CN117552406B - A method for pre-grouting reinforcement of joints in underground continuous walls in complex strata - Google Patents
A method for pre-grouting reinforcement of joints in underground continuous walls in complex strataInfo
- Publication number
- CN117552406B CN117552406B CN202410006632.2A CN202410006632A CN117552406B CN 117552406 B CN117552406 B CN 117552406B CN 202410006632 A CN202410006632 A CN 202410006632A CN 117552406 B CN117552406 B CN 117552406B
- Authority
- CN
- China
- Prior art keywords
- grouting
- holes
- hole
- wall
- reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Paleontology (AREA)
- Mining & Mineral Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Soil Sciences (AREA)
- Hydrology & Water Resources (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
The invention belongs to the technical field of underground diaphragm wall construction, and discloses a construction method for pre-grouting reinforcement of a seam of an underground diaphragm wall in a complex stratum, which aims to solve the problems of long construction period, high cost and poor stratum adaptability of the existing seepage-proofing treatment mode of the seam of the underground diaphragm wall. The method comprises the steps of carrying out positioning paying-off on guide walls, joints and grouting holes according to a survey report and a design drawing, wherein the grouting holes comprise a first grouting hole, at least one group of second grouting holes and at least one group of third grouting holes, and then grouting and reinforcing the first grouting hole, the second grouting holes and the third grouting holes by utilizing sectional grouting. The invention has the advantages of flexible adjustment and the like according to local conditions, and is suitable for ultra-deep underground continuous wall construction under various stratum conditions. The invention fully utilizes the advantages of sleeve valve pipe grouting, the grouting quantity is accurate and controllable, and the engineering benefit can be obviously improved.
Description
Technical Field
The invention belongs to the technical field of underground continuous wall construction, and particularly relates to a construction method for joint pre-grouting reinforcement of an underground continuous wall in a complex stratum.
Background
The underground diaphragm wall is a containment and waterproof structure for ultra-deep foundation pit (depth is more than 10 m), and has the advantages of good structural continuity, good impermeability, large overall rigidity and the like. In particular to deep foundation pit engineering in coastal areas, precipitation is difficult due to high water level, and underground continuous walls are mostly adopted for supporting. In addition, the underground diaphragm wall construction vibration is little, and the noise is low, and space utilization is high, is particularly suitable for the construction in the city. Along with the gradual development and utilization of urban underground space, the excavation depth of foundation pit engineering is larger and larger, and as one of the building envelope commonly used for foundation pits, namely an underground continuous wall, the stratum traversed by construction is more complex and changeable, so that the difficulty of seam quality control in the construction process is increased, and the water seepage problem is quite remarkable.
Aiming at the problem of water seepage at the joint position of the underground diaphragm wall, the prior art also discloses a water seepage prevention treatment technology for the joint position, for example, application number 201310676753X discloses a waterproof structure for the joint of the underground diaphragm wall and a construction method thereof, the waterproof structure comprises a first underground diaphragm wall and a second underground diaphragm wall which are intersected with each other, a flat bending section is arranged at the end of the second underground diaphragm wall connected with the first underground diaphragm wall, the bending section extends towards the outer side of a pit, the bending section is close to the first underground diaphragm wall, a single-row triaxial stirring pile continuously extending along the length direction of the wall body is arranged at the wall body of the second underground diaphragm wall towards the inner side of the pit, and a triaxial stirring pile group formed by a plurality of parallel triaxial stirring piles continuously extending along the length direction of the wall body is arranged at the wall body of the outer side of the second underground diaphragm wall; and a plurality of high-pressure jet grouting piles for sealing are arranged at the joint between the end head of the bending section of the second underground diaphragm wall and the first underground diaphragm wall.
For example, patent number 2019209006779 discloses a water seepage prevention structure at a joint of a continuous wall, which comprises a plurality of steel sheet piles and jet grouting piles, wherein the steel sheet piles are mutually overlapped and inserted into a row outside a seepage point and form a region which is enough to cover the seepage point, the jet grouting piles are arranged at a gap between the steel sheet piles at two ends and the continuous wall, and the gap between the steel sheet piles at the other positions and the continuous wall is grouting reinforced.
For example, patent application number 2020201216470 discloses a new and old diaphragm wall joint treatment structure, which comprises an extension diaphragm wall, a new diaphragm wall and an old diaphragm wall, wherein one end of the extension diaphragm wall is connected with the new diaphragm wall, the other end of the extension diaphragm wall is contacted with the old diaphragm wall, a plurality of grouting pipes are arranged at the contact part of the extension diaphragm wall and the old diaphragm wall, and the grouting pipes are used for grouting to fill gaps between the new diaphragm wall and the old diaphragm wall and gaps between the extension diaphragm wall and the old diaphragm wall. The novel underground continuous wall comprises a first-stage groove section and a second-stage groove section, a seam water stop device is arranged between the first-stage groove section and the second-stage groove section, and the lengthened underground continuous wall is connected with the first-stage groove section.
The prior art has the main solutions for the problem of water seepage at the joints of the underground diaphragm wall, such as (1) construction of high-pressure jet grouting piles outside the wall of the groove on the earth facing side, (2) high-pressure grouting of the wall of the groove on the earth facing side, and (3) grouting after hole wall penetrating after excavation.
However, for the construction high-pressure jet grouting pile, the seepage prevention effect is best, because the jet grouting can form a tight inclusion around the joint, the grouting pressure is generally high, the slurry diffusion radius is guaranteed, the construction cost is high, the space requirement on the site is high, and the stratum adaptability is poor.
For high-pressure grouting, the seepage prevention effect is not as good as that of the first type due to the limitation of grouting pressure, and waste is easily caused due to the fact that the grouting cannot be carried out in a segmented mode during ultra-deep excavation.
For post-grouting of perforated walls after excavation, the post-grouting method is a substantial remedy, and timeliness of grouting is difficult to guarantee. In addition, the water seepage retreatment is found to affect other working procedures after excavation, and the safety influence is considered when the water seepage is serious, and the shutdown is also possible.
Disclosure of Invention
The invention aims to solve the technical problems, and provides a construction method for pre-grouting reinforcement of joints of underground continuous walls of complex strata, which has the advantages of being suitable for seepage prevention treatment of joints of underground continuous walls of complex strata, being capable of being flexibly adjusted according to local conditions in a specific construction process, being suitable for ultra-deep underground continuous wall construction under various stratum conditions, and the like.
In order to solve the technical problems, the invention adopts the following technical scheme:
A construction method for joint pre-grouting reinforcement of a complex stratum underground continuous wall is characterized by comprising the following steps:
S1, determining a strong permeable layer and a grouting range which need grouting reinforcement according to a reconnaissance report and a design drawing;
S2, positioning and paying off guide walls, joints and grouting holes according to a survey report and a design drawing according to coordinate datum points provided by owners; the grouting holes comprise a first grouting hole, at least one group of second grouting holes and at least one group of third grouting holes, wherein the first grouting hole comprises a back soil side grouting hole and a soil facing side grouting hole, the back soil side grouting hole is positioned at the outer side of a back soil side groove wall of the underground diaphragm wall, and the soil facing side grouting hole, the second grouting hole and the third grouting hole are positioned at the outer side of a soil facing side groove wall of the underground diaphragm wall; the back soil side grouting holes are uniformly distributed along the length direction of the back soil side slot wall of the underground diaphragm wall and are distributed on the whole back soil side slot wall, the number of each group of third grouting holes is 3, the 3 third grouting holes are triangular, 2 third grouting holes correspond to the left end and the right end of an I-shaped steel joint of the underground diaphragm wall, the other 1 third grouting holes correspond to the central position of the I-shaped steel joint, the positions of the 1 third grouting holes corresponding to the central position of the I-shaped steel joint are far away from the earth facing side slot wall compared with the 2 third grouting holes corresponding to the left end and the right end of the I-shaped steel joint, each group of second grouting holes comprises 2 second grouting holes, the 2 third grouting holes are distributed on the outer side of one group of third grouting holes (namely, the 3 third grouting holes are distributed in a soil body between the 2 second grouting holes), and the earth facing side slot wall of the underground diaphragm wall is uniformly distributed except for the positions occupied by the second grouting holes and the rest of the third grouting holes.
In the concrete implementation process, the distances between each back soil side grouting hole arranged on the outer side of the back soil side groove wall of the underground diaphragm wall and the back soil side groove wall are the same, namely, each back soil side grouting hole is arranged side by side along the back soil side groove wall. The distance between the soil-facing side grouting holes, the second grouting holes and the third grouting holes corresponding to the central positions of the I-steel connectors from the wall of the soil-facing side slot is the same, namely the soil-facing side grouting holes, the second grouting holes and the third grouting holes corresponding to the central positions of the I-steel connectors are arranged side by side along the wall of the soil-facing side slot.
And S3, drilling holes by using a drilling machine according to the drilling positions, wherein the drilling depth is determined according to the grouting depth, the depth of the first grouting hole is 0.5m below the bottom of the filling stone layer, the depth of the second grouting hole is 0.5m below the bottom of the middle sand layer, and the depth of the third grouting hole is 0.5m below the bottom of the strong weathered bedrock. Even though the hole forming depth of the first grouting hole needs to penetrate through the bottom of the filling block stone layer and drill down by 0.5m, the hole forming depth of the second grouting hole needs to penetrate through the bottom of the middle sand layer in the stratum and drill down by 0.5m, and the hole forming depth of the third grouting hole needs to penetrate through the bottom of the strong weathered bedrock in the stratum and drill down by 0.5m.
S4, pressing the prepared shell material into the bottom of a drilled hole by using a drill rod through a squeezing grouting machine after forming the hole;
s5, immediately and sequentially putting the prepared sleeve valve tubes after the shell material replacement is completed;
S6, arranging a movable grouting station and a pump station;
S7, preparing grouting slurry according to the type of the reinforced stratum;
s8, after the grouting pipe is connected, carrying out a pressurized water test;
s9, starting a backward type sectional grouting process to perform sectional grouting reinforcement on the drilled grouting holes by using sleeve valve pipes. Namely, sectional grouting is carried out in each grouting hole from the bottom of the hole to the top.
In some embodiments, when the drill is used to drill the hole in step S3, the third grouting hole should be drilled first, then the second grouting hole should be drilled, and finally the first grouting hole should be drilled.
In some embodiments, the first grouting hole should be drilled by a jump drill when drilling. Specifically, a jump drilling mode of 'jump 1 drill 1' is adopted to drill the hole. Namely, the first grouting holes (the earth facing side grouting holes and the earth backing side grouting holes) are formed by drilling 1 hole and jumping 1 hole. The manner of drilling the hole is well understood and appreciated by those skilled in the art.
In some embodiments, in the step S9, the sleeve valve pipe is utilized for segmented grouting reinforcement, the first grouting holes are fully filled with the first grouting holes, the second grouting holes are used for grouting the distance of more than 0.5m below the bottom of the filling block stone layer, the range of more than 0.5m above the top of the middle sand layer to less than 0.5m below the bottom of the middle sand layer in the stratum is grouted, the rest of the sections in the second grouting holes are not grouted, the third grouting holes are used for grouting the distance of more than 0.5m below the bottom of the filling block stone layer, the range of more than 0.5m above the top of the middle sand layer to less than 0.5m below the bottom of the middle sand layer in the stratum is grouted, the range of more than 0.5m above the top of the strongly weathered bedrock in the stratum is grouted, and the rest of the sections in the third grouting holes are not grouted.
In some embodiments, after the guide wall and joint positions in step S2 are determined, permanent marks and temporary marks should be made, and then positioning and paying-off of the positions of the grouting holes are performed.
In some embodiments, when the sectional grouting is performed in step S9, the length of each grouting section is 0.3-0.4m, and after one section of grouting is completed, a lower section of grouting is performed on the grouting core pipe of the sleeve lifting valve pipe.
In some embodiments, when the reinforcement cage of the underground diaphragm wall is processed, one wall toe grouting pipe is respectively arranged at the left end and the right end of the reinforcement cage.
Compared with the prior art, the invention has the following beneficial effects:
the invention relates to a construction method for pre-grouting reinforcement of a seam of a complex stratum underground diaphragm wall, which utilizes sleeve valve pipe grouting technology to perform seepage prevention reinforcement of the seam of the underground diaphragm wall. Compared with the common steel pipe grouting, the grouting pile can realize sectional grouting and repeated grouting. Compared with high-pressure grouting, the method can realize sectional grouting, so that the method can be flexibly applied according to geological conditions, and economic benefits are considered on the premise of achieving waterproof underground continuous wall.
The blanking length and grouting quantity of the sleeve valve pipe can be estimated according to geotechnical engineering investigation reports and the geological section of the continuous wall structure in the design file, so that the sleeve valve pipe has stronger pertinence and good economic benefit.
The invention provides the arrangement of the first grouting holes, the second grouting holes and the third grouting holes by adopting the combination of length and length, and the properly encrypted grouting hole arrangement form has originality in the field of underground diaphragm wall construction, and reduces the grouting amount and the construction period to the greatest extent on the premise of ensuring water resistance so as to realize the maximization of safety and economy. And the first grouting hole, the second grouting hole and the third grouting hole can be used for reinforcing the groove wall after being reinforced in a segmented mode, and in subsequent construction, the reinforcement of the groove wall (the back soil side groove wall and the earth facing side groove wall) can be reduced or not required, so that the construction period of the whole underground continuous wall is further shortened, and the construction cost is reduced.
The joint position and the grouting holes are staggered due to construction reasons in the later stage, and the adjustment can be carried out by adopting measures such as drilling supplement, lengthening and the like.
The pre-grouting reinforcement method provided by the invention has the advantages of flexible adjustment and the like according to local conditions, and is suitable for ultra-deep underground continuous wall construction under various stratum conditions. Meanwhile, the method fully utilizes the advantages of sleeve valve pipe grouting, the grouting amount is accurate and controllable, and the engineering benefit can be obviously improved.
Drawings
FIG. 1 is a flow chart of an embodiment of the present invention;
FIG. 2 is a schematic plan view of a first grouting hole, a second grouting hole and a third grouting hole according to the present invention;
FIG. 3 is a schematic cross-sectional view of a reinforced grouting hole in the center of an I-steel joint of an underground diaphragm wall, wherein the left side of FIG. 3 shows a schematic cross-sectional view of a first grouting hole in the wall of a back soil side, the right side of FIG. 3 shows a schematic cross-sectional view of a third grouting hole in the wall of a front soil side, the first grouting hole is grouting reinforced to form a filling stone layer grouting body 11, the second grouting hole and a middle sand layer grouting body 12 are grouting reinforced to form a middle sand layer grouting body in the third grouting hole, and the second grouting hole and a strong weathered bedrock grouting body 13 are grouting reinforced to form a weathered bedrock grouting body;
The figure shows that the grouting device comprises a first grouting hole 1, a second grouting hole 2, a third grouting hole 3, a wall toe grouting hole 4, a I-steel joint 5, a back soil side groove wall 6, a reinforcing cage 7, a soil facing side groove wall 8, a sealing rib 9, a pouring guide pipe 10, a filling block stone layer grouting body 11, a middle sand layer grouting body 12, a weathered bedrock grouting body 13, a sleeve pipe 15 and a sleeve valve pipe.
Detailed Description
The present invention is further described below in conjunction with embodiments, which are merely some, but not all embodiments of the present invention. Based on the embodiments of the present invention, other embodiments that may be used by those of ordinary skill in the art without making any inventive effort are within the scope of the present invention.
In the description of the present invention, it should be noted that the terms "center," "upper," "lower," "left," "right," "vertical," "horizontal," "inner," "outer," and the like are merely for convenience of description and to simplify the description of the present invention, but rather to indicate or imply that the apparatus or elements being referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the present invention, the terms "first," "second," "third," are used for descriptive purposes only and should not be construed as indicating or implying relative importance, and furthermore, the terms "mounted," "connected," should be construed broadly, e.g., as being fixedly connected, detachably connected, or integrally connected, or indirectly connected through intermediaries unless otherwise explicitly stated or limitations. The specific meaning of the above terms in the present invention will be understood in specific cases by those of ordinary skill in the art.
Referring to fig. 1 to 3, the construction method for pre-grouting reinforcement of the joint of the underground diaphragm wall of the complex stratum comprises the following steps:
S1, determining a strong permeable layer and a grouting range which need grouting reinforcement according to a reconnaissance report and a design drawing. The investigation report is used for carrying out list description on the permeability coefficient of each soil layer, so that the reinforcement range of the sectional grouting can be conveniently determined in the later period. The design drawing is used for explaining the framing condition of the continuous wall, and the groove width number and the groove width are determined so as to facilitate later checking and lofting.
S2, positioning and paying off guide walls, joints and grouting holes according to a survey report and a design drawing according to coordinate datum points provided by owners; the first grouting holes 1 comprise a back soil side grouting hole and an earth facing side grouting hole, the earth facing side grouting holes, the second grouting holes 2 and the third grouting holes 3 are located on the outer side of an earth facing side slot wall 8 of the underground continuous wall, the back soil side grouting holes are uniformly distributed along the length direction of the back soil side slot wall 6 of the underground continuous wall and are distributed on the whole back soil side slot wall 6, the number of each group of third grouting holes is 3, the 3 third grouting holes are in a triangular shape, 2 third grouting holes 3 correspond to the left end and the right end of an I-steel joint 5 of the underground continuous wall, the 1 third grouting holes 3 are located on the outer side of the earth facing side slot wall 8 of the underground continuous wall, the 2 third grouting holes correspond to each other, the 3I-steel joint 5 correspond to the center position of the I-steel joint 5, the three grouting holes are distributed on the outer side wall 2 of the left end of the I-steel joint 5, and the other I-steel joint 3 are distributed on the outer side wall 2 of the I-steel joint 2, and the other grouting holes are distributed on the left end of the wall 2 of the underground continuous wall, and the three grouting holes are distributed on the left end of the wall 2 more evenly, namely, the three grouting holes are distributed on the outer side wall of the wall of each group of the wall are distributed on the wall along the length direction of the back soil side slot wall 6, the back soil side grouting holes are distributed on the back soil side wall, the number of the third grouting holes is 3, and the third grouting holes are distributed on the three I-shaped.
In the concrete implementation process, the distances between each back soil side grouting hole arranged on the outer side of the back soil side groove wall 6 of the underground diaphragm wall and the back soil side groove wall are the same, that is, each back soil side grouting hole is arranged side by side along the back soil side groove wall. The distance between the soil-facing side grouting holes, the second grouting holes and the third grouting holes corresponding to the central positions of the I-steel connectors from the wall of the soil-facing side slot is the same, namely the soil-facing side grouting holes, the second grouting holes and the third grouting holes corresponding to the central positions of the I-steel connectors are arranged side by side along the wall of the soil-facing side slot.
The first grouting holes are grouting reinforcement holes of the filling stone layers, and because the filling stone layers are generally loose and uneven, water seepage channels are easy to form in the gaps between the filling stone layers, water stagnation strips can be formed due to the difference of the compaction degree, and therefore the permeability coefficient and the water content are generally larger, and grouting reinforcement is needed.
The second grouting holes are middle sand layer grouting holes, the sand layer is generally complex in pore structure and uniform in pore diameter, and has larger permeability coefficient when being positioned in coastal areas or in areas facing rivers and lakes, and grouting reinforcement is also needed.
The third grouting holes are strong-weathered bedrock grouting holes, the strong-weathered bedrock is generally broken in rock mass structure, weathered cracks develop, the strong-weathered bedrock below the underground water level contains more bedrock crack water, and the permeability coefficient is generally larger, so that grouting reinforcement is still necessary for the strong-weathered bedrock.
And S3, drilling holes by using a drilling machine according to the drilling positions, wherein the drilling depth is determined according to the grouting depth, the depth of the first grouting hole is 0.5m below the bottom of the filling stone layer, the depth of the second grouting hole is 0.5m below the bottom of the middle sand layer, and the depth of the third grouting hole is 0.5m below the bottom of the strong weathered bedrock. Even though the hole forming depth of the first grouting hole needs to penetrate through the bottom of the filling block stone layer and drill down by 0.5m, the hole forming depth of the second grouting hole needs to penetrate through the bottom of the middle sand layer in the stratum and drill down by 0.5m, and the hole forming depth of the third grouting hole needs to penetrate through the bottom of the strong weathered bedrock in the stratum and drill down by 0.5m.
And S4, pressing the prepared shell material into the bottom of the drilled hole through a drill rod by using a squeezing grouting machine after forming the hole, wherein the shell material is formed by mixing cement, bentonite and water in the specific implementation process.
The mass ratio of the three materials in the shell material is cement, bentonite and water=1:1.5:2, and the viscosity of the prepared shell material is 27s.
And S5, immediately and sequentially putting the prepared sleeve valve tubes after the sleeve material replacement is completed.
And S6, arranging a movable grouting station and a pump station.
And S7, preparing liquid slurry according to the type of the reinforced stratum. The proportion of concrete slurry should be adjusted correspondingly according to the actual situation of the site, and records are made, so that the quality of the subsequent underground diaphragm wall construction is guaranteed, and the water glass can be used after being diluted. The ordinary silicate cement with the strength grade of 42.5 and diluted water glass are used as main preparation materials, the water cement ratio is 0.8:1-1:1, the volume ratio of cement slurry to water glass slurry is preferably 0.6-1, the modulus of the water glass is 2.6-3.0, the water glass concentration is preferably 30-40Be degrees, and the slurry concentration is from thin to thick.
And S8, after the grouting pipe is connected, performing a water pressing test, and checking whether the grouting pipe leaks water or not by using 1.5-2 times of grouting pressure by using the grouting pump, and judging whether the equipment state is normal or not.
S9, starting a backward type sectional grouting process to perform sectional grouting reinforcement on the drilled grouting holes by using sleeve valve pipes. Namely, sectional grouting is carried out in each grouting hole from the bottom of the hole to the top.
In the concrete implementation process, the sleeve valve pipe and the grouting system can be purchased directly as required, and the three-section reinforcing system of the filled stone layer, the sand layer and the strong-weathered bedrock is realized by utilizing the backward grouting of the sleeve valve pipe. For example, sleeve valve pipes are purchased with 4m standard segment PVC sleeve valve pipes with the diameter of 48mm, and the sleeve valve pipes are assembled and put down on site according to the needs.
In the concrete implementation process, the rubber sleeve is tightly fastened at the opening of the sleeve valve pipe 15 and covers the grouting holes, and the bottom end of the sleeve valve pipe is tightly fastened by geotextile and other objects to prevent the sleeve shell material from entering the sleeve valve pipe. The sleeve valve tubes 15 of each section are connected with each other through the sleeve 14, and the sleeve valve tubes and the connecting sleeve are firmly adhered at the joint of the sleeve 14 and the sleeve valve tubes 15 by adopting U-PVC adhesive.
When the sleeve valve tube is lowered, the verticality of the sleeve valve tube should be ensured, the deviation is not more than 0.3%, and the upper part of the sleeve valve tube should be higher than the ground.
The pre-grouting reinforcement method provided by the invention has the advantages of flexible adjustment and the like according to local conditions, and is suitable for ultra-deep underground continuous wall construction under various stratum conditions. Meanwhile, the method fully utilizes the advantages of sleeve valve pipe grouting, the grouting amount is accurate and controllable, and the engineering benefit can be obviously improved.
In some embodiments, when the drill is used to drill the hole in step S3, the third grouting hole should be drilled first, then the second grouting hole should be drilled, and finally the first grouting hole should be drilled.
In some embodiments, the first grouting hole should be drilled by a jump drill when drilling. Specifically, a jump drilling mode of 'jump 1 drill 1' is adopted to drill the hole. Namely, the first grouting holes (the earth facing side grouting holes and the earth backing side grouting holes) are formed by drilling 1 hole and jumping 1 hole. The manner of drilling the hole is well understood and appreciated by those skilled in the art.
In some embodiments, in the step S9, the sleeve valve pipe is utilized for segmented grouting reinforcement, the first grouting holes are fully filled with the first grouting holes, the second grouting holes are used for grouting the distance of more than 0.5m below the bottom of the filling block stone layer, the range of more than 0.5m above the top of the middle sand layer to less than 0.5m below the bottom of the middle sand layer in the stratum is grouted, the rest of the sections in the second grouting holes are not grouted, the third grouting holes are used for grouting the distance of more than 0.5m below the bottom of the filling block stone layer, the range of more than 0.5m above the top of the middle sand layer to less than 0.5m below the bottom of the middle sand layer in the stratum is grouted, the range of more than 0.5m above the top of the strongly weathered bedrock in the stratum is grouted, and the rest of the sections in the third grouting holes are not grouted.
In some embodiments, after the guide wall and joint positions in step S2 are determined, permanent marks and temporary marks should be made, and then positioning and paying-off of the positions of the grouting holes are performed.
In some embodiments, when the sectional grouting is performed in step S9, the length of each grouting section is 0.3-0.4m, and after one section of grouting is completed, a lower section of grouting is performed on the grouting core pipe of the sleeve lifting valve pipe.
When the grouting pressure reaches the design final pressure and the duration is not less than 2min, the grouting can be finished, and when the grouting of the sleeve valve pipe is finished, the sleeve valve pipe is cleaned by clean water to prepare secondary grouting.
In order to further guarantee the joint construction quality, the two toe grouting pipes 4 are arranged when the continuous wall reinforcement cage 7 is processed, the toe grouting pipes 4 are bound by avoiding the position of the concrete pouring guide pipe 10, and the toe grouting is carried out after the concrete strength reaches 80%. Wherein, the underground diaphragm wall is furnished with steel reinforcement cage 7, and steel reinforcement cage 7 is furnished with and seals muscle 9, and the person skilled in the art can understand and understand, and this is not repeated here.
The invention relates to a construction method for pre-grouting reinforcement of a seam of a complex stratum underground diaphragm wall, which utilizes sleeve valve pipe grouting technology to perform seepage prevention reinforcement of the seam of the underground diaphragm wall. Compared with the common steel pipe grouting, the grouting pile can realize sectional grouting and repeated grouting. Compared with high-pressure grouting, the method can realize sectional grouting, so that the method can be flexibly applied according to geological conditions, and economic benefits are considered on the premise of achieving waterproof underground continuous wall.
The blanking length and grouting quantity of the sleeve valve pipe can be estimated according to geotechnical engineering investigation reports and the geological section of the continuous wall structure in the design file, so that the sleeve valve pipe has stronger pertinence and good economic benefit.
The invention provides the arrangement of the first grouting holes, the second grouting holes and the third grouting holes by adopting the combination of length and length, and the properly encrypted grouting hole arrangement form has originality in the field of underground diaphragm wall construction, and reduces the grouting amount and the construction period to the greatest extent on the premise of ensuring water resistance so as to realize the maximization of safety and economy. And the first grouting hole, the second grouting hole and the third grouting hole can be used for reinforcing the groove wall after being reinforced in a segmented mode, and in subsequent construction, the reinforcement of the groove wall (the back soil side groove wall and the earth facing side groove wall) can be reduced or not required, so that the construction period of the whole underground continuous wall is further shortened, and the construction cost is reduced.
The joint position and the grouting holes are staggered due to construction reasons in the later stage, and the adjustment can be carried out by adopting measures such as drilling supplement, lengthening and the like.
As a preferred implementation mode in the present case, foundation pit supporting construction of a certain subway project station in Shenzhen city is taken as an example. Taking III-9 pairs of continuous walls as an example according to geotechnical engineering investigation reports and design files, the continuous wall construction penetrating stratum is mainly a three-phase stratum of a typical coastal area of artificial filling-sea phase deposition-lower granite.
Further, according to the strong permeable layer judgment standard, namely the permeability coefficient is larger than 1m/d, the strong permeable layer penetrated by the continuous wall construction is determined to be a filling stone layer, a middle sand layer and a strong weathered granite layer (namely the strong weathered base rock layer) in sequence.
Further, confirm and fill block stone layer, sand bed and cubic strong weathered granite layer segmentation reinforcement degree of depth and scope, consolidate each layer top, bottom elevation expansion 0.5m respectively, have:
the top elevation of the reinforced area = stratum top elevation +0.5m, and the depth is the guide wall top elevation-stratum top elevation-0.5 m;
reinforcing stratum bottom elevation = stratum bottom elevation-0.5 m, and depth is guide wall top elevation-stratum bottom elevation +0.5m;
The reinforcing range of the filling stone layer is 4.8-9.8m, the reinforcing range of the middle sand layer is-13.1-21.2 m, and the reinforcing range of the strong weathered granite layer is-42.5-50.6 m.
Further, positions of the earth facing side groove wall 8, the earth backing side groove wall 6, the I-steel joint 5, the first grouting hole 1, the second grouting hole 2 and the third grouting hole 3 are carried out according to design files and investigation reports, and the positions are positioned by using striking red marks according to paying-off results.
Further, the blanking length of the sleeve valve pipe is determined according to the grouting range, the blanking length of the first grouting hole 1 is 16m, 4 standard sections are adopted, the blanking length of the second grouting hole 2 is 28m, and the blanking length of the third grouting hole 3 is 56m.
Further, a drilling machine is adopted for guiding holes, the model of the drilling machine is selected to be XY-100 type, the drilling sequence is 3 type, 2 type and 1 type, holes are formed by expanding the center position of the I-steel joint 5 to two sides, and the principle of 'jumping 1 to drill 1' is adopted when the first grouting hole 1 is drilled.
Further, the casing materials are prepared according to the cement, bentonite and water=1:1.5:2 and the viscosity is 27s, and after the casing materials are formed, the prepared casing materials are pressed into the bottoms of drilling holes (namely, into the first grouting hole 1, the second grouting hole 2 and the third grouting hole 3) respectively through a drill rod by using an extrusion grouting machine, and the pressing sequence is the same as the drilling sequence.
Further, immediately after the casing material replacement is completed, sleeve valve pipes are sequentially put into the drill holes 1, 2 and 3 (namely, the first grouting hole 1, the second grouting hole 2 and the third grouting hole 3), and the pipe-down sequence is the same as the drilling sequence.
Further, a mobile grouting station and a pump station are then arranged.
Further, grouting slurry is prepared, water glass is required to Be diluted for use, ordinary Portland cement with the strength grade of 42.5 and diluted water glass are used as main preparation materials, the water cement ratio is 0.8:1-1:1, the volume ratio of the cement slurry to the water glass slurry is preferably 0.6-1, the modulus of the water glass is 2.6-3.0, the water glass concentration is preferably 30-40Be degrees, and the slurry concentration is preferably from thin to thick.
Further, after the grouting pipe is connected, the grouting pump is used for checking whether the grouting pipe leaks water or not by using 1.5-2 times of grouting pressure, and whether the equipment state is normal or not is judged.
Further, a backward type sectional grouting process is started, grouting is performed in grouting holes 1,2 and 3 (namely a first grouting hole 1, a second grouting hole 2 and a third grouting hole 3) from bottom to top, the lifting distance is 0.3-0.4m each time, the grouting sequence is the same as the drilling sequence, the grouting pressure is 0.2-1.5MPa, when the grouting pressure reaches the design final pressure, the grouting can be finished after the duration is not less than 2min, and the sleeve valve pipe is cleaned by clean water when the grouting of the sleeve valve pipe is finished so as to prepare secondary grouting.
As the preferred embodiment of the scheme, grouting holes 1, 2 and 3 are covered by a rubber sleeve with a tight hoop outside the pipe at the position of the opening, the bottom end and the head of a sleeve valve pipe 15 are tightly bound by geotextile and the like to prevent the sleeve shell material from entering the sleeve valve pipe, a sleeve pipe 14 with the length of 20cm is used for connecting adjacent sleeve valve pipes, and the sleeve valve pipe 15 and a connecting sleeve pipe 14 are firmly adhered by adopting U-PVC adhesive.
As a preferred embodiment of the present case, the verticality of the holes 1, 2 and 3 of the grouting holes should be ensured, the deviation is regulated to be not more than 0.3%, the sleeve valve tube 15 should be lowered to the bottom of the holes, and the upper part should be 20cm higher than the ground.
In the preferred embodiment, the sleeve valve tube 15 is sealed at the tube opening after the sleeve valve tube is completely put down, so as to prevent sundries from entering the grouting tube and affecting grouting quality.
As a preferred embodiment of the present case, the first sleeve 15 is provided with a stopper, and clean water is injected into the stopper to prevent the sleeve 15 from being excessively bent.
As a preferable implementation mode of the scheme, after the grouting pipe is installed, quick setting cement mortar is filled at the position 3-5m below the ground surface and the orifice, so that the grouting is prevented from returning.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202410006632.2A CN117552406B (en) | 2024-01-03 | 2024-01-03 | A method for pre-grouting reinforcement of joints in underground continuous walls in complex strata |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202410006632.2A CN117552406B (en) | 2024-01-03 | 2024-01-03 | A method for pre-grouting reinforcement of joints in underground continuous walls in complex strata |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN117552406A CN117552406A (en) | 2024-02-13 |
| CN117552406B true CN117552406B (en) | 2026-05-19 |
Family
ID=89821879
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202410006632.2A Active CN117552406B (en) | 2024-01-03 | 2024-01-03 | A method for pre-grouting reinforcement of joints in underground continuous walls in complex strata |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN117552406B (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN120083209A (en) * | 2025-04-16 | 2025-06-03 | 中国铁路设计集团有限公司 | A method for grouting gaps in assembled ground-connected wall grooves |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105804107A (en) * | 2016-05-10 | 2016-07-27 | 吉林大学 | High-pressure-jetting and anti-seepage treatment method for triple tube of joint of underground diaphragm wall |
| CN106013078A (en) * | 2016-07-11 | 2016-10-12 | 中建市政工程有限公司 | A construction method for strengthening curtain structure in highly permeable ground |
| CN107503342A (en) * | 2017-08-22 | 2017-12-22 | 中建八局第三建设有限公司 | A kind of diaphram wall and its construction method |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2021013201A1 (en) * | 2019-07-24 | 2021-01-28 | 青岛理工大学 | Water stopping device and method for ground continuous wall joint in high-water-rich coastal area |
| CN113756370A (en) * | 2020-06-02 | 2021-12-07 | 中交哈尔滨地铁投资建设有限公司 | Underground continuous wall seam water stop reinforcing measure and detection method |
-
2024
- 2024-01-03 CN CN202410006632.2A patent/CN117552406B/en active Active
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105804107A (en) * | 2016-05-10 | 2016-07-27 | 吉林大学 | High-pressure-jetting and anti-seepage treatment method for triple tube of joint of underground diaphragm wall |
| CN106013078A (en) * | 2016-07-11 | 2016-10-12 | 中建市政工程有限公司 | A construction method for strengthening curtain structure in highly permeable ground |
| CN107503342A (en) * | 2017-08-22 | 2017-12-22 | 中建八局第三建设有限公司 | A kind of diaphram wall and its construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN117552406A (en) | 2024-02-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110230309B (en) | Karst area bridge karst cave pile foundation construction method | |
| CN106759473B (en) | The constructing structure and its construction method of underground pipe gallery and road | |
| CN112761166A (en) | Construction method for shallow foundation pit of combined support of piles and pre-grouting steel pipes based on SMW (soil mixing wall) construction method | |
| CN105525619B (en) | A kind of water rich strata bored tunnel occlusion pipe curtain | |
| CN104499479A (en) | Dig-hole pile construction method based on penetration of sand gravel backfilling layer | |
| CN206736963U (en) | Ditch millet section high water level district lid tunnel stagnant water structure | |
| CN109537615A (en) | Improve the construction method of karst or crushed zone area pile foundation first-time qualification rate | |
| CN114738050A (en) | Seepage-proofing drainage construction method for complex soft rock tunnel | |
| CN106013078A (en) | A construction method for strengthening curtain structure in highly permeable ground | |
| CN110017149A (en) | A kind of underground structure and construction method of underground excavation and construction of arch cover | |
| CN115539048A (en) | A construction method for shallow-buried bias-pressure tunnel entrance | |
| CN108005682A (en) | A kind of shield tunnel reinforcement means | |
| CN108571000A (en) | The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river | |
| CN117552406A (en) | A construction method for pre-grouting reinforcement of underground diaphragm wall joints in complex strata | |
| CN116446436A (en) | Construction method of precast pile group pile foundation in beaded karst cave stratum | |
| CN113982598B (en) | Non-drop grouting reinforcement construction method for shield connection channel of water-rich sandy pebble stratum | |
| CN119465986B (en) | A foundation pit retaining structure and its construction method in a confined space under weathered rock geological strata | |
| CN105484270B (en) | Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit | |
| CN120159029A (en) | Composite foundation construction method in strong erosion geological environment | |
| CN114575355A (en) | Soil protection and descent construction method | |
| CN119711526A (en) | A micro steel pipe pile embankment landslide reinforcement structure and its construction method | |
| CN111733841A (en) | A kind of lake bottom karst treatment method for deep buried shield tunnel | |
| CN118793070A (en) | A comprehensive construction method for supporting ultra-deep foundation pits in weakly permeable soil with high water level | |
| CN102191770B (en) | Geology improving method for trenchless construction | |
| CN217298895U (en) | Sand bed geological pile foundation hole bottom grouting device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |