CN116752789A - A method for retrofitting and strengthening roof suspension beams by pulling out columns - Google Patents
A method for retrofitting and strengthening roof suspension beams by pulling out columns Download PDFInfo
- Publication number
- CN116752789A CN116752789A CN202310194594.3A CN202310194594A CN116752789A CN 116752789 A CN116752789 A CN 116752789A CN 202310194594 A CN202310194594 A CN 202310194594A CN 116752789 A CN116752789 A CN 116752789A
- Authority
- CN
- China
- Prior art keywords
- column
- roof
- steel
- steel arch
- rods
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
本发明提供了一种屋面吊梁拨柱加固改造方法,属建筑技术领域,旨在解决现有托梁拔柱技术影响建筑净高、需加固周边构件等次生问题。本发明技术要点主要包括以下步骤:对需要架设钢拱架的立柱加高,得到支撑钢拱架的柱帽,将工厂加工好的钢拱架运至施工现场放置在加高柱帽处,钢拱架与拟加固屋面梁通过Y形吊杆相连,屋面荷载通过Y形吊杆传递到钢拱架。同时在钢拱架两拱脚处增设的预应力钢索,以平衡钢拱架受吊杆传来屋面荷载后拱脚处产生的水平推力。钢拱架、Y形吊杆以及预应力钢索形成独立受力体系,受力性能优异,传力路径明确,确保因拆除柱而缺少支撑的屋面梁挠度、裂缝、承载力要求,创造性的提供了一种新的加固改造方法。
The invention provides a roof suspension beam pulling column reinforcement and transformation method, which belongs to the field of construction technology and aims to solve secondary problems such as the existing joist column pulling technology affecting the clear height of the building and the need to reinforce surrounding components. The technical key points of the present invention mainly include the following steps: heighten the columns that need to be erected with steel arch frames, obtain column caps that support the steel arch frames, transport the factory-processed steel arch frames to the construction site and place them at the heightened column caps. The arch frame and the roof beam to be reinforced are connected through a Y-shaped hanger, and the roof load is transmitted to the steel arch frame through the Y-shaped hanger. At the same time, prestressed steel cables are added at the two arch feet of the steel arch to balance the horizontal thrust generated at the arch feet after the steel arch receives the roof load from the hanger. Steel arches, Y-shaped hangers and prestressed steel cables form an independent stress-bearing system with excellent stress-bearing performance and clear force transmission paths to ensure the deflection, cracks and bearing capacity requirements of roof beams that lack support due to the removal of columns, and creatively provide A new reinforcement and transformation method was developed.
Description
技术领域Technical field
本发明属于建筑技术领域,涉及一种屋面吊梁拔柱改造加固方法。The invention belongs to the field of construction technology and relates to a roof suspension beam pulling out column reconstruction and reinforcement method.
背景技术Background technique
托梁拔柱是托屋架拔柱、托梁拆墙及托梁拆柱的总称,是在不拆或少拆上部结构的情况下实施拆除、更换、接长柱子的一门综合性技术,包括相关结构加固技术、上部结构顶升技术及断柱技术等。与传统的大掀盖改造相比,托梁拔柱法具有对生产及生活影响小,改造时间短、费用低等优点。Joist column pulling is a general term for roof truss column pulling, joist wall removal, and joist column removal. It is a comprehensive technology that removes, replaces, and extends columns without dismantling or dismantling the superstructure, including Relevant structural reinforcement technology, superstructure jacking technology and column breaking technology, etc. Compared with the traditional large-scale cover renovation, the joist and column pulling method has the advantages of less impact on production and life, shorter renovation time, and lower cost.
现有的托梁拔柱施工主要是在梁底增设支撑或者增加预应力钢筋,此方法不仅降低了房屋使用高度,而且需要进行较大范围的结构加固处理,对建筑原结构扰动比较大,尤其是对立柱处影响更加明显。The existing construction of pulling out joists and columns mainly involves adding supports or adding prestressed steel bars at the bottom of the beams. This method not only reduces the height of the house, but also requires a large range of structural reinforcement, which greatly disturbs the original structure of the building, especially The impact on the pillars is more obvious.
发明内容Contents of the invention
本发明的目的是针对现有技术存在的上述问题,提供一种对建筑原结构扰动小、传力路径明确且施工简便快捷的屋面吊梁拔柱加固改造方法。The purpose of the present invention is to solve the above-mentioned problems existing in the prior art and provide a method for reinforcing and transforming roof beams by pulling out columns with little disturbance to the original structure of the building, a clear force transmission path, and simple and quick construction.
本发明的目的可通过下列技术方案来实现:The object of the present invention can be achieved through the following technical solutions:
一种屋面吊梁拔柱加固改造方法,拟对相应立柱进行拆除,并对由于立柱拆除后导致跨度增大的屋面梁增设支撑,其特征在于:该加固方法包括以下步骤:A method for reinforcing and transforming roof suspension beams by pulling out columns. It is intended to dismantle the corresponding columns and add supports to the roof beams whose spans have increased due to the removal of the columns. It is characterized in that: the reinforcement method includes the following steps:
A、钢拱架制备:准备上弦杆、下弦杆、腹杆和钢索,上述上弦杆、下弦杆均呈弧形且两者上下设置,上述腹杆的数量为若干根,若干腹杆沿上弦杆的长度方向均布连接在上弦杆和下弦杆之间,得到两端朝下且呈弧形的钢拱架,最后将钢索连接在钢拱架的两端之间;A. Preparation of steel arch frame: prepare the upper chord bar, lower chord bar, web bar and steel cable. The above-mentioned upper chord bar and lower chord bar are both arc-shaped and arranged up and down. The number of the above-mentioned web bar is several, and several web bars are arranged along the upper chord. The length direction of the rods is evenly connected between the upper chord rods and the lower chord rods, resulting in a steel arch with both ends facing downwards and an arc shape. Finally, the steel cables are connected between the two ends of the steel arch;
上弦杆和下弦杆的数量均为两根,上弦杆和上弦杆之间也具有腹杆,下弦杆和下弦杆之间也具有腹杆;The number of upper chord rods and lower chord rods is two. There are also web rods between the upper chord rods and the upper chord rods, and there are also web rods between the lower chord rods and the lower chord rods;
B、立柱上端处理:立柱上端进行凿毛处理并通过混凝土浇筑得到凸出的加高柱帽;B. Treatment of the upper end of the column: The upper end of the column is chiseled and concrete is poured to obtain a protruding and heightened column cap;
C、连接作业一:钢拱架的一端连接在其中一根立柱的加高柱帽处,钢拱架的另一端连接在另外一根立柱的加高柱帽处;C. Connection operation one: One end of the steel arch frame is connected to the heightened column cap of one of the columns, and the other end of the steel arch frame is connected to the heightened column cap of the other column;
D、连接作业二:准备Y形的吊杆,将吊杆的上端固连在钢拱架上,将吊杆的下端固连在屋面梁处;D. Connection operation 2: Prepare a Y-shaped boom, secure the upper end of the boom to the steel arch, and secure the lower end of the boom to the roof beam;
E、上述步骤BCD后在对应的屋面梁上部得到加固单榀拱架,相邻两屋面梁的加固单榀拱架成型后采用水平的连杆将相邻两加固单榀拱架连接。E. After the above steps BCD, a reinforced single-frame arch frame is obtained on the upper part of the corresponding roof beam. After the reinforced single-frame arch frame of the two adjacent roof beams is formed, a horizontal connecting rod is used to connect the two adjacent reinforced single-frame arch frames.
本屋面吊梁拔柱加固改造方法创造性的预先制备钢拱架,立柱上端处理后形成具备足够连接位置且凸出的加高柱帽。This roof suspension beam column reinforcement and transformation method creatively prepares steel arch frames in advance, and the upper ends of the columns are processed to form elevated column caps with sufficient connection positions and protrusions.
连接作业一后能使钢拱架稳定的连接在其中一根立柱的加高柱帽上,连接作业二后能使吊杆稳定的连接在钢拱架与屋面梁之间。After the first connection operation, the steel arch can be stably connected to the heightened column cap of one of the columns. After the second connection operation, the hanger can be stably connected between the steel arch and the roof beam.
上述加固施工作业后能将屋面荷载传递至钢拱架。同时,高强预应力的钢索由于连接在钢拱架两端,因此,通过钢索能平衡钢拱架端部处水平作用力。After the above reinforcement construction operations, the roof load can be transferred to the steel arch. At the same time, high-strength prestressed steel cables are connected to both ends of the steel arch, so the horizontal forces at the ends of the steel arch can be balanced by the steel cables.
也就是说,钢拱架形成单独的受力体系,将荷载以竖向轴力传递给钢拱架支撑柱,避免因拔柱后此处梁柱节点弯矩过大而发生破坏,最大限度的保护原结构。That is to say, the steel arch forms a separate force-bearing system, which transmits the load to the steel arch support columns in the form of vertical axial force to avoid damage due to excessive bending moments of the beam-column nodes after the columns are pulled out, and maximize the Preserve the original structure.
对应立柱上端经过BCD步骤处理后,单个钢拱架稳定的连接在对应的立柱上,得到单个的加固单榀拱架。After the upper ends of the corresponding columns are processed through the BCD step, a single steel arch is stably connected to the corresponding column to obtain a single reinforced single arch.
步骤E中通过水平设置的连杆将相邻的两个加固单榀拱架稳定连接,最终完成整个屋面吊梁拨柱的加固处理。当然,加固后将拟拆除的立柱按照设定长度截断即可。In step E, the two adjacent reinforced single arch frames are stably connected through horizontal connecting rods, and finally the reinforcement of the entire roof suspension beam and column is completed. Of course, after reinforcement, the column to be removed can be cut off according to the set length.
在上述的屋面吊梁拔柱加固改造方法中,所述步骤A中上弦杆、下弦杆、腹杆和钢索连接成一整体式结构后运输至施工场合。In the above-mentioned method of pulling out column reinforcements for roof suspension beams, in step A, the upper chord, lower chord, web rod and steel cable are connected into an integral structure and then transported to the construction site.
钢拱架作为预制件运输至施工场合安装,能减少施工时间,提高作业效率。Steel arch frames are transported to the construction site as prefabricated parts for installation, which can reduce construction time and improve work efficiency.
在上述的屋面吊梁拔柱加固改造方法中,所述步骤A中对钢拱架制备为若干段半成品,将半成品运输至施工场合处拼接。In the above-mentioned method for reinforcing and transforming roof beams by pulling out columns, in step A, the steel arch frame is prepared into several sections of semi-finished products, and the semi-finished products are transported to the construction site for splicing.
钢拱架分段制备,这样便于运输,对于受限的安装施工场合,它也能适应,有效的提高适用性。The steel arch frame is prepared in sections, which facilitates transportation. It can also be adapted to restricted installation and construction situations, effectively improving applicability.
在上述的屋面吊梁拔柱加固改造方法中,所述步骤B中凿毛处理后在立柱上端植入锚固钢筋,钢筋处连接锚垫板,然后浇筑混凝土将上述锚固钢筋和锚垫板包覆,待混凝土凝固后得到凸出的加高柱帽。In the above-mentioned method of pulling out and reinforcing columns of roof suspension beams, in step B, after the roughening treatment, anchoring steel bars are implanted at the upper ends of the columns, anchor pads are connected to the steel bars, and then concrete is poured to cover the above-mentioned anchor steel bars and anchor pads. , after the concrete solidifies, a protruding and elevated column cap is obtained.
凸出的加高柱帽提供了足够的位置供钢拱架端部稳定连接安装。The protruding and elevated column caps provide sufficient space for the steel arch ends to be stably connected and installed.
在上述的屋面吊梁拔柱加固改造方法中,所述步骤B中浇筑的混凝土强度等级高于立柱的混凝土强度等级。In the above-mentioned method for reinforcing and transforming roof beams by pulling out columns, the strength level of the concrete poured in step B is higher than the concrete strength level of the columns.
这样的结构能有效提高加高柱帽处强度。Such a structure can effectively improve the strength of the elevated column cap.
在上述的屋面吊梁拔柱加固改造方法中,所述连接作业一时将钢拱架吊放至安装位置处,然后通过临时支撑保证钢拱架稳定。In the above-mentioned method for reinforcing and transforming roof beams by pulling out columns, the connection operation temporarily suspends the steel arch to the installation position, and then ensures the stability of the steel arch through temporary support.
通过临时支撑能保证钢拱架能稳定的安装在加高柱帽处。Temporary support can ensure that the steel arch can be stably installed at the elevated column cap.
在上述的屋面吊梁拔柱加固改造方法中,所述钢拱架端部与加高柱帽通过螺栓连接。In the above-mentioned method of pulling out and strengthening columns of roof suspension beams, the end of the steel arch frame is connected to the heightening column cap through bolts.
在上述的屋面吊梁拔柱加固改造方法中,所述钢拱架端部与加高柱帽通过焊接固连。In the above-mentioned method of pulling out and strengthening columns of roof suspension beams, the end of the steel arch frame and the heightening column cap are connected by welding.
无论是通过螺栓还是焊接,都能使钢拱架端部稳定的连接在加高柱帽上。Whether through bolts or welding, the end of the steel arch can be stably connected to the elevated column cap.
在上述的屋面吊梁拔柱加固改造方法中,所述吊杆与屋面梁通过化学锚栓连接。In the above-mentioned method of pulling out and reinforcing columns of roof suspension beams, the suspension rods and roof beams are connected through chemical anchor bolts.
化学锚栓是一种新型的紧固材料,它是通过特制的化学粘接剂,将螺杆胶结固定于砼基材钻孔中,以实现对固定件锚固的复合件。Chemical anchor bolt is a new type of fastening material. It is a composite component that uses a special chemical adhesive to cement and fix the screw rod in the drilled hole of the concrete base material to achieve anchoring of the fastener.
产品广泛应用于固定幕墙结构、安装机器、钢结构、栏杆、窗户等。它具有安装快捷、迅速固化,不拖延施工进度。Products are widely used in fixed curtain wall structures, installation machines, steel structures, railings, windows, etc. It is quick to install and solidifies without delaying the construction progress.
在上述的屋面吊梁拔柱加固改造方法中,所述吊杆与钢拱架的下弦杆通过焊接固连。In the above-mentioned method of pulling out column reinforcements of roof suspension beams, the suspension rod and the lower chord of the steel arch are connected by welding.
吊杆的Y形两端分别焊接固定在钢拱架的两侧处,这样的结构能使吊杆上端与钢拱架稳定连接。The Y-shaped ends of the boom are welded and fixed on both sides of the steel arch. This structure can make the upper end of the boom stably connected to the steel arch.
在上述的屋面吊梁拔柱加固改造方法中,所述步骤D中在拟拆除立柱上设置抱柱梁,所述抱柱梁与屋面层板面之间的距离为1.2—1.7米位置,此为支点对拟拆除柱与屋面梁交界处梁端设置临时千斤顶支撑,然后梁底标高处截断梁柱连接,以方便下箍板施工。In the above-mentioned roof suspension beam pulling out column reinforcement and transformation method, in the step D, a column-holding beam is set on the column to be removed, and the distance between the column-holding beam and the roof deck surface is 1.2-1.7 meters. This is the fulcrum to set up temporary jack support at the beam end at the junction of the column to be removed and the roof beam, and then cut off the beam-column connection at the bottom elevation of the beam to facilitate the construction of the lower hoop plate.
抱柱梁的设置,提供了足够的空间供千斤顶安装,在千斤顶的作用下能方便的安装连接下箍板。The setting of the column-holding beam provides enough space for the installation of the jack, and the lower hoop plate can be easily installed and connected under the action of the jack.
在上述的屋面吊梁拔柱加固改造方法中,所述步骤D中将上箍板固连在化学锚栓上,下箍板设置在上箍板下部且上箍板与下箍板通过若干对拉螺栓连接,吊杆下端与上箍板固连后,对上述连接处浇筑混凝土,混凝土凝固后形成的混凝土墩将化学锚栓、对拉螺栓、上箍板和下箍板包覆。In the above-mentioned roof beam lifting column reinforcement and transformation method, in step D, the upper hoop plate is fixed to the chemical anchor bolt, the lower hoop plate is arranged at the lower part of the upper hoop plate, and the upper hoop plate and the lower hoop plate pass through several pairs of After the lower end of the boom is connected with the upper hoop plate, concrete is poured into the connection. After the concrete is solidified, the concrete pier formed will be covered with chemical anchor bolts, pull bolts, upper hoop plate and lower hoop plate.
在对拉螺栓的作用下上箍板和下箍板稳定连接,混凝土浇筑后上述各个零件均被包覆,提高其结构紧凑性。The upper hoop plate and the lower hoop plate are stably connected under the action of the tension bolts. After the concrete is poured, all the above parts are covered, improving the compactness of the structure.
在上述的屋面吊梁拔柱加固改造方法中,所述对拉螺栓的数量为若干根,若干对拉螺栓呈栅格状连接在上箍板与下箍板之间。In the above-mentioned method for pulling out column reinforcements of roof suspension beams, the number of the tension bolts is several, and the plurality of tension bolts are connected in a grid shape between the upper hoop plate and the lower hoop plate.
多根对拉螺栓能有效提高上箍板与下箍板之间的连接稳定性。Multiple pull bolts can effectively improve the connection stability between the upper hoop plate and the lower hoop plate.
在上述的屋面吊梁拔柱加固改造方法中,所述步骤E后拆卸千斤顶。In the above-mentioned method of pulling out and reinforcing columns of roof suspension beams, the jack is dismantled after step E.
与现有技术相比,本屋面吊梁拔柱加固改造方法由于对拉螺栓配合化学锚栓、上箍板和下箍板使吊杆下端与屋面梁保持稳定连接,吊杆上端固连在钢拱梁上,通过钢索平衡钢拱架产生的水平作用力,这样的结构具有以下优点:Compared with the existing technology, this roof suspension beam column reinforcement and transformation method maintains a stable connection between the lower end of the suspension rod and the roof beam because the pull bolts cooperate with the chemical anchor bolts, the upper hoop plate and the lower hoop plate, and the upper end of the suspension rod is fixedly connected to the steel On the arch beam, the horizontal force generated by the steel arch frame is balanced by steel cables. This structure has the following advantages:
1、对原建筑结构扰动小,施工安全可靠;1. There is little disturbance to the original building structure, and the construction is safe and reliable;
2、造型美观,经济环保;2. Beautiful appearance, economical and environmentally friendly;
3、受力性能优异;3. Excellent stress performance;
4、受环境影响小,施工速度快;4. Small impact on the environment and fast construction speed;
5、钢拱架、Y形吊杆以及高强预应力钢索单独形成受力体系;5. The steel arch frame, Y-shaped boom and high-strength prestressed steel cables form a separate stress system;
6、受力性能优异,传力路径明确,为设计提供充分的依据。6. Excellent force-bearing performance and clear force transmission path, providing sufficient basis for design.
附图说明Description of the drawings
图1是原结构屋面梁的立体结构示意图。Figure 1 is a schematic three-dimensional structural diagram of the original structural roof beam.
图2是吊梁拔柱加固整体三维示意图。Figure 2 is an overall three-dimensional schematic diagram of the lifting beam and column reinforcement.
图3是吊梁拔柱加固单榀拱架三维示意图。Figure 3 is a three-dimensional schematic diagram of pulling out the suspension beam and strengthening the single-frame arch frame.
图4是Y形吊杆与屋面梁连接节点。Figure 4 shows the connection node between the Y-shaped boom and the roof beam.
图5是Y形吊杆与屋面梁连接节点1-1剖面图。Figure 5 is a cross-sectional view of node 1-1 connecting the Y-shaped boom and the roof beam.
图6是Y形吊杆与屋面梁连接节点2-2剖面图。Figure 6 is a cross-sectional view of node 2-2 connecting the Y-shaped boom and the roof beam.
图7是Y形型吊杆与钢拱架连接节点。Figure 7 shows the connection node between the Y-shaped boom and the steel arch.
图8是钢拱架与柱端连接节点。Figure 8 is the connection node between the steel arch frame and the column end.
图9是抱柱梁平面图。Figure 9 is a plan view of the pillar-supported beam.
图10是抱柱梁平面图1-1剖面图。Figure 10 is a cross-sectional view of the plan view 1-1 of the column-holding beam.
图11是抱柱梁钢支撑平面布置图。Figure 11 is the plan layout of the column-supported beam steel support.
图中,1、屋面梁;2、吊杆与屋面梁连接节点;201、混凝土;202、上箍板;203、化学锚栓;204、对拉螺栓;205、下箍板;206、钢筋;3、钢索;4、上弦杆;5、下弦杆;6、钢拱架与立柱连接节点;601、锚垫板;602、锚固钢筋;603、加高柱帽;7、吊杆;8、腹杆。In the figure, 1. Roof beam; 2. Connection node between hanger and roof beam; 201. Concrete; 202. Upper hoop plate; 203. Chemical anchor bolt; 204. Tension bolt; 205. Lower hoop plate; 206. Steel bar; 3. Steel cable; 4. Upper chord; 5. Bottom chord; 6. Connection node between steel arch and column; 601. Anchor pad; 602. Anchor steel bar; 603. Heightened column cap; 7. Suspender rod; 8. Abdominal rod.
具体实施方式Detailed ways
下面将结合本发明实施方式中的附图,对本发明实施方式中的技术方案进行清楚、完整地描述,显然,所描述的实施方式仅仅是本发明一部分实施方式,而不是全部的实施方式。基于本发明中的实施方式,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施方式,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts fall within the scope of protection of the present invention.
需要说明的是,当组件被称为“装设于”另一个组件,它可以直接装设在另一个组件上或者也可以存在居中的组件。当一个组件被认为是“设置于”另一个组件,它可以是直接设置在另一个组件上或者可能同时存在居中组件。当一个组件被认为是“固定于”另一个组件,它可以是直接固定在另一个组件上或者可能同时存在居中组件。It should be noted that when a component is referred to as being "mounted on" another component, it can be mounted directly on the other component or intervening components may also be present. When a component is said to be "set on" another component, it can be directly set on the other component or there may be a centered component at the same time. When a component is said to be "anchored" to another component, it can be directly anchored to the other component or there may be an intermediate component present as well.
除非另有定义,本文所使用的所有的技术和科学术语与属于本发明的技术领域的技术人员通常理解的含义相同。本文中在本发明的说明书中所使用的术语只是为了描述具体的实施方式的目的,不是旨在于限制本发明。本文所使用的术语“或/及”包括一个或多个相关的所列项目的任意的和所有的组合。Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the technical field to which the invention belongs. The terminology used herein in the description of the invention is for the purpose of describing specific embodiments only and is not intended to limit the invention. As used herein, the term "or/and" includes any and all combinations of one or more of the associated listed items.
如图1和图2所示,拟对相应立柱进行拆除,并对由于立柱拆除后导致跨度增大的屋面梁增设支撑。As shown in Figures 1 and 2, it is planned to dismantle the corresponding columns, and add supports to the roof beams whose spans will increase due to the removal of the columns.
如图3和图4和图5和图6和图7和图8和图9和图10和图11所示,本屋面吊梁拔柱加固改造方法包括以下步骤:As shown in Figure 3 and Figure 4 and Figure 5 and Figure 6 and Figure 7 and Figure 8 and Figure 9 and Figure 10 and Figure 11, this method of reinforcing and transforming roof beams by pulling out columns includes the following steps:
A、钢拱架制备:准备上弦杆4、下弦杆5、腹杆8和钢索3,上述上弦杆4、下弦杆5均呈弧形且两者上下设置,上述腹杆8的数量为若干根,若干腹杆8沿上弦杆4的长度方向均布连接在上弦杆4和下弦杆5之间,得到两端朝下且呈弧形的钢拱架,最后将钢索3连接在钢拱架的两端之间;A. Preparation of the steel arch frame: prepare the upper chord 4, the lower chord 5, the web rod 8 and the steel cable 3. The above upper chord 4 and the lower chord 5 are both arc-shaped and are arranged up and down. The number of the above web rods 8 is several root, a number of web rods 8 are evenly connected between the upper chord 4 and the lower chord 5 along the length direction of the upper chord 4, to obtain a steel arch with both ends facing downwards and an arc shape, and finally the steel cable 3 is connected to the steel arch between the two ends of the rack;
上弦杆和下弦杆的数量均为两根,上弦杆和上弦杆之间也具有腹杆,下弦杆和下弦杆之间也具有腹杆;The number of upper chord rods and lower chord rods is two. There are also web rods between the upper chord rods and the upper chord rods, and there are also web rods between the lower chord rods and the lower chord rods;
所述步骤A中上弦杆4、下弦杆5、腹杆8和钢索3连接成一整体式结构后运输至施工场合。当然,根据实际情况,步骤A中对钢拱架制备为若干段半成品,将半成品运输至施工场合处拼接也是可行的。In step A, the upper chord 4, the lower chord 5, the web rod 8 and the steel cable 3 are connected into an integral structure and then transported to the construction site. Of course, depending on the actual situation, it is also feasible to prepare the steel arch frame into several semi-finished products in step A, and transport the semi-finished products to the construction site for splicing.
B、立柱上端处理:立柱上端进行凿毛处理并通过混凝土浇筑得到凸出的加高柱帽;B. Treatment of the upper end of the column: The upper end of the column is chiseled and concrete is poured to obtain a protruding and heightened column cap;
所述步骤B中凿毛处理后在立柱上端植入锚固钢筋602,钢筋206处连接锚垫板601,然后浇筑混凝土将上述锚固钢筋602和锚垫板601包覆,待混凝土凝固后得到凸出的加高柱帽。In the step B, after the roughening treatment, the anchoring steel bar 602 is implanted at the upper end of the column, and the steel bar 206 is connected to the anchor pad 601. Then concrete is poured to cover the anchoring steel bar 602 and the anchor pad 601. After the concrete solidifies, a protrusion is obtained. of elevated column caps.
本实施例中,加高柱帽处浇筑的混凝土强度等级高于立柱的混凝土强度等级。In this embodiment, the strength level of the concrete poured at the heightened column cap is higher than the concrete strength level of the column.
加高柱帽与钢拱架端部连接后形成钢拱架与立柱连接节点6。The heightened column cap is connected to the end of the steel arch frame to form a connection node 6 between the steel arch frame and the column.
C、连接作业一:钢拱架的一端连接在其中一根立柱的加高柱帽处,钢拱架的另一端连接在另外一根立柱的加高柱帽处;C. Connection operation one: One end of the steel arch frame is connected to the heightened column cap of one of the columns, and the other end of the steel arch frame is connected to the heightened column cap of the other column;
所述连接作业一时将钢拱架吊放至安装位置处,然后通过临时支撑保证钢拱架稳定。The connection operation involves temporarily hoisting the steel arch to the installation position, and then ensuring the stability of the steel arch through temporary support.
所述钢拱架端部与加高柱帽通过螺栓连接。根据实际情况,所述钢拱架端部与加高柱帽通过焊接固连也是可行的。The end of the steel arch frame is connected to the elevated column cap through bolts. Depending on the actual situation, it is also feasible for the end of the steel arch frame and the elevated column cap to be connected by welding.
D、连接作业二:准备Y形的吊杆7,将吊杆的上端固连在钢拱架上,将吊杆7的下端固连在屋面梁1处;D. Connection operation 2: Prepare the Y-shaped boom 7, fasten the upper end of the boom to the steel arch, and fasten the lower end of the boom 7 to roof beam 1;
所述吊杆7与屋面梁1通过化学锚栓连接。The suspender 7 is connected to the roof beam 1 through chemical anchor bolts.
所述吊杆7与钢拱架的下弦杆5通过焊接固连。The suspension rod 7 and the lower chord 5 of the steel arch are fixedly connected by welding.
所述步骤D中在拟拆除立柱上设置抱柱梁,所述抱柱梁与屋面层板面之间的距离为1.2—1.7米位置,此为支点对拟拆除柱与屋面梁交界处梁端设置临时千斤顶支撑,然后梁底标高处截断梁柱连接,以方便下箍板施工。In step D, a column-holding beam is set on the column to be removed. The distance between the column-holding beam and the roof deck is 1.2-1.7 meters. This is the fulcrum at the junction of the column to be removed and the roof beam. Set up temporary jack support at the end, and then cut off the beam-column connection at the bottom elevation of the beam to facilitate the construction of the lower hoop plate.
所述步骤D中将上箍板202固连在化学锚栓203上,下箍板205设置在上箍板202下部且上箍板202与下箍板205通过若干对拉螺栓204连接,吊杆7下端与上箍板202固连后,对上述连接处浇筑混凝土201,混凝土201凝固后形成的混凝土墩将化学锚栓203、对拉螺栓204、上箍板202和下箍板205包覆。In step D, the upper hoop plate 202 is fixed to the chemical anchor bolt 203, the lower hoop plate 205 is arranged at the lower part of the upper hoop plate 202, and the upper hoop plate 202 and the lower hoop plate 205 are connected through a number of pull bolts 204, and the suspension rod 7. After the lower end is firmly connected to the upper hoop plate 202, concrete 201 is poured into the above-mentioned connection. The concrete pier formed after the concrete 201 is solidified will cover the chemical anchor bolts 203, the tension bolts 204, the upper hoop plate 202 and the lower hoop plate 205.
混凝土墩将化学锚栓203、对拉螺栓204、上箍板202和下箍板205包覆后,形成吊杆与屋面梁的连接节点2。The concrete pier covers the chemical anchor bolts 203, tension bolts 204, upper hoop plate 202 and lower hoop plate 205 to form a connection node 2 between the suspender and the roof beam.
所述对拉螺栓204的数量为若干根,若干对拉螺栓204呈栅格状连接在上箍板202与下箍板205之间。The number of the tension bolts 204 is several, and the plurality of tension bolts 204 are connected in a grid shape between the upper hoop plate 202 and the lower hoop plate 205 .
E、上述步骤BCD后在对应的屋面梁1上部得到加固单榀拱架,相邻两屋面梁1的加固单榀拱架成型后采用水平的连杆将相邻两加固单榀拱架连接。E. After the above steps BCD, a reinforced single-frame arch is obtained on the upper part of the corresponding roof beam 1. After the reinforced single-frame arches of the two adjacent roof beams 1 are formed, horizontal connecting rods are used to connect the two adjacent reinforced single-frame arches.
所述步骤E后拆卸千斤顶。Remove the jack after step E.
本屋面吊梁拔柱加固改造方法创造性的预先制备钢拱架,立柱上端处理后形成具备足够连接位置且凸出的加高柱帽。This roof suspension beam column reinforcement and transformation method creatively prepares steel arch frames in advance, and the upper ends of the columns are processed to form elevated column caps with sufficient connection positions and protrusions.
连接作业一后能使钢拱架稳定的连接在其中一根立柱的加高柱帽上,连接作业二后能使吊杆稳定的连接在钢拱架与屋面梁之间。After the first connection operation, the steel arch can be stably connected to the heightened column cap of one of the columns. After the second connection operation, the hanger can be stably connected between the steel arch and the roof beam.
上述加固施工作业后能将屋面荷载传递至钢拱架。同时,高强预应力的钢索由于连接在钢拱架两端,因此,通过钢索能平衡钢拱架端部处水平作用力。After the above reinforcement construction operations, the roof load can be transferred to the steel arch. At the same time, high-strength prestressed steel cables are connected to both ends of the steel arch, so the horizontal forces at the ends of the steel arch can be balanced by the steel cables.
也就是说,钢拱架形成单独的受力体系,将荷载以竖向轴力传递给钢拱架支撑柱,避免因拔柱后此处梁柱节点弯矩过大而发生破坏,最大限度的保护原结构。That is to say, the steel arch forms a separate force-bearing system, which transmits the load to the steel arch support columns in the form of vertical axial force to avoid damage due to excessive bending moments of the beam-column nodes after the columns are pulled out, and maximize the Preserve the original structure.
对应立柱上端经过BCD步骤处理后,单个钢拱架稳定的连接在对应的立柱上,得到单个的加固单榀拱架。After the upper ends of the corresponding columns are processed through the BCD step, a single steel arch is stably connected to the corresponding column to obtain a single reinforced single arch.
步骤E中通过水平设置的连杆将相邻的两个加固单榀拱架稳定连接,最终完成整个屋面梁吊梁拨柱的加固处理。当然,加固后将拟拆除的立柱按照设定长度截断即可。In step E, the two adjacent reinforced single arch frames are stably connected through horizontal connecting rods, and finally the reinforcement of the entire roof beam, suspension beam and column is completed. Of course, after reinforcement, the column to be removed can be cut off according to the set length.
由于钢索连接在钢拱架的两端之间,通过高强预应力钢索平衡钢拱架端部的水平拉力,保证钢拱架稳定的连接在加高柱帽上。Since the steel cables are connected between the two ends of the steel arch, the horizontal tension at the ends of the steel arch is balanced by high-strength prestressed steel cables to ensure that the steel arch is stably connected to the elevated column cap.
以上所述实施方式的各技术特征可以进行任意的组合,为使描述简洁,未对上述实施方式中的各个技术特征所有可能的组合都进行描述,然而,只要这些技术特征的组合不存在矛盾,都应当认为是本说明书记载的范围。The technical features of the above-described embodiments can be combined in any way. To simplify the description, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, All should be considered to be within the scope of this manual.
本技术领域的普通技术人员应当认识到,以上的实施方式仅是用来说明本发明,而并非用作为对本发明的限定,只要在本发明的实质精神范围内,对以上实施方式所作的适当改变和变化都落在本发明要求保护的范围内。Those of ordinary skill in the art should realize that the above embodiments are only used to illustrate the present invention and are not used to limit the invention. As long as they are within the scope of the essential spirit of the present invention, appropriate changes can be made to the above embodiments. and changes all fall within the scope of protection claimed by the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310194594.3A CN116752789A (en) | 2023-02-27 | 2023-02-27 | A method for retrofitting and strengthening roof suspension beams by pulling out columns |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310194594.3A CN116752789A (en) | 2023-02-27 | 2023-02-27 | A method for retrofitting and strengthening roof suspension beams by pulling out columns |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116752789A true CN116752789A (en) | 2023-09-15 |
Family
ID=87948407
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310194594.3A Pending CN116752789A (en) | 2023-02-27 | 2023-02-27 | A method for retrofitting and strengthening roof suspension beams by pulling out columns |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116752789A (en) |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101761241A (en) * | 2009-12-17 | 2010-06-30 | 中国瑞林工程技术有限公司 | Roof suspended type method for pulling out pillars |
| CN102605885A (en) * | 2012-04-02 | 2012-07-25 | 张培聪 | Large-sized closed roof formed by light steel truss arch for building |
| CN104251014A (en) * | 2013-06-27 | 2014-12-31 | 沈阳铝镁设计研究院有限公司 | Connecting structure of concrete bent frame column and roof steel beam |
| CN104358314A (en) * | 2014-11-26 | 2015-02-18 | 天津港航工程有限公司 | Industrial factory building framework structure adopting prefabricated concrete post structure |
| CN107816209A (en) * | 2017-11-09 | 2018-03-20 | 浙江中南建设集团钢结构有限公司 | The large-scale Roof Truss construction technology of installation is lifted across outer both sides |
| CN115324379A (en) * | 2022-10-13 | 2022-11-11 | 河北中科朗博环保科技有限公司 | Steel column base reinforcing process |
-
2023
- 2023-02-27 CN CN202310194594.3A patent/CN116752789A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101761241A (en) * | 2009-12-17 | 2010-06-30 | 中国瑞林工程技术有限公司 | Roof suspended type method for pulling out pillars |
| CN102605885A (en) * | 2012-04-02 | 2012-07-25 | 张培聪 | Large-sized closed roof formed by light steel truss arch for building |
| CN104251014A (en) * | 2013-06-27 | 2014-12-31 | 沈阳铝镁设计研究院有限公司 | Connecting structure of concrete bent frame column and roof steel beam |
| CN104358314A (en) * | 2014-11-26 | 2015-02-18 | 天津港航工程有限公司 | Industrial factory building framework structure adopting prefabricated concrete post structure |
| CN107816209A (en) * | 2017-11-09 | 2018-03-20 | 浙江中南建设集团钢结构有限公司 | The large-scale Roof Truss construction technology of installation is lifted across outer both sides |
| CN115324379A (en) * | 2022-10-13 | 2022-11-11 | 河北中科朗博环保科技有限公司 | Steel column base reinforcing process |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105113389B (en) | Prefabricated steel-concrete composite structure pier column member | |
| CN109339229B (en) | Prefabricated assembled concrete-filled steel tube frame structure of perforation thick liquid anchor | |
| CN107476476A (en) | Combined construction method of long-span steel bar truss floor bearing plate and reinforced concrete beam | |
| CN108571070B (en) | Prefabricated steel tube concrete ring beam connecting structure and construction method | |
| CN111648468B (en) | Ultrahigh space utilization rate fabricated building system and efficient construction method thereof | |
| CN107476470A (en) | Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls and its construction method | |
| CN103046645A (en) | Large span prefabricated monolithic casting structure and construction method | |
| CN110886217B (en) | Precast prestressed concrete anchor beam structure for anchoring stay cable and bridge tower | |
| CN106013432A (en) | Joint connecting structure in high-ductility assembled integrated frame and construction method | |
| CN103122691A (en) | Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method | |
| CN216042835U (en) | A layering device for a high-rise frame structure with lightweight wall panels | |
| CN106499211A (en) | Newly-increased outrigger framework Baogang anchor traction therapy structure and technique | |
| CN117248438A (en) | Truss structure form-based assembled UHPC web plate flange arch structure and construction method thereof | |
| CN102704574A (en) | Node structure of precast concrete tubular column steel beam and construction method of node structure | |
| CN207686092U (en) | A kind of assembled overlapped hollow floor system | |
| CN106869317A (en) | The beam column edge of a wing is the group frame system and construction method of concrete-filled rectangular steel tube | |
| CN203834738U (en) | T-shaped prefabricated mixed coupled wall | |
| CN203034799U (en) | Tower hoist standard knot bearing overhead support formwork steel platform structure | |
| CN107447873B (en) | Device for connecting prefabricated laminated connecting beam and prefabricated shear wall and installation method | |
| CN206769200U (en) | First wear formula post stretching vertical prestressing cast-in-place concrete rod structure | |
| CN213204915U (en) | Overweight overhanging suspended component supporting system of super high-rise residential conversion layer | |
| CN107989247A (en) | A kind of assembled overlapped hollow floor system and its construction method | |
| CN104032855A (en) | Assembly-type cross-shaped mixed coupled wall and construction method thereof | |
| CN202831219U (en) | Large-span precast monolithic concrete structure | |
| CN216664766U (en) | Assembled parapet that cornices |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |