CN117144801A - Construction device and method for installing plate girder in sliding manner on track under height limiting environment - Google Patents

Construction device and method for installing plate girder in sliding manner on track under height limiting environment Download PDF

Info

Publication number
CN117144801A
CN117144801A CN202310947734.XA CN202310947734A CN117144801A CN 117144801 A CN117144801 A CN 117144801A CN 202310947734 A CN202310947734 A CN 202310947734A CN 117144801 A CN117144801 A CN 117144801A
Authority
CN
China
Prior art keywords
track
segmented
plate
trolley
height
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310947734.XA
Other languages
Chinese (zh)
Inventor
徐庆凯
苏绍泳
张强
孙君
陶涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Urban Development And Construction Co ltd
Original Assignee
China Railway 12th Bureau Group Urban Development And Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Urban Development And Construction Co ltd filed Critical China Railway 12th Bureau Group Urban Development And Construction Co ltd
Priority to CN202310947734.XA priority Critical patent/CN117144801A/en
Publication of CN117144801A publication Critical patent/CN117144801A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a construction device and a construction method for installing a plate girder in a sliding way of a track in a height-limited environment, wherein the construction device comprises a track trolley, a plurality of section tracks and a lifting device which are spliced in sequence; the plurality of section tracks which are spliced in sequence are a long section track group and a short section track group, the long section track group is a plurality of long section tracks which are spliced in sequence, the short section track group is a plurality of short section tracks which are spliced in sequence, and the last long section track in the long section track group is spliced with the first short section track in the short section track group; the length of the long section track is N times of that of the short section track, and N is a positive integer; the length of the short section track is consistent with the bottom width of the plate girder. The advantages are that: the girder is put in place by utilizing the spliced sectional track and the track trolley and the movable plate girder and utilizing the lifting device, so that the girder can be erected in a limited height space, mechanical operations such as a bridge girder erection machine and the like are avoided, and the construction cost is saved; the device can also work in dangerous areas such as high-voltage lines and the like where a crane and large equipment cannot work, and the safety risk is reduced.

Description

一种限高环境下轨道滑移安装板梁的施工装置及方法A construction device and method for track sliding installation of plate beams in a height-restricted environment

技术领域Technical field

本发明涉及一种限高环境下轨道滑移安装板梁的施工装置及方法,属于板梁安装施工技术领域。The invention relates to a construction device and method for track sliding installation of plate beams in a height-limited environment, and belongs to the technical field of plate beam installation and construction.

背景技术Background technique

在进行城市桥梁板梁安装施工时,有时会受到上方高压线、既有桥梁等高度限制,难以采用汽车吊起吊施工,选择架桥机或龙门吊等施工机械往往成本较大,施工难度较大。When installing and constructing urban bridge plate girders, sometimes due to height restrictions such as high-voltage lines above and existing bridges, it is difficult to use truck cranes for construction. Choosing construction machinery such as bridge erecting machines or gantry cranes is often more costly and difficult to construct.

发明内容Contents of the invention

本发明所要解决的技术问题是克服现有技术的缺陷,提供一种限高环境下轨道滑移安装板梁的施工装置及方法。The technical problem to be solved by the present invention is to overcome the defects of the existing technology and provide a construction device and method for track sliding installation of plate beams in a height-restricted environment.

为解决上述技术问题,本发明提供一种限高环境下轨道滑移安装板梁的施工装置,包括:轨道小车、若干个依次拼接的分节轨道和起重装置;In order to solve the above technical problems, the present invention provides a construction device for track sliding installation of plate beams in a height-restricted environment, including: a track trolley, several segmented tracks that are spliced in sequence, and a lifting device;

所述轨道小车放置在所述分节轨道上,并能够在分节轨道上移动;The track trolley is placed on the segmented track and can move on the segmented track;

所述轨道小车上放置板梁;Plate beams are placed on the rail trolley;

所述起重装置用于托起所述轨道小车上的板梁,且托起板梁后,板梁的高度低于限高环境的限制高度;The lifting device is used to lift the plate beam on the track trolley, and after lifting the plate beam, the height of the plate beam is lower than the height limit of the height-limited environment;

所述若干个依次拼接的分节轨道为长分节轨道组和短分节轨道组,所述长分节轨道组为若干个依次拼接的长分节轨道,所述短分节轨道组为若干个依次拼接的短分节轨道,长分节轨道组中最后一个长分节轨道与短分节轨道组第一个短分节轨道拼接;所述长分节轨道的长度是短分节轨道的长度的N倍,N为正整数;所述短分节轨道的长度与板梁底宽一致。The plurality of segmented rails spliced in sequence are a long segmented rail group and a short segmented rail group. The long segmented rail group is a plurality of long segmented rails spliced in sequence. The short segmented rail group is a plurality of long segmented rails spliced in sequence. short segmented tracks that are spliced in sequence, the last long segmented track in the long segmented track group is spliced with the first short segmented track in the short segmented track group; the length of the long segmented track is the length of the short segmented track N times the length, N is a positive integer; the length of the short segmented track is consistent with the bottom width of the plate girder.

进一步的,每个所述分节轨道之间通过钢轨连接夹板连接。Further, each of the segmented rails is connected through rail connecting splints.

进一步的,所述分节轨道的长度为分节轨道本身的长度和其两侧钢轨连接夹板的长度之和。Further, the length of the segmented track is the sum of the length of the segmented track itself and the length of the rail connecting splints on both sides.

进一步的,所述分节轨道下方设有用于垫平处理的木靴。Furthermore, wooden boots for leveling are provided under the segmented track.

进一步的,在将板梁起吊放置于轨道小车上时,在轨道小车前后轮处设置用于固定小车的第一木楔;在将板梁起吊放置于轨道小车上之后,在板梁和轨道小车之间设置用于固定板梁的第二木楔。Further, when the plate beam is lifted and placed on the track trolley, first wooden wedges for fixing the trolley are provided at the front and rear wheels of the track trolley; after the plate beam is lifted and placed on the track trolley, the plate beam and the track trolley are A second wooden wedge is placed between them for fixing the plate beams.

进一步的,在将板梁起吊放置于轨道小车上之后,所述板梁和轨道小车之间通过钢丝绳拉结固定。Further, after the plate beam is lifted and placed on the rail trolley, the plate beam and the rail trolley are fixed by a wire rope tie.

进一步的,所述起重装置采用千斤顶。Further, the lifting device adopts a jack.

一种限高环境下轨道滑移安装板梁的施工方法,包括:A construction method for track sliding installation of plate beams in a height-restricted environment, including:

沿盖梁方向依次铺设轨道,所述轨道包括若干个依次拼接的分节轨道;Tracks are laid sequentially along the direction of the cover beam, and the tracks include several segmented tracks that are spliced in sequence;

在盖梁受限空间外的轨道上安装轨道小车;Install the track trolley on the track outside the restricted space of the cover beam;

将板梁起吊放置于轨道小车上;Lift the plate beam and place it on the track trolley;

在轨道上移动轨道小车至盖梁受限空间内指定位置;Move the track trolley on the track to the designated position within the restricted space of the cover beam;

采用千斤顶将板梁从轨道小车上方托起,移开小车,并将该板梁下方的分节轨道拆除,解除千斤顶托起动作,将板梁放下至该指定位置,落梁就位;Use a jack to lift the plate beam from the top of the track trolley, remove the trolley, remove the segmented track below the plate beam, release the jack lifting action, lower the plate beam to the designated position, and drop the beam into place;

重复落梁就位直至盖梁受限空间内的所有板梁安装到位。Repeat the drop beam placement until all plate beams within the restricted space of the cover beam are in place.

进一步的,采用葫芦倒链将搭载板梁的轨道小车沿盖梁方向横向滑移至受限空间内指定位置。Further, the hoist inverted chain is used to slide the rail car carrying the plate beam laterally along the direction of the cover beam to a designated position in the restricted space.

进一步的,所述指定位置沿盖梁方向由远及近依次进行选取,每安装一片板梁,拆除对应的一节分节轨道。Further, the designated positions are selected from far to near along the direction of the cover beam, and each time a plate beam is installed, the corresponding segmented track is removed.

本发明所达到的有益效果:Beneficial effects achieved by the present invention:

本发明利用拼接的分节轨道和轨道小车,将板梁移动到位后,利用千斤顶落梁就位,能够在有限高度空间内架梁,避免架桥机等机械作业,节约施工成本;还能够在吊车、大型设备无法作业的高压线等危险区域工作,降低安全风险。The present invention uses spliced segmented rails and track trolleys to move the plate beams into place, and then uses jacks to lower the beams into place. This invention can erect beams in a limited height space, avoid mechanical operations such as bridge erecting machines, and save construction costs; it can also be used in Work in dangerous areas such as high-voltage lines where cranes and large equipment cannot operate to reduce safety risks.

附图说明Description of the drawings

图1是本发明的轨道滑移安装板梁整体结构示意图;Figure 1 is a schematic diagram of the overall structure of the track sliding installation plate beam of the present invention;

图2是本发明的轨道小车及板梁组合示意图;Figure 2 is a schematic diagram of the rail car and plate beam combination of the present invention;

图3是本发明的超薄液压千斤顶顶升板梁组合示意图;Figure 3 is a schematic diagram of the ultra-thin hydraulic jack lifting plate beam assembly of the present invention;

图4是本发明的超薄液压千斤顶示意图。Figure 4 is a schematic diagram of the ultra-thin hydraulic jack of the present invention.

图中的1、长分节轨道,2、短分节轨道,3、钢轨连接夹板,4、木靴,5、轨道小车,6、板梁,7、第一木楔,8、第二木楔,9、钢丝绳,10、钢板,11、千斤顶,12、支座,13、垫石,14、桥墩 ,15、分节轨道15。In the picture, 1. Long segmented track, 2. Short segmented track, 3. Rail connecting plywood, 4. Wooden boots, 5. Track trolley, 6. Plate beam, 7. First wooden wedge, 8. Second wooden wedge , 9. Wire rope, 10. Steel plate, 11. Jack, 12. Bearing, 13. Padstone, 14. Bridge pier, 15. Segmented track 15.

实施方式Implementation

下面结合附图对本发明作进一步描述。以下实施例仅用于更加清楚地说明本发明的技术方案,而不能以此来限制本发明的保护范围。The present invention will be further described below in conjunction with the accompanying drawings. The following examples are only used to more clearly illustrate the technical solutions of the present invention, but cannot be used to limit the scope of the present invention.

实施例1,如图1和2所示,本发明公开了一种限高环境下轨道滑移安装板梁的施工装置,包括:轨道小车5、若干个依次拼接的分节轨道15和千斤顶;Embodiment 1, as shown in Figures 1 and 2, the present invention discloses a construction device for track sliding installation of plate beams in a height-restricted environment, including: a track trolley 5, several segmented tracks 15 that are spliced in sequence, and a jack;

所述轨道小车5放置在所述分节轨道上,并能够在分节轨道上移动;The track trolley 5 is placed on the segmented track and can move on the segmented track;

所述轨道小车5上放置板梁6;Plate beams 6 are placed on the rail car 5;

所述千斤顶用于托起所述轨道小车5上的板梁6,且托起板梁6后,板梁6的高度低于限高环境的限制高度;The jack is used to lift the plate beam 6 on the rail car 5, and after lifting the plate beam 6, the height of the plate beam 6 is lower than the height limit of the height-limited environment;

所述若干个依次拼接的分节轨道为长分节轨道组和短分节轨道组,所述长分节轨道组为若干个依次拼接的长分节轨道1,所述短分节轨道组为若干个依次拼接的短分节轨道2,长分节轨道组中最后一个长分节轨道1与短分节轨道组第一个短分节轨道2拼接;所述长分节轨道1的长度是短分节轨道2的长度的N倍,N为正整数;所述短分节轨道2的长度与板梁6底宽一致。The plurality of segmented rails spliced in sequence are a long segmented rail group and a short segmented rail group. The long segmented rail group is a plurality of long segmented rails 1 spliced in sequence. The short segmented rail group is Several short segmented rails 2 are spliced in sequence, and the last long segmented rail 1 in the long segmented rail group is spliced with the first short segmented rail 2 of the short segmented rail group; the length of the long segmented track 1 is N times the length of the short segmented track 2, N is a positive integer; the length of the short segmented track 2 is consistent with the bottom width of the plate beam 6.

每个所述分节轨道之间通过钢轨连接夹板3连接。Each of the segmented rails is connected by a rail connecting splint 3 .

所述分节轨道的长度为分节轨道本身的长度和其两侧钢轨连接夹板3的长度之和。The length of the segmented track is the sum of the length of the segmented track itself and the length of the rail connecting splints 3 on both sides.

分节轨道下方设有用于垫平处理的木靴4。Wooden boots 4 for leveling are provided below the segmented track.

在将板梁6起吊放置于轨道小车5上时,在轨道小车5前后轮处设置用于固定小车的第一木楔7。When the plate beam 6 is hoisted and placed on the track trolley 5, first wooden wedges 7 for fixing the trolley are provided at the front and rear wheels of the track trolley 5.

在将板梁6起吊放置于轨道小车5上之后,在板梁6和轨道小车5之间设置用于固定板梁6的第二木楔8。After the plate beam 6 is lifted and placed on the rail car 5 , a second wooden wedge 8 for fixing the plate beam 6 is provided between the plate beam 6 and the rail car 5 .

在将板梁6起吊放置于轨道小车5上之后,所述板梁6和轨道小车5之间通过钢丝绳9拉结固定。After the plate beam 6 is hoisted and placed on the rail car 5 , the plate beam 6 and the rail car 5 are tied and fixed by a wire rope 9 .

实施例2,本发明提供一种限高环境下轨道滑移安装板梁的施工方法,包括:Embodiment 2, the present invention provides a construction method for track sliding installation of plate beams in a height-restricted environment, including:

1、沿盖梁方向分别铺设分节轨道,每节轨道通过钢轨连接夹板3连接,轨道放置在同跨盖梁垫石13上面,采用木靴4垫平,垫石13位于桥墩上。1. Lay segmented tracks separately along the direction of the cap beam. Each track is connected by a rail connecting splint 3. The track is placed on the padding stone 13 of the same span cap beam and is leveled with wooden boots 4. The padding stone 13 is located on the pier.

2、在盖梁受限空间外的轨道对应位置处安装轨道小车5,轨道小车5前后轮处用第一木楔7固定。2. Install the track trolley 5 at the corresponding position of the track outside the restricted space of the cover beam. The front and rear wheels of the track trolley 5 are fixed with the first wooden wedge 7.

3、安装好轨道小车5后,板梁6从现浇梁投影面外侧起吊两端放置于轨道小车5上面,采用2只葫芦倒链将板梁6沿盖梁方向横向滑移。板梁6放置在轨道小车5后,采用钢丝绳9拉结固定,轨道小车两端设有用于隔挡的钢板10,在板梁6和钢板10之间通过第二木楔8进一步对板梁6进行固定,以保证移动过程中板梁6不偏移。3. After the track trolley 5 is installed, the plate beam 6 is lifted from the outside of the cast-in-place beam projection surface and both ends are placed on the track trolley 5. Two hoist inverted chains are used to slide the plate beam 6 laterally along the cover beam direction. The plate beam 6 is placed behind the track car 5 and fixed with a steel wire rope 9. Steel plates 10 are provided at both ends of the track car for blocking. A second wooden wedge 8 is used between the plate beam 6 and the steel plate 10 to further support the plate beam 6. Fix it to ensure that the plate beam 6 does not shift during movement.

4、滑移到位后,解除固定后,采用千斤顶11将板梁6从轨道小车上方托起,移走轨道小车5,拆除板梁6下方的分节轨道,落梁就位,本实施例中如图3和图4所示,千斤顶11采用超薄液压千斤顶,其下端放置在桥墩上,上端用于顶起板梁6。4. After the slide is in place and the fixation is released, use the jack 11 to lift the plate beam 6 from above the track trolley, remove the track trolley 5, remove the segmented track below the plate beam 6, and put the falling beam in place. In this embodiment As shown in Figures 3 and 4, the jack 11 is an ultra-thin hydraulic jack, the lower end of which is placed on the bridge pier, and the upper end is used to lift the plate beam 6.

5、本实施例中轨道采用3根1米的短分节轨道2和2根3米的长分节轨道1组装完成,3根1米的的短分节轨道2放置于盖梁受限空间内最远段,最远端每架设完成一片板梁6后拆除一节对应的1米的短分节轨道2,架设3片板梁6后拆除完3节1米的短分节轨道2。架设第四片时,拆除一根3米的长分节轨道1,安装3根1米的短分节轨道2,重复上一次操作工序,每安装一片拆除一节短分节轨道2。架设第七片梁时,拆除第二根3米的长分节轨道1,重复上一次操作工序,每安装一片拆除一节短分节轨道2,直至盖梁受限空间内的板梁6全部安装完成;通过短分节轨道2和长分节轨道1的组合搭配,能够在有限的分节轨道个数下,快速精确的进行板梁6的安装。5. In this embodiment, the track is assembled using three 1-meter short segmented rails 2 and two 3-meter long segmented rails 1. The three 1-meter short segmented rails 2 are placed in the restricted space of the cover beam. In the farthest section, after each plate beam 6 is erected at the farthest end, a corresponding 1-meter short segmented track 2 is dismantled. After three plate beams 6 are erected, three 1-meter short segmented track 2 is dismantled. When erecting the fourth piece, remove one 3-meter long segmented track 1 and install three 1-meter short segmented tracks 2. Repeat the previous operation and remove one short segmented track 2 for each piece installed. When erecting the seventh beam, dismantle the second 3-meter long segmented track 1 and repeat the previous operation. Remove one short segmented track 2 for each piece installed until all plate beams 6 in the restricted space of the cover beam are covered. The installation is completed; through the combination of the short segmented track 2 and the long segmented track 1, the plate beam 6 can be installed quickly and accurately with a limited number of segmented tracks.

以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明技术原理的前提下,还可以做出若干改进和变形,这些改进和变形也应视为本发明的保护范围。The above are only preferred embodiments of the present invention. It should be noted that those of ordinary skill in the art can also make several improvements and modifications without departing from the technical principles of the present invention. These improvements and modifications It should also be regarded as the protection scope of the present invention.

Claims (10)

1.一种限高环境下轨道滑移安装板梁的施工装置,其特征在于,包括:轨道小车、若干个依次拼接的分节轨道和起重装置;1. A construction device for track sliding installation of plate beams in a height-restricted environment, which is characterized in that it includes: a track trolley, several segmented tracks that are spliced in sequence, and a lifting device; 所述轨道小车放置在所述分节轨道上,并能够在分节轨道上移动;The track trolley is placed on the segmented track and can move on the segmented track; 所述轨道小车上放置板梁;Plate beams are placed on the rail trolley; 所述起重装置用于托起所述轨道小车上的板梁,且托起板梁后,板梁的高度低于限高环境的限制高度;The lifting device is used to lift the plate beam on the track trolley, and after lifting the plate beam, the height of the plate beam is lower than the height limit of the height-limited environment; 所述若干个依次拼接的分节轨道为长分节轨道组和短分节轨道组,所述长分节轨道组为若干个依次拼接的长分节轨道,所述短分节轨道组为若干个依次拼接的短分节轨道,长分节轨道组中最后一个长分节轨道与短分节轨道组第一个短分节轨道拼接;所述长分节轨道的长度是短分节轨道的长度的N倍,N为正整数;所述短分节轨道的长度与板梁底宽一致。The plurality of segmented rails spliced in sequence are a long segmented rail group and a short segmented rail group. The long segmented rail group is a plurality of long segmented rails spliced in sequence. The short segmented rail group is a plurality of long segmented rails spliced in sequence. short segmented tracks that are spliced in sequence, the last long segmented track in the long segmented track group is spliced with the first short segmented track in the short segmented track group; the length of the long segmented track is the length of the short segmented track N times the length, N is a positive integer; the length of the short segmented track is consistent with the bottom width of the plate girder. 2.根据权利要求1所述的限高环境下轨道滑移安装板梁的施工装置,其特征在于,每个所述分节轨道之间通过钢轨连接夹板连接。2. The construction device for track sliding installation of plate beams in a height-restricted environment according to claim 1, characterized in that each of the segmented tracks is connected by a rail connecting splint. 3.根据权利要求2所述的限高环境下轨道滑移安装板梁的施工装置,其特征在于,所述分节轨道的长度为分节轨道本身的长度和其两侧钢轨连接夹板的长度之和。3. The construction device for track sliding installation of plate beams in a height-limited environment according to claim 2, characterized in that the length of the segmented track is the length of the segmented track itself and the length of the rail connecting splints on both sides of the track. Sum. 4.根据权利要求1所述的限高环境下轨道滑移安装板梁的施工装置,其特征在于,所述分节轨道下方设有用于垫平处理的木靴。4. The construction device for track sliding installation of plate beams in a height-restricted environment according to claim 1, characterized in that wooden boots for flattening are provided below the segmented track. 5.根据权利要求1所述的限高环境下轨道滑移安装板梁的施工装置,其特征在于,5. The construction device for track sliding installation of plate beams in a height-restricted environment according to claim 1, characterized in that: 在将板梁起吊放置于轨道小车上时,在轨道小车前后轮处设置用于固定小车的第一木楔;When lifting the plate beam and placing it on the track trolley, first wooden wedges for fixing the trolley are provided at the front and rear wheels of the track trolley; 在将板梁起吊放置于轨道小车上之后,在板梁和轨道小车之间设置用于固定板梁的第二木楔。After the plate beam is lifted and placed on the rail trolley, a second wooden wedge for fixing the plate beam is set between the plate beam and the rail trolley. 6.根据权利要求1所述的限高环境下轨道滑移安装板梁的施工装置,其特征在于,在将板梁起吊放置于轨道小车上之后,所述板梁和轨道小车之间通过钢丝绳拉结固定。6. The construction device for track sliding installation of plate beams in a height-restricted environment according to claim 1, characterized in that after the plate beams are hoisted and placed on the track trolley, a steel wire rope is passed between the plate beam and the track trolley. Fastened with tie. 7.根据权利要求1所述的限高环境下轨道滑移安装板梁的施工装置,其特征在于,所述起重装置采用千斤顶。7. The construction device for track sliding installation of plate beams in a height-restricted environment according to claim 1, characterized in that the lifting device adopts a jack. 8.一种限高环境下轨道滑移安装板梁的施工方法,其特征在于,包括:8. A construction method for track sliding installation of plate beams in a height-restricted environment, which is characterized by including: 沿盖梁方向依次铺设轨道,所述轨道包括若干个依次拼接的分节轨道;Tracks are laid sequentially along the direction of the cover beam, and the tracks include several segmented tracks that are spliced in sequence; 在盖梁受限空间外的轨道上安装轨道小车;Install the track trolley on the track outside the restricted space of the cover beam; 将板梁起吊放置于轨道小车上;Lift the plate beam and place it on the track trolley; 在轨道上移动轨道小车至盖梁受限空间内指定位置;Move the track trolley on the track to the designated position within the restricted space of the cover beam; 采用千斤顶将板梁从轨道小车上方托起,移开小车,并将该板梁下方的分节轨道拆除,解除千斤顶托起动作,将板梁放下至该指定位置,落梁就位;Use a jack to lift the plate beam from the top of the track trolley, remove the trolley, remove the segmented track below the plate beam, release the jack lifting action, lower the plate beam to the designated position, and drop the beam into place; 重复落梁就位直至盖梁受限空间内的所有板梁安装到位。Repeat the drop beam placement until all plate beams within the restricted space of the cover beam are in place. 9.根据权利要求8所述的限高环境下轨道滑移安装板梁的施工方法,其特征在于,采用葫芦倒链将搭载板梁的轨道小车沿盖梁方向横向滑移至受限空间内指定位置。9. The construction method for track sliding installation of plate beams in a height-restricted environment according to claim 8, characterized in that a hoist inverted chain is used to slide the track trolley carrying the plate beam laterally into the restricted space along the direction of the cover beam. Specify location. 10.根据权利要求8所述的限高环境下轨道滑移安装板梁的施工方法,其特征在于,所述指定位置沿盖梁方向由远及近依次进行选取,每安装一片板梁,拆除对应的一节分节轨道。10. The construction method for track sliding installation of plate beams in a height-restricted environment according to claim 8, characterized in that the designated positions are selected from far to near in the direction of the cover beam, and each plate beam is installed and removed. The corresponding segmented track.
CN202310947734.XA 2023-07-31 2023-07-31 Construction device and method for installing plate girder in sliding manner on track under height limiting environment Pending CN117144801A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310947734.XA CN117144801A (en) 2023-07-31 2023-07-31 Construction device and method for installing plate girder in sliding manner on track under height limiting environment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310947734.XA CN117144801A (en) 2023-07-31 2023-07-31 Construction device and method for installing plate girder in sliding manner on track under height limiting environment

Publications (1)

Publication Number Publication Date
CN117144801A true CN117144801A (en) 2023-12-01

Family

ID=88899610

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310947734.XA Pending CN117144801A (en) 2023-07-31 2023-07-31 Construction device and method for installing plate girder in sliding manner on track under height limiting environment

Country Status (1)

Country Link
CN (1) CN117144801A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118563650A (en) * 2024-04-19 2024-08-30 中铁广州工程局集团有限公司 A method for closure construction of large-span cap beam with few supports under an existing bridge

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108517785A (en) * 2018-05-11 2018-09-11 中国二十二冶集团有限公司 Bridge precast beam plate translational installation method
CN111691304A (en) * 2020-06-09 2020-09-22 中交第二航务工程局有限公司 Method and device for mounting prefabricated bridge deck between sections of steel-concrete composite beam
CN212153123U (en) * 2020-03-23 2020-12-15 中交四公局第三工程有限公司 Sideslip device is used in construction of T roof beam
CN216892056U (en) * 2022-02-21 2022-07-05 中铁二十四局集团有限公司 Precast beam sideslip device
CN220550458U (en) * 2023-07-31 2024-03-01 中铁十二局集团城市发展建设有限公司 Construction device for sliding and installing plate girder on rail in height-limiting environment

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108517785A (en) * 2018-05-11 2018-09-11 中国二十二冶集团有限公司 Bridge precast beam plate translational installation method
CN212153123U (en) * 2020-03-23 2020-12-15 中交四公局第三工程有限公司 Sideslip device is used in construction of T roof beam
CN111691304A (en) * 2020-06-09 2020-09-22 中交第二航务工程局有限公司 Method and device for mounting prefabricated bridge deck between sections of steel-concrete composite beam
CN216892056U (en) * 2022-02-21 2022-07-05 中铁二十四局集团有限公司 Precast beam sideslip device
CN220550458U (en) * 2023-07-31 2024-03-01 中铁十二局集团城市发展建设有限公司 Construction device for sliding and installing plate girder on rail in height-limiting environment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118563650A (en) * 2024-04-19 2024-08-30 中铁广州工程局集团有限公司 A method for closure construction of large-span cap beam with few supports under an existing bridge

Similar Documents

Publication Publication Date Title
US11634877B2 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
CN108374296A (en) The construction method of straddle type monorail rail tracks installation
KR101287455B1 (en) System and method for launching upper structure of bridege
CN111778857B (en) Process for synchronously erecting upper and lower beams of double-layer overhead bridge of urban public rail
CN105019357B (en) Installation method of special-shaped prefabricated bridge deck on open lattice steel girder of arch bridge
CN100441779C (en) Bridge construction method with prefabricated translation in place in the air
CN103821087A (en) Precast bridge deck space steel pipe concrete truss composite beam and construction method
WO2024148715A1 (en) Method for erecting continuous steel truss bridge
CN108589568A (en) A rapid construction method of T-beams in shed openings spanning business lines in narrow spaces
CN110820602A (en) A single-segment box girder bridge erecting machine and its operation method
CN111335185A (en) Large-tonnage box girder erection construction system for realizing height control and erection method thereof
CN110468743B (en) A mobile hanger and construction method for the renovation of old bridge pier caps
KR100627102B1 (en) Precast Segment Bridge Construction Method Using Lifting Traveler
CN114086485B (en) Construction method for replacing large-span high-speed rail continuous beam support
CN101122115A (en) A construction method for tower crane displacement
CN108423565A (en) The erection of U-shaped twin beams gantry crane with hook and Demolition Construction method
CN208009277U (en) A kind of short sliding installation system of land-based area large-tonnage steel box beam
CN117144801A (en) Construction device and method for installing plate girder in sliding manner on track under height limiting environment
CN105484166A (en) Ladder-shaped mast type cantilever assembling crane
CN115897387B (en) A method for erecting curved bridges
CN204919341U (en) Installing the system of prefabricated decking of dysmorphism on uncovered lattice formula girder steel of arched bridge
CN112211112A (en) Steel box girder installation method adopting double-guide-girder erection machine on existing bridge
CN115961549A (en) Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge
CN115323931A (en) A construction method and system for a progressive and retrograde assembled steel box tied arch bridge
CN111139742B (en) Method for mounting and dismounting highway bridge girder erection machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination