CN116856550A - A reverse construction method for new construction above ground with reinforced concrete frame structure steel slideway jacking - Google Patents

A reverse construction method for new construction above ground with reinforced concrete frame structure steel slideway jacking Download PDF

Info

Publication number
CN116856550A
CN116856550A CN202310324372.9A CN202310324372A CN116856550A CN 116856550 A CN116856550 A CN 116856550A CN 202310324372 A CN202310324372 A CN 202310324372A CN 116856550 A CN116856550 A CN 116856550A
Authority
CN
China
Prior art keywords
columns
steel
prefabricated
column
precast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310324372.9A
Other languages
Chinese (zh)
Inventor
高作平
刘春年
张畅
吴博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Jucheng Structure Group Co ltd
Original Assignee
Wuhan Jucheng Structure Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Jucheng Structure Group Co ltd filed Critical Wuhan Jucheng Structure Group Co ltd
Priority to CN202310324372.9A priority Critical patent/CN116856550A/en
Publication of CN116856550A publication Critical patent/CN116856550A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3522Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by raising a structure and then adding structural elements under it
    • E04B1/3527Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by raising a structure and then adding structural elements under it the structure being a roof

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a newly-built reverse construction method for lifting a steel slideway of a reinforced concrete frame structure. When the reinforced concrete frame structure is newly built, all frame columns are prefabricated in a segmented mode, the installed prefabricated columns are synchronously lengthened and synchronously jacked, the floor part is built at the bottom, and the reverse construction on the ground is achieved. In the lengthening process, steel plates at the bottom and the top of the adjacent prefabricated columns are welded, annular gaps of reserved grooves of the tops of the columns are grouted, and structural butt joint is achieved. The construction method can realize that all floor structures of the building are constructed within the height range of 2 meters at the bottom, can avoid construction protection such as scaffolds, climbing forms and the like, can avoid overhead operation, reduces capital and resource occupation time, and can be popularized and applied according to the novel construction method.

Description

一种钢筋混凝土框架结构钢滑道顶升地上新建逆向施工方法A reverse construction method for new construction above ground with reinforced concrete frame structure steel slideway jacking

技术领域Technical field

本发明涉及建筑技术领域,具体涉及一种钢筋混凝土框架结构钢滑道顶升地上新建逆向施工方法。The invention relates to the field of construction technology, and in particular to a reverse construction method for a steel slideway jacking above ground for a reinforced concrete frame structure.

背景技术Background technique

建筑业是国民经济的支柱产业,为我国经济持续健康发展提供了有力支撑。但建筑业生产方式仍然比较粗放,与高质量发展要求相比还有很大差距。为推进建筑工业化、数字化、智能化升级,加快建造方式转变,推动建筑业高质量发展,住建部联合12部委发布了《关于推动智能建造与建筑工业化协同发展的指导意见》等国家级文件,为建筑业智能建造大变革拉开了序幕。传统建筑建造模式为单层式由下而上逐层施工,需采用爬模、脚手架等施工防护且占用时间长,为此,研究出一种在地下建造并顶升的施工方法,免除爬架及脚手架的搭设,此新型地上新建逆向施工方法应用前景广阔。The construction industry is a pillar industry of the national economy and provides strong support for the sustained and healthy development of our country's economy. However, the production methods of the construction industry are still relatively extensive, and there is still a big gap compared with the requirements for high-quality development. In order to promote the industrialization, digitalization and intelligent upgrading of construction, accelerate the transformation of construction methods, and promote the high-quality development of the construction industry, the Ministry of Housing and Urban-Rural Development and 12 ministries and commissions jointly issued the "Guiding Opinions on Promoting the Coordinated Development of Intelligent Construction and Construction Industrialization" and other national documents, providing The great revolution of intelligent construction in the construction industry has begun. The traditional building construction mode is a single-story construction from bottom to top, which requires the use of climbing formwork, scaffolding and other construction protection and takes a long time. Therefore, a construction method of building underground and jacking up is developed, eliminating the need for climbing frames. and the erection of scaffolding, this new above-ground reverse construction method has broad application prospects.

发明内容Contents of the invention

本发明的目的在于,针对现有钢筋混凝土框架结构单层式由下而上逐层施工建造技术工期长、施工面高、需使用爬架或脚手架等现象,提供一种在离地约两米处浇筑楼层梁板结构,可免除搭设脚手架或使用爬架的高效建造方法。The purpose of this invention is to provide a method for constructing a single-layer reinforced concrete frame structure about two meters above the ground in view of the long construction period, high construction surface, and the need to use climbing frames or scaffolding. The floor beam-slab structure is poured everywhere, which is an efficient construction method that eliminates the need to set up scaffolding or use climbing frames.

为实现上述目的,本发明的技术解决方案是:一种钢筋混凝土框架结构钢滑道顶升地上新建逆向施工方法,其特征在于,包括以下步骤:In order to achieve the above object, the technical solution of the present invention is: a new reverse construction method for steel slide jacking on the ground with reinforced concrete frame structure, which is characterized by including the following steps:

步骤一、首先将各层混凝土框架柱拆分为三段预制混凝土柱,分为首节预制柱、中间节预制柱和下节预制柱,并提前按相关节点构造进行预制;Step 1: First, split the concrete frame columns of each layer into three sections of precast concrete columns, which are divided into the first section of precast columns, the middle section of precast columns and the lower section of precast columns, and precast in advance according to the relevant node structure;

步骤二、浇筑钢筋混凝土柱的基础,并预埋钢滑道垫板及埋件;Step 2: Pour the foundation of the reinforced concrete column and embed the steel slide pad and embedded parts;

步骤三、安装钢滑道及钢牛腿,随后将顶层层首节预制柱(按2米)安装到位(见图1);Step 3: Install the steel slides and steel corbels, and then install the first prefabricated column (2 meters) on the top floor in place (see Figure 1);

步骤四、在离地不高处安装顶层梁、板模板并现场绑扎钢筋笼,浇筑混凝土,混凝土整体养护至指定强度值,使得顶层梁与顶层首节柱连接形成整体,而顶层板与顶层首节柱脱开,便于钢滑道穿过顶层楼面;Step 4: Install the top beams and slab formwork at a low height from the ground, tie the steel cage on site, pour concrete, and maintain the concrete to the specified strength value so that the top beams and the first column of the top floor are connected to form a whole, and the top slab and the first column of the top floor are connected as a whole. The knotted columns are detached to allow steel slides to pass through the top floor;

步骤五、对顶层及已安装好的顶层首节预制柱所形成的整体进行顶升,顶升达到一定高度后,在钢滑道内安装顶层中间节预制柱,同时浇筑顶层下一结构层的柱混凝土(见图2);Step 5: Jack up the whole structure formed by the top layer and the installed first section of the precast columns on the top layer. After the jacking reaches a certain height, install the top middle section of precast columns in the steel slide, and at the same time pour the columns of the next structural layer on the top layer. Concrete (see Figure 2);

步骤六、待顶层中间节预制柱与顶层首节预制柱形成整体后,继续向上顶升,顶升达到一定高度后安装顶层下节预制柱(见图3);Step 6: After the prefabricated columns in the middle section of the top layer and the precast columns in the first section of the top layer are integrated, continue to lift upward. After reaching a certain height, install the prefabricated columns in the lower section of the top layer (see Figure 3);

步骤七、待形成整体后,顶层建成,继续顶升,并浇筑顶层下一楼层楼面结构,同时安装顶层下一楼层首节预制柱(见图4);Step 7: After forming a whole, the top floor is completed, continue to lift, and pour the floor structure of the next floor on the top floor, and at the same time install the first section of prefabricated columns on the next floor on the top floor (see Figure 4);

步骤八、多次循环实现顶层下2层、下3层、下4层…,直至浇筑完成2层楼面;Step 8: Repeat multiple cycles to achieve 2 floors below the top, 3 floors below, 4 floors below... until the 2 floors are poured;

步骤九、所有楼层浇筑完成并达到设计标高后,安装底层下节柱,与基础内预埋底板进行焊接,并包500高混凝土柱脚;Step 9: After the pouring of all floors is completed and the design elevation is reached, the lower section columns of the bottom floor are installed, welded to the embedded bottom plate in the foundation, and covered with 500-meter-high concrete column feet;

步骤十、拆除钢滑道,浇筑楼板与预制柱间的混凝土。Step 10: Remove the steel slide and pour the concrete between the floor slab and the prefabricated columns.

所述步骤三中钢牛腿可临时固定于钢滑道上,当安装预制柱后,钢牛腿与预制柱可靠连接,千斤顶顶升钢牛腿时可带动预制柱向上滑动。In step three, the steel corbels can be temporarily fixed on the steel slide. After the prefabricated columns are installed, the steel corbels are reliably connected to the prefabricated columns. When the jack lifts the steel corbels, the prefabricated columns can be driven to slide upward.

所述步骤四实施前需充分考虑各框架梁纵筋与预制柱纵筋、钢滑道间的碰撞问题。Before the implementation of step four, the collision problem between the longitudinal bars of each frame beam, the longitudinal bars of the prefabricated columns, and the steel slides must be fully considered.

所述步骤五、六、七中需考虑中间节预制柱与首节预制柱、下节预制柱间的连接,可通过预制柱上下预埋钢板焊接、各预制柱的杯口、各预制柱凸出的柱脚灌浆形成整体。In the steps five, six and seven, it is necessary to consider the connection between the middle section of the precast column, the first section of the precast column and the lower section of the precast column. This can be done by welding the upper and lower embedded steel plates of the precast column, the cup mouth of each precast column, and the convex part of each precast column. The outgoing column feet are grouted to form a whole.

本发明中涉及的一种钢筋混凝土框架结构钢滑道顶升地上新建逆向施工方法具有以下有益效果:The invention involves a reinforced concrete frame structure steel slideway jacking above ground new construction reverse construction method, which has the following beneficial effects:

本发明公开的一种钢筋混凝土框架结构钢滑道顶升地上新建逆向施工方法,通过钢滑道将已建好的部分钢筋混凝土框架结构向上顶升,可实现在地面低处施工,免除脚手架搭设或爬架的使用,从而达到地上新建逆向施工。该施工方法可免除脚手架搭设或爬架的使用,减少高空作业,减少资金、资源占用时间,符合智能建造的发展趋势,可大范围推广应用。The invention discloses a reverse construction method for a reinforced concrete frame structure that is lifted up by steel slides to build a new building on the ground. Part of the already built reinforced concrete frame structure is lifted upward through the steel slides, which can realize construction at low places on the ground and eliminate the need for scaffolding erection. Or the use of climbing frames to achieve reverse construction of new buildings on the ground. This construction method can eliminate the need for scaffolding or climbing frames, reduce high-altitude operations, and reduce the time occupied by funds and resources. It is in line with the development trend of intelligent construction and can be widely promoted and applied.

附图说明Description of the drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单的介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to explain the embodiments of the present invention or the technical solutions in the prior art more clearly, the following will briefly introduce the drawings needed to describe the embodiments or the prior art. Obviously, the drawings in the following description are only These are some embodiments of the present invention. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without exerting creative efforts.

图1为本发明公开的浇筑顶层梁板后状态示意图;Figure 1 is a schematic diagram of the state after pouring the top beam plate disclosed in the present invention;

图2为本发明公开的顶层中间节预制柱安装后状态示意图;Figure 2 is a schematic diagram of the prefabricated column in the top middle section disclosed by the present invention after installation;

图3为本发明公开的顶层下节预制柱安装后状态示意图;Figure 3 is a schematic diagram of the prefabricated column in the lower section of the top layer disclosed in the present invention after installation;

图4为本发明公开的顶层下一层浇筑后状态示意图;Figure 4 is a schematic diagram of the state after the top layer and the next layer are poured according to the invention;

图5为本发明公开的建筑施工完成后状态示意图;Figure 5 is a schematic diagram of the state of the building disclosed in the present invention after completion of construction;

图6为本发明公开的预制柱底部构造大样图(仰视);Figure 6 is a large diagram of the bottom structure of the prefabricated column disclosed by the present invention (looking down);

图7为本发明公开的预制柱顶部构造大样图(俯视)。Figure 7 is a large-scale view (top view) of the top structure of the prefabricated column disclosed in the present invention.

具体实施方式Detailed ways

下面将结合本发明实施方式,对本发明实施方式中的技术方案进行清楚、完整地描述,显然,所描述的实施方式仅仅是本发明一部分实施方式,而不是全部的实施方式。基于本发明中的实施方式,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施方式,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the embodiments of the present invention. Obviously, the described embodiments are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts fall within the scope of protection of the present invention.

为使本发明的目的、技术方案和优点表达得更加清楚明白,下面结合附图对本发明作进一步的介绍。In order to express the purpose, technical solutions and advantages of the present invention more clearly, the present invention will be further introduced below in conjunction with the accompanying drawings.

步骤一、首先根据结构施工图确定首先需要浇筑的顶层楼面梁7、板8,并将所有混凝土框架柱拆分为三段预制混凝土柱,分为首节预制柱(6和16)、中间节预制柱12和下节预制柱14,其中首节预制柱(6和16,按2米左右考虑)需考虑框架梁(7和17)柱(6和16)之间的连接,并避免钢筋碰撞(见图1~图4);Step 1: First determine the top floor beams 7 and slabs 8 that need to be poured first according to the structural construction drawings, and split all concrete frame columns into three sections of precast concrete columns, divided into the first section of precast columns (6 and 16), the middle section Precast column 12 and lower precast column 14. Among them, the first section of precast columns (6 and 16, considered at about 2 meters) needs to consider the connection between frame beams (7 and 17) and columns (6 and 16), and avoid steel bar collisions. (See Figures 1 to 4);

步骤二、浇筑钢筋混凝土柱的基础1,并预埋埋件2和钢滑道垫板3(见图1);Step 2: Pour the foundation 1 of the reinforced concrete column, and embed the embedded parts 2 and the steel slide pad 3 (see Figure 1);

步骤三、安装钢滑道4及钢牛腿5,随后将第4层首节预制柱6安装到位(见图1);Step 3: Install the steel slides 4 and steel corbels 5, and then install the first prefabricated column 6 of the 4th floor in place (see Figure 1);

步骤四、在离地不高处安装顶层梁7、板8模板并现场绑扎钢筋笼,浇筑混凝土,混凝土整体养护至指定强度值,使得顶层梁7与顶层首节柱6连接形成整体,而顶层板8与顶层首节柱脱开,便于钢滑道穿过顶层楼面(见图1);Step 4: Install the top beam 7 and plate 8 formwork at a low height from the ground and tie the steel cage on site. Concrete is poured and the concrete is cured to the specified strength value so that the top beam 7 and the top first column 6 are connected to form a whole. The plate 8 is detached from the first column on the top floor to facilitate the steel slide to pass through the top floor (see Figure 1);

步骤五、千斤顶9就位后,对顶层已安装好的板8、梁7和柱6形成的整体进行顶升,顶升达到一定高度后,将顶层中间节预制柱12移至钢滑道4内,将顶层首节预制柱6的下凸柱头10落入中间节预制柱12的上凹槽11内,并将首节预制柱6的下预埋钢板19与中间节预制柱12的上预埋钢板20进行焊接,并对凹槽11的下预埋注浆管21进行灌浆,待上出浆管22出浆后,对注浆口和出浆口均进行封堵(见图2)。Step 5: After the jack 9 is in place, jack up the whole body formed by the installed plate 8, beam 7 and column 6 on the top floor. After the jack 9 reaches a certain height, move the prefabricated column 12 in the middle section of the top floor to the steel slide 4 , drop the lower convex column head 10 of the first section of the precast column 6 on the top floor into the upper groove 11 of the middle section of the precast column 12, and connect the lower embedded steel plate 19 of the first section of the precast column 6 with the upper precast column of the middle section of the precast column 12. The embedded steel plate 20 is welded, and the lower embedded grouting pipe 21 of the groove 11 is grouted. After the upper grouting pipe 22 is grouted, both the grouting port and the grouting port are blocked (see Figure 2).

步骤六、待所灌浆料强度均达到顶升要求后,继续向上顶升,顶升达到一定高度后,将顶层下节预制柱14移至钢滑道4内,将顶层中间节预制柱12的下凸柱头13落入下节预制柱14的上凹槽内,并将中间节预制柱12的下预埋钢板19与下节预制柱14的上预埋钢板20进行焊接,并对下节预制柱14的上凹槽11的下预埋注浆管21进行灌浆,待上出浆管22出浆后,对注浆口和出浆口均进行封堵(见图3)。Step 6: After the strength of the grouting materials reaches the lifting requirements, continue to lift upward. After the lifting reaches a certain height, move the precast column 14 of the lower section of the top layer to the steel slide 4, and move the precast column 12 of the middle section of the top layer. The lower convex column head 13 falls into the upper groove of the lower prefabricated column 14, and the lower prefabricated steel plate 19 of the middle prefabricated column 12 and the upper prefabricated steel plate 20 of the lower prefabricated column 14 are welded, and the lower prefabricated column 14 is welded. The lower pre-embedded grouting pipe 21 of the upper groove 11 of the column 14 is grouted. After the upper grouting pipe 22 is grouted, both the grouting port and the grouting port are blocked (see Figure 3).

步骤七、继续顶升,待顶升达到一定高度后,将顶层下一层首节预制柱16移至钢滑道4内,将顶层下一层下节预制柱14的下凸柱头15落入顶层下一层上节预制柱16的上凹槽内,并将下节预制柱14的下预埋钢板19与顶层下一层首节预制柱16的上预埋钢板20进行焊接,并对凹槽11的下预埋注浆管21进行灌浆,待上出浆管22出浆后,对注浆口和出浆口均进行封堵,同时浇筑顶层下一层梁17、板18(见图4)。Step 7: Continue jacking. After the jacking reaches a certain height, move the first section of the prefabricated column 16 of the next layer on the top layer to the steel slide 4, and drop the lower convex column head 15 of the lower section of the prefabricated column 14 of the next layer on the top layer. into the upper groove of the upper section of the precast column 16 on the next layer of the top layer, and weld the lower embedded steel plate 19 of the lower section of the precast column 14 with the upper embedded steel plate 20 of the first section of the precast column 16 of the next layer on the top layer, and The lower pre-embedded grouting pipe 21 of the tank 11 is grouted. After the upper grouting pipe 22 is grouted, both the grouting port and the grouting port are blocked. At the same time, the beams 17 and slabs 18 of the lower layer of the top layer are poured (see figure). 4).

步骤八、多次循环实现顶层下2层、下3层、下4层…,直至浇筑完成2层楼面;Step 8: Repeat multiple cycles to achieve 2 floors below the top, 3 floors below, 4 floors below... until the 2 floors are poured;

步骤九、所有楼层浇筑完成并达到设计标高后,安装底层下节柱,将底层下节柱的下预埋钢板与基础内预制底板进行焊接,并包500高混凝土柱脚;Step 9: After the pouring of all floors is completed and reaches the design elevation, install the lower section columns of the bottom floor, weld the lower embedded steel plate of the lower section columns of the bottom floor to the prefabricated bottom plate in the foundation, and wrap 500-meter-high concrete column feet;

步骤十、拆除钢滑道,浇筑楼板与预制柱间的混凝土。Step 10: Remove the steel slide and pour the concrete between the floor slab and the prefabricated columns.

最后应说明的是,以上仅为本发明的优选实施例而已,并不用于限制本发明,尽管参照实施例,对本发明进行了详细的说明,对于本领域的技术人员来说,其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换,但是凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。Finally, it should be noted that the above are only preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the embodiments, those skilled in the art can still The technical solutions described in the foregoing embodiments may be modified, or some of the technical features may be equivalently substituted. However, any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention shall be included in this document. within the scope of protection of the invention.

Claims (5)

1.一种钢筋混凝土框架结构钢滑道顶升地上新建逆向施工方法,其特征在于,该方法包括以下步骤:1. A reverse construction method for a reinforced concrete frame structure steel slide jacking above ground, characterized in that the method includes the following steps: 步骤一、首先将各层混凝土框架柱拆分为三段预制混凝土柱,分为首节预制柱、中间节预制柱和下节预制柱,并提前按相关节点构造进行预制;Step 1: First, split the concrete frame columns of each layer into three sections of precast concrete columns, which are divided into the first section of precast columns, the middle section of precast columns and the lower section of precast columns, and precast in advance according to the relevant node structure; 步骤二、浇筑钢筋混凝土柱的基础,并预埋钢滑道垫板及埋件;Step 2: Pour the foundation of the reinforced concrete column and embed the steel slide pad and embedded parts; 步骤三、安装钢滑道及钢牛腿,随后将顶层首节预制柱(按2米)安装到位;Step 3: Install the steel slides and steel corbels, and then install the first prefabricated column (2 meters) on the top floor in place; 步骤四、在离地不高处安装顶层梁、板模板并现场绑扎钢筋笼,浇筑混凝土,混凝土整体养护至指定强度值,使得顶层梁与顶层首节柱连接形成整体,而顶层板与顶层首节柱脱开,便于钢滑道穿过顶层楼面;Step 4: Install the top beams and slab formwork at a low height from the ground, tie the steel cage on site, pour concrete, and maintain the concrete to the specified strength value so that the top beams and the first column of the top floor are connected to form a whole, and the top slab and the first column of the top floor are connected as a whole. The knotted columns are detached to allow steel slides to pass through the top floor; 步骤五、对顶层梁板及已安装好的顶层首节预制柱所形成的整体进行顶升,顶升达到一定高度后,在钢滑道内安装顶层中间节预制柱;Step 5: Jack up the whole structure formed by the top beam plate and the installed top first section precast column. After the jacking reaches a certain height, install the top middle section prefabricated column in the steel slideway; 步骤六、待顶层中间节预制柱与顶层首节预制柱形成整体后,继续向上顶升,顶升达到一定高度后安装顶层下节预制柱;Step 6: After the prefabricated columns in the middle section of the top layer and the precast columns in the first section of the top layer are integrated, continue to lift upward. After reaching a certain height, install the prefabricated columns in the lower section of the top layer; 步骤七、待形成整体后,继续顶升,并浇筑顶层下一层楼面结构,同时顶层下一层首节预制柱;Step 7: After forming a whole, continue to jack up and pour the structure of the next floor on the top floor, and at the same time, the first section of the prefabricated column on the next floor on the top floor; 步骤八、多次循环实现顶层下2层、下3层、下4层…,直至浇筑完成2层楼面;Step 8: Repeat multiple cycles to achieve 2 floors below the top, 3 floors below, 4 floors below... until the 2 floors are poured; 步骤九、所有楼层浇筑完成并达到设计标高后,安装底层下节柱,与基础内预制底板进行焊接,并包500高混凝土柱脚;Step 9: After the pouring of all floors is completed and the design elevation is reached, the lower section columns of the bottom floor are installed, welded to the prefabricated bottom plate in the foundation, and covered with 500-meter-high concrete column feet; 步骤十、拆除钢滑道,浇筑楼板与预制柱间的混凝土。Step 10: Remove the steel slide and pour the concrete between the floor slab and the prefabricated columns. 2.如权利要求1所述的一种钢筋混凝土框架结构钢滑道顶升地上新建逆向施工方法,其特征在于:通过预制柱间的接长,钢滑道的顶升,建筑楼层可在地面2米高范围内施工,实现地上新建逆向施工,且免除脚手架或爬架施工防护,免除高空作业。2. A reverse construction method for a reinforced concrete frame structure with steel slides jacking up above ground as claimed in claim 1, characterized in that: through the lengthening of the prefabricated columns and the lifting of the steel slides, the building floors can be placed on the ground Construction within a 2-meter-high range enables reverse construction of new buildings on the ground, and eliminates the need for scaffolding or climbing frame construction protection, and eliminates the need for high-altitude operations. 3.如权利要求1所述的一种钢筋混凝土框架结构钢滑道顶升地上新建逆向施工方法,其特征在于:预制柱间连接湿作业少,采用预制柱底部及顶部预埋钢板,且钢板与预制柱中纵筋进行焊接,相邻预制柱底部及顶部钢板焊接可认为相邻预制柱中的纵筋已可靠连接,且在不灌浆或灌浆不密实时不影响施工的顺利进行。3. A reverse construction method for a reinforced concrete frame structure steel slide jacking above ground as claimed in claim 1, characterized in that: there is less wet work to connect the prefabricated columns, the bottom and top of the prefabricated columns are embedded with steel plates, and the steel plates Welding with the longitudinal bars in the precast columns and welding the bottom and top steel plates of the adjacent precast columns can be considered to have reliably connected the longitudinal bars in the adjacent precast columns, and it will not affect the smooth progress of the construction when grouting is not performed or the grouting is not dense. 4.如权利要求1所述的一种钢筋混凝土框架结构钢滑道顶升地上新建逆向施工方法,其特征在于:预制柱间间隙小,且为环形相连空间,通过预留波纹管向间隙灌浆,操作便捷,灌浆量小,且可通过出浆口判断灌浆是否饱满。4. A reverse construction method for a reinforced concrete frame structure steel slide jacking above ground as claimed in claim 1, characterized in that: the gaps between the prefabricated columns are small and are annular connected spaces, and the gaps are grouted through reserved bellows. , easy to operate, small grouting volume, and whether the grouting is full can be judged through the grouting outlet. 5.如权利要求1所述的一种钢筋混凝土框架结构钢滑道顶升地上新建逆向施工方法,其特征在于:底部楼层下预制柱预埋钢板与基础内预埋底板进行焊接,并在底部浇筑500高外包柱脚混凝土,使预制柱与基础形成可靠整体。5. A reverse construction method for a reinforced concrete frame structure steel slide jacking above ground as claimed in claim 1, characterized in that: the prefabricated column embedded steel plate under the bottom floor is welded to the embedded bottom plate in the foundation, and the precast steel plate is welded to the bottom floor. The 500-meter-high outer column base concrete is poured to form a reliable integration between the prefabricated columns and the foundation.
CN202310324372.9A 2023-03-29 2023-03-29 A reverse construction method for new construction above ground with reinforced concrete frame structure steel slideway jacking Pending CN116856550A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310324372.9A CN116856550A (en) 2023-03-29 2023-03-29 A reverse construction method for new construction above ground with reinforced concrete frame structure steel slideway jacking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310324372.9A CN116856550A (en) 2023-03-29 2023-03-29 A reverse construction method for new construction above ground with reinforced concrete frame structure steel slideway jacking

Publications (1)

Publication Number Publication Date
CN116856550A true CN116856550A (en) 2023-10-10

Family

ID=88225555

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310324372.9A Pending CN116856550A (en) 2023-03-29 2023-03-29 A reverse construction method for new construction above ground with reinforced concrete frame structure steel slideway jacking

Country Status (1)

Country Link
CN (1) CN116856550A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2025001278A1 (en) * 2024-02-07 2025-01-02 山东润国建筑工业科技有限公司 Jacking-type reverse construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008255636A (en) * 2007-04-04 2008-10-23 Kajima Corp RC beam construction method
CN101538897A (en) * 2009-04-10 2009-09-23 袁斌 Construction method for main project of reinforced concrete building
CN104989121A (en) * 2015-07-24 2015-10-21 武大巨成结构股份有限公司 Steel slide way jacking building layer increasing device
CN105839784A (en) * 2016-03-17 2016-08-10 杨春 Assemble-jacking type building construction method
CN107542267A (en) * 2016-06-28 2018-01-05 中国二十冶集团有限公司 The jacking contrary sequence method of skyscraper
CN108360685A (en) * 2018-02-12 2018-08-03 杨春 Monoblock type jack-up construction method
CN112112283A (en) * 2019-06-19 2020-12-22 高继良 Layered flow structure installation method matched with fabricated building jacking construction method
CN114562071A (en) * 2022-03-17 2022-05-31 华侨大学 Grouting joint bar compaction grouting sleeve precast concrete column and construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008255636A (en) * 2007-04-04 2008-10-23 Kajima Corp RC beam construction method
CN101538897A (en) * 2009-04-10 2009-09-23 袁斌 Construction method for main project of reinforced concrete building
CN104989121A (en) * 2015-07-24 2015-10-21 武大巨成结构股份有限公司 Steel slide way jacking building layer increasing device
CN105839784A (en) * 2016-03-17 2016-08-10 杨春 Assemble-jacking type building construction method
CN107542267A (en) * 2016-06-28 2018-01-05 中国二十冶集团有限公司 The jacking contrary sequence method of skyscraper
CN108360685A (en) * 2018-02-12 2018-08-03 杨春 Monoblock type jack-up construction method
CN112112283A (en) * 2019-06-19 2020-12-22 高继良 Layered flow structure installation method matched with fabricated building jacking construction method
CN114562071A (en) * 2022-03-17 2022-05-31 华侨大学 Grouting joint bar compaction grouting sleeve precast concrete column and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2025001278A1 (en) * 2024-02-07 2025-01-02 山东润国建筑工业科技有限公司 Jacking-type reverse construction method

Similar Documents

Publication Publication Date Title
CN105839784B (en) Assembled jacking type construction techniques
CN106121039A (en) Villages and small towns masonry structure assembled integral ring beam and construction column combination technique
CN101775844A (en) Connecting joint of ring beam of steel core concrete column used for topdown construction method foundation pit engineering
CN107090908B (en) A joint connection method of vertical prefabricated components
CN103850363A (en) Prefabricated through-hole assembled reinforced concrete shear wall and its construction method
CN108867860A (en) A kind of precast reinforced concrete beam plate body system and prefabricated rod structure entirety assembling constructing method
CN111188457A (en) Edge sealing beam structure of super high-rise steel structure building and construction method
CN112502714A (en) Assembled shaft barrel structure and design and construction method
CN110670722A (en) Implementation method of beam-column connecting node of fabricated building
CN114541242A (en) Hoop type concrete connecting structure of assembly type pier stud and pile foundation and construction method
CN116220384A (en) Synchronous construction method for steel structure frame and reinforced concrete core tube
CN112160594B (en) Construction method beneficial to resisting horizontal force of multi-layer special-shaped steel structure building
CN116856752A (en) A kind of steel slide jacking technology and construction method
CN116856550A (en) A reverse construction method for new construction above ground with reinforced concrete frame structure steel slideway jacking
CN114263275B (en) Construction method for same-layer construction of high-rise assembled steel structure-core tube
CN117027183A (en) Pistil steel structure and construction method thereof
CN105040810B (en) Suitable for the connecting node of frame supported shear wall structure reverse construction
CN202401667U (en) Prefabricated column with reserved embedded column porous channel and embedded column type full-assembly anti-seismic building
CN116791750B (en) Construction method for reverse newly-built column connection structure based on self-locking anchoring technology
CN104775363A (en) Assembling method of steel bar segments of upper tower column
WO2025152576A1 (en) Segmented jacking device with alternately stressed steel slideways and column cores and construction method therefor
CN104963344B (en) The deep basal pit underground construction method that concrete supporting removal and structure construction are synchronously carried out
CN104032859B (en) Assembled L-shaped mixing coupled wall and construction method thereof
CN115162697B (en) Special-shaped column construction work I-shaped steel cantilever platform and construction method
CN219011479U (en) Assembled frame connecting node and assembled frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination