CN116927204A - Suitable for deep foundation pit underground diaphragm wall reverse construction method and lining wall inter-layer slope treatment method - Google Patents

Suitable for deep foundation pit underground diaphragm wall reverse construction method and lining wall inter-layer slope treatment method Download PDF

Info

Publication number
CN116927204A
CN116927204A CN202311004998.8A CN202311004998A CN116927204A CN 116927204 A CN116927204 A CN 116927204A CN 202311004998 A CN202311004998 A CN 202311004998A CN 116927204 A CN116927204 A CN 116927204A
Authority
CN
China
Prior art keywords
lining
wall
layer
concrete
deep foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311004998.8A
Other languages
Chinese (zh)
Inventor
高元博
王晓轩
刘杰
杨仲洪
庞三余
李海耀
邓浩
田巧玲
张松艳
李双
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 11 Co Ltd
PowerChina 11th Bureau Engineering Co Ltd
Original Assignee
Sinohydro Bureau 11 Co Ltd
PowerChina 11th Bureau Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 11 Co Ltd, PowerChina 11th Bureau Engineering Co Ltd filed Critical Sinohydro Bureau 11 Co Ltd
Priority to CN202311004998.8A priority Critical patent/CN116927204A/en
Publication of CN116927204A publication Critical patent/CN116927204A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a method for processing a slope between lining walls in a reverse construction method of a deep foundation pit underground diaphragm wall, which relates to the technical field of hydraulic engineering and comprises the following steps of S10, roughening the underground diaphragm wall, and binding a capping beam and steel bars of the lining walls in the deep foundation pit; s20, excavating until the elevation of the lining concrete of the layer is lower than that of the lining concrete, and installing a longitudinal main rib; s30, backfilling with medium coarse sand to a preset height below the elevation of the substrate in the layer; s40, filling fine stone concrete to form an interlayer slope, and pouring concrete on the laminated top beam and the lining wall; s50, removing the mould and chiseling the fine stone concrete part after the preset condition is reached to enable the middle coarse sand to fall off; s60, repeating the steps S10-S50 to perform lining wall construction in the lower layer. The construction method is simple and convenient to operate, quality can be guaranteed, construction progress is processed, and construction cost is saved.

Description

适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法Suitable for deep foundation pit underground diaphragm wall reverse construction method and lining wall inter-layer slope treatment method

技术领域Technical field

本发明涉及水利工程技术领域,尤其涉及一种适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法。The invention relates to the technical field of water conservancy engineering, and in particular to a method for treating slopes between layers of lining walls using reverse construction of continuous walls in deep foundation pits.

背景技术Background technique

随着我国国民经济飞速发展,国家土地资源的日益紧张,许多高层建筑物、地铁、引水工程等都存在深基坑施工,尤其是南方地区,地下水丰富,深基坑的围护结构多采用地下连续墙结合内衬墙的形式,内衬墙层间结合质量直接关系到基坑内部开挖及混凝土施工的安全。深基坑地下连续墙逆作法内衬墙为保证层间结合效果,防止层间渗水,保证基坑开挖安全,内衬墙墙底即上下两层内衬墙结合面一般采用斜坡的形式,每层内衬墙截面形状为平行四边形。现有技术是按照设计图纸进行钢筋制安以及层间止水安装,侧墙采用大钢模,底部模板采用木模板,竖向钢筋通过模板上凿孔保证穿过进入下层开挖层。现有的技术中,由于内衬墙空间狭小,安装模板困难,并且需要对模板进行凿孔,对于工艺要求更高,不易保证质量。With the rapid development of my country's national economy and the increasing shortage of national land resources, many high-rise buildings, subways, water diversion projects, etc. have deep foundation pit construction. Especially in the southern region, where groundwater is abundant, the retaining structure of deep foundation pits is mostly underground. In the form of a continuous wall combined with a lining wall, the quality of the interlayer bonding of the lining wall is directly related to the safety of internal excavation and concrete construction of the foundation pit. In order to ensure the bonding effect between layers, prevent water seepage between layers, and ensure the safety of foundation pit excavation, the bottom of the lining wall, that is, the joint surface of the upper and lower lining walls, generally adopts the form of a slope. The cross-section shape of each layer of lining wall is parallelogram. The existing technology is to fabricate steel bars and install water-proofing between layers according to the design drawings. Large steel formwork is used for the side walls, and wooden formwork is used for the bottom formwork. The vertical steel bars are drilled through the formwork to ensure that they pass through to the lower excavation layer. In the existing technology, due to the narrow space of the lining wall, it is difficult to install the formwork, and the formwork needs to be drilled, which requires higher process requirements and it is difficult to ensure quality.

发明内容Contents of the invention

本发明要解决的技术问题在于,提供一种适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,可有效解决内衬墙空间狭小安装木模板困难、施工复杂,并且需要凿孔对于工艺要求更高的问题。The technical problem to be solved by the present invention is to provide a method for processing the inter-layer slope of the lining wall using the reverse construction method of the underground diaphragm wall in deep foundation pits, which can effectively solve the difficulty of installing wooden formwork in the narrow space of the lining wall, the construction complexity, and the need for chiseling. Holes have higher process requirements.

本发明解决其技术问题所采用的技术方案是:该适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,包括如下步骤,The technical solution adopted by the present invention to solve the technical problem is: the method for treating the slope between layers of the lining wall by reverse construction of the diaphragm wall in the deep foundation pit, including the following steps:

S10、对地下连续墙进行凿毛处理,压顶梁及本层内衬墙钢筋绑扎;S10. Carry out roughening treatment on the underground diaphragm wall, and tie the steel bars of the top beam and the lining wall of this layer;

S20、开挖至本层内衬混凝土标高以下,并安装纵向主筋;S20. Excavate to below the elevation of the concrete lining of this layer, and install longitudinal main bars;

S30、采用中粗砂回填至距本层内衬底标高以下预设高度;S30. Use medium-coarse sand to backfill to the preset height below the elevation of the inner lining of this layer;

S40、采用细石混凝土填充形成层间斜坡,对本层压顶梁及内衬墙进行混凝土浇筑;S40. Fill with fine stone concrete to form an inter-layer slope, and pour concrete for the laminated roof beam and lining wall;

S50、达到预设条件后拆模并凿除细石混凝土部分使中粗砂脱落;S50. After reaching the preset conditions, remove the formwork and chisel away the fine stone concrete part to make the medium-coarse sand fall off;

S60、重复步骤S10-S50进行下层内衬墙施工。S60. Repeat steps S10-S50 to construct the lower lining wall.

进一步地,步骤S10之前还包括预处理步骤,Further, step S10 also includes a preprocessing step,

基于已完成的地下连续墙,进行深基坑降水井、挡水墙、给排水施工;Based on the completed underground diaphragm wall, carry out deep foundation pit dewatering well, retaining wall, water supply and drainage construction;

从上而下破除地下连续墙桩头,凿出地下连续墙预设高度。Break the underground diaphragm wall pile heads from top to bottom and dig out the preset height of the underground diaphragm wall.

进一步地,所述预设高度为500mm。Further, the preset height is 500mm.

进一步地,步骤S20中纵向主筋采用塑料薄膜或PVC管保护。Further, in step S20, the longitudinal main ribs are protected by plastic film or PVC pipes.

进一步地,步骤S20中开挖至本层内衬混凝土标高以下至少1000mm。Further, in step S20, the excavation is carried out to at least 1000 mm below the elevation of the lining concrete of the current layer.

进一步地,步骤S30中预设高度为100mm。Further, the preset height in step S30 is 100 mm.

进一步地,步骤S40中,对本层压顶梁及内衬墙进行混凝土浇筑,包括Further, in step S40, concrete is poured on the laminated roof beam and the lining wall, including

混凝土浇筑时采用两台泵车对称浇筑,浇筑应分层,每层浇筑高度不大于500mm。When pouring concrete, two pump trucks are used for symmetrical pouring. The pouring should be in layers, and the pouring height of each layer should not be greater than 500mm.

进一步地,步骤S50中,达到预设条件后拆模混凝土满足的条件为,混凝土强度达到设计强度的80%后拆模。Further, in step S50, the conditions for removing the concrete form after reaching the preset conditions are: removing the formwork after the strength of the concrete reaches 80% of the design strength.

进一步地,步骤S50中,凿除细石混凝土部分使中粗砂脱落,包括Further, in step S50, the fine stone concrete part is chiseled off to make the medium-coarse sand fall off, including

使用风镐凿掉细石混凝土,底部的中粗砂自然脱落。Use a pneumatic pick to chisel away the fine stone concrete, and the medium-coarse sand at the bottom will naturally fall off.

该适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,深基坑开挖时先开挖至本层内衬混凝土标高以下,随后安装纵向主筋,主筋安装完毕后采用中粗砂回填至距内衬底设计标高以下预设高度,之后采用细石混凝土形成层间斜坡。混凝土达到设计强度后凿掉细石混凝土,底部的中粗砂自然脱落,层间的接触面毛面效果也能得到保证,施工方法操作简便,并且能够保证质量,加工了施工进度,节约施工成本。This method is suitable for the reverse construction method of underground diaphragm walls in deep foundation pits. When excavating deep foundation pits, excavate to below the elevation of the lining concrete layer, and then install the longitudinal main bars. After the main bars are installed, use medium-thick Sand is backfilled to a preset height below the design elevation of the inner substrate, and then fine stone concrete is used to form an inter-layer slope. After the concrete reaches the design strength, the fine stone concrete is chiseled off, and the medium-coarse sand at the bottom will naturally fall off, and the rough surface effect of the contact surface between layers can also be guaranteed. The construction method is easy to operate, and can ensure quality, process the construction progress, and save construction costs. .

附图说明Description of the drawings

下面将结合附图及实施例对本发明作进一步说明,附图中:The present invention will be further described below in conjunction with the accompanying drawings and examples. In the accompanying drawings:

图1是本发明实施例方法的流程框图;Figure 1 is a flow chart of the method according to the embodiment of the present invention;

图2是本发明实施例施工程序对应的结构示意图;Figure 2 is a structural schematic diagram corresponding to the construction procedure of the embodiment of the present invention;

图3是本发明实施例施工程序对应的结构示意图;Figure 3 is a schematic structural diagram corresponding to the construction procedure of the embodiment of the present invention;

图4是本发明实施例施工程序对应的结构示意图。Figure 4 is a schematic structural diagram corresponding to the construction procedure of the embodiment of the present invention.

具体实施方式Detailed ways

为了对本发明的技术特征、目的和效果有更加清楚的理解,现对照附图详细说明本发明的具体实施方式。In order to have a clearer understanding of the technical features, purposes and effects of the present invention, the specific embodiments of the present invention will now be described in detail with reference to the accompanying drawings.

该适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,整体工艺流程为:地下连续墙施工→降水井、挡水墙施工→地下连续墙桩头破除→压顶梁及第一层内衬墙钢筋绑扎→内衬墙上下层间斜坡处理→混凝土浇筑→拆模→层间凿毛处理→进入下一循环。This method is suitable for the reverse construction method of underground diaphragm walls in deep foundation pits and the inter-layer slope treatment method of lining walls. The overall process flow is: underground diaphragm wall construction → dewatering well and retaining wall construction → underground diaphragm wall pile head breaking → top beam pressing and first The steel bars of the lining wall are tied → the slope between the upper and lower floors of the lining wall is processed → the concrete is poured → the formwork is removed → the roughening between the layers is processed → enter the next cycle.

参阅图1-4,为各步骤的具体施工细节及响应工序的结构示意图,该适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,包括如下步骤,Refer to Figure 1-4, which shows the specific construction details of each step and the structural schematic diagram of the corresponding process. This method is suitable for the reverse construction method of underground diaphragm walls in deep foundation pits and the inter-layer slope treatment method of lining walls, including the following steps:

S10、对地下连续墙进行凿毛处理,压顶梁及本层内衬墙钢筋绑扎。当然,在该步骤之前还包括预处理步骤,S10. Carry out roughening treatment on the underground diaphragm wall, and tie the steel bars of the top beam and the lining wall of this layer. Of course, there is also a preprocessing step before this step,

基于已完成的地下连续墙,进行深基坑降水井、挡水墙、给排水施工;Based on the completed underground diaphragm wall, carry out deep foundation pit dewatering well, retaining wall, water supply and drainage construction;

从上而下破除地下连续墙桩头,凿出地下连续墙预设高度,其中,该预设高度为500mm。Break the pile heads of the underground diaphragm wall from top to bottom, and dig out the preset height of the underground diaphragm wall, where the preset height is 500mm.

S20、开挖至本层内衬混凝土标高以下,并安装纵向主筋。具体为,开挖至本层内衬混凝土标高以下至少1000mm,优选为1050mm,纵向主筋优选采用塑料薄膜或PVC管保护。S20. Excavate to below the elevation of the concrete lining of this layer, and install longitudinal main bars. Specifically, the excavation is carried out to at least 1000mm, preferably 1050mm, below the elevation of the lining concrete of this layer, and the longitudinal main bars are preferably protected by plastic films or PVC pipes.

S30、采用中粗砂回填至距本层内衬底标高以下100mm。S30. Use medium-coarse sand to backfill to 100mm below the elevation of the inner lining of this layer.

S40、采用细石混凝土填充形成层间斜坡,对本层压顶梁及内衬墙进行混凝土浇筑;混凝土浇筑时采用两台泵车对称浇筑,浇筑应分层,每层浇筑高度不大于500mm。S40. Use fine stone concrete to fill the inter-layer slopes, and concrete the laminated roof beams and lining walls; use two pump trucks to pour the concrete symmetrically. The pouring should be in layers, and the pouring height of each layer should not be greater than 500mm.

S50、混凝土强度达到设计强度的80%后拆模并使用风镐凿除细石混凝土部分,中粗砂自然脱落。S50. After the concrete strength reaches 80% of the design strength, remove the formwork and use a pneumatic pick to remove the fine stone concrete part. The medium-coarse sand will naturally fall off.

S60、重复步骤S10-S50进行下层内衬墙施工。即进行下层基坑土石方开挖至设计高程,按照上述步骤进行下层内衬墙施工。S60. Repeat steps S10-S50 to construct the lower lining wall. That is, the earth and rockwork of the lower foundation pit is excavated to the design elevation, and the lower lining wall construction is carried out according to the above steps.

该适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,深基坑开挖时先开挖至本层内衬混凝土标高以下,随后安装纵向主筋,主筋安装完毕后采用中粗砂回填至距内衬底设计标高以下预设高度,之后采用细石混凝土形成层间斜坡。混凝土达到设计强度后凿掉细石混凝土,底部的中粗砂自然脱落,层间的接触面毛面效果也能得到保证,施工方法操作简便,并且能够保证质量,加工了施工进度,节约施工成本。This method is suitable for the reverse construction method of underground diaphragm walls in deep foundation pits. When excavating deep foundation pits, excavate to below the elevation of the lining concrete layer, and then install the longitudinal main bars. After the main bars are installed, use medium-thick Sand is backfilled to a preset height below the design elevation of the inner substrate, and then fine stone concrete is used to form an inter-layer slope. After the concrete reaches the design strength, the fine stone concrete is chiseled off, and the medium-coarse sand at the bottom will naturally fall off, and the rough surface effect of the contact surface between layers can also be guaranteed. The construction method is easy to operate, and can ensure quality, process the construction progress, and save construction costs. .

最后,还需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。Finally, it should be noted that in this article, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply that these entities or any such actual relationship or sequence between operations. Furthermore, the terms "comprises," "comprises," or any other variations thereof are intended to cover a non-exclusive inclusion such that a process, method, article, or apparatus that includes a list of elements includes not only those elements, but also those not expressly listed other elements, or elements inherent to the process, method, article or equipment. Without further limitation, an element defined by the statement "comprises a..." does not exclude the presence of additional identical elements in a process, method, article, or apparatus that includes the stated element.

显然,上述实施例仅仅是为清楚地说明所作的举例,而并非对实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里无需也无法对所有的实施方式予以穷举。而由此所引伸出的显而易见的变化或变动仍处于本发明创造的保护范围之中。Obviously, the above-mentioned embodiments are only examples for clear explanation and are not intended to limit the implementation. For those of ordinary skill in the art, other different forms of changes or modifications can be made based on the above description. An exhaustive list of all implementations is neither necessary nor possible. The obvious changes or modifications derived therefrom are still within the protection scope of the present invention.

Claims (9)

1.适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,其特征在于,包括如下步骤,1. It is suitable for the reverse construction method of underground diaphragm walls in deep foundation pits and is a method for treating inter-layer slopes of lining walls. It is characterized by including the following steps: S10、对地下连续墙进行凿毛处理,压顶梁及本层内衬墙钢筋绑扎;S10. Carry out roughening treatment on the underground diaphragm wall, and tie the steel bars of the top beam and the lining wall of this layer; S20、开挖至本层内衬混凝土标高以下,并安装纵向主筋;S20. Excavate to below the elevation of the concrete lining of this layer, and install longitudinal main bars; S30、采用中粗砂回填至距本层内衬底标高以下预设高度;S30. Use medium-coarse sand to backfill to the preset height below the elevation of the inner lining of this layer; S40、采用细石混凝土填充形成层间斜坡,对本层压顶梁及内衬墙进行混凝土浇筑;S40. Fill with fine stone concrete to form an inter-layer slope, and pour concrete for the laminated roof beam and lining wall; S50、达到预设条件后拆模并凿除细石混凝土部分使中粗砂脱落;S50. After reaching the preset conditions, remove the formwork and chisel away the fine stone concrete part to make the medium-coarse sand fall off; S60、重复步骤S10-S50进行下层内衬墙施工。S60. Repeat steps S10-S50 to construct the lower lining wall. 2.根据权利要求1所述的适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,其特征在于,步骤S10之前还包括预处理步骤,2. The method for treating inter-layer slopes of lining walls using the reverse construction method for underground diaphragm walls in deep foundation pits according to claim 1, characterized in that step S10 also includes a preprocessing step, 基于已完成的地下连续墙,进行深基坑降水井、挡水墙、给排水施工;Based on the completed underground diaphragm wall, carry out deep foundation pit dewatering well, retaining wall, water supply and drainage construction; 从上而下破除地下连续墙桩头,凿出地下连续墙预设高度。Break the underground diaphragm wall pile heads from top to bottom and dig out the preset height of the underground diaphragm wall. 3.根据权利要求2所述的适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,其特征在于,所述预设高度为500mm。3. The method for treating inter-layer slopes of lining walls by reverse construction of underground diaphragm walls in deep foundation pits according to claim 2, characterized in that the preset height is 500mm. 4.根据权利要求1所述的适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,其特征在于,步骤S20中纵向主筋采用塑料薄膜或PVC管保护。4. The interlayer slope treatment method suitable for reverse construction of underground continuous walls in deep foundation pits and lining walls according to claim 1, characterized in that in step S20, the longitudinal main bars are protected by plastic films or PVC pipes. 5.根据权利要求1所述的适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,其特征在于,步骤S20中开挖至本层内衬混凝土标高以下至少1000mm。5. The method for treating the inter-layer slope of the lining wall using the reverse construction method of the underground diaphragm wall in deep foundation pits according to claim 1, characterized in that in step S20, the excavation is carried out to at least 1000 mm below the elevation of the lining concrete of the current layer. 6.根据权利要求1所述的适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,其特征在于,步骤S30中预设高度为100mm。6. The method for treating the inter-layer slope of the lining wall by the reverse construction method of the underground diaphragm wall in deep foundation pits according to claim 1, characterized in that the preset height in step S30 is 100mm. 7.根据权利要求1所述的适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,其特征在于,步骤S40中,对本层压顶梁及内衬墙进行混凝土浇筑,包括7. The method for processing the inter-layer slope of the lining wall using the reverse construction method of the underground diaphragm wall in the deep foundation pit according to claim 1, characterized in that in step S40, concrete pouring is performed on the laminated top beam and the lining wall, including 混凝土浇筑时采用两台泵车对称浇筑,浇筑应分层,每层浇筑高度不大于500mm。When pouring concrete, two pump trucks are used for symmetrical pouring. The pouring should be in layers, and the pouring height of each layer should not be greater than 500mm. 8.根据权利要求1所述的适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,其特征在于,步骤S50中,达到预设条件后拆模混凝土满足的条件为,混凝土强度达到设计强度的80%后拆模。8. The method for treating inter-layer slopes of lining walls using the reverse construction method of underground diaphragm walls in deep foundation pits according to claim 1, characterized in that, in step S50, the conditions for removing the formwork concrete after reaching the preset conditions are: concrete Remove the formwork after the strength reaches 80% of the design strength. 9.根据权利要求1所述的适用于深基坑地下连续墙逆作法内衬墙层间斜坡处理方法,其特征在于,步骤S50中,凿除细石混凝土部分使中粗砂脱落,包括9. The interlayer slope treatment method suitable for reverse construction of underground continuous walls in deep foundation pits and lining walls according to claim 1, characterized in that in step S50, the fine stone concrete part is chiseled off to cause the medium-coarse sand to fall off, including 使用风镐凿掉细石混凝土,底部的中粗砂自然脱落。Use a pneumatic pick to chisel away the fine stone concrete, and the medium-coarse sand at the bottom will naturally fall off.
CN202311004998.8A 2023-08-10 2023-08-10 Suitable for deep foundation pit underground diaphragm wall reverse construction method and lining wall inter-layer slope treatment method Pending CN116927204A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311004998.8A CN116927204A (en) 2023-08-10 2023-08-10 Suitable for deep foundation pit underground diaphragm wall reverse construction method and lining wall inter-layer slope treatment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311004998.8A CN116927204A (en) 2023-08-10 2023-08-10 Suitable for deep foundation pit underground diaphragm wall reverse construction method and lining wall inter-layer slope treatment method

Publications (1)

Publication Number Publication Date
CN116927204A true CN116927204A (en) 2023-10-24

Family

ID=88392501

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311004998.8A Pending CN116927204A (en) 2023-08-10 2023-08-10 Suitable for deep foundation pit underground diaphragm wall reverse construction method and lining wall inter-layer slope treatment method

Country Status (1)

Country Link
CN (1) CN116927204A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758458A (en) * 2012-07-30 2012-10-31 上海隧道工程股份有限公司 Underground continuous wall repairing method
CN106609508A (en) * 2015-10-22 2017-05-03 中铁十四局集团有限公司 Construction technology and construction method for large-particle-size pebble stratum super-deep foundation pit in strong water permeation environment of Yellow River flood plain
CN110552370A (en) * 2019-08-30 2019-12-10 中国一冶集团有限公司 Reverse construction method based annular lining wall integral single-side formwork construction method
CN110552371A (en) * 2019-08-30 2019-12-10 中国一冶集团有限公司 Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method
CN114875972A (en) * 2022-04-21 2022-08-09 中铁隧道集团二处有限公司 Open-cut top-down foundation pit main structure construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758458A (en) * 2012-07-30 2012-10-31 上海隧道工程股份有限公司 Underground continuous wall repairing method
CN106609508A (en) * 2015-10-22 2017-05-03 中铁十四局集团有限公司 Construction technology and construction method for large-particle-size pebble stratum super-deep foundation pit in strong water permeation environment of Yellow River flood plain
CN110552370A (en) * 2019-08-30 2019-12-10 中国一冶集团有限公司 Reverse construction method based annular lining wall integral single-side formwork construction method
CN110552371A (en) * 2019-08-30 2019-12-10 中国一冶集团有限公司 Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method
CN114875972A (en) * 2022-04-21 2022-08-09 中铁隧道集团二处有限公司 Open-cut top-down foundation pit main structure construction method

Similar Documents

Publication Publication Date Title
CN101768976B (en) Base pit dewatering and water saving device and construction method thereof
CN207512745U (en) A kind of caisson device and its foundation pit structure
CN103321246B (en) Construction Method of Foundation Pit Using Underground Diaphragm Wall
CN106884433A (en) Control vibrations pile pulling causes the structure of underground structure depression and control depression method
CN112627212B (en) Water-faced cofferdam inner tube well dewatering dry excavation construction method
CN109653223A (en) River anti-floating weighting board construction method
WO2007129693A1 (en) Soil improvement method
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN104790410A (en) Foundation pit excavation supporting method suitable for watercourse with shallow water and sludge
CN210163910U (en) Pipeline pipe jacking receiving well foundation pit supporting structure
CN106480891B (en) A kind of shaft construction method
CN111733842A (en) Cofferdam construction method and cofferdam structure
CN113957913A (en) Construction method of film bag sand filling combined steel sheet pile cofferdam
CN111155429A (en) Construction method for bridge sand blowing island building in still water deep water area
CN106884427A (en) Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water
CN201567582U (en) A water-saving device for foundation pit dewatering
CN212641468U (en) Pit-in-pit rapid construction structure
CN205776282U (en) A kind of immersed tube tunnel rebuilds cofferdam structure
CN111535298A (en) Seepage-proofing construction method for underground diaphragm wall
CN110144871A (en) A kind of dark bank treatment construction method
CN117569263A (en) Dam impervious wall and construction method thereof
CN114837455B (en) Method for reconstructing sunken hydraulic building
CN116927204A (en) Suitable for deep foundation pit underground diaphragm wall reverse construction method and lining wall inter-layer slope treatment method
CN106192880A (en) The box harbour of L-type and method of construction thereof
CN113668585B (en) Open caisson structure for deep and large water intaking in high-pressure water area and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination