CN116771122A - A construction method for a T-shaped cantilevered unloading platform in a C-shaped material yard - Google Patents
A construction method for a T-shaped cantilevered unloading platform in a C-shaped material yard Download PDFInfo
- Publication number
- CN116771122A CN116771122A CN202310757848.8A CN202310757848A CN116771122A CN 116771122 A CN116771122 A CN 116771122A CN 202310757848 A CN202310757848 A CN 202310757848A CN 116771122 A CN116771122 A CN 116771122A
- Authority
- CN
- China
- Prior art keywords
- shaped
- construction
- construction method
- bailey
- unloading platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/166—Landings, receiving platforms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G25/00—Shores or struts; Chocks
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
本发明涉及一种C型料场T型悬挑卸料平台施工方法,包括如下步骤:一、安装贝雷架,在刮板机上轨道平台上利用吊车按照方案图纸安装贝雷架单元;二、搭设支模架体,围绕T型悬挑梁的结构柱,通过设置的工字钢连接梁及U型螺栓将支模架体安装于所述贝雷架体上;三、安装主、次龙骨,将主龙骨和次龙骨安装于所述支模架体上;四、浇筑混凝土,全部安装完成后,并检查合格后,交付钢筋班组进行钢筋安装绑扎作业,验收合格后,浇筑平台混凝土,合格后拆除支模架体。本发明的优点是,通过使用贝雷架与传统落地式满堂支撑架施工相比,节省了2/3的架体,提高施工进度,贴合绿色施工理念;利用T型悬挑梁结构柱进行贝雷架支模架体的搭设,提供了施工安全性。
The invention relates to a construction method of a T-shaped cantilevered unloading platform in a C-type material yard, which includes the following steps: 1. Install the rack, and use a crane on the upper track platform of the scraper to install the rack unit according to the plan drawings; 2. Set up the formwork body, surrounding the structural columns of the T-shaped cantilever beam, and install the formwork body on the Bailey frame body through the set I-beam connecting beams and U-shaped bolts; 3. Install the main and secondary keels , install the main keel and secondary keel on the formwork frame; 4. Pour the concrete. After all installations are completed and the inspection is qualified, the steel bar team is delivered to the steel bar installation and binding operation. After acceptance, the platform concrete is poured and it is qualified. Then remove the formwork body. The advantage of this invention is that compared with the traditional floor-standing full-hall support frame construction by using Bailey frames, 2/3 of the frame body is saved, the construction progress is improved, and it conforms to the green construction concept; T-shaped cantilever beam structural columns are used for construction The erection of the Bailey frame formwork body provides construction safety.
Description
技术领域Technical field
本发明涉及建筑施工技术领域,尤其是涉及一种C型料场钢筋混凝土T型悬挑卸料平台施工方法。The invention relates to the technical field of building construction, and in particular to a construction method of a C-shaped reinforced concrete T-shaped cantilevered unloading platform in a C-shaped material yard.
背景技术Background technique
目前,C型料场因其贮料能力大、占地省、操作灵活可靠、环保效果好等优势,近年来在冶金行业得到了广泛应用。At present, the C-type material yard has been widely used in the metallurgical industry in recent years due to its advantages such as large material storage capacity, space saving, flexible and reliable operation, and good environmental protection effect.
C型料场卸料平台一般为钢筋混凝土T型悬挑结构,悬挑长度大,支模高度超高,混凝土平台荷载重,是C型料场施工的重难点,属于超危大工程,需要组织专家论证。C型料场卸料平台模板支撑体系一般采用落地式满堂普通扣件式钢管脚手架和落地式满堂承插盘扣式脚手架。The C-type material yard unloading platform is generally a reinforced concrete T-shaped cantilever structure. The overhang length is large, the formwork height is extremely high, and the concrete platform has a heavy load. This is a major and difficult point in the construction of the C-type material yard. It is a super-hazardous large-scale project and requires Organize expert arguments. The C-type material yard unloading platform formwork support system generally adopts floor-standing full-hall ordinary fastener-type steel pipe scaffolding and floor-standing full-hall socket-disc buckle type scaffolding.
由于卸料平台高度高且长度长,通常高度能达到30m左右,长度一般为500m左右,采用落地式满堂普通扣件式钢管脚手架作为C型料场卸料平台模板支撑体,材料用量大,施工周期长,危险系数高,安全不易保证;采用落地式满堂承插盘扣式脚手架作为C型料场卸料平台模板支撑架体时,安全性能得到保证,但脚手架用量巨大,成本高,施工周期长。Due to the high height and long length of the unloading platform, usually the height can reach about 30m and the length is generally about 500m. Floor-standing full-length ordinary fastener-type steel pipe scaffolding is used as the C-type material yard unloading platform formwork support. The amount of material is large and the construction is difficult. The cycle is long, the risk factor is high, and safety is not easy to ensure; when using floor-standing full-floor socket-in-disk buckle scaffolding as the C-type material yard unloading platform formwork support frame, the safety performance is guaranteed, but the amount of scaffolding is huge, the cost is high, and the construction period long.
发明内容Contents of the invention
针对现有技术存在的不足,本发明的目的是提供一种C型料场T型悬挑卸料平台施工方法,包括:In view of the shortcomings of the existing technology, the purpose of the present invention is to provide a construction method for a T-shaped cantilevered unloading platform in a C-shaped material yard, including:
步骤一、安装贝雷架,在刮板机上轨道平台上利用吊车按照方案图纸安装贝雷架单元;Step 1. Install the rack, and use a crane on the upper rail platform of the scraper to install the rack unit according to the plan drawings;
步骤二、搭设支模架体,围绕T型悬挑梁的结构柱,通过设置的工字钢连接梁及U型螺栓将支模架体安装于所述贝雷架体上;Step 2: Set up the formwork body, surrounding the structural columns of the T-shaped cantilever beam, and install the formwork body on the Bailey frame body through the provided I-beam connecting beams and U-shaped bolts;
步骤三、安装主、次龙骨,将主龙骨和次龙骨安装于所述支模架体上;Step 3: Install the main and secondary keels, and install the main and secondary keels on the formwork body;
步骤四、浇筑混凝土,全部安装完成后,并检查合格后,交付钢筋班组进行钢筋安装绑扎作业,验收合格后,浇筑平台混凝土,合格后拆除支模架体。Step 4: Pour concrete. After all installations are completed and the inspection is qualified, the steel bar team will be handed over to install and tie the steel bars. After passing the inspection, the platform concrete will be poured. After passing the inspection, the formwork body will be removed.
进一步地,所述步骤一中,安装贝雷架时,利用上轨道螺栓固定,利用T型悬挑梁的结构柱作为贝雷架单元上拉固定点,安装上拉钢丝绳。Further, in step one, when installing the bailey frame, use the upper track bolts to fix it, use the structural column of the T-shaped cantilever beam as the pull-up fixed point of the bailey frame unit, and install the pull-up wire rope.
进一步地,所述步骤二中,搭设支模架体之前,安装工字钢连梁,利用U型螺栓与贝雷架固定,并在工字钢连接梁顶每根立杆的位置焊接一根竖向钢筋,用于搭设支模架体时便于套入。Further, in the second step, before erecting the formwork body, install the I-beam connecting beam, use U-shaped bolts to fix it with the bailey frame, and weld a vertical pole at the top of each vertical pole on the I-beam connecting beam. Directional steel bars are used to facilitate insertion when erecting the formwork body.
进一步地,工字钢连接梁安装完成后,采用脚手板及模板将工字钢连接梁之间的空隙封堵,形成硬防护。Furthermore, after the installation of the I-beam connecting beams is completed, scaffolding boards and templates are used to seal the gaps between the I-beam connecting beams to form hard protection.
进一步地,所述步骤二中,支模架体的搭设方法包括:围绕在工字钢连梁安装立杆、水平杆、竖向斜撑、水平剪刀撑及抱柱措施,梁底采用双槽钢托梁支撑。Further, in the second step, the erection method of the formwork body includes: installing vertical poles, horizontal poles, vertical diagonal braces, horizontal scissor braces and column holding measures around the I-beam connecting beams, and the bottom of the beam adopts double grooves. Steel joist supports.
进一步地,所述步骤二中,支模架体的外侧还安装三角托撑作为施工作业外防护。Furthermore, in the second step, a triangular support is installed on the outside of the formwork body as external protection during construction operations.
进一步地,所述步骤二中,在所述立杆的顶部设置U型托,并按照标高调整U型托的高度。Further, in the second step, a U-shaped bracket is provided on the top of the vertical pole, and the height of the U-shaped bracket is adjusted according to the elevation.
进一步地,所述步骤二中,在作业面以下安装防坠网。Further, in the second step, an anti-fall net is installed below the working surface.
进一步地,所述步骤四中,所述混凝土的浇筑方法为:用两台泵车同时从中间至两侧对称浇筑。Further, in the fourth step, the concrete pouring method is: using two pump trucks to pour symmetrically from the middle to both sides at the same time.
进一步地,所述步骤一中,所述贝雷架安装之前,在地面将贝雷片拼装成贝雷架单元,18片贝雷片为一个单元。Further, in the first step, before installing the rack, the racks are assembled on the ground into a unit of the rack, with 18 racks being one unit.
综上所述,本发明的有益技术效果为:本发明提出了C型料场T型悬挑卸料平台施工方法,通过使用贝雷架,本发明与传统落地式满堂支撑架施工相比,节省了2/3的架体(传统架体支模高度30m左右,本发明支模高度10m左右),提高了施工安全和施工进度,贴合绿色施工理念;并利用T型悬挑梁的结构柱进行贝雷架与支模架体的搭设,提供了施工过程中的安全性。To sum up, the beneficial technical effects of the present invention are: the present invention proposes a construction method for a T-shaped cantilevered unloading platform in a C-shaped material yard. By using Bailey frames, compared with the construction of traditional floor-standing full-hall support frames, the present invention 2/3 of the frame is saved (the formwork height of the traditional frame is about 30m, the formwork height of the present invention is about 10m), which improves construction safety and construction progress, conforms to the green construction concept; and utilizes the T-shaped cantilever beam structure The columns are used to erect the Bailey frame and the formwork body, which provides safety during the construction process.
附图说明Description of drawings
通过以下参照附图对本发明实施例的描述,本发明的上述以及其他目的特征和优点将更为清楚。附图仅用于表示优选实施例方式的目的,而并不认为是对本发明的限制。而且在整个附图中,用相同的参考符号表示相同的部件。The above and other objects, features and advantages of the present invention will become more apparent through the following description of the embodiments of the present invention with reference to the accompanying drawings. The drawings are for the purpose of illustrating preferred embodiments only and are not to be construed as limitations of the invention. Also throughout the drawings, the same reference characters are used to designate the same components.
图1是本发明的施工方法流程示意;Figure 1 is a schematic flow chart of the construction method of the present invention;
图2是本发明中贝雷架施工结构图一;Figure 2 is the construction structure diagram 1 of the Bailey frame in the present invention;
图3是本发明中贝雷架施工结构图二;Figure 3 is the second structural diagram of the construction of the Bailey frame in the present invention;
图4是本发明中贝雷架施工结构图三;Figure 4 is the third structural diagram of the construction of the Bailey frame in the present invention;
图5是本发明中支模架体施工过程结构图一;Figure 5 is a structural diagram of the construction process of the formwork body in the present invention;
图6是本发明中支模架体施工过程结构图二;Figure 6 is the second structural diagram of the construction process of the formwork body in the present invention;
图7是本发明中支模架体施工过程结构图三;Figure 7 is the third structural diagram of the construction process of the formwork body in the present invention;
图8是本发明中支模架体施工过程结构图四;Figure 8 is a structural diagram 4 of the construction process of the formwork body in the present invention;
图9是本发明中主次龙骨架施工结构示意图一;Figure 9 is a schematic diagram of the construction structure of the primary and secondary dragon frames in the present invention;
图10是本发明中主次龙骨架施工结构示意图二;Figure 10 is a schematic diagram 2 of the construction structure of the primary and secondary dragon skeleton in the present invention;
图11是本发明中浇筑混凝土方法示意图;Figure 11 is a schematic diagram of the concrete pouring method in the present invention;
图中,1、贝雷架单元,2、上轨道螺栓,3、上拉钢丝绳,4、工字钢连梁,5、U型螺栓,6、竖向钢筋,7、立杆,8、脚手架,9、模板,10、水平杆,11、竖向斜撑,12、水平剪刀撑,13、抱柱措施,14、双槽钢托梁支撑,15、U托,16、三角托撑,17、防坠网,18、主龙骨,19、次龙骨。In the picture, 1. Bailey frame unit, 2. Upper track bolts, 3. Pull-up wire rope, 4. I-beam connecting beam, 5. U-shaped bolts, 6. Vertical steel bars, 7. Vertical poles, 8. Scaffolding, 9. Formwork, 10. Horizontal pole, 11. Vertical diagonal brace, 12. Horizontal scissor brace, 13. Column holding measures, 14. Double channel steel joist support, 15. U bracket, 16. Triangular bracket, 17. Anti-fall net, 18, main keel, 19, secondary keel.
具体实施方式Detailed ways
以下结合附图对本发明作进一步详细说明。虽然附图中显示了本公开的示例性实施例,然而应当理解,可以以各种形式实现本公开而不应被这里阐述的实施例所限制。相反,提供这些实施例是为了能够更透彻地理解本公开,并且能够将本公开的范围完整的传达给本领域的技术人员。需要说明的是,在不冲突的情况下,本发明中的实施例及实施例中的特征可以相互组合。The present invention will be further described in detail below with reference to the accompanying drawings. Although exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be implemented in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided to provide a thorough understanding of the disclosure, and to fully convey the scope of the disclosure to those skilled in the art. It should be noted that, as long as there is no conflict, the embodiments and features in the embodiments of the present invention can be combined with each other.
参照图1所示,为本发明公开的一种C型料场T型悬挑卸料平台施工方法,包括:步骤一、安装贝雷架,在刮板机上轨道平台上利用吊车按照方案图纸安装贝雷架单元;步骤二、搭设支模架体,围绕T型悬挑梁的结构柱,通过设置的工字钢连接梁及U型螺栓将支模架体安装于所述贝雷架体上;步骤三、安装主、次龙骨,将主龙骨和次龙骨安装于所述支模架体上;步骤四、浇筑混凝土,全部安装完成后,并检查合格后,交付钢筋班组进行钢筋安装绑扎作业,验收合格后,浇筑平台混凝土,合格后拆除支模架体。Referring to Figure 1 , a construction method for a T-shaped cantilevered unloading platform in a C-shaped material yard disclosed by the present invention includes: Step 1: Install the Bailey frame, and install it on the upper track platform of the scraper using a crane according to the plan drawings. Bailey frame unit; Step 2: Set up the formwork body around the structural columns of the T-shaped cantilever beam, and install the formwork body on the Bailey frame body through the set I-beam connecting beams and U-shaped bolts ; Step 3, install the main and secondary keels, and install the main keels and secondary keels on the formwork frame; Step 4, pour the concrete. After all installations are completed and the inspection is qualified, deliver the steel bars to the steel bar team for installation and binding of steel bars. , after the acceptance is passed, the platform concrete is poured, and the formwork body is removed after passing the inspection.
该施工方法的最优选实施例如下(参照图2-11所示)The most preferred embodiment of this construction method is as follows (see Figure 2-11)
1、施工准备1. Construction preparation
施工机具、作业条件及劳动力准备,贝雷架组装,在地面将贝雷片拼装成贝雷架单元,18片贝雷片为一个单元。其中采用贝雷架,在施工成本方面,贝雷架支撑系统的耗价仅占钢管脚手架支撑系统耗价的70%;在施工周期方面,安装与拆卸贝雷架支撑系统的时间也非常短,可以大幅缩短作业工期;此外,采用贝雷架支撑系统可以为施工人员提供更大的作业空间,它的稳定性也非常高,可降低安全事故发生的概率。本实施例中,采用贝雷架节省了2/3的架体,传统架体支模高度30m左右,本发明支模高度10m左右,提高了施工安全和施工进度,贴合绿色施工理念。Construction machinery and tools, operating conditions and labor preparation, and assembly of the Bailey frame. The Bailey pieces are assembled on the ground into a Bailey frame unit, with 18 Bailey pieces as one unit. Among them, the Bailey frame is used. In terms of construction cost, the cost of the Bailey frame support system only accounts for 70% of the cost of the steel pipe scaffolding support system; in terms of construction period, the time to install and dismantle the Bailey frame support system is also very short. The construction period can be greatly shortened; in addition, the use of the Bayley support system can provide construction workers with a larger working space. Its stability is also very high, which can reduce the probability of safety accidents. In this embodiment, the use of Bailey frames saves 2/3 of the frame body. The formwork height of the traditional frame body is about 30m, while the formwork height of the present invention is about 10m, which improves construction safety and construction progress, and conforms to the green construction concept.
2、安装贝雷架2. Install the Bailey rack
在刮板机上轨道平台上利用吊车按照方案图纸安装贝雷架单元1;贝雷架单元利用上轨道螺栓2固定;利用浇筑完成的结构柱作为贝雷架单元上拉固定点安装上拉钢丝绳3,参照图2所示,本实施例中,利用T型悬挑梁的结构柱进行贝雷架与支模架体的搭设,提供了施工过程中的安全性。Use a crane on the upper rail platform of the scraper to install the Bailey frame unit 1 according to the plan drawing; the Bailey frame unit is fixed with the upper track bolts 2; use the cast structural column as the pull-up fixed point of the Bailey frame unit to install the pull-up wire rope 3. Referring to Figure 2, in this embodiment, the structural columns of T-shaped cantilever beams are used to erect the Bailey frame and the formwork body, which provides safety during the construction process.
3、安装工字钢连梁,安装硬防护3. Install I-beam connecting beams and install hard protection
按照支撑架体平面布置图安装工字钢连梁4;利用U型螺栓5与贝雷架1固定;在钢梁4顶每根立杆的位置焊接一根竖向钢筋6,搭支模架时立杆7套入钢筋,防止立杆移位;连梁安装完成后,采用脚手板8及模板9将连梁之间的空隙封堵,形成硬防护;参照图3-5所示。Install the I-beam connecting beam 4 according to the plan layout of the support frame; use U-shaped bolts 5 to fix it with the Bailey frame 1; weld a vertical steel bar 6 at the position of each vertical pole on top of the steel beam 4. When setting up the formwork The vertical poles 7 are inserted into the steel bars to prevent the vertical poles from shifting; after the coupling beams are installed, scaffolding boards 8 and templates 9 are used to seal the gaps between the coupling beams to form hard protection; refer to Figure 3-5.
4、搭设支模架体4. Set up the formwork body
在工字钢连梁安装立杆7、水平杆10、竖向斜撑11、水平剪刀撑12(附图中未标出)及抱柱措施13,梁底采用双槽钢托梁支撑14,并按照标高调整顶部U托15高度,并在架体外侧安装三角托撑16作为施工作业外防护,在作业面以下安装防坠网17,如图5-8所示。Install vertical poles 7, horizontal poles 10, vertical diagonal braces 11, horizontal scissor braces 12 (not shown in the drawings) and column holding measures 13 on the I-beam connecting beam. The bottom of the beam is supported by double channel steel joists 14. Adjust the height of the top U bracket 15 according to the elevation, install a triangular bracket 16 on the outside of the frame as external protection during construction operations, and install an anti-fall net 17 below the working surface, as shown in Figure 5-8.
5、安装主次龙骨及模板5. Install primary and secondary keels and templates
安装主龙骨18、次龙骨19及模板9,如图9-10所示。Install main keel 18, secondary keel 19 and template 9, as shown in Figure 9-10.
6、检查验收,钢筋安装6. Inspection and acceptance, steel bar installation
全部安装完成后,检查各项参数是否符合方案及规范要求,满足要求后,交付钢筋班组进行钢筋安装绑扎作业。After all installations are completed, check whether all parameters comply with the plan and specification requirements. Once the requirements are met, the steel bar team will be handed over to install and tie the steel bars.
7、浇筑混凝土7. Pouring concrete
钢筋安装绑扎完成,验收合格后,浇筑平台混凝土,浇筑时应采用两台泵车同时从中间至两侧对称浇筑,以防荷载不均匀影响施工安全,如图11所示。After the steel bars are installed and tied, and after passing the acceptance inspection, the concrete for the platform should be poured. During pouring, two pump trucks should be used to pour symmetrically from the middle to both sides at the same time to prevent uneven loads from affecting construction safety, as shown in Figure 11.
8、混凝土养护8. Concrete maintenance
浇筑完成后严格按照施工规范进行混凝土养护。After the pouring is completed, the concrete shall be cured in strict accordance with the construction specifications.
9、模板及架体拆除9. Dismantling the formwork and frame
混凝土同条件试块强度达到100%时,方可拆除模板及脚手架,拆除时严格按照相关操作规程及规范作业。Only when the strength of the concrete test block under the same conditions reaches 100% can the formwork and scaffolding be dismantled. During disassembly, the relevant operating procedures and specifications must be strictly followed.
本发明实施例公开的一种C型料场T型悬挑卸料平台施工方法,具有如下优点:通过使用贝雷架,本发明与传统落地式满堂支撑架施工相比,节省了2/3的架体(传统架体支模高度30m左右,本发明支模高度10m左右),提高了施工安全和施工进度,贴合绿色施工理念;并利用T型悬挑梁的结构柱进行贝雷架与支模架体的搭设,提供了施工过程中的安全性。The embodiment of the present invention discloses a construction method for a T-shaped cantilevered unloading platform in a C-type material yard, which has the following advantages: by using the Bailey frame, the present invention saves 2/3 compared with the construction of the traditional floor-standing full-hall support frame. The frame body (the formwork height of the traditional frame body is about 30m, the formwork height of the present invention is about 10m), which improves construction safety and construction progress, conforms to the green construction concept; and uses the structural columns of T-shaped cantilever beams to carry out the Bailey frame The erection with the formwork body provides safety during the construction process.
应当说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。It should be noted that in this article, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply that these entities or operations are mutually exclusive. any such actual relationship or sequence exists between them. Furthermore, the terms "comprises," "comprises," or any other variations thereof are intended to cover a non-exclusive inclusion such that a process, method, article, or apparatus that includes a list of elements includes not only those elements, but also those not expressly listed other elements, or elements inherent to the process, method, article or equipment. Without further limitation, an element defined by the statement "comprises a..." does not exclude the presence of additional identical elements in a process, method, article, or apparatus that includes the stated element.
最后应说明的是:显然,上述实施例仅仅是为清楚地说明本发明所作的举例,而并非对实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里无需也无法对所有的实施方式予以穷举。而由此所引申出的显而易见的变化或变动仍处于本发明的保护范围之中。Finally, it should be noted that: obviously, the above-mentioned embodiments are only examples to clearly illustrate the present invention, and are not intended to limit the implementation. For those of ordinary skill in the art, other different forms of changes or modifications can be made based on the above description. An exhaustive list of all implementations is neither necessary nor possible. However, obvious changes or modifications derived therefrom are still within the protection scope of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310757848.8A CN116771122A (en) | 2023-06-26 | 2023-06-26 | A construction method for a T-shaped cantilevered unloading platform in a C-shaped material yard |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310757848.8A CN116771122A (en) | 2023-06-26 | 2023-06-26 | A construction method for a T-shaped cantilevered unloading platform in a C-shaped material yard |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116771122A true CN116771122A (en) | 2023-09-19 |
Family
ID=88013014
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310757848.8A Pending CN116771122A (en) | 2023-06-26 | 2023-06-26 | A construction method for a T-shaped cantilevered unloading platform in a C-shaped material yard |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116771122A (en) |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101649604A (en) * | 2009-08-28 | 2010-02-17 | 中铁八局集团第一工程有限公司 | Construction bracket of 1# block of inclined pull bridge and constructing method thereof |
| CN208685427U (en) * | 2018-04-30 | 2019-04-02 | 安徽省公路桥梁工程有限公司 | Assembled steel suspension bridge structure |
| CN111042006A (en) * | 2020-01-16 | 2020-04-21 | 中建七局安装工程有限公司 | High pier edge span suspension casting beam Bailey truss structure and construction method thereof |
| CN214271734U (en) * | 2020-09-05 | 2021-09-24 | 中交第四公路工程局有限公司 | Reinforced structure of long-span steel trestle |
| CN216587872U (en) * | 2021-12-20 | 2022-05-24 | 中国二冶集团有限公司 | Supporting device |
| CN217231491U (en) * | 2022-03-31 | 2022-08-19 | 广州工程总承包集团有限公司 | Two-way support system of pre-buried formula in operation pier position on water |
-
2023
- 2023-06-26 CN CN202310757848.8A patent/CN116771122A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101649604A (en) * | 2009-08-28 | 2010-02-17 | 中铁八局集团第一工程有限公司 | Construction bracket of 1# block of inclined pull bridge and constructing method thereof |
| CN208685427U (en) * | 2018-04-30 | 2019-04-02 | 安徽省公路桥梁工程有限公司 | Assembled steel suspension bridge structure |
| CN111042006A (en) * | 2020-01-16 | 2020-04-21 | 中建七局安装工程有限公司 | High pier edge span suspension casting beam Bailey truss structure and construction method thereof |
| CN214271734U (en) * | 2020-09-05 | 2021-09-24 | 中交第四公路工程局有限公司 | Reinforced structure of long-span steel trestle |
| CN216587872U (en) * | 2021-12-20 | 2022-05-24 | 中国二冶集团有限公司 | Supporting device |
| CN217231491U (en) * | 2022-03-31 | 2022-08-19 | 广州工程总承包集团有限公司 | Two-way support system of pre-buried formula in operation pier position on water |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103452311B (en) | A kind of erection method of shaped steel suspended structural support frame | |
| CN105971274A (en) | Cantilever support frame formwork system and construction method thereof | |
| CN105803947B (en) | A kind of cast-in-situ box girder gate-type full framing whole lateral moving system and method for traversing | |
| CN205443958U (en) | Composite truss support of big cantilever bent cap | |
| CN113550578A (en) | A kind of high-altitude cantilever structure formwork support and construction method of upper protection system | |
| CN110878522B (en) | Construction system and construction method of beam under main tower | |
| CN109457814B (en) | Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure | |
| CN109267487A (en) | A kind of long big section bent cap bracket system of overhanging | |
| CN103469735B (en) | The installation method of the formwork of the solid section of the pier top of the hollow column and slab pier with curved superelevation | |
| CN108360380A (en) | A kind of bridge pier column construction operation platform and its construction method | |
| CN106522102A (en) | Side span construction support, rigid frame bridge side span and rigid frame bridge | |
| CN107687254A (en) | A kind of concrete disjunctor group storehouse slip form construction device and construction method | |
| CN111749142A (en) | A BIM-based 0# block prefabricated bracket design and construction method | |
| CN109869153A (en) | The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method | |
| CN205653708U (en) | Work platform that inclined plane climbed follows | |
| CN204282803U (en) | To encorbelment formwork structure for mounting platform | |
| CN217151150U (en) | Overhanging steel truss formwork supporting platform for aluminum mould-full concrete outer wall | |
| CN104963295A (en) | Support frame for non-ground internal-force balanced cast-in-place beam and construction method thereof | |
| CN204662929U (en) | A kind of cross-line walking fence operation device | |
| CN115538678A (en) | Construction method for large-angle overhanging landscape platform side small platform | |
| CN222990595U (en) | Multifunctional portal for suspension bridge construction | |
| CN111593874B (en) | Support system and construction method for super-high-rise residential transfer layer super-heavy cantilevered components | |
| CN105544402B (en) | A kind of hanging gang form support frame and construction method for pier capping beam high | |
| CN210025768U (en) | A operation platform system for caisson template installation | |
| CN116771122A (en) | A construction method for a T-shaped cantilevered unloading platform in a C-shaped material yard |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |