CN117328895A - A high-stress soft and broken surrounding rock tunnel support method - Google Patents
A high-stress soft and broken surrounding rock tunnel support method Download PDFInfo
- Publication number
- CN117328895A CN117328895A CN202311454293.6A CN202311454293A CN117328895A CN 117328895 A CN117328895 A CN 117328895A CN 202311454293 A CN202311454293 A CN 202311454293A CN 117328895 A CN117328895 A CN 117328895A
- Authority
- CN
- China
- Prior art keywords
- surrounding rock
- hydraulic
- steel arch
- tunnel
- stress
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/107—Reinforcing elements therefor; Holders for the reinforcing elements
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/12—Temporary supports for use during building; Accessories
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/15—Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
- E21D11/152—Laggings made of grids or nettings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/18—Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/18—Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
- E21D11/186—Pre-stressing or dismantling devices therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D15/00—Props; Chocks, e.g. made of flexible containers filled with backfilling material
- E21D15/14—Telescopic props
- E21D15/44—Hydraulic, pneumatic, or hydraulic-pneumatic props
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D15/00—Props; Chocks, e.g. made of flexible containers filled with backfilling material
- E21D15/50—Component parts or details of props
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D15/00—Props; Chocks, e.g. made of flexible containers filled with backfilling material
- E21D15/50—Component parts or details of props
- E21D15/51—Component parts or details of props specially adapted to hydraulic, pneumatic, or hydraulic-pneumatic props, e.g. arrangements of relief valves
- E21D15/512—Arrangement of valves
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
- E21D20/02—Setting anchoring-bolts with provisions for grouting
- E21D20/025—Grouting with organic components, e.g. resin
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D21/00—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
- E21D21/0026—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/18—Special adaptations of signalling or alarm devices
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Mechanical Engineering (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
The invention discloses a high-stress soft broken surrounding rock roadway support method, which comprises the following steps: s1, measuring geomechanical parameters of surrounding rocks of a roadway, S2, constructing a flexible buffer layer, S3, selecting and installing a hydraulic steel arch frame assembly, S4, drilling and installing an anchor cable on the roadway, S5, injecting liquid into an inner cavity of a hydraulic damping rod, and setting a pressure threshold value of a three-purpose valve of the hydraulic damping rod according to stress of the surrounding rocks. More importantly, the deformation and damage of surrounding rocks of the roadway can be fully controlled, and rock dynamic disasters such as rock burst and the like can be prevented and treated.
Description
Technical Field
The invention relates to the technical field of mine roadway support, in particular to a high-stress soft broken surrounding rock roadway support method.
Background
Underground mining typically requires a large number of roadway projects to access the ore body, which in turn enables deposit development and mining of ore blocks, cutting and stoping operations. The report 2022 of Chinese mineral resources shows that the total underground mines corresponding to 173 minerals in the whole country are 3 ten thousand, and each roadway is newly excavated every year up to 1.5 ten thousand kilometers. It is clear that tunnelling plays an extremely important role in the production of underground mines. When a roadway is excavated in a rock body, the stress balance state of the original rock is destroyed, and stress concentration or transient unloading is caused by stress redistribution of surrounding rock. When the stability of the surrounding rock of the roadway is insufficient to bear, accidents such as roof fall, ledge, large deformation, rock burst and water burst disasters are easily caused if the supporting cannot be carried out timely and effectively. Therefore, the roadway support is a key for keeping the roadway smooth and surrounding rock stable, and has great significance for realizing safe and efficient mining of mines.
As mineral resources in the shallow part of the earth are increasingly exhausted, underground mines successively enter a kilometer-level deep mining stage, and the maximum mining depth reaches 4350m. The deep resource occurrence condition is complex, the mining environment presents the characteristics of high stress (> 40 MPa), high ground temperature (> 40 ℃) and high karst water pressure (> 10 MPa), strong disturbance and the like, so that disasters such as roof caving, rock burst and the like of a roadway frequently occur in the mining process, the disasters are difficult to predict and effectively prevent, particularly the roof caving and the large deformation of the roof caving of surrounding rock of a soft broken roadway are particularly prominent, and the construction and production operation of the roadway are seriously plagued. Therefore, how to effectively support the soft broken surrounding rock in the high-stress environment is a primary problem to be solved in the current mine industry. At present, a supporting mode mainly comprising grouting or a steel arch is generally adopted for supporting soft broken surrounding rock, but the practice finds that the supporting mode is difficult to adapt to high ground pressure and large energy under deep high stress, and is difficult to stably control the deformation of the surrounding rock and the occurrence of dynamic rock disasters. Therefore, the invention of a supporting structure or a method which can stably yielding, resisting deformation and releasing high-elasticity energy storage in matching complex geological conditions of deep surrounding rock and working is urgently needed.
Disclosure of Invention
The invention provides a high-stress soft broken surrounding rock roadway support method, which comprises the steps of firstly, constructing different numbers of drilling holes on surrounding rock around the roadway, measuring geomechanical parameters such as the thickness of a loose ring of the surrounding rock of the roadway, the stress of the surrounding rock and the like, then, firstly filling bagged light granular materials into the rock wall after the roadway is excavated, hanging metal meshes, then, assembling and erecting a hydraulic steel arch assembly to form a rectangular or trapezoid support structure, and finally constructing a certain number of horizontal drilling holes on the side of the roadway, installing short anchor cables to fix the hydraulic steel arch and anchor the surrounding rock of the side, and realizing the effective control of the deformation of the soft broken surrounding rock and the inhibition of rock disasters under the high-stress environment based on the steady state pressure release function of the hydraulic steel arch and the bagged light granular materials.
The scheme of the invention is as follows:
a high-stress soft broken surrounding rock roadway support method comprises the following steps:
s1, measuring geomechanical parameters of surrounding rock of roadway
Constructing a plurality of measuring holes in the surrounding rock of the roadway to be supported, measuring the loose circle range of the surrounding rock of the roadway and the displaying characteristics of the mine pressure of the roadway by adopting a drilling peeping instrument and a drilling stress meter, obtaining the loose circle thickness of the surrounding rock of the roadway and the stress of the surrounding rock, and providing basic data for the subsequent short anchor cable size design, the hydraulic steel arch model and the pressure threshold setting;
s2, flexible buffer layer construction
Continuously stacking bagged light granular materials on the wall surface of the surrounding rock of the roadway along the circumferential direction, forming a flexible buffer layer with a certain thickness on the surface of the wall of the roadway, then paving a metal net on the surface of the buffer layer, and supporting the metal net by adopting a rod piece for temporary support;
s3, selecting and installing hydraulic steel arch frame assembly
Selecting a hydraulic steel arch frame assembly according to the section of a roadway and the stress of surrounding rock, assembling the upper steel arch frame, the top plate steel arch frame, the hydraulic support and the hydraulic damping rod into a whole by virtue of bolts and nuts to form a supporting structure, attaching the supporting structure to a metal net, and placing the supporting structure along the axis of the roadway at a certain row distance; setting a hydraulic prop pressure threshold value, and injecting hydraulic oil to the hydraulic prop to the threshold value through a three-way valve by utilizing a liquid injection gun, so that the roof steel arch forms a certain supporting working resistance to the roof;
s4, roadway side drilling construction and anchor cable installation
Drilling anchor cable drill holes with a certain number and depth at intervals towards the roadway side along the vertical direction on the basis of the thickness of the roadway loosening ring, filling resin anchoring agent into the drill holes, sequentially installing an anchor cable body, a special-shaped tray and a lockset, forming a certain prestress, and realizing deep anchoring of surrounding rock of the roadway side and locking of the anchor cable and the roadway side steel arch;
s5, injecting liquid into inner cavity of hydraulic damping rod
The pressure threshold value of the three-purpose valve of the hydraulic damping rod is set according to the stress of the surrounding rock, hydraulic oil is injected into the left cavity and the right cavity of the hydraulic damping rod through the three-purpose valves at the two ends of the hydraulic damping rod by using the liquid injection gun until the rated pressure is reached, and the hydraulic damping rod and the hydraulic prop act together to realize the two-stage linkage of the pressure release energy and deformation resistance of the surrounding rock.
As a preferable technical scheme, the aperture of the measuring drilling hole is 30-90 mm, the depth of the measuring drilling hole is 3-5 m, and 5-11 measuring drilling holes are uniformly distributed along the circumferential direction of the roadway.
As the preferable technical scheme, the light granular material comprises one or more of spherical polyphenyl granules, polyurethane granules and ceramsite, and the thickness of a flexible layer constructed by the bagged light granular material is 20-40 cm.
As a preferable technical scheme, the hydraulic steel arch assembly comprises two upper steel arches, two top plate steel arches, two hydraulic supports and a hydraulic damping rod, wherein square iron plates are welded at the bottoms of the upper steel arches to increase the stress area of the steel arches so as to improve stability, the tops of the upper steel arches are in pin joint with one end of one top plate steel arch through bolts and nuts, and the waist parts of the upper steel arches and one end of the top plate steel arch are also in pin joint with one hydraulic support, so that the lifting of the top plate steel arches in the annular direction can be realized; a telescopic hydraulic damping rod is connected between the two roof steel arches in a pin joint mode; based on surrounding rock stress and theoretical mechanics, the section size of the steel arch can be obtained, and the row distance of the steel arch assembly in the axial direction of the roadway is 0.8-1.5 m.
As the preferable technical scheme, the steel arch frame is one of I-steel, channel steel and U-steel.
As the preferable technical scheme, the hydraulic damping rod comprises drum, telescopic link, piston, spring and three way valve, the pin joint of taking the round hole has been welded to the head of telescopic link, the afterbody of telescopic link extends into in the drum with the piston welds, be equipped with the hydraulic oil pocket in the drum, be equipped with the three way valve on the both ends lateral surface of drum, the tail end of telescopic link, piston and hydraulic oil pocket are in both ends symmetric distribution in the drum, be equipped with big stiffness spring between two pistons in the drum. The telescopic length range of the hydraulic damping rod is 0.5-1.5 m.
As an optimal technical scheme, the three-purpose valve has the functions of liquid injection, liquid discharge and liquid discharge, and when the hydraulic oil exceeds a set threshold value, the hydraulic oil can automatically discharge to keep constant resistance, so that the functions of pressure relief, energy release and large deformation adaptation are realized.
As the preferable technical scheme, the aperture of the anchor cable drilling hole is 30-60 mm, the depth of the anchor cable drilling hole is more than 0.5-3.0 m of the thickness of the loose coil, and the diameter of the cable body is 15-25 mm; a round hole for a rope body to pass through is formed in the middle of the special-shaped tray, one end of the round hole is clung to one end of the rock wall outside the anchor rope hole, the clamp is arranged on the upper steel arch frame, locking of the upper steel arch frame and prestress anchoring of surrounding rock are achieved through the prestress action of the anchor rope, the distance between adjacent anchor ropes is 0.5-2.0 m, and the row spacing is consistent with that of the steel arch frame assembly.
Due to the adoption of the technical scheme, the roadway support method for the high-stress soft broken surrounding rock comprises the following steps of S1, determining geomechanical parameters of the surrounding rock: constructing a plurality of measuring holes in the surrounding rock of the roadway to be supported, measuring the loose circle range of the surrounding rock of the roadway and the displaying characteristics of the mine pressure of the roadway by adopting a drilling peeping instrument and a drilling stress meter, obtaining the loose circle thickness of the surrounding rock of the roadway and the stress of the surrounding rock, and providing basic data for the subsequent short anchor cable size design, the hydraulic steel arch model and the pressure threshold setting; s2, constructing a flexible buffer layer: continuously stacking bagged light granular materials on the wall surface of the surrounding rock of the roadway along the circumferential direction, forming a flexible buffer layer with a certain thickness on the surface of the wall of the roadway, then paving a metal net on the surface of the buffer layer, and supporting the metal net by adopting a rod piece for temporary support; s3, selecting and installing the hydraulic steel arch frame assembly, selecting the hydraulic steel arch frame assembly according to the stress of surrounding rock, assembling the upper steel arch frame, the top plate steel arch frame, the hydraulic support and the hydraulic damping rod into a whole by virtue of bolts and nuts to form a supporting structure, attaching the supporting structure to a metal net, and placing the supporting structure along the axis of a roadway at a certain row distance; setting a hydraulic prop pressure threshold value, and injecting hydraulic oil to the hydraulic prop to the threshold value through a three-way valve by utilizing a liquid injection gun, so that the roof steel arch forms a certain supporting working resistance to the roof; s4, roadway side drilling construction and anchor cable installation: drilling anchor cable drill holes with a certain number and depth at intervals towards the roadway side along the vertical direction on the basis of the thickness of the roadway loosening ring, filling resin anchoring agent into the drill holes, sequentially installing an anchor cable body, a special-shaped tray and a lockset, forming a certain prestress, and realizing deep anchoring of surrounding rock of the roadway side and locking of the anchor cable and the roadway side steel arch; s5, injecting liquid into the inner cavity of the hydraulic damping rod, setting a pressure threshold value of a three-way valve of the hydraulic damping rod according to the stress of surrounding rock, simultaneously injecting hydraulic oil into the left and right cavities inside the hydraulic damping rod through the three-way valves at the two ends of the hydraulic damping rod by using a liquid injection gun until the rated pressure is reached, and realizing the two-stage linkage of the pressure release energy and deformation resistance of the surrounding rock under the combined action of the hydraulic prop.
The invention has the advantages that:
the support structure is matched with complex geological conditions of deep surrounding rock, and can stably yielding deformation resistance and release high-elasticity energy storage in operation. More importantly, the deformation and damage of surrounding rocks of the roadway can be fully controlled, and rock dynamic disasters such as rock burst and the like can be prevented and treated.
(1) The flexible layer constructed by the bag-shaped light granular material is light and easy to install, and has the functions of dispersing surrounding rock stress, absorbing surrounding rock crushing and expanding deformation and inhibiting surrounding rock energy release and preventing impact.
(2) The hydraulic steel arch frame assembly is assembled in a pin joint mode, the installation is convenient, high constant working resistance can be kept under high ground pressure and high energy storage release through the double-stage linkage action of the hydraulic support posts and the hydraulic damping rods, and the surrounding rock large deformation and the sudden release of energy are adapted by means of oil drainage and pressure relief;
(3) The short anchor cable after installation has a certain prestress, improves the stress state of the surrounding rock of the upper part, and plays a double purpose of efficiently anchoring the surrounding rock of the upper part and locking the steel arch assembly.
Drawings
FIG. 1 is a schematic view of a support structure according to the present invention;
FIG. 2 is a schematic view of the hydraulic damping lever structure of the present invention;
fig. 3 is a schematic view of the cable attachment structure of the present invention;
fig. 4 is a three view of the shaped tray of the present invention.
Wherein: the drilling machine comprises the following components of a roadway 1, a surrounding rock loosening ring 2, surrounding rock 3, a flexible buffer layer 4, a metal net 5, a side steel arch 6, a top steel arch 7, a hydraulic prop 8, a pin joint bolt 9, a hydraulic damping rod 10, a square iron plate 11, an anchor cable 12, a cylinder 101, a telescopic rod 102, a piston 103, a hydraulic oil 104, a three-purpose valve 105, a spring 106, a cable body 121, a special-shaped tray 122, a lock 123, a resin anchoring agent 124 and an anchor cable 125.
Detailed Description
The invention provides a high-stress soft broken surrounding rock roadway support method.
The invention is further described in connection with the following embodiments in order to make the technical means, the creation features, the achievement of the purpose and the effect of the invention easy to understand.
Example 1:
as shown in fig. 1, 2, 3 and 4, firstly, after a roadway 1 is excavated, drilling 5-11 measuring drill holes with depth of 3-5 m and aperture of 30-90 mm around the roadway 1, and measuring geomechanical parameters such as thickness of a loose coil 2, secondary stress in surrounding rock 3 and the like by using a drilling stress meter and a drilling peeping instrument;
secondly, paving a bagged light granular material filled with polyphenyl granules, polyurethane granules or ceramsite on the basis of ground pressure measurement to construct a flexible buffer layer 4 with the thickness of 20-40 cm, tightly paving a metal net 5, and supporting the flexible buffer layer by adopting a pipe/rod piece to temporarily support the flexible buffer layer;
thirdly, the upper steel arch 6, the roof steel arch 7, the hydraulic prop 8 and the hydraulic damping rod 10, the bottom ends of which are welded with square iron plates 11, are assembled into a whole by utilizing the pin joint bolts 9 to form a supporting structure, the supporting structure is arranged according to the row spacing of 0.8-1.2 m, and hydraulic oil 104 is injected into the hydraulic prop 8 through the three-purpose valve 105 to enable the roof steel arch 7 to generate supporting working resistance to the roof of the roadway 1;
then, drilling anchor cable drilling holes 125 with vertical spacing of 0.5-2.0 m, aperture of 30-60 mm and depth of 0.5-3.0 m larger than the thickness of the loosening ring at one side of the steel arch 6 of the upper part of the roadway 1, then filling resin anchoring agent 124, and installing the cable body 121 into the anchor cable drilling holes 125 through the special-shaped tray 122 for anchoring, wherein the special-shaped tray 122 is clamped on the steel arch 6 of the upper part and locked by a lock 123, so that the anchor cable 12 has certain prestress.
Finally, hydraulic oil 104 is injected into the left and right cavities inside the hydraulic damping rod 10 through three-purpose valves 105 at the two ends of the hydraulic damping rod by using a liquid injection gun until reaching rated pressure, and the hydraulic damping rod and the hydraulic support 8 jointly act to realize two-stage linkage of pressure release energy and deformation resistance, namely after the large deformation extrusion or impact energy of two sides exceeds the supporting efficiency of the anchor cable 12, the flexible buffer layer 4 firstly absorbs or disperses part of stress and energy, the upper steel arch 6 is stressed and transmits the stress to the top steel arch 7 through the constant resistance hydraulic support 8 to drive the telescopic rod 102 to shrink, so that the piston 103 moves in opposite directions and extrudes the spring 105, and the purposes of pressure release energy and strain change are realized. When the roof pressure is great, roof steel arch 7 receives the extrusion and exceeds the rated operating resistance of hydraulic prop 8, hydraulic prop 8's three-way valve 105 keeps operating resistance invariable through automatic oil drainage shrink but accompanies roof steel arch 7 phenomenon of sinking, damping rod 10 receives the tensile effect from this, telescopic link 102 is stretched and drive two pistons 103 reverse motion this moment, thereby the hydraulic oil 104 produces tensile resistance and keeps the constant resistance throughout the automatic oil drainage process of three-way valve 105 in the extrusion two cavities, to a great extent has supported roof stress, have steady state let the pressure release energy anti-deformation's function equally.
The hydraulic damping rod 10 is composed of a cylinder 101, a telescopic rod 102, a piston 103, a spring 106 and a three-way valve 105, a pin joint with a round hole is welded at the head of the telescopic rod 102, the tail of the telescopic rod 102 extends into the cylinder 101 to be welded with the piston 103, a hydraulic oil cavity is arranged in the cylinder 101, the three-way valve 105 is arranged on the outer side surfaces of two ends of the cylinder 101, the tail end of the telescopic rod 102, the piston 103 and the hydraulic oil cavity are symmetrically distributed at two ends of the cylinder 101, and a high-rigidity spring 106 is arranged between the two pistons 103 in the cylinder 101. The telescopic length of the hydraulic damping rod 10 ranges from 0.5m to 1.5m.
The steps of the invention are described below in connection with an embodiment:
the mining depth of a mine is 800m, and the phenomenon of high stress is more prominent. The roadway engineering reveals that the lithology of surrounding rock mainly comprises dolomite and phosphorite, joint cracks are very developed, geological structures such as karst cave and faults are widely distributed, the quality of the surrounding rock is poor, and the surrounding rock belongs to soft broken rock. In addition, the development of surrounding rock karst fissure water is also found in the tunneling process, large-range water spraying and water flushing appear on the full section of the tunnel, and the maximum water inflow is 200m 3 And/h. In the early stage of tunnel tunneling, the supporting effect of the steel arch net spraying, anchor net spraying and other processes under the advanced supporting of the guide pipe and the steel pipe is poor, roof collapse and side wall caving accidents frequently occur in the tunnel, and the tunnel construction operation and maintenance are seriously affected. Although grouting is performed by adopting cement slurry, cement-water glass dual-liquid slurry and chemical slurry to achieve a certain effect of controlling surrounding rock and water shutoff, the defects of high grouting cost, long construction period and the like exist, and the operation period and the cost are seriously influenced. The section of the main tunnel of the mine is designed into a rectangle, the length is 5.0m, and the width is 4.0m. In view of the above conditions, the implementation steps of the method of the invention are as follows:
(S1) measuring geomechanical parameters of surrounding rocks of the roadway: and 5 measuring holes with the diameter of 40mm and the depth of 4m are uniformly constructed in the roadway 1 to be supported towards the surrounding rock 3, the thickness of the loose ring of the surrounding rock of the roadway 1 is 2.2m by adopting a drilling peeping instrument and a buried drilling stress meter, and the maximum surrounding rock stress is 28MPa.
(S2) flexible buffer layer construction: continuously stacking bagged light ceramsite on the wall surface of surrounding rock 3 of a roadway 1 along the circumferential direction, forming a flexible buffer layer 4 with the thickness of 0.4m on the surface of the roadway wall, then paving a 6mm metal net 5 with the size of 0.5m multiplied by 1.0m and the grid of 100mm multiplied by 100mm on the surface of the buffer layer 4, and propping the metal net 5 for temporary support by adopting 40mm round steel pipes with different lengths;
(S3) selecting and installing the hydraulic steel arch assembly: according to the maximum surrounding rock stress of 28MPa, 16H-shaped steel is selected to manufacture a steel arch, two 4.0M long upper steel arches 6, two 2.0M long roof steel arches 7, two hydraulic supports 8 and one hydraulic damping rod 10 are assembled into a whole by means of M20 bolts and nuts to form a rectangular supporting structure, the rectangular supporting structure is installed and distributed according to a 1.0M row distance, the pressure threshold of the hydraulic supports 8 is set to be 35MPa, hydraulic oil 104 is injected into the hydraulic supports 8 to the threshold by using a liquid injection gun through a three-way valve 105, and the roof steel arches 7 form a certain supporting working resistance to the roof of a roadway 1;
(S4) roadway side drilling construction and anchor cable installation: drilling 3 anchor cable drilling holes 125 with the depth of 4.5m towards the roadway side at an interval of 1.0m along the vertical direction on the basis of the thickness of the roadway loosening ring on one side of the side steel arch 6, filling an MSCK2850 resin anchoring agent 124 in the holes, sequentially installing an anchor cable body 121 with the diameter of 22mm and the diameter of 32mm, a special-shaped tray 122 and a lockset 123 to form pretightening force not less than 150KN, and supporting surrounding rock by the special-shaped tray 122 and clamping hoop action on the side steel arch 6 realize deep anchoring of the side surrounding rock 3 of the roadway 1 and locking of the anchor cable 12 and the side steel arch 6;
(S5) injecting liquid into the inner cavity of the hydraulic damping rod: the three-way valve 105 of the hydraulic damping rod 10 is set to have a pressure threshold of 35MPa, hydraulic oil is simultaneously injected into the left and right cavities inside the three-way valve 105 at the two ends of the hydraulic damping rod 10 with the shortest length of 1.0m and the telescopic length of 1.0m by using a liquid injection gun until the pressure reaches the rated pressure, and the two-way linkage of steady-state pressure release energy and deformation resistance of the surrounding rock 3 is realized by coaction with the hydraulic prop 8.
In addition, since the three-way valve 105 has the basic function of discharging liquid, the hydraulic steel arch assembly is formed by connecting the hydraulic steel arch assembly in a pin joint manner. Therefore, the hydraulic steel arch assembly can be disassembled after the liquid is discharged through the three-way valve 105 after the roadway is scrapped, so that recycling is realized.
The foregoing has shown and described the basic principles, main features and advantages of the present invention. It will be understood by those skilled in the art that the present invention is not limited to the embodiments described above, and that the above embodiments and descriptions are merely illustrative of the principles of the present invention, and various changes and modifications may be made without departing from the spirit and scope of the invention, which is defined in the appended claims. The scope of the invention is defined by the appended claims and equivalents thereof.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202311454293.6A CN117328895A (en) | 2023-11-03 | 2023-11-03 | A high-stress soft and broken surrounding rock tunnel support method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202311454293.6A CN117328895A (en) | 2023-11-03 | 2023-11-03 | A high-stress soft and broken surrounding rock tunnel support method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN117328895A true CN117328895A (en) | 2024-01-02 |
Family
ID=89283061
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202311454293.6A Pending CN117328895A (en) | 2023-11-03 | 2023-11-03 | A high-stress soft and broken surrounding rock tunnel support method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN117328895A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN119982073A (en) * | 2025-03-07 | 2025-05-13 | 中国矿业大学 | A method for coordinated control of an external self-bearing ring and a near-surface yielding support ring for constructing a tunnel surrounding rock fracturing ring |
-
2023
- 2023-11-03 CN CN202311454293.6A patent/CN117328895A/en active Pending
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN119982073A (en) * | 2025-03-07 | 2025-05-13 | 中国矿业大学 | A method for coordinated control of an external self-bearing ring and a near-surface yielding support ring for constructing a tunnel surrounding rock fracturing ring |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106401645B (en) | A kind of deep high stress tunnel pressure relief support control method for coordinating based on drilling release | |
| CN114233385B (en) | Treatment method for mud-bursting water of inclined shaft | |
| CN101349064B (en) | The construction method of the vertical shaft of the surge chamber of the hydropower station under the soft rock geological condition | |
| CN104763432B (en) | A kind of method that high stress tunnel country rock release controls large deformation | |
| CN108775252A (en) | The supporting construction and method for protecting support in Deep Soft Rock tunnel | |
| CN102278128B (en) | High-stress poor rock roadway supporting process | |
| Jiang et al. | Failure mechanism analysis and support design for deep composite soft rock roadway: A case study of the Yangcheng coal mine in China | |
| CN113107489A (en) | High-ground-pressure three-soft coal seam along-empty crossheading advanced grouting reinforcement method | |
| Chen et al. | Evolution law and engineering application on main stress difference for a novel stress relief technology in two ribs on deep coal roadway | |
| CN116220795B (en) | A filling bag, a filling isolation wall for mining and filling, and a construction method thereof. | |
| CN107143338A (en) | A kind of coal mine roadway driving and method for protecting support | |
| CN113107525A (en) | Support system for extruded large-deformation tunnel, construction method and application | |
| CN105604065A (en) | Foundation fit support and peat-soil deep-foundation-pit-support high-pressure jet grouting anchoring method | |
| CN121088430A (en) | Active and passive reinforcement supporting method for full space of deep roadway | |
| CN114687769A (en) | A precise support method for deep circular roadway based on surrounding rock zoning | |
| CN110552731A (en) | top coal caving stoping roadway grouting anchor cable supporting structure and advanced supporting method thereof | |
| CN117780382A (en) | A flexible support method for surrounding rock of roadway (tunnel) | |
| CN112144551A (en) | Secondary reinforcement old side slope structure and construction method | |
| CN110593903B (en) | A new grouting anchor cable support method and grouting anchor cable | |
| CN116537784B (en) | Stabilization method of small coal pillar roadway along goaf | |
| CN115680668B (en) | Swirling flow vertical shaft construction method suitable for high-ground-stress hard rock area | |
| HUANG | Stability control of gate groups in deep wells | |
| AU2023369907A1 (en) | Roadside reinforcement support method for small coal pillar mining | |
| CN116658212A (en) | A construction method for the treatment of water gushing and mud gushing in karst tunnel rainwater-type dissolved tanks | |
| CN113203533A (en) | Method and equipment for verifying support body of roadway with large rock burst |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |