方式的基础上,所述耐力板屋面单元3的安装步骤如下:S301:如图29所示,安装檩托二31、檩条二32、龙骨二33;S302:如图30所示,安装耐力板34;S303:如图31所示,安装压板35、扣盖36。On the basis of the above embodiment, the installation steps of the endurance board roof unit 3 are as follows: S301: As shown in Figure 29, install the second purlin 31, the second purlin 32, and the second keel 33; S302: As shown in Figure 30, Install the endurance plate 34; S303: As shown in Figure 31, install the pressure plate 35 and buckle cover 36.

在上述实施方式的基础上,所述穿孔铝单板屋面单元4的安装步骤如下: S401:如图32所示,安装檩托三41、檩条三42;S402:如图33所示,安装铝单板龙骨三43;S403:如图34所示,安装穿孔铝单板44。On the basis of the above embodiment, the installation steps of the perforated aluminum veneer roof unit 4 are as follows: S401: As shown in Figure 32, install the third purlin 41 and the third purlin 42; S402: As shown in Figure 33, install the aluminum Veneer keel three 43; S403: As shown in Figure 34, install the perforated aluminum veneer 44.

具体地,为了屋面具有良好的吸声降噪功能,型材屋面单元2的底板采用0.6mm厚镀铝锌镁穿孔压型板,YX25-210-840型,穿孔率为23%,穿孔直径2.5mm,孔中心距5mm,等边三角形排列。型材屋面单元2的最外层装饰板为不穿孔铝单板,穿孔铝单板屋面单元4采用的是穿孔铝单板,耐力板屋面单元3的耐力板选择8mm后聚碳酸酯实心平板耐力板,板材双面采用共计技术加工UV层,抗UV层厚度为光照面面≥80μm,背光面≥50um,颜色乳白色,具有漫反射功能,透光率为50%±3%,耐力板屋面在一个屋面单体内为双曲造型,板宽度方向在750-1200mm,长度方向最长为5000mm,耐力板均为双曲造型,部分耐力板板面曲率较大,须通过加工成预制弧度,冷弯、热成型来实现造型。内檐口收边单元5采用的是不穿孔铝单板。铝单板弯弧通常采用金属板折弯加工时。弯弧半径应符合设计要求;使用卷板机弯弧必须先弯弧后折边。折边开口的间距必须严格按照15mm、尺寸2-3mm加工,必须保证折边弯弧处无毛刺、凹凸、尖角等缺陷,折边线条光滑顺直。Specifically, in order to ensure that the roof has good sound absorption and noise reduction functions, the bottom plate of the profile roof unit 2 adopts 0.6mm thick aluminum-zinc-magnesium perforated corrugated plate, YX25-210-840 type, with a perforation rate of 23%, a perforation diameter of 2.5mm, a hole center distance of 5mm, and an equilateral triangle arrangement. The outermost decorative plate of the profile roof unit 2 is a non-perforated aluminum veneer, and the perforated aluminum veneer roof unit 4 is a perforated aluminum veneer. The endurance board of the endurance board roof unit 3 is a 8mm polycarbonate solid flat endurance board. The UV layer is processed on both sides of the board using a total technology. The thickness of the UV-resistant layer is ≥80μm on the illuminated side and ≥50um on the backlit side. The color is milky white, has diffuse reflection function, and the light transmittance is 50%±3%. The endurance board roof is a hyperbolic shape in a roof monomer. The width of the board is 750-1200mm and the longest length is 5000mm. The endurance boards are all hyperbolic shapes. Some endurance boards have a large curvature on the board surface, which must be processed into prefabricated arcs, cold bending, and hot forming to achieve the shape. The inner eaves edge unit 5 uses a non-perforated aluminum veneer. The bending of aluminum veneers is usually processed by metal plate bending. The bending radius should meet the design requirements; when using a plate rolling machine to bend the arc, the arc must be bent first and then the edge folded. The spacing of the folded edge opening must be strictly processed according to 15mm and the size must be 2-3mm. It must be ensured that there are no defects such as burrs, bumps, sharp corners, etc. at the folded edge bending arc, and the folded edge lines must be smooth and straight.

一种体育场曲面异形金属屋面的施工方法,包括以下步骤:S1:根据设计图纸使用3D建模软件深化主体钢结构、屋面表皮模型,在模型中进行屋面龙骨建模,设计审核确认后,工厂根据龙骨模型进行预加工、预拼装试验。A construction method for a stadium curved special-shaped metal roof, including the following steps: S1: Use 3D modeling software to deepen the main steel structure and roof skin model according to the design drawings, and perform roof keel modeling in the model. After the design is reviewed and confirmed, the factory will The keel model undergoes pre-processing and pre-assembly testing.

具体地,根据设计图纸,使用takla深化主体钢结构管桁架各杆件,明确各杆件节点,使用Rhino深化金属屋面表皮模型,在模型上针对节点图位置关系进行龙骨的建模工作,将建立好的模型进行设计审核,设计确认后,根据模型发往加工厂进行加工,需要拼接的双曲龙骨在加工厂预拼装试验,发往现场进行安装,安装过程中采用三点坐标控制的方式进行安装,确保安装精度,保证龙骨的流畅性。Specifically, according to the design drawings, use takla to deepen each member of the main steel structure tube truss, clarify the nodes of each member, use Rhino to deepen the metal roof skin model, and perform modeling work on the keel according to the position relationship of the node diagram on the model, which will be established The good model is subject to design review. After the design is confirmed, it is sent to the processing plant for processing according to the model. The hyperbolic keels that need to be spliced are pre-assembled and tested in the processing plant and sent to the site for installation. During the installation process, three-point coordinate control is used. Install, ensure the installation accuracy and ensure the smoothness of the keel.

S2:使用3D扫描技术进行安装点位扫描,对主体钢结构及屋面龙骨点位进行复核,将复核有偏差的点位再次导入模型进行调整。S2: Use 3D scanning technology to scan the installation points, review the main steel structure and roof keel points, and import the deviated points into the model again for adjustment.

具体地,铝单板龙骨下料前对钢结构及屋面进行复核,找出偏差,龙骨安装过程中根据龙骨的点位进行安装,如图9a、9b所示,确保龙骨完成面与模型偏差较小。在铝单板已耐力板交接位置、天沟位置,大面区域每隔三跨设置调节板,现场复核尺寸下料,其他位置按照模型进行下料;每个屋面单体为一个加工单元进行加工,穿孔板和不穿孔板分开加工,板面覆膜标注安装方向,板内面标注加工编号;复尺下料铝单板根据复核点位和尺寸导入模型内进行重新建模,去比对原有铝单板的尺寸,是否存在错位及重大偏差,对复核尺寸有问题的重新进行反尺下料;发往加工厂的加工清单,主要是模型和版型加工样式为主,反尺下料板以模型下料为主,cad加工图为辅。Specifically, before cutting the aluminum veneer keel, the steel structure and roof were reviewed to find out the deviation. During the keel installation process, the keel was installed according to the point position of the keel, as shown in Figure 9a and 9b, to ensure that the deviation between the completed surface of the keel and the model was relatively close. Small. Adjustment plates are installed at every three spans in the large area at the junction of the aluminum veneer and the endurance board and at the gutter position. The dimensions are checked on site and the cutting is carried out according to the model. Each roof unit is processed as a processing unit. , the perforated board and the non-perforated board are processed separately, the installation direction is marked on the surface of the board, and the processing number is marked on the inner surface of the board; the aluminum veneer blanked from the composite ruler is imported into the model according to the review points and dimensions for remodeling to compare with the original The size of the aluminum veneer, whether there is any misalignment or major deviation, if there is any problem with the size, re-cut the blank; the processing list sent to the processing factory is mainly about the model and version processing style, and the back-cut plate Mainly focus on model cutting, supplemented by CAD processing drawings.

S3:根据最终模型出图,完成各部分的材料加工,如屋面檩拖、檩条、龙骨,压型板及穿孔压型板,铝单板、耐力板及配套铝型材,不锈钢天沟。S3: According to the final model drawing, complete the material processing of each part, such as roof purlins, purlins, keels, profiled plates and perforated profiled plates, aluminum veneers, endurance panels and supporting aluminum profiles, stainless steel gutters.

S4:内天沟6、外天沟7、内檐口的龙骨均在地面预拼装,待主体钢结构完成,进行吊装。S4: The inner gutter 6, outer gutter 7, and the keels of the inner cornice are all pre-assembled on the ground, and will be hoisted after the main steel structure is completed.

具体地,天沟骨架和内檐口骨架均在地面预拼装,内檐口拼装单元为三个立面分隔。预拼装无误,可以在钢结构安装期间按照加工图纸提前在现场预拼装,待钢结构完成,达到安装条件时,直接吊装即可,可大量节约工期。Specifically, the gutter frame and the inner cornice frame are pre-assembled on the ground, and the inner cornice assembly unit is divided into three facades. The pre-assembly is correct and can be pre-assembled on site in advance according to the processing drawings during the steel structure installation. When the steel structure is completed and the installation conditions are met, it can be hoisted directly, which can save a lot of construction time.

S5:根据提供的测量基准点、基准线、水准点进行复核,按屋面布置图、主体结构轴线、标高进行全面的测量放线。S5: Review based on the provided measurement reference points, baselines, and level points, and conduct comprehensive measurement and setting out according to the roof layout, main structure axis, and elevation.

S6:主体钢结构未提升部分在吊装前先在地面完成屋面檩托的安装工作,主体钢结构已提升部分采用屋面定位进行安装。S6: The unlifted part of the main steel structure must complete the installation of roof purlins on the ground before hoisting. The lifted part of the main steel structure must be installed using roof positioning.

具体地,如图5所示,在钢结构复测无误后,先用全站仪在已安装好的主体结构上,放出屋面檩托、连接件定位点,在主结构上标记檩托和连接件位置,然后将檩托、连接件焊接在已安装好的主结构上。在焊接过程中要采取减小变形的措施,先对称点焊。检查檩托、连接件的位置,合格后再焊接,不合格的要校正。点焊要牢固。型材屋面区域的铝单板檩托在屋面主檩条安装完成后进行安装。焊接时电流要适当,焊缝成形后不能出现气孔和裂纹,也不能出现咬边和焊瘤,焊缝尺寸应达到设计要求,焊波应均匀,焊缝成型应美观,焊接完成后应及时做好铝单板檩托焊接处的防腐措施,避免锈蚀。在屋面檩托防腐完成后进行可视面的氟碳喷涂处理。Specifically, as shown in Figure 5, after the retest of the steel structure is correct, a total station is first used to release the positioning points of the roof purlins and connectors on the installed main structure, and mark the purlins and connections on the main structure. position of the parts, and then weld the purlin supports and connecting parts to the installed main structure. During the welding process, measures should be taken to reduce deformation, starting with symmetrical spot welding. Check the position of the purlin support and connecting parts, and weld them if they are qualified. If they are not qualified, they need to be corrected. The spot welds should be firm. The aluminum veneer purlin brackets in the profile roof area are installed after the main roof purlins are installed. The current should be appropriate during welding. After the weld is formed, there should be no pores and cracks, nor undercuts or welding flashes. The size of the weld should meet the design requirements, the welding wave should be uniform, the weld shape should be beautiful, and the welding should be done promptly after the welding is completed. Take good anti-corrosion measures at the welding joints of aluminum veneer purlins to avoid rust. After the anti-corrosion of the roof purlin is completed, fluorocarbon spraying treatment on the visible surface is carried out.

S7:如图11-图13所示,将型材屋面单元2、耐力板屋面单元3、穿孔铝单板屋面单元4中的主檩条分别与屋面连接、次檩条与主檩条连接。S7: As shown in Figures 11 to 13, connect the main purlins in the profile roof unit 2, the endurance board roof unit 3, and the perforated aluminum veneer roof unit 4 to the roof, and connect the secondary purlins to the main purlins respectively.

具体地,主檩条根据模型导出主檩条的加工尺寸和弯弧半径,在加工厂弯弧后发往现场进行制孔与安装,屋面主檩条通过螺栓与屋面连接。屋面次檩条根据模型导出的加工尺寸和弯弧半径,在加工进行成型、制孔后发往现场进行安装,屋面C型檩条通过T型连接板屋面主檩条连接,屋面镀锌方管次檩通过连接件与屋面主檩条连接,次檩条与连接板螺栓固定,连接板与主檩条焊接固定。型材屋面次檩条沿屋面坡度方向布置,屋面次檩条需要进行弯弧处理,每段龙骨均采用坐标点控制安装,坐标点由模型导出。每段圆弧龙骨,安装控制点不少于三个。Specifically, the processing dimensions and bending radius of the main purlins are derived based on the model. After bending in the processing plant, they are sent to the site for hole making and installation. The main roof purlins are connected to the roof through bolts. The roof secondary purlins are shaped and drilled according to the processing dimensions and bending radius derived from the model, and then sent to the site for installation. The roof C-shaped purlins are connected to the main roof purlins through T-shaped connecting plates, and the roof galvanized square tube secondary purlins pass through The connecting piece is connected to the main purlin of the roof, the secondary purlin is fixed to the connecting plate with bolts, and the connecting plate is welded to the main purlin. The secondary purlins of the profile roof are arranged along the direction of the roof slope. The secondary purlins of the roof need to be curved. Each keel section is installed using coordinate point control, and the coordinate points are derived from the model. Each section of arc keel must be installed with no less than three control points.

檩条安装的注意事项如下:The precautions for purlin installation are as follows:

1)复测主钢结构尺寸偏移。安装前要先对主体钢结构进行复测,因为结构尺寸安装误差较大,特别是高度方向尺寸。部分结构偏差较大的需通过檩托进行整改,保证屋面外观质量。1) Re-measure the dimensional deviation of the main steel structure. Before installation, the main steel structure must be re-tested, because the installation error in structural dimensions is large, especially in the height direction. Some structural deviations with large deviations need to be rectified through purlin supports to ensure the quality of the roof appearance.

2)檩托与主体钢结构采用焊接连接形式,檩托安装时,根据图纸分格要求及测量坐标点对檩托进行定位,并标记好上层主檩条安装位置,再调整到所需标高并焊接牢固。焊接完成后,要检查焊缝质量,及时敲除焊渣并进行防锈补漆,以免生锈。2) The purlin brackets are welded to the main steel structure. When installing the purlin brackets, position the purlin brackets according to the drawing requirements and measurement coordinate points, mark the installation position of the upper main purlins, and then adjust to the required elevation and weld. firm. After welding is completed, check the quality of the weld, remove the welding slag in time and perform anti-rust touch-up paint to avoid rust.

3)主檩条与檩托采用不锈钢螺栓组进行连接,主檩托上开设有竖向长椭圆孔,故可以上下调节。安装时,先将主檩条与檩托进行初步螺栓连接,当该区域整片檩条全部安装后,由专人在技术人员的指导,进行主檩条的最终微调定位并拧紧全部螺栓。3) The main purlins and purlin brackets are connected with a set of stainless steel bolts. There are vertical long oval holes on the main purlin brackets, so they can be adjusted up and down. During installation, the main purlins and purlin supports are initially connected with bolts. After the entire purlins in this area are installed, a dedicated person will perform the final fine-tuning and positioning of the main purlins and tighten all the bolts under the guidance of technical personnel.

4)屋面次檩托采用焊接方式直接焊接于主檩条上,屋面次檩托焊接前,先根据图纸分格进行测量放线,确定次檩托焊接位置。次檩托与次檩条采用不锈钢螺栓连接,螺栓先进行初步固定后,调整次檩条表面与主檩条表面平整后,再进行紧固。对于焊接位置,检查焊缝质量,及时敲除焊渣并进行防锈补漆,以免生锈。4) The roof secondary purlin supports are welded directly to the main purlins. Before welding the roof secondary purlin supports, measure and lay out the lines according to the drawings to determine the welding position of the secondary purlin supports. The secondary purlin supports and secondary purlins are connected with stainless steel bolts. After the bolts are initially fixed, the surface of the secondary purlins is adjusted to be smooth with the surface of the main purlins before tightening. For welding positions, check the quality of the weld, remove the welding slag in time and perform anti-rust touch-up paint to avoid rust.

6)完成区域屋面的檩条系统及檩托安装补漆工作后,经自检合格后报监理隐蔽验收,待验收合格后再进行下道工序底板的安装。6) After completing the installation and touch-up painting of the purlin system and purlin supports on the regional roof, submit it to the supervisor for concealed acceptance after passing the self-inspection. After passing the inspection, the installation of the floor plate will be carried out in the next step.

7)主檩条安装定位尺寸参照檩条安装定位图,安装偏差不大于5mm;檩托的长度较多,安装时要注意根据图纸进行选择,不允许代用。7) The installation and positioning dimensions of the main purlins refer to the purlin installation positioning diagram. The installation deviation is not greater than 5mm. The length of the purlin brackets is large. When installing, pay attention to the selection according to the drawings. Substitution is not allowed.

S8:将型材屋面单元2中的穿孔压型底板18安装在屋面与主檩条之间。S8: Install the perforated profiled base plate 18 in the profile roof unit 2 between the roof and the main purlin.

具体地,穿孔压型底板18采用搭接形式,搭接长度不小于80mm,底板根据排版图,在天沟两侧、与耐力板交接位置、与檩条斜接位置,进行斜切处理,保证底板的观感质量,同时在天沟两侧和与耐力板交接位置,安装底板收边,确保底板的观感质量。Specifically, the perforated profiled bottom plate 18 adopts an overlapping form, and the overlap length is not less than 80mm. According to the layout diagram, the bottom plate is beveled on both sides of the gutter, at the intersection position with the endurance board, and at the oblique connection position with the purlins to ensure that the bottom plate is At the same time, install the edge of the bottom plate on both sides of the gutter and at the intersection with the endurance board to ensure the visual quality of the bottom plate.

S9:在主檩条与次檩条的上部设置行走通道;如图16所示,利用麻绳与屋面檩条固定,行走通道设置成6m一段,跨越四根檩条,跨度为5m。屋面底板通过檩条间隙下放到屋面檩条底部进行安装。S9: Set up a walking channel on the upper part of the main purlin and the secondary purlin; as shown in Figure 16, use hemp rope to fix it to the roof purlin. The walking channel is set into a 6m section, spanning four purlins, with a span of 5m. The roof base plate is lowered to the bottom of the roof purlins through the purlin gaps for installation.

优选地,行走通道框架采用D25*2圆管材质Q235B,每段通道板长度6m。Preferably, the walking channel frame is made of D25*2 round pipe material Q235B, and the length of each channel plate is 6m.

S10:在穿孔压型底板18上铺设无纺布、吸音棉;S10: Lay non-woven fabric and sound-absorbing cotton on the perforated profiled bottom plate 18;

具体地,压型穿孔板经验收合格后进行憎水无纺布的铺设,铺设前需对压型板基面进行清理,去除屋面尖锐的异物。相邻玻无纺布搭接100mm,无纺布要求平整覆盖、紧贴、铺满、无明显褶皱。为了使得具有良好的整体性,横向搭接必须严实不露缝。Specifically, after the profiled perforated board has passed the acceptance inspection, the hydrophobic non-woven fabric is laid. Before laying, the base surface of the profiled board needs to be cleaned to remove sharp foreign objects on the roof. Adjacent glass non-woven fabrics should be overlapped by 100mm. The non-woven fabrics must be flat, close to each other, fully covered, and have no obvious wrinkles. In order to achieve good integrity, the horizontal overlap must be tight and no seams are exposed.

具体地,采用的吸音棉材料为50mm容重32kg/m³玻璃丝棉,玻璃棉为不燃的无机物,并有良好的隔声、吸音、防火功能。Specifically, the sound-absorbing cotton material used is 50mm glass wool with a bulk density of 32kg/m³. Glass wool is a non-combustible inorganic material and has good sound insulation, sound absorption, and fire prevention functions.

S11:根据排版图,在天沟两侧、与耐力板交接位置、与檩条斜接位置,压型钢板进行斜切处理,同时在天沟两侧和与耐力板交接位置,安装收边。S11: According to the layout drawing, the corrugated steel sheet is beveled on both sides of the gutter, at the intersection with the endurance board, and at the beveled position with the purlin. At the same time, the trim is installed on both sides of the gutter and at the intersection with the endurance board.

具体地,压型钢板安装采用搭接形式,搭接长度不小于80mm,在压型钢板安装前先放出定位板边线,安装定位板,如图14a、14b所示,根据定位板依次安装底板,每十排板放一条复核线,复核底板安装尺寸偏差并进行调整,以免产生较大的累积误差。当第一块压型板固定就位后,在板端与板顶各拉一根连续的准线,这两根线和第一块板将成为引导线,便于后续压型板的快速固定,在安装一段区域后要定段检查,方法是测量已固定好的压型板宽度,在其顶部与底部各测一次,以保证不出现移动。钢板沿屋面坡度方向铺设,铺设过程中利用自攻钉固定,逐波固定。压型钢板在铝单板龙骨檩托穿洞位置,使用短板就行封堵,四周打钉固定,保证板材在穿洞位置的稳定性。Specifically, the profiled steel plate is installed in the form of overlap, and the overlap length is not less than 80mm. Before installing the profiled steel plate, release the edge of the positioning plate and install the positioning plate. As shown in Figures 14a and 14b, install the bottom plate in sequence according to the positioning plate. Place a review line for every ten rows of boards to review the base plate installation size deviation and make adjustments to avoid large cumulative errors. When the first profiled plate is fixed in place, draw a continuous alignment line at the end of the plate and the top of the plate. These two lines and the first plate will become the guide lines to facilitate the rapid fixation of subsequent profiled plates. After installing a section of the area, it is necessary to check the section by measuring the width of the fixed profile plate once at the top and bottom to ensure that there is no movement. The steel plates are laid along the slope of the roof, and are fixed with self-tapping nails during the laying process, wave by wave. The profiled steel plate is used to seal the hole in the aluminum veneer keel purlin with a short plate, and is fixed with nails around it to ensure the stability of the plate at the hole.

S12:支撑压型钢板上铺设隔汽膜、岩棉、TPO柔性防水卷材;不小于0.25mm厚符合聚丙烯隔汽膜,为防止铺设过程中隔汽膜被风吹开。S12: Lay vapor barrier film, rock wool, and TPO flexible waterproofing membrane on the supporting profiled steel plate; the thickness shall not be less than 0.25mm and conform to the polypropylene vapor barrier film to prevent the vapor barrier film from being blown open by the wind during the laying process.

具体地,型材屋面单元TPO为机械固定方式,天沟单元TPO卷材为粘结固定方式,型材屋面单元施工的TPO为1.5mm厚,天沟单元施工的TPO为2mm厚。Specifically, the TPO of the profile roof unit is mechanically fixed, and the TPO membrane of the gutter unit is adhesively fixed. The TPO of the profile roof unit is 1.5mm thick, and the TPO of the gutter unit is 2mm thick.

S13:在屋面设置临时材料堆放平台,将型材屋面单元2、耐力板屋面单元3、穿孔铝单板屋面单元4中的龙骨均与屋面檩托连接;S13: Set up a temporary material storage platform on the roof, and connect the keels in the profile roof unit 2, endurance board roof unit 3, and perforated aluminum veneer roof unit 4 to the roof purlins;

具体地,在屋面适当位置设置临时材料堆放平台,装饰铝单板位于铝单板龙骨上层,施工时可以利用龙骨搭设作业面。主龙骨根据模型导出主加工尺寸和弯弧半径,在加工厂弯弧后发往现场进行安装,主龙骨通过屋面连接板与檩托连接;主龙骨通过连接件与次龙骨进行连接。Specifically, a temporary material storage platform is set up at an appropriate location on the roof, and the decorative aluminum veneer is located on the upper layer of the aluminum veneer keel. The keel can be used to set up the working surface during construction. The main keel is derived from the main processing size and bending radius based on the model, and is sent to the site for installation after bending in the processing plant. The main keel is connected to the purlin support through the roof connecting plate; the main keel is connected to the secondary keel through connectors.

S14:在已安装好的龙骨上划出中心线,将预制铝单板依据编号图的位置,进行安装。S14: Draw the center line on the installed keel and install the prefabricated aluminum panels according to the positions on the numbered diagram.

具体地,前期测量是安装精度的基础,是关键步骤。如图11所示,拟采取区域放样,逐点投测的形式进行操作。首先,根据原始测量基准点,布设平面测量控制点。从外围进行坐标点的测设,投放轴线,闭合轴线,调整测量误差。为了保证装饰板的安装精度,控制整体误差。防止出现一个区域安装失误,整体顺次误差的情况发生,对测量轴线进行加密,以各加密轴线划分一个个独立的安装区域,进行安装及精度控制。这样做,即使在一个区内的安装出现误差,也只是影响了局部,而不会引起连锁反应,使整体安装精度出现大偏差。采用全站仪进行单位区域内的安装定位,首先应测量出各位置的结构偏差,得出数据。然后根据偏差重新调整,使承载面满足屋面弧度及标高要求。根据测量数据,在檩托上部安装转接件。以全站仪、经纬仪进行测量,保证连接件的安装精度。转接件的承载端面,以全站仪投测标高。如标高有设计有差异,利用连接件自身的调节系统予以调节。Specifically, preliminary measurement is the basis for installation accuracy and is a key step. As shown in Figure 11, it is planned to operate in the form of regional stakeout and point-by-point measurement. First, lay out plane measurement control points based on the original measurement datum points. Measure and set coordinate points from the periphery, place the axis, close the axis, and adjust the measurement error. In order to ensure the installation accuracy of decorative panels, control the overall error. To prevent installation errors in one area and overall sequence errors from occurring, the measurement axes are encrypted, and each encrypted axis is divided into independent installation areas for installation and accuracy control. In this way, even if there is an error in the installation in one area, it will only affect the local area and will not cause a chain reaction and cause a large deviation in the overall installation accuracy. When using a total station for installation and positioning within a unit area, the structural deviation at each location should first be measured and the data obtained. Then readjust according to the deviation so that the bearing surface meets the roof radian and elevation requirements. According to the measurement data, install the adapter on the upper part of the purlin support. Measure with a total station and theodolite to ensure the installation accuracy of the connectors. The elevation of the load-bearing end face of the adapter is measured with a total station. If the elevation is different in design, use the adjustment system of the connector itself to adjust it.

S15:安装耐力板屋面单元3中的耐力板34。S15: Install the solid sheet 34 in the solid sheet roof unit 3.

具体地,耐力板根据模型导出加工尺寸,耐力板均为四边异形曲面板,耐力板只能加工成矩形板,现场或者工程根据加工尺寸进行四边的切割,耐力板在天沟位置、与型材屋面交接位置、底部造型位置和异形板位置,需要进行切割处理。对于耐力板曲率较大的板块,进行冷弯或者热成型进行加工。耐力板表面进行UV处理,提高耐力板的耐久性和抗老化性能。龙骨根据加工弧度,在加工厂进行弯弧处理。龙骨表面进行氟碳喷涂处理。Specifically, the processing dimensions of the endurance board are derived based on the model. The endurance panels are all four-sided special-shaped curved panels. The endurance panels can only be processed into rectangular panels. The four sides are cut according to the processing dimensions on site or in the project. The endurance panels are in the gutter position and with the profile roof. The handover position, bottom shape position and special-shaped plate position need to be cut. For plates with a large curvature of endurance boards, they are processed by cold bending or hot forming. The surface of the endurance board is UV treated to improve the durability and anti-aging performance of the endurance board. The keel is bent in the processing plant according to the processing arc. The surface of the keel is treated with fluorocarbon spraying.

S16:内檐口收边单元5的龙骨在地面拼装成单元,吊装到屋面进行连接。S16: The keels of the inner cornice edge unit 5 are assembled into units on the ground and hoisted to the roof for connection.

具体地,檐口龙骨安装前测量定出檐口支撑位置,内檐口小龙骨采用地面拼装成单元,吊装到屋面,在屋面上进行拼装焊接固定。铝单板龙骨三个空档为一个单元,相邻单元进行补档。单元拼装过程中,按照加工图进行放样,调整角度。Specifically, the cornice support position is determined by measuring before installing the cornice keels. The small inner cornice keels are assembled into units on the ground, hoisted to the roof, and assembled and welded on the roof. The three gaps of the aluminum veneer keel form one unit, and the adjacent units are supplemented. During the unit assembly process, set out and adjust the angle according to the processing drawing.

S17:在施工过程中,用全站仪对每块预制铝单板的三维坐标放样,在龙骨上标记,要求每块预制铝单板的四个角点与三维坐标放样点重合、与模型中的三维坐标点一致。S17: During the construction process, use a total station to stake out the three-dimensional coordinates of each prefabricated aluminum veneer and mark it on the keel. It is required that the four corner points of each prefabricated aluminum veneer coincide with the three-dimensional coordinate stakeout points and in the model. The three-dimensional coordinate points are consistent.

具体地,铝单板在加工厂加工完成后,表面覆保护薄膜运输至现场及工作面。铝单板在安装前将铝板胶缝的定位线测设在钢龙骨上,以控制安装位置。在安装前应认真检查其编号、数量、分清安装方向、位置。预先装好铝板固定角码,安装应牢固不松动,不漏装。在施工过程中,用全站仪进行每块板的三维坐标放样,并且在装饰骨架上面做好标记,在安装过程中要求每块板的四个角点与三维坐标放样点重合,保证每块板必须与模型中的三维坐标点一致,来保证整个屋面的造型。Specifically, after the aluminum veneer is processed in the processing plant, the surface is covered with a protective film and transported to the site and working surface. Before installing the aluminum veneer, set the positioning line of the aluminum plate glue seam on the steel keel to control the installation position. Before installation, the number, quantity, and installation direction and location should be carefully checked. The aluminum plate fixing corner codes are installed in advance. The installation should be firm and not loose or missing. During the construction process, a total station was used to stake out the three-dimensional coordinates of each panel, and marks were made on the decorative skeleton. During the installation process, the four corner points of each panel were required to coincide with the three-dimensional coordinate stakeout points to ensure that each panel The panels must be consistent with the three-dimensional coordinate points in the model to ensure the shape of the entire roof.

S18:内天沟6与外天沟7的龙骨采用地面拼装,再吊至屋面进行连接。S18: The keels of the inner gutter 6 and the outer gutter 7 are assembled on the ground and then hoisted to the roof for connection.

具体地,屋面天沟为弧形天沟,内天沟为S型布置,外天沟为弧形布置,在沿屋面平面环向进行弯弧处理,根据模型导出加工尺寸和弯弧半径。天沟龙骨采用地面拼装,每个轴线间天沟为一个独立单元,拼装完成后,然后吊装到屋面,在屋面上进行拼装焊接固定。Specifically, the roof gutter is an arc gutter, the inner gutter is S-shaped, and the outer gutter is arc-shaped. The gutter is curved along the roof plane, and the processing size and arc radius are derived according to the model. The gutter keel is assembled on the ground, and the gutter between each axis is an independent unit. After the assembly is completed, it is hoisted to the roof and assembled, welded and fixed on the roof.

具体地,屋面檩托分为两种表面处理方式,不外露的构件表面为镀锌处理,外露构件表面进行氟碳喷涂处理。屋面檩条及龙骨表面处理方式分为两种表面处理方式,不外露的构件表面为镀锌处理,外露构件表面进行氟碳喷涂处理。Specifically, the roof purlins are divided into two surface treatment methods. The surface of the non-exposed components is galvanized, and the surface of the exposed components is treated with fluorocarbon spraying. The surface treatment methods of roof purlins and keels are divided into two surface treatment methods. The surfaces of non-exposed components are galvanized, and the surfaces of exposed components are treated with fluorocarbon spraying.

具体地,不穿孔铝单板分为型材屋面铝单板、内檐口铝单板、屋面交接铝单板,外露表面氟碳喷涂处理,穿孔铝单板,双面氟碳喷涂处理,其穿孔率10%~40%,其中型材屋面铝单板和穿孔铝单板采用附框与加劲肋的方式进行板面加固。Specifically, non-perforated aluminum veneer is divided into profile roof aluminum veneer, inner cornice aluminum veneer, roof junction aluminum veneer, exposed surface fluorocarbon spray treatment, perforated aluminum veneer, double-sided fluorocarbon spray treatment, and its perforation rate 10%~40%, among which profile roof aluminum veneers and perforated aluminum veneers are reinforced with frames and stiffeners.

在上述实施方式的基础上,如图8所示,采用三点坐标控制法进行安装。对于单曲或双曲龙骨在龙骨表面控制点位置黏贴反光贴,在安装过程中,通过不少于三点坐标进行控制,安装完成后通过全站仪进行点位复测,增加测量点位,必要时使用3D扫描技术进行安装点位扫描,将点位导入到3d模型内与模型龙骨进行分析,对于偏差较大的龙骨进行调整。如图10所示,分区的测量控制点以宽缝间分格线交叉点为控制点,将整个装饰铝板屋面进行分区。各分区独立进行装饰铝板龙骨的测量及安装,误差分区内部消化,不累计到下一分区。On the basis of the above implementation, as shown in FIG8 , a three-point coordinate control method is used for installation. For single-curved or double-curved keels, reflective stickers are pasted at the control point position on the keel surface. During the installation process, control is performed through no less than three-point coordinates. After the installation is completed, the point position is re-measured by the total station, and the measurement points are added. If necessary, 3D scanning technology is used to scan the installation points, and the points are imported into the 3D model for analysis with the model keel, and the keels with large deviations are adjusted. As shown in FIG10 , the measurement control points of the partitions are divided into partitions with the intersection of the grid lines between the wide seams as the control points. Each partition independently measures and installs the decorative aluminum plate keel, and the error is absorbed within the partition and is not accumulated to the next partition.

在上述实施方式的基础上,所述穿孔压型底板18、所述支撑压型钢板21在与相邻板材交接时均进行斜切处理,在天沟两侧、与耐力板交接位置、与檩条斜接位置,进行斜切处理,同时在天沟两侧和与耐力板交接位置,安装收边,确保观感质量。On the basis of the above embodiment, the perforated profiled bottom plate 18 and the support profiled steel plate 21 are all beveled when they are connected with adjacent plates. Bevel cutting is performed at the mitered joint position. At the same time, edge trimming is installed on both sides of the gutter and at the intersection with the endurance board to ensure the visual quality.

本发明中屋面与体育场的主体钢结构可调整连接有檩条、檩托、龙骨,可以适应异性曲面,使屋面安装更加简便和灵活,在模型上的节点位置进行龙骨的建模工作,安装过程中采用三点坐标控制的方式进行安装,确保安装精度,保证龙骨的流畅性;使用3D扫描技术进行安装点位扫描,将点位导入到3d模型内,与模型龙骨进行分析;根据模型对现有耐力板板材和型材龙骨的曲率和贴合度进行分析,明确板材哪些需要热成型哪些需要现场冷弯,对模型进行分析,铝型材为双向弯曲造型,需要对铝型材进行热加工处理,通过模具加工出和耐力板相吻合的造型,确保耐力板和铝型材紧密贴合,起到防水效果;采用三维激光扫描仪对项目现场进行逆向,保证天幕与建筑结构的精准定位,为减少项目实施二次拆改成本;建立建筑最终外表皮模型,确定屋面、天沟、内檐口的空间位置与主体钢结构的相对位置关系,通过建筑施工图提供的外轮廓断面,结合钢结构壳体模型进行排水分析,对局部区域微调,优化设置天沟,降低渗漏隐患,通过模型计算天沟伸缩缝位置,计算因温度变化产出的应力,防止局部位置应力集中,造成焊缝拉裂,确保流水顺畅性;基于BIM信息化模型,坐标定位提取,定制软件导出三维坐标,生成现场安装控制坐标,采用BIM信息化模型协同化深化设计、所有构件进行预下料加工,提高加工精度,缩短工期,验算最不利荷载作用下紧固件抗拔力,保证屋面系统受力性能满足要求;地面预拼装加工操作空间充足,可节约大量人力,且方便对构件室外加工制作精度以及接口能够满足现场的安装需要以及满足规范设计要求进行检查,最大程度地把问题留在地面,及时解决,而不是在现场安装时才发现构件的加工精度问题,影响工期,减少现场安装时的错误调整时间,为工程的整体进度和质量保证创造条件;最大限度的降低了发生安全事故的可能性。In the present invention, the roof and the main steel structure of the stadium are adjustably connected with purlins, purlin brackets and keels, which can adapt to the anisotropic curved surface, making the roof installation more convenient and flexible. The keel modeling work is carried out at the node position on the model, and the installation is carried out in the form of three-point coordinate control during the installation process to ensure the installation accuracy and the smoothness of the keel; the installation point is scanned using 3D scanning technology, and the point is imported into the 3D model for analysis with the model keel; the curvature and fit of the existing endurance board and profile keel are analyzed according to the model to clarify which boards need Which parts of hot forming need to be cold-bent on site? The model is analyzed. The aluminum profile is a two-way bending shape, which requires heat processing. The shape that matches the endurance board is processed through the mold to ensure that the endurance board and the aluminum profile fit closely and have a waterproof effect. A 3D laser scanner is used to reverse the project site to ensure the accurate positioning of the canopy and the building structure to reduce the cost of secondary demolition and modification during project implementation. The final outer skin model of the building is established to determine the spatial position of the roof, gutter, and inner eaves and the relative position relationship with the main steel structure. The outer wheel provided by the building construction drawing is used to The steel structure shell model is used to analyze the drainage profile, fine-tune the local area, optimize the setting of the gutter, reduce the risk of leakage, calculate the location of the gutter expansion joint through the model, calculate the stress generated by temperature changes, prevent stress concentration in local positions, cause weld cracking, and ensure smooth water flow; based on the BIM information model, coordinate positioning extraction, customized software to export three-dimensional coordinates, generate on-site installation control coordinates, use the BIM information model to collaboratively deepen the design, pre-cut all components, improve processing accuracy, shorten the construction period, verify the pull-out force of fasteners under the most unfavorable load, and ensure that the force performance of the roof system meets the requirements; the ground pre-assembly processing operation space is sufficient, which can save a lot of manpower, and it is convenient to check the outdoor processing and manufacturing accuracy of the components and whether the interface can meet the on-site installation needs and meet the standard design requirements, so as to keep the problems on the ground to the greatest extent and solve them in time, instead of discovering the processing accuracy problems of the components during on-site installation, affecting the construction period, reducing the error adjustment time during on-site installation, and creating conditions for the overall progress and quality assurance of the project; the possibility of safety accidents is minimized.

本发明未详尽之处均为本领域技术人员所公知的常规技术手段。The non-exhaustive aspects of the present invention are all conventional technical means known to those skilled in the art.

以上内容显示和描述了本发明的基本原理、主要特征及本发明的有益效果。以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above content shows and describes the basic principles, main features and beneficial effects of the present invention. The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims (10)

1.一种体育场曲面异形金属屋面,其特征在于:包括多个沿体育场周向设置的屋面单体(1),所述屋面单体(1)上设置有天沟单元,所述屋面单体(1)包括呈异形曲面的型材屋面单元(2)、耐力板屋面单元(3)、穿孔铝单板屋面单元(4),所述屋面单体(1)的屋檐处设置有内檐口收边单元(5)。1. A stadium curved special-shaped metal roof, characterized by: including a plurality of roofing units (1) arranged along the circumference of the stadium. Gutter units are provided on the roofing units (1). The roofing units are (1) It includes profile roof units (2) with special-shaped curved surfaces, endurance board roof units (3), and perforated aluminum veneer roof units (4). The eaves of the roof units (1) are provided with inner eaves. Unit (5). 2.根据权利要求1所述的体育场曲面异形金属屋面,其特征在于:所述型材屋面单元(2)的下端与所述穿孔铝单板屋面单元(4)的上端相连,所述耐力板屋面单元(3)连接于所述耐力板屋面单元(3)与所述型材屋面单元(2)的左侧或右侧。2. The stadium curved special-shaped metal roof according to claim 1, characterized in that: the lower end of the profile roof unit (2) is connected to the upper end of the perforated aluminum veneer roof unit (4), and the endurance board roof The unit (3) is connected to the left or right side of the endurance board roof unit (3) and the profile roof unit (2). 3.根据权利要求1或2所述的体育场曲面异形金属屋面,其特征在于:所述天沟单元包括设置于所述型材屋面单元(2)上的内天沟(6)与外天沟(7),所述型材屋面单元(2)与穿孔铝单板屋面单元(4)上设置有导水槽(8),所述内天沟(6)与所述外天沟(7)沿所述屋面单体(1)横向设置,所述导水槽(8)沿所述屋面单体(1)纵向设置。3. The stadium curved special-shaped metal roof according to claim 1 or 2, characterized in that: the gutter unit includes an inner gutter (6) and an outer gutter (6) provided on the profile roof unit (2). 7), the profile roof unit (2) and the perforated aluminum veneer roof unit (4) are provided with water conduits (8), and the inner gutter (6) and the outer gutter (7) are installed along the The roof unit (1) is arranged transversely, and the water guide channel (8) is arranged longitudinally along the roof unit (1). 4.根据权利要求3所述的体育场曲面异形金属屋面,其特征在于:所述内天沟(6)设置于所述型材屋面单元(2)的屋檐处,所述内檐口收边单元(5)设置于所述内天沟(6)的外侧,所述内檐口收边单元(5)包括相连的内檐口龙骨(9)、内檐口铝单板(10),所述内檐口龙骨(9)与主体钢结构、所述内天沟(6)连接。4. The curved special-shaped metal roof for a stadium according to claim 3, characterized in that: the inner gutter (6) is arranged at the eaves of the profile roof unit (2), the inner eaves edge trimming unit (5) is arranged on the outside of the inner gutter (6), the inner eaves edge trimming unit (5) comprises connected inner eaves keels (9) and inner eaves aluminum panels (10), and the inner eaves keels (9) are connected to the main steel structure and the inner gutter (6). 5.根据权利要求1-2、4任一项所述的体育场曲面异形金属屋面,其特征在于:所述型材屋面单元(2)的安装步骤如下:5. The stadium curved special-shaped metal roof according to any one of claims 1-2 and 4, characterized in that the installation steps of the profile roof unit (2) are as follows: S201:安装檩托一(15)、檩条一(16);S201: Install purlin support one (15) and purlin one (16); S202:安装铝单板檩托(17);S202: Install aluminum purlin bracket (17); S203:安装穿孔压型底板(18);S203: Installing the perforated profiled bottom plate (18); S204:铺设无纺布(19);S204: Laying non-woven fabric (19); S205:铺设吸音棉(20);S205: Laying sound-absorbing cotton (20); S206:安装支撑压型钢板(21);S206: Install the supporting profiled steel plate (21); S207:铺设隔汽膜(22);S207: Laying a vapor barrier membrane (22); S208:铺设岩棉(23);S208: Laying rock wool (23); S209:铺设TPO柔性防水卷材(24);S209: Laying TPO flexible waterproof membrane (24); S2010:安装铝单板主龙骨一(25);S2010: Install aluminum veneer main keel one (25); S2011:安装铝单板次龙骨一(26);S2011: Installation of aluminum veneer sub-keel one (26); S2012:安装铝单板(27)。S2012: Installation of aluminum veneer (27). 6.根据权利要求1-2、4任一项所述的体育场曲面异形金属屋面,其特征在于:所述耐力板屋面单元(3)的安装步骤如下:6. The stadium curved special-shaped metal roof according to any one of claims 1-2 and 4, characterized in that: the installation steps of the endurance board roof unit (3) are as follows: S301:安装檩托二(31)、檩条二(32)、龙骨二(33);S301: Install the second purlin support (31), the second purlin (32), and the second keel (33); S302:安装耐力板(34);S302: Install endurance board (34); S303:安装压板(35)、扣盖(36)。S303: Install the pressing plate (35) and the buckle cover (36). 7.根据权利要求1-2、4任一项所述的体育场曲面异形金属屋面,其特征在于:所述穿孔铝单板屋面单元(4)的安装步骤如下:7. The stadium curved special-shaped metal roof according to any one of claims 1-2 and 4, characterized in that the installation steps of the perforated aluminum veneer roof unit (4) are as follows: S401:安装檩托三(41)、檩条三(42);S401: Install purlin support three (41) and purlin three (42); S402:安装铝单板龙骨三(43);S402: Install aluminum veneer keel three (43); S403:安装穿孔铝单板(44)。S403: Install perforated aluminum veneer (44). 8.一种体育场曲面异形金属屋面的施工方法,其特征在于:包括权利要求1所述的体育场曲面异形金属屋面,施工方法包括以下步骤:8. A construction method for a stadium curved special-shaped metal roof, characterized in that it includes the stadium curved special-shaped metal roof according to claim 1, and the construction method includes the following steps: S1:根据设计图纸使用3D建模软件深化主体钢结构、屋面表皮模型,在模型中进行屋面龙骨建模,设计审核确认后,工厂根据龙骨模型进行预加工、预拼装试验;S1: Use 3D modeling software to deepen the main steel structure and roof skin model according to the design drawings, and model the roof keel in the model. After the design is reviewed and confirmed, the factory conducts pre-processing and pre-assembly tests based on the keel model; S2:使用3D扫描技术进行安装点位扫描,对主体钢结构及屋面龙骨点位进行复核,将复核有偏差的点位再次导入模型进行调整;S2: Use 3D scanning technology to scan the installation points, review the main steel structure and roof keel points, and import the deviated points into the model again for adjustment; S3:根据最终模型出图,完成各部分的材料加工;S3: Draw the final model and complete the material processing of each part; S4:内天沟(6)、外天沟(7)、内檐口的龙骨构件均在地面预拼装,待主体钢结构完成,进行吊装;S4: The keel components of the inner gutter (6), the outer gutter (7) and the inner eaves are pre-assembled on the ground and hoisted after the main steel structure is completed; S5:根据提供的测量基准点、基准线、水准点进行复核,按屋面布置图、主体结构轴线、标高进行全面的测量放线;S5: Review based on the provided measurement reference points, baselines, and level points, and conduct comprehensive measurement and setting out according to the roof layout, main structure axis, and elevation; S6:主体钢结构未提升部分在吊装前先在地面完成屋面檩托构件的安装工作,主体钢结构已提升部分采用屋面定位进行安装;S6: The unlifted part of the main steel structure must complete the installation of roof purlin components on the ground before hoisting. The lifted part of the main steel structure must be installed using roof positioning; S7:将型材屋面单元(2)、耐力板屋面单元(3)、穿孔铝单板屋面单元(4)中的檩条构件与屋面连接;S7: Connect the purlin components in the profile roof unit (2), endurance board roof unit (3), and perforated aluminum veneer roof unit (4) to the roof; S8:将型材屋面单元(2)中的穿孔压型底板(18)安装在屋面与檩条构件之间;S8: Install the perforated profiled bottom plate (18) in the profile roof unit (2) between the roof and purlin components; S9:在檩条构件的上部设置行走通道(11);S9: Set up a walking channel (11) on the upper part of the purlin member; S10:在穿孔压型底板(18)上铺设无纺布(19)、吸音绵(20);S10: Lay non-woven fabric (19) and sound-absorbing cotton (20) on the perforated profiled bottom plate (18); S11:在檩条构件与龙骨构件之间安装支撑压型钢板(21);S11: Install the supporting profiled steel plate (21) between the purlin components and the keel components; S12:支撑压型钢板(21)上依次铺设隔汽膜(22)、岩棉(23)、TPO柔性防水卷材(24);S12: The steam barrier membrane (22), rock wool (23), and TPO flexible waterproofing membrane (24) are laid on the supporting profiled steel plate (21) in sequence; S13:在屋面设置临时材料堆放平台,将型材屋面单元(2)、耐力板屋面单元(3)、穿孔铝单板屋面单元(4)中的龙骨构件均与屋面檩托构件连接;S13: Set up a temporary material storage platform on the roof, and connect the keel components in the profile roof unit (2), endurance board roof unit (3), and perforated aluminum veneer roof unit (4) to the roof purlin components; S14:在已安装好的龙骨构件上划出中心线,将预制铝单板依据编号图的位置,进行安装;S14: Draw the center line on the installed keel components and install the prefabricated aluminum panels according to the positions in the numbered diagram; S15:安装耐力板屋面单元(3)中的耐力板(34);S15: Install the endurance panels (34) in the endurance panel roof unit (3); S16:内檐口收边单元(5)的龙骨构件在地面拼装成单元,吊装到屋面进行连接;S16: The keel components of the inner cornice closing unit (5) are assembled into units on the ground and hoisted to the roof for connection; S17:在施工过程中,用全站仪对每块预制铝单板的三维坐标放样,在龙骨构件上标记,要求每块预制铝单板的四个角点与三维坐标放样点重合、与模型中的三维坐标点一致;S17: During the construction process, use a total station to stake out the three-dimensional coordinates of each prefabricated aluminum veneer, and mark the keel components. It is required that the four corner points of each prefabricated aluminum veneer coincide with the three-dimensional coordinate stakeout points and be consistent with the model. The three-dimensional coordinate points in are consistent; S18:内天沟(6)与外天沟(7)的龙骨构件采用地面拼装,再吊至屋面进行连接。S18: The keel components of the inner gutter (6) and the outer gutter (7) are assembled on the ground and then hoisted to the roof for connection. 9.根据权利要求8所述的体育场曲面异形金属屋面的施工方法,其特征在于:采用三点坐标控制法进行安装。9. The construction method of the stadium curved special-shaped metal roof according to claim 8, characterized in that: the three-point coordinate control method is used for installation. 10.根据权利要求8所述的适用于体育场曲面异性金属屋面的施工方法,其特征在于:所述穿孔压型底板(18)、所述支撑压型钢板(21)在与相邻板材交接时均进行斜切处理。10. The construction method suitable for stadium curved metal roofs with different shapes according to claim 8, characterized in that: the perforated profiled bottom plate (18) and the support profiled steel plate (21) are connected with adjacent plates when they are connected with each other. All are beveled.
CN202311760258.7A 2023-12-20 2023-12-20 A kind of stadium curved special-shaped metal roof and construction method Pending CN117803140A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311760258.7A CN117803140A (en) 2023-12-20 2023-12-20 A kind of stadium curved special-shaped metal roof and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311760258.7A CN117803140A (en) 2023-12-20 2023-12-20 A kind of stadium curved special-shaped metal roof and construction method

Publications (1)

Publication Number Publication Date
CN117803140A true CN117803140A (en) 2024-04-02

Family

ID=90428918

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311760258.7A Pending CN117803140A (en) 2023-12-20 2023-12-20 A kind of stadium curved special-shaped metal roof and construction method

Country Status (1)

Country Link
CN (1) CN117803140A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN119577910A (en) * 2024-11-22 2025-03-07 广东省水利水电第三工程局有限公司 Construction supervision method and system of steel structure canopy based on BIM

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN119577910A (en) * 2024-11-22 2025-03-07 广东省水利水电第三工程局有限公司 Construction supervision method and system of steel structure canopy based on BIM

Similar Documents

Publication Publication Date Title
CN105298143A (en) Construction method of multi-lateral double-curved-face open-type titanium composite board curtain wall
CN113914517B (en) Stone curtain wall system and construction method thereof
CN113982198B (en) Lotus leaf molding roof
CN106284857A (en) A kind of construction technology of aluminium sheet roofing standing-seam system
CN114000661A (en) Waterproof pressure tank sealing structure for vertical serging roof coiled material and construction method
CN117803140A (en) A kind of stadium curved special-shaped metal roof and construction method
CN114059721A (en) Construction method for continuously welding stainless steel metal roof of tennis court
CN115075476B (en) Metal roof structure and construction method thereof
CN113107142B (en) Construction method of wind-resistant metal roof structure
CN219327216U (en) Curtain wall structure
CN216516508U (en) Metal roof construction node
CN216516085U (en) Daylighting roof construction joint
CN115478654A (en) A waterproof structure of split roof panels in a metal roof system
CN110778035B (en) Construction method of combined roof of metal tiles and metal eaves rafters
CN216276498U (en) Gutter structure arranged on metal roof
CN116988604A (en) Construction method of open hyperboloid overlapping metal curtain wall mounting structure
CN217379531U (en) BIM-based complex roof system for adjustable theme parks with tiled roof
CN117248690A (en) Integrated steel structure sloping roof cornice and construction method thereof
CN110064857A (en) Stainless steel roofing continuous welding construction method
CN116771021A (en) Construction method for large hyperboloid special-shaped decorative aluminum veneer
CN217420264U (en) Novel combined roof board
CN104533027A (en) Construction method of steel structure roof waterproof and heat insulation system
CN219992895U (en) Hyperbolic metal roofing with gentle regional waterproof construction
CN116657813B (en) Construction method of multi-curvature variable-angle type wavy roof system
CN216893080U (en) Waterproof drainage structure of roof with steel track beam protruding out of concrete structure roof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination