Construction method of frame beam with reinforced concrete and steel structure mixed
Technical Field
The invention relates to a construction method of a frame beam with reinforced concrete and steel structure mixed.
Background
In order to meet the requirements of green energy conservation and low carbon and environmental protection, the prior fabricated building is more and more widely applied, and has a reinforced concrete fabricated structure and a steel structure fabricated structure, compared with the two fabricated structures, the reinforced concrete fabricated structure has the advantages of low manufacturing cost and good fireproof performance, but long construction period, and the steel structure fabricated structure has the advantages of short construction time, high manufacturing cost and poor fireproof performance, so that part of building design adopts a frame structure with reinforced concrete and steel structure mixed, such as a frame column and a frame girder adopt reinforced concrete, and a frame secondary beam adopts a steel structure.
For this structure, the traditional construction method is: and in the process of binding the reinforcing steel bars on the reinforced concrete frame girder, installing the frame steel structure secondary beam embedded part in an inserting way, removing the template after the frame girder concrete pouring and curing are completed, exposing the embedded part, hoisting the frame steel structure secondary beam after measuring and paying off, connecting the frame steel structure secondary beam with the embedded part by using a connecting plate, paving a floor bearing plate and the reinforcing steel bars on the upper part of the girder, and pouring floor slab concrete. The construction method has the following defects: 1. the secondary beam of the frame steel structure can be installed after the maintenance of the reinforced concrete frame main beam reaches the strength; 2. and the concrete needs to be poured twice, namely, the reinforced concrete frame main beam is cast once and the floor slab is cast once.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provides a construction method of a reinforced concrete and steel structure mixed frame beam, which is used for casting at one time, so that the construction period is saved.
The technical scheme for achieving the purpose is as follows:
a method of constructing a frame beam of a reinforced concrete and steel structure mix comprising:
step S1, setting up scaffolds on two sides of the lower part of a reinforced concrete girder of a frame;
s2, installing a beam bottom die and binding beam bottom steel bars of the frame reinforced concrete main beam;
s3, installing adjustable connecting devices at two ends or one end of a frame steel secondary beam to be installed on the ground;
s4, hoisting a first frame steel secondary beam with the same axis;
s5, hoisting second frame steel secondary beams at two ends of the first frame steel secondary beam, and adjusting the plane positions of the frame steel secondary beams through the adjustable connecting devices at two ends of the first frame steel secondary beam;
s6, repeating the steps S1-S5, and installing the frame steel secondary beams with other axes;
step S7, binding upper steel bars and stirrups of the frame reinforced concrete main beams, supporting beam side templates, paving floor support plates and binding floor support plate steel bars;
and S8, pouring the frame reinforced concrete girder and the floor support plate concrete.
Preferably, in the step S3, before the first frame steel secondary beam is hoisted, two adjustable connection devices are respectively installed at two ends of the first frame steel secondary beam on the ground through high-strength bolts, and before the second frame steel secondary beam at two ends of the first frame steel secondary beam is hoisted, one adjustable connection device is installed at the left end or the right end of the second frame steel secondary beam on the ground through high-strength bolts.
Preferably, in the step S4 and the step S5, after the frame steel secondary beam is in place, the frame steel secondary beam is temporarily supported on the scaffolds on both sides of the frame reinforced concrete main beam.
Preferably, in the step S4, a first frame steel secondary beam is temporarily fixed on the scaffold at both sides of the frame reinforced concrete main beam by manufacturing a first frame steel secondary beam positioning plate;
the frame steel secondary beam locating plate comprises: the scaffold comprises a bottom plate and a vertical plate, wherein the bottom plate is horizontally arranged, the vertical plate is arranged above the bottom plate, the length direction of the vertical plate is consistent with the length direction of the bottom plate, the vertical plate is positioned on two sides of the width direction of the bottom plate, and the bottom plate is fixed on the scaffold through bolts.
Preferably, in the step S5, the plane positions of the second frame steel secondary beams at the two ends of the first frame steel secondary beam are adjusted by the adjustable connection device at the end of the first frame steel secondary beam, and the second frame steel secondary beam is temporarily fixed on the installed first frame steel secondary beam.
Preferably, the adjustable connection means comprises: the adjustable movable connecting piece and the non-adjustable movable connecting piece, the adjustable movable connecting piece is fixed on the first frame steel secondary beam or the second frame steel secondary beam, the adjustable movable connecting piece is connected with the non-adjustable movable connecting piece through four screws, one end of each screw is threaded and connected with the adjustable movable connecting piece, and the other end of each screw is welded with a protruding circular ring and connected with the non-adjustable movable connecting piece.
Preferably, the adjustable mobile connection comprises: the novel screw bolt comprises a first steel plate, a first screw bolt sleeve, a first anchor bar and a first connecting steel plate, wherein threads inside the first screw bolt sleeve are matched with screws, the first screw bolt sleeve is welded at four corner positions of the first steel plate, the first connecting steel plate is welded at the middle position of the first steel plate, holes are formed in the first connecting steel plate, high-strength bolts penetrate through the holes of the first connecting steel plate and are connected with a first frame steel secondary beam or a second frame steel secondary beam, and the first anchor bar is welded between the first screw bolt sleeves on two sides of the first steel plate and is arranged in parallel with the first connecting steel plate.
Preferably, one end of the screw thread can rotate in the first screw sleeve and horizontally move.
Preferably, the non-adjustable mobile connection comprises: the novel steel plate structure comprises a second steel plate, a second screw rod sleeve, second anchor bars and second connecting steel plates, wherein grooves are formed in the second screw rod sleeve and matched with the screws, the second screw rod sleeve is welded at four corner positions of the second steel plate, the second connecting steel plates are welded at the middle positions of the second steel plate, holes are formed in the second connecting steel plates, high-strength bolts penetrate through the holes of the second connecting steel plates and are connected with the first frame steel secondary beams or the second frame steel secondary beams, and the second anchor bars are welded between the second screw rod sleeves on two sides of the second steel plate and are arranged in parallel with the second connecting steel plates.
Preferably, one end of the screw welding protruding circular ring can rotate in the second screw sleeve and cannot move horizontally.
The beneficial effects of the invention are as follows: the invention saves the maintenance time of the frame reinforced concrete girder, improves the embedded part into an adjustable connecting device, connects the adjustable connecting device with the frame steel secondary girder on the ground, temporarily supports the frame steel secondary girder on scaffolds on two sides of the frame reinforced concrete girder after the frame steel secondary girder is in place, has high construction efficiency, reduces overhead operation, has small potential safety hazard, and ensures the accurate installation position of the frame steel secondary girder by arranging the adjustable connecting device at the end part of the frame steel secondary girder; before pouring concrete, the frame steel secondary beams on the same floor are connected together through the adjustable connecting devices at the two ends of the frame steel secondary beams to form a whole, so that the problem that before concrete pouring, the frame steel secondary beams are firmly positioned, the looseness caused by the disturbance of high-strength bolts at the connecting positions of the frame steel secondary beams in the next working procedure can be prevented, the installation quality is ensured, and the frame reinforced concrete main beams and the building carrier plates are simultaneously subjected to concrete pouring, so that the construction period is saved.
Drawings
Fig. 1 is a flow chart of a method of constructing a reinforced concrete and steel structure hybrid frame beam of the present invention;
FIG. 2 is a top view of a frame structure arrangement of the present invention in which reinforced concrete and steel structures are mixed;
FIG. 3 is a cross-sectional view A-A of FIG. 2;
fig. 4 is a plan view showing the construction of scaffolds on both sides of the lower part of the reinforced concrete girder of the frame according to the present invention;
FIG. 5 is a section B-B of FIG. 4;
FIG. 6 is a top view of the present invention with the beam bottom form installed on the framed reinforced concrete main beam and with the beam bottom reinforcement tie;
FIG. 7 is a cross-sectional view taken along line C-C of FIG. 6;
FIG. 8 is a cross-sectional view of the present invention with the frame steel secondary beam and adjustable attachment installed on the ground;
FIG. 9 is a top view of a first frame steel secondary beam of the present invention hoisted;
FIG. 10 is a cross-sectional view taken along line D1-D1 of FIG. 9;
FIG. 11 is a top view of a second frame steel secondary beam of the present invention lifting both ends of the first frame steel secondary beam;
FIG. 12 is a cross-sectional view taken along line D2-D2 of FIG. 11;
FIG. 13 is a top view of a lashing frame reinforced concrete main beam upper reinforcement and stirrups, supporting beam side templates, laying floor deck and lashing floor deck reinforcement in accordance with the present invention;
FIG. 14 is a section E-E of FIG. 13;
FIG. 15 is a top view of a cast-in-frame reinforced concrete girder and deck concrete of the present invention;
FIG. 16 is a section F-F of FIG. 15;
FIG. 17 is a schematic view of an adjustable connection of the present invention;
FIG. 18 is a schematic view of an adjustable mobile connector of the present invention;
FIG. 19 is a section G-G of FIG. 18;
FIG. 20 is a schematic view of a non-adjustable mobile connector of the present invention;
FIG. 21 is a section H-H of FIG. 20;
FIG. 22 is a schematic view of a screw according to the present invention.
In the figure: 1. a frame reinforced concrete column; 2. a frame reinforced concrete girder; 3. a frame steel secondary beam; 3-1, a first frame steel secondary beam; 3-2, a second frame steel secondary beam; 4. a scaffold; 5. a bottom die of the frame reinforced concrete girder; 6. frame reinforced concrete girder bottom steel bar; 7. an adjustable connection device; 7-1, an adjustable mobile connection; 7-2, an unadjustable mobile connection; 7-3, a screw rod; 8. frame reinforced concrete girder side templates; 7-1-1, a first steel plate; 7-1-2, a first screw sleeve; 7-1-3, a first anchor bar; 7-1-4, a first connecting steel plate; 7-2-1, a second steel plate; 7-2-2, a second screw sleeve; 7-2-3, second anchor bars; 7-2-4, a second connecting steel plate; 9. reinforcing steel bars and stirrups; 10. floor support plate; 11. reinforcing steel bars of floor support plates; 12. floor support plate concrete.
Detailed Description
The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings. In the description of the present invention, it should be noted that the directions or positional relationships indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. are based on the directions or positional relationships shown in the drawings, are merely for convenience of describing the present invention and simplifying the description, and do not indicate or imply that the devices or elements referred to must have a specific orientation, be configured and operated in a specific orientation, and thus should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying positive importance.
The invention will be further described with reference to the accompanying drawings.
As shown in fig. 1, a construction method of a frame beam in which reinforced concrete and a steel structure are mixed includes:
and S1, setting up scaffolds 4 on two sides of the lower part of the frame reinforced concrete girder 2 supported by the frame reinforced concrete column 1, as shown in figures 2-5.
And S2, installing a frame reinforced concrete girder bottom die 5 and a frame reinforced concrete girder bottom steel bar 6 on the frame reinforced concrete girder 2 for binding, as shown in figures 6 and 7.
And S3, installing adjustable connecting devices 7 at two ends or one end of the frame steel secondary beam 3 to be installed on the ground.
In the embodiment, before the first frame steel secondary beam 3-1 is hoisted, two adjustable connecting devices 7 are respectively installed at two ends of the first frame steel secondary beam 3-1 on the ground through high-strength bolts, before the second frame steel secondary beam 3-2 at two ends of the first frame steel secondary beam 3-1 is hoisted, one adjustable connecting device 7 is installed at the left end or the right end of the second frame steel secondary beam 3-2 on the ground through high-strength bolts, as shown in fig. 8, the construction efficiency is high, the high quality of high-altitude operation is reduced, and the potential safety hazard is small.
And S4, hoisting the first frame steel secondary beams 3-1 with the same axis, as shown in figures 9 and 10.
S5, hoisting second frame steel secondary beams 3-2 at two ends of the first frame steel secondary beam 3-1, and adjusting the plane positions of the frame steel secondary beams through adjustable connecting devices 7 at two ends of the first frame steel secondary beam 3-1, as shown in figures 11 and 12; before concrete is poured, the frame steel secondary beams 3 on the same floor are connected together through the adjustable connecting devices 7 at the two ends of the frame steel secondary beams to form a whole, so that looseness caused by disturbance of high-strength bolts at the connecting positions of the frame steel secondary beams in the next working procedure (such as concrete pouring and the like) can be prevented, and the installation quality is guaranteed.
As shown in fig. 17-22, the adjustable connection means 7 comprises: the adjustable movable connecting piece 7-1 and the non-adjustable movable connecting piece 7-2, wherein the adjustable movable connecting piece 7-1 is fixed on the first frame steel secondary beam 3-1 or the second frame steel secondary beam 3-2, the adjustable movable connecting piece 7-1 is connected with the non-adjustable movable connecting piece 7-2 through four screw rods 7-3, one end of each screw rod 7-3 is threaded, the other end of each screw rod is connected with the adjustable movable connecting piece 7-1, and the other end of each screw rod is welded with a protruding circular ring and is connected with the non-adjustable movable connecting piece 7-2.
In an embodiment, the adjustable mobile connection 7-1 comprises: the first steel plate 7-1-1, the first screw sleeve 7-1-2, the first anchor bar 7-1-3 and the first connecting steel plate 7-1-4, wherein threads inside the first screw sleeve 7-1-2 are matched with the screws 7-3, the first screw sleeve 7-1-2 is welded at four corner positions of the first steel plate 7-1-1, the first connecting steel plate 7-1-4 is welded at the middle position of the first steel plate 7-1-1, holes are formed in the first connecting steel plate 7-1-4, high-strength bolts penetrate through the holes of the first connecting steel plate 7-1-4 and are connected with the first frame steel secondary beam 3-1 or the second frame steel secondary beam 3-2, and the first anchor bar 7-1-3 is welded between the first screw sleeves 7-1-2 on two sides of the first steel plate 7-1-1 and is arranged parallel to the first connecting steel plate 7-1-4.
In an embodiment, one end of the screw 7-3 is rotatable in the first screw sleeve 7-1-2 and horizontally movable.
In an embodiment, the non-adjustable mobile connection 7-2 comprises: the second steel plate 7-2-1, the second screw sleeve 7-2-2, the second anchor bar 7-2-3 and the second connecting steel plate 7-2-4, grooves are formed in the second screw sleeve 7-2-2 and matched with the screws 7-3, the second screw sleeve 7-2-2 is welded at four corner positions of the second steel plate 7-2-1, the second connecting steel plate 7-2-4 is welded at the middle position of the second steel plate 7-2-1, holes are formed in the second connecting steel plate 7-2-4, high-strength bolts penetrate through the holes of the second connecting steel plate 7-2-4 and are connected with the first frame steel secondary beam 3-1 or the second frame steel secondary beam 3-2, and the second anchor bar 7-2-3 is welded between the second screw sleeves 7-2-2 on two sides of the second steel plate 7-2-1 and is arranged parallel to the second connecting steel plate 7-2-4.
In the embodiment, one end of the welding convex circular ring of the screw rod 7-3 can rotate in the second screw rod sleeve 7-2-2 and cannot horizontally move.
In the embodiment, the first frame steel secondary beam 3-1 is temporarily fixed on scaffolds 4 on two sides of the frame reinforced concrete main beam 2 by manufacturing a first frame steel secondary beam positioning plate; the frame steel secondary beam locating plate includes: the bottom plate that the level set up and the riser of locating the bottom plate top, the length direction of riser is unanimous with the length direction of bottom plate to be located bottom plate width direction's both sides, the bottom plate passes through the bolt fastening on scaffold 4.
In the embodiment, the plane position of the second frame steel secondary beam 3-2 at the two ends of the first frame steel secondary beam 3-1 is adjusted through the adjustable connecting device 7 at the end part of the first frame steel secondary beam 3-1, and is temporarily fixed on the installed first frame steel secondary beam 3-1.
In the embodiment, after the frame steel secondary beams 3 are in place, the frame steel secondary beams 3 are temporarily supported on scaffolds 4 on two sides of the frame reinforced concrete main beam 2; specifically, one end of the adjustable connecting device is initially connected with an adjustable connecting device 7 at the end part of the installed first frame steel secondary beam 3-1, then a screw rod 7-3 is rotated by a wrench, the position of the second frame steel secondary beam 3-2 at the two ends of the first frame steel secondary beam 3-1 is accurately adjusted, after the position correction is accurate, the second frame steel secondary beam 3-2 is fixed on the installed second frame steel secondary beam 3-2 through the adjustable connecting device 7, and the problem that the frame steel secondary beam 3 is firmly positioned before concrete pouring is solved.
And S6, repeating the steps S1 to S5, and installing the frame steel secondary beams 3 with other axes.
Step S7, binding the upper steel bars and the stirrups 9 of the frame reinforced concrete main beam 1, supporting the beam side templates 8, and paving the floor support plates 10 and binding the floor support plate steel bars 11, as shown in figures 13 and 14.
And S8, pouring the reinforced concrete main beam 2 of the frame and the floor support plate 10, and performing water spraying maintenance to form the floor support plate concrete 12, as shown in figures 15 and 16.
The conventional construction method is to embed embedded parts into the frame reinforced concrete main beams 2 to cast concrete, and install the frame steel secondary beams 3 after the concrete is cured to reach the strength. In addition, the adjustable connecting device 7 is arranged at the end part of the frame steel secondary beam, so that the accurate installation position of the frame steel secondary beam 3 is ensured; before pouring concrete, the frame steel secondary beams 3 on the same floor are connected together through the adjustable connecting devices 7 at the two ends of the frame steel secondary beams to form a whole, so that looseness caused by disturbance of high-strength bolts at the connecting positions of the frame steel secondary beams in the next working procedure (such as pouring concrete) can be prevented, and the installation quality is guaranteed.
The above embodiments are only for illustrating the technical solution of the present invention, and not for limiting the same; although the invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some or all of the technical features thereof can be replaced by equivalents; such modifications and substitutions do not depart from the spirit of the invention.