CN117582732A - A silt pumping mechanism for sewage treatment - Google Patents

A silt pumping mechanism for sewage treatment Download PDF

Info

Publication number
CN117582732A
CN117582732A CN202311394530.4A CN202311394530A CN117582732A CN 117582732 A CN117582732 A CN 117582732A CN 202311394530 A CN202311394530 A CN 202311394530A CN 117582732 A CN117582732 A CN 117582732A
Authority
CN
China
Prior art keywords
temporary storage
filter plate
storage tank
roller
sprocket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202311394530.4A
Other languages
Chinese (zh)
Other versions
CN117582732B (en
Inventor
尹长海
王小刚
周立娜
孙建胜
董超
李泽军
王建青
李腾飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Engineering Group Co Ltd
Tianjin Construction Engineering Co Ltd of China Railway First Engineering Group Co Ltd
Original Assignee
China Railway First Engineering Group Co Ltd
Tianjin Construction Engineering Co Ltd of China Railway First Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Engineering Group Co Ltd, Tianjin Construction Engineering Co Ltd of China Railway First Engineering Group Co Ltd filed Critical China Railway First Engineering Group Co Ltd
Priority to CN202311394530.4A priority Critical patent/CN117582732B/en
Publication of CN117582732A publication Critical patent/CN117582732A/en
Application granted granted Critical
Publication of CN117582732B publication Critical patent/CN117582732B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01D—SEPARATION
    • B01D36/00—Filter circuits or combinations of filters with other separating devices
    • B01D36/02—Combinations of filters of different kinds
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01D—SEPARATION
    • B01D29/00—Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor
    • B01D29/60—Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor integrally combined with devices for controlling the filtration
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01D—SEPARATION
    • B01D29/00—Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor
    • B01D29/62—Regenerating the filter material in the filter
    • B01D29/70—Regenerating the filter material in the filter by forces created by movement of the filter element
    • B01D29/72—Regenerating the filter material in the filter by forces created by movement of the filter element involving vibrations
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01D—SEPARATION
    • B01D29/00—Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor
    • B01D29/88—Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor having feed or discharge devices
    • B01D29/94—Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor having feed or discharge devices for discharging the filter cake, e.g. chutes
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01D—SEPARATION
    • B01D33/00—Filters with filtering elements which move during the filtering operation
    • B01D33/044—Filters with filtering elements which move during the filtering operation with filtering bands or the like supported on cylinders which are pervious for filtering
    • B01D33/048—Filters with filtering elements which move during the filtering operation with filtering bands or the like supported on cylinders which are pervious for filtering with endless filtering bands
    • B—PERFORMING OPERATIONS; TRANSPORTING
    • B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01D—SEPARATION
    • B01D33/00—Filters with filtering elements which move during the filtering operation
    • B01D33/70—Filters with filtering elements which move during the filtering operation having feed or discharge devices
    • B01D33/72—Filters with filtering elements which move during the filtering operation having feed or discharge devices for feeding

Landscapes

  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Treatment Of Sludge (AREA)

Abstract

本申请公开了一种污水处理用抽淤机构,属于污水处理技术领域,其技术方案要点是包括暂存罐和抽淤装置,抽淤装置包括抽淤管、排污泵和输送管,抽淤管与排污泵的进口端连通,输送管的一端与排污泵的出口端连通、另一端与暂存罐内部连通,暂存罐连接有前进装置,排污泵与前进装置连接,暂存罐的内壁连接有第一隔板,第一隔板将暂存罐隔离为存液腔和存泥腔,存液腔与存泥腔上部半连通,存液腔连通有出液管,存泥腔连通有出泥管;存液腔顶部设置有使污水和淤泥分离的分离装置,分离装置包括链板输送带、带动链板输送带运动的驱动组件,驱动组件与暂存罐连接,链板输送带覆盖存液腔,输送管位于链板输送带上方,达到减小工作人员的工作量的效果。

This application discloses a sludge extraction mechanism for sewage treatment, which belongs to the technical field of sewage treatment. The key points of its technical solution include a temporary storage tank and a sludge extraction device. The sludge extraction device includes a siltation extraction pipe, a sewage drainage pump and a conveying pipe. The siltation extraction pipe It is connected to the inlet end of the sewage pump, one end of the delivery pipe is connected to the outlet end of the sewage pump, and the other end is connected to the inside of the temporary storage tank. The temporary storage tank is connected to a forward device, the sewage pump is connected to the forward device, and the inner wall of the temporary storage tank is connected. There is a first partition, which isolates the temporary storage tank into a liquid storage chamber and a mud storage chamber. The liquid storage chamber is semi-connected with the upper part of the mud storage chamber. The liquid storage chamber is connected with a liquid outlet pipe, and the mud storage cavity is connected with an outlet pipe. Mud pipe; the top of the liquid storage chamber is equipped with a separation device to separate sewage and sludge. The separation device includes a chain plate conveyor belt and a driving component that drives the chain plate conveyor belt to move. The driving component is connected to the temporary storage tank, and the chain plate conveyor belt covers the storage tank. The liquid chamber and conveying pipe are located above the chain plate conveyor belt, which reduces the workload of the staff.

Description

Sludge pumping mechanism for sewage treatment
Technical Field
The application relates to the technical field of sewage treatment, in particular to a sludge pumping mechanism for sewage treatment.
Background
At present, sewage treatment is a process for purifying sewage to meet the water quality requirement of being discharged into a certain water body or reused, and a sludge pumping process is an indispensable procedure in sewage treatment engineering.
In the related art, a sewage treatment plant is with taking out silt mechanism includes to take out silt device and temporary storage tank, takes out silt device including taking out silt pipe, dredge pump and conveyer pipe, dredge pump and temporary storage tank fixed connection, dredge pump's entrance point and the one end intercommunication of taking out the silt pipe, dredge pump's exit end and the one end intercommunication of conveyer pipe, the other end and the temporary storage tank inside intercommunication of conveyer pipe. The temporary storage tank bottom is fixedly connected with a plurality of rollers, and the rollers are uniformly distributed at the temporary storage tank bottom. One end of the silt pumping pipe extends into the sewage, a sewage pump is started, silt is sucked into the conveying pipe through the silt pumping pipe, and the silt is conveyed into the temporary storage tank through the conveying pipe for temporary storage.
To the above-mentioned related art, the sediment pumping device is taken in together with the sewage in the silt and is kept in the jar, consequently can lead to keeping in the jar to fill soon to the staff can clear up keeping in the jar many times, has increased staff's work load, has reduced staff's work efficiency.
Disclosure of Invention
In order to reduce the workload of workers, the invention provides a sludge pumping mechanism for sewage treatment.
The invention provides a sludge pumping mechanism for sewage treatment, which adopts the following technical scheme:
the utility model provides a sewage treatment is with taking out silt mechanism, includes temporary storage tank and takes out silt device, take out silt device including taking out silt pipe, dredge pump and conveyer pipe, take out silt pipe with dredge pump's entrance point intercommunication, the one end of conveyer pipe with dredge pump's exit end intercommunication, the other end with the inside intercommunication of temporary storage tank, temporary storage tank is connected with the drive temporary storage tank removes advancing device, dredge pump with advancing device connects, temporary storage tank's inner wall is connected with first baffle, first baffle will temporary storage tank keeps apart into liquid chamber and deposit the mud chamber, liquid chamber with deposit mud chamber upper portion half intercommunication, liquid chamber intercommunication has the drain pipe, deposit mud chamber intercommunication has out mud pipe;
the utility model discloses a sewage and silt separation device, including the mud is deposited the link joint conveyer belt of mud intracavity, drive the drive assembly of link joint conveyer belt motion, drive assembly with the jar of keeping in is connected, the link joint conveyer belt covers deposit the liquid chamber, the exit end of conveyer pipe is located link joint conveyer belt top.
By adopting the technical scheme, when the sludge in the sewage needs to be pumped, the sewage pump is started, so that the inlet end of the sludge pumping pipe is close to the sludge, and the sludge and the sewage are sent into the temporary storage pipe together by the sewage pump for temporary storage through the conveying pipe. The silt and water drop to the link joint conveyer belt after discharging from the exit end of conveyer pipe, start drive assembly, drive assembly drives silt and water and to depositing the transportation of mud chamber, with silt and separation of water in the link joint conveyer belt motion in-process, water falls into and deposits the liquid intracavity, the silt is transported to depositing the mud intracavity and is kept in, has improved the volume that bears the weight of silt after separating sewage and silt, has reduced the number of times that the temporary storage pipe was filled, and then has reduced the staff and to keeping in jar clearance number of times, has reduced staff's work load, has improved staff's work efficiency. The advancing device drives the silt pumping mechanism to advance or retreat, so that the silt in the sewage is conveniently pumped. The drain pipe is used for discharging the sewage temporarily stored in the liquid storage cavity. The mud outlet pipe is used for discharging the temporarily stored mud in the mud storage cavity.
Preferably, the driving assembly comprises a motor, a first roller and a second roller, the motor is connected with the temporary storage tank, the first roller is horizontally and parallelly arranged with the second roller, the first roller is rotationally connected with the temporary storage tank, the second roller is fixedly connected with the motor, the chain plate conveyer belt is sleeved on the first roller and the second roller, the chain plate conveyer belt is in butt joint with the first roller and the second roller, the separating device further comprises a linkage assembly for driving the first roller and the second roller to synchronously move, a placing cavity is formed in the side wall of the temporary storage tank, and the linkage assembly is arranged in the placing cavity.
Through adopting above-mentioned technical scheme, start the motor, the motor drives the second roller and rotates, and the second roller passes through the linkage subassembly and drives first roller rotation, and first roller, second roller drive the link joint conveyer belt motion jointly. The placing cavity isolates the linkage assembly from water and silt, so that the normal working state of the linkage assembly is ensured.
Preferably, the inner wall of the temporary storage tank is connected with a baffle which enables sludge to fall off from a gap between the chain plate conveying belt and the temporary storage tank difficultly, the baffle is provided with a plurality of baffles, one side, away from the temporary storage tank, of the baffle is located above the chain plate conveying belt, the baffle is obliquely arranged, and the baffle is obliquely downwards from one end, close to the temporary storage tank, to the other end.
By adopting the technical scheme, the baffle plate reduces the possibility that the sludge falls to the liquid storage pipe from the gap between the chain plate conveying belt and the temporary storage tank. The baffle that the slope set up is convenient for drop of silt, has reduced the possibility that silt deposited on the baffle, and then has reduced staff's clearance temporary storage tube's work load.
Preferably, the inner wall of the temporary storage tank is connected with a second partition board, the second partition board is used for isolating the mud storage cavity into a transition cavity and a temporary storage cavity, the transition cavity is close to the liquid storage cavity, a filter assembly for further separating mud and sewage is arranged in the transition cavity, and the filter assembly is connected with the temporary storage tank, the first partition board and the second partition board.
Through adopting above-mentioned technical scheme, the link joint conveyer belt is transported silt to the filter equipment of transition intracavity on, by the water in the filter equipment separation silt once more, has further improved the volume that bears silt, has reduced the number of times that the temporary storage pipe was filled up, and then has reduced staff's work load, has improved staff's work efficiency. And after the sludge on the filtering assembly is temporarily accumulated, the sludge is transported to the temporary storage cavity by the transport assembly for temporary storage.
Preferably, the filter assembly comprises a first filter plate and a second filter plate, wherein the end wall of the first filter plate is connected with the end wall of the second filter plate, the first filter plate is far away from the side wall of the second filter plate and is connected with the first partition plate, the second filter plate is far away from the side wall of the first filter plate and is connected with the second partition plate, the end wall of the same side of the first filter plate is connected with the inner wall of the temporary storage tank, the first filter plate and the second filter plate are obliquely arranged, the first filter plate is obliquely upwards from one end close to the second filter plate to the other end, and the second filter plate is obliquely upwards from one end close to the first filter plate to the other end.
By adopting the technical scheme, the chain plate conveyer belt conveys sludge to the first filter plate and the second filter plate, and the first filter plate and the second filter plate filter out residual sewage in the sludge. The first filter plate and the second filter plate are obliquely arranged, so that the contact area between sludge and the filter plates is increased, the area of sewage filtering out is increased, and the filtering efficiency is improved.
Preferably, the temporary storage tank is connected with a knocking device, the knocking device comprises two groups of knocking components and a synchronous component for driving the two groups of knocking components to synchronously move with the second roller, the two groups of knocking components are in one-to-one correspondence with the first filter plate and the second filter plate, the knocking components are arranged below the first filter plate and the second filter plate, the knocking components comprise a rotating shaft, a fixed cylinder, a moving rod, a spring and a knocking block, the rotating shaft is rotationally connected with the temporary storage tank, the two rotating shafts are connected with the synchronous component, one end of the fixed cylinder is connected with the peripheral wall of the rotating shaft, the moving rod stretches into the fixed cylinder and is in sliding connection with the fixed cylinder, the spring is positioned in the fixed cylinder, one end of the spring is connected with the fixed cylinder, the other end of the spring is connected with the moving rod, the knocking block is rotationally connected with the moving rod relatively, and when the knocking block is in contact with the first filter plate or the second filter plate, the knocking block is rotationally connected with the first filter plate.
Through adopting above-mentioned technical scheme, the second roller drives synchronous subassembly motion when the pivoted, and synchronous subassembly drives two pivots and rotates, and the pivot drives the fixed section of thick bamboo that is connected with self along the axis rotation of pivot, and the fixed section of thick bamboo drives the movable rod and rotates, and the movable rod drives and beats the piece and rotate. In the process of rotating the fixed cylinder, the spring is stretched, the knocking block knocks the first filter plate or the second filter plate, the rotating shaft continues to rotate, the spring slowly contracts, the knocking block is in sliding butt with the first filter plate or the second filter plate, then the knocking block is far away from the first filter plate or the second filter plate again, and the spring is stretched again. The spring repeatedly stretches and contracts, and the knocking block knocks the first filter plate or the second filter plate, so that the possibility of blocking the first filter plate and the second filter plate is reduced. The knocking block is connected with the movable rod in a relative rotation way, so that the possibility of abrasion between the knocking block and the first filter plate or the second filter plate is reduced, and the service life of the knocking block is prolonged.
Preferably, the synchronization assembly is located place the intracavity, the one end of pivot runs through temporary storage jar and stretches into place the chamber, the synchronization assembly includes first sprocket, second sprocket, third sprocket and synchronous chain, first sprocket with the second roller is connected, the second sprocket the third sprocket is connected respectively in two the pivot, first sprocket is connected with self the pivot, the second sprocket is connected with self the pivot, synchronous chain cover is established first sprocket the second sprocket on the third sprocket, synchronous chain with first sprocket the second sprocket the third sprocket all meshes.
Through adopting above-mentioned technical scheme, the second roller drives first sprocket and rotates, and first sprocket drives second sprocket, third sprocket through synchronous chain and rotates, and second sprocket, third sprocket drive two pivots and rotate.
Preferably, the second partition board is connected with a transport assembly for transporting the sludge in the transition cavity into the temporary storage cavity, the transport assembly comprises a suction pump, a suction pipe and a transport pipe, the suction pump is connected with the temporary storage tank, the inlet end of the suction pump is communicated with the suction pipe, the outlet end of the suction pump is communicated with the transport pipe, the suction pipe is communicated with the transition cavity, the suction pipe is located on one side, close to the second filter plate, of the first filter plate, and the transport pipe is communicated with the temporary storage cavity.
Through adopting above-mentioned technical scheme, when the silt in the transition chamber is stored to certain altitude, start the suction pump, the suction pump is with the silt suction pipe on first filter plate, the second filter plate, in the transportation pipe is exported to the transportation pipe by the suction pump again, and the silt in the transportation pipe is transported to temporary storage intracavity and is kept in.
Preferably, the second filter plate is connected with a vibration sensor, the vibration sensor is electrically connected with a control module, and the control module is electrically connected with the suction pump.
Through adopting above-mentioned technical scheme, when knocking the piece and knocking the second filter plate, if the silt storage capacity on the second filter plate is less, the vibration frequency of second filter plate is great, if the silt storage capacity on the second filter plate is more, the vibration frequency of second filter plate is less, vibration sensor detects the vibration of second filter plate, when the biggest vibration frequency of second filter plate reduces to the fixed value, vibration sensor gives the electric signal transmission for control module. The control module receives the electric signal and then transmits the electric signal to the suction pump, and the suction pump is started.
Preferably, the advancing device comprises a bottom plate and rollers, the temporary storage tank is fixedly connected with the top of the bottom plate, the rollers are provided with a plurality of rollers, and the rollers are fixedly connected with the bottom plate.
Through adopting above-mentioned technical scheme, the gyro wheel drives the bottom plate and removes, and the bottom plate drives the jar that keeps in and removes, the continuous extraction of the silt of being convenient for.
In summary, the invention has the following beneficial effects:
1. when the sludge in the sewage needs to be pumped, a sewage pump is started, so that the inlet end of the sludge pumping pipe is close to the sludge, and the sludge and the sewage are sent into a temporary storage pipe together by the sewage pump for temporary storage through a conveying pipe. The sludge and water drop onto the chain plate conveyer belt after being discharged from the conveyer pipe, the chain plate conveyer belt separates the sludge from water, the water drops into the liquid storage cavity, the driving assembly drives the chain plate conveyer belt to transport the sludge to the sludge storage cavity, the amount of carrying the sludge is increased after the sewage and the sludge are separated, the times of filling the temporary storage pipe are reduced, the cleaning times of workers to the temporary storage tank are further reduced, the workload of the workers is reduced, and the working efficiency of the workers is improved;
2. the mud storage cavity is divided into a transition cavity and a temporary storage cavity, the first filter plate and the second filter plate in the transition cavity further separate mud and water, the amount of bearing the mud is further increased, the times of filling the temporary storage pipe are reduced, the cleaning times of a temporary storage tank by workers are further reduced, and the workload of the workers is reduced.
Drawings
FIG. 1 is a schematic diagram of the whole structure of a sludge pumping mechanism for sewage treatment.
Fig. 2 is a schematic diagram of the internal structure of the temporary storage tank.
Fig. 3 is a top view of the interior of the temporary storage tank.
Fig. 4 is a schematic view of the structure of the synchronization assembly and the second roller.
FIG. 5 is a cross-sectional view of the tapping assembly.
Reference numerals illustrate:
1. an advancing device; 11. a bottom plate; 12. a roller; 2. a temporary storage tank; 21. a first separator; 22. a second separator; 23. a baffle; 24. a liquid outlet pipe; 25. a mud outlet pipe; 3. a silt pumping device; 31. a silt suction pipe; 32. a sewage pump; 33. a delivery tube; 4. a separation device; 41. a motor; 42. a first roller; 43. a second roller; 44. a link plate conveyor belt; 45. a linkage assembly; 5. a filter assembly; 51. a first filter plate; 52. a second filter plate; 6. a striking assembly; 61. a rotating shaft; 62. a fixed cylinder; 63. a moving rod; 64. a spring; 65. a mounting frame; 66. knocking the block; 7. a synchronization component; 71. a first sprocket; 72. a second sprocket; 73. a third sprocket; 74. a synchronous chain; 8. a vibration sensor; 9. a transport assembly; 91. a suction pump; 92. a suction pipe; 93. and (5) transporting the pipe.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
The utility model provides a sewage treatment is with taking out silt mechanism, referring to fig. 1 and 2, including advancing device 1, temporary storage tank 2, take out silt device 3 and separator 4, temporary storage tank 2 is connected with advancing device 1, and advancing device 1 is used for driving and takes out silt mechanism and remove. The sludge pumping device 3 is connected with the temporary storage tank 2, and the sludge pumping device 3 is used for pumping sludge and transporting the sludge into the temporary storage tank 2 for temporary storage. The inner wall of the temporary storage tank 2 is connected with a first baffle plate 21, the first baffle plate 21 isolates the temporary storage tank 2 into a liquid storage cavity and a mud storage cavity, and the liquid storage cavity is semi-communicated with the upper part of the mud storage cavity. The separating device 4 comprises a driving assembly and a chain plate conveying belt 44, the driving assembly is connected with the temporary storage tank 2, the chain plate conveying belt 44 is connected with the driving assembly, and the driving assembly is used for driving the chain plate conveying belt 44 to move. The chain plate conveyer belt 44 covers the top of the liquid storage cavity, and the chain plate conveyer belt 44 is used for separating water and sludge pumped by the sludge pumping device 3 and conveying the sludge into the sludge storage cavity for temporary storage. The liquid storage cavity is communicated with a liquid outlet pipe 24, and the mud storage cavity is communicated with a mud outlet pipe 25. After the sludge pumping device 3 pumps water and sludge into the temporary storage tank 2, the chain plate conveyer belt 44 reduces the times of filling the temporary storage tank 2, so that the cleaning times of workers to the temporary storage tank 2 are reduced, and the workload of the workers is reduced.
Referring to fig. 1, the advancing device 1 includes a base plate 11 and rollers 12, the base plate 11 is horizontally disposed, the bottom of the base plate 11 is fixedly connected with the rollers 12, the rollers 12 are four, and the four rollers 12 are respectively located at four corners of the base plate 11. The temporary storage tank 2 is fixedly connected with the bottom plate 11.
Referring to fig. 2 and 3, a baffle plate 23 is fixedly connected to the inner wall of the temporary storage tank 2, and one side of the baffle plate 23 away from the temporary storage tank 2 is close to the top of the chain plate conveyer belt 44. The three baffles 23 are provided, and the three baffles 23 are respectively positioned at both sides of the conveying direction of the scraper conveyer 44 and at the starting end of the conveying direction of the scraper conveyer 44. One end of the baffle plate 23 far away from the temporary storage tank 2 is positioned above the chain plate conveying belt 44, the baffle plate 23 is obliquely arranged, and the baffle plate 23 is obliquely downward from one end close to the temporary storage tank 2 to the other end. The baffle plate 23 reduces the likelihood of sludge falling from the gap between the flight conveyor belt 44 and the surge tank 2 to the storage tube.
Referring to fig. 1, the sludge pumping device 3 includes a sludge pumping pipe 31, a sludge pump 32 and a conveying pipe 33, the sludge pump 32 is fixedly connected with the bottom plate 11, an inlet end of the sludge pump 32 is communicated with an outlet end of the sludge pumping pipe 31, an outlet end of the sludge pump 32 is communicated with an inlet end of the conveying pipe 33, and an outlet end of the conveying pipe 33 is communicated with the interior of the temporary storage tank 2. The outlet end of the duct 33 is located above the flight conveyor 44.
Referring to fig. 2, the driving assembly includes a motor 41, a first roller 42 and a second roller 43, the motor 41 is fixedly connected with the outer wall of the temporary storage tank 2, the first roller 42 and the second roller 43 are horizontally arranged, the first roller 42 is parallel to the second roller 43, and the first roller 42 and the second roller 43 are rotatably connected with the temporary storage tank 2. One end of the second roller 43 penetrates through the temporary storage tank 2 and is fixedly connected with the driving shaft of the motor 41. The apron conveyer 44 is sleeved on the first roller 42 and the second roller 43, and the apron conveyer 44 abuts against both the first roller 42 and the second roller 43.
The motor 41 is started, the motor 41 drives the second roller 43 to rotate, the second roller 43 drives the first roller 42 to rotate through the linkage assembly 45, the first roller 42 and the second roller 43 drive the chain plate conveyer belt 44 to move together, and the chain conveyer belt separates sludge from water and conveys the sludge into the sludge storage cavity.
Referring to fig. 2 and 3, the separating device 4 further includes a linkage assembly 45, a placing cavity is formed in the side wall of the temporary storage tank 2, the linkage assembly 45 is arranged in the placing cavity, one ends of the same sides of the first roller 42 and the second roller 43 penetrate through the temporary storage tank 2 and extend into the placing cavity, and the linkage assembly 45 is connected with the first roller 42 and the second roller 43.
Referring to fig. 2, in order to achieve the same purpose, the linkage assembly 45 may be a chain and sprocket matching, a belt and pulley matching, or the like, in this embodiment, the chain wheels are a chain matching, two sprockets are provided, the two sprockets are respectively in one-to-one correspondence with the first roller 42 and the second roller 43, the sprockets are fixedly connected with the first roller 42 and the second roller 43, the chain is sleeved on the two sprockets, and the chain is meshed with the sprockets. The two sprockets cooperate with the chain to effect synchronous movement of the first roller 42 and the second roller 43 for transporting the flight belt 44.
Referring to fig. 3 and 4, the inner wall of the temporary storage tank 2 is fixedly connected with a second partition plate 22, the second partition plate 22 isolates the mud storage cavity into a transition cavity and a temporary storage cavity, and the transition cavity is close to the liquid storage cavity. A filter assembly 5 is arranged in the transition cavity, the filter assembly 5 comprises a first filter plate 51 and a second filter plate 52, and the end wall of the first filter plate 51 is fixedly connected with the end wall of the second filter plate 52. The first filter plate 51 and the second filter plate 52 are both arranged obliquely, the first filter plate 51 is obliquely upward from one end close to the second filter plate 52 to the other end, and the second filter plate 52 is obliquely upward from one end close to the first filter plate 51 to the other end.
Referring to fig. 3, the end wall of the first filter plate 51 far from the second filter plate 52 is fixedly connected with the first partition plate 21, the end wall of the second filter plate 52 far from the first filter plate 51 is fixedly connected with the second partition plate 22, and the end walls of the same sides of the first filter plate 51 and the second filter plate 52 are fixedly connected with the inner wall of the temporary storage tank 2.
The link plate conveyor belt 44 conveys the sludge to the first filter plate 51 and the second filter plate 52, and the first filter plate 51 and the second filter plate 52 further filter the sewage in the sludge.
Referring to fig. 3, the transition chamber is also connected to a drain pipe 24, the top of the drain pipe 24 being lower than the bottom of the first filter plate 51. The mud pipe 25 is communicated with the temporary storage cavity, and the mud pipe 25 is positioned at the bottom of the temporary storage cavity. The mud outlet pipe 25 and the two liquid outlet pipes 24 are fixedly connected with a switch valve (not shown in the figure), and the switch valve can be a ball valve, a butterfly valve or the like.
The drain pipe 24 communicated with the transition cavity is used for discharging the sewage in the transition cavity, and the drain pipe 24 communicated with the liquid storage cavity is used for discharging the sewage in the liquid storage cavity. The mud storage cavity is used for discharging mud in the temporary storage cavity.
Referring to fig. 2, the temporary storage tank 2 is connected with a knocking device, and the knocking device is located in the transition cavity. The knocking device comprises knocking components 6 and synchronizing components 7, wherein the knocking components 6 are provided with two groups, the knocking components 6 of the two groups are respectively in one-to-one correspondence with the first filter plate 51 and the second filter plate 52, and the knocking components 6 are arranged below the first filter plate 51 and the second filter plate 52.
Referring to fig. 4 and 5, the striking assembly 6 includes a rotation shaft 61, a fixed cylinder 62, a moving rod 63, a spring 64, a mounting bracket 65 and a striking block 66, the rotation shaft 61 is horizontally arranged, the length direction of the rotation shaft 61 is perpendicular to the sludge conveying direction of the link plate conveying belt 44, both ends of the rotation shaft 61 are rotatably connected with the temporary storage tank 2, and one end of the rotation shaft 61 penetrates through the temporary storage tank 2 and extends into the placing cavity.
Referring to fig. 4 and 5, a fixed cylinder 62 is fixedly connected to a rotating shaft 61, one end of a moving rod 63 extends into the fixed cylinder 62, the other end is fixedly connected to a mounting frame 65, and the moving rod 63 is slidably connected to the fixed cylinder 62. The spring 64 is provided in the fixed cylinder 62, and one end of the spring 64 is fixedly connected to the fixed cylinder 62, and the other end is fixedly connected to the moving rod 63. The knocking block 66 is sleeved on the mounting frame 65 and is rotationally connected with the mounting frame 65. When the knocking block 66 knocks the first filter sheet 51 or the second filter sheet 52, the knocking block 66 abuts against the first filter sheet 51 or the second filter sheet 52.
The second roller 43 drives the synchronous component 7 to move when rotating, the synchronous component 7 drives the two rotating shafts 61 to rotate, the rotating shafts 61 drive the fixed cylinder 62 connected with the synchronous component to rotate along the axis of the rotating shafts 61, the fixed cylinder 62 drives the moving rod 63 to rotate, the spring 64 is stretched at the moment, the moving rod 63 drives the knocking block 66 to rotate, the rotating shafts 61 continue to rotate, the spring 64 slowly contracts, the knocking block 66 is in sliding abutting connection with the first filter plate 51 or the second filter plate 52, the knocking block 66 is separated from the first filter plate 51 or the second filter plate 52, and the spring 64 is stretched again.
Referring to fig. 4, the synchronizing assembly 7 is disposed in the placement cavity, and the synchronizing assembly 7 includes a first sprocket 71, a second sprocket 72, a third sprocket 73 and a synchronizing chain 74, wherein the first sprocket 71 is fixedly connected with the second roller 43, the first sprocket 71 and the second sprocket 72 are respectively connected with the two rotating shafts 61, the first sprocket 71 is coaxially and fixedly connected with the rotating shaft 61 connected with the first sprocket 72, and the second sprocket 72 is coaxially and fixedly connected with the rotating shaft 61 connected with the second sprocket 72. The synchronizing chain 74 is sleeved on the first sprocket 71, the second sprocket 72 and the third sprocket 73, and the synchronizing chain 74 is meshed with the first sprocket 71, the second sprocket 72 and the third sprocket 73.
The second roller 43 drives the first sprocket 71 to rotate, the first sprocket 71 drives the second sprocket 72 and the third sprocket 73 to rotate through the synchronous chain 74, and the second sprocket 72 and the third sprocket 73 drive the two rotating shafts 61 to rotate.
Referring to fig. 2 and 4, the second filter plate 52 is connected to the vibration sensor 8, and the vibration sensor 8 is electrically connected to the control module. The temporary storage tank 2 is connected with a transport assembly 9, the transport assembly 9 comprises a suction pump 91, a suction pipe 92 and a transport pipe 93, the suction pump 91 is fixedly connected with the temporary storage tank 2, and the suction pump 91 is electrically connected with a control module. One end of the suction pipe 92 extends into the temporary storage tank 2, and the suction pipe 92 is communicated with the transition cavity and is positioned on one side of the first filter plate 51 close to the second filter plate 52. The other end of the suction pipe 92 communicates with the inlet end of the suction pump 91. One end of the transport pipe 93 is communicated with the outlet end of the suction pump 91, and the other end extends into the temporary storage tank 2 and is communicated with the temporary storage cavity.
When the knocking block 66 knocks the second filter plate 52, if the sludge storage amount on the second filter plate 52 is large, the vibration frequency of the second filter plate 52 is small, the vibration sensor 8 detects the vibration of the second filter plate 52, and when the maximum vibration frequency of the second filter plate 52 is reduced to a fixed value, the vibration sensor 8 transmits an electric signal to the control module. The control module receives the electrical signal and then transmits the electrical signal to the suction pump 91, and the suction pump 91 is started.
After the suction pump 91 is started, the suction pump 91 sucks the sludge on the first filter plate 51 and the second filter plate 52 into the suction pipe 92, and the sludge is output into the conveying pipe 93 by the suction pump 91, and the sludge in the conveying pipe 93 is conveyed into the temporary storage cavity for temporary storage.
The application principle is as follows: when the sludge in the sewage needs to be pumped, the sewage pump 32 is started, so that the inlet end of the sludge pumping pipe 31 is close to the sludge, and the sludge and the sewage are sent into the temporary storage tank 2 together by the sewage pump 32 through the conveying pipe 33 for temporary storage. The sludge and water fall onto the drag conveyor belt 44 after being discharged from the conveying pipe 33, the drag conveyor belt 44 separates the sludge from the water, the sludge continues to exist on the drag conveyor belt 44, and the water falls into the liquid storage cavity. The motor 41 is started, the motor 41 drives the second roller 43 to rotate, the second roller 43 drives the first roller 42 to synchronously move through the cooperation of a chain and two chain wheels, the first roller 42 and the second roller 43 jointly drive the chain plate conveying belt 44 to move, and the chain conveying belt conveys sludge into the transition cavity.
The sludge falls onto the first filter plate 51 and the second filter plate 52, and the first filter plate 51 and the second filter plate 52 further filter the sewage in the sludge. The second roller 43 drives the first sprocket 71 to rotate when rotating, the first sprocket 71 drives the second sprocket 72 and the third sprocket 73 to rotate through the synchronous chain 74, the second sprocket 72 and the third sprocket 73 drive the two rotating shafts 61 to rotate, the rotating shafts 61 drive the fixed cylinder 62 connected with the second roller to rotate along the axis of the rotating shafts 61, the fixed cylinder 62 drives the moving rod 63 to rotate, at the moment, the spring 64 is stretched, the moving rod 63 drives the knocking block 66 to rotate, and the knocking block 66 knocks the first filter plate 51 or the second filter plate 52 under the action of the spring 64 and the action of force, so that the possibility of blocking the first filter plate 51 or the second filter plate 52 is reduced.
The rotation shaft 61 continues to rotate, the spring 64 slowly contracts, the knocking block 66 is in sliding contact with the first filter plate 51 or the second filter plate 52, the knocking block 66 is separated from the first filter plate 51 or the second filter plate 52, and the spring 64 is stretched again.
When the knocking block 66 is separated from the first filter plate 51 or the second filter plate 52, if the storage amount of sludge in the transition cavity is more, the vibration frequency of the second filter plate 52 is smaller, and when the maximum vibration frequency of the second filter plate 52 detected by the second filter plate 52 is reduced to a fixed value, the vibration sensor 8 transmits an electric signal to the control module. After receiving the electric signal, the control module transmits the electric signal to the suction pump 91, the suction pump 91 is started, the suction pump 91 sucks the sludge on the first filter plate 51 and the second filter plate 52 into the suction pipe 92, and the sludge is output into the conveying pipe 93 by the suction pump 91, so that the sludge in the conveying pipe 93 is conveyed into the temporary storage cavity for temporary storage.
After the temporary storage tank 2 is filled, the opening and closing valves of the liquid outlet pipe 24 and the mud outlet pipe 25 are opened, sewage in the transition cavity and the liquid storage cavity is discharged, and mud in the temporary storage cavity is discharged. After the sewage and the sludge are discharged, the switch valve is closed, so that the sludge can be pumped out again.
The embodiments of the present invention are all preferred embodiments of the present invention, and are not intended to limit the scope of the present invention in this way, therefore: all equivalent changes in structure, shape and principle of the invention should be covered in the scope of protection of the invention.

Claims (10)

1.一种污水处理用抽淤机构,包括暂存罐(2)和抽淤装置(3),所述抽淤装置(3)包括抽淤管(31)、排污泵(32)和输送管(33),所述抽淤管(31)与所述排污泵(32)的进口端连通,所述输送管(33)的一端与所述排污泵(32)的出口端连通、另一端与所述暂存罐(2)内部连通,其特征在于:所述暂存罐(2)连接有带动所述暂存罐(2)移动的前进装置(1),所述排污泵(32)与所述前进装置(1)连接,所述暂存罐(2)的内壁连接有第一隔板(21),所述第一隔板(21)将所述暂存罐(2)隔离为存液腔和存泥腔,所述存液腔与所述存泥腔上部半连通,所述存液腔连通有出液管(24),所述存泥腔连通有出泥管(25);1. A silt extraction mechanism for sewage treatment, including a temporary storage tank (2) and a silt extraction device (3). The silt extraction device (3) includes a silt extraction pipe (31), a sewage pump (32) and a delivery pipe. (33), the siltation pipe (31) is connected to the inlet end of the sewage pump (32), one end of the delivery pipe (33) is connected to the outlet end of the sewage pump (32), and the other end is connected to the outlet end of the sewage pump (32). The temporary storage tank (2) is internally connected, and is characterized in that: the temporary storage tank (2) is connected to an advancing device (1) that drives the temporary storage tank (2) to move, and the sewage pump (32) is connected to the The advancing device (1) is connected, and the inner wall of the temporary storage tank (2) is connected with a first partition (21). The first partition (21) isolates the temporary storage tank (2) into storage. Liquid chamber and mud storage chamber, the liquid storage chamber is semi-connected with the upper part of the mud storage chamber, the liquid storage chamber is connected with a liquid outlet pipe (24), and the mud storage cavity is connected with a mud outlet pipe (25); 所述暂存罐(2)的内壁连接有使污水和淤泥分离的分离装置(4),所述分离装置(4)包括将淤泥输送至所述存泥腔内的链板输送带(44)、带动所述链板输送带(44)运动的驱动组件,所述驱动组件与所述暂存罐(2)连接,所述链板输送带(44)覆盖所述存液腔,所述输送管(33)的出口端位于所述链板输送带(44)上方。The inner wall of the temporary storage tank (2) is connected with a separation device (4) that separates sewage and sludge. The separation device (4) includes a chain plate conveyor belt (44) that transports sludge into the mud storage chamber. , a driving assembly that drives the chain plate conveyor belt (44) to move, the driving assembly is connected to the temporary storage tank (2), the chain plate conveyor belt (44) covers the liquid storage chamber, and the conveyor belt The outlet end of the tube (33) is located above the chain plate conveyor belt (44). 2.根据权利要求1所述的一种污水处理用抽淤机构,其特征在于:所述驱动组件包括电机(41)、第一辊(42)和第二辊(43),所述电机(41)与所述暂存罐(2)连接,所述第一辊(42)、所述第二辊(43)水平且平行设置,所述第一辊(42)、所述第二辊(43)均与所述暂存罐(2)转动连接,所述第二辊(43)与所述电机(41)固定连接,所述链板输送带(44)套设在所述第一辊(42)、所述第二辊(43)上,所述链板输送带(44)与所述第一辊(42)、所述第二辊(43)均抵接,所述分离装置(4)还包括带动所述第一辊(42)、所述第二辊(43)同步运动的联动组件(45),所述暂存罐(2)的侧壁内开设有放置腔,所述联动组件(45)设置在所述放置腔内。2. A sludge extraction mechanism for sewage treatment according to claim 1, characterized in that: the driving assembly includes a motor (41), a first roller (42) and a second roller (43), and the motor (41) 41) is connected to the temporary storage tank (2), the first roller (42) and the second roller (43) are arranged horizontally and parallel, the first roller (42) and the second roller (41) are 43) are all rotatably connected to the temporary storage tank (2), the second roller (43) is fixedly connected to the motor (41), and the chain conveyor belt (44) is sleeved on the first roller. (42) On the second roller (43), the chain conveyor belt (44) is in contact with both the first roller (42) and the second roller (43), and the separation device (42) 4) It also includes a linkage component (45) that drives the first roller (42) and the second roller (43) to move synchronously, and a placement cavity is provided in the side wall of the temporary storage tank (2). The linkage component (45) is arranged in the placement cavity. 3.根据权利要求1所述的一种污水处理用抽淤机构,其特征在于:所述暂存罐(2)的内壁连接有使淤泥不易从所述链板输送带(44)与所述暂存罐(2)的缝隙掉落的挡板(23),所述挡板(23)设置有多个,所述挡板(23)远离所述暂存罐(2)的一侧位于所述链板输送带(44)上方,所述挡板(23)倾斜设置,所述挡板(23)由靠近所述暂存罐(2)的一端至另一端倾斜向下。3. A sludge extraction mechanism for sewage treatment according to claim 1, characterized in that: the inner wall of the temporary storage tank (2) is connected to the inner wall of the temporary storage tank (2) to prevent sludge from easily flowing from the chain conveyor belt (44) to the The baffle (23) is used to fall down from the gap of the temporary storage tank (2). There are multiple baffles (23). The side of the baffle (23) away from the temporary storage tank (2) is located on the side of the temporary storage tank (2). Above the chain plate conveyor belt (44), the baffle (23) is arranged obliquely, and the baffle (23) is inclined downward from one end close to the temporary storage tank (2) to the other end. 4.根据权利要求2所述的一种污水处理用抽淤机构,其特征在于:所述暂存罐(2)的内壁连接有第二隔板(22),所述第二隔板(22)将所述存泥腔隔离为过渡腔和暂存腔,所述过渡腔靠近所述存液腔,所述过渡腔内设置有进一步分离淤泥和污水的过滤组件(5),所述过滤组件(5)与所述暂存罐(2)、所述第一隔板(21)、所述第二隔板(22)均连接。4. A sludge extraction mechanism for sewage treatment according to claim 2, characterized in that: the inner wall of the temporary storage tank (2) is connected with a second partition (22), and the second partition (22) ) Separate the mud storage chamber into a transition chamber and a temporary storage chamber. The transition chamber is close to the liquid storage chamber. A filter assembly (5) for further separating sludge and sewage is provided in the transition chamber. The filter assembly (5) Connected to the temporary storage tank (2), the first partition (21), and the second partition (22). 5.根据权利要求4所述的一种污水处理用抽淤机构,其特征在于:所述过滤组件(5)包括第一滤板(51)和第二滤板(52),所述第一滤板(51)的端壁与所述第二滤板(52)的端壁连接,所述第一滤板(51)远离所述第二滤板(52)的侧壁与所述第一隔板(21)连接,所述第二滤板(52)远离所述第一滤板(51)的侧壁与所述第二隔板(22)连接,所述第一滤板(51)、所述第二滤板(52)同侧的端壁与所述暂存罐(2)的内壁均连接,所述第一滤板(51)、所述第二滤板(52)均倾斜设置,所述第一滤板(51)由靠近所述第二滤板(52)的一端至另一端倾斜向上,所述第二滤板(52)由靠近所述第一滤板(51)的一端至另一端倾斜向上。5. A sludge extraction mechanism for sewage treatment according to claim 4, characterized in that: the filter assembly (5) includes a first filter plate (51) and a second filter plate (52), and the first The end wall of the filter plate (51) is connected to the end wall of the second filter plate (52), and the side wall of the first filter plate (51) away from the second filter plate (52) is connected to the first The partition plate (21) is connected, and the side wall of the second filter plate (52) away from the first filter plate (51) is connected to the second partition plate (22). The first filter plate (51) , the end wall on the same side of the second filter plate (52) is connected to the inner wall of the temporary storage tank (2), and the first filter plate (51) and the second filter plate (52) are both inclined It is arranged that the first filter plate (51) is tilted upward from one end close to the second filter plate (52) to the other end, and the second filter plate (52) is tilted upward from close to the first filter plate (51) Sloping upward from one end to the other. 6.根据权利要求5所述的一种污水处理用抽淤机构,其特征在于:所述暂存罐(2)连接有敲击装置,所述敲击装置包括两组敲击组件(6)、带动两组所述敲击组件(6)与所述第二辊(43)同步运动的同步组件(7),两组所述敲击组件(6)与所述第一滤板(51)、所述第二滤板(52)一一对应,所述敲击组件(6)设置在所述第一滤板(51)和所述第二滤板(52)下方,所述敲击组件(6)包括转轴(61)、固定筒(62)、移动杆(63)、弹簧(64)和敲击块(66),所述转轴(61)与所述暂存罐(2)转动连接,且两个所述转轴(61)均与所述同步组件(7)连接,所述固定筒(62)的一端与所述转轴(61)的外周壁连接,所述移动杆(63)伸入所述固定筒(62)内、与所述固定筒(62)滑动连接,所述弹簧(64)位于所述固定筒(62)内,所述弹簧(64)的一端与所述固定筒(62)连接、另一端与所述移动杆(63)连接,所述敲击块(66)与所述移动杆(63)相对转动连接,当所述敲击块(66)与所述第一滤板(51)或所述第二滤板(52)抵接时,所述敲击块(66)敲击所述第一滤板(51)或所述第二滤板(52)。6. A sludge extraction mechanism for sewage treatment according to claim 5, characterized in that: the temporary storage tank (2) is connected with a knocking device, and the knocking device includes two sets of knocking components (6) , a synchronization component (7) that drives two sets of knocking components (6) and the second roller (43) to move synchronously, and two sets of knocking components (6) and the first filter plate (51) , the second filter plate (52) corresponds one to one, the knocking assembly (6) is arranged below the first filter plate (51) and the second filter plate (52), the knocking assembly (6) includes a rotating shaft (61), a fixed cylinder (62), a moving rod (63), a spring (64) and a knocking block (66). The rotating shaft (61) is rotationally connected to the temporary storage tank (2) , and the two rotating shafts (61) are connected to the synchronization component (7), one end of the fixed cylinder (62) is connected to the outer peripheral wall of the rotating shaft (61), and the moving rod (63) extends into the fixed cylinder (62) and slidingly connected with the fixed cylinder (62). The spring (64) is located in the fixed cylinder (62), and one end of the spring (64) is connected to the fixed cylinder (62). (62) is connected, and the other end is connected to the moving rod (63). The knocking block (66) is relatively rotatably connected with the moving rod (63). When the knocking block (66) is connected with the third When a filter plate (51) or the second filter plate (52) is in contact, the knocking block (66) knocks the first filter plate (51) or the second filter plate (52). 7.根据权利要求6所述的一种污水处理用抽淤机构,其特征在于:所述同步组件(7)位于所述放置腔内,所述转轴(61)的一端贯穿暂存罐(2)伸入放置腔,所述同步组件(7)包括第一链轮(71)、第二链轮(72)、第三链轮(73)和同步链条(74),所述第一链轮(71)与所述第二辊(43)连接,所述第二链轮(72)、所述第三链轮(73)分别连接于两个所述转轴(61),所述第一链轮(71)与自身连接的所述转轴(61)连接,所述第二链轮(72)与自身连接的所述转轴(61)连接,所述同步链条(74)套设在所述第一链轮(71)、所述第二链轮(72)、所述第三链轮(73)上,所述同步链条(74)与所述第一链轮(71)、所述第二链轮(72)、所述第三链轮(73)均啮合。7. A sludge extraction mechanism for sewage treatment according to claim 6, characterized in that: the synchronization component (7) is located in the placement cavity, and one end of the rotating shaft (61) penetrates the temporary storage tank (2 ) extends into the placement cavity. The synchronization assembly (7) includes a first sprocket (71), a second sprocket (72), a third sprocket (73) and a synchronization chain (74). The first sprocket (71) is connected to the second roller (43), the second sprocket (72) and the third sprocket (73) are respectively connected to the two rotating shafts (61), and the first chain The wheel (71) is connected to the rotating shaft (61) connected to itself, the second sprocket (72) is connected to the rotating shaft (61) connected to itself, and the synchronizing chain (74) is sleeved on the third sprocket. On one sprocket (71), the second sprocket (72), and the third sprocket (73), the synchronization chain (74) is connected with the first sprocket (71), the second sprocket (71), and the third sprocket (73). The sprocket (72) and the third sprocket (73) are both in mesh. 8.根据权利要求5所述的一种污水处理用抽淤机构,其特征在于:所述第二隔板(22)连接有将所述过渡腔的污泥运输至所述暂存腔内的运输组件(9),所述运输组件(9)包括吸泵(91)、吸管(92)和运输管(93),所述吸泵(91)与所述暂存罐(2)连接,所述吸泵(91)的进口端与所述吸管(92)连通、出口端与所述运输管(93)连通,所述吸管(92)与所述过渡腔连通,且所述吸管(92)位于所述第一滤板(51)靠近所述第二滤板(52)的一侧,所述运输管(93)与所述暂存腔连通。8. A sludge extraction mechanism for sewage treatment according to claim 5, characterized in that: the second partition (22) is connected with a device for transporting the sludge in the transition chamber to the temporary storage chamber. Transport component (9). The transport component (9) includes a suction pump (91), a suction pipe (92) and a transport pipe (93). The suction pump (91) is connected to the temporary storage tank (2), so The inlet end of the suction pump (91) is connected to the suction pipe (92), the outlet end is connected to the transport pipe (93), the suction pipe (92) is connected to the transition chamber, and the suction pipe (92) Located on the side of the first filter plate (51) close to the second filter plate (52), the transport tube (93) is connected to the temporary storage chamber. 9.根据权利要求8所述的一种污水处理用抽淤机构,其特征在于:所述第二滤板(52)连接有振动传感器(8),所述振动传感器(8)电连接有控制模块,所述控制模块与所述吸泵(91)电连接。9. A sludge extraction mechanism for sewage treatment according to claim 8, characterized in that: the second filter plate (52) is connected to a vibration sensor (8), and the vibration sensor (8) is electrically connected to a control module, the control module is electrically connected to the suction pump (91). 10.根据权利要求1所述的一种污水处理用抽淤机构,其特征在于:所述前进装置(1)包括底板(11)和滚轮(12),所述暂存罐(2)与所述底板(11)顶部固定连接,所述滚轮(12)设置有多个,多个所述滚轮(12)均与所述底板(11)固定连接。10. A sludge extraction mechanism for sewage treatment according to claim 1, characterized in that: the advancing device (1) includes a bottom plate (11) and a roller (12), and the temporary storage tank (2) is connected to the The top of the bottom plate (11) is fixedly connected, and there are multiple rollers (12). The plurality of rollers (12) are all fixedly connected to the bottom plate (11).
CN202311394530.4A 2023-10-25 2023-10-25 A sludge pumping mechanism for sewage treatment Active CN117582732B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311394530.4A CN117582732B (en) 2023-10-25 2023-10-25 A sludge pumping mechanism for sewage treatment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311394530.4A CN117582732B (en) 2023-10-25 2023-10-25 A sludge pumping mechanism for sewage treatment

Publications (2)

Publication Number Publication Date
CN117582732A true CN117582732A (en) 2024-02-23
CN117582732B CN117582732B (en) 2026-05-15

Family

ID=89917295

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311394530.4A Active CN117582732B (en) 2023-10-25 2023-10-25 A sludge pumping mechanism for sewage treatment

Country Status (1)

Country Link
CN (1) CN117582732B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN209556009U (en) * 2018-12-02 2019-10-29 郭子铭 A kind of hydraulic engineering construction riverway sludge cleaning plant
CN217103126U (en) * 2022-05-09 2022-08-02 安徽四邦环境科技有限公司 Sewage treatment engineering is with taking out silt device
CN217724755U (en) * 2022-06-20 2022-11-04 青岛冠军石油化学有限公司 Antifreeze filter
CN218924063U (en) * 2023-01-30 2023-04-28 惠州市兴牧环保科技股份有限公司 Sludge discharging device for sewage treatment
CN116145757A (en) * 2023-01-09 2023-05-23 河南水利与环境职业学院 Hydraulic engineering dredging device based on automatic information acquisition and feedback

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN209556009U (en) * 2018-12-02 2019-10-29 郭子铭 A kind of hydraulic engineering construction riverway sludge cleaning plant
CN217103126U (en) * 2022-05-09 2022-08-02 安徽四邦环境科技有限公司 Sewage treatment engineering is with taking out silt device
CN217724755U (en) * 2022-06-20 2022-11-04 青岛冠军石油化学有限公司 Antifreeze filter
CN116145757A (en) * 2023-01-09 2023-05-23 河南水利与环境职业学院 Hydraulic engineering dredging device based on automatic information acquisition and feedback
CN218924063U (en) * 2023-01-30 2023-04-28 惠州市兴牧环保科技股份有限公司 Sludge discharging device for sewage treatment

Also Published As

Publication number Publication date
CN117582732B (en) 2026-05-15

Similar Documents

Publication Publication Date Title
CN115504600A (en) An intelligent sewage treatment system and its application method
CN111210709A (en) A coal floating and sinking experiment system
CN117446448B (en) Automatic cleaning device for return belt and using method thereof
CN117582732B (en) A sludge pumping mechanism for sewage treatment
CN113107038A (en) River channel dredging vehicle capable of being used for cleaning river channels of different depths
CN210432750U (en) Shellfish steaming and separating system
CN216798779U (en) Circulating extraction device of water-soluble natural product
CN115245704A (en) Intelligent water treatment is with multi-functional promotion pump station
CN120618086A (en) Dense overflow solid material recycling device and process
CN221155779U (en) Sludge filtering device in sewage
CN220976777U (en) Filtering and deslagging device for cleaning septic tank
CN220723924U (en) Transmission structure of sludge press filtration device
CN219836208U (en) Sludge conveying system of integrated sewage treatment equipment
CN219817270U (en) Mineral cleaning device
CN217103126U (en) Sewage treatment engineering is with taking out silt device
CN218950515U (en) Impurity removing device for grain conveyor
CN218423967U (en) Take slime dispersion devices of self-cleaning mechanism
CN211555317U (en) Coal floating and sinking experiment system
CN110882921A (en) General grain loading machine with environment-friendly vibrating screen and pulse dust collector
CN205585285U (en) Take conveyor components's turnip cleaning equipment
CN107952503A (en) A kind of Cirulation type grain washing device
CN216825244U (en) A separator for petroleum crude oil processing
CN119186089B (en) Circuit board membrane removal filtration system
CN205585289U (en) Cleaning equipment of turnip
CN215632929U (en) Oil liquid conveying device for oil exploitation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant