CN117661463A - Assembled truss for large-span beam construction and installation method thereof - Google Patents
Assembled truss for large-span beam construction and installation method thereof Download PDFInfo
- Publication number
- CN117661463A CN117661463A CN202311691776.8A CN202311691776A CN117661463A CN 117661463 A CN117661463 A CN 117661463A CN 202311691776 A CN202311691776 A CN 202311691776A CN 117661463 A CN117661463 A CN 117661463A
- Authority
- CN
- China
- Prior art keywords
- truss
- trusses
- upper chord
- chord member
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
技术领域Technical field
本发明涉及桥梁施工技术领域,具体涉及一种大跨度横梁施工用的装配式桁架及其安装方法。The invention relates to the technical field of bridge construction, and in particular to a prefabricated truss for large-span beam construction and an installation method thereof.
背景技术Background technique
主塔是桥梁的重要受力构件之一,其主要用来承受主缆传递的压力。为增加主塔的横向刚度,同时保证结构受力的合理性,一般会在主塔的两根塔柱之间设置上横梁与下横梁。对于主塔上横梁,现有的施工方法通常使用钢管脚手架、钢管柱等作为落地支架进行施工安装,使用贝雷梁作为横梁支架的主梁进行施工。The main tower is one of the important stress-bearing components of the bridge. It is mainly used to withstand the pressure transmitted by the main cable. In order to increase the lateral stiffness of the main tower and ensure the rationality of the structural stress, upper and lower beams are generally set between the two columns of the main tower. For the beams on the main tower, existing construction methods usually use steel pipe scaffolding, steel pipe columns, etc. as floor supports for construction and installation, and Bailey beams as the main beams of the beam supports for construction.
现有的施工方法的缺点有:1、采用钢管脚手架或者钢管柱等作为落地支架的施工方法,使得支架材料用量大、使用成本高、高空钢结构吊装风险大、施工安全性低且施工工期长;2、主塔横梁施工采用常见的贝雷梁作为横梁支架的主梁,在面对更高挑战的高原大风环境下,贝雷梁的承载能力不足,抗风稳定性差。The disadvantages of the existing construction methods are: 1. The construction method of using steel pipe scaffolding or steel pipe columns as floor-standing supports results in a large amount of support materials, high usage costs, high risks of high-altitude steel structure hoisting, low construction safety and long construction period. ; 2. The main tower beam construction uses common Bailey beams as the main beams of the beam supports. In the plateau wind environment with higher challenges, Bailey beams have insufficient load-bearing capacity and poor wind resistance stability.
发明内容Contents of the invention
针对现有技术中存在的缺陷,本申请提供了一种大跨度横梁施工用的装配式桁架及其安装方法,可以解决现有的施工方法成本高、高空钢结构吊装风险大、施工安全性低且施工工期长的问题。In view of the shortcomings in the existing technology, this application provides a prefabricated truss for long-span beam construction and its installation method, which can solve the problems of high cost of existing construction methods, high risks of hoisting high-altitude steel structures, and low construction safety. And the problem of long construction period.
第一方面,本申请实施例提供了一种大跨度横梁施工用的装配式桁架,包括:桁架组,所述桁架组包括多个平行设置的桁架,且相邻桁架之间通过横向联结系相连,所述桁架包括下弦杆、上弦杆以及多根位于所述下弦杆和所述上弦杆之间的桁架腹杆,所述桁架组的底部的每个角处均设有至少两个支撑组件;其中,所述桁架腹杆包括多根垂直腹杆和多根斜向腹杆,相邻的两根垂直腹杆之间设有两根斜向腹杆以形成倒M形,且所述垂直腹杆顶部、中部和底部均设有操作平台。In a first aspect, embodiments of the present application provide a prefabricated truss for long-span beam construction, including: a truss group, the truss group includes a plurality of trusses arranged in parallel, and adjacent trusses are connected through transverse connections. , the truss includes a lower chord, an upper chord and a plurality of truss web rods located between the lower chord and the upper chord, and at least two support assemblies are provided at each corner of the bottom of the truss group; Wherein, the truss web members include a plurality of vertical web members and a plurality of oblique web members, and two oblique web members are provided between two adjacent vertical web members to form an inverted M shape, and the vertical web members There are operating platforms at the top, middle and bottom of the pole.
结合第一方面,在一种实施方式中,所述横向联结系包括联结系上弦杆、联结系腹杆和联结系下弦杆,所述联结上弦杆与所述联结系下弦杆相互平行,所述联结系腹杆的一端与所述联结系上弦杆相连,另一端与所述联结系下弦杆相连,且所述横向联结系为Z字型。In conjunction with the first aspect, in one embodiment, the transverse connection system includes an upper chord bar of the connection system, a web bar of the connection system and a lower chord bar of the connection system, the upper chord bar of the connection system and the lower chord bar of the connection system are parallel to each other, and the One end of the connecting system web bar is connected to the upper chord bar of the connecting system, and the other end is connected to the lower chord bar of the connecting system, and the transverse connecting system is in a Z-shape.
结合第一方面,在一种实施方式中,所述支撑组件包括分配梁和牛腿,所述牛腿与塔柱相连,所述分配梁架设在所述牛腿上,且所述分配梁和所述牛腿之间设有钢板抄垫和楔块。In conjunction with the first aspect, in one embodiment, the support assembly includes a distribution beam and a corbel, the corbel is connected to the tower column, the distribution beam is erected on the corbel, and the distribution beam and the corbel are There are steel plate pads and wedges between the corbels.
结合第一方面,在一种实施方式中,所述下弦杆包括三根下弦短杆,所述下弦短杆首尾相连,且相邻的两个下弦短杆之间的连接处均设有第一联结系;所述上弦杆包括五根上弦短杆,所述上弦短杆首尾相连,且相邻的两个上弦短杆之间的连接处均设有第一联结系其中,所述第一联结系包括四片钢板和多个长条螺栓。In conjunction with the first aspect, in one embodiment, the lower chord bar includes three lower chord short bars, the lower chord short bars are connected end to end, and the connection between the two adjacent lower chord short bars is provided with a first connection The upper chord bar includes five upper chord short bars, the upper chord short bars are connected end to end, and the connection between the two adjacent upper chord short bars is provided with a first connection system, wherein the first connection system Includes four steel plates and multiple long bolts.
结合第一方面,在一种实施方式中,所述桁架腹杆与所述下弦杆的连接处均设有第二联结系,且所述桁架腹杆与所述上弦杆的连接处均设有第二联结系;其中,所述第二联结系包括吊耳和多个销轴。Combined with the first aspect, in one embodiment, the connection between the truss web and the lower chord is provided with a second connection system, and the connection between the truss web and the upper chord is provided with a second connection system. A second connection system; wherein the second connection system includes lifting lugs and a plurality of pins.
结合第一方面,在一种实施方式中,所述上弦杆的两端设有限位装置8,以用于限制所述上弦杆与塔柱之间的距离。In connection with the first aspect, in one embodiment, limiting devices 8 are provided at both ends of the upper chord rod for limiting the distance between the upper chord rod and the tower column.
第二方面,本申请实施例提供了一种大跨度横梁施工用的装配式桁架的安装方法,基于上述的任意一种装配式桁架进行安装,具体包括以下步骤:In the second aspect, embodiments of the present application provide an installation method of prefabricated trusses for long-span beam construction. The installation is based on any of the above prefabricated trusses, which specifically includes the following steps:
S1:拼接下弦杆、上弦杆和桁架腹杆形成桁架,并在桁架上焊接操作平台;S1: Splice the lower chord, upper chord and truss web rod to form a truss, and weld the operating platform on the truss;
S2:在塔柱的预埋件上焊接支撑组件,并按照施工计划在支撑组件的顶部标记每片桁架的安装位置;S2: Weld the support components on the embedded parts of the tower columns, and mark the installation position of each truss on the top of the support components according to the construction plan;
S3:将多个桁架分批次平行安装至支撑组件的标记位置处,并在桁架之间焊接横向联结系。S3: Install multiple trusses in batches in parallel to the marked positions of the support components, and weld the transverse connections between the trusses.
结合第二方面,在一种实施方式中,所述拼接下弦杆、上弦杆和桁架腹杆形成桁架,并在桁架上焊接操作平台,具体包括以下步骤:Combined with the second aspect, in one embodiment, the lower chord, the upper chord and the truss web are spliced to form a truss, and an operating platform is welded on the truss, which specifically includes the following steps:
S101:拼接下弦杆和上弦杆,并在下弦杆和上弦杆上焊接第二联结系;S101: Splice the lower chord and the upper chord, and weld the second connection system on the lower chord and the upper chord;
S102:将下弦杆、上弦杆和桁架腹杆拼接形成桁架,安装桁架侧面和顶面的螺栓,然后起吊桁架,安装桁架底部的螺栓,并在每个螺栓上进行防松标记;S102: Splice the lower chord, upper chord and truss web to form a truss, install the bolts on the side and top of the truss, then lift the truss, install the bolts at the bottom of the truss, and mark each bolt to prevent loosening;
S103:在每根桁架腹杆的顶部、中部和底部焊接操作平台。S103: Weld operating platforms at the top, middle and bottom of each truss web member.
结合第二方面,在一种实施方式中,所述在塔柱的预埋件上焊接支撑组件,并按照施工计划在支撑组件的顶部标记每片桁架的安装位置,具体包括以下步骤:Combined with the second aspect, in one embodiment, welding the support components on the embedded parts of the tower columns, and marking the installation position of each truss on the top of the support components according to the construction plan, specifically includes the following steps:
S201:在两侧的塔柱中的预埋件上焊接牛腿,并在牛腿的顶部铺设楔块;S201: Weld the corbels on the embedded parts in the tower columns on both sides, and lay wedges on the top of the corbels;
S202:在楔块的顶部装设钢板抄垫,然后在钢板抄垫的顶部安装分配梁;S202: Install a steel plate pad on the top of the wedge block, and then install a distribution beam on the top of the steel plate pad;
S203:按照预先设计的工程计划,在分配梁的顶部确定桁架的安装位置,在每个确定的位置处进行标记,并在每个标记位置处的一侧焊接底部限位件,且每片桁架对应一标记位置。S203: According to the pre-designed engineering plan, determine the installation position of the trusses on the top of the distribution beam, mark each determined position, and weld the bottom limiter on one side of each marked position, and each truss Corresponds to a marked position.
结合第二方面,在一种实施方式中,所述将多个桁架分批次平行安装至支撑组件的标记位置处,并在桁架之间焊接横向联结系,具体包括以下步骤:In conjunction with the second aspect, in one embodiment, the multiple trusses are installed in batches in parallel at marked positions of the support assembly, and transverse connections are welded between the trusses, which specifically includes the following steps:
S301:基于设定安装逻辑进行第一组桁架的安装,进行相邻两桁架间横向联结系的安装,然后基于设定安装逻辑进行第二组桁架的安装,进行相邻两桁架间横向联结系的安装,然后拆除临时撑杆;S301: Install the first group of trusses based on the set installation logic, and install the transverse connection system between two adjacent trusses. Then, install the second group of trusses based on the set installation logic, and perform the transverse connection system between two adjacent trusses. installation, and then remove the temporary struts;
其中,安装完成的每组桁架包括4片桁架,分别为依次平行设置第一片桁架、第二片桁架、第三片桁架和第四片桁架,第一组桁架的第四片桁架与第二组桁架的第四片桁架相邻,所述设定安装逻辑为:Among them, each set of trusses that has been installed includes four trusses, which are the first truss, the second truss, the third truss and the fourth truss arranged in parallel in sequence. The fourth truss of the first set of trusses is connected to the second truss. The fourth truss of the group of trusses is adjacent. The installation logic is as follows:
S311:在第一片桁架的顶部焊接临时撑杆,且临时撑杆的顶端与第一片桁架的顶端相邻,选取第一片桁架的上弦杆的第二联结系为起吊点,采用钢丝绳连接第一片桁架与起吊装置,起吊第一片桁架;S311: Weld the temporary struts on the top of the first truss, and the top of the temporary struts is adjacent to the top of the first truss. Select the second connection of the upper chord of the first truss as the lifting point, and use steel wire ropes to connect it. The first truss and lifting device are used to lift the first truss;
S312:将第一片桁架吊装至第一片桁架对应的标记位置处,在第一片桁架对应标记位置的另一端安装底部限位件;S312: Lift the first truss to the corresponding marked position of the first truss, and install the bottom limiter at the other end of the first truss corresponding to the marked position;
S313:将第一片桁架上临时撑杆的下端与分配梁靠近第一片桁架的端点间焊接;S313: Weld the lower end of the temporary brace on the first truss to the end point of the distribution beam close to the first truss;
S314:在第四片桁架对应标记位置的一端安装底部限位件,选取第四片桁架的上弦杆的第二联结系为起吊点,采用钢丝绳连接第四片桁架与起吊装置,起吊第四片桁架;S314: Install the bottom limiter at one end of the fourth truss corresponding to the marked position, select the second connection system of the upper chord of the fourth truss as the lifting point, use a wire rope to connect the fourth truss and the lifting device, and lift the fourth truss truss;
S315:将第四片桁架吊装至第四片桁架对应的标记位置处,在第四片桁架对应标记位置的另一端安装底部限位件;S315: Lift the fourth truss to the corresponding marked position of the fourth truss, and install the bottom limiter at the other end of the fourth truss corresponding to the marked position;
S316:在第三片桁架对应标记位置的一端安装底部限位件,选取第三片桁架的上弦杆的第二联结系为起吊点,采用钢丝绳连接第三片桁架与起吊装置,起吊第三片桁架;S316: Install the bottom limiter at one end of the third truss corresponding to the marked position, select the second connection of the upper chord of the third truss as the lifting point, use a wire rope to connect the third truss and the lifting device, and lift the third truss truss;
S317:将第三片桁架吊装至第三片桁架对应的标记位置处,在第三片桁架对应标记位置的另一端安装底部限位件;S317: Lift the third truss to the corresponding marked position of the third truss, and install the bottom limiter at the other end of the third truss corresponding to the marked position;
S318:在第二片桁架对应标记位置的一端安装底部限位件,选取第二片桁架的上弦杆的第二联结系为起吊点,采用钢丝绳连接第二片桁架与起吊装置,起吊第二片桁架;S318: Install the bottom limiter on one end of the second truss corresponding to the marked position, select the second connection of the upper chord of the second truss as the lifting point, use a wire rope to connect the second truss and the lifting device, and lift the second truss truss;
S319:将第二片桁架吊装至第二片桁架对应的标记位置处,在第二片桁架对应标记位置的另一端安装底部限位件。S319: Lift the second truss to the corresponding marked position of the second truss, and install the bottom limiter at the other end of the second truss corresponding to the marked position.
本申请实施例提供的技术方案带来的有益效果至少包括:The beneficial effects brought by the technical solutions provided by the embodiments of this application at least include:
1、本申请提供的一种装配式桁架的各杆件之间均为螺栓或销轴连接,可根据不同的施工环境组装不同的桁架;1. The members of the assembled truss provided by this application are all connected by bolts or pins, and different trusses can be assembled according to different construction environments;
2、本申请提供的一种装配式桁架中的桁架组承载能力强,是贝雷梁的数倍,可以满足高原大风环境下的施工要求;2. The truss group in the prefabricated truss provided by this application has a strong load-bearing capacity, several times that of Bailey beams, and can meet the construction requirements in plateau windy environments;
3、本申请提供的一种装配式桁架中设置了三层操作平台,便于桁架组装和检查验收。3. The assembled truss provided by this application is equipped with a three-layer operating platform to facilitate the assembly and inspection of the truss.
附图说明Description of drawings
为了更清楚地说明本申请实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本申请的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings needed to be used in the description of the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present application. For those of ordinary skill in the art, other drawings can also be obtained based on these drawings without exerting creative efforts.
图1为本发明实施例提供的一种大跨度横梁施工用的装配式桁架的结构示意图;Figure 1 is a schematic structural diagram of a prefabricated truss for long-span beam construction provided by an embodiment of the present invention;
图2为本发明实施例提供的一种大跨度横梁施工用的装配式桁架的结构俯视图;Figure 2 is a structural top view of a prefabricated truss for long-span beam construction provided by an embodiment of the present invention;
图3为本发明实施例提供的一种大跨度横梁施工用的装配式桁架的桁架组结构侧视图;Figure 3 is a side view of the truss group structure of a prefabricated truss for long-span beam construction provided by an embodiment of the present invention;
图4为本发明实施例提供的一种大跨度横梁施工用的装配式桁架的操作平台的布置正视图;Figure 4 is a front view of the layout of the operating platform of a prefabricated truss for long-span beam construction provided by an embodiment of the present invention;
图5为本发明实施例提供的一种大跨度横梁施工用的装配式桁架的操作平台的布置侧视图;Figure 5 is a side view of the layout of the operating platform of a prefabricated truss for long-span beam construction provided by an embodiment of the present invention;
图6为本发明实施例提供的一种大跨度横梁施工用的装配式桁架的吊点布置示意图;Figure 6 is a schematic diagram of the suspension point arrangement of a prefabricated truss for long-span beam construction provided by an embodiment of the present invention;
图7为小里程侧第一片桁架的安装示意图;Figure 7 is a schematic diagram of the installation of the first truss on the small mileage side;
图8为小里程侧第二片桁架的安装示意图;Figure 8 is a schematic diagram of the installation of the second truss on the small mileage side;
图9为小里程侧的四片桁架的安装示意图;Figure 9 is a schematic diagram of the installation of the four-piece truss on the small-mileage side;
图10为桁架组的安装示意图;Figure 10 is a schematic diagram of the installation of the truss group;
图中:1、下弦杆;2、桁架腹杆;21、斜向腹杆;22、垂直腹杆;3、上弦杆;4、第一联结系;5、第二联结系;6、操作平台;7、吊耳;8、限位装置;9、横向联结系;91、联结系上弦杆;92、联结系腹杆;93、联结系下弦杆;10、分配梁;11、牛腿;12、钢板抄垫;13、楔块。In the picture: 1. Lower chord; 2. Truss web; 21. Oblique web; 22. Vertical web; 3. Upper chord; 4. First connection; 5. Second connection; 6. Operation platform ; 7. Lifting lugs; 8. Limiting device; 9. Transverse connection system; 91. Connection system upper chord; 92. Connection system web rod; 93. Connection system lower chord; 10. Distribution beam; 11. Corbel; 12 , steel plate copy pad; 13. wedge.
具体实施方式Detailed ways
为使本申请实施例的目的、技术方案和优点更加清楚,下面将结合本申请实施例中的附图,对本申请实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本申请的一部分实施例,而不是全部的实施例。基于本申请中的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所获得的所有其他实施例,都属于本申请保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments These are part of the embodiments of this application, but not all of them. Based on the embodiments in this application, all other embodiments obtained by those of ordinary skill in the art without creative efforts fall within the scope of protection of this application.
本申请实施例提供了一种大跨度横梁施工用的装配式桁架及其安装方法,其能解决现有的施工方法成本高、高空钢结构吊装风险大、施工安全性低且施工工期长的问题。The embodiment of the present application provides a prefabricated truss for long-span beam construction and an installation method thereof, which can solve the problems of high cost of existing construction methods, high risks of hoisting high-altitude steel structures, low construction safety, and long construction period. .
参见图1、图3和图5所示,本申请实施例提供了一种大跨度横梁施工用的装配式桁架,包括桁架组,桁架组包括多个平行设置的桁架,且相邻桁架之间通过横向联结系9相连,桁架包括下弦杆1、上弦杆3以及多根位于下弦杆1和上弦杆3之间的桁架腹杆2,桁架组的底部的每个角处均设有至少两个支撑组件;其中,桁架腹杆2包括多根垂直腹杆21和多根斜向腹杆22,相邻的两根垂直腹杆21之间设有两根斜向腹杆22以形成倒M形,且垂直腹杆21顶部、中部和底部均设有操作平台6。Referring to Figures 1, 3 and 5, embodiments of the present application provide an assembled truss for long-span beam construction, including a truss group. The truss group includes a plurality of trusses arranged in parallel, and between adjacent trusses Connected by a transverse connection 9, the truss includes a lower chord 1, an upper chord 3 and a plurality of truss webs 2 located between the lower chord 1 and the upper chord 3. Each corner of the bottom of the truss group is provided with at least two Support assembly; wherein, the truss web rod 2 includes a plurality of vertical web rods 21 and a plurality of oblique web rods 22, and two oblique web rods 22 are provided between two adjacent vertical web rods 21 to form an inverted M shape. , and the top, middle and bottom of the vertical web rod 21 are provided with operating platforms 6.
本申请实施例提供的一种大跨度横梁施工用的装配式桁架的跨度为31.6m,高度为6m。其中,下弦杆1、上弦杆3和桁架腹杆2均采用新制箱型结构,下弦杆1的截面为380mm×300mm,上弦杆3的截面为388mm×560mm,位于位于正中部的一根垂直腹杆21以及该垂直腹杆21两侧的斜向腹杆22和位于桁架两端的垂直腹杆为受力较小的腹杆,采用2[20b型钢制作,其余的腹杆为受力较大的腹杆,在受力较大的腹杆中,垂直腹杆21采用截面284mm×260mm的新制箱型结构,斜向腹杆22采用截面为为288mm×300mm的新制箱型结构。所有的桁架杆件通过数控加工,等尺寸的杆件可实现完全替换,使得本申请提供的一种装配式桁架可以根据不同的施工环境组装出不同的桁架。同时本申请提供的一种装配式桁架上还装设有多个操作平台6,位于底部的平台用于桁架安装完成后的检查验收,位于中部的平台用于桁架之间的联结系9的施工,位于顶部的平台用于摘钩和施工后期拆除底模。The embodiment of the present application provides a prefabricated truss for long-span beam construction with a span of 31.6m and a height of 6m. Among them, the lower chord 1, the upper chord 3 and the truss web 2 all adopt new box structures. The cross section of the lower chord 1 is 380mm×300mm, and the cross section of the upper chord 3 is 388mm×560mm. They are located on a vertical web in the middle. The rod 21 and the oblique web rods 22 on both sides of the vertical web rod 21 and the vertical web rods at both ends of the truss are web rods with smaller stresses and are made of 2[20b steel. The remaining web rods are with larger stresses. As for the web bars, among the web bars that bear greater stress, the vertical web bar 21 adopts a new box-shaped structure with a cross-section of 284mm×260mm, and the oblique web bar 22 adopts a new box-shaped structure with a cross-section of 288mm×300mm. All truss rods are processed by CNC, and rods of equal size can be completely replaced, so that the assembled truss provided by this application can assemble different trusses according to different construction environments. At the same time, the assembled truss provided by this application is also equipped with multiple operating platforms 6. The platform located at the bottom is used for inspection and acceptance after the truss is installed, and the platform located in the middle is used for the construction of the connection system 9 between the trusses. , the platform located at the top is used for unhooking and dismantling the bottom formwork in the later stages of construction.
作为可选的实施例方式,参见图2和图3所示,横向联结系9包括联结系上弦杆91、联结系腹杆92和联结系下弦杆93,联结上弦杆91与联结系下弦杆93相互平行,联结系腹杆92的一端与联结系上弦杆91相连,另一端与联结系下弦杆93相连,且横向联结系9为Z字型。每两个相邻的桁架之间的横向联结系9与垂直腹杆21一一对应相连,在垂直腹杆21的中部焊接带孔的钢板,联结系上弦杆91和联结系下弦杆93的两端通过长条螺栓与相邻桁架的垂直腹杆21上的带孔钢板连接。结系上弦杆91、联结系腹杆92和联结系下弦杆93均采用HW200×200/2[20b型钢制成,以增强面外稳定性。As an optional embodiment, as shown in Figures 2 and 3, the transverse connecting system 9 includes an upper connecting chord 91, a connecting web 92 and a lower connecting chord 93. The upper connecting chord 91 and the lower connecting chord 93 Parallel to each other, one end of the connecting system web rod 92 is connected to the connecting system upper chord 91 and the other end is connected to the connecting system lower chord 93, and the transverse connecting system 9 is Z-shaped. The transverse connection system 9 between every two adjacent trusses is connected to the vertical web rod 21 in a one-to-one correspondence. A steel plate with holes is welded in the middle of the vertical web rod 21. The upper chord bar 91 and the lower chord bar 93 are connected to each other. The end is connected to the perforated steel plate on the vertical web rod 21 of the adjacent truss through a long bolt. The upper chord bar 91 of the knot system, the web bar 92 of the connecting system and the lower chord bar 93 of the connecting system are all made of HW200×200/2[20b steel to enhance the out-of-plane stability.
作为可选的实施例方式,参见图1和图7所示,支撑组件包括分配梁10和牛腿11,牛腿11与塔柱相连,分配梁10架设在牛腿11上,且分配梁10和牛腿11之间设有钢板抄垫12和楔块13。分配梁10采用2HN800×300型钢,牛腿11采用厚度为30mm及厚度为20mm的钢板焊制。As an optional embodiment, as shown in Figures 1 and 7, the support assembly includes a distribution beam 10 and a corbel 11. The corbel 11 is connected to the tower column. The distribution beam 10 is erected on the corbel 11, and the distribution beam 10 and the corbel are Steel plate pads 12 and wedges 13 are provided between the legs 11 . The distribution beam 10 is made of 2HN800×300 steel, and the corbels 11 are welded by steel plates with a thickness of 30mm and a thickness of 20mm.
作为可选的实施例方式,参见图1、图2和图4所示,下弦杆1包括三根下弦短杆,下弦短杆首尾相连,且相邻的两个下弦短杆之间的连接处均设有第一联结系4;上弦杆3包括五根上弦短杆,上弦短杆首尾相连,且相邻的两个上弦短杆之间的连接处均设有第一联结系4;其中,第一联结系4包括四片钢板和多个长条螺栓。在连接相邻两个杆件时,先在相邻两个杆件之间的顶面、侧面和底面上均焊接钢板,然后将长条螺栓穿过钢板与杆件,进一步的将杆件和钢板固定在一起,以保证杆件和钢板之间不会发生相对移动,确保相邻两个杆件之间的连接的稳定性。As an optional embodiment, as shown in Figure 1, Figure 2 and Figure 4, the lower chord bar 1 includes three lower chord short bars, the lower chord short bars are connected end to end, and the connections between the two adjacent lower chord short bars are evenly spaced. A first connecting system 4 is provided; the upper chord rod 3 includes five upper chord short rods, the upper chord short rods are connected end to end, and the connection between two adjacent upper chord short rods is provided with a first connecting system 4; wherein, the first connecting system 4 is provided. A connecting system 4 includes four steel plates and a plurality of long bolts. When connecting two adjacent rods, first weld steel plates on the top, side and bottom surfaces between the two adjacent rods, then pass long bolts through the steel plates and rods, and further connect the rods and The steel plates are fixed together to ensure that there will be no relative movement between the rods and the steel plates, ensuring the stability of the connection between two adjacent rods.
作为可选的实施例方式,参见图1和图6所示,桁架腹杆22与下弦杆1的连接处均设有第二联结系5,且桁架腹杆22与上弦杆3的连接处均设有第二联结系5;其中,第二联结系5包括吊耳和多个销轴。桁架腹杆22通过与吊耳相连,间接地与上弦杆3和下弦杆1相连,上弦杆3和下弦杆1上均设有五个用于连接垂直腹杆21的吊耳和4个用于连接斜向腹杆22的吊耳。As an optional embodiment, as shown in Figures 1 and 6, the connections between the truss web 22 and the lower chord 1 are provided with second connecting systems 5, and the connections between the truss web 22 and the upper chord 3 are A second connection system 5 is provided; wherein the second connection system 5 includes lifting lugs and a plurality of pins. The truss web rod 22 is connected to the lifting lugs and indirectly connected to the upper chord 3 and the lower chord 1. Both the upper chord 3 and the lower chord 1 are provided with five lifting lugs for connecting the vertical web rods 21 and 4 lifting lugs for connecting the vertical web rods 21. Lifting lugs connected to the oblique web rods 22.
作为可选的实施例方式,参见图1所示,上弦杆3的两端设有限位装置8,以用于限制上弦杆3与塔柱之间的距离。限位装置8用于确保上弦杆3与塔柱之间的距离,上弦杆3的两端通过限位装置8与塔柱相连,保证了上弦杆3在水平方向上不会发生晃动,确保了本申请提供的一种装配式桁架的结构的稳定性。As an optional embodiment, as shown in FIG. 1 , limiting devices 8 are provided at both ends of the upper chord 3 for limiting the distance between the upper chord 3 and the tower column. The limiting device 8 is used to ensure the distance between the upper chord 3 and the tower column. The two ends of the upper chord 3 are connected to the tower column through the limiting device 8, ensuring that the upper chord 3 will not shake in the horizontal direction, ensuring that This application provides the structural stability of an assembled truss.
参见图6、图7、图8、图9和图10所示,本申请还提供一种大跨度横梁施工用的装配式桁架的安装方法,基于上述任意一项的装配式桁架进行安装,具体包括以下步骤:Referring to Figures 6, 7, 8, 9 and 10, this application also provides an installation method of a prefabricated truss for large-span beam construction, which is based on any of the above prefabricated trusses. Specifically, Includes the following steps:
S1:拼接下弦杆1、上弦杆3和桁架腹杆2形成桁架,并在桁架上焊接操作平台6;S1: Splice the lower chord 1, the upper chord 3 and the truss web 2 to form a truss, and weld the operating platform 6 on the truss;
S2:在塔柱的预埋件上焊接支撑组件,并按照施工计划在支撑组件的顶部标记每片桁架的安装位置;S2: Weld the support components on the embedded parts of the tower columns, and mark the installation position of each truss on the top of the support components according to the construction plan;
S3:将多个桁架分批次平行安装至支撑组件的标记位置处,并在桁架之间焊接横向联结系9。S3: Install multiple trusses in batches in parallel to the marked positions of the support components, and weld the transverse connections 9 between the trusses.
在步骤S1中,先按照桁架结构对桁架进行组装,同时在桁架上焊接操作平台6以便于工作人员在后续步骤中对桁架进行施工操作。In step S1, the truss is first assembled according to the truss structure, and at the same time, the operating platform 6 is welded on the truss to facilitate the staff to perform construction operations on the truss in subsequent steps.
在步骤S2中,在建造塔柱时即放置好预埋件,预埋件采用预埋开孔板连接件形式,开孔板件厚30mm,穿入φ20HRB400E钢筋,所穿入钢筋的长度为1050mm,锚板辅以焊接φ22mm的ML15剪力钉,预埋钢板的材质均采用镀锌或不锈钢板。按照工作人员预先设计好的施工计划,在支撑组件的顶部标记每片桁架的安装位置,在后续对桁架进行下放时,只需按照标记位置下放即可,提高了施工效率,确保了桁架安装的准确性。In step S2, the embedded parts are placed when building the tower columns. The embedded parts are in the form of embedded perforated plate connectors. The perforated plate parts are 30mm thick and φ20HRB400E steel bars are inserted. The length of the inserted steel bars is 1050mm. , the anchor plate is supplemented by welding φ22mm ML15 shear nails, and the embedded steel plates are all made of galvanized or stainless steel plates. According to the construction plan pre-designed by the staff, mark the installation position of each truss on the top of the support assembly. When lowering the trusses later, you only need to lower them according to the marked position, which improves construction efficiency and ensures the safety of truss installation. accuracy.
在步骤S3中,对桁架进行吊装组合,完成本申请提供的一种装配式桁架的构建。In step S3, the trusses are hoisted and assembled to complete the construction of an assembled truss provided by this application.
作为可选的实施例方式,参见图4、图5和图6所示,拼接下弦杆1、上弦杆3和桁架腹杆2形成桁架,并在桁架上焊接操作平台6,具体包括以下步骤:As an optional embodiment, as shown in Figures 4, 5 and 6, the lower chord 1, the upper chord 3 and the truss web 2 are spliced to form a truss, and the operating platform 6 is welded on the truss, which specifically includes the following steps:
S101:拼接下弦杆1和上弦杆3,并在下弦杆1和上弦杆3上焊接第二联结系5;S101: Splice the lower chord 1 and the upper chord 3, and weld the second connection 5 on the lower chord 1 and the upper chord 3;
S102:将下弦杆1、上弦杆3和桁架腹杆2拼接形成桁架,安装桁架侧面和顶面的螺栓,然后起吊桁架,安装桁架底部的螺栓,并在每个螺栓上进行防松标记;S102: Splice the lower chord 1, the upper chord 3 and the truss web 2 to form a truss, install the bolts on the side and top of the truss, then lift the truss, install the bolts at the bottom of the truss, and mark each bolt to prevent loosening;
S103:在每根桁架腹杆2的顶部、中部和底部焊接操作平台6。S103: Weld the operating platform 6 at the top, middle and bottom of each truss web rod 2.
在步骤S101中,先将三个下弦短杆拼接成下弦杆1,将五个上弦短杆拼接成上弦杆3,且拼接处均设有第一联结系4,然后在下弦杆1和上弦杆3上的对应位置焊接第二联结系5,等待后续拼装;In step S101, three lower chord short poles are first spliced into lower chord poles 1, and five upper chord short poles are spliced into upper chord poles 3, and the first connection system 4 is provided at the splicing joints, and then the lower chord poles 1 and the upper chord poles are spliced together. Weld the second connection system 5 at the corresponding position on 3 and wait for subsequent assembly;
在步骤S102中,将多根桁架腹杆2通过第二联结系5与下弦杆1和上弦杆3相连,组合形成桁架,在拼装时可以通过两台25t的汽车吊和上下游塔吊辅助拼装工作进行。在拼装好桁架后,先安装桁架侧面和顶面的螺栓,然后通过两台25t的汽车吊起吊桁架,对桁架进行局部抄垫后,安装桁架底部的螺栓。螺栓采用M24型号且施拧扭矩为630-860N·m的螺栓,在施拧到位后采用记号笔在螺母与连接板上做好防松标记,以记录螺母的当前位置。In step S102, multiple truss web rods 2 are connected to the lower chord 1 and the upper chord 3 through the second connection system 5, and are combined to form a truss. During assembly, the assembly work can be assisted by two 25t truck cranes and upstream and downstream tower cranes. conduct. After assembling the truss, first install the bolts on the sides and top of the truss, then lift the truss using two 25t trucks, partially pad the truss, and then install the bolts at the bottom of the truss. The bolts are M24 type with a tightening torque of 630-860N·m. After the bolts are tightened in place, use a marker to mark the nut and the connecting plate to prevent loosening to record the current position of the nut.
在步骤S103中,通过25t的汽车吊将桁架立起,在桁架的两侧先设置临时支撑,对桁架进行焊接操作平台6的施工,共设置3层操作平台6,底部平台设置在垂直腹杆21正下方的下弦杆1上,中部平台设置垂直腹杆21的中间位置,顶部平台设置在垂直腹杆21正上方的上弦杆3上。底部平台用于安装完成后检查验收,中部平台用于桁架之间的横向联结系9的施工,顶部平台用于摘钩和后期拆除底模使用。In step S103, the truss is erected by a 25t truck crane, temporary supports are first set up on both sides of the truss, and the welding operation platform 6 is constructed on the truss. A total of 3 layers of operation platforms 6 are set up, and the bottom platform is set on the vertical web rod. On the lower chord 1 just below 21, the middle platform is set at the middle position of the vertical web 21, and the top platform is set on the upper chord 3 just above the vertical web 21. The bottom platform is used for inspection and acceptance after installation is completed, the middle platform is used for the construction of the transverse connection system 9 between the trusses, and the top platform is used for unhooking and later dismantling the bottom formwork.
作为可选的实施例方式,参见图7所示,在塔柱的预埋件上焊接支撑组件,并按照施工计划在支撑组件的顶部标记每片桁架的安装位置,具体包括以下步骤:As an optional embodiment, see Figure 7, weld the support components on the embedded parts of the tower columns, and mark the installation position of each truss on the top of the support components according to the construction plan, which specifically includes the following steps:
S201:在两侧的塔柱中的预埋件上焊接牛腿11,并在牛腿11的顶部铺设楔块13;S201: Weld the corbels 11 on the embedded parts in the tower columns on both sides, and lay wedges 13 on the top of the corbels 11;
S202:在楔块13的顶部装设钢板抄垫12,然后在钢板抄垫12的顶部安装分配梁10;S202: Install the steel plate pad 12 on the top of the wedge 13, and then install the distribution beam 10 on the top of the steel plate pad 12;
S203:按照预先设计的工程计划,在分配梁10的顶部确定桁架的安装位置,在每个确定的位置处进行标记,并在每个标记位置处的一侧焊接底部限位件,且每片桁架对应一标记位置。S203: According to the pre-designed engineering plan, determine the installation position of the truss on the top of the distribution beam 10, mark each determined position, and weld the bottom limiter on one side of each marked position, and each piece The truss corresponds to a marked position.
在步骤S201中,现在在两侧的塔柱中的预埋件上焊接牛腿11,每个牛腿11均需通过6根规格为JL1080-φ40精轧螺纹钢筋与预埋件相连,每根螺纹钢预张拉60t。In step S201, the corbels 11 are now welded to the embedded parts in the tower columns on both sides. Each corbel 11 needs to be connected to the embedded parts through 6 JL1080-φ40 precision-rolled threaded steel bars. Each corbel 11 Rebar pre-tensioned 60t.
在步骤S202中,分配梁10纵向固定在楔块13上,工作人员需要确保分配梁10与楔块13之间的连接稳定,以保证在吊装桁架时,分配梁10不会出现移动。In step S202, the distribution beam 10 is longitudinally fixed on the wedge block 13. The staff needs to ensure that the connection between the distribution beam 10 and the wedge block 13 is stable to ensure that the distribution beam 10 will not move when the truss is hoisted.
在步骤S203中,确定每个桁架的放置位置,并现安装一侧的底部限位件,以用于在吊装桁架时,对桁架进行一个初步的限位,在桁架吊装到位后再将另一侧的底部限位件焊接上,已完成对桁架的限位。In step S203, the placement position of each truss is determined, and the bottom limiter on one side is installed to provide a preliminary limit to the truss when the truss is hoisted. After the truss is hoisted in place, the other side is installed. The bottom limiters on the side are welded on, and the limits on the trusses are completed.
作为可选的实施例方式,参见图7、图8、图9和图10所示,将多个桁架分批次平行安装至支撑组件的标记位置处,并在桁架之间焊接横向联结系9,具体包括以下步骤:As an optional embodiment, as shown in Figures 7, 8, 9 and 10, multiple trusses are installed in batches in parallel to the marked positions of the support assembly, and transverse connections 9 are welded between the trusses. , specifically including the following steps:
S301:基于设定安装逻辑进行第一组桁架的安装,进行相邻两桁架间横向联结系9的安装,然后基于设定安装逻辑进行第二组桁架的安装,进行相邻两桁架间横向联结系9的安装,然后拆除临时撑杆;S301: Install the first group of trusses based on the set installation logic, and install the lateral connection system 9 between two adjacent trusses, and then install the second group of trusses based on the set installation logic, and perform the lateral connection between the two adjacent trusses. Installation of tie 9, and then removal of temporary braces;
在步骤S301中,先将多片桁架分为两组进行安装,然后拆除安装过程中焊接上的固定装置,即可完成本申请提供的一种装配式桁架的安装。In step S301, first divide the multiple trusses into two groups for installation, and then remove the fixing devices welded during the installation process to complete the installation of the prefabricated truss provided by this application.
其中,安装完成的每组桁架包括4片桁架,分别为依次平行设置第一片桁架、第二片桁架、第三片桁架和第四片桁架,第一组桁架的第四片桁架与第二组桁架的第四片桁架相邻,设定安装逻辑为:Among them, each set of trusses that has been installed includes four trusses, which are the first truss, the second truss, the third truss and the fourth truss arranged in parallel in sequence. The fourth truss of the first set of trusses is connected to the second truss. The fourth truss of the group truss is adjacent, and the installation logic is set as:
S311:在第一片桁架的顶部焊接临时撑杆,且临时撑杆的顶端与第一片桁架的顶端相邻,选取第一片桁架的上弦杆3的第二联结系5为起吊点,采用钢丝绳连接第一片桁架与起吊装置,起吊第一片桁架;S311: Weld the temporary struts on the top of the first truss, and the top of the temporary struts is adjacent to the top of the first truss. Select the second connection 5 of the upper chord 3 of the first truss as the lifting point. Use The steel wire rope connects the first truss and the lifting device to lift the first truss;
S312:将第一片桁架吊装至第一片桁架对应的标记位置处,在第一片桁架对应标记位置的另一端安装底部限位件;S312: Lift the first truss to the corresponding marked position of the first truss, and install the bottom limiter at the other end of the first truss corresponding to the marked position;
S313:将第一片桁架上临时撑杆的下端与分配梁10靠近第一片桁架的端点间焊接;S313: Weld the lower end of the temporary brace on the first truss to the end point of the distribution beam 10 close to the first truss;
S314:在第四片桁架对应标记位置的一端安装底部限位件,选取第四片桁架的上弦杆3的第二联结系5为起吊点,采用钢丝绳连接第四片桁架与起吊装置,起吊第四片桁架;S314: Install the bottom limiter at one end of the fourth truss corresponding to the marked position, select the second connection 5 of the upper chord 3 of the fourth truss as the lifting point, use a wire rope to connect the fourth truss and the lifting device, and lift the fourth truss. four-piece trusses;
S315:将第四片桁架吊装至第四片桁架对应的标记位置处,在第四片桁架对应标记位置的另一端安装底部限位件;S315: Lift the fourth truss to the corresponding marked position of the fourth truss, and install the bottom limiter at the other end of the fourth truss corresponding to the marked position;
S316:在第三片桁架对应标记位置的一端安装底部限位件,选取第三片桁架的上弦杆3的第二联结系5为起吊点,采用钢丝绳连接第三片桁架与起吊装置,起吊第三片桁架;S316: Install the bottom limiter on one end of the third truss corresponding to the marked position, select the second connection 5 of the upper chord 3 of the third truss as the lifting point, use a wire rope to connect the third truss and the lifting device, and lift the third truss. three-piece truss;
S317:将第三片桁架吊装至第三片桁架对应的标记位置处,在第三片桁架对应标记位置的另一端安装底部限位件;S317: Lift the third truss to the corresponding marked position of the third truss, and install the bottom limiter at the other end of the third truss corresponding to the marked position;
S318:在第二片桁架对应标记位置的一端安装底部限位件,选取第二片桁架的上弦杆3的第二联结系5为起吊点,采用钢丝绳连接第二片桁架与起吊装置,起吊第二片桁架;S318: Install the bottom limiter at one end of the second truss corresponding to the marked position, select the second connection 5 of the upper chord 3 of the second truss as the lifting point, use a wire rope to connect the second truss and the lifting device, and lift the second truss. two-piece truss;
S319:将第二片桁架吊装至第二片桁架对应的标记位置处,在第二片桁架对应标记位置的另一端安装底部限位件。S319: Lift the second truss to the corresponding marked position of the second truss, and install the bottom limiter at the other end of the second truss corresponding to the marked position.
在步骤S311中,先在第一片桁架的顶部焊接临时撑杆,当将第一片桁架焊接至分配梁10上时,可以通过将临时撑杆焊接在分配梁10上,以达到固定并限位第一片桁架的目的,临时撑杆采用工25型钢。同时在起吊时,采用两台塔吊抬吊,为避免起吊时桁架出现旁弯,采用4根φ32mm钢丝绳,每根钢丝绳长10m,用4个17t卸扣起吊。吊点布置在上弦杆3的吊耳处,采用钢丝绳绕过上弦杆3进行捆绑吊装。In step S311, temporary struts are first welded on the top of the first truss. When the first truss is welded to the distribution beam 10, the temporary struts can be welded to the distribution beam 10 to achieve fixation and limitation. For the purpose of the first truss, the temporary support rods are made of I-25 steel. At the same time, two tower cranes are used for lifting. In order to avoid side bending of the truss during lifting, four φ32mm steel wire ropes are used. Each steel wire rope is 10m long and four 17t shackles are used for lifting. The lifting point is arranged at the lifting eye of the upper chord 3, and the steel wire rope is used to wrap around the upper chord 3 for bundling and lifting.
在步骤S312中,在第一片桁架吊装至第一片桁架对应的标记位置处后,焊接第一片桁架另一侧的底部限位件,以对第一片桁架进行初步固定。In step S312, after the first truss is hoisted to the corresponding marked position of the first truss, the bottom limiter on the other side of the first truss is welded to preliminarily fix the first truss.
在步骤S313中,将临时撑杆与分配梁10焊接在一起,进一步的固定第一片桁架,并对第一片桁架进行限位。In step S313, the temporary support rod and the distribution beam 10 are welded together, the first truss is further fixed, and the first truss is limited.
在步骤S314至步骤S319中,依次对组中的第四片、第三片和第二片桁架进行吊装以及限位固定,完成该组的所有桁片的吊装作业后,焊接相邻两片桁架之间的横向联结系9,然后进行下一组桁架的吊装作业,并焊接下一组桁架中的相邻两片桁架之间的横向联结系9。在吊装完全部桁架后,焊接两组桁架之间的横向联结系9,完成本申请提供的一种装配式桁架的安装,然后拆除本申请提供的一种装配式桁架两侧的临时撑杆。In steps S314 to S319, the fourth, third and second trusses in the group are hoisted and limited fixed in sequence. After completing the hoisting operation of all trusses in the group, two adjacent trusses are welded. The lateral connection system 9 between them is then carried out to hoist the next set of trusses, and the lateral connection system 9 between the two adjacent trusses in the next set of trusses is welded. After all the trusses are hoisted, the transverse connection system 9 between the two sets of trusses is welded to complete the installation of the prefabricated truss provided by this application, and then the temporary braces on both sides of the prefabricated truss provided by this application are removed.
在本申请的描述中,需要说明的是,术语“上”、“下”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本申请和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本申请的限制。除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本申请中的具体含义。In the description of this application, it should be noted that the orientation or positional relationship indicated by terms such as "upper" and "lower" is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing this application and simplifying the description. It is not intended to indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore should not be construed as a limitation on the present application. Unless otherwise clearly stated and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, It can also be an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be an internal connection between two components. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.
需要说明的是,在本申请中,诸如“第一”和“第二”等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。It should be noted that in this application, relational terms such as “first” and “second” are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply There is no such actual relationship or sequence between these entities or operations. Furthermore, the terms "comprises," "comprises," or any other variations thereof are intended to cover a non-exclusive inclusion such that a process, method, article, or apparatus that includes a list of elements includes not only those elements, but also those not expressly listed other elements, or elements inherent to the process, method, article or equipment. Without further limitation, an element defined by the statement "comprises a..." does not exclude the presence of additional identical elements in a process, method, article, or apparatus that includes the stated element.
以上所述仅是本申请的具体实施方式,使本领域技术人员能够理解或实现本申请。对这些实施例的多种修改对本领域的技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本申请的精神或范围的情况下,在其它实施例中实现。因此,本申请将不会被限制于本文所示的这些实施例,而是要符合与本文所申请的原理和新颖特点相一致的最宽的范围。The above descriptions are only specific embodiments of the present application, enabling those skilled in the art to understand or implement the present application. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be practiced in other embodiments without departing from the spirit or scope of the application. Thus, the present application is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features claimed herein.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202311691776.8A CN117661463A (en) | 2023-12-11 | 2023-12-11 | Assembled truss for large-span beam construction and installation method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202311691776.8A CN117661463A (en) | 2023-12-11 | 2023-12-11 | Assembled truss for large-span beam construction and installation method thereof |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN117661463A true CN117661463A (en) | 2024-03-08 |
Family
ID=90067885
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202311691776.8A Pending CN117661463A (en) | 2023-12-11 | 2023-12-11 | Assembled truss for large-span beam construction and installation method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN117661463A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN118894217A (en) * | 2024-10-09 | 2024-11-05 | 沪东中华造船(集团)有限公司 | A kind of enclosure system installation platform and installation method |
-
2023
- 2023-12-11 CN CN202311691776.8A patent/CN117661463A/en active Pending
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN118894217A (en) * | 2024-10-09 | 2024-11-05 | 沪东中华造船(集团)有限公司 | A kind of enclosure system installation platform and installation method |
| WO2026077199A1 (en) * | 2024-10-09 | 2026-04-16 | 沪东中华造船(集团)有限公司 | Containment system installation platform and installation method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN208072213U (en) | A kind of steel box-girder installation temporary support | |
| CN103614967B (en) | A kind of stiff skeleton and utilize it to carry out the method for bridge king-post construction | |
| CN106149572A (en) | A kind of beam bridge ruggedized construction and reinforcement means | |
| CN104929373A (en) | Large-span square steel pipe truss and accumulative sliding construction method thereof | |
| CN103255838A (en) | Construction method with adoption of large-tonnage long-stroke oil cylinder jacking mold frame | |
| CN101555680B (en) | Large-span Pi type socle beam construction process in non-rope area of cable stayed bridge | |
| CN115288449A (en) | Construction method of middle support installation of large-span grid frame | |
| CN111395850A (en) | A prefabricated tower and erection method for a cable hoisting system | |
| CN110241727A (en) | A kind of cable tower structure and bridge | |
| CN114892874A (en) | A kind of containment long-span dome and its construction method | |
| CN117661463A (en) | Assembled truss for large-span beam construction and installation method thereof | |
| CN110318344A (en) | A kind of No. 0 block bracket of novel steel box-girder and No. 0 block erection construction method | |
| CN213204915U (en) | Overweight overhanging suspended component supporting system of super high-rise residential conversion layer | |
| CN109653517B (en) | Multidirectional unloading system and construction method for assembling steel corridor by using same | |
| CN114086473B (en) | High pier cast-in-situ beam bracket and construction method thereof | |
| CN207227957U (en) | Pier body construction safety protection platform | |
| CN106758855B (en) | Arc-shaped pier cap construction arch support component and arc-shaped pier cap construction method | |
| CN111593874B (en) | Support system and construction method for super-high-rise residential transfer layer super-heavy cantilevered components | |
| CN108797350B (en) | Tower column inner and outer stiff skeleton device and construction method thereof | |
| CN111472285A (en) | A method for installing the main bridge variable-section continuous steel truss girder using cable crane | |
| CN201209237Y (en) | Multi-beam-section bracket of movable formwork | |
| CN104961058A (en) | Double-Z-type supporting steel girder, crane supporting component with same and use method | |
| CN212611918U (en) | Connecting structure of steel plate beam | |
| CN116657875A (en) | Cantilever steel structure construction platform with formwork system and construction method | |
| CN210917011U (en) | Cable tower structure and bridge |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |