CN117027412A - Construction method of frame structure - Google Patents

Construction method of frame structure Download PDF

Info

Publication number
CN117027412A
CN117027412A CN202310762701.8A CN202310762701A CN117027412A CN 117027412 A CN117027412 A CN 117027412A CN 202310762701 A CN202310762701 A CN 202310762701A CN 117027412 A CN117027412 A CN 117027412A
Authority
CN
China
Prior art keywords
mold
column
frame structure
concrete slab
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310762701.8A
Other languages
Chinese (zh)
Inventor
刘韶华
许圣洁
张步亭
唐修国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sany Construction Technology Co Ltd
Original Assignee
Sany Construction Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sany Construction Technology Co Ltd filed Critical Sany Construction Technology Co Ltd
Priority to CN202310762701.8A priority Critical patent/CN117027412A/en
Publication of CN117027412A publication Critical patent/CN117027412A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/02Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及装配式建筑施工技术领域,公开了框架结构的施工方法,施工方法包括以下步骤:在下层框架结构的混凝土板上安装柱作业平台;安装预制柱及现浇模具中的柱底外模;安装现浇模具中除了柱底外模之外的其余模具;在现浇区域内浇筑混凝土;拆除现浇模具;在下层框架结构的混凝土板上安装柱作业平台的步骤之前,施工方法还包括:将面内作业防护装置安装在下层框架结构的混凝土板上;或者,在安装预制柱及现浇模具中的柱底外模的步骤和在安装现浇模具中除了柱底外模之外的其余模具的步骤之间,施工方法还包括:将面内作业防护装置安装在预制柱上。安装或拆除面内作业防护装置时,施工人员在混凝土板的面内操作,无需在外部施工,安拆风险小。

The invention relates to the technical field of prefabricated building construction, and discloses a construction method of a frame structure. The construction method includes the following steps: installing a column working platform on the concrete slab of the lower frame structure; installing prefabricated columns and column bottom outer molds in cast-in-place molds ; Install the remaining molds in the cast-in-place mold except the column bottom outer mold; pour concrete in the cast-in-place area; remove the cast-in-place mold; before installing the column working platform on the concrete slab of the lower frame structure, the construction method also includes : Install the in-plane work protection device on the concrete slab of the lower frame structure; or, the steps of installing the precast columns and the column bottom outer mold in the cast-in-place mold and the steps other than the column bottom outer mold in the installation of the cast-in-place mold. Between the rest of the molding steps, the construction method also includes installing in-plane work guards on the precast columns. When installing or removing protective devices for in-plane operations, construction workers operate within the surface of the concrete slab, without the need for external construction, and the installation and removal risks are small.

Description

框架结构的施工方法Construction methods of frame structures

技术领域Technical field

本发明涉及装配式建筑施工技术领域,具体涉及框架结构的施工方法。The present invention relates to the technical field of prefabricated building construction, and specifically to a construction method of a frame structure.

背景技术Background technique

装配式混凝土结构是我国建筑结构发展的重要方向之一,它有利于我国建筑工业化的发展,提高生产效率节约能源,发展绿色环保建筑,并且有利于提高和保证建筑工程质量。与现浇施工工法相比,装配式混凝土结构有利于绿色施工,因为装配式施工更能符合绿色施工的节地、节能、节材、节水和环境保护等要求。Prefabricated concrete structure is one of the important directions for the development of building structures in my country. It is conducive to the development of my country's construction industrialization, improves production efficiency, saves energy, develops green and environmentally friendly buildings, and is conducive to improving and ensuring the quality of construction projects. Compared with the cast-in-situ construction method, prefabricated concrete structures are conducive to green construction, because prefabricated construction can better meet the requirements of green construction such as land saving, energy saving, material saving, water saving and environmental protection.

在框架混凝土结构在主体施工过程中,现有的通用施工工艺均需搭设外部脚手架,一方面作为安全防护,一方面为结构施工提供外部作业面。外脚手架搭设需全人工搭设、拆除,搭设速度慢,材料多,使用成本相对较高;且搭设过程本身安全风险大,外架安拆事故、外架垮塌事故时有发生。During the main construction process of the frame concrete structure, the existing general construction technology requires the erection of external scaffolding, on the one hand, as a safety protection, and on the other hand, to provide an external working surface for the structure construction. The erection of external scaffolding requires full manual erection and dismantling. The erection speed is slow, the materials are large, and the use cost is relatively high. Moreover, the erection process itself has high safety risks, and external frame installation and disassembly accidents and external frame collapse accidents occur from time to time.

发明内容Contents of the invention

有鉴于此,本发明提供了一种框架结构的施工方法,以解决人工搭设外部脚手架的过程中以及施工人员在脚手架上作业存在安全风险大的问题。In view of this, the present invention provides a construction method of a frame structure to solve the problem of high safety risks during the manual erection of external scaffolding and when construction personnel work on the scaffolding.

本发明提供了一种框架结构的施工方法,包括以下步骤:在下层框架结构的混凝土板上的平台安装位置处安装柱作业平台;安装上层框架结构的预制柱及现浇模具中的柱底外模;在混凝土板上安装现浇模具中除了柱底外模之外的其余模具;在现浇区域内浇筑混凝土;拆除所有的现浇模具,以形成上层框架结构;如此重复上述步骤,直至完成整个框架结构的施工;其中,在下层框架结构的混凝土板上的平台安装位置处安装柱作业平台的步骤之前,施工方法还包括:将面内作业防护装置安装在下层框架结构的混凝土板上;或者,在安装上层框架结构的预制柱及现浇模具中的柱底外模的步骤和在混凝土板上安装现浇模具中除了柱底外模之外的其余模具的步骤之间,施工方法还包括:将面内作业防护装置安装在预制柱上。The invention provides a construction method of a frame structure, which includes the following steps: installing a column working platform at the platform installation position on the concrete slab of the lower frame structure; installing prefabricated columns of the upper frame structure and the outer column bottom in the cast-in-place mold formwork; install the remaining molds in the cast-in-place mold on the concrete slab except the column bottom outer mold; pour concrete in the cast-in-place area; remove all the cast-in-place molds to form the upper frame structure; repeat the above steps until completed The construction of the entire frame structure; wherein, before the step of installing the column work platform at the platform installation position on the concrete slab of the lower frame structure, the construction method also includes: installing the in-plane work protection device on the concrete slab of the lower frame structure; Or, between the steps of installing the prefabricated columns of the upper frame structure and the column bottom outer mold in the cast-in-place mold and the step of installing the remaining molds in the cast-in-place mold except the column bottom outer mold on the concrete slab, the construction method also Includes: Installing in-plane work protection devices on precast columns.

有益效果:在预制柱的安装、柱底外模的安装等必须在外部完成的工序,使用柱作业平台辅助完成;安装或拆除面内作业防护装置时,施工人员系挂安全带在混凝土板的面内操作,无需在外部施工,安拆风险小,保证施工人员的安全,提高施工时的安全性,避免搭设外部脚手架时安全风险大的情况,进而避免安拆事故、垮塌事故,可在无外部脚手架的条件下完成框架结构的施工,可加快防护设施安装、拆除工效。Beneficial effects: The installation of prefabricated columns, the installation of external molds at the bottom of columns, and other processes that must be completed externally are completed with the help of the column work platform; when installing or removing protective devices for in-plane operations, construction workers should fasten safety belts on the concrete slab. In-plane operation, no external construction required, low installation and dismantling risks, ensuring the safety of construction workers, improving safety during construction, avoiding high safety risks when erecting external scaffolding, thereby avoiding installation and dismantling accidents and collapse accidents, and can be installed without Completing the construction of the frame structure under the condition of external scaffolding can speed up the installation and removal of protective facilities.

在一种可选的实施方式中,面内作业防护装置包括:防护框架和若干防护片,防护框架具有若干框口,若干防护片设置在对应的框口中,若干防护片形成开合片和固定片,开合片与平台安装位置对应设置,开合片具有打开对应的框口的打开状态及关闭对应的框口的关闭状态,安装柱作业平台时,开合片处于打开状态;在下层框架结构的混凝土板上的平台安装位置处安装柱作业平台的步骤包括:通过垂直运输设备将柱作业平台吊至靠近平台安装位置的位置处;将面内作业防护装置的开合片打开;将柱作业平台吊装到位并固定在混凝土板上,以完成柱作业平台的安装。In an optional implementation, the in-plane work protection device includes: a protective frame and several protective sheets. The protective frame has several frame openings. The plurality of protective sheets are arranged in corresponding frame openings. The plurality of protective sheets form opening and closing pieces and fixed pieces. The opening and closing piece is set corresponding to the installation position of the platform. The opening and closing piece has an open state to open the corresponding frame opening and a closed state to close the corresponding frame opening. When installing the column work platform, the opening and closing piece is in an open state; in the lower frame The steps for installing the column work platform at the platform installation position on the concrete slab of the structure include: lifting the column work platform to a position close to the platform installation position through vertical transportation equipment; opening the opening and closing tab of the in-plane work protection device; The work platform is hoisted into place and fixed to the concrete slab to complete the installation of the column work platform.

有益效果:通过防护框架和若干防护片形成面内作业防护装置,防护框架的底部固定在混凝土板上,相比现有技术中的外部脚手架,面内作业防护装置的结构比较简单,可简化外防护设施,保证防护效果的同时使防护轻量化、简单化,降低防护设施的成本投入。Beneficial effects: An in-plane work protection device is formed by a protective frame and a number of protective sheets. The bottom of the protective frame is fixed on the concrete slab. Compared with the external scaffolding in the prior art, the structure of the in-plane work protection device is relatively simple and can simplify the external work. Protective facilities ensure the protective effect while making the protection lightweight and simple, reducing the cost of protective facilities.

在一种可选的实施方式中,开合片的一侧铰接在防护框架上,开合片和其相邻的防护片通过防护连接工装连接,防护连接工装具有锁定状态及解锁状态,防护连接工装处于锁定状态时,防护连接工装将开合片和其相邻的防护片锁定在一起,开合片处于关闭状态;防护连接工装处于解锁状态时,开合片可打开。In an optional embodiment, one side of the opening and closing piece is hinged to the protective frame, and the opening and closing piece and its adjacent protective piece are connected through a protective connection tool. The protective connection tool has a locked state and an unlocked state. The protective connection When the tooling is in the locked state, the protective connection tooling locks the opening and closing piece and its adjacent protective piece together, and the opening and closing piece is in the closed state; when the protective connection tooling is in the unlocked state, the opening and closing piece can be opened.

有益效果:开合片可摆动地设置在防护框架上,打开或关闭开合片时只需要操作防护连接工装,无需拆装整个开合片,操作更简便,提高施工效率。Beneficial effects: The opening and closing piece can be swingably arranged on the protective frame. When opening or closing the opening and closing piece, only the protective connection tool needs to be operated, and there is no need to disassemble and assemble the entire opening and closing piece. The operation is easier and the construction efficiency is improved.

在一种可选的实施方式中,防护连接工装包括固定件、锁固件以及连接杆,固定件固定在开合片和其相邻的防护片中的一个上,锁固件固定在开合片和其相邻的防护片中的另一个上,连接杆可活动地设置于固定件,连接杆可锁定在锁固件上或与锁固件解锁。In an optional embodiment, the protective connection tooling includes a fixing piece, a locking piece and a connecting rod. The fixing piece is fixed on one of the opening and closing piece and its adjacent protective piece, and the locking piece is fixed on the opening and closing piece and the connecting rod. On the other of the adjacent protective pieces, the connecting rod is movably arranged on the fixing part, and the connecting rod can be locked on the locking member or unlocked with the locking member.

有益效果:通过操作连接杆就可以实现开合片的关闭或打开,操作简便省力。Beneficial effects: The opening and closing piece can be closed or opened by operating the connecting rod, which is easy and labor-saving to operate.

在一种可选的实施方式中,将面内作业防护装置安装在下层框架结构的混凝土板上的步骤包括:通过垂直运输设备将面内作业防护装置吊运至混凝土板处;通过防护固定装置将面内作业防护装置与混凝土板上的地面锚固件连接,以完成面内作业防护装置的安装。In an optional embodiment, the step of installing the in-plane work protection device on the concrete slab of the lower frame structure includes: hoisting the in-plane work protection device to the concrete slab through vertical transportation equipment; using the protective fixing device Attach the in-plane work guard to the ground anchors on the concrete slab to complete the installation of the in-plane work guard.

有益效果:通过垂直运输设备实现面内作业防护装置的吊装,通过防护固定装置实现面内作业防护装置的固定,面内作业防护装置的安装步骤简便,提高施工效率。Beneficial effects: The vertical transportation equipment is used to hoist the in-plane operation protective device, and the in-plane operation protective device is fixed through the protective fixing device. The installation steps of the in-plane operation protective device are simple and the construction efficiency is improved.

在一种可选的实施方式中,柱底外模包括L形工模、两个支撑件和两个旋转件,两个支撑件设置于L形工模的底部,两个旋转件可旋转地设置于L形工模的顶部,安装上层框架结构的预制柱及现浇模具中的柱底外模的步骤包括:通过柱作业平台将柱底外模搬运至预制柱的外侧底部;将柱底外模的L形工模贴合至预制柱的结构面及支撑件搭至混凝土板的板面上;转动旋转件时使其卡在预制柱的两个阳角处;将锁定件插入L形工模的锁定孔中锁定旋转件,以完成柱底外模的安装。In an optional embodiment, the outer mold at the bottom of the column includes an L-shaped mold, two supports and two rotating parts. The two supporting parts are arranged at the bottom of the L-shaped mold, and the two rotating parts are rotatable. Set on the top of the L-shaped mold, the steps for installing the precast columns of the upper frame structure and the column bottom outer mold in the cast-in-place mold include: transporting the column bottom outer mold to the outer bottom of the precast column through the column work platform; The L-shaped mold of the outer mold is attached to the structural surface of the prefabricated column and the supporting parts are placed on the surface of the concrete slab; when turning the rotating part, it is stuck at the two external corners of the prefabricated column; insert the locking part into the L-shaped Lock the rotating part in the locking hole of the working mold to complete the installation of the outer mold at the bottom of the column.

有益效果:通过柱作业平台实现柱底外模的安装,柱底外模的安装更简便,也可以保证施工人员的安全。Beneficial effects: The column bottom external formwork is installed through the column work platform, which makes the installation of the column bottom external formwork easier and ensures the safety of construction workers.

在一种可选的实施方式中,柱底外模包括L形工模、两个支撑件和两个旋转件,两个支撑件设置于L形工模的底部,两个旋转件可旋转地设置于L形工模的顶部,预制柱包括预制边柱,安装上层框架结构的预制柱及现浇模具中的柱底外模的步骤包括:将柱底外模侧放于预制边柱的侧边;翻转柱底外模使L形工模靠紧预制边柱的结构面及支撑件搭至混凝土板的板面上;转动旋转件时使其卡在预制柱的两个阳角处;将锁定件插入L形工模的锁定孔中锁定旋转件,以完成柱底外模的安装。In an optional embodiment, the outer mold at the bottom of the column includes an L-shaped mold, two supports and two rotating parts. The two supporting parts are arranged at the bottom of the L-shaped mold, and the two rotating parts are rotatable. Set on the top of the L-shaped mold, the prefabricated columns include prefabricated side columns. The steps for installing the prefabricated columns of the upper frame structure and the column bottom outer mold in the cast-in-place mold include: placing the column bottom outer mold sideways on the side of the prefabricated side columns. edge; turn over the outer formwork at the bottom of the column to make the L-shaped mold close to the structural surface of the prefabricated side column and the supporting parts to the surface of the concrete slab; when turning the rotating part, make it stuck at the two external corners of the prefabricated column; The locking piece is inserted into the locking hole of the L-shaped mold to lock the rotating piece to complete the installation of the outer mold at the bottom of the column.

有益效果:预制边柱的柱底外模可在混凝土板的板面内安装,无需通过边柱作业平台就可以安装,进而提高施工效率。Beneficial effects: The column bottom outer formwork of the prefabricated side columns can be installed within the surface of the concrete slab without passing through the side column working platform, thereby improving construction efficiency.

在一种可选的实施方式中,拆除所有的现浇模具,以形成上层框架结构的步骤包括:将垂直运输设备与L形工模连接;解除L形工模和柱底内模的连接;将锁定件从锁定孔中拔出;转动旋转件使其离开对应的阳角;将柱底外模吊至上层框架结构上的混凝土板上,以完成柱底外模的拆除。In an optional embodiment, the step of removing all the cast-in-place molds to form the upper frame structure includes: connecting the vertical transportation equipment with the L-shaped mold; releasing the connection between the L-shaped mold and the inner mold at the bottom of the column; Pull out the locking piece from the locking hole; turn the rotating piece away from the corresponding sun angle; hoist the column bottom outer mold to the concrete slab on the upper frame structure to complete the removal of the column bottom outer mold.

有益效果:通过垂直运输设备吊着L形工模来拆除柱底外模,拆除简便,提高模具拆卸效率。Beneficial effects: The L-shaped mold is hoisted by vertical transportation equipment to dismantle the outer mold at the bottom of the column, which is easy to dismantle and improves the efficiency of mold disassembly.

在一种可选的实施方式中,现浇模具包括边梁模具,边梁模具包括边梁外模、边梁内模、对拉螺杆以及预置螺母,预置螺母固定在边梁外模的外侧上,对拉螺杆的一端穿过边梁内模、边梁外模与预置螺母螺纹连接;在混凝土板上安装现浇模具中除了柱底外模之外的其余模具的步骤包括:在混凝土板上组装边梁模具,将组装完成的边梁模具吊装至边梁模具安装位置处,以完成边梁模具的安装;拆除所有的现浇模具,以形成上层框架结构的步骤包括:将垂直运输设备与边梁外模连接,在边梁内侧拆除对拉螺杆,将边梁外模吊至上层框架结构上的混凝土板上,以完成边梁外模的拆除。In an optional embodiment, the cast-in-place mold includes an edge beam mold. The edge beam mold includes an edge beam outer mold, an edge beam inner mold, a pull screw, and a preset nut. The preset nut is fixed on the outside of the edge beam outer mold. One end of the pull screw passes through the inner mold of the edge beam and the outer mold of the edge beam and is threaded with the preset nut; the steps for installing the remaining molds in the cast-in-place mold on the concrete slab except the column bottom outer mold include: assembling the edge beam on the concrete slab Mold, lift the assembled side beam mold to the side beam mold installation position to complete the installation of the side beam mold; remove all cast-in-place molds to form the upper frame structure. The steps include: Connecting the vertical transportation equipment to the side beam outer mold , remove the tension screws on the inside of the side beam, and lift the side beam outer formwork to the concrete slab on the upper frame structure to complete the removal of the side beam outer formwork.

有益效果:边梁模具采用在混凝土板的面内对拉加固的构造,避免施工人员探身至边梁模具与面内作业防护装置间完成施工作业,保证施工人员的安全,也可以提高施工效率。Beneficial effects: The side beam mold adopts an in-plane tensile reinforcement structure of the concrete slab, which prevents construction workers from leaning between the side beam mold and the in-plane work protection device to complete construction operations, ensuring the safety of construction workers and improving construction efficiency.

在一种可选的实施方式中,现浇模具包括对现浇模具的外模进行拼接的对接工装,对接工装包括:第一固定件,适于与一个待拼接模具连接,第一固定件上开设有插孔;第二固定件,适于与另一个待拼接模具连接;竖向移动件,插设于第二固定件内,竖向移动件包括插块,竖向移动件的上端适于延伸出待拼接模具以形成操作部,竖向移动件适于沿竖直方向移动,以使插块插入或移出插孔;在混凝土板上安装现浇模具中除了柱底外模之外的其余模具的步骤还包括:将若干个第一固定件安装于一个待拼接模具;将若干个第二固定件连同竖向移动件安装于另一个待拼接模具;将组装完成的两个待拼接模具吊装至对应位置,使两个待拼接模具贴紧安装;沿竖直方向移动竖向移动件,使插块插入至插孔内;将竖向移动件的竖向位置锁定,以完成两个待拼接模具的对接;拆除所有的现浇模具,以形成上层框架结构的步骤还包括:解除竖向移动件的竖向位置锁定;沿竖直方向移动竖向移动件,使插块移出插孔,以解除两个待拼接模具的连接。In an optional embodiment, the cast-in-place mold includes a docking tool for splicing the outer mold of the cast-in-place mold. The docking tool includes: a first fixing piece, which is suitable for connecting with a mold to be spliced. A socket is provided; the second fixing part is suitable for connecting with another mold to be spliced; the vertical moving part is inserted into the second fixing part, the vertical moving part includes an inserting block, and the upper end of the vertical moving part is suitable for Extend the mold to be spliced to form an operating part, and the vertical moving part is adapted to move in the vertical direction to insert or remove the plug into the socket; install the rest of the cast-in-place mold on the concrete slab except the outer mold at the bottom of the column. The steps of the mold also include: installing a plurality of first fixing parts on a mold to be spliced; installing a plurality of second fixing parts together with vertical moving parts on another mold to be spliced; and hoisting the two assembled molds to be spliced. to the corresponding position, so that the two molds to be spliced are installed closely; move the vertical moving part in the vertical direction to insert the plug into the socket; lock the vertical position of the vertical moving part to complete the two molds to be spliced. Mold docking; the steps of dismantling all cast-in-place molds to form the upper frame structure also include: unlocking the vertical position of the vertical moving part; moving the vertical moving part in the vertical direction to move the insert block out of the socket. Unlock the connection between the two molds to be spliced.

有益效果:对接工装利用竖向移动件的竖向移动,即可使竖向移动件的插块与第一固定件的插孔进行配合,从而便于两个待拼接模具的拆装,并且,将竖向移动件的操作部设置于上端,使得对两个待拼接模具的拆装过程不会局限于待拼接模具的外部作业面上,更加简单方便且安全。Beneficial effects: The docking tool utilizes the vertical movement of the vertical moving part to match the inserting block of the vertical moving part with the socket of the first fixing part, thereby facilitating the disassembly and assembly of the two molds to be spliced, and also The operating part of the vertical moving part is arranged at the upper end, so that the disassembly and assembly process of the two molds to be spliced is not limited to the external working surface of the molds to be spliced, making it simpler, more convenient and safer.

在一种可选的实施方式中,将面内作业防护装置安装在下层框架结构的混凝土板上时,拆除所有的现浇模具,以形成上层框架结构的步骤之后,施工方法还包括:在下层框架结构的混凝土板上安装临边防护装置;或者,将面内作业防护装置安装在预制柱上时,在安装上层框架结构的预制柱及现浇模具中的柱底外模的步骤和将面内作业防护装置安装在预制柱上的步骤之间,施工方法还包括:在下层框架结构的混凝土板安装临边防护装置。In an optional embodiment, when the in-plane work protection device is installed on the concrete slab of the lower frame structure, after the step of removing all the cast-in-place molds to form the upper frame structure, the construction method further includes: Install the edge protection device on the concrete slab of the frame structure; or, when installing the in-plane work protection device on the precast column, install the precast column of the upper frame structure and the column bottom outer mold in the cast-in-place mold and install the surface. Between the steps of installing internal work guards on the precast columns, the construction method also includes installing edge guards on the concrete slab of the underlying frame structure.

有益效果:面内作业防护装置拆除倒运前,需在下层框架结构的混凝土板上的临边位置搭设临边防护装置,临边防护装置起到防护的作用。Beneficial effects: Before the in-plane work protection device is dismantled and transported, an edge protection device needs to be erected on the edge of the concrete slab of the lower frame structure. The edge protection device plays a protective role.

在一种可选的实施方式中,将面内作业防护装置安装在预制柱上的步骤包括:通过垂直运输设备将面内作业防护装置吊至预制柱的防护安装位置处;通过防护固定架将面内作业防护装置与预制柱连接,以完成面内作业防护装置的安装。In an optional embodiment, the step of installing the in-plane work protection device on the precast column includes: lifting the in-plane work protection device to the protection installation position of the prefabricated column through vertical transportation equipment; The in-plane work protection device is connected to the prefabricated column to complete the installation of the in-plane work protection device.

附图说明Description of the drawings

为了更清楚地说明本发明具体实施方式或现有技术中的技术方案,下面将对具体实施方式或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图是本发明的一些实施方式,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly explain the specific embodiments of the present invention or the technical solutions in the prior art, the accompanying drawings that need to be used in the description of the specific embodiments or the prior art will be briefly introduced below. Obviously, the drawings in the following description The drawings illustrate some embodiments of the present invention. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without exerting any creative effort.

图1为本发明实施例的一种框架结构的施工方法中将面内作业防护装置固定在混凝土板的局部放大示意图;Figure 1 is a partially enlarged schematic diagram of fixing an in-plane work protection device to a concrete slab in a construction method of a frame structure according to an embodiment of the present invention;

图2为本发明实施例的一种框架结构的施工方法中将两个柱作业平台固定在混凝土板上的局部放大示意图;Figure 2 is a partially enlarged schematic diagram of two column work platforms being fixed on a concrete slab in a construction method of a frame structure according to an embodiment of the present invention;

图3为本发明实施例的一种框架结构的施工方法中将预制边柱和预制角柱固定在混凝土板的局部放大示意图;Figure 3 is a partially enlarged schematic diagram of fixing prefabricated side columns and prefabricated corner columns to a concrete slab in a construction method of a frame structure according to an embodiment of the present invention;

图4为本发明实施例的一种框架结构的施工方法中将柱底外模固定在预制柱的柱底的外侧的局部放大示意图;Figure 4 is a partially enlarged schematic diagram of fixing the column bottom outer mold to the outside of the column bottom of the prefabricated column in a construction method of a frame structure according to an embodiment of the present invention;

图5为本发明实施例的一种框架结构的施工方法中将柱底内模固定在预制柱的柱底的内侧的立体图;Figure 5 is a perspective view of the column bottom inner mold being fixed on the inside of the column bottom of the prefabricated column in a construction method of a frame structure according to an embodiment of the present invention;

图6为本发明实施例的一种框架结构的施工方法中拆除边柱作业平台的立体图;Figure 6 is a perspective view of the side pillar removal work platform in a construction method of a frame structure according to an embodiment of the present invention;

图7为本发明实施例的一种框架结构的施工方法中安装边梁模具、面内梁模具、梁钢筋的局部放大示意图;Figure 7 is a partially enlarged schematic diagram of the installation of side beam molds, in-plane beam molds, and beam steel bars in a construction method of a frame structure according to an embodiment of the present invention;

图8为本发明实施例的一种框架结构的施工方法中现浇混凝土凝固后的局部放大示意图;Figure 8 is a partially enlarged schematic diagram of the cast-in-place concrete after solidification in a construction method of a frame structure according to an embodiment of the present invention;

图9为本发明实施例的一种框架结构的施工方法中拆除边梁外模时的立体图;Figure 9 is a perspective view of the outer mold of the side beam when the outer mold of the side beam is removed in a construction method of a frame structure according to an embodiment of the present invention;

图10为图9所示拆除边梁外模时的局部放大示意图;Figure 10 is a partial enlarged schematic diagram of the removal of the side beam outer mold shown in Figure 9;

图11为本发明实施例的一种面内作业防护装置的一片的立体图;Figure 11 is a perspective view of a piece of an in-plane work protection device according to an embodiment of the present invention;

图12为图11所示的面内作业防护装置的局部示意图;Figure 12 is a partial schematic diagram of the in-plane work protection device shown in Figure 11;

图13为本发明实施例的一种防护连接工装和防护片配合的局部放大示意图;Figure 13 is a partially enlarged schematic diagram of the cooperation between a protective connection tooling and a protective sheet according to an embodiment of the present invention;

图14为本发明实施例的一种边柱作业平台的立体图;Figure 14 is a perspective view of a side post working platform according to an embodiment of the present invention;

图15为本发明实施例的一种角柱作业平台的立体图;Figure 15 is a perspective view of a corner post work platform according to an embodiment of the present invention;

图16为图15所示的角柱作业平台的另一角度的立体图;Figure 16 is a perspective view of the corner post work platform shown in Figure 15 from another angle;

图17为本发明实施例的一种柱底外模的立体图;Figure 17 is a perspective view of a column bottom outer mold according to an embodiment of the present invention;

图18为图17所示的柱底外模安装后的局部放大示意图;Figure 18 is a partial enlarged schematic diagram of the column bottom outer mold shown in Figure 17 after installation;

图19为图17所示的柱底外模安装时的局部放大示意图;Figure 19 is a partial enlarged schematic diagram of the column bottom outer mold shown in Figure 17 during installation;

图20为图19所示的柱底外模安装后的局部放大示意图;Figure 20 is a partial enlarged schematic diagram of the column bottom outer mold shown in Figure 19 after installation;

图21为本发明实施例的一种框架结构的施工方法中边梁模具安装后的局部放大示意图;Figure 21 is a partially enlarged schematic diagram of the side beam mold after installation in a construction method of a frame structure according to an embodiment of the present invention;

图22为本发明实施例的一种边梁模具的立体图;Figure 22 is a perspective view of a side beam mold according to an embodiment of the present invention;

图23为图22所示的边梁模具的局部分解图;Figure 23 is a partially exploded view of the side beam mold shown in Figure 22;

图24为本发明实施例的一种对接工装的部分立体图;Figure 24 is a partial perspective view of a docking tool according to an embodiment of the present invention;

图25为图24所示的对接工装安装在第一模具和第二模具上的立体图;Figure 25 is a perspective view of the docking tool shown in Figure 24 installed on the first mold and the second mold;

图26为图25所示的对接工装的竖向移动件旋转时的立体图;Figure 26 is a perspective view of the vertical moving part of the docking tool shown in Figure 25 when rotating;

图27为图26所示的对接工装的竖向移动件旋转到位后向上移动的立体图;Figure 27 is a perspective view of the vertical moving part of the docking tool shown in Figure 26 rotated in place and moved upward;

图28为图27所示的对接工装的竖向移动件向上移动到位的立体图;Figure 28 is a perspective view of the vertical moving part of the docking tool shown in Figure 27 moved upward into place;

图29为图24所示的对接工装与共面的第一模具和第二模具配合的立体图;Figure 29 is a perspective view of the docking tool shown in Figure 24 mated with the coplanar first mold and the second mold;

图30为本发明实施例的一种框架结构的施工方法中拆除边梁外模时的局部放大示意图;Figure 30 is a partially enlarged schematic diagram of a side beam outer mold being removed in a construction method of a frame structure according to an embodiment of the present invention;

图31为本发明实施例的一种框架结构的施工方法中拆除柱底外模时的立体图;Figure 31 is a perspective view of the column bottom outer mold when the column bottom outer mold is removed in a construction method of a frame structure according to an embodiment of the present invention;

图32为图31所示拆除柱底外模的局部放大示意图;Figure 32 is a partial enlarged schematic diagram of the removal of the column bottom outer mold shown in Figure 31;

图33为本发明实施例的一种框架结构的施工方法中安装完成临边防护装置的局部放大示意图;Figure 33 is a partially enlarged schematic diagram of the edge protection device installed in a construction method of a frame structure according to an embodiment of the present invention;

图34为本发明实施例的一种框架结构的施工方法中将面内作业防护装置提升后的局部放大示意图;Figure 34 is a partially enlarged schematic view of the in-plane work protection device after lifting in a construction method of a frame structure according to an embodiment of the present invention;

图35为本发明实施例的另一种框架结构的施工方法中将面内作业防护装置固定在预制柱的立体图;Figure 35 is a perspective view of the in-plane work protection device being fixed to the prefabricated column in another construction method of the frame structure according to the embodiment of the present invention;

图36为本发明实施例的另一种框架结构的施工方法中将柱作业平台固定在混凝土板的立体图;Figure 36 is a perspective view of a column work platform fixed to a concrete slab in another construction method of a frame structure according to an embodiment of the present invention;

图37为图36所示的将柱作业平台固定在混凝土板的另一视角的局部放大示意图;Figure 37 is a partially enlarged schematic diagram of the column work platform fixed to the concrete slab shown in Figure 36 from another perspective;

图38为图36所示的面内作业防护装置固定在预制柱的部分示意图。Figure 38 is a partial schematic diagram of the in-plane work protection device shown in Figure 36 being fixed on a prefabricated column.

附图标记说明:Explanation of reference symbols:

1、面内作业防护装置;101、防护片;1011、开合片;1012、固定片;102、防护框架;1021、防护立杆;1022、防护横杆;1023、固定底杆;104、斜拉杆;105、底部固定装置;1051、锚环;1052、插销;1053、楔块;107、地面锚固件;1. Protection device for in-plane work; 101. Protective piece; 1011. Opening and closing piece; 1012. Fixed piece; 102. Protective frame; 1021. Protective vertical pole; 1022. Protective crossbar; 1023. Fixed bottom pole; 104. Inclined Tie rod; 105, bottom fixing device; 1051, anchor ring; 1052, latch; 1053, wedge; 107, ground anchor;

2、防护连接工装;201、固定件;202、连接杆;203、锁固件;2. Protective connection tooling; 201. Fixings; 202. Connecting rods; 203. Locks;

3、柱作业平台;301、固定杆;302、作业台;303、防护围片;3. Column working platform; 301. Fixed pole; 302. Working table; 303. Protective enclosure;

4、预制柱;4. Prefabricated columns;

5、柱底外模;501、L形工模;5011、锁定孔;502、旋转件;503、支撑件;504、固定螺栓;5. Column bottom outer mold; 501, L-shaped mold; 5011, locking hole; 502, rotating part; 503, support part; 504, fixing bolt;

6、梁钢筋;6. Beam reinforcement;

7、面内梁模具;7. In-plane beam mold;

8、边梁模具;801、边梁外模;802、工模背楞;803、预置螺母;805、对拉螺杆;806、边梁内模;8. Side beam mold; 801, side beam outer mold; 802, mold back fluting; 803, preset nut; 805, pull screw; 806, side beam inner mold;

9、混凝土板;9. Concrete slab;

10、楼面起吊设备;10. Floor lifting equipment;

11、对接工装;1101、第一固定件;11011、插孔;11012、第一固定板;11013、第一紧固件;11014、定位板;1102、第二固定件;11021、第二固定板;11022、第二紧固件;1103、竖向移动件;11031、插块;11032、竖直杆;11033、连接部;1104、限位件;1105、压片;11. Docking tooling; 1101. First fixing piece; 11011. Jack hole; 11012. First fixing plate; 11013. First fastener; 11014. Positioning plate; 1102. Second fixing piece; 11021. Second fixing plate ; 11022. Second fastener; 1103. Vertical moving part; 11031. Insert block; 11032. Vertical rod; 11033. Connection part; 1104. Limiting member; 1105. Pressing piece;

12、临边防护装置;12. Edge protection device;

13、防护托架;13. Protective bracket;

14、防护支座;14. Protective support;

15、平台固定装置;1501、预埋件;1502、紧固板;1503、紧固螺母;15. Platform fixing device; 1501. Embedded parts; 1502. Fastening plate; 1503. Fastening nut;

16、上连接架;16. Upper connecting frame;

17、上支座;17. Upper support;

21、第一模具;21. The first mold;

22、第二模具。22. The second mold.

具体实施方式Detailed ways

为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments These are some embodiments of the present invention, rather than all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative efforts fall within the scope of protection of the present invention.

下面结合图1至图38,描述本发明的实施例。The following describes embodiments of the present invention with reference to FIGS. 1 to 38 .

根据本发明的实施例,提供了一种框架结构的施工方法,如图1至图10所示,包括以下步骤:According to an embodiment of the present invention, a construction method of a frame structure is provided, as shown in Figures 1 to 10, including the following steps:

将面内作业防护装置1安装在下层框架结构的混凝土板9上;Install the in-plane work protection device 1 on the concrete slab 9 of the lower frame structure;

在下层框架结构的混凝土板9上的平台安装位置处安装柱作业平台3;Install the column work platform 3 at the platform installation position on the concrete slab 9 of the lower frame structure;

安装上层框架结构的预制柱4及现浇模具中的柱底外模5;Install the prefabricated columns 4 of the upper frame structure and the column bottom outer mold 5 in the cast-in-place mold;

在混凝土板9上安装现浇模具中除了柱底外模5之外的其余模具;Install the remaining molds in the cast-in-place mold except the column bottom outer mold 5 on the concrete slab 9;

在现浇区域内浇筑混凝土;Concrete is poured in the cast-in-place area;

拆除所有的现浇模具,以形成上层框架结构;Remove all cast-in-place molds to form the upper frame structure;

如此重复上述步骤,直至完成整个框架结构的施工。Repeat the above steps until the construction of the entire frame structure is completed.

应用本实施例的框架结构的施工方法,每层框架结构使用预制柱4,可以规避在竖向施工过程中使用大量模具,在预制柱4的安装、柱底外模5的安装等必须在外部完成的工序,使用柱作业平台3辅助完成;安装或拆除面内作业防护装置1时,施工人员系挂安全带在混凝土板9的面内操作,无需在外部施工,安拆风险小,保证施工人员的安全,提高施工时的安全性,避免搭设外部脚手架时安全风险大的情况,进而避免安拆事故、垮塌事故,可在无外部脚手架的条件下完成框架结构的施工,可加快防护设施安装、拆除工效。Applying the construction method of the frame structure of this embodiment, each layer of the frame structure uses prefabricated columns 4, which can avoid the use of a large number of molds during the vertical construction process. The installation of the prefabricated columns 4, the installation of the outer mold 5 at the bottom of the column, etc. must be done outside. The completed process is assisted by the column work platform 3; when installing or dismantling the in-plane work protection device 1, the construction personnel wear safety belts and operate within the surface of the concrete slab 9. There is no need for external construction, and the installation and disassembly risks are small, ensuring the construction. Safety of personnel, improve safety during construction, avoid high safety risks when erecting external scaffolding, thereby avoiding installation and dismantling accidents and collapse accidents. The construction of the frame structure can be completed without external scaffolding, and the installation of protective facilities can be accelerated. , Demolition efficiency.

需要说明的是,每层框架结构包括若干柱和若干柱所支撑的混凝土板9、梁等,每个柱包括预制柱4和在预制柱4的空腔内浇筑现浇混凝土形成的现浇柱结构。It should be noted that each layer of the frame structure includes a number of columns and concrete slabs 9, beams, etc. supported by the columns. Each column includes a prefabricated column 4 and a cast-in-place column formed by pouring in-situ concrete in the cavity of the prefabricated column 4. structure.

值得说明的是,预制构件也可以仅包括预制柱,梁和楼板均通过现浇方式形成。可以理解,每层框架结构中的预制构件可以包括预制柱、预制梁、预制楼板,在安装预制柱4的步骤之后,施工方法还包括:安装预制梁和预制楼板,此时,现浇区域是指所有的预制构件和现浇模具所围成的区域。It is worth noting that prefabricated components can also only include prefabricated columns, and beams and floors are formed by cast-in-situ methods. It can be understood that the prefabricated components in each layer of the frame structure can include prefabricated columns, prefabricated beams, and prefabricated floor slabs. After the step of installing the prefabricated columns 4, the construction method also includes: installing prefabricated beams and prefabricated floor slabs. At this time, the cast-in-place area is Refers to the area surrounded by all prefabricated components and cast-in-place molds.

另外,在其他实施例中,如图35至图38所示,面内作业防护装置1也可以不固定在混凝土板9上,面内作业防护装置1固定在上层框架结构的预制柱4上,具体地,框架结构的施工方法包括:In addition, in other embodiments, as shown in Figures 35 to 38, the in-plane work protection device 1 does not need to be fixed on the concrete slab 9, and the in-plane work protection device 1 is fixed on the prefabricated column 4 of the upper frame structure. Specifically, the construction methods of frame structures include:

在下层框架结构的混凝土板9上的平台安装位置处安装柱作业平台3;Install the column work platform 3 at the platform installation position on the concrete slab 9 of the lower frame structure;

安装上层框架结构的预制柱4及现浇模具中的柱底外模5;Install the prefabricated columns 4 of the upper frame structure and the column bottom outer mold 5 in the cast-in-place mold;

将面内作业防护装置1安装在预制柱4上;Install the in-plane work protection device 1 on the prefabricated column 4;

在混凝土板9上安装现浇模具中除了柱底外模5之外的其余模具;Install the remaining molds in the cast-in-place mold except the column bottom outer mold 5 on the concrete slab 9;

在现浇区域内浇筑混凝土;Concrete is poured in the cast-in-place area;

拆除所有的现浇模具,以形成上层框架结构;Remove all cast-in-place molds to form the upper frame structure;

如此重复上述步骤,直至完成整个框架结构的施工。Repeat the above steps until the construction of the entire frame structure is completed.

需要说明的是,面内作业防护装置1固定在上层框架结构的预制柱4上的前提是上层框架结构的预制柱4与下层框架结构的混凝土板9稳固连接,预制柱4可承载防护荷载。It should be noted that the premise for the in-plane work protection device 1 to be fixed on the precast columns 4 of the upper frame structure is that the precast columns 4 of the upper frame structure are firmly connected to the concrete slab 9 of the lower frame structure, and the precast columns 4 can bear the protective load.

如图10和图11所示,在本实施例中,面内作业防护装置1包括:防护框架102和若干防护片101,防护框架102具有若干框口,若干防护片101设置在对应的框口中,若干防护片101形成开合片1011和固定片1012,开合片1011与平台安装位置对应设置,开合片1011具有打开对应的框口的打开状态及关闭对应的框口的关闭状态,安装柱作业平台3时,开合片1011处于打开状态。通过防护框架102和若干防护片101形成面内作业防护装置1,防护框架102的底部固定在混凝土板9上,相比现有技术中的外部脚手架,面内作业防护装置1的结构比较简单,可简化外防护设施,保证防护效果的同时使防护轻量化、简单化,降低防护设施的成本投入。As shown in Figures 10 and 11, in this embodiment, the in-plane work protection device 1 includes: a protective frame 102 and a plurality of protective pieces 101. The protective frame 102 has a plurality of frame openings, and a plurality of protective pieces 101 are arranged in corresponding frame openings. , a plurality of protective pieces 101 form opening and closing pieces 1011 and fixed pieces 1012. The opening and closing pieces 1011 are set corresponding to the installation position of the platform. The opening and closing pieces 1011 have an open state of opening the corresponding frame opening and a closed state of closing the corresponding frame opening. Installation When the column work platform 3 is installed, the opening and closing piece 1011 is in an open state. The in-plane work protection device 1 is formed by the protection frame 102 and several protective sheets 101. The bottom of the protection frame 102 is fixed on the concrete slab 9. Compared with the external scaffolding in the prior art, the structure of the in-plane work protection device 1 is relatively simple. It can simplify the external protective facilities, ensure the protective effect while making the protection lightweight and simple, and reduce the cost of protective facilities.

具体地,防护片101上开设有若干网孔,可以减轻防护框架102的重量,此时防护片101也可以称为防护网片。Specifically, the protective sheet 101 is provided with a number of meshes, which can reduce the weight of the protective frame 102. In this case, the protective sheet 101 may also be called a protective mesh.

在本实施例中,在下层框架结构的混凝土板9上的平台安装位置处安装柱作业平台3的步骤包括:In this embodiment, the steps of installing the column work platform 3 at the platform installation position on the concrete slab 9 of the lower frame structure include:

通过垂直运输设备将柱作业平台3吊至靠近平台安装位置的位置处;其中,垂直运输设备为塔吊或起吊等;Lift the column work platform 3 to a position close to the installation position of the platform through vertical transportation equipment; where the vertical transportation equipment is a tower crane or hoisting, etc.;

将面内作业防护装置1的开合片1011打开;Open the opening and closing piece 1011 of the in-plane work protection device 1;

将柱作业平台3吊装到位并固定在混凝土板9上,以完成柱作业平台3的安装。Lift the column work platform 3 into place and fix it on the concrete slab 9 to complete the installation of the column work platform 3.

在拆除柱作业平台3后,应立即将对应位置的开合片1011关闭,保证施工人员的安全。开合片1011的设置便于安装柱作业平台3,也便于在拆除柱作业平台3后封闭框口,提高面内作业防护装置1的适应性。After the column work platform 3 is dismantled, the opening and closing pieces 1011 at the corresponding positions should be closed immediately to ensure the safety of construction workers. The arrangement of the opening and closing piece 1011 facilitates the installation of the column work platform 3 and the closing of the frame opening after the column work platform 3 is dismantled, thereby improving the adaptability of the in-plane work protection device 1 .

在本实施例中,每层框架结构的若干预制柱4由于位置不同可分为预制角柱、预制边柱及预制面内柱等,此时若干柱作业平台3也分为边柱作业平台和角柱作业平台,安装预制角柱之前需要安装角柱作业平台;安装预制面内柱直接在混凝土板9上安装即可,无需设置柱作业平台3;安装预制边柱之前需要安装边柱作业平台;角柱作业平台的安装步骤和边柱作业平台的安装步骤均采用上述柱作业平台3的安装步骤,即角柱作业平台的安装方法和边柱作业平台的安装方法相同。In this embodiment, several prefabricated columns 4 of each layer of frame structure can be divided into prefabricated corner columns, prefabricated side columns, prefabricated in-plane columns, etc. due to different positions. At this time, several column working platforms 3 are also divided into side column working platforms and corner columns. Working platform, you need to install the corner column working platform before installing the prefabricated corner columns; you can install the prefabricated in-plane columns directly on the concrete slab 9 without setting up the column working platform 3; you need to install the side column working platform before installing the prefabricated side columns; the corner column working platform The installation steps of the column work platform and the installation steps of the side column working platform all adopt the installation steps of the column working platform 3 mentioned above, that is, the installation method of the corner column working platform is the same as that of the side column working platform.

如图14至图16所示,优选地,角柱作业平台和边柱作业平台均包括两个固定杆301、作业台302和若干防护围片303,作业台302固定在两个固定杆301上,作业台302的侧边包括在安装时靠近混凝土板9的内侧边、远离混凝土板9的外侧边以及设置在内侧边和外侧边之间的连接边,外侧边和连接边上均设有防护围片303。角柱作业平台和边柱作业平台的区别在于:角柱作业平台的两个固定杆301不平行,角柱作业平台的作业台302、内侧边、外侧边的形状均为L形,边柱作业平台的两个固定杆301平行,边柱作业平台的内侧边、外侧边均直线形,边柱作业平台的作业台302的形状为矩形。As shown in Figures 14 to 16, preferably, both the corner post working platform and the side post working platform include two fixed rods 301, a working platform 302 and several protective enclosures 303. The working platform 302 is fixed on the two fixed rods 301. The sides of the workbench 302 include an inner side that is close to the concrete slab 9 during installation, an outer side that is far away from the concrete slab 9, and a connecting side provided between the inner side and the outer side. The outer side and the connecting side Both are equipped with protective enclosures 303. The difference between the corner post work platform and the side post work platform is that the two fixed rods 301 of the corner post work platform are not parallel, the shape of the work platform 302, the inner side, and the outer side of the corner post work platform are all L-shaped, and the side post work platform The two fixed rods 301 are parallel, the inner side and the outer side of the side column working platform are both linear, and the shape of the workbench 302 of the side column working platform is rectangular.

需要说明的是,作业台302的形状不限,固定杆301的数量及固定杆301的布置方式也不限,满足作业要求即可。It should be noted that the shape of the workbench 302 is not limited, and the number of fixed rods 301 and the arrangement of the fixed rods 301 are also not limited, as long as the work requirements are met.

如图3和图14至图16所示,具体地,固定杆301通过平台固定装置15固定在混凝土板9上,每个平台固定装置15包括两个预埋件1501、一个紧固板1502、一个紧固螺母1503及一个插销1052,两个预埋件1501间隔预埋在混凝土板9中,预埋件1501具有从混凝土板9的板面伸出的螺纹杆,固定杆301上开设供插销1052穿设的若干通孔,紧固板1502具有供螺纹杆穿设的两个穿设孔。安装柱作业平台3时,将固定杆301插入两个预埋件1501的螺纹杆之间,将紧固板1502套在螺纹杆上,然后将紧固螺母1503拧在螺纹杆上,最后将插销1052插在通孔中,插销1052的长度大于两个螺纹杆之间的最大距离,紧固板1502和紧固螺母1503对固定杆301的上方进行限位,混凝土板9对固定杆301的下方进行限位,两个螺纹杆对固定杆301的两侧进行限位,插销1052对固定杆301的延伸方向的位置进行限位。通过平台固定装置15将柱作业平台3固定在混凝土板9上,平台固定装置15的结构简单,便于施工。As shown in Figures 3 and 14 to 16, specifically, the fixing rod 301 is fixed on the concrete slab 9 through the platform fixing device 15. Each platform fixing device 15 includes two embedded parts 1501, a fastening plate 1502, A fastening nut 1503 and a latch 1052, and two embedded parts 1501 are embedded in the concrete slab 9 at intervals. The embedded parts 1501 have threaded rods extending from the surface of the concrete slab 9, and fixed rods 301 are provided with latch holes. 1052 has several through holes, and the fastening plate 1502 has two through holes for threaded rods to pass through. When installing the column work platform 3, insert the fixing rod 301 between the threaded rods of the two embedded parts 1501, put the fastening plate 1502 on the threaded rod, then screw the fastening nut 1503 on the threaded rod, and finally tighten the latch 1052 is inserted into the through hole, the length of the latch 1052 is greater than the maximum distance between the two threaded rods, the fastening plate 1502 and the fastening nut 1503 limit the upper part of the fixed rod 301, and the concrete plate 9 limits the lower part of the fixed rod 301. To limit the position, the two threaded rods limit the two sides of the fixed rod 301, and the latch 1052 limits the position of the fixed rod 301 in the extension direction. The column work platform 3 is fixed on the concrete slab 9 through the platform fixing device 15. The platform fixing device 15 has a simple structure and is convenient for construction.

另外,在其他实施例中,平台固定装置15包括锚环1051、插销1052和楔块1053(如图12所示),锚环1051呈倒U形且预埋在混凝土板9中,固定杆301上开设供插销1052穿设的若干通孔。安装柱作业平台3时,将固定杆301插入锚环1051中,将楔块1053塞入锚环1051和固定杆301之间,最后将插销1052插在通孔中,插销1052的长度大于两个螺纹杆之间的最大距离,锚环1051对固定杆301的上方和两侧进行限位,混凝土板9对固定杆301的下方进行限位,插销1052对固定杆301的延伸方向的位置进行限位,楔块1053的设置可以防止固定杆301在锚环1051中上下晃动,保证柱作业平台3不上下晃动,提高柱作业平台3的稳固性。可以理解,平台固定装置15的具体结构并不局限于此,可以根据具体情况进行设计。In addition, in other embodiments, the platform fixing device 15 includes an anchor ring 1051, a latch 1052 and a wedge 1053 (as shown in Figure 12). The anchor ring 1051 is in an inverted U shape and is pre-embedded in the concrete slab 9. The fixing rod 301 A number of through holes are provided for the pins 1052 to pass through. When installing the column work platform 3, insert the fixing rod 301 into the anchor ring 1051, insert the wedge 1053 between the anchor ring 1051 and the fixing rod 301, and finally insert the latch 1052 into the through hole. The length of the latch 1052 is greater than two The maximum distance between threaded rods, the anchor ring 1051 limits the upper and both sides of the fixed rod 301, the concrete slab 9 limits the lower part of the fixed rod 301, and the latch 1052 limits the position of the fixed rod 301 in the extension direction. position, the setting of the wedge 1053 can prevent the fixed rod 301 from shaking up and down in the anchor ring 1051, ensuring that the column working platform 3 does not shake up and down, and improving the stability of the column working platform 3. It can be understood that the specific structure of the platform fixing device 15 is not limited to this, and can be designed according to specific circumstances.

需要说明的是,柱作业平台3的数量可不全数设置,即柱作业平台3的数量少于需要安装柱作业平台3对应的预制柱4的数量,在不同作业区域周转使用,柱作业平台拆除后应立即将对应位置的开合片1011关闭并连接固定。It should be noted that the number of column work platforms 3 does not need to be fully set, that is, the number of column work platforms 3 is less than the number of prefabricated columns 4 corresponding to the column work platforms 3 that need to be installed. They can be used in turn in different operating areas. After the column work platforms are dismantled, The opening and closing piece 1011 at the corresponding position should be closed immediately and connected and fixed.

如图11所示,在本实施例中,开合片1011的一侧铰接在防护框架102上,开合片1011和其相邻的防护片101通过防护连接工装2连接,防护连接工装2具有锁定状态及解锁状态,防护连接工装2处于锁定状态时,防护连接工装2将开合片1011和其相邻的防护片101锁定在一起,开合片1011处于关闭状态;防护连接工装2处于解锁状态时,开合片1011可打开。开合片1011可摆动地设置在防护框架102上,打开或关闭开合片1011时只需要操作防护连接工装2,无需拆装整个开合片1011,操作更简便,提高施工效率。As shown in Figure 11, in this embodiment, one side of the opening and closing piece 1011 is hinged on the protective frame 102, and the opening and closing piece 1011 and its adjacent protective piece 101 are connected through a protective connection tool 2. The protective connection tool 2 has Locked state and unlocked state, when the protective connection tool 2 is in the locked state, the protective connection tool 2 locks the opening and closing piece 1011 and its adjacent protective piece 101 together, and the opening and closing piece 1011 is in the closed state; the protective connection tool 2 is in the unlocked state When in the state, the opening and closing piece 1011 can be opened. The opening and closing piece 1011 is swingably arranged on the protective frame 102. When opening or closing the opening and closing piece 1011, you only need to operate the protective connection tool 2, and there is no need to disassemble and assemble the entire opening and closing piece 1011. The operation is simpler and the construction efficiency is improved.

另外,在其他实施例中,也可以开合片1011不铰接在防护框架102上,开合片1011可拆卸地安装在防护框架102上,打开或关闭开合片1011时需要拆装整个开合片1011。In addition, in other embodiments, the opening and closing piece 1011 may not be hinged on the protective frame 102. The opening and closing piece 1011 may be detachably installed on the protective frame 102. When opening or closing the opening and closing piece 1011, the entire opening and closing piece needs to be disassembled. Film 1011.

如图10和图13所示,在本实施例中,防护连接工装2包括固定件201、锁固件203以及连接杆202,固定件201固定在开合片1011和其相邻的防护片101中的一个上,锁固件203固定在开合片1011和其相邻的防护片101中的另一个上,连接杆202可活动地设置于固定件201,连接杆202可锁定在锁固件203上或与锁固件203解锁。通过操作连接杆202就可以实现开合片1011的关闭或打开,操作简便省力。As shown in Figures 10 and 13, in this embodiment, the protective connection tool 2 includes a fixing piece 201, a locking piece 203 and a connecting rod 202. The fixing piece 201 is fixed in the opening and closing piece 1011 and its adjacent protective piece 101. On one of them, the locking piece 203 is fixed on the other one of the opening and closing piece 1011 and its adjacent protective piece 101. The connecting rod 202 is movably provided on the fixing piece 201. The connecting rod 202 can be locked on the locking piece 203 or Unlock with lock firmware 203. The opening and closing piece 1011 can be closed or opened by operating the connecting rod 202, which is easy and labor-saving to operate.

在本实施例中,与开合片1011相邻的防护片101可以为固定片1012,也可以为开合片1011,即防护连接工装2可以连接相邻的开合片1011和固定片1012,也可以连接相邻的两个开合片1011。开合片1011和其相邻的防护片101可以垂直设置,也可以共面设置。In this embodiment, the protective piece 101 adjacent to the opening and closing piece 1011 can be a fixed piece 1012 or an opening and closing piece 1011, that is, the protective connection tool 2 can connect the adjacent opening and closing pieces 1011 and the fixed piece 1012, Two adjacent opening and closing pieces 1011 can also be connected. The opening and closing piece 1011 and its adjacent protective piece 101 can be arranged vertically or coplanarly.

具体地,连接杆202可相对于固定件201移动和旋转,开合片1011的初始状态为关闭状态,连接杆202锁定在锁固件203上,开合片1011不能打开;当需要打开开合片1011时,先转动连接杆202,再移动连接杆202,使得连接杆202从锁固件203拔出,然后打开开合片1011即可;关闭开合片1011时,先将开合片1011转动至关闭状态,再移动连接杆202,然后转动连接杆202,使得连接杆202锁定在锁固件203上,此时开合片1011保持在关闭状态,不能将开合片1011打开。Specifically, the connecting rod 202 can move and rotate relative to the fixing member 201. The initial state of the opening and closing piece 1011 is a closed state. The connecting rod 202 is locked on the locking member 203, and the opening and closing piece 1011 cannot be opened; when the opening and closing piece needs to be opened, the connecting rod 202 is locked on the locking member 203. 1011, first rotate the connecting rod 202, and then move the connecting rod 202, so that the connecting rod 202 is pulled out from the lock 203, and then open the opening and closing piece 1011; when closing the opening and closing piece 1011, first rotate the opening and closing piece 1011 to In the closed state, move the connecting rod 202, and then rotate the connecting rod 202 so that the connecting rod 202 is locked on the locking member 203. At this time, the opening and closing piece 1011 remains in the closed state, and the opening and closing piece 1011 cannot be opened.

在本实施例中,固定件201为固定管,锁固件203为锁固管,锁固管上开设有贯穿其两端的锁固开口,锁固开口呈L形。另外,防护连接工装2的具体结构并不局限于此,防护连接工装2的结构类似于门栓门锁,防护连接工装2也可以采用其他结构的门栓和门锁。In this embodiment, the fixing member 201 is a fixing tube, and the locking member 203 is a locking tube. The locking tube is provided with locking openings penetrating both ends thereof, and the locking opening is L-shaped. In addition, the specific structure of the protective connection tool 2 is not limited to this. The structure of the protective connection tool 2 is similar to a door bolt and door lock. The protective connection tool 2 can also use door bolts and door locks of other structures.

如图6和图11所示,在本实施例中,将面内作业防护装置1安装在下层框架结构的混凝土板9上的步骤包括:As shown in Figures 6 and 11, in this embodiment, the steps of installing the in-plane work protection device 1 on the concrete slab 9 of the lower frame structure include:

通过垂直运输设备将面内作业防护装置1吊运至混凝土板9处;Lift the in-plane operation protection device 1 to the concrete slab 9 through vertical transportation equipment;

通过防护固定装置将面内作业防护装置1与混凝土板9上的地面锚固件107连接,以完成面内作业防护装置1的安装。The in-plane work protection device 1 is connected to the ground anchors 107 on the concrete slab 9 through the protective fixing device to complete the installation of the in-plane work protection device 1 .

通过垂直运输设备实现面内作业防护装置1的吊装,通过防护固定装置实现面内作业防护装置1的固定,面内作业防护装置1的安装步骤简便,提高施工效率。The in-plane operation protection device 1 is hoisted through vertical transportation equipment, and the in-plane operation protection device 1 is fixed through protective fixing devices. The installation steps of the in-plane operation protection device 1 are simple and construction efficiency is improved.

如图11所示,在本实施例中,防护固定装置包括若干底部固定装置105和若干斜拉杆104,斜拉杆104的一端与防护框架102连接且另一端与混凝土板9连接。底部固定装置105的具体结构与平台固定装置15的具体结构相同,在此不再详细赘述,底部固定装置105优先选用锚环1051、插销1052和楔块1053。具体地,斜拉杆104的一端具有钩部,地面锚固件107可以为锚环1051或预埋螺母等,混凝土板9上预埋有若干锚环1051,钩部钩在锚环1051上。As shown in FIG. 11 , in this embodiment, the protective fixing device includes several bottom fixing devices 105 and several diagonal tie rods 104 . One end of the diagonal tie rods 104 is connected to the protective frame 102 and the other end is connected to the concrete slab 9 . The specific structure of the bottom fixing device 105 is the same as that of the platform fixing device 15 and will not be described in detail here. The bottom fixing device 105 preferably uses an anchor ring 1051, a latch 1052 and a wedge 1053. Specifically, one end of the diagonal tie rod 104 has a hook, and the ground anchor 107 can be an anchor ring 1051 or an embedded nut, etc. There are several anchor rings 1051 embedded in the concrete slab 9 , and the hook is hooked on the anchor ring 1051 .

在本实施例中,防护框架102包括若干防护立杆1021、若干防护横杆1022及若干固定底杆1023,若干防护立杆1021间隔设置,相邻的两个防护立杆1021通过若干防护横杆1022连接,防护立杆1021的底部固定有固定底杆1023,若干防护立杆1021和若干防护横杆1022围成若干框口,固定底杆1023通过底部固定装置105与混凝土板9固定连接。In this embodiment, the protective frame 102 includes a number of protective vertical poles 1021, a number of protective crossbars 1022 and a number of fixed bottom poles 1023. The plurality of protective vertical poles 1021 are arranged at intervals, and two adjacent protective vertical poles 1021 pass through several protective horizontal poles. 1022 connection, a fixed bottom pole 1023 is fixed at the bottom of the protective vertical pole 1021. Several protective vertical poles 1021 and several protective cross bars 1022 form several frame openings. The fixed bottom pole 1023 is fixedly connected to the concrete slab 9 through the bottom fixing device 105.

在本实施例中,面内作业防护装置1包括若干片,面内作业防护装置1可以整片安装,整片安装是指面内作业防护装置1中如图11所示的一片在地面上组装完成后整体吊至混凝土板上进行安装,整片安装效率高。需要说明的是,每片的尺寸可以根据具体情况进行选择,若干片的长度尺寸可以相同,也可以不同。In this embodiment, the in-plane work protection device 1 includes several pieces. The in-plane work protection device 1 can be installed as a whole piece. The whole-piece installation means that one piece of the in-plane work protection device 1 as shown in Figure 11 is assembled on the ground. After completion, the whole piece is hoisted to the concrete slab for installation. The whole piece is installed with high efficiency. It should be noted that the size of each piece can be selected according to specific circumstances, and the lengths and dimensions of several pieces can be the same or different.

当然,面内作业防护装置1可以不整片安装,可以一个一个零件的安装,即分件安装,分件安装是指将若干的防护立杆、若干的防护横梁、若干的防护片均吊至混凝土板上,然后在混凝土板9的边沿处一个一个的将其安装。Of course, the in-plane work protection device 1 does not need to be installed as a whole piece, but can be installed one by one, that is, installed in pieces. The piece-by-piece installation refers to lifting a number of protective poles, a number of protective beams, and a number of protective sheets to the concrete. board, and then install them one by one at the edge of the concrete slab 9.

如图17和图18所示,在本实施例中,柱底外模5包括L形工模501、两个支撑件503和两个旋转件502,两个支撑件503设置于L形工模501的底部,两个旋转件502可旋转地设置于L形工模501的顶部。As shown in Figures 17 and 18, in this embodiment, the column bottom outer mold 5 includes an L-shaped mold 501, two supporting members 503 and two rotating members 502. The two supporting members 503 are arranged on the L-shaped mold. At the bottom of the L-shaped mold 501, two rotating members 502 are rotatably arranged on the top of the L-shaped mold 501.

在本实施例中,安装上层框架结构的预制柱4及现浇模具中的柱底外模5的步骤包括:In this embodiment, the steps of installing the prefabricated columns 4 of the upper frame structure and the column bottom outer mold 5 in the cast-in-place mold include:

通过柱作业平台3将柱底外模5搬运至预制柱4的外侧底部;The column bottom outer mold 5 is transported to the outer bottom of the prefabricated column 4 through the column working platform 3;

将柱底外模5的L形工模501贴合至预制柱4的结构面及支撑件503搭至混凝土板9的板面上;Fit the L-shaped mold 501 of the column bottom outer mold 5 to the structural surface of the prefabricated column 4 and the support 503 to the surface of the concrete slab 9;

转动旋转件502时使其卡在预制柱4的两个阳角处;When rotating the rotating member 502, make it stuck at the two external corners of the prefabricated column 4;

将锁定件插入L形工模501的锁定孔5011中锁定旋转件502,以完成柱底外模5的安装。Insert the locking piece into the locking hole 5011 of the L-shaped mold 501 to lock the rotating piece 502 to complete the installation of the outer mold 5 at the bottom of the column.

通过柱作业平台3实现柱底外模5的安装,柱底外模5的安装更简便,也可以保证施工人员的安全。The column bottom outer mold 5 is installed through the column working platform 3, which makes the installation of the column bottom outer mold 5 easier and ensures the safety of construction workers.

具体地,支撑件503和旋转件502均为L形片,锁定件为锁定销,旋转件502通过固定螺栓504固定在L形工模501上。Specifically, the supporting member 503 and the rotating member 502 are both L-shaped pieces, the locking member is a locking pin, and the rotating member 502 is fixed on the L-shaped mold 501 through the fixing bolts 504.

需要说明的是,预制角柱的柱底外模5的安装步骤和预制边柱的柱底外模5的安装步骤均采用上述柱底外模5的安装步骤,即预制角柱的柱底外模5的安装方法和预制边柱的柱底外模5的安装方法相同。It should be noted that the installation steps of the column bottom outer mold 5 of the prefabricated corner columns and the installation steps of the column bottom outer mold 5 of the prefabricated side columns all adopt the above-mentioned installation steps of the column bottom outer mold 5, that is, the column bottom outer mold 5 of the prefabricated corner column. The installation method is the same as the installation method of the column bottom outer mold 5 of the prefabricated side column.

另外,预制边柱的柱底外模5可不通过边柱作业平台辅助施工,具体地,如图19和图20所示,安装柱底外模5的步骤包括:In addition, the column bottom outer formwork 5 of the prefabricated side columns can be constructed without the assistance of the side column working platform. Specifically, as shown in Figures 19 and 20, the steps for installing the column bottom outer formwork 5 include:

将柱底外模5侧放于预制边柱的侧边;Place the outer mold 5 of the column bottom on the side of the prefabricated side column;

翻转柱底外模5使L形工模501靠紧预制边柱的结构面及支撑件503搭至混凝土板9的板面上;Turn over the outer mold 5 at the bottom of the column so that the L-shaped mold 501 is close to the structural surface of the prefabricated side column and the support 503 is placed on the surface of the concrete slab 9;

转动旋转件502时使其卡在预制柱4的两个阳角处;When rotating the rotating member 502, make it stuck at the two external corners of the prefabricated column 4;

将锁定件插入L形工模501的锁定孔5011中锁定旋转件502,以完成柱底外模5的安装。Insert the locking piece into the locking hole 5011 of the L-shaped mold 501 to lock the rotating piece 502 to complete the installation of the outer mold 5 at the bottom of the column.

预制边柱的柱底外模5可在混凝土板9的板面内安装,无需通过边柱作业平台就可以安装,进而提高施工效率。The column bottom outer mold 5 of the prefabricated side column can be installed within the surface of the concrete slab 9 without passing through the side column working platform, thereby improving construction efficiency.

在本实施例中,预制边柱和预制角柱的柱底内模、预制面内柱的柱底模具在钢筋验收完成后,根据实际情况完成安装,与普通施工工艺相同。In this embodiment, the inner column bottom molds of the prefabricated side columns and prefabricated corner columns and the column bottom molds of the prefabricated in-plane columns are installed according to the actual situation after the steel bars are accepted, which is the same as the ordinary construction process.

如图31和图32所示,在本实施例中,拆除所有的现浇模具,以形成上层框架结构的步骤包括:As shown in Figures 31 and 32, in this embodiment, the steps of removing all cast-in-place molds to form the upper frame structure include:

将垂直运输设备与L形工模501连接;Connect the vertical transportation equipment to the L-shaped mold 501;

解除L形工模501和柱底内模的连接;Unlock the connection between the L-shaped mold 501 and the inner mold at the bottom of the column;

将锁定件从锁定孔5011中拔出;Pull out the locking piece from the locking hole 5011;

转动旋转件502使其离开对应的阳角;Rotate the rotating member 502 to move it away from the corresponding sun angle;

将柱底外模5吊至上层框架结构上的混凝土板9上,以完成柱底外模5的拆除。Lift the column bottom outer form 5 to the concrete slab 9 on the upper frame structure to complete the disassembly of the column bottom outer form 5.

通过垂直运输设备吊着L形工模501来拆除柱底外模5,拆除简便,提高模具拆卸效率。The L-shaped mold 501 is hoisted by vertical transportation equipment to dismantle the column bottom outer mold 5, which is easy to dismantle and improves the mold disassembly efficiency.

如图21至图23所示,在本实施例中,现浇模具包括边梁模具8,边梁模具8包括边梁外模801、边梁内模806、对拉螺杆805以及预置螺母803,预置螺母803固定在边梁外模801的外侧上,对拉螺杆805的一端穿过边梁内模806、边梁外模801与预置螺母803螺纹连接;边梁模具8采用在混凝土板9的面内对拉加固的构造,避免施工人员探身至边梁模具8与面内作业防护装置1间完成施工作业,保证施工人员的安全,也可以提高施工效率。As shown in Figures 21 to 23, in this embodiment, the cast-in-place mold includes the side beam mold 8. The side beam mold 8 includes the side beam outer mold 801, the side beam inner mold 806, the pull screw 805 and the preset nut 803. The setting nut 803 is fixed on the outside of the side beam outer mold 801, one end of the pull screw 805 passes through the side beam inner mold 806, and the side beam outer mold 801 is threadedly connected to the preset nut 803; the side beam mold 8 is aligned in the surface of the concrete slab 9 The tension-reinforced structure prevents construction workers from leaning between the side beam mold 8 and the in-plane work protection device 1 to complete construction operations, ensuring the safety of construction workers and improving construction efficiency.

在本实施例中,在混凝土板9上安装现浇模具中除了柱底外模5之外的其余模具的步骤包括:在混凝土板9上组装边梁模具8,将组装完成的边梁模具8吊装至边梁模具安装位置处,以完成边梁模具8的安装。在混凝土板9的面内完成边梁模具8的安装,安装效率高,也可以提高施工安全性。In this embodiment, the steps of installing the rest of the cast-in-place molds on the concrete slab 9 except the column bottom outer mold 5 include: assembling the side beam mold 8 on the concrete slab 9 and placing the assembled side beam mold 8 Lift it to the installation position of the side beam mold to complete the installation of the side beam mold 8. The installation of the side beam mold 8 is completed within the surface of the concrete slab 9, which has high installation efficiency and can also improve construction safety.

在本实施例中,拆除所有的现浇模具,以形成上层框架结构的步骤包括:将垂直运输设备与边梁外模801连接,在边梁内侧拆除对拉螺杆805以及边梁外模801与边梁底模、不同跨度之间的边梁外模801连接的配件,将边梁外模801吊至上层框架结构上的混凝土板9上,以完成边梁外模801的拆除。通过垂直运输设备吊着边梁外模801来拆除边梁外模801,拆除简便,模具拆卸效率高。In this embodiment, the steps of removing all the cast-in-place molds to form the upper frame structure include: connecting the vertical transportation equipment to the side beam outer mold 801, removing the tension screws 805 on the inside of the side beam, and the side beam outer mold 801 and the side beam bottom mold. , accessories for connecting the side beam outer form 801 between different spans, and lift the side beam outer form 801 to the concrete slab 9 on the upper frame structure to complete the disassembly of the side beam outer form 801. The side beam outer mold 801 is lifted by vertical transportation equipment to dismantle the side beam outer mold 801. The disassembly is simple and the mold disassembly efficiency is high.

如图7所示,在本实施例中,现浇模具还包括面内梁模具7,面内梁模具7根据现场需求使用木模、铝模等,均在面内完成,不存在临边作业,按正常施工工艺即可。As shown in Figure 7, in this embodiment, the cast-in-place mold also includes an in-plane beam mold 7. The in-plane beam mold 7 uses wood molds, aluminum molds, etc. according to on-site needs, and is all completed in the plane, without edge work. , just follow normal construction techniques.

如图21和图24至图28所示,在本实施例中,现浇模具包括对现浇模具的外模进行拼接的对接工装11,对接工装11包括:第一固定件1101、第二固定件1102及竖向移动件1103,第一固定件1101适于与一个待拼接模具连接,第一固定件1101上开设有插孔11011;第二固定件1102适于与另一个待拼接模具连接;竖向移动件1103插设于第二固定件1102内,竖向移动件1103包括插块11031,竖向移动件1103的上端适于延伸出待拼接模具以形成操作部,竖向移动件1103适于沿竖直方向移动,以使插块11031插入或移出插孔11011。As shown in Figure 21 and Figure 24 to Figure 28, in this embodiment, the cast-in-place mold includes a docking tool 11 for splicing the outer mold of the cast-in-place mold. The docking tool 11 includes: a first fixing part 1101, a second fixing part 1101 and a second fixing part 1101. Part 1102 and vertical moving part 1103, the first fixing part 1101 is suitable for connecting with a mold to be spliced, and the first fixing part 1101 is provided with an insertion hole 11011; the second fixing part 1102 is suitable for connecting with another mold to be spliced; The vertical moving part 1103 is inserted into the second fixing part 1102. The vertical moving part 1103 includes an insert block 11031. The upper end of the vertical moving part 1103 is suitable for extending out of the mold to be spliced to form an operating part. The vertical moving part 1103 is suitable for Move in the vertical direction to insert or remove the plug 11031 into the jack 11011.

如图24至图28所示,在本实施例中,在混凝土板9上安装现浇模具中除了柱底外模5之外的其余模具的步骤还包括:As shown in Figures 24 to 28, in this embodiment, the step of installing the remaining molds in the cast-in-place mold on the concrete slab 9 except the column bottom outer mold 5 also includes:

将若干个第一固定件1101安装于一个待拼接模具;Install several first fixing parts 1101 on a mold to be spliced;

将若干个第二固定件1102连同竖向移动件1103安装于另一个待拼接模具;Install several second fixing parts 1102 together with the vertical moving parts 1103 on another mold to be spliced;

将组装完成的两个待拼接模具吊装至对应位置,使两个待拼接模具贴紧安装;Lift the assembled two molds to be spliced to the corresponding positions so that the two molds to be spliced are installed closely;

沿竖直方向移动竖向移动件1103,使插块11031插入至插孔11011内;Move the vertical moving member 1103 in the vertical direction to insert the plug 11031 into the plug hole 11011;

将竖向移动件1103的竖向位置锁定,以完成两个待拼接模具的对接。The vertical position of the vertical moving part 1103 is locked to complete the docking of the two molds to be spliced.

在本实施例中,拆除所有的现浇模具,以形成上层框架结构的步骤还包括:In this embodiment, the step of removing all the cast-in-place molds to form the upper frame structure also includes:

解除竖向移动件1103的竖向位置锁定;Release the vertical position lock of the vertical moving member 1103;

沿竖直方向移动竖向移动件1103,使插块11031移出插孔11011,以解除两个待拼接模具的连接。Move the vertical moving member 1103 in the vertical direction to move the insertion block 11031 out of the insertion hole 11011 to release the connection between the two molds to be spliced.

对接工装11利用竖向移动件1103的竖向移动,即可使竖向移动件1103的插块11031与第一固定件1101的插孔11011进行配合,从而便于两个待拼接模具的拆装,并且,将竖向移动件1103的操作部设置于上端,使得对两个待拼接模具的拆装过程不会局限于待拼接模具的外部作业面上,更加简单方便且安全。The docking tool 11 utilizes the vertical movement of the vertical moving part 1103 to match the insertion block 11031 of the vertical moving part 1103 with the socket 11011 of the first fixing part 1101, thereby facilitating the disassembly and assembly of the two molds to be spliced. Moreover, the operating part of the vertical moving part 1103 is arranged at the upper end, so that the disassembly and assembly process of the two molds to be spliced is not limited to the external working surface of the molds to be spliced, making it simpler, more convenient and safer.

在本实施例中,如图26和图28所示,竖向移动件1103绕竖直方向可转动设置。因此,便于使插块11031转动至与插孔11011对应配合,提高对接工装使用的灵活性。In this embodiment, as shown in Figures 26 and 28, the vertical moving member 1103 is rotatably arranged around the vertical direction. Therefore, it is easy to rotate the insert block 11031 to match the socket 11011, thereby improving the flexibility of the docking tool.

值得说明的是,请参阅图26和图27,竖向移动件1103既能够沿竖直方向移动,也可以绕竖直方向转动。It is worth noting that, please refer to Figures 26 and 27, the vertical moving member 1103 can move in the vertical direction and can also rotate around the vertical direction.

需要说明的是,施工人员可通过手持操作部实现对竖向移动件1103的移动或转动。进一步的,操作部可以为图24至图29所示的光杆,也可以在竖向移动件1103的上端设置把手(例如在光杆上设置把手),或者是通过将光杆进行折弯形成。It should be noted that construction workers can move or rotate the vertical moving part 1103 through the hand-held operating part. Furthermore, the operating part may be a polished rod as shown in FIGS. 24 to 29 , or may be provided with a handle on the upper end of the vertical moving member 1103 (for example, a handle is provided on the polished rod), or may be formed by bending the polished rod.

在本实施例中,如图24所示,竖向移动件1103还包括竖直杆11032和连接部11033,竖直杆11032插设于第二固定件1102内,连接部11033的一端与竖直杆11032连接,插块11031设置于连接部11033的另一端处。通过设置竖直杆11032,便于与第二固定件1102进行插接配合;通过设置连接部11033,便于插块11031的安装以及插块11031与插孔11011的对应配合。In this embodiment, as shown in Figure 24, the vertical moving part 1103 also includes a vertical rod 11032 and a connecting part 11033. The vertical rod 11032 is inserted into the second fixing part 1102. One end of the connecting part 11033 is connected to the vertical The rod 11032 is connected, and the inserting block 11031 is provided at the other end of the connecting part 11033. By arranging the vertical rod 11032, it is convenient to plug and fit with the second fixing member 1102; by arranging the connecting part 11033, it is convenient to install the plug-in block 11031 and to facilitate the corresponding cooperation between the plug-in block 11031 and the jack 11011.

值得说明的是,请参阅图28和图29,根据两个待拼接模具所呈的夹角不同,连接部11033呈不同角度进行折弯的板体,可以为钝角、锐角、直角以及平角(图29所示未折弯板体)。It is worth noting that, please refer to Figures 28 and 29. According to the different angles of the two molds to be spliced, the connecting portion 11033 can be bent at different angles, which can be obtuse angles, acute angles, right angles and flat angles (Fig. The plate shown in 29 is not bent).

当然,连接部11033也可以为杆体、管体等结构;可以为圆柱形,也可以为方形。Of course, the connecting portion 11033 can also be a rod, a tube, or other structures; it can be cylindrical or square.

需要说明的是,竖直杆11032的上端形成上述的操作部。It should be noted that the upper end of the vertical rod 11032 forms the above-mentioned operating part.

在本实施例中,如图24至图29所示,连接部11033间隔设置有若干个,每个连接部11033对应设置有一个插块11031,第一固定件1101也设置有若干个,若干个连接部11033与若干个第一固定件1101对应设置。通过将连接部11033和第一固定件1101均设置为若干个,便于若干个插块11031与若干个插孔11011的对应插接,保证两个待拼接模具连接的稳定性。In this embodiment, as shown in FIGS. 24 to 29 , several connecting portions 11033 are provided at intervals, each connecting portion 11033 is provided with a plug-in block 11031 , and several first fixing members 1101 are also provided. The connecting portion 11033 is provided corresponding to the plurality of first fixing members 1101 . By arranging several connecting parts 11033 and several first fixing parts 1101, the corresponding insertion of several plug-in blocks 11031 and several sockets 11011 is facilitated, ensuring the stability of the connection of two molds to be spliced.

值得说明的是,请参阅图24,若干个连接部11033沿竖直杆11032的轴向间隔设置,也即,若干个连接部11033沿竖直方向间隔设置,相应的,请参阅图24至图29所示,若干个第一固定件1101也沿竖直方向间隔设置,以使每个连接部11033上的插块11031均与一个第一固定件1101上的插孔11011对应设置。It is worth noting that, please refer to Figure 24, several connecting parts 11033 are arranged at intervals along the axial direction of the vertical rod 11032, that is, several connecting parts 11033 are arranged at intervals along the vertical direction. Correspondingly, please refer to Figures 24 to 24. As shown in 29, several first fixing members 1101 are also spaced apart in the vertical direction, so that the insertion block 11031 on each connecting part 11033 is arranged corresponding to the socket 11011 on one first fixing member 1101.

需要说明的是,在相关技术中,两个待拼接模具之间通常会采用若干个连接件(销钉、销片或者是螺栓)进行连接,并且,若干个连接件需要逐个进行安装,相应的,在拆除时也需要逐个进行拆除,导致混凝土模具的拆装过程繁琐,耽误施工进度。而在本申请中,通过驱动竖直杆11032运动,即可使若干个连接部11033和若干个插块11031同时运动,以使若干个插块11031同时插入至若干个插孔11011内或同时从若干个插孔11011内移出,提高施工效率。It should be noted that in related technologies, two molds to be spliced are usually connected using several connectors (pins, pins or bolts), and several connectors need to be installed one by one. Correspondingly, During dismantling, they also need to be dismantled one by one, which makes the disassembly and assembly process of concrete molds cumbersome and delays the construction progress. In this application, by driving the vertical rod 11032 to move, several connecting parts 11033 and several plug-in blocks 11031 can be moved simultaneously, so that several plug-in blocks 11031 can be inserted into or removed from several jack holes 11011 at the same time. Several jacks 11011 are moved out to improve construction efficiency.

在本实施例中,如图28所示,连接部11033按照待拼接模具的边带或背楞的位置设置于竖直杆11032上,连接部11033可通过焊接或销接的方式与竖直杆11032连接。In this embodiment, as shown in Figure 28, the connecting portion 11033 is arranged on the vertical rod 11032 according to the position of the side strips or back corrugations of the molds to be spliced. The connecting portion 11033 can be connected to the vertical rod by welding or pinning. 11032 connection.

在本实施例中,如图27所示,插块11031设置于连接部11033的上侧,因此,在进行两个待拼接模具的连接时,使竖直杆11032向上移动,从而使插块11031由下至上插入至插孔11011内实现固定。In this embodiment, as shown in Figure 27, the inserting block 11031 is disposed on the upper side of the connecting part 11033. Therefore, when connecting two molds to be spliced, the vertical rod 11032 is moved upward, so that the inserting block 11031 Insert it into the jack 11011 from bottom to top to achieve fixation.

此时,模板连接装置还包括限位件1104,限位件1104设置于竖向移动件1103上,限位件1104适于固定插块11031和插孔11011的插接位置。当插块11031和插孔11011配合插接后,通过限位件1104将竖向移动件1103的位置固定,保证插块11031稳定的插设于插孔11011内,实现两个待拼接模具的稳定连接。At this time, the template connecting device also includes a limiting member 1104, which is provided on the vertical moving member 1103. The limiting member 1104 is suitable for fixing the insertion position of the plug 11031 and the jack 11011. When the insert block 11031 and the socket 11011 are mated and connected, the position of the vertical moving member 1103 is fixed through the limiter 1104 to ensure that the insert block 11031 is stably inserted into the socket 11011 to achieve the stability of the two molds to be spliced. connect.

在本实施例中,如图24至图29所示,限位件1104包括螺母,螺母与竖向移动件1103螺纹连接,螺母的下侧与第二固定件1102可转动抵接。因此,通过设置螺母,即可将竖向移动件1103在竖直方向的位置进行固定,整体结构简单;进一步的,当插块11031在插入插孔11011过程中受到较大阻力而不便于插入时,可以通过拧紧工具(例如电动扳手)转动螺母,此时可以向竖向移动件1103提供更大的驱动力,从而驱动竖向移动件1103向上移动,驱动方式简单。In this embodiment, as shown in FIGS. 24 to 29 , the limiting member 1104 includes a nut, which is threadedly connected to the vertical moving member 1103 , and the lower side of the nut is rotatably abutted against the second fixing member 1102 . Therefore, by arranging a nut, the vertical moving member 1103 can be fixed in the vertical position, and the overall structure is simple; further, when the plug 11031 encounters a large resistance during the insertion into the jack 11011, it is not easy to insert. , the nut can be rotated by a tightening tool (such as an electric wrench). At this time, greater driving force can be provided to the vertical moving member 1103, thereby driving the vertical moving member 1103 to move upward. The driving method is simple.

具体的,请参阅图24,竖直杆11032的上端设置有螺纹段(图中未示出),螺母螺纹连接于螺纹段上。因此,两个待拼接模具的拼接操作可在待拼接模具的顶部完成,无需在待拼接模具的外部设置操作面。Specifically, please refer to Figure 24. The upper end of the vertical rod 11032 is provided with a threaded section (not shown in the figure), and the nut is threadedly connected to the threaded section. Therefore, the splicing operation of two molds to be spliced can be completed on the top of the molds to be spliced, without the need to provide an operating surface outside the molds to be spliced.

值得说明的是,螺母可以为六角螺母、羊角螺母、带手柄螺母等不同形式。It is worth mentioning that the nuts can be in different forms such as hexagon nuts, claw nuts, nuts with handles, etc.

在本实施例中,如图24所示,插块11031呈上窄下宽的梯形结构,以便于插块11031顺利插入。In this embodiment, as shown in FIG. 24 , the plug-in block 11031 has a trapezoidal structure with a narrow top and a wide bottom, so that the plug-in block 11031 can be inserted smoothly.

当然,在其他可替代的实施方式中,也可以将插块11031设置于连接部11033的下侧,从而,在将两个待拼接模具进行连接时,使竖直杆11032向下移动,从而使插块11031由上至下插入至插孔11011内实现固定。此时,工作人员可以手持操作部驱动竖直杆11032,使插块11031和插孔11011相对应,然后松开操作部,在重力作用下,插块11031即可插入至插孔11011内,并在连接部11033与第一固定件1101的抵接配合下保持稳定。Of course, in other alternative embodiments, the insert block 11031 can also be provided on the lower side of the connecting portion 11033, so that when two molds to be spliced are connected, the vertical rod 11032 moves downward, so that the vertical rod 11032 moves downward. The inserting block 11031 is inserted into the socket 11011 from top to bottom to achieve fixation. At this time, the staff can hold the operating part to drive the vertical rod 11032 to make the inserting block 11031 correspond to the jack 11011, and then release the operating part. Under the action of gravity, the inserting block 11031 can be inserted into the jack 11011, and The connecting portion 11033 remains stable under the abutment and cooperation with the first fixing member 1101 .

在本实施例中,如图24至图29所示,第二固定件1102设置有若干个,若干个第二固定件1102沿竖直方向间隔设置。In this embodiment, as shown in FIGS. 24 to 29 , several second fixing members 1102 are provided, and the plurality of second fixing members 1102 are spaced apart along the vertical direction.

需要说明的是,第二固定件1102的数量可以与连接部11033的数量相同,也可以不同,第一固定件1101的数量、第二固定件1102的数量以及连接部11033的数量可以根据实际需要具体设置。It should be noted that the number of second fixing parts 1102 may be the same as the number of connecting parts 11033, or may be different. The number of first fixing parts 1101, the number of second fixing parts 1102, and the number of connecting parts 11033 may be determined according to actual needs. specific settings.

在本实施例中,如图25至图29所示,第一固定件1101包括第一固定板11012和第一紧固件11013,第一紧固件11013固定第一固定板11012,插孔11011开设于第一固定板11012上。第一固定件1101整体结构简单,便于组装。In this embodiment, as shown in Figures 25 to 29, the first fixing part 1101 includes a first fixing plate 11012 and a first fastener 11013. The first fastener 11013 fixes the first fixing plate 11012, and the insertion hole 11011 Opened on the first fixed plate 11012. The first fixing part 1101 has a simple overall structure and is easy to assemble.

需要说明的是,第一紧固件11013为螺栓,螺栓贯穿第一固定板11012后紧固于一个待拼接模具上。It should be noted that the first fastener 11013 is a bolt, and the bolt penetrates the first fixing plate 11012 and is then fastened to a mold to be spliced.

值得说明的是,当插块11031由下至上插入插孔11011内,并且插块11031和插孔11011完全配合插接时,连接部11033的上侧面与第一固定板11012的下侧面抵接;当插块11031由上至下插入插孔11011内,并且插块11031和插孔11011完全配合插接时,连接部11033的下侧面与第一固定板11012的上侧面抵接。It is worth noting that when the insert block 11031 is inserted into the jack 11011 from bottom to top, and the insert block 11031 and the jack 11011 are completely mated and inserted, the upper side of the connecting portion 11033 abuts the lower side of the first fixing plate 11012; When the insert block 11031 is inserted into the jack 11011 from top to bottom, and the insert block 11031 and the jack 11011 are fully mated and inserted, the lower side of the connecting portion 11033 abuts the upper side of the first fixing plate 11012.

在本实施例中,如图25至图29所示,第一固定件1101还包括定位板11014,定位板11014与第一固定板11012连接,竖向移动件1103与定位板11014可滑动抵接。通过设置定位板11014,保证竖向移动件1103与第一固定件1101配合位置的准确性,便于插块11031与插孔11011进行对应。In this embodiment, as shown in Figures 25 to 29, the first fixing part 1101 also includes a positioning plate 11014. The positioning plate 11014 is connected to the first fixing plate 11012. The vertical moving part 1103 and the positioning plate 11014 can slide and abut. . By providing the positioning plate 11014, the accuracy of the matching position of the vertical moving part 1103 and the first fixing part 1101 is ensured, and the insertion block 11031 and the socket 11011 are facilitated to correspond.

值得说明的是,请参阅图25,定位板11014连接于第一固定板11012的下表面且向下延伸设置。进一步的,请参阅图27和图28,转动竖直杆11032,使连接部11033的内侧面和定位板11014的外侧面相抵接,再向上驱动竖直杆11032运动,即可使插块11031插入至插孔11011内。It is worth mentioning that, please refer to FIG. 25 , the positioning plate 11014 is connected to the lower surface of the first fixing plate 11012 and extends downward. Further, please refer to Figures 27 and 28, rotate the vertical rod 11032 to make the inner side of the connecting portion 11033 contact the outer side of the positioning plate 11014, and then drive the vertical rod 11032 upward to insert the plug 11031. into jack 11011.

需要进一步说明的是,定位板11014的内侧面与待拼接模具的边带或背楞贴合设置。It should be further explained that the inner side of the positioning plate 11014 is arranged to be in close contact with the side strips or back corrugations of the molds to be spliced.

在本实施例中,如图24至图29所示,第二固定件1102包括第二固定板11021和第二紧固件11022,第二紧固件11022固定第二固定板11021,竖向移动件1103插设于第二固定板11021内。第二固定件1102整体结构简单,便于组装。In this embodiment, as shown in Figures 24 to 29, the second fixing part 1102 includes a second fixing plate 11021 and a second fastener 11022. The second fastener 11022 fixes the second fixing plate 11021 and moves vertically. The component 1103 is inserted into the second fixing plate 11021. The second fixing member 1102 has a simple overall structure and is easy to assemble.

需要说明的是,第二紧固件11022为螺栓,螺栓贯穿第二固定板11021后紧固于另一个待拼接模具上。It should be noted that the second fastener 11022 is a bolt, and the bolt penetrates the second fixing plate 11021 and is then fastened to another mold to be spliced.

在本实施例中,如图25至图29所示,两个待拼接模具分别为第一模具21和第二模具22,第一模具21和第二模具22包括工模模板和边带或背楞,第一固定件1101连接于第一模具21的边带或背楞上,第二固定件1102连接于第二模具22的边带或背楞上。In this embodiment, as shown in Figures 25 to 29, the two molds to be spliced are a first mold 21 and a second mold 22 respectively. The first mold 21 and the second mold 22 include a mold template and a side belt or backing. The first fixing part 1101 is connected to the side strip or the back fluting of the first mold 21 , and the second fixing part 1102 is connected to the side strip or the back fluting of the second mold 22 .

在本实施例中,如图24至图29所示,对接工装11还包括压片1105,压片1105的下表面与第一模具21和第二模具22的上侧面抵接。通过设置压片1105,使第一模具21和第二模具22的上侧面平齐,保证两个待拼接模具连接位置的准确性。In this embodiment, as shown in FIGS. 24 to 29 , the docking tool 11 further includes a pressing piece 1105 , and the lower surface of the pressing piece 1105 is in contact with the upper sides of the first mold 21 and the second mold 22 . By setting the pressing piece 1105, the upper sides of the first mold 21 and the second mold 22 are flush, ensuring the accuracy of the connection position of the two molds to be spliced.

在本实施例中,压片1105与第二固定件1102连接。具体的,请参阅图25,压片1105与第二固定板11021连接。进一步的,压片1105与第二固定板11021一体成型设置;当然,压片1105也可以采用焊接等方式与第二固定板11021进行连接。In this embodiment, the pressing piece 1105 is connected to the second fixing member 1102 . Specifically, please refer to Figure 25. The pressing piece 1105 is connected to the second fixing plate 11021. Furthermore, the pressing piece 1105 is integrally formed with the second fixing plate 11021; of course, the pressing piece 1105 can also be connected to the second fixing plate 11021 by welding or other methods.

值得说明的是,请参阅图25至图29所示,压片1105与若干个第二固定件1102中位于最上方的第二固定件1102相连接。It is worth noting that, as shown in FIGS. 25 to 29 , the pressing piece 1105 is connected to the uppermost second fixing part 1102 among the plurality of second fixing parts 1102 .

当然,在其他可替代的实施方式中,压片1105也可以与第一固定件1101连接,例如与第一固定板11012连接;或者是,压片1105也可以单独设置,只需能够使第一模具21和第二模具22的上侧面平齐即可。Of course, in other alternative embodiments, the pressing piece 1105 can also be connected to the first fixing member 1101, such as the first fixing plate 11012; or, the pressing piece 1105 can also be set separately, as long as it can make the first It suffices that the upper sides of the mold 21 and the second mold 22 are flush.

在使用本实施例的模板连接装置连接第一模具21和第二模具22时,首先,如图25所示,将若干个第一固定件1101安装于第一模具21上,将若干个第二固定件1102连同竖向移动件1103安装于第二模具22上;然后,将组装完成的第一模具21和第二模具22吊装至对应位置,使第一模具21和第二模具22贴紧安装;最后,如图26至图28所示,绕竖直方向转动竖直杆11032,使连接部11033与定位板11014相贴合,再驱动竖直杆11032向上移动,使插块11031插入至插孔11011内,当插块11031在插入插孔11011过程中受到较大阻力而不便于插入时,使用电动扳手转动螺母,直至插块11031与插孔11011完全配合,此时,使用螺母将竖直杆11032的竖向位置固定,并且压片1105与第一模具21和第二模具22的上侧面相贴合。When using the template connecting device of this embodiment to connect the first mold 21 and the second mold 22, first, as shown in FIG. The fixing part 1102 and the vertical moving part 1103 are installed on the second mold 22; then, the assembled first mold 21 and the second mold 22 are hoisted to the corresponding positions, so that the first mold 21 and the second mold 22 are installed closely. ; Finally, as shown in Figures 26 to 28, rotate the vertical rod 11032 in the vertical direction to make the connecting portion 11033 fit the positioning plate 11014, and then drive the vertical rod 11032 to move upward to insert the plug 11031 into the plug. In the hole 11011, when the insert block 11031 encounters great resistance during insertion into the jack 11011 and is not easy to insert, use an electric wrench to turn the nut until the insert block 11031 fully matches the jack 11011. At this time, use the nut to push the nut vertically. The vertical position of the rod 11032 is fixed, and the pressing piece 1105 is in contact with the upper sides of the first mold 21 and the second mold 22 .

需要说明的是,第一模具21和第二模具22均为边梁外模801。It should be noted that both the first mold 21 and the second mold 22 are side beam outer molds 801 .

如图33所示,在本实施例中,将面内作业防护装置1安装在下层框架结构的混凝土板9上时,拆除所有的现浇模具,以形成上层框架结构的步骤之后,施工方法还包括:在下层框架结构的混凝土板9上安装临边防护装置12。As shown in Figure 33, in this embodiment, when the in-plane work protection device 1 is installed on the concrete slab 9 of the lower frame structure, all the cast-in-place molds are removed to form the upper frame structure. After the step, the construction method also It includes: installing edge protection device 12 on the concrete slab 9 of the lower frame structure.

面内作业防护装置1拆除倒运前,需在下层框架结构的混凝土板9上的临边位置搭设临边防护装置12,临边防护装置12起到防护的作用。Before the in-plane work protection device 1 is dismantled and transported, an edge protection device 12 needs to be erected at the edge position on the concrete slab 9 of the lower frame structure. The edge protection device 12 plays a protective role.

具体地,临边防护装置12可为钢管防护、普通定型防护等。Specifically, the edge protection device 12 can be steel pipe protection, ordinary shaping protection, etc.

在本实施例中,边梁外模801、柱底外模5拆除时,垂直运输设备可以为楼面起吊设备10、塔吊或汽车吊等。In this embodiment, when the side beam outer mold 801 and the column bottom outer mold 5 are removed, the vertical transportation equipment may be a floor lifting equipment 10, a tower crane or a truck crane, etc.

另外,在其他实施例中,如图35至图38所示,将面内作业防护装置1安装在预制柱4上时,在安装上层框架结构的预制柱4及现浇模具中的柱底外模5的步骤和将面内作业防护装置1安装在预制柱4上的步骤之间,施工方法还包括:在下层框架结构的混凝土板9安装临边防护装置12。In addition, in other embodiments, as shown in Figures 35 to 38, when the in-plane work protection device 1 is installed on the precast column 4, the precast column 4 of the upper frame structure and the column bottom in the cast-in-place mold are installed. Between the step of formwork 5 and the step of installing the in-plane work protection device 1 on the prefabricated column 4, the construction method also includes: installing the edge protection device 12 on the concrete slab 9 of the lower frame structure.

具体地,将面内作业防护装置1安装在预制柱4上的步骤包括:Specifically, the steps of installing the in-plane work protection device 1 on the prefabricated column 4 include:

通过垂直运输设备将面内作业防护装置1吊至预制柱4的防护安装位置处;Lift the in-plane operation protection device 1 to the protection installation position of the prefabricated column 4 through vertical transportation equipment;

通过防护固定架将面内作业防护装置1与预制柱4连接,以完成面内作业防护装置1的安装。The in-plane work protection device 1 is connected to the prefabricated column 4 through a protective fixing frame to complete the installation of the in-plane work protection device 1 .

如图38所示,具体地,防护固定架包括上下设置的上固定架和下固定架,上固定架包括固定连接的上连接架16和上支座17,上连接架16固定在防护框架102上,上支座17固定在预制柱4上,下固定架包括若干防护托架13和若干防护支座14,防护框架102的底部设置于对应的防护托架13,防护托架13设置于对应的防护支座14,防护支座14固定在对应的预制柱4上,此时预制柱4为预制角柱或预制边柱。As shown in Figure 38, specifically, the protective fixing frame includes an upper fixing frame and a lower fixing frame arranged up and down. The upper fixing frame includes an upper connecting frame 16 and an upper support 17 that are fixedly connected. The upper connecting frame 16 is fixed on the protective frame 102. The upper support 17 is fixed on the prefabricated column 4. The lower fixed frame includes a plurality of protective brackets 13 and a plurality of protective supports 14. The bottom of the protective frame 102 is arranged on the corresponding protective bracket 13, and the protective bracket 13 is arranged on the corresponding protective bracket 13. The protective support 14 is fixed on the corresponding prefabricated column 4. At this time, the prefabricated column 4 is a prefabricated corner column or a prefabricated side column.

优选地,防护托架13具有防护托槽,防护支座14具有防护支槽,安装防护固定架时,先将防护支座14通过紧固件固定在对应的预制柱4上,再将防护托架13吊至防护支座14的上方并放置于防护支槽内,然后将面内作业防护装置1吊至防护托架13的上方并放置于防护托槽内,防护框架102和防护托架13之间以及防护托架13和防护支座14之间无需采用紧固件固定,施工更简便。防护托架13和防护支座14均为U形钢等。Preferably, the protection bracket 13 has a protection bracket, and the protection support 14 has a protection support slot. When installing the protection fixing frame, first fix the protection support 14 on the corresponding prefabricated column 4 through fasteners, and then fix the protection support 14 to the corresponding prefabricated column 4 through fasteners. The frame 13 is lifted above the protective support 14 and placed in the protective support slot. Then the in-plane operation protection device 1 is lifted above the protective bracket 13 and placed in the protective bracket. The protective frame 102 and the protective bracket 13 There is no need to use fasteners to fix between the protective bracket 13 and the protective support 14, and the construction is simpler. The protective bracket 13 and the protective support 14 are both made of U-shaped steel or the like.

在本实施例中,安装上层框架结构的预制柱4的步骤包括:通过垂直运输设备将预制柱4吊装,预制柱4吊装到位后,将预制柱4安装在混凝土板9上。In this embodiment, the step of installing the prefabricated columns 4 of the upper frame structure includes: hoisting the prefabricated columns 4 through vertical transportation equipment. After the prefabricated columns 4 are hoisted in place, the prefabricated columns 4 are installed on the concrete slab 9 .

下面对框架结构的一种面内作业施工工艺的具体步骤进行说明:The following is an explanation of the specific steps of an in-plane construction process for frame structures:

第一步:面内作业防护装置1的深化设计The first step: in-depth design of protective device 1 for in-plane operations

根据楼层高度、边梁高度及柱位置,对面内作业防护装置1的尺寸进行深化,以适应相应楼栋主体结构施工;安装柱作业平台3的位置需预留安装空间和对应封闭组件。面内作业防护装置1的结构组成如图8所示,防护长度和高度依实际情况调整。According to the floor height, side beam height and column position, the size of the inner working protection device 1 should be deepened to adapt to the construction of the main structure of the corresponding building; the position of the column installation platform 3 needs to reserve installation space and corresponding closing components. The structural composition of the in-plane work protection device 1 is shown in Figure 8, and the protection length and height are adjusted according to the actual situation.

第二步:面内作业防护装置1的提升安装Step 2: Lift and install the in-plane work protection device 1

将面内作业防护装置1借助塔吊或汽车吊等垂直运输设备吊运至需安装的混凝土板9的板面,通过底部固定装置105及斜拉杆104与混凝土板9的板面连接,地面锚固件107可为锚环1051或预埋螺母等形式;面内作业防护装置1安装最终完成形式如图1所示。The in-plane operation protection device 1 is lifted to the surface of the concrete slab 9 to be installed with the help of vertical transportation equipment such as a tower crane or a truck crane, and is connected to the surface of the concrete slab 9 through the bottom fixing device 105 and the diagonal tie rod 104, and the ground anchor 107 may be in the form of an anchor ring 1051 or an embedded nut; the final installation form of the in-plane operation protection device 1 is shown in Figure 1 .

面内作业防护装置1的开合片1011通过防护连接工装2完成,防护连接工装2的结构组成如图11所示,连接杆202通过固定件201固定于一侧的防护网片上,锁固件203固定于另一侧的防护网片。通过转动连接杆202,可实现网片间的连接锁定和解除锁定。The opening and closing piece 1011 of the in-plane work protective device 1 is completed by the protective connection tool 2. The structural composition of the protective connection tool 2 is shown in Figure 11. The connecting rod 202 is fixed on the protective mesh on one side through the fixing piece 201, and the locking piece 203 The protective mesh fixed on the other side. By rotating the connecting rod 202, the connection between the mesh sheets can be locked and unlocked.

第三步:柱作业平台3的安装倒用Step Three: Installation and Inversion of Column Working Platform 3

借助垂直运输设备将柱作业平台3吊运至相应位置,平台安装位置的防护网片使用可开合的构造,柱作业平台3安装时打开,作业人员手扶柱作业平台3吊装就位,柱作业平台3通过锚环1051等与混凝土板9的板面固定;安装完成后如图2所示。Lift the column work platform 3 to the corresponding position with the help of vertical transportation equipment. The protective mesh at the installation position of the platform uses an openable and closable structure. When the column work platform 3 is installed, it is opened. The operator holds the column work platform 3 and lifts it into place. The working platform 3 is fixed to the surface of the concrete slab 9 through anchor rings 1051 and the like; as shown in Figure 2 after the installation is completed.

柱作业平台3安装期间,可同时进行测量放线、凿毛、插筋处理等工作;柱作业平台3可不全数设置,在不同作业区域周转使用,柱作业平台3拆除后应立即将对应位置可开合的防护网片关闭并连接固定。During the installation of the column work platform 3, work such as measuring and setting out, cutting hair, inserting bars, etc. can be carried out at the same time; not all of the column work platforms 3 can be installed and used in different working areas. After the column work platform 3 is dismantled, the corresponding positions should be immediately removed. The opening and closing protective mesh is closed and connected and fixed.

第四步:预制柱4的吊装Step 4: Hoisting of prefabricated column 4

柱作业平台3安装完毕经过验收后可进行预制柱4的吊装,预制柱4吊装前,完成相应套筒部件预安装;预制柱4的纵向钢筋使用机械连接的,需借助柱作业平台3完成,作业人员通过柱作业平台3提供的工作面完成外部钢筋连接操作。预制柱4安装完成后,如图3所示。After the column working platform 3 is installed and accepted, the precast column 4 can be hoisted. Before the precast column 4 is hoisted, the pre-installation of the corresponding sleeve components must be completed; if the longitudinal steel bars of the precast column 4 are mechanically connected, it needs to be completed with the help of the column working platform 3. The operator completes the external steel bar connection operation through the working surface provided by the column working platform 3. After the prefabricated column 4 is installed, it is shown in Figure 3.

第五步:预制柱4的柱底外模的安装Step 5: Installation of the column bottom outer mold of prefabricated column 4

依靠柱作业平台3,将柱底外模5搬运至预制柱4的外侧底部,调整柱底外模5的L形工模501位置使其贴合预制柱4的结构面、柱底外模5的底部的支撑件503搭至混凝土板9的板面。转动柱底外模5的顶部的旋转件502,使其抱住预制柱4的两侧边的阳角,拧紧固定螺栓504,并将锁定销插入锁定孔5011。柱底外模5的结构形式如图17所示,柱底外模5固定完成后工况见图4。Relying on the column work platform 3, transport the column bottom outer mold 5 to the outer bottom of the prefabricated column 4, adjust the position of the L-shaped tool mold 501 of the column bottom outer mold 5 so that it fits the structural surface of the prefabricated column 4 and the column bottom outer mold 5 The bottom support member 503 is placed on the surface of the concrete slab 9 . Rotate the rotating member 502 on the top of the column bottom outer mold 5 so that it hugs the external corners of both sides of the prefabricated column 4, tighten the fixing bolts 504, and insert the locking pin into the locking hole 5011. The structural form of the column bottom outer mold 5 is shown in Figure 17. The working condition after the column bottom outer mold 5 is fixed is shown in Figure 4.

柱底外模5固定完成后可将柱作业平台3吊起、转运至下处作业点(如图6所示);柱作业平台3拆除后开合片1011复位,使用防护连接工装2将两侧网片连接固定。After the outer mold 5 at the column bottom is fixed, the column working platform 3 can be lifted and transferred to the lower working point (as shown in Figure 6); after the column working platform 3 is removed, the opening and closing piece 1011 is reset, and the protective connection tool 2 is used to connect the two The side mesh panels are connected and fixed.

预制边柱的柱底外模5的安装可不通过柱作业平台3辅助施工,将柱底外模5侧放于预制边柱的侧边,翻转柱底外模5使其靠紧预制柱4的结构面、柱底外模5的支撑件503搭至混凝土板9的板面。转动柱底外模5的顶部的旋转件502,使其抱住预制柱4的两侧边的阳角,拧紧固定螺栓,并将锁定销插入锁定孔5011,安装过程如图19和图20所示。The column bottom outer mold 5 of the prefabricated side columns can be installed without the assistance of the column work platform 3. Place the column bottom outer mold 5 sideways on the side of the prefabricated side column, and flip the column bottom outer mold 5 so that it is close to the prefabricated column 4. The support members 503 of the structural surface and column bottom outer mold 5 are placed on the surface of the concrete slab 9 . Rotate the rotating part 502 on the top of the column bottom outer mold 5 so that it hugs the external corners of both sides of the prefabricated column 4, tighten the fixing bolts, and insert the locking pin into the locking hole 5011. The installation process is as shown in Figure 19 and Figure 20 Show.

预制边柱和预制角柱的柱底模具的柱底内模、面内柱底模具在钢筋验收完成后,根据实际情况完成,与普通施工工艺相同。其中,预制边柱和预制角柱的柱底模具包括柱底外模5和柱底内模。The inner mold of the column base and the in-plane column base mold of the prefabricated side columns and prefabricated corner columns will be completed according to the actual situation after the acceptance of the steel bars, and are the same as ordinary construction techniques. Among them, the column bottom molds of prefabricated side columns and prefabricated corner columns include column bottom outer molds 5 and column bottom inner molds.

第六步:边梁模具的吊装Step Six: Lifting of Side Beam Mold

边梁模具8由定制工模组件在混凝土板的板面组拼完成,借助塔吊或汽车吊等垂直运输设备整体吊装;吊装完成后如图7和21所示。The side beam mold 8 is assembled by custom mold components on the surface of the concrete slab, and is hoisted as a whole with the help of vertical transportation equipment such as tower cranes or truck cranes; after the hoisting is completed, it is shown in Figures 7 and 21.

边梁模具使用在面内对拉加固的构造,避免探身至边梁模具8与面内作业防护装置1间完成施工作业;边梁模具的边梁外模801上预装预置螺母803,配合一端焊接螺母的对拉螺杆805可达到作业面内拆装螺杆的目的,如图16和图17所示。The side beam mold uses an in-plane tensile reinforcement structure to avoid leaning between the side beam mold 8 and the in-plane work protection device 1 to complete the construction work; the side beam outer mold 801 of the side beam mold is pre-installed with a preset nut 803, which is welded with one end The nut's pulling screw 805 can achieve the purpose of disassembling and assembling the screw in the working surface, as shown in Figures 16 and 17.

边梁模具8可包含梁柱节点位置工模统一吊装,边梁外模801对接可使用对接工装11完成,对接工装11的结构形式如图24至29所示。The side beam mold 8 can include the beam and column node positions and the molds can be hoisted in a unified manner. The docking of the side beam outer mold 801 can be completed using the docking tool 11. The structural form of the docking tool 11 is shown in Figures 24 to 29.

面内梁模具7根据现场需求使用木模、铝模等,均在面内完成,不存在临边作业,按正常施工工艺即可。The in-plane beam mold 7 uses wood molds, aluminum molds, etc. according to on-site requirements, and is completed in-plane. There is no edge work, and normal construction techniques can be followed.

第七步:钢筋及混凝土作业Step 7: Steel and concrete work

梁钢筋6和板钢筋绑扎均在面内作业防护装置1的保护下完成,工艺与普通现浇施工一致;板钢筋施工阶段完成预埋件1501等预埋构件的安装。The beam steel bars 6 and plate steel bar binding are all completed under the protection of the in-plane work protection device 1, and the process is consistent with ordinary cast-in-situ construction; the installation of embedded components such as embedded parts 1501 is completed during the plate steel bar construction stage.

混凝土浇筑在面内作业防护装置1的保护下完成,工艺与普通现浇施工一致。混凝土浇筑完成后情况见图8。Concrete pouring is completed under the protection of the in-plane operation protection device 1, and the process is consistent with ordinary cast-in-place construction. The situation after the concrete pouring is completed is shown in Figure 8.

第八步:边梁模具的拆除Step 8: Removal of the side beam mold

混凝土浇筑完成达到可拆模强度后进行外模具拆除,外模具主要包含边梁外模801及柱底外模5。After the concrete pouring is completed and reaches the removable form strength, the outer mold is removed. The outer mold mainly includes the edge beam outer mold 801 and the column bottom outer mold 5.

将楼面起吊设备10吊运至浇筑完成的混凝土板9的板面上,边梁外模801拆除需两台楼面起吊设备10配合完成;楼面起吊设备10安置于要拆除的边梁外模801两侧,楼面起吊设备10的挂钩与边梁外模801连接,在边梁内侧拆除对拉螺杆805,随后将边梁的边梁外模801的对接工装11、与边梁底模连接的销钉销片等连接配件拆除,如边梁外模801与边梁的结构面粘贴较紧,可使用撬棍辅助边梁外模801脱离混凝土。Lift the floor lifting equipment 10 to the surface of the poured concrete slab 9. The removal of the side beam outer form 801 requires the cooperation of two floor lifting equipment 10; the floor lifting equipment 10 is placed on both sides of the side beam outer form 801 to be removed. , the hook of the floor lifting equipment 10 is connected to the side beam outer mold 801, remove the pull screw 805 on the inside of the side beam, and then connect the docking tooling 11 of the side beam outer mold 801, the pin pins and other connecting accessories connected to the side beam bottom mold. During disassembly, if the edge beam outer mold 801 is tightly adhered to the structural surface of the edge beam, a crowbar can be used to assist the edge beam outer mold 801 to separate from the concrete.

边梁外模801脱离后,启动楼面起吊设备10,将边梁外模801由面内作业防护装置与混凝土结构之间空隙提升至混凝土板9的板面以上,推动楼面起吊设备10将外模具转移至混凝土板9的板面内部,由作业人员将外模具清理后集中码放。拆除工况如图9、图10和图30。After the side beam outer form 801 is detached, the floor lifting equipment 10 is started to lift the side beam outer form 801 from the gap between the in-plane work protection device and the concrete structure to above the surface of the concrete slab 9, and the floor lifting equipment 10 is pushed to transfer the outer mold to Inside the concrete slab 9, the workers clean the outer molds and stack them together. The dismantling conditions are shown in Figure 9, Figure 10 and Figure 30.

边梁的边梁内模806在边梁外模801拆除时可同步拆除,梁底模及支撑体系需结构强度达到拆模要求后再完成拆除工作。The side beam inner mold 806 of the side beam can be dismantled simultaneously when the side beam outer mold 801 is removed. The beam bottom mold and support system must have structural strength that meets the mold removal requirements before completing the disassembly work.

第九步:柱底外模5的拆除Step 9: Removal of the outer mold 5 at the bottom of the column

将楼面起吊设备10移动至角柱位置,楼面起吊设备10的挂钩与柱底外模5的L形工模501连接,柱底外模5不平衡时可使用吊索辅助;将L形工模501与柱底内模连接的配件拆除,随后将L形工模501的顶部的旋转件502处的锁定销移除,转动旋转件502至松动状态,如柱底外模5与柱的结构面粘贴较紧,可使用撬棍辅助柱底外模5脱离混凝土面。Move the floor lifting equipment 10 to the corner column position, and connect the hook of the floor lifting equipment 10 with the L-shaped mold 501 of the column bottom outer mold 5. When the column bottom outer mold 5 is unbalanced, you can use a sling to assist; Remove the accessories connecting the mold 501 and the inner mold at the bottom of the column. Then remove the locking pin at the rotating part 502 at the top of the L-shaped mold 501, and rotate the rotating part 502 to a loose state, such as the structure of the outer mold 5 at the bottom of the column and the column. If the surface is tightly adhered, you can use a crowbar to assist the outer mold 5 at the bottom of the column to separate from the concrete surface.

柱底外模5脱离后,启动楼面起吊设备10,将柱底外模5由面内作业防护装置1与混凝土结构之间空隙提升至混凝土板9的板面以上,推动楼面起吊设备10将柱底外模5转移至混凝土板9的板面内部,由作业人员将柱底外模5清理后集中码放。拆除工况如图31和图32。After the outer formwork 5 at the column bottom is detached, start the floor lifting equipment 10, lift the outer formwork 5 at the column bottom from the gap between the in-plane work protection device 1 and the concrete structure to above the surface of the concrete slab 9, and push the floor lifting equipment 10 The column bottom outer mold 5 is transferred to the inside of the concrete slab 9, and the operator cleans the column bottom outer mold 5 and then stacks them together. The dismantling conditions are shown in Figure 31 and Figure 32.

第十步:施工层临边防护装置12的搭设Step 10: Erection of construction layer edge protection device 12

面内作业防护装置1拆除倒运前,需在混凝土结构的临边位置搭设临边防护装置12,临边防护装置12的形式可为钢管防护、普通定型防护等。搭设完成后如图33所示。Before the in-plane operation protection device 1 is dismantled and transported, an edge protection device 12 needs to be erected at the edge position of the concrete structure. The edge protection device 12 can be in the form of steel pipe protection, ordinary shaping protection, etc. After the installation is completed, it is shown in Figure 33.

临边防护装置12搭设完成、现浇模具拆除完成后,根据现场进度进行第二步面内作业防护装置1的提升安装工作,第二至第十步每层循环作业。防护提升完成后工况如图34所示。After the edge protection device 12 is erected and the cast-in-place mold is dismantled, the second step of lifting and installation of the in-plane operation protection device 1 is carried out according to the on-site progress, and the second to tenth steps are cyclically operated on each layer. The working conditions after the protection lifting is completed are shown in Figure 34.

上述施工工艺的施工总体流程为:面内作业防护装置1的提升安装→柱作业平台3的安装倒用→预制柱4的安装→预制柱4的柱底外模的安装→支撑体系搭设→边梁模具的吊装→面内梁及楼板模具的安装→梁板钢筋绑扎的安装→预埋件1501等预埋构件的安装→现浇混凝土的浇筑→现浇模具的拆除;上述流程每层循环。The overall construction process of the above-mentioned construction technology is: lifting and installing the in-plane work protection device 1→installing the column working platform 3→installing the prefabricated column 4→installing the column bottom outer mold of the prefabricated column 4→setting up the support system→edge Hoisting of beam mold → Installation of in-plane beam and floor mold → Installation of beam and plate steel bar binding → Installation of embedded components such as embedded parts 1501 → Pouring of cast-in-place concrete → Dismantling of cast-in-place mold; the above process is cycled on each floor.

框架结构的竖向结构使用预制构件,规避在竖向施工过程中使用大量模具,预制柱的纵筋连接等必须在外部完成的工序,使用作业平台辅助完成;柱底及柱顶节点使用与面内作业匹配的定制工模,模具安拆均在作业面内完成;边梁使用工模整体吊装、分片拆除,使其不依靠外部作业面也可完成安拆作业。在上述工艺整体配合下,简化外部防护,使用定制的面内作业定型防护栏杆完成作业过程中的临边防护。The vertical structure of the frame structure uses prefabricated components to avoid the use of a large number of molds during the vertical construction process. The longitudinal reinforcement connection of prefabricated columns and other processes that must be completed externally are completed using a work platform to assist; the nodes at the bottom and top of the columns are used with the surface. Customized molds are used for internal operations, and the mold installation and disassembly are all completed within the working surface; the side beams are hoisted as a whole and dismantled in pieces using the mold, so that installation and dismantling operations can be completed without relying on the external working surface. With the overall cooperation of the above-mentioned processes, external protection is simplified, and customized in-plane work-shaped protective railings are used to complete edge protection during the operation.

通过上述面内作业施工方法,可在无外部脚手架的条件下完成框架主体结构施工,可简化外防护设施,保证防护效果的同时使防护轻量化、简单化,降低防护设施的成本投入;可加快防护设施安装、拆除工效;可在无外部作业面条件下完成模具安拆作业。通过上述描述的各类工装、模具,达到面内施工的目的,有效的解决了如何在不依靠外部作业面的条件下完成主体结构施工的、如何加快防护设施安装拆除工效、如何在无外部作业面条件下完成模具安拆作业以及如何简化外防护设施使其在满足防护需求的前提下做到尽量轻量化、简单化的问题。Through the above-mentioned in-plane construction method, the construction of the main structure of the frame can be completed without external scaffolding, which can simplify the external protective facilities, ensure the protective effect while making the protection lightweight and simple, reducing the cost of protective facilities; it can speed up The installation and removal of protective facilities are efficient; the mold installation and removal operations can be completed without an external working surface. Through the various types of tooling and molds described above, the purpose of in-plane construction is achieved, which effectively solves how to complete the construction of the main structure without relying on external working surfaces, how to speed up the installation and removal of protective facilities, and how to complete the construction without external work. Complete the mold installation and disassembly operations under surface conditions and how to simplify the external protection facilities to make them as lightweight and simple as possible while meeting the protection requirements.

需要说明的是,楼面起吊设备10可使用塔吊、汽车吊等垂直运输设备替代。It should be noted that the floor lifting equipment 10 can be replaced by vertical transportation equipment such as tower cranes and truck cranes.

另外,在其他可替代的实施方式中,面内作业防护装置1也可附着在预制柱4上,防护高度根据楼层高度调整,构成方式如图35至图38。该替代方式的前提是预制柱4与混凝土板9稳固连接,可承载防护荷载;该替代方式的施工总体流程为:测量放线→柱作业平台3的安装倒用→预制柱4的安装→预制柱4的柱底外模的安装→临边防护装置的搭设→面内作业防护装置1的安装→支撑体系搭设→边梁模具的整体吊装→面内梁及楼板模具的安装→梁板钢筋绑扎的安装→预埋件1501等预埋构件的安装→现浇混凝土的浇筑→现浇模具的拆除;上述施工流程每层循环,该替代方式的施工工艺与上述面内作业施工方法类似,仅面内作业防护装置1的附着方式及倒运安装时间不同。In addition, in other alternative embodiments, the in-plane work protection device 1 can also be attached to the prefabricated column 4, and the protection height is adjusted according to the floor height. The structure is shown in Figures 35 to 38. The premise of this alternative method is that the precast column 4 is firmly connected to the concrete slab 9 and can bear the protective load; the overall construction process of this alternative method is: measurement and setting → installation and installation of the column working platform 3 → installation of the precast column 4 → prefabrication Installation of the outer formwork at the bottom of column 4→Erection of the edge protection device→Installation of the in-plane operation protection device 1→Erection of the support system→Integral hoisting of the edge beam mold→Installation of the in-plane beam and floor mold→Beam and plate steel bar binding Installation→Installation of embedded components such as embedded parts 1501→Pouring of cast-in-place concrete→Removal of cast-in-place molds; the above construction process is cycled at each layer. The construction process of this alternative method is similar to the above-mentioned in-plane construction method, only the surface The attachment method and installation time of the internal work protection device 1 are different.

需要说明的是,在相关技术中,框架结构施工需外部落地脚手架、悬挑架或爬架辅助,在外部作业面完成部分主体结构施工作业,施工局限性大。而本发明通过使用预制构件、工装、模具及配套的施工工艺,可以在不依赖外部脚手架作业面的情况下,完成框架结构的全部主体结构施工作业。It should be noted that in related technologies, the construction of frame structures requires the assistance of external landing scaffolds, cantilever frames or climbing frames, and part of the main structure construction operations are completed on the external working surface, which has great construction limitations. By using prefabricated components, tooling, molds and supporting construction techniques, the present invention can complete all main structure construction operations of the frame structure without relying on external scaffolding working surfaces.

在相关技术中,外部脚手架搭设全部人工完成,架体安拆本身施工量大、风险大。而发明的框架结构施工阶段外部无需搭设脚手架,防护整体提升重复使用,安拆风险小。In related technologies, the erection of external scaffolding is all done manually, and the installation and disassembly of the scaffolding itself involves a large amount of construction work and high risks. However, the invented frame structure does not require external scaffolding during the construction phase, and the overall protection can be improved and reused, so the risk of installation and dismantling is small.

虽然结合附图描述了本发明的实施例,但是本领域技术人员可以在不脱离本发明的精神和范围的情况下做出各种修改和变型,这样的修改和变型均落入由所附权利要求所限定的范围之内。Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art can make various modifications and variations without departing from the spirit and scope of the invention, and such modifications and variations fall within the scope of the appended rights. within the scope of the requirements.

Claims (12)

1. The construction method of the frame structure is characterized by comprising the following steps of:
installing a column work platform (3) at a platform installation position on a concrete slab (9) of the lower frame structure;
A prefabricated column (4) of an upper layer frame structure and a column bottom outer mold (5) in a cast-in-situ mold are installed;
installing the rest of the cast-in-situ moulds except the bottom outer mould (5) on the concrete slab (9);
pouring concrete in the cast-in-situ area;
removing all cast-in-situ molds to form the upper layer frame structure;
repeating the steps until the construction of the whole frame structure is completed;
wherein, before the step of installing the column work platform (3) at a platform installation position on the concrete slab (9) of the lower frame structure, the construction method further comprises: mounting an in-plane operation protection device (1) on a concrete slab (9) of the lower frame structure;
or, between the step of installing a prefabricated column (4) of an upper frame structure and a column bottom external mold (5) in a cast-in-situ mold and the step of installing the rest of the cast-in-situ mold except for the column bottom external mold (5) on the concrete slab (9), the construction method further comprises: an in-plane work protection device (1) is mounted on the prefabricated column (4).
2. The construction method according to claim 1, wherein,
the in-plane work protection device (1) comprises: the protection frame (102) is provided with a plurality of frame openings, the plurality of protection sheets (101) are arranged in the corresponding frame openings, the plurality of protection sheets (101) form an opening and closing sheet (1011) and a fixing sheet (1012), the opening and closing sheet (1011) is arranged corresponding to the mounting position of the platform, the opening and closing sheet (1011) is provided with an opening state for opening the corresponding frame openings and a closing state for closing the corresponding frame openings, and when the column operation platform (3) is mounted, the opening and closing sheet (1011) is in the opening state;
The step of installing the column work platform (3) at a platform installation location on a concrete slab (9) of the underlying frame structure comprises:
hoisting the column work platform (3) to a position close to the platform mounting position by vertical transport equipment;
opening an opening/closing sheet (1011) of the in-plane operation protection device (1);
and hoisting the column working platform (3) in place and fixing the column working platform on the concrete slab (9) to finish the installation of the column working platform (3).
3. The construction method according to claim 2, wherein one side of the opening and closing piece (1011) is hinged on the protective frame (102), the opening and closing piece (1011) and the adjacent protective piece (101) thereof are connected by a protective connection tool (2), the protective connection tool (2) has a locking state and an unlocking state, when the protective connection tool (2) is in the locking state, the protective connection tool (2) locks the opening and closing piece (1011) and the adjacent protective piece (101) thereof together, and the opening and closing piece (1011) is in a closed state; when the protection connection tool (2) is in the unlocking state, the opening and closing piece (1011) can be opened.
4. A construction method according to claim 3, wherein the protective connection tool (2) comprises a fixing member (201), a locking member (203) and a connecting rod (202), the fixing member (201) is fixed on one of the opening and closing sheet (1011) and the adjacent protective sheet (101), the locking member (203) is fixed on the other of the opening and closing sheet (1011) and the adjacent protective sheet (101), the connecting rod (202) is movably arranged on the fixing member (201), and the connecting rod (202) can be locked on the locking member (203) or unlocked from the locking member (203).
5. A construction method according to any one of claims 1 to 4, wherein the step of mounting an in-plane work guard (1) on a concrete slab (9) of the underlying frame structure comprises:
lifting the in-plane operation protection device (1) to the position of the concrete slab (9) through vertical conveying equipment;
the in-plane operation protection device (1) is connected with a ground anchor (107) on the concrete slab (9) through a protection fixing device so as to complete the installation of the in-plane operation protection device (1).
6. The construction method according to any one of claims 1 to 4, wherein the column bottom outer mold (5) includes an L-shaped work mold (501), two supporting members (503), and two rotating members (502), the two supporting members (503) are provided at the bottom of the L-shaped work mold (501), the two rotating members (502) are rotatably provided at the top of the L-shaped work mold (501),
the steps of installing the prefabricated column (4) of the upper layer frame structure and the column bottom outer mold (5) in the cast-in-situ mold comprise the following steps:
carrying the column bottom outer mold (5) to the outer side bottom of the prefabricated column (4) through the column operation platform (3);
attaching an L-shaped working die (501) of the column bottom outer die (5) to the structural surface of the prefabricated column (4) and the supporting piece (503) to the plate surface of the concrete plate (9);
The rotating piece (502) is clamped at two external corners of the prefabricated column (4) when being rotated;
a locking member is inserted into a locking hole (5011) of the L-shaped working mold (501) to lock the rotating member (502) so as to complete the installation of the column bottom outer mold (5).
7. The construction method according to any one of claims 1 to 4, wherein the column bottom outer mold (5) comprises an L-shaped work mold (501), two supporting members (503) and two rotating members (502), the two supporting members (503) are provided at the bottom of the L-shaped work mold (501), the two rotating members (502) are rotatably provided at the top of the L-shaped work mold (501), the prefabricated column (4) comprises prefabricated side columns,
the steps of installing the prefabricated column (4) of the upper layer frame structure and the column bottom outer mold (5) in the cast-in-situ mold comprise the following steps:
placing the column bottom outer mold (5) on the side of the prefabricated side column;
turning the column bottom outer mold (5) to enable the L-shaped working mold (501) to lean against the structural surface of the prefabricated side column and the supporting piece (503) to be lapped on the surface of the concrete slab (9);
the rotating piece (502) is clamped at two external corners of the prefabricated column (4) when being rotated;
a locking member is inserted into a locking hole (5011) of the L-shaped working mold (501) to lock the rotating member (502) so as to complete the installation of the column bottom outer mold (5).
8. The method of claim 7, wherein the step of removing all of the cast-in-place molds to form the upper frame structure comprises:
connecting a vertical transport device with the L-shaped work die (501);
releasing the connection between the L-shaped working die (501) and the column bottom internal die;
pulling the locking piece out of the locking hole (5011);
rotating the rotating member (502) away from the corresponding external corner;
and (3) hanging the column bottom outer mold (5) onto a concrete slab (9) on the upper frame structure to finish the dismantling of the column bottom outer mold (5).
9. The construction method according to any one of claims 1 to 4, wherein,
the cast-in-situ mold comprises an edge beam mold (8), wherein the edge beam mold (8) comprises an edge beam outer mold (801), an edge beam inner mold (806), a counter-pulling screw rod (805) and a preset nut (803), the preset nut (803) is fixed on the outer side of the edge beam outer mold (801), and one end of the counter-pulling screw rod (805) penetrates through the edge beam inner mold (806) and is in threaded connection with the preset nut (803);
the step of installing the remaining molds of the cast-in-place mold excluding the bottom outer mold (5) on the concrete slab (9) includes:
Assembling the boundary beam mould (8) on the concrete slab (9), and hoisting the assembled boundary beam mould (8) to a boundary beam mould mounting position to finish the mounting of the boundary beam mould (8);
the step of removing all of the cast-in-place molds to form the upper layer frame structure includes:
and connecting vertical transportation equipment with the side beam external mold (801), dismantling the opposite-pulling screw rod (805) at the inner side of the side beam, and hanging the side beam external mold (801) onto a concrete slab (9) on the upper frame structure so as to finish dismantling the side beam external mold (801).
10. The construction method according to any one of claims 1 to 4, wherein the cast-in-place mold includes a butt joint tool (11) for splicing an outer mold of the cast-in-place mold, the butt joint tool (11) including:
the first fixing piece (1101) is suitable for being connected with a die to be spliced, and an inserting hole (11011) is formed in the first fixing piece (1101);
a second fixing piece (1102) suitable for being connected with another die to be spliced;
the vertical moving piece (1103) is inserted into the second fixing piece (1102), the vertical moving piece (1103) comprises an insertion block (11031), the upper end of the vertical moving piece (1103) is suitable for extending out of the die to be spliced to form an operation part, and the vertical moving piece (1103) is suitable for moving along the vertical direction so that the insertion block (11031) is inserted into or removed from the insertion hole (11011);
The step of installing the remaining ones of the cast-in-place molds, excluding the bottom outer mold (5), on the concrete slab (9) further comprises:
installing a plurality of first fixing pieces (1101) on a die to be spliced;
a plurality of second fixing pieces (1102) and vertical moving pieces (1103) are arranged on another die to be spliced;
hoisting the two assembled dies to be spliced to corresponding positions, so that the two dies to be spliced are tightly attached;
moving the vertical moving member (1103) in a vertical direction so that the insertion block (11031) is inserted into the insertion hole (11011);
locking the vertical position of the vertical moving piece (1103) to finish the butt joint of the two dies to be spliced;
the step of removing all of the cast-in-place molds to form the upper layer frame structure further comprises:
releasing the vertical position lock of the vertical mover (1103);
and moving a vertical moving piece (1103) along the vertical direction to enable the inserting block (11031) to move out of the inserting hole (11011) so as to release the connection of the two dies to be spliced.
11. The construction method according to any one of claims 1 to 4, wherein after the step of removing all the cast-in-place molds to form the upper layer frame structure when the in-plane work guard (1) is installed on the concrete slab (9) of the lower layer frame structure, the construction method further comprises: installing a limb protection device (12) on the concrete slab (9) of the lower frame structure;
Or,
when the in-plane operation protection device (1) is installed on the prefabricated column (4), the construction method further comprises the following steps between the step of installing the prefabricated column (4) of an upper frame structure and a column bottom outer mold (5) in a cast-in-situ mold and the step of installing the in-plane operation protection device (1) on the prefabricated column (4): and installing a limb protection device (12) on the concrete slab (9) of the lower frame structure.
12. The construction method according to any one of claims 1 to 4, wherein the step of mounting an in-plane work guard (1) on the prefabricated column (4) comprises:
hoisting the in-plane operation protection device (1) to a protection installation position of the prefabricated column (4) through vertical transportation equipment;
the in-plane operation protection device (1) is connected with the prefabricated column (4) through a protection fixing frame so as to finish the installation of the in-plane operation protection device (1).
CN202310762701.8A 2023-06-26 2023-06-26 Construction method of frame structure Pending CN117027412A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310762701.8A CN117027412A (en) 2023-06-26 2023-06-26 Construction method of frame structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310762701.8A CN117027412A (en) 2023-06-26 2023-06-26 Construction method of frame structure

Publications (1)

Publication Number Publication Date
CN117027412A true CN117027412A (en) 2023-11-10

Family

ID=88643706

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310762701.8A Pending CN117027412A (en) 2023-06-26 2023-06-26 Construction method of frame structure

Country Status (1)

Country Link
CN (1) CN117027412A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI848863B (en) * 2023-11-29 2024-07-11 潤弘精密工程事業股份有限公司 Architecture structure, sleeve structure, and architecture method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09235880A (en) * 1996-03-04 1997-09-09 Daisue Kensetsu Kk Pillar positioning jig for pillar system formwork, auxiliary formwork and construction method
CN110644664A (en) * 2019-09-24 2020-01-03 孔瑞清 Fabricated building construction method and laminated slab construction supporting system
CN211366665U (en) * 2019-12-23 2020-08-28 山东开拓建设有限公司 Assembled interlayer protection device of construction elevator
CN113605666A (en) * 2021-09-03 2021-11-05 耀华建设管理有限公司 Face supplementary construction platform of limit structure post
CN116290345A (en) * 2023-04-19 2023-06-23 中亿丰建设集团股份有限公司 Prefabricated assembly frame structure and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09235880A (en) * 1996-03-04 1997-09-09 Daisue Kensetsu Kk Pillar positioning jig for pillar system formwork, auxiliary formwork and construction method
CN110644664A (en) * 2019-09-24 2020-01-03 孔瑞清 Fabricated building construction method and laminated slab construction supporting system
CN211366665U (en) * 2019-12-23 2020-08-28 山东开拓建设有限公司 Assembled interlayer protection device of construction elevator
CN113605666A (en) * 2021-09-03 2021-11-05 耀华建设管理有限公司 Face supplementary construction platform of limit structure post
CN116290345A (en) * 2023-04-19 2023-06-23 中亿丰建设集团股份有限公司 Prefabricated assembly frame structure and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI848863B (en) * 2023-11-29 2024-07-11 潤弘精密工程事業股份有限公司 Architecture structure, sleeve structure, and architecture method

Similar Documents

Publication Publication Date Title
WO2013185277A1 (en) Constructing method for concrete cylinder of construction steel bar of high-rise steel structure
CN110805257A (en) Flower basket overhanging type section steel bearing beam structure and construction method
CN110145124A (en) A reinforcement tool and its construction method for controlling the quality of horizontal stubble of shear walls
CN114508231B (en) Quick combination construction method for I-steel component
JP3196043B2 (en) Construction method of stairs and staircase, construction method of stairs, and stair members
CN117027412A (en) Construction method of frame structure
CN210396134U (en) Reinforcing tool for controlling horizontal joint quality of shear wall
CN110735530A (en) external wall steel formwork and internal wall aluminum formwork combination system and operation method thereof
CN110259087A (en) Scaffold support structure and scaffold support system
CN110578338A (en) An integrally movable aluminum alloy formwork system and operation method
CN103243908B (en) Slab form system and building construction build method
US20090121373A1 (en) Method and Apparatus for Construction
CN113719116A (en) Laminated floor slab construction method based on aluminum alloy formwork support
CN210025768U (en) A operation platform system for caisson template installation
JP3531111B2 (en) Apparatus and method for constructing tower-like structure
CN113216587A (en) High-rise building outer wall construction operation platform fixing structure and construction method thereof
CN111561071A (en) A kind of prefabricated shear wall connecting device and installation method
CN110306784A (en) A kind of aluminum tunnel modular system and its operating method
JP2009299346A (en) Construction method of building
CN111877749B (en) Integral lifting type elevator shaft template and elevator shaft template supporting method
CN214658693U (en) A fixed chassis for outer wall construction goes up and down
CN110118014B (en) Exterior wall template system free of exterior scaffold and construction method thereof
CN211447763U (en) Improved post-cast strip formwork device for laminated floor
CN2434378Y (en) Climbing formwork construction device for columnar building construction
CN216157149U (en) Aluminum alloy formwork support system of coincide floor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination