CN117027495A - Construction method for dismantling steel-concrete combined inner support of deep foundation pit - Google Patents

Construction method for dismantling steel-concrete combined inner support of deep foundation pit Download PDF

Info

Publication number
CN117027495A
CN117027495A CN202311192753.2A CN202311192753A CN117027495A CN 117027495 A CN117027495 A CN 117027495A CN 202311192753 A CN202311192753 A CN 202311192753A CN 117027495 A CN117027495 A CN 117027495A
Authority
CN
China
Prior art keywords
support
steel
foundation pit
dismantling
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311192753.2A
Other languages
Chinese (zh)
Inventor
何均
王涛
宋震
罗书剑
王颖智
柴小明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Zhejiang Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Zhejiang Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202311192753.2A priority Critical patent/CN117027495A/en
Publication of CN117027495A publication Critical patent/CN117027495A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/08Wrecking of buildings
    • E04G23/082Wrecking of buildings using shears, breakers, jaws and the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • E02D5/765Anchorings for bulkheads or sections thereof in as much as specially adapted therefor removable
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Electrochemistry (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Chemical & Material Sciences (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明公开了一种深基坑钢‑混组合内支撑拆除施工方法,包括以下步骤:在基坑内钢筋混凝土支撑下放置临时支撑,采用静力切割方式拆除钢筋混凝土支撑并吊装至临时堆放位置;逐级卸载型钢支撑的预加轴力,并采用气割方式将型钢支撑从竖向围护结构上割除,并吊装至临时堆放位置;采用以静力切割拆除为主、机械破拆为辅的拆除方法按照自上而下的顺序逐层拆除中隔墙结构。本发明优化了深基坑钢‑混组合内支撑拆除工艺,采用静力切割对凝土支撑、冠梁分坑地连墙及中隔壁墙拆除,降低了振动对周边环境的影响,保证了施工安全,具有较高的推广价值。

The invention discloses a construction method for dismantling the inner support of a deep foundation pit steel-concrete combination, which includes the following steps: placing a temporary support under the reinforced concrete support in the foundation pit, using static cutting to remove the reinforced concrete support and hoisting it to a temporary stacking position; Unload the pre-loaded axial force of the steel supports step by step, and use gas cutting to cut off the steel supports from the vertical enclosure structure and hoist them to the temporary stacking position; use static cutting and demolition as the main method, supplemented by mechanical demolition. Method: Dismantle the middle partition wall structure layer by layer in a top-down order. This invention optimizes the removal process of steel-concrete composite internal supports in deep foundation pits, and uses static cutting to remove concrete supports, crown beams, pit connecting walls, and middle partition walls, thereby reducing the impact of vibration on the surrounding environment and ensuring construction It is safe and has high promotion value.

Description

深基坑钢-混组合内支撑拆除施工方法Construction method for dismantling steel-concrete composite internal supports in deep foundation pits

技术领域Technical field

本发明涉及基坑拆除施工技术领域,尤其涉及一种深基坑钢-混组合内支撑拆除施工方法。The invention relates to the technical field of foundation pit dismantling construction, and in particular to a construction method for dismantling steel-concrete composite internal supports in deep foundation pits.

背景技术Background technique

随着城市地下空间的开展和利用,地下人防工程、地下车库、城市基础设施的建设越来越多,地下工程基坑施工过程中需要对周围房屋建筑和市政设施进行保护,以保证建筑和市政设施的正常和安全使用,为此,需要采用妥善有效的支护措施。因钢-混组合内支撑刚度大、变形小、施工方便,是沿海软土地区的地下工程的深基坑支护常用的支护结构形式。深基坑钢筋混凝土内支撑是地下工程主体结构施工的临时施工措施,需随着地下工程主体结构的施工及时拆除,进行必要的“换撑”,以保证地下工程主体结构顺利施工。工程表明,多数深基坑支护结构的最大变形值并不在其开挖阶段,而是在支撑拆除阶段。以往研究只考虑了基坑开挖阶段产生的变形,忽略了支撑拆除对基坑变形的影响,进而导致工程施工存在较大的安全隐患。With the development and utilization of urban underground space, more and more underground civil air defense projects, underground garages, and urban infrastructure are being constructed. During the construction of underground engineering foundation pits, surrounding buildings and municipal facilities need to be protected to ensure that construction and municipal facilities are protected. For the normal and safe use of facilities, proper and effective support measures are required. Because the steel-concrete composite internal support has high stiffness, small deformation, and convenient construction, it is a commonly used support structure form for deep foundation pit support of underground projects in coastal soft soil areas. The reinforced concrete internal support in deep foundation pits is a temporary construction measure for the construction of the main structure of the underground project. It needs to be dismantled in time with the construction of the main structure of the underground project, and necessary "bracing replacement" is carried out to ensure the smooth construction of the main structure of the underground project. Engineering shows that the maximum deformation value of most deep foundation pit supporting structures is not during the excavation stage, but during the support removal stage. Previous studies only considered the deformation produced during the excavation stage of the foundation pit and ignored the impact of support removal on the deformation of the foundation pit, which in turn led to greater safety hazards in engineering construction.

目前,常用的基坑支撑拆除技术主要有爆破拆除和液压锤拆除2种方式,其中,爆破拆除具有飞石、冲击波和振动等危害,易对工程主体以及周边环境产生较大影响,需搭设安全防护架,人力物力成本高,同时,该技术专业性高,需经过相关部门审批,审批程序繁琐。液压锤拆除技术工期长,施工过程中易产生持续噪音,对周边居民区影响大,同时机械功率大,振动强烈,机械破碎块度较大,会影响到楼板上预留钢筋。At present, the commonly used foundation pit support removal technologies mainly include blasting and hydraulic hammer removal. Among them, blasting and demolition have hazards such as flying rocks, shock waves and vibrations, and can easily have a greater impact on the main body of the project and the surrounding environment. Therefore, safety measures are required. Protective racks require high manpower and material costs. At the same time, this technology is highly professional and requires approval from relevant departments, and the approval procedures are cumbersome. Hydraulic hammer demolition technology has a long construction period and is prone to continuous noise during the construction process, which has a great impact on surrounding residential areas. At the same time, the mechanical power is large, the vibration is strong, and the mechanical crushing is large, which will affect the reserved steel bars on the floor.

发明内容Contents of the invention

为克服现有技术中存在的缺陷,本发明提供了一种深基坑钢-混组合内支撑高效拆除施工方法,提高了支撑拆除的安全性,同时避免对周边建筑设施的不利影响。In order to overcome the defects existing in the prior art, the present invention provides an efficient construction method for dismantling steel-concrete composite internal supports in deep foundation pits, which improves the safety of support dismantling and avoids adverse effects on surrounding building facilities.

为了实现上述目的,本发明提供了一种深基坑钢-混组合内支撑拆除施工方法,用于拆除深基坑钢-混组合内支撑体系,所述内支撑体系包括水平支撑于所述深基坑内水平支撑结构以及竖向支撑于所述深基坑内的中隔墙结构,所述水平支撑结构包括与所述深基坑的围护结构连接的钢筋混凝土支撑以及固定连接于所述钢筋混凝土支撑的型钢支撑,拆除施工方法包括如下施工步骤:In order to achieve the above object, the present invention provides a construction method for dismantling the steel-concrete composite internal support of a deep foundation pit, which is used to dismantle the steel-concrete composite internal support system of a deep foundation pit. The internal support system includes a horizontal support on the deep foundation pit. A horizontal support structure in the foundation pit and a middle partition wall structure vertically supported in the deep foundation pit. The horizontal support structure includes a reinforced concrete support connected to the enclosure structure of the deep foundation pit and a reinforced concrete support fixedly connected to the reinforced concrete The supporting steel support, the dismantling construction method includes the following construction steps:

在基坑内钢筋混凝土支撑下放置临时支撑,采用静力切割方式拆除钢筋混凝土支撑并吊装至临时堆放位置;Place temporary supports under the reinforced concrete supports in the foundation pit, use static cutting to remove the reinforced concrete supports and hoist them to the temporary stacking position;

逐级卸载型钢支撑的预加轴力,将型钢支撑从竖向围护结构上割除,并吊装至临时堆放位置;Unload the pre-loaded axial force of the steel support step by step, cut the steel support from the vertical enclosure structure, and hoist it to the temporary stacking position;

采用以静力切割拆除为主、机械破拆为辅的拆除方法按照自上而下的顺序逐层拆除中隔墙结构。The middle partition wall structure will be dismantled layer by layer in a top-down order using a demolition method that mainly involves static cutting and demolition, supplemented by mechanical demolition.

较佳地,所述钢筋混凝土支撑在拆除时利用气割枪切断钢筋混凝土支撑两侧的钢筋。Preferably, when the reinforced concrete support is dismantled, a gas cutting gun is used to cut off the steel bars on both sides of the reinforced concrete support.

较佳地,所述钢筋混凝土支撑在拆除前在所述钢筋混凝土支撑的上部拉设钢丝绳,并拆除上部钢管防护,放切割线。Preferably, before the reinforced concrete support is dismantled, a steel wire rope is stretched on the upper part of the reinforced concrete support, the upper steel pipe protection is removed, and the cutting line is placed.

较佳地,所述临时支撑为马凳支撑托架,每段所述钢筋混凝土支撑的下方设有两个所述马凳支撑托架,且所述马凳支撑托架与所述钢筋混凝土支撑之间预留有空隙,所述空隙内设有填充物。Preferably, the temporary support is a horse stool support bracket, and two horse stool support brackets are provided below each section of the reinforced concrete support, and the horse stool support bracket is in contact with the reinforced concrete support. A gap is reserved between them, and a filler is provided in the gap.

较佳地,所述型钢支撑在拆除时采用气割方式割除所述型钢支撑与所述竖向围护结构连接的支架以及传力件。Preferably, when the steel support is dismantled, gas cutting is used to cut off the brackets and force transmission parts connecting the steel support and the vertical enclosure structure.

较佳地,所述中隔墙结构在拆除时,包括以下步骤:Preferably, when the middle partition wall structure is dismantled, the following steps are included:

在中隔墙结构的两侧至主体结构框架柱之间设置换撑立柱;Set bracing columns between both sides of the central partition wall structure and the frame columns of the main structure;

拆除中隔墙结构至两侧主体结构框架柱范围内的竖向支撑排架;采用跳仓法按照先两侧向中间,再中间向两侧的顺序将中隔墙结构与两侧的主体结构楼板进行割除;Remove the vertical support racks within the range from the middle partition wall structure to the frame columns of the main structure on both sides; use the jump method to connect the middle partition wall structure with the main structure on both sides in the order of first two sides to the middle, and then the middle to both sides. Floor slabs are cut;

逐次分段施工连接楼板以连接中隔墙结构两侧的主体结构楼板,并追层拆除换撑立柱。The connecting floors are constructed in sections to connect the main structural floors on both sides of the middle partition wall structure, and the supporting columns are removed and replaced at each floor.

由于采用上述技术方案,使得本发明具有以下有益效果:Due to the adoption of the above technical solutions, the present invention has the following beneficial effects:

1)通过将多种单一内支撑拆除方法进行组合配套,弥补了传统单一基坑内支撑拆除存在的不足,可适用于更为广泛的基坑工程,与传统施工方法相比较,施工过程中所产生的建筑垃圾与噪声较少,型钢支撑拆除后可回收利用,避免资源浪费,满足国家所倡导的绿色施工理念,具有安全、经济和快捷等优点。1) By combining a variety of single internal support removal methods, the shortcomings of traditional single internal support removal in foundation pits are made up, and can be applied to a wider range of foundation pit projects. Compared with traditional construction methods, the There is less construction waste and noise, and the steel supports can be recycled after being dismantled to avoid waste of resources, meet the green construction concept advocated by the country, and have the advantages of safety, economy and speed.

2)对深基坑钢-混组合内支撑进行局部、分次、分段拆除,对混凝土支撑、冠梁、分坑地连墙及中隔壁墙采用静力切割方法进行拆除,并采用钻石链条锯搭配钻孔机切割混凝土,且用气割枪将支撑的两侧钢筋割断,避免振动对周边建筑设施的不利影响。2) Carry out local, graded and segmented demolition of the internal supports of the deep foundation pit steel-concrete combination, and use static cutting methods to remove the concrete supports, crown beams, sub-pit ground connecting walls and middle partition walls, and use diamond chains The saw is used with a drilling machine to cut concrete, and a gas cutting gun is used to cut the steel bars on both sides of the support to avoid adverse effects of vibration on surrounding construction facilities.

3)在拆除型钢支撑时,采用逐级卸载的方式卸载预加轴力,有效避免瞬间预加应力释放过大而导致的结构局部变形开裂。3) When dismantling the steel support, use a step-by-step unloading method to unload the pre-loaded axial force, which can effectively avoid local deformation and cracking of the structure caused by excessive instantaneous pre-loaded stress release.

4)采用手动葫芦吊住托座后再取出高强螺栓,并利用葫芦放至楼板面、运至临时堆放区域,自动化程度高,有利于缩短工期。4) Use a manual hoist to lift the bracket, then take out the high-strength bolts, and use the hoist to place them on the floor and transport them to the temporary storage area. This has a high degree of automation and is conducive to shortening the construction period.

5)采用气割方式进行割除与竖向围护结构焊接连接的支架、传力件,使型钢可回收利用,具有较高经济效益。5) Use gas cutting to cut off the brackets and force transmission parts welded to the vertical enclosure structure, so that the steel can be recycled and have high economic benefits.

6)与传统施工方法相比较,施工过程中所产生的建筑垃圾与噪声较少,型钢支撑拆除后可回收利用,避免资源浪费,满足国家所倡导的绿色施工理念,具有良好的经济效益和社会效益6) Compared with traditional construction methods, less construction waste and noise are generated during the construction process. The steel supports can be recycled after being dismantled, avoiding waste of resources, meeting the green construction concept advocated by the country, and having good economic and social benefits. benefit

附图说明Description of the drawings

为了更清楚地说明本发明实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings needed to be used in the description of the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present invention. For those of ordinary skill in the art, other drawings can also be obtained based on these drawings without exerting creative efforts.

图1为本发明深基坑钢-混组合内支撑拆除施工方法的工艺流程图。Figure 1 is a process flow chart of the construction method for dismantling the inner support of the deep foundation pit steel-concrete combination according to the present invention.

图2为本发明中基坑型钢组合支撑拆除顺序的平面布置图。Figure 2 is a plan layout diagram of the dismantling sequence of the foundation pit steel combined support in the present invention.

图3为本发明的一种较佳实施例中钢筋混凝土支撑与型钢支撑的连接关系示意图。Figure 3 is a schematic diagram of the connection relationship between the reinforced concrete support and the steel support in a preferred embodiment of the present invention.

图4为本发明中底板后浇带传力件剖面图。Figure 4 is a cross-sectional view of the force-transmitting component of the back-cast belt of the mid-sole plate of the present invention.

附图中标号对应关系如下:The corresponding relationship between the numbers in the attached drawing is as follows:

1C1、1C2、1C3、1C4、1C5、1C6-一层基坑角撑;1C7、1C8、1C9-一层基坑对撑;2C1、2C2、2C3、2C4、2C5、2C6-二层基坑角撑;2C7、2C8、2C9-二层基坑对撑;3-拆除顺序;4-底板;5-封头板;6-止水钢板;7-工字钢;8-钢筋混凝土支撑;91-第一道型钢支撑;92-第二道型钢支撑;101-第一围檩;102-第二围檩;11-栈桥梁;12-栈桥板;13-压顶梁;14-格构柱。1C1, 1C2, 1C3, 1C4, 1C5, 1C6 - first-floor foundation pit corner braces; 1C7, 1C8, 1C9 - first-floor foundation pit corner braces; 2C1, 2C2, 2C3, 2C4, 2C5, 2C6 - second-floor foundation pit corner braces ; 2C7, 2C8, 2C9-Second-story foundation pit supporting; 3-Demolition sequence; 4-Bottom plate; 5-Head plate; 6-Waterproof steel plate; 7-I-beam; 8-Reinforced concrete support; 91-No. One section steel support; 92 - the second section steel support; 101 - the first purlin; 102 - the second purlin; 11 - trestle bridge; 12 - trestle board; 13 - top beam; 14 - lattice column.

具体实施方式Detailed ways

下面结合附图对本发明的具体实施方式作进一步说明。在此需要说明的是,对于这些实施方式的说明用于帮助理解本发明,但并不构成对本发明的限定。此外,下面所描述的本发明各个实施方式中所涉及的技术特征只要彼此之间未构成冲突就可以相互组合。The specific embodiments of the present invention will be further described below with reference to the accompanying drawings. It should be noted here that the description of these embodiments is used to help understand the present invention, but does not constitute a limitation of the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

本发明所要解决的技术问题是针对目前常用的基坑支撑拆除技术主要由爆破拆除和液压锤拆除两种方式其中,爆破拆除具有飞石、冲击波和振动等危害,易对工程主体以及周边环境产生较大影响,并且需搭设安全防护架,人力物力成本高,该技术专业性高,需经过相关部门审批,审批程序繁琐。液压锤拆除技术工期长,施工过程中易产生持续噪音,对周边居民区影响大。同时,机械功率大,振动强烈,机械破碎块度较大,会影响到楼板上预留钢筋,因此提供一种深基坑钢-混组合内支撑拆除施工方法,降低了施工成本,避免了拆撑导致围护结构变形过大,保证了施工安全,同时采用静力切割对凝土支撑、冠梁分坑地连墙及中隔壁墙拆除,降低了振动对周边环境的影响。The technical problem to be solved by this invention is that the currently commonly used foundation pit support removal technology mainly consists of two methods: blasting demolition and hydraulic hammer demolition. Blasting demolition has hazards such as flying rocks, shock waves and vibrations, and is easy to cause damage to the project body and the surrounding environment. It has a large impact and requires the erection of safety protection frames. The cost of manpower and material resources is high. The technology is highly professional and needs to be approved by relevant departments, and the approval procedures are cumbersome. Hydraulic hammer demolition technology has a long construction period and is prone to continuous noise during the construction process, which has a great impact on surrounding residential areas. At the same time, the mechanical power is large, the vibration is strong, and the mechanical broken pieces are large, which will affect the reserved steel bars on the floor. Therefore, a construction method for the removal of steel-concrete composite internal supports in deep foundation pits is provided, which reduces the construction cost and avoids the need for demolition. The bracing caused excessive deformation of the enclosure structure, ensuring construction safety. At the same time, static cutting was used to remove the concrete supports, crown beams, pit-to-ground connecting walls and middle partition walls, reducing the impact of vibration on the surrounding environment.

请参阅图1至图3所示,本发明提供了一种深基坑钢-混组合内支撑拆除施工方法,用于拆除深基坑钢-混组合内支撑体系,内支撑体系包括水平支撑于深基坑内的水平支撑结构以及竖向支撑与深基坑内的中隔墙结构,水平支撑结构包括与深基坑的围护结构连接的钢筋混凝土支撑以及与钢筋混凝土支撑固定连接的型钢支撑。Referring to Figures 1 to 3, the present invention provides a construction method for dismantling the steel-concrete composite internal support of a deep foundation pit, which is used to dismantle the steel-concrete composite internal support system of a deep foundation pit. The internal support system includes horizontal supports on The horizontal support structure and the vertical support in the deep foundation pit are combined with the intermediate partition wall structure in the deep foundation pit. The horizontal support structure includes a reinforced concrete support connected to the enclosure structure of the deep foundation pit and a steel support fixedly connected to the reinforced concrete support.

进一步地,如图4所示,为本发明中钢筋混凝土支撑与型钢支撑的连接关系的一种较佳实施例,本实施例中包括多道预应力型钢支撑,分别为第一道型钢支撑91以及第二道型钢支撑92,第二道型钢支撑92通过第一围檩101与钢架混凝土支撑8固定连接,钢架混泥土支撑8通过第二围檩102与基坑围护结构固定连接,更进一步地,本实施例中基坑内通过栈桥梁11代替第一道钢架混凝土支撑,栈桥梁11上浇筑有栈桥板12,且栈桥梁11与栈桥板12均通过压顶梁13与基坑围护结构固定连接,较优地,基坑内第一道型钢支撑91则与栈桥梁11以及栈桥板12相对于基坑围护结构的一端固定连接,第一围檩101通过竖向的格构柱14进行临时支撑。Further, as shown in Figure 4, it is a preferred embodiment of the connection relationship between the reinforced concrete support and the profile steel support in the present invention. This embodiment includes multiple prestressed profile steel supports, respectively the first profile steel support 91 and a second profile steel support 92. The second profile steel support 92 is fixedly connected to the steel frame concrete support 8 through the first purlin 101, and the steel frame concrete support 8 is fixedly connected to the foundation pit enclosure structure through the second purlin 102. Furthermore, in this embodiment, the first steel frame concrete support is replaced by a trestle bridge 11 in the foundation pit. A trestle bridge 11 is poured with a trestle plate 12, and both the trestle bridge 11 and the trestle plate 12 are connected to the foundation pit enclosure through the top beam 13. The protective structure is fixedly connected. Preferably, the first steel support 91 in the foundation pit is fixedly connected to one end of the trestle bridge 11 and the trestle plate 12 relative to the foundation pit protective structure. The first purlin 101 passes through vertical lattice columns. 14 Carry out temporary support.

本发明深基坑钢-混组合内支撑拆除施工方法包括如下施工步骤:The present invention's deep foundation pit steel-concrete combination internal support removal construction method includes the following construction steps:

S1施工准备S1 construction preparation

依据图纸、规范要求,结合工程现场实际情况,复核确认支撑拆除条件,及时向监理单位提出拆除申请,经批准后向专业分包单位签发拆除指令;According to the drawings and specification requirements, combined with the actual situation of the project site, review and confirm the support removal conditions, submit a removal application to the supervision unit in a timely manner, and issue a removal instruction to the professional subcontracting unit after approval;

确定支撑件临时堆放场地、规划好支撑件的装车吊装点(满足50吨汽车吊停放、吊运的要求)和场内交通线路,当日支撑拆除件不得集中堆放楼板上部,同时靠近基坑5m范围内不允许长时间堆载,应及时装车外运;Determine the temporary storage site for the support parts, plan the loading and lifting points of the support parts (to meet the requirements for parking and lifting of the 50-ton truck crane) and the traffic routes on the site. The support dismantling parts on the day shall not be stacked in a concentrated manner on the upper part of the floor, and at the same time, it shall be 5m close to the foundation pit. Long-term stacking is not allowed within the scope and should be loaded and transported in time;

商定支撑拆除与地下结构施工的交叉作业条件,明确工作面移交要求、为拆除部位的地下结构后续施工尽早移交工作面;Agree on the cross-working conditions for support demolition and underground structure construction, clarify the working surface handover requirements, and hand over the working surface as soon as possible for the subsequent construction of the underground structure at the demolition site;

落实拆除所需人员、设备的投入,当多道支撑同时具备拆除条件的,应结合进度要求增加人员与设备的投入,并确保各道支撑的拆除各有必要的安全作业空间,避免因作业空间拥挤造成的安全隐患;Implement the investment in personnel and equipment required for dismantling. When multiple supports are eligible for dismantling at the same time, the investment in personnel and equipment should be increased according to the progress requirements, and ensure that each support has the necessary safe operating space to avoid safety hazards caused by crowding;

结合拆除工程量,提前安排好运输车辆,确保拆除后的支撑件尽快装车运出现场(现场临时堆放时间不宜超过24小时);Combined with the amount of demolition work, arrange transportation vehicles in advance to ensure that the dismantled supports are loaded and transported out of the site as soon as possible (the temporary stacking time on site should not exceed 24 hours);

落实坑外降水(以减少坑外压力)、加大支撑拆除期间的基坑监测频率,拆除过程中,加强与基坑监测单位的协作、做到信息的及时共享。Implement precipitation outside the pit (to reduce pressure outside the pit), increase the frequency of foundation pit monitoring during support dismantling, and strengthen collaboration with foundation pit monitoring units during the dismantling process to achieve timely sharing of information.

S2钢筋混凝土支撑拆除S2 reinforced concrete support removal

在基坑内钢筋混凝土支撑下设置临时支撑,采用静力切割方式拆除钢筋混凝土支撑并吊装至临时堆放位置,具体包括以下操作要点:Set up temporary supports under the reinforced concrete supports in the foundation pit, use static cutting to remove the reinforced concrete supports and hoist them to the temporary stacking position, including the following operating points:

①切割钢丝绳与放切割线① Cutting wire rope and placing cutting line

根据采用的静力切割施工工艺,切割前先在支撑上部拉设钢丝绳作为支撑拆除工人生命线,其次拆除钢筋混凝土支撑上部钢管防护,放切割线时,应严格按实际施工方案要求,准确标示出支撑切割线并通知监理延后。According to the static cutting construction technology adopted, before cutting, a steel wire rope is first stretched on the upper part of the support as a lifeline for the support dismantling workers, and then the steel pipe protection on the upper part of the reinforced concrete support is removed. When placing the cutting line, the support should be accurately marked according to the actual construction plan requirements. Cut the line and notify the supervisor of the delay.

②设立临时支撑② Set up temporary support

验收通过后采用工字钢托架搭设好临时支撑,本实施例中临时支撑采用马凳支撑托架,并且马凳支撑托架立柱采用12号工字钢,横梁采用横截面规格参数为120mm×60mm×5mm(长*宽*厚)的方管,单个定制马凳支撑托架采用钢架拼接而成,每段钢筋混凝土支撑下放置两个托架,马凳支撑托架离支撑立柱距离控制在300mm~600mm,马凳支撑托架离混凝土切割线距离控制在300mm~500mm,支撑分段切割线完成标识后进行三方联合验收,马凳支撑托架与混凝土支撑之间预留有空隙,空隙内设有填充物,本实施例中采用方木塞垫牢固,需要说明的是,使用方形木块作为填充物,以确保支撑托架与混凝土支撑之间的连接牢固。这样做可以提供更好的稳定性和支撑力,防止支撑托架在使用过程中发生松动或移位。方木塞垫可以填充空隙并提供额外的支撑,使整个结构更加牢固可靠。After passing the acceptance check, I-beam brackets are used to set up temporary supports. In this embodiment, the temporary supports use horse stool support brackets, and the horse stool support bracket columns are made of No. 12 I-beam steel, and the cross-section specifications of the cross beams are 120mm× A 60mm×5mm (length*width*thick) square tube. A single custom-made horse stool support bracket is made of steel frames. Two brackets are placed under each section of reinforced concrete support. The distance between the horse stool support bracket and the supporting column is controlled. The distance between the horse stool support bracket and the concrete cutting line should be controlled at 300mm to 600mm. The distance between the support bracket and the concrete cutting line should be controlled at 300mm to 500mm. After the support section cutting line is marked, a joint inspection by the three parties should be carried out. There should be a gap between the horse stool support bracket and the concrete support. The gap There is a filler inside, and in this embodiment, square wooden plugs are used to cushion it firmly. It should be noted that square wooden blocks are used as fillers to ensure that the connection between the support bracket and the concrete support is firm. This provides better stability and support and prevents the support bracket from loosening or shifting during use. Square cork pads can fill in gaps and provide additional support, making the entire structure stronger and more reliable.

③切割钢筋混凝土内支撑③Cut reinforced concrete inner supports

采用钻石链条锯搭配钻孔机切割,链条锯其纯切割速度:40分钟/断面~60分钟/断面,安装时间:20分钟/次~40分钟/次,钻孔机纯切割速度:12小时/断面,安装时间:5分钟/次,接水和接电进行切割。利用链锯自下往上切割,上部保留支撑100mm~150mm左右(梁上部主筋未断)。Use a diamond chain saw with a drilling machine for cutting. The pure cutting speed of the chain saw is: 40 minutes/section to 60 minutes/section. The installation time is: 20 minutes/time to 40 minutes/time. The pure cutting speed of the drilling machine is: 12 hours/time. Section, installation time: 5 minutes/time, connect water and electricity for cutting. Use a chain saw to cut from bottom to top, leaving about 100mm to 150mm of support on the upper part (the main ribs on the upper part of the beam are not broken).

④固定钻台销子尺寸④Drill floor pin size

穿好链条并用液压钳接好接头并开通。开通水管,调节水流大小,通过控制器将链条收紧。固定钻台的销子尺寸,从切割线到销子中央的距离是42cm。Thread the chain and use hydraulic pliers to connect the joints and open them. Open the water pipe, adjust the water flow, and tighten the chain through the controller. The size of the pin that fixes the drill floor, the distance from the cutting line to the center of the pin is 42cm.

⑤切割两侧钢筋并运输、堆放混凝土块⑤ Cut the steel bars on both sides and transport and stack the concrete blocks

采用20吨叉车插入工字钢托架和支撑之间空隙并向上托紧,然后用气割枪将支撑的两侧钢筋割断,然后叉车将混凝块慢慢下放至楼面高度,再将混凝土块运至指定堆放位置,叉车位置通过楼板插筋区域铺设1cm厚钢板避免破坏钢筋。Use a 20-ton forklift to insert into the gap between the I-beam bracket and the support and tighten it upward. Then use a gas cutting gun to cut the steel bars on both sides of the support. Then the forklift slowly lowers the concrete block to the floor height, and then removes the concrete block. Transport to the designated stacking location, and lay 1cm thick steel plates through the floor reinforcement area at the forklift location to avoid damaging the steel bars.

⑥吊装、外运混凝土块⑥ Hoisting and transporting concrete blocks

采用70吨-100吨汽车吊将混凝土块吊运装车外运,混凝土支撑块及围檩在结构楼板堆放平铺,严禁叠堆,且堆放在梁位置,避免集中荷载。A 70-ton to 100-ton truck crane is used to lift and load the concrete blocks for outbound transportation. The concrete support blocks and purlins are stacked and laid flat on the structural floor. Stacking is strictly prohibited and should be stacked on beams to avoid concentrated loads.

S3型钢支撑拆除S3 steel support removal

钢筋混凝土支撑拆除完毕后,采用逐级卸载的方式卸载型钢支撑的预加轴力,并采用气割方式割除型钢支撑与竖向围护结构焊接连接的支架和传力件,以拆除型钢支撑。需要说明的是,在拆除与型钢立柱连接的托座时,需先松开高强螺栓,采用手动葫芦吊住托座后再取出高强螺栓,利用葫芦放至楼板面、运至临时堆放区域,同时采用气割方式割除与竖向围护结构焊接连接的支架、传力件,以满足型钢回收要求,型钢支撑拆除具体包括以下操作要点:After the reinforced concrete supports are removed, the pre-loaded axial force of the steel supports is unloaded step by step, and the brackets and force transmission parts welded between the steel supports and the vertical enclosure structure are cut off using gas cutting to dismantle the steel supports. It should be noted that when dismantling the bracket connected to the steel column, it is necessary to loosen the high-strength bolts first, use a manual hoist to lift the bracket, then take out the high-strength bolts, use the hoist to place it on the floor surface, and transport it to the temporary storage area. Use gas cutting to cut off the brackets and force transmission parts welded to the vertical enclosure structure to meet the requirements for section steel recycling. The removal of section steel supports specifically includes the following operating points:

①支撑卸压①Support and pressure relief

办理完成支撑拆除令后对型钢支撑进行拆除。拆除前先松开机械锁。拆除时为避免瞬间预加应力释放过大而导致结构局部变形开裂采用逐级卸载的方式,卸载按预加轴力80%、50%、0%三级,卸压至0时收回千斤顶活塞。After completing the support removal order, the steel supports will be removed. Release the mechanical lock before removal. During dismantling, in order to avoid excessive instantaneous pre-stress release and causing local deformation and cracking of the structure, a step-by-step unloading method is adopted. The unloading is performed in three levels of 80%, 50%, and 0% of the pre-loaded axial force. When the pressure is relieved to 0, the jack piston is retracted.

②拆除油管及传感器②Remove the oil pipe and sensor

接下来拆除油管及传感器接线将超声波传感器拆除(超声波必须提前拆除,严禁在有超声波传感器的情况下对支撑头总成进行吊装作业)。位移线航插用电工胶带缠紧,油管接头和千斤顶接头用堵头旋紧,防止液压油泄露。卸载中随时观察油泵邮箱的油尺,若液压油充满应及时将液压油抽取到油桶中。Next, remove the oil pipe and sensor wiring and remove the ultrasonic sensor (the ultrasonic must be removed in advance, and it is strictly prohibited to hoist the support head assembly when there is an ultrasonic sensor). The displacement line plug should be tightly wrapped with electrical tape, and the oil pipe joint and jack joint should be tightened with plugs to prevent hydraulic oil leakage. Observe the dipstick of the oil pump mailbox at any time during unloading. If the hydraulic oil is full, pump the hydraulic oil into the oil barrel in time.

③吊装、外运零部件③ Hoisting and outsourcing parts

随后吊出钢支撑,在地面进行分解,拆卸的零部件应分类有序存放至指定区域,集中装车外运。The steel supports are then lifted out and disassembled on the ground. The disassembled parts should be sorted and stored in designated areas in an orderly manner for centralized loading and transportation.

如图2所示,为本发明一种实施例的基坑型钢组合支撑拆除顺序的平面布置图,一层钢支撑由六道基坑角撑和三道基坑对撑组成,六道一层角撑命名为1C1、1C2、1C3、1C4、1C5、1C6,三道一层基坑对撑的命名为1C7、1C8、1C9,二层钢支撑同样由六道基坑角撑和三道基坑对撑组成,六道二层角撑命名为2C1、2C2、2C3、2C4、2C5、2C6,三道二层基坑对撑的命名为2C7、2C8、2C9,按照先二层再一层的顺序进行拆除,二层基坑角撑的拆除顺序3为①2C1→2C2→2C3;②2C4→2C5→2C6,一层基坑角撑拆除顺序3为①1C1→1C2→1C3;②1C4→1C5→1C6,二层基坑对撑的拆除顺序3为2C9→2C8→2C7(随工况进行调整);一层基坑对撑的拆除顺序3为1C9→1C8→2C7(随工况进行调整)。S4中隔墙拆除As shown in Figure 2, it is a plan layout diagram of the demolition sequence of the foundation pit steel composite support according to one embodiment of the present invention. The one-layer steel support is composed of six foundation pit corner braces and three foundation pit opposite braces. The six-layer one-layer corner braces They are named 1C1, 1C2, 1C3, 1C4, 1C5, and 1C6. The three first-floor foundation pit braces are named 1C7, 1C8, and 1C9. The second-floor steel supports are also composed of six foundation pit corner braces and three foundation pit braces. , the six second-story corner braces are named 2C1, 2C2, 2C3, 2C4, 2C5, and 2C6, and the three second-story foundation pit braces are named 2C7, 2C8, and 2C9. They are to be removed in the order of first the second floor and then the first floor. The removal sequence 3 of the corner braces of the first-floor foundation pit is ①2C1→2C2→2C3; ②2C4→2C5→2C6. The removal sequence 3 of the corner braces of the first-floor foundation pit is ①1C1→1C2→1C3; ②1C4→1C5→1C6, the opposite braces of the second-floor foundation pit. The dismantling sequence 3 is 2C9→2C8→2C7 (adjusted according to the working conditions); the dismantling sequence 3 of the first-floor foundation pit support is 1C9→1C8→2C7 (adjusted according to the working conditions). Removal of partition wall in S4

采用以静力切割为主、机械破拆为辅的拆除方法按照自上而下的顺序逐层拆除中隔墙结构。具体地,包括如下步骤:The middle partition wall structure will be dismantled layer by layer in a top-down order using a demolition method mainly based on static cutting and supplemented by mechanical demolition. Specifically, it includes the following steps:

在中隔墙结构的两侧至主体结构框架柱之间设置换撑立柱;Set bracing columns between both sides of the central partition wall structure and the frame columns of the main structure;

拆除中隔墙结构至两侧主体结构框架柱范围内的竖向支撑排架;Remove the vertical support racks from the middle partition wall structure to the frame columns of the main structure on both sides;

采用跳仓法按照先两侧向中间,再中间向两侧的顺序将中隔墙结构与两侧的主体结构楼板进行割除;Use the vaulting method to cut off the middle partition wall structure and the main structural floors on both sides in the order of first moving from the two sides to the middle, and then from the middle to both sides;

逐次分段施工连接楼板以连接中隔墙结构两侧的主体结构楼板,并逐层拆除换撑立柱。The connecting floors are constructed in sections to connect the main structural floors on both sides of the central partition wall structure, and the supporting columns are removed and replaced layer by layer.

进一步地,中隔墙结构在拆除还包括以下操作要点:Furthermore, the demolition of the middle partition wall structure also includes the following operating points:

①中间向两边拆除中隔墙①Remove the middle partition wall from the middle to both sides

中隔墙两侧结构出±0达到设计强度后拆除中隔墙。中隔墙拆除以2m一个拆除区段进行拆除,采用跳仓法分段进行拆除。并由两侧向中间拆除,逐次分段施工连接楼板,再从中间向两边拆除,施工连接楼板。完成后自上而下逐层拆除,封闭后浇带,如图3所示,后浇带在封闭时将工字钢7两侧的封板5与两侧楼板进行连接,图中标号4为底板,标号6为止水钢板。The middle partition wall will be removed after the structures on both sides of the middle partition wall reach the design strength. The middle partition wall will be dismantled in 2m sections, and will be dismantled section by section using the warehouse jumping method. It is dismantled from both sides to the middle, and the floor slabs are connected in sections, and then dismantled from the middle to both sides, and the floor slabs are connected. After completion, it is dismantled layer by layer from top to bottom, and the post-casting tape is closed, as shown in Figure 3. When the post-casting tape is closed, the sealing plates 5 on both sides of the I-beam 7 are connected to the floor slabs on both sides. Number 4 in the figure is Bottom plate, number 6 is a water-proof steel plate.

②自上而下拆除中隔墙②Remove the middle partition wall from top to bottom

中隔墙结构除起分坑开挖的作用外,同时又是深基坑支护结构中水平传力的重要构造”的特性,故实施中隔墙结构拆除时,必须确保不致主体结构水平向受力失衡。采用以静力切割拆除为主,机械破拆为辅的施工方法,自上而下逐层拆除中隔墙结构。In addition to playing the role of dividing pit excavation, the middle partition wall structure is also an important horizontal force transmission structure in the deep foundation pit support structure. Therefore, when dismantling the middle partition wall structure, it must be ensured that the main structure does not move horizontally. The force is unbalanced. The construction method is mainly static cutting and demolition, supplemented by mechanical demolition, and the middle partition wall structure is demolished layer by layer from top to bottom.

主体结构施工过程中,中隔墙结构两侧至框架柱范围内的各层楼面竖向支撑排架,在中隔墙结构拆除施工准备前均不拆除,拆除前为腾出施工作业面,设置换撑立柱后拆除支撑排架。切割完成后,利用叉车清运施工层楼面处的中隔墙结构,然后实施施工层楼面对接,随着结构施工,换撑立柱逐层拆除。During the construction of the main structure, the vertical support racks on each floor within the range from both sides of the central partition wall structure to the frame columns will not be dismantled before preparations for the demolition and construction of the central partition wall structure. In order to free up the construction work surface before demolition, After installing the replacement support columns, remove the support racks. After the cutting is completed, a forklift is used to clear and transport the middle partition wall structure at the construction floor, and then the construction floors are connected. As the structure is constructed, the supporting columns are removed layer by layer.

S4吊装、外运拆卸物S4 hoisting and outbound transportation of dismantled objects

全部支撑拆除完毕后,利用吊车将拆卸物进行吊装并运送至场外。After all supports are removed, a crane is used to hoist the dismantled objects and transport them off-site.

以上结合附图对本发明的实施方式作了详细说明,但本发明不限于所描述的实施方式。对于本领域的技术人员而言,在不脱离本发明原理和精神的情况下,对这些实施方式进行多种变化、修改、替换和变型,仍落入本发明的保护范围内。The embodiments of the present invention have been described in detail above with reference to the accompanying drawings, but the present invention is not limited to the described embodiments. For those skilled in the art, various changes, modifications, substitutions and modifications can be made to these embodiments without departing from the principle and spirit of the invention, and they still fall within the protection scope of the invention.

Claims (6)

1. The construction method for dismantling the steel-concrete combined inner support of the deep foundation pit is used for dismantling the steel-concrete combined inner support system of the deep foundation pit, the inner support system comprises a horizontal support structure and a vertical support structure, wherein the horizontal support structure is arranged in the deep foundation pit and comprises a reinforced concrete support connected with an enclosure structure of the deep foundation pit and a section steel support fixedly connected with the reinforced concrete support, and the construction method is characterized by comprising the following steps of:
placing a temporary support under the reinforced concrete support in the foundation pit, dismantling the reinforced concrete support in a static cutting mode, and hoisting to a temporary stacking position;
unloading the pre-applied axial force of the section steel support step by step, cutting off the section steel support from the vertical enclosure structure, and hoisting to a temporary stacking position;
and adopting a dismantling method taking static cutting dismantling as a main part and mechanical breaking dismantling as an auxiliary part to dismantle the intermediate wall structure layer by layer according to the sequence from top to bottom.
2. The deep foundation pit steel-concrete combined inner support dismantling construction method is characterized by comprising the following steps of: and when the reinforced concrete support is dismantled, the gas cutting gun is used for cutting off the steel bars at the two sides of the reinforced concrete support.
3. The deep foundation pit steel-concrete combined inner support dismantling construction method is characterized by comprising the following steps of: and the reinforced concrete support is pulled to be provided with a steel wire rope at the upper part of the reinforced concrete support before the reinforced concrete support is removed, the upper steel tube is removed for protection, and a cutting line is placed.
4. The deep foundation pit steel-concrete combined inner support dismantling construction method is characterized by comprising the following steps of: the temporary support is a split heads support bracket, two split heads support brackets are arranged below each section of reinforced concrete support, a gap is reserved between each split heads support bracket and each reinforced concrete support, and a filler is arranged in each gap.
5. The deep foundation pit steel-concrete combined inner support dismantling construction method is characterized by comprising the following steps of: and when the section steel support is dismantled, a gas cutting mode is adopted to cut off the support and the force transmission piece, which are connected with the vertical enclosure structure, of the section steel support.
6. The deep foundation pit steel-concrete combined inner support dismantling construction method as claimed in claim 1, wherein the intermediate wall structure comprises the following steps when dismantling:
a replacement supporting column is arranged between two sides of the intermediate wall structure and the frame column of the main body structure;
removing the intermediate wall structure to the vertical support bent within the range of the frame columns of the main body structures at the two sides;
the middle partition wall structure and the main structure floors at the two sides are cut off by adopting a bin jump method according to the sequence from the two sides to the middle and then from the middle to the two sides;
and successively constructing connection floors in sections to connect main structure floors on two sides of the intermediate wall structure, and removing support-changing upright posts layer by layer.
CN202311192753.2A 2023-09-15 2023-09-15 Construction method for dismantling steel-concrete combined inner support of deep foundation pit Pending CN117027495A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311192753.2A CN117027495A (en) 2023-09-15 2023-09-15 Construction method for dismantling steel-concrete combined inner support of deep foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311192753.2A CN117027495A (en) 2023-09-15 2023-09-15 Construction method for dismantling steel-concrete combined inner support of deep foundation pit

Publications (1)

Publication Number Publication Date
CN117027495A true CN117027495A (en) 2023-11-10

Family

ID=88602576

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311192753.2A Pending CN117027495A (en) 2023-09-15 2023-09-15 Construction method for dismantling steel-concrete combined inner support of deep foundation pit

Country Status (1)

Country Link
CN (1) CN117027495A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN119121962A (en) * 2024-10-29 2024-12-13 中国建筑第八工程局有限公司 Steel-concrete composite support structure for large-span deep foundation pit and its construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105421491A (en) * 2015-09-06 2016-03-23 上海建工七建集团有限公司 Construction method for middle wall dismantling and two-side structure connecting
CN111608186A (en) * 2020-04-14 2020-09-01 中国建筑第二工程局有限公司 Construction method for inner support of pit-in-pit section steel of super high-rise pit
CN116122298A (en) * 2022-12-30 2023-05-16 中国建筑第八工程局有限公司 Early jointing of the main structure of the deep foundation pit near the subway and early demolition of the middle partition wall
CN116289981A (en) * 2023-02-23 2023-06-23 中国建筑第五工程局有限公司 Construction method for dismantling support in irregular deep and large foundation pit

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105421491A (en) * 2015-09-06 2016-03-23 上海建工七建集团有限公司 Construction method for middle wall dismantling and two-side structure connecting
CN111608186A (en) * 2020-04-14 2020-09-01 中国建筑第二工程局有限公司 Construction method for inner support of pit-in-pit section steel of super high-rise pit
CN116122298A (en) * 2022-12-30 2023-05-16 中国建筑第八工程局有限公司 Early jointing of the main structure of the deep foundation pit near the subway and early demolition of the middle partition wall
CN116289981A (en) * 2023-02-23 2023-06-23 中国建筑第五工程局有限公司 Construction method for dismantling support in irregular deep and large foundation pit

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周志华: "大型深基坑内支撑拆除工艺研究", 城市建设理论研究, no. 11, 31 October 2019 (2019-10-31), pages 168 - 171 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN119121962A (en) * 2024-10-29 2024-12-13 中国建筑第八工程局有限公司 Steel-concrete composite support structure for large-span deep foundation pit and its construction method

Similar Documents

Publication Publication Date Title
CN109162204B (en) Construction method for transverse block rapid assembling of bridge substructure
CN102864737A (en) Steel-structured passenger foot bridge
CN108104284B (en) Wall panel connection structure and assembly method with steel arm of shear wall embedded in floor slab
CN105839985A (en) Hydropower station rectangular high tower hydraulic climb slip form system and construction method
CN102653938B (en) Offshore dismantling construction method for descending movable formwork
CN117027495A (en) Construction method for dismantling steel-concrete combined inner support of deep foundation pit
CN106320192A (en) Beam section replacement reinforcement method for large-span concrete continuous beam bridge
CN114809703B (en) Column-pulling conversion reinforcing structure and construction method thereof
CN113774972B (en) Reinforcing method for overload punching damage of independent foundation under column
CN209837765U (en) Reverse Demolition of Reinforced Concrete Structure Temporary Support Conversion Device
CN115897600A (en) Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area
CN116876890A (en) Method for dismantling steel-concrete combined inner support of deep foundation pit
CN203639841U (en) Steel plate-concrete combined reinforcement structure of hollow plate beam
CN117513792A (en) Method for updating, reforming and recycling large-scale assembled industrial building factory building column
CN117449215A (en) A kind of bridge main tower cross beam construction method
CN114875813B (en) Construction equipment and construction method for dismantling and rebuilding reinforced concrete steel frame arch bridge
CN114812190B (en) A double series kiln tail frame layer adding system and method
CN116876326A (en) Construction method of urban overhead cast-in-situ bent cap
CN112211426B (en) Method for repairing historical building
CN108483247A (en) A kind of townhouse carrying pole type hoisting frame being mounted laterally based on concrete isolated beam
CN115522569A (en) A construction method for dismantling the shared enclosure structure of a subway station
CN114622952A (en) Repairing and reinforcing method for metal mine ore pass
CN206844680U (en) Steel gallery ground assembly load transfer device
Halding et al. The potential for direct reuse of precast concrete slabs in buildings with “wet” joints
CN223446657U (en) A steel transfer platform connection structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination