Construction decoration method for cantilever structure of flat roof framework layer
Technical Field
The invention relates to the technical field of construction decoration of a flat roof overhanging structure in house building engineering, in particular to a construction decoration method of a flat roof framework layer overhanging structure.
Background
The construction decoration of the overhanging structure of the flat roof framework layer adopts an I-steel supporting method, namely a plurality of I-steels are placed on a roof, part of the overhanging structure is overhanging, a protective railing is firstly erected at the overhanging end, then an overhanging operation platform is erected at the overhanging part, a steel pipe support is erected above the overhanging operation platform by taking the I-steels as a bottom support according to the reinforced concrete structure position of the roof framework layer, a template is installed, steel bars are bound, a concrete structure of the roof framework layer is poured, the steel pipe support and the template are removed when the concrete reaches the design strength, and then an operation platform is erected below the concrete structure of the framework layer by using a double-row scaffold, so that the platform and the overhanging platform are used together to finish the decoration work of the roof framework layer. In addition, before the method is adopted, a plurality of long diagonal rods, a plurality of transverse horizontal rods, a plurality of longitudinal horizontal rods, a plurality of dense mesh nets, a plurality of safety nets and ropes are selected from the outer side of the scaffold at the lower layer of the roof layer to form a net curtain for protection, and the area of a protection area exceeds the area of the area covered by the outer side of the I-steel.
The I-steel support method has the following defects:
(1) The steel pipe support and the bottom support of the overhanging platform are constructed by taking the steel pipe support as a framework layer concrete structure, so that the I-steel type adopted on site is large in size, heavy in weight and long in length, and the corresponding transportation, lifting and installation difficulties are increased;
(2) I-steel is buried when the roof framework layer is constructed, the I-steel can be removed until the aluminum veneer decoration on the framework layer is completed, the occupied time is long, the renting cost is high, and a lot of cost is increased;
(3) The requirement of overhanging support is met, the laying interval of I-steel is compact, a large-area roof field is occupied, the development of other procedures is not facilitated, and the risk of stumbling and falling injury of operators exists.
Disclosure of Invention
In order to solve the problems, the invention provides a construction and decoration method for the overhanging structure of the flat roof framework layer, which is suitable for being used in building projects with overhanging structures on the flat roof framework layer and solves the problems of high construction and decoration cost and great difficulty in material transportation, lifting and installation of the roof framework layer.
The invention provides a construction and decoration method of a cantilever structure of a flat roof framework layer, which comprises the following steps:
Lifting double-row scaffolds on the outer side of a house structure, enabling the outer row of the double-row scaffolds on the outer side of the house structure to be higher than a reinforced concrete bottom plate of a flat roof framework layer, providing protection for construction of the reinforced concrete bottom plate, positioning a reinforced pull ring and a wall connecting piece steel tube on a pre-buried plate on the periphery of the plate surface, pre-burying the reinforced pull ring in a column at the bottom of a reinforced concrete column of a male angle steel bar, and welding steel plate pre-buried pieces required by a cantilever framework of a steel structure for decoration on all reinforced concrete columns of the flat roof framework layer;
Secondly, pouring a reinforced concrete bottom plate of a flat roof framework layer, and then building a protection device on a double-row scaffold outside the building structure, wherein the protection device comprises an overhanging scaffold, a wall connecting piece steel pipe pre-buried in the first step, a plurality of first longitudinal horizontal rods, a plurality of horizontal pull rods, a plurality of diagonal rods, a plurality of catches, a plurality of safety nets and a plurality of dense meshes, and the overhanging scaffold consists of a plurality of transverse horizontal rods, a plurality of second longitudinal horizontal rods, a plurality of vertical rods, a plurality of diagonal rods, a plurality of short diagonal rods, a plurality of catches, a plurality of foot blocking plates and a plurality of steel mesh sheets;
The horizontal pull rod is positioned below the overhanging scaffold, one end of the horizontal pull rod is connected with the double-row scaffold outside the house structure through a lock catch, the other end of the horizontal pull rod is outwards overhanging and connected with the first longitudinal horizontal rod outside the house structure through a lock catch, one end of the diagonal pull rod is connected with the first longitudinal horizontal rod outside the house structure through a lock catch, the other end of the diagonal pull rod is fixedly connected with the double-row scaffold outside the house structure below the horizontal pull rod through a lock catch, steel pipe grids are formed by sequentially and alternately erecting, and the dense mesh net and the safety net are sequentially bound on the adjacent diagonal pull rods through a tether, wherein the dense mesh net is arranged inside, and the safety net is arranged outside;
Splicing an overhanging operation platform above the protection device, connecting an outer row of double-row scaffolds on the outer side of the building structure with an inner row of scaffolds on the overhanging scaffold through a transverse horizontal rod, a second longitudinal horizontal rod and a lock catch to form the overhanging operation platform, protecting the overhanging operation platform by the outer row of scaffolds on the overhanging scaffold, and correspondingly placing various I-steels according to the pre-embedded position of a steel bar pull ring in the step, wherein the various I-steels comprise a plurality of I-steels in columns, a plurality of I-steels in standard sections, a plurality of I-steels in reinforced sections and a plurality of connecting Liang Gongzi steels;
the male angle steel reinforced concrete column is square, I-steel in the column is inserted along the diagonal direction of the male angle steel reinforced concrete column, one end of the I-steel is fixed with a pre-embedded steel bar pull ring in the column, the other end of the I-steel is overhanging, a first diagonal bracing is arranged below the overhanging section, one end of the first diagonal bracing is fixed with the bottom of the overhanging section, and the other end of the first diagonal bracing is welded and fixed with a first embedded part in the lower Fang Yang angle steel reinforced concrete column;
Arranging a reinforcing section I-steel at a certain angle with the side line of the reinforced concrete bottom plate at the position of the reinforced concrete bottom plate close to the male angle steel reinforced concrete column, wherein one end of the reinforcing section I-steel is fixed with an on-board steel bar pull ring pre-buried on the reinforced concrete bottom plate, the other end of the reinforcing section I-steel is overhanging, a second diagonal bracing is arranged below the overhanging section, one end of the second diagonal bracing is fixed with the reinforcing section I-steel, and the other end of the second diagonal bracing is welded and fixed with a second embedded part on the lower reinforced concrete bottom plate;
The connecting Liang Gongzi steel is welded on the upper parts of overhanging sections of the I-steel in the column and the I-steel in the reinforcing section;
The standard section I-steel is perpendicular to the side line of the reinforced concrete bottom plate, one end of the standard section I-steel is fixed with an on-board steel bar pull ring pre-buried on the reinforced concrete bottom plate, the other end of the standard section I-steel is overhanging, the standard section I-steel is spread along the edge of the reinforced concrete bottom plate in a straight shape, and the connection Liang Gongzi steel is spread in an orthogonal manner with the standard section I-steel;
Step four, constructing a steel pipe support above each I-steel, wherein the steel pipe support comprises a plurality of steel pipe vertical rods, a plurality of steel pipe transverse horizontal rods, a plurality of steel pipe longitudinal horizontal rods, a plurality of locks and a plurality of scissor supports, the tops of the I-steel are provided with steel bar bulges, the bottoms of the steel pipe vertical rods are erected on the I-steel through the steel bar bulges, the steel pipe transverse horizontal rods and the steel pipe longitudinal horizontal rods are connected with the steel pipe vertical rods through the locks, the upper parts of the steel pipe support are provided with U-shaped jacking, the upper parts of the U-shaped jacking are supported with templates, the scissor supports are arranged on the vertical surfaces of the steel pipe support, the scissor supports are arranged at intervals of four rows and no more than 5000mm along the longitudinal direction of the steel pipe support, and each I-steel and the steel pipe support jointly form a concrete wall, a column and a cantilever structure pouring support platform of a flat roof framework layer in a construction stage;
Step five, a template of the flat roof framework layer is installed by utilizing a steel pipe support, and a concrete member of the flat roof framework layer is poured;
Step six, dismantling each I-steel, a steel pipe support above the I-steel and a concrete structure template when the concrete of the framework layer of the roof to be flattened reaches the design strength, and erecting an operation platform used in the decoration stage by utilizing a double-row scaffold on the outer side of the house structure, wherein the operation platform is formed by connecting a plurality of transverse horizontal rods, a plurality of longitudinal horizontal rods, a plurality of vertical rods and a plurality of fasteners;
Welding aluminum veneer decorative steel structure frameworks on the steel plate embedded parts in the reinforced concrete columns in the step one, and installing aluminum veneers on an operation platform after the steel structure frameworks are welded, so as to finish the decoration work of the overhanging structure of the roof framework layer.
Further, be equipped with vertical main muscle and horizontal stirrup in the angle steel reinforced concrete column, vertical main muscle runs through the cylinder, and horizontal stirrup is located reinforced concrete bottom plate top, and the I-steel is fixed through 3 in the post reinforcing bar pull rings, and the reinforcing bar pull rings adopts several style of calligraphy reinforcing bar pull rings in the post, is makeed by phi 16 round steel, buries into angle steel reinforced concrete column in length not less than 500mm, and the vertical welded length of reinforcing bar pull rings and vertical main muscle in 3 posts is not less than 160mm.
Further, the I-steel in the column adopts 16a I-steel, the length of the overhanging section is 2133mm, and the anchoring length in the column is 697mm.
Further, the first diagonal bracing is made of 16a I-steel, the horizontal distance between the first diagonal bracing and the upper and lower fixing points of the first embedded part is 1000mm, and the vertical distance is greater than 1000mm.
Further, the reinforcing section I-steel and the standard section I-steel are fixed on the reinforced concrete bottom plate by adopting 2 steel bar pull rings on the plate, the steel bar pull rings on the plate are in a shape of a Chinese character 'ji', the height is 320mm, the steel bar pull rings on the plate are embedded to the steel bar position of the reinforced concrete bottom plate, the two ends of the bottom extend into the anchoring length of the bottom plate to be 300mm, the steel bar pull rings on the outermost plate are firmly welded with the steel bar of the reinforced concrete bottom plate, the steel bar pull rings on the innermost plate are arranged at the position 100mm away from the outer wall surface, and the steel bar pull rings on the innermost plate are arranged at the position close to the inner overhanging end of 200 mm.
Further, spaces formed by the upper wing plate surfaces of the standard section I-steel and the reinforcing section I-steel and the steel bar pull rings on the plates are filled by square lumber.
Further, the standard section I-steel adopts 16a I-steel, the anchoring length on the reinforced concrete bottom plate is 2300mm, the external anchoring length of the reinforced concrete bottom plate is 1600mm, and the reinforced concrete bottom plate is distributed at 1500mm intervals.
Further, the I-steel of the reinforcing section adopts 16a I-steel, the anchoring length in the building is 2300mm, the anchoring length outside the building is 1600mm, the second diagonal bracing adopts 16a I-steel, and the second embedded part fixed with the second diagonal bracing adopts a steel pipe.
The U-shaped jacking comprises a screw, an adjustable nut and a U-shaped jacking disc, wherein the diameter of the screw is smaller than the inner diameter of a vertical rod of a steel pipe and can be inserted into the steel pipe, the inner diameter of the adjustable nut is matched with the outer diameter of the screw and can be sleeved into the screw, the screw can be inserted into the steel pipe by rotating the nut, the lower part of the U-shaped jacking disc is welded with the upper end part of the screw, a welded junction is full, the U-shaped opening is upwards contacted with a concrete structure template, and a space formed by the U-shaped opening and the concrete structure template is filled with square timber.
The beneficial effects of the invention are as follows:
1. By constructing and decorating in stages, the I-steel and the steel pipe support are erected in the construction stage, the I-steel is dismantled after the construction stage is finished to serve as a supporting device of a main component, and then a small-sized operation platform is erected to carry out the decoration stage, so that the turnover rate of materials is improved, the lease cost of the I-steel is effectively reduced, and the problems that the occupied time of the I-steel is long, the occupied area of the site is large and other procedures are influenced are solved.
2. The overhanging operation platform and the overhanging screen at the lower part thereof strengthen the safety protection, in the conventional I-steel supporting method, the lower part of the I-steel is only protected by one layer of screen, and potential safety hazards exist at the gap between the I-steels.
3. The construction requirement of the cantilever structure of the flat roof framework layer can be realized by adopting small-size short I-steel and strengthening the support of local I-steel stress concentration areas such as the external corners of the roof, the operation is more convenient, the construction efficiency can be effectively improved, and the input of resources is reduced.
4. The I-steel is small in model, short in length and small in occupied area of the site, and can be removed in time after the construction stage, so that the risk of stumbling and falling injury of operators in the operation of a roof construction area can be reduced, and the safety of the operators is further guaranteed.
The invention adopts staged construction decoration, can remove the I-steel as the supporting device of the main component after the construction stage is finished, effectively solves the problems of high I-steel leasing cost, long occupied time and the like, reduces the risk of stumbling and falling injury of operators in construction area operation, does not need to use a large amount of large-scale I-steel, has simple and convenient transportation, lifting, installation and disassembly, can shorten a certain construction period, and can carry out construction decoration of a framework overhanging structure on a flat roof of a house building.
Drawings
FIG. 1 is a cross-sectional view of the present invention showing the embedment of I-steel in a column of male angle steel reinforced concrete.
Fig. 2 is a cross-sectional view of a figure-shaped reinforcing bar pull ring of the invention pre-buried in a male angle steel bar concrete column.
Fig. 3 is a top view of the present invention with the i-steel pre-embedded in the male angle steel reinforced concrete column.
Fig. 4 is a front view showing the fixing of the several-shaped reinforcing steel bar pull ring to the reinforced concrete floor.
Fig. 5 is a top view of each of the i-beam constructions of the present invention.
FIG. 6 is a schematic cross-sectional view of the I-beam overhanging operation platform in the column of the invention.
Fig. 7 is a schematic cross-sectional view of the standard section i-steel overhanging operation platform of the invention.
Fig. 8 is a schematic cross-sectional view of the cantilever operation platform of the i-steel reinforcement section of the present invention.
Fig. 9 is a schematic overall cross-sectional view of a double-row scaffold outside the building structure of the present invention.
Fig. 10 is a schematic cross-sectional view showing the connection between the double-row scaffold and the overhanging scaffold on the outer side of the house structure.
FIG. 11 is a schematic overall cross-sectional view of the construction stage of the present invention.
FIG. 12 is a schematic overall cross-sectional view of the present invention at a decoration stage.
In the figure, a double-row scaffold 1 at the outer side of a house structure, a transverse horizontal rod 101, a longitudinal horizontal rod 102, a vertical rod 103 and a lock catch 104;
The reinforced concrete bottom plate 2 of the flat roof framework layer is provided with a reinforced pull ring 201 and a wall connecting steel pipe 202;
The external angle steel reinforced concrete column 3 comprises a column internal steel reinforced pull ring 301, a vertical main reinforcement 302 and a horizontal stirrup 303;
The cantilever scaffold 401, a transverse horizontal rod 4011, a second longitudinal horizontal rod 4012, a vertical rod 4013, an inclined strut 4014, a short inclined rod 4015, a lock catch 4016, a foot baffle 4017 and a steel net sheet 4018;
A first longitudinal horizontal rod 402, a horizontal pull rod 403, a diagonal pull rod 404, a lock catch 405, a safety net 406 and a dense mesh net 407;
An overhanging operation platform 5;
the column I-steel 601, the standard section I-steel 602, the reinforced section I-steel 603, the connecting Liang Gongzi steel 604, the first diagonal bracing 605, the first embedded part 606, the second diagonal bracing 607 and the second embedded part 608;
A steel pipe bracket 7, a steel pipe vertical rod 701, a transverse horizontal rod 702, a longitudinal horizontal rod 703, a scissor stay 705, a U-shaped jacking 706, a template 707 and square lumber 609/708;
the operation platform 8, a transverse horizontal rod 801, a longitudinal horizontal rod 802, a vertical rod 803 and a fastener 804.
Detailed Description
The technical solution of the present invention is further described below with reference to the accompanying drawings, but the scope of the claimed invention is not limited to the above.
As shown in fig. 1-12, a construction and decoration method for a cantilever structure of a flat roof framework layer comprises the following steps:
Step one, lifting a double-row scaffold 1 on the outer side of a house structure, enabling the outer row of the double-row scaffold 1 to be higher than a reinforced concrete bottom plate 2 of a flat roof framework layer, providing protection for construction of the reinforced concrete bottom plate 2, positioning a reinforced pull ring 201 and a wall connecting piece steel tube 202 on a pre-buried plate on the periphery of a plate surface, pre-burying a reinforced pull ring 301 in a column at the bottom of a reinforced concrete column 3 of a male angle steel column, and welding steel plate pre-buried pieces required by a cantilever framework of a decorative steel structure on all reinforced concrete columns of the flat roof framework layer;
Secondly, pouring a reinforced concrete bottom plate 2 of a flat roof framework layer, and then building a protection device on a double-row scaffold 1 outside a house structure, wherein the protection device comprises an overhanging scaffold 401, a wall connecting piece steel pipe 202 pre-buried in the first step, a plurality of first longitudinal horizontal rods 402, a plurality of horizontal pull rods 403, a plurality of diagonal rods 404, a plurality of catches 405, a plurality of safety nets 406 and a plurality of dense meshes 407, the overhanging scaffold 401 is composed of a plurality of transverse horizontal rods 4011, a plurality of second longitudinal horizontal rods 4012, a plurality of vertical rods 4013, a plurality of diagonal rods 4014, a plurality of short diagonal rods 4015, a plurality of catches 4016, a plurality of foot blocking plates 4017 and a plurality of steel meshes 4018, one end of the transverse horizontal rods 4011 close to the flat roof framework layer concrete bottom plate 2 is fixedly connected with the wall connecting piece steel pipe 202 through the catches 4016, the other end of the cantilever rods 403 extends along the vertical rods and is fixedly connected with the vertical rods through the catches, the other end of the diagonal rods as a foundation of the overhanging scaffold, one end of the diagonal rods 4014 is connected with the second longitudinal horizontal rods 4012 arranged on the transverse horizontal rods through the catches 4012, the other end of the diagonal rods 4012 is connected with the horizontal rods 4012 through the horizontal rods 4015, and the outer side of the horizontal rods 4013 is further arranged on the flat roof framework layer, and the outer side of the horizontal rods 4013 is further connected with the horizontal rods 4013 through the horizontal rods 4016, and the horizontal rods 4017 are further arranged on the horizontal rods 4013 and the lower side of the horizontal rods 4013 are arranged on the horizontal rods are connected with the horizontal rods 3 and the horizontal rods 4013;
The horizontal pull rod 403 is positioned below the overhanging scaffold 401, one end of the horizontal pull rod is connected with the double-row scaffold outside the house structure through a lock catch 405, the other end of the horizontal pull rod is outwards overhanging and connected with the first longitudinal horizontal rod 402 outside through the lock catch 405, one end of the diagonal pull rod 404 is connected with the first longitudinal horizontal rod 402 outside through the lock catch 405, the other end of the diagonal pull rod is fixedly connected with the double-row scaffold outside the house structure below the horizontal pull rod 403 through the lock catch, steel tube grids are formed by sequentially erecting at intervals, the dense mesh 407 and the safety mesh 406 are sequentially bound on the adjacent diagonal pull rods 404 through ropes, the dense mesh 407 is arranged inside, and the safety mesh 406 is arranged outside;
Step three, splicing an overhanging operation platform 5 above a protection device, connecting the outer row of double-row scaffolds 1 outside a house structure with the inner row scaffolds of the overhanging scaffolds 401 through a transverse horizontal rod 4011, a second longitudinal horizontal rod 4012 and a lock catch 4016 to form the overhanging operation platform 5, protecting the overhanging operation platform 5 by the outer row scaffolds of the overhanging scaffolds 401, and correspondingly placing various I-steels according to the embedded position of a step one steel bar pull ring, wherein the various I-steels comprise I-steels 601 in columns, standard section I-steels 602, reinforcing section I-steels 603 and connecting Liang Gongzi steels 604;
The male angle steel reinforced concrete column 3 is square, the I-steel 601 in the column is inserted along the opposite angle of the male angle steel reinforced concrete column 3, one end of the I-steel 601 is fixed with the pre-embedded steel reinforced pull ring 301 in the column, the other end of the I-steel is overhanging, a first diagonal bracing 605 is arranged below the overhanging section, one end of the first diagonal bracing 605 is fixed with the bottom of the overhanging section, and the other end of the first diagonal bracing 605 is welded and fixed with a first embedded part 606 in the lower Fang Yang angle steel reinforced concrete column 3;
A reinforcing section I-steel 603 is arranged at a position of the reinforced concrete bottom plate 2, which is close to the male angle steel reinforced concrete column 3, and forms a certain angle with the side line of the reinforced concrete bottom plate 2, one end of the reinforcing section I-steel 603 is fixed with an on-board steel bar pull ring 201 pre-buried on the reinforced concrete bottom plate 2, the other end of the reinforcing section I-steel 603 is overhanging, a second diagonal bracing 607 is arranged below the overhanging section, one end of the second diagonal bracing 607 is fixed with the reinforcing section I-steel 603, and the other end of the second diagonal bracing 607 is welded and fixed with a second embedded part 608 on the lower reinforced concrete bottom plate;
The connecting beam I-steel 604 is welded at the upper parts of overhanging sections of the I-steel 601 in the column and the I-steel 603 in the reinforcing section;
The standard section I-steel 602 is perpendicular to the side line of the reinforced concrete bottom plate 2, one end of the standard section I-steel 602 is fixed with an on-board reinforced steel pull ring 201 pre-buried on the reinforced concrete bottom plate 2, the other end of the standard section I-steel 602 is overhanging, the standard section I-steel 602 is spread along the edge of the reinforced concrete bottom plate 2 in a straight shape, and the connection Liang Gongzi steel 604 is spread in an orthogonal manner with the standard section I-steel 602;
Step four, constructing a steel pipe support 7 above each I-shaped steel, wherein the steel pipe support 7 comprises a plurality of steel pipe vertical rods 701, a plurality of steel pipe transverse horizontal rods 702, a plurality of steel pipe longitudinal horizontal rods 703, a plurality of lock catches 704 and a plurality of scissor supports 705, the tops of the I-shaped steel are provided with steel bar bulges, the bottoms of the steel pipe vertical rods 701 are erected on the I-shaped steel through the steel bar bulges, the steel pipe transverse horizontal rods 702 and the steel pipe longitudinal horizontal rods 703 are connected with the steel pipe vertical rods 701 through the lock catches 704, a U-shaped jacking 706 is arranged at the upper part of the steel pipe support 7, templates 707 are supported at the upper part of the U-shaped jacking 706, the scissor supports 705 are arranged on the vertical surface of the steel pipe support 7, the scissor supports 705 are arranged at intervals of four rows along the longitudinal direction of the steel pipe support, and are not more than 5000mm, and each I-shaped steel and the steel pipe support jointly form a concrete wall, a column and a cantilever structure pouring support platform of a flat roof framework layer in a construction stage;
Step five, a template of a flat roof framework layer is installed by utilizing a steel pipe support 7, and a reinforced concrete bottom plate concrete member is poured;
Step six, dismantling each I-steel, a steel pipe support and a template above the I-steel when the concrete of the framework layer of the roof to be flattened reaches the design strength, and erecting an operation platform 8 for decoration construction by utilizing the double-row scaffold 1 on the outer side of the house structure, wherein the operation platform 8 is formed by connecting a plurality of transverse horizontal rods 801, a plurality of longitudinal horizontal rods 802, a plurality of vertical rods 803 and a plurality of fasteners 804;
Welding aluminum veneer decorative steel structure frameworks on the steel plate embedded parts in the reinforced concrete columns in the step one, and installing aluminum veneers on an operation platform after the steel structure frameworks are welded, so as to finish the decoration work of the overhanging structure of the roof framework layer.
As an alternative embodiment, the vertical main reinforcement 302 and the transverse stirrup 303 are arranged in the male angle steel reinforced concrete column 3, the vertical main reinforcement 302 penetrates through the column, the transverse stirrup 303 is positioned above the reinforced concrete bottom plate 2 of the flat roof framework layer, the I-shaped steel 601 in the column is fixed through 3 steel bar pull rings in the column, the steel bar pull rings 301 in the column are made of phi 16 round steel, the length in the embedded male angle steel reinforced concrete column 3 is not less than 500mm, and the vertical welding length between the steel bar pull rings 301 in the 3 columns and the vertical main reinforcement 302 is not less than 160mm. When the steel bar is inconvenient to weld with the vertical main bar 302, the anchoring length of the steel bar pull ring 301 in the column below the male steel bar reinforced concrete column 3 is increased, so that the anchoring length is not less than 1500mm, or 2 phi 16 horizontal steel bars are respectively welded at the left and right sides of the bent hook of the steel bar pull ring 301 in the column with the original length, and the anchoring cohesive force and the pulling resistance of the square round steel are increased. When the pouring of the reinforced concrete bottom plate 2 of the flat roof framework layer is completed and the design strength is reached, the in-column reinforced bar pull ring 301 is completely fixed.
As an alternative embodiment, the in-column I-steel 601 is 16a I-steel, the length of the overhanging section is 2133mm, and the anchoring length in the column is 697mm.
As an alternative embodiment, the first diagonal bracing 605 adopts 16a I-steel, the horizontal distance between the first diagonal bracing 605 and the upper and lower fixing points of the I-steel 601 and the first embedded part 606 in the column is 1000mm, and the vertical distance is more than 1000mm.
As an alternative embodiment, the standard section I-steel 602 and the reinforcing section I-steel 603 are both fixed on the reinforced concrete bottom plate 2 by adopting 2 steel bar pull rings 201 on the plate, the steel bar pull rings 201 on the plate are in a shape like a Chinese character 'ji', the height is 320mm, the steel bar pull rings 201 on the plate are pre-buried to the steel bar position of the reinforced concrete bottom plate 2, the anchoring lengths of the two ends of the bottom of the plate extend into the bottom of the plate are 300mm, the steel bars of the steel bar reinforced concrete bottom plate 2 are firmly welded, the steel bar pull ring on the outermost plate is arranged at a position 100mm away from the outer wall surface, and the steel bar pull ring on the innermost plate is arranged at a position near the inner overhanging end by 200 mm.
As an alternative embodiment, the spaces formed by the upper wing plate surfaces of the standard section i-steel 602 and the reinforcing section i-steel 603 and the steel bar pull ring 201 on the plate are filled by square timber 609, and the square timber 609 plays a role in fastening the i-steel.
As an alternative embodiment, the standard section I-steel 602 adopts 16a I-steel, the anchoring length on the reinforced concrete bottom plate 2 is 2300mm, the outer anchoring length of the reinforced concrete bottom plate 2 of the flat roof framework layer is 1600mm, the reinforced concrete bottom plate is distributed at intervals of 1500mm, the lower part is not provided with a support, the upper part is provided with a steel pipe support, and the template is supported in the construction stage to assist in completing the construction of the overhanging structure of the roof framework layer.
As an alternative embodiment, the reinforcing section I-steel 603 adopts 16a I-steel, the anchoring length in the building is 2300mm, the anchoring length outside the building is 1600mm, the reinforcing section I-steel is arranged according to practical conditions, the second diagonal bracing 607 also adopts 16a I-steel, and the second embedded part 608 fixed with the second diagonal bracing 607 can adopt steel pipes.
As an alternative embodiment, the U-shaped jacking 706 comprises a screw, an adjustable nut and a U-shaped jacking disc, wherein the diameter of the screw is smaller than the inner diameter of a steel pipe vertical rod and can be inserted into the steel pipe, the inner diameter of the adjustable nut is matched with the outer diameter of the screw and can be sleeved into the screw, the screw can be inserted into the steel pipe by rotating the nut, the lower part of the U-shaped jacking disc is welded with the upper end part of the screw, a welded joint is full, the U-shaped joint is upwards contacted with a concrete structure template, and a space formed by the U-shaped joint and the concrete structure template is filled with square timber 708.
As an alternative embodiment, the reinforcing section i-steel 603 is arranged at an angle a with the reinforced concrete floor 2 of the flat roof framework layer, wherein 0< a <90 °, and the specific angle is set according to actual needs.
As an alternative embodiment, the double-row scaffold 1 is built on the outside of the building structure and comprises a plurality of transverse horizontal bars 101, a plurality of longitudinal horizontal bars 102, a plurality of vertical bars 103 and a plurality of catches 104.
The foregoing description is only illustrative of the preferred embodiments of the present invention, and although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described, or equivalents may be substituted for elements thereof, and any modifications, equivalents, improvements or changes may be made without departing from the spirit and principles of the present invention.