CN117627312A - Cantilever operation frame for high-altitude construction and construction method thereof - Google Patents

Cantilever operation frame for high-altitude construction and construction method thereof Download PDF

Info

Publication number
CN117627312A
CN117627312A CN202311681770.2A CN202311681770A CN117627312A CN 117627312 A CN117627312 A CN 117627312A CN 202311681770 A CN202311681770 A CN 202311681770A CN 117627312 A CN117627312 A CN 117627312A
Authority
CN
China
Prior art keywords
truss
cantilever
trusses
construction
overhanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311681770.2A
Other languages
Chinese (zh)
Inventor
马吉星
代威
王巧
刘奕玮
张峰
王超凡
钟伟雄
李勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202311681770.2A priority Critical patent/CN117627312A/en
Publication of CN117627312A publication Critical patent/CN117627312A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/15Scaffolds primarily resting on the ground essentially comprising special means for supporting or forming platforms; Platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/18Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by cantilevers or other provisions mounted in openings in the building, e.g. window openings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/20Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/001Safety or protective measures against falling down relating to scaffoldings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/007Devices and methods for erecting scaffolds, e.g. automatic scaffold erectors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/046Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to an overhanging operation frame for high-altitude construction and a construction method thereof, and relates to the technical field of high-altitude overhanging operation frame construction, wherein the overhanging operation frame comprises overhanging trusses, the overhanging trusses are formed by erecting a plurality of single truss in parallel, the front sections of the overhanging trusses are fixed in a room through stabilizing frames and are tightly propped by propping up rods, the rear sections of the overhanging trusses extend out of the room and are tightly pulled by diagonal tension rods, and a single truss is at least matched with two propping up rods and one diagonal tension rod for fixation, so that the load born by the rear sections of the overhanging trusses is improved, and the safety in construction is ensured; a scaffold board is paved on the cantilever truss; the single truss is connected and assembled by adopting the fastener type steel pipes, two adjacent single trusses are connected by adopting the fastener type steel pipes, the tightening rod and the diagonal draw bar are both made of the fastener type steel pipes, the whole fastener type steel pipes are used as main bearing structures, the requirement on the overhanging operation frame in high-altitude construction is completed by using simpler materials and processes, the construction efficiency is improved, and the construction cost is reduced.

Description

一种用于高空施工的悬挑作业架及其施工方法A cantilevered work frame for high-altitude construction and its construction method

技术领域Technical field

本发明涉及高空悬挑作业架施工技术领域,尤其是涉及一种用于高空施工的悬挑作业架及其施工方法。The invention relates to the technical field of high-altitude cantilevered work frame construction, and in particular to a cantilevered work frame for high-altitude construction and a construction method thereof.

背景技术Background technique

现有技术中,传统的悬挑作业架采用型钢作为支撑梁,并在型钢上搭设钢管架,造价高,施工工期长,且型钢重量大,工人的劳动强度大,需要在墙体上打孔,增加安装工序的同时容易产生渗漏,同时,悬挑桁架后段承载力无法满足施工需求,施工人员在悬挑作业架上施工的安全性得不到保障。In the existing technology, the traditional cantilevered work frame uses shaped steel as the supporting beam, and sets up a steel pipe frame on the shaped steel. The cost is high, the construction period is long, and the shaped steel is heavy, labor intensity is high for workers, and holes need to be drilled in the wall. , while increasing the installation process, it is easy to cause leakage. At the same time, the bearing capacity of the rear section of the cantilever truss cannot meet the construction needs, and the safety of construction personnel working on the cantilever work frame cannot be guaranteed.

发明内容Contents of the invention

为了改善上述背景技术中悬挑作业架施工的缺陷,本发明提供一种用于高空施工的悬挑作业架及其施工方法。In order to improve the deficiencies in the construction of cantilevered work frames in the above background technology, the present invention provides a cantilevered work frame for high-altitude construction and a construction method thereof.

本发明提供的一种用于高空施工的悬挑作业架及其施工方法采用如下的技术方案:The invention provides a cantilevered work frame for high-altitude construction and its construction method using the following technical solutions:

一种用于高空施工的悬挑作业架,包括悬挑桁架,所述悬挑桁架采用多片单榀桁架平行搭设,所述悬挑桁架通过墙体分隔为悬挑桁架前段和悬挑桁架后段,所述悬挑桁架前段通过稳定架固定在屋内并通过顶紧杆顶紧,所述悬挑桁架后段延伸到屋外并通过斜拉杆拉紧,单片单榀桁架至少搭配两条顶紧杆和一条斜拉杆进行固定,提高悬挑桁架后段的承载力,保障施工人员在悬挑作业架上施工的安全性;所述悬挑桁架上铺设有脚手板,所述悬挑桁架外端安装防护栏并挂设密目安全网,方便施工人员进行施工,保证施工人员安全。A cantilever work frame for high-altitude construction, including a cantilever truss. The cantilever truss is set up in parallel with multiple single-piece trusses. The cantilever truss is divided into a front section of the cantilever truss and a rear section of the cantilever truss through a wall. The front section of the cantilever truss is fixed inside the house through a stabilizer and is tightened by jacking rods. The rear section of the cantilever truss extends outside the house and is tightened by diagonal tie rods. The single-piece single-frame truss is equipped with at least two jacking rods. The rod and a diagonal tie rod are fixed to improve the bearing capacity of the rear section of the cantilever truss and ensure the safety of construction workers on the cantilever work frame; scaffolding boards are laid on the cantilever truss, and the outer end of the cantilever truss Install protective fences and hang dense mesh safety nets to facilitate construction workers and ensure their safety.

优选的,所述顶紧杆和斜拉杆均采用扣件式钢管,所述顶紧杆的一端顶紧在墙体内侧且另一端分别连接在单榀桁架前段和稳定架上;所述斜拉杆的一端连接在稳定架上且另一端连接在单榀桁架后段。Preferably, the clamping rod and the diagonal tie rod are both made of fastener steel pipes. One end of the jacking rod is fastened to the inside of the wall and the other end is connected to the front section of the single truss and the stabilizer respectively; the diagonal tie rod One end is connected to the stabilizer and the other end is connected to the rear section of the single truss.

优选的,所述单榀桁架采用扣件式钢管连接拼装,相邻两片单榀桁架之间通过扣件式钢管连接。Preferably, the single-frame trusses are assembled and connected by fastener-type steel pipes, and two adjacent single-frame trusses are connected by fastener-type steel pipes.

一种用于高空施工的悬挑作业架的施工方法,包括以下步骤:A construction method of a cantilevered work frame for high-altitude construction, including the following steps:

S1、在施工现场进行测量放线定位;S1. Conduct measurement and setting out positioning at the construction site;

S2、预拼装单榀桁架;S2, pre-assembled single truss;

S3、将两片预拼装好的单榀桁架在屋内立起并组装成两榀的悬挑桁架,根据现场放线确定两片单榀桁架之间的间距不大于1.5m;S3. Erect the two pre-assembled single-frame trusses in the house and assemble them into a two-frame cantilever truss. According to the on-site wiring, determine that the distance between the two single-frame trusses is not greater than 1.5m;

S4、将两榀的悬挑桁架滑移至放线好的位置;S4. Slide the two cantilever trusses to the position where the wiring is good;

S5、将第三片预拼装好的单榀桁架搬运到两榀的悬挑桁架一侧并组装成三榀的悬挑桁架,根据现场放线确定第三片单榀桁架与两榀的悬挑桁架之间的间距不大于1.5m;S5. Move the third piece of pre-assembled single-frame truss to one side of the two-frame cantilever truss and assemble it into a three-frame cantilever truss. Determine the third piece of single-frame truss and the two-frame cantilever according to the on-site laying out. The spacing between trusses shall not be greater than 1.5m;

S6、在屋内搭设落地式的作业脚手架,同时兼做稳定架,将三榀的悬挑桁架与稳定架通过扣件式钢管连接固定;S6. Set up floor-standing work scaffolding in the house, which also serves as a stabilizer, and connect and fix the three cantilever trusses and stabilizers through fastener-type steel pipes;

S7、按上述步骤重复安装后续的悬挑桁架和稳定架,至全部完成;S7. Repeat the above steps to install the subsequent cantilever trusses and stabilizers until all are completed;

S8、拉设斜拉杆并安装顶紧杆,单片单榀桁架至少搭配两条顶紧杆和一条斜拉杆进行固定;S8. Stretch the diagonal tie rods and install the jacking rods. The single-piece single-frame truss should be fixed with at least two jacking rods and one diagonal tie rod;

S9、在悬挑桁架上铺设脚手板,在悬挑桁架外端安装防护栏并挂设密目安全网,密目安全网高度不低于1.5m;S9. Lay scaffolding boards on the cantilever trusses, install protective fences at the outer ends of the cantilever trusses and hang dense-mesh safety nets. The height of the dense-mesh safety nets shall not be less than 1.5m;

S10、检测验收合格。S10. Pass the inspection and acceptance.

综上所述,本发明具有如下的有益技术效果:To sum up, the present invention has the following beneficial technical effects:

1.本发明整体应用扣件式钢管作为主要承力结构,突破传统的型钢作为支撑主梁的构造方式,无需在墙体上打孔,避免后期修补和产生的渗漏等质量风险,用更简单的材料和工艺完成高空施工中对于悬挑作业架的需求,减少人力物力的使用,提高施工效率,降低施工成本,各构件方便重复使用。1. The present invention uses fastener-type steel pipes as the main load-bearing structure as a whole, breaking through the traditional structural method of steel as supporting the main beam. There is no need to drill holes in the wall, avoiding later repairs and leakage and other quality risks, and using more reliable materials. Simple materials and processes meet the needs for cantilevered work frames in high-altitude construction, reduce the use of manpower and material resources, improve construction efficiency, reduce construction costs, and make each component easy to reuse.

2.搭设在屋内的作业脚手架同时兼做稳定架,固定悬挑桁架前段,单片单榀桁架至少搭配两条顶紧杆和一条斜拉杆进行固定,提高悬挑桁架后段承载力,保障施工人员在悬挑作业架上施工的安全性。2. The working scaffolding set up in the house also serves as a stabilizer to fix the front section of the cantilever truss. The single-piece single-frame truss should be fixed with at least two jacking rods and one diagonal tie rod to increase the bearing capacity of the rear section of the cantilever truss and ensure construction. Safety of personnel working on cantilevered work frames.

附图说明Description of drawings

图1是本发明实施例的一种用于高空施工的悬挑作业架的平面结构示意图;Figure 1 is a schematic plan view of a cantilevered work frame used for high-altitude construction according to an embodiment of the present invention;

图2是本发明实施例的一种用于高空施工的悬挑作业架的三维结构示意图;Figure 2 is a schematic three-dimensional structural diagram of a cantilevered work frame used for high-altitude construction according to an embodiment of the present invention;

附图标记说明:1、悬挑桁架;2、单榀桁架;3、悬挑桁架前段;4、稳定架;5、屋内;6、顶紧杆;7、悬挑桁架后段;8、屋外;9、斜拉杆;10、脚手板;11、防护栏;12、密目安全网;13、扣件式钢管;14、墙体。Explanation of reference signs: 1. Cantilever truss; 2. Single truss; 3. Front section of cantilever truss; 4. Stabilizer; 5. Inside the house; 6. Tightening rod; 7. Rear section of the cantilever truss; 8. Outside the house. ; 9. Diagonal tie rod; 10. Scaffolding board; 11. Guardrail; 12. Dense mesh safety net; 13. Fastener type steel pipe; 14. Wall.

具体实施方式Detailed ways

以下结合附图1-2对本发明作进一步详细说明。The present invention will be further described in detail below with reference to the accompanying drawings 1-2.

本发明实施例公开一种用于高空施工的悬挑作业架及其施工方法。The embodiment of the invention discloses a cantilevered work frame used for high-altitude construction and a construction method thereof.

参照图1、图2,一种用于高空施工的悬挑作业架,包括悬挑桁架1,悬挑桁架1采用多片单榀桁架2平行搭设,悬挑桁架1通过墙体14分隔为悬挑桁架前段3和悬挑桁架后段7,悬挑桁架前段3通过稳定架4固定在屋内5并通过顶紧杆6顶紧,悬挑桁架后段7延伸到屋外8并通过斜拉杆9拉紧,单片单榀桁架2至少搭配两条顶紧杆6和一条斜拉杆9进行固定,提高悬挑桁架7后段承载力,保障施工人员在悬挑作业架上施工的安全性;悬挑桁架1上铺设有脚手板10,悬挑桁架1外端安装防护栏11并挂设密目安全网12。Referring to Figures 1 and 2, a cantilever work frame for high-altitude construction includes a cantilever truss 1. The cantilever truss 1 is erected in parallel with multiple single-piece trusses 2. The cantilever truss 1 is divided into cantilevered parts by walls 14. The front section 3 of the cantilever truss and the rear section 7 of the cantilever truss. The front section 3 of the cantilever truss is fixed inside the house 5 through the stabilizer 4 and is tightened by the jacking rod 6. The rear section 7 of the cantilever truss extends to the outside of the house 8 and is pulled through the diagonal tie rod 9 Tight, the single-piece single-frame truss 2 is fixed with at least two tightening rods 6 and one diagonal tie rod 9 to improve the bearing capacity of the rear section of the cantilever truss 7 and ensure the safety of construction workers on the cantilever work frame; cantilever Scaffolding boards 10 are laid on the truss 1. A protective fence 11 is installed on the outer end of the cantilevered truss 1 and a dense mesh safety net 12 is hung.

参照图1、图2,顶紧杆6和斜拉杆9均采用扣件式钢管13,顶紧杆6的一端顶紧在墙体14内侧且另一端分别连接在单榀桁架2前段和稳定架4上,墙体14分隔屋内5和屋外8;斜拉杆9的一端连接在稳定架4上且另一端连接在单榀桁架2后段。Referring to Figures 1 and 2, both the jacking rod 6 and the diagonal tie rod 9 are made of fastener-type steel pipes 13. One end of the jacking rod 6 is fastened to the inside of the wall 14 and the other end is connected to the front section of the single truss 2 and the stabilizer respectively. 4, the wall 14 separates the interior 5 and the exterior 8; one end of the diagonal tie rod 9 is connected to the stabilizer 4 and the other end is connected to the rear section of the single truss 2.

参照图2,单榀桁架2采用扣件式钢管13连接拼装,相邻两片单榀桁架2之间通过扣件式钢管13连接,Referring to Figure 2, the single-frame trusses 2 are connected and assembled by fastener-type steel pipes 13. Two adjacent single-frame trusses 2 are connected by fastener-type steel pipes 13.

扣件式钢管13采用Q235普通钢管并在钢管两端设置扣接件,扣接件采用螺栓紧固,其安装简单,便于拆卸,性能比较优越,在使用时保证扣接件不会发生锈蚀,拧紧力矩达到规定要求。The fastener type steel pipe 13 uses Q235 ordinary steel pipe and is provided with fasteners at both ends of the steel pipe. The fasteners are fastened with bolts. It is simple to install, easy to disassemble, and has superior performance. It ensures that the fasteners will not rust during use. The tightening torque meets the specified requirements.

参照图1、图2,一种用于高空施工的悬挑作业架的施工方法,包括以下步骤:Referring to Figures 1 and 2, a construction method of a cantilevered work frame for high-altitude construction includes the following steps:

S1、在施工现场进行测量放线定位;S1. Conduct measurement and setting out positioning at the construction site;

S2、预拼装单榀桁架2,单榀桁架2采用扣件式钢管13连接拼装,这种工艺形式突破了传统的型钢作为支撑主梁的构造方式,无需在墙体上打孔,避免后期修补和产生的渗漏等质量风险,用更简单的材料和工艺完成高空施工中对于悬挑作业架的需求,完成悬挑作业架的搭设,各构件方便重复使用;S2. Pre-assembled single-frame truss 2. The single-frame truss 2 is assembled and connected by fastener-type steel pipes 13. This process breaks through the traditional construction method of steel as a supporting main beam. There is no need to drill holes in the wall and avoid later repairs. and quality risks such as leakage, use simpler materials and processes to meet the needs for cantilevered work frames in high-altitude construction, complete the erection of cantilevered work frames, and make each component easy to reuse;

S3、将两片预拼装好的单榀桁架2在屋内5立起并组装成两榀的悬挑桁架1,两片单榀桁架2之间通过扣件式钢管13连接,根据现场放线确定两片单榀桁架2之间的间距不大于1.5m;S3. Erect the two pre-assembled single-frame trusses 2 in the house 5 and assemble them into a two-frame cantilever truss 1. The two single-frame trusses 2 are connected by a fastener steel pipe 13, which is determined according to the on-site wiring. The distance between two single-frame trusses 2 shall not be greater than 1.5m;

S4、将两榀的悬挑桁架1滑移至放线好的位置;由于悬挑桁架1整体为扣件式钢管13拼装组成,重量比较轻,本步骤可以由人工抬起,完成外移就位;S4. Slide the two cantilever trusses 1 to the position where the wiring is good; since the cantilever truss 1 is assembled entirely from fastener-type steel pipes 13 and is relatively light in weight, this step can be lifted manually to complete the outward movement. Bit;

S5、将第三片预拼装好的单榀桁架2搬运到两榀的悬挑桁架1一侧并组装成三榀的悬挑桁架1,第三片单榀桁架2与两榀的悬挑桁架1之间通过扣件式钢管13连接,根据现场放线确定第三片单榀桁架2与两榀的悬挑桁架1之间的间距不大于1.5m;通过增加单片单榀桁架2的安装形式,少量施工人员就可以完成施工,减少施工成本;S5. Transport the third piece of pre-assembled single-frame truss 2 to one side of the two-frame cantilever truss 1 and assemble it into a three-frame cantilever truss 1. The third piece of single-frame truss 2 and the two-frame cantilever truss 1 are connected through fastener steel pipes 13. According to the on-site wiring, it is determined that the distance between the third single-piece truss 2 and the two-piece cantilever trusses 1 is not greater than 1.5m; by adding the installation of the single-piece single-piece truss 2 In this way, a small number of construction workers can complete the construction and reduce construction costs;

S6、在屋内5搭设落地式的作业脚手架,同时兼做稳定架4,将三榀的悬挑桁架1与稳定架4通过扣件式钢管13连接固定;屋内5的落地式的作业脚手架包括立杆、扫地杆、纵横水平杆等,方便施工人员屋内施工的同时,对悬挑桁架前段3进行固定。S6. Set up a floor-standing operating scaffolding in the house 5, which also serves as a stabilizer 4. Connect and fix the three cantilever trusses 1 and the stabilizer 4 through fastener steel pipes 13; the floor-standing operating scaffolding in the house 5 includes vertical poles, sweeping poles, vertical and horizontal horizontal poles, etc., to facilitate construction workers to fix the front section 3 of the cantilever truss while working inside the house.

S7、按上述步骤重复安装后续的悬挑桁架1和稳定架4,至全部完成,在屋内5稳定架4和屋外悬挑桁架1上安装剪刀撑;剪刀撑是安装在脚手架上的斜向支撑,在本实施例中加强悬挑桁架1的刚性和稳定性,保证其不变形;S7. Repeat the above steps to install the subsequent cantilever truss 1 and stabilizer 4 until all are completed. Install scissor braces on the stabilizer 4 inside the house 5 and the cantilever truss 1 outside the house; the scissor braces are diagonal supports installed on the scaffolding. , in this embodiment, the rigidity and stability of the cantilever truss 1 are strengthened to ensure that it does not deform;

S8、拉设斜拉杆9并安装顶紧杆6,单片单榀桁架2至少搭配两条顶紧杆6和一条斜拉杆9进行固定;顶紧杆6抵消单榀桁架2前段和稳定架4产生的横向水平滑移力;S8. Set up the diagonal tie rod 9 and install the jacking rod 6. The single-piece single-frame truss 2 is fixed with at least two jacking rods 6 and one diagonal tie rod 9; the jacking rod 6 offsets the front section of the single-frame truss 2 and the stabilizer 4. The resulting transverse horizontal slip force;

S9、在悬挑桁架1上铺设脚手板10,在悬挑桁架1外端安装防护栏11并挂设密目安全网12,密目安全网12高度不低于1.5m,且在防护栏11下部设置踢脚板,对施工区域进行全包围防护,方便施工人员进行施工,保证施工人员安全;S9. Lay the scaffolding board 10 on the cantilever truss 1, install a protective fence 11 on the outer end of the cantilever truss 1 and hang a dense-mesh safety net 12. The height of the dense-mesh safety net 12 shall not be less than 1.5m, and the height of the dense-mesh safety net 12 shall be no less than 1.5m, and the safety net 12 shall be installed on the outer end of the cantilever truss 1. The lower part is equipped with skirting boards to fully surround and protect the construction area, making it convenient for construction workers to carry out construction and ensuring the safety of construction workers;

S10、检测验收合格,验收合格后挂验收牌、限载牌、警示牌和安全宣传标语;S10. After passing the inspection and acceptance, hang the acceptance sign, load limit sign, warning sign and safety slogan;

本发明实施例一种用于高空施工的悬挑作业架的实施原理为:本发明整体应用扣件式钢管作为主要承力结构拼装单榀桁架2,通过增加单片单榀桁架2的安装形式,完成悬挑桁架1的组装,并应用扣件式钢管13顶紧、斜拉以提高悬挑桁架1承载力,用更简单的材料和工艺完成高空施工中对于悬挑作业架的需求。The implementation principle of a cantilevered work frame for high-altitude construction in the embodiment of the present invention is as follows: the present invention integrally uses fastener-type steel pipes as the main load-bearing structure to assemble the single-frame truss 2, and increases the installation form of the single-piece single-frame truss 2. , complete the assembly of the cantilever truss 1, and use fastener-type steel pipes 13 to tighten and cable-stay to increase the bearing capacity of the cantilever truss 1, and use simpler materials and processes to meet the needs for cantilever work frames in high-altitude construction.

以上均为本发明的较佳实施例,并非依此限制本发明的保护范围,故:凡依本发明的结构、形状、原理所做的等效变化,均应涵盖于本发明的保护范围之内。The above are all preferred embodiments of the present invention, and are not intended to limit the scope of protection of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be covered by the scope of protection of the present invention. Inside.

Claims (4)

1. A operation frame encorbelments for construction in high altitude, its characterized in that: the cantilever truss comprises cantilever trusses (1), wherein the cantilever trusses (1) are parallelly erected by adopting a plurality of single truss frames (2), the cantilever trusses (1) are divided into a cantilever truss front section (3) and a cantilever truss rear section (7) through a wall body (14), the cantilever truss front section (3) is fixed in a room (5) through a stabilizing frame (4) and is tightly jacked through a jacking rod (6), the cantilever truss rear section (7) extends out of the room (8) and is tightly tensioned through diagonal rods (9), and at least two jacking rods (6) and one diagonal rod (9) are matched with the single truss frames (2) to fix; the scaffold board (10) is paved on the cantilever truss (1), and a protective fence (11) is installed at the outer end of the cantilever truss (1) and a dense mesh safety net (12) is hung on the outer end of the cantilever truss.
2. The overhanging work rack for high-altitude construction according to claim 1, wherein: the jacking rod (6) and the diagonal draw bar (9) are both buckle type steel pipes (13), one end of the jacking rod (6) is jacked on the inner side of the wall body (14) and the other end of the jacking rod is respectively connected to the front section of the single truss (2) and the stabilizing frame (4); one end of the diagonal draw bar (9) is connected to the stabilizing frame (4) and the other end of the diagonal draw bar is connected to the rear section of the single truss (2).
3. The overhanging work rack for high-altitude construction according to claim 1, wherein: the single truss (2) is connected and spliced by adopting the fastener type steel pipes (13), and two adjacent single trusses (2) are connected by the fastener type steel pipes (13).
4. A construction method of the overhanging work rack for high-altitude construction according to any one of claims 2 to 3, comprising the steps of:
s1, measuring, paying-off and positioning on a construction site;
s2, pre-assembling a single truss (2);
s3, two pre-assembled single truss frames (2) are erected in a room (5) and assembled into two cantilever truss frames (1), and the distance between the two single truss frames (2) is not more than 1.5m according to on-site paying-off;
s4, sliding the cantilever trusses (1) of the two trusses to a well-paid-out position;
s5, carrying the third pre-assembled single truss (2) to one side of the two cantilever trusses (1) and assembling the third pre-assembled single truss into the three cantilever trusses (1), and determining that the distance between the third single truss (2) and the two cantilever trusses (1) is not more than 1.5m according to on-site paying-off;
s6, erecting a floor type operation scaffold in the house (5), simultaneously serving as a stabilizing frame (4), and connecting and fixing the cantilever trusses (1) of the three trusses and the stabilizing frame (4) through fastener type steel pipes (13);
s7, repeatedly installing the subsequent cantilever truss (1) and the stabilizing frame (4) according to the steps until all the cantilever truss and the stabilizing frame are completed;
s8, pulling the diagonal draw bar (9) and installing the jacking rods (6), and fixing the single truss (2) at least by matching with the two jacking rods (6) and the diagonal draw bar (9);
s9, paving a scaffold board (10) on the cantilever truss (1), installing a protective fence (11) at the outer end of the cantilever truss (1) and hanging a dense mesh safety net (12), wherein the height of the dense mesh safety net (12) is not less than 1.5m;
s10, detecting acceptance qualification.
CN202311681770.2A 2023-12-08 2023-12-08 Cantilever operation frame for high-altitude construction and construction method thereof Pending CN117627312A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311681770.2A CN117627312A (en) 2023-12-08 2023-12-08 Cantilever operation frame for high-altitude construction and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311681770.2A CN117627312A (en) 2023-12-08 2023-12-08 Cantilever operation frame for high-altitude construction and construction method thereof

Publications (1)

Publication Number Publication Date
CN117627312A true CN117627312A (en) 2024-03-01

Family

ID=90016224

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311681770.2A Pending CN117627312A (en) 2023-12-08 2023-12-08 Cantilever operation frame for high-altitude construction and construction method thereof

Country Status (1)

Country Link
CN (1) CN117627312A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103276886A (en) * 2013-06-25 2013-09-04 北京金港机场建设有限责任公司 Overhanging frame at position of high-rise building sloping roof outer eave window and construction method thereof
CN204001651U (en) * 2014-08-25 2014-12-10 中国化学工程第六建设有限公司 Overhanging type fastener-style steel pipe scaffolding
CN110629996A (en) * 2019-09-30 2019-12-31 杭州昂创科技有限公司 Construction method of profile steel cantilever through-wall-free heightening and anchoring support system
CN213297074U (en) * 2020-07-06 2021-05-28 浙江省东阳第三建筑工程有限公司 A convenient outer wall cantilever operation frame
CN215594831U (en) * 2021-08-31 2022-01-21 易盛通达工程技术(上海)有限公司 Outer frame of visiting of aluminum alloy swinging sash

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103276886A (en) * 2013-06-25 2013-09-04 北京金港机场建设有限责任公司 Overhanging frame at position of high-rise building sloping roof outer eave window and construction method thereof
CN204001651U (en) * 2014-08-25 2014-12-10 中国化学工程第六建设有限公司 Overhanging type fastener-style steel pipe scaffolding
CN110629996A (en) * 2019-09-30 2019-12-31 杭州昂创科技有限公司 Construction method of profile steel cantilever through-wall-free heightening and anchoring support system
CN213297074U (en) * 2020-07-06 2021-05-28 浙江省东阳第三建筑工程有限公司 A convenient outer wall cantilever operation frame
CN215594831U (en) * 2021-08-31 2022-01-21 易盛通达工程技术(上海)有限公司 Outer frame of visiting of aluminum alloy swinging sash

Similar Documents

Publication Publication Date Title
CN101775896B (en) Rigid suspended scaffold for installing pipeline of steel roof equipment
CN102561669A (en) Cantilever scaffold and construction method thereof
CN116537534A (en) Construction method of high and large formwork engineering supporting system
CN104234447B (en) Deep foundation ditch tool-type hangs stair
CN108590242A (en) Assembling type steel structure one-shot job canopy and its installation method
CN113550550A (en) Overhanging unit type scaffold convenient to assemble and disassemble
CN106906756B (en) Can Fast Installation remove maintenance operation platform and its construction method
CN205330140U (en) Tall support rack of structure encorbelments greatly in high altitude
CN215212255U (en) Suspension type frame combined high-altitude operation platform
CN111764623B (en) Hanging construction platform module and construction method of high altitude large cantilever steel roof frame
CN117627312A (en) Cantilever operation frame for high-altitude construction and construction method thereof
CN211689948U (en) A suspension operation platform device for the construction of a cable-stayed bridge tower
CN112227688A (en) A stiffened plate-supported construction platform without outer frame and its method for residential buildings
CN219691041U (en) Construction support system
CN209081302U (en) A tower crane attached assembled operation maintenance platform
CN206376514U (en) Tool climbing scaffold
CN207062787U (en) Can Fast Installation remove maintenance construction platform
CN212053723U (en) Fastener type combined steel pipe stair
CN214785809U (en) Stiffening plate bearing type outer frame-free construction platform for residential building
CN206458067U (en) Operation platform in high-rise building elevator
CN111608377B (en) Comprehensive construction method for building overhanging scaffold
CN208870409U (en) A kind of vertical pump line room external fixer of concrete
CN117090408A (en) Attached lifting protection shed and installation and lifting method thereof
CN219710903U (en) Civil engineering is with support of equipment of being convenient for
TWI911008B (en) Construction method of sound absorption system at the bottom of viaduct

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination