CN116657812A - Prefabricated folding roof structure for daylighting, power generation and smoke exhaust - Google Patents

Prefabricated folding roof structure for daylighting, power generation and smoke exhaust Download PDF

Info

Publication number
CN116657812A
CN116657812A CN202310618828.2A CN202310618828A CN116657812A CN 116657812 A CN116657812 A CN 116657812A CN 202310618828 A CN202310618828 A CN 202310618828A CN 116657812 A CN116657812 A CN 116657812A
Authority
CN
China
Prior art keywords
smoke exhaust
horizontal structure
prefabricated
power generation
roof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310618828.2A
Other languages
Chinese (zh)
Inventor
陈国义
韩伟
吴楠
谢朋
刘清江
龚林
王晋蕾
张双尧
冯光明
张文书
孟宝桂
姜健
梁圣伟
宋国旺
张磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Urban Construction North Group Co ltd
Original Assignee
Beijing Urban Construction North Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Urban Construction North Group Co ltd filed Critical Beijing Urban Construction North Group Co ltd
Priority to CN202310618828.2A priority Critical patent/CN116657812A/en
Publication of CN116657812A publication Critical patent/CN116657812A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/08Vaulted roofs
    • E04B7/10Shell structures, e.g. of hyperbolic-parabolic shape; Grid-like formations acting as shell structures; Folded structures
    • E04B7/107Folded structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/02Roofs; Roof construction with regard to insulation with plane sloping surfaces, e.g. saddle roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/02Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
    • E04C2/04Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres
    • E04C2/06Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres reinforced
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/30Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the shape or structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D11/00Roof covering, as far as not restricted to features covered by only one of groups E04D1/00 - E04D9/00; Roof covering in ways not provided for by groups E04D1/00 - E04D9/00, e.g. built-up roofs, elevated load-supporting roof coverings
    • E04D11/02Build-up roofs, i.e. consisting of two or more layers bonded together in situ, at least one of the layers being of watertight composition
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/16Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure
    • E04D13/1606Insulation of the roof covering characterised by its integration in the roof structure
    • EFIXED CONSTRUCTIONS
    • E05LOCKS; KEYS; WINDOW OR DOOR FITTINGS; SAFES
    • E05FDEVICES FOR MOVING WINGS INTO OPEN OR CLOSED POSITION; CHECKS FOR WINGS; WING FITTINGS NOT OTHERWISE PROVIDED FOR, CONCERNED WITH THE FUNCTIONING OF THE WING
    • E05F15/00Power-operated mechanisms for wings
    • E05F15/70Power-operated mechanisms for wings with automatic actuation
    • E05F15/71Power-operated mechanisms for wings with automatic actuation responsive to temperature changes, rain, wind or noise
    • EFIXED CONSTRUCTIONS
    • E05LOCKS; KEYS; WINDOW OR DOOR FITTINGS; SAFES
    • E05FDEVICES FOR MOVING WINGS INTO OPEN OR CLOSED POSITION; CHECKS FOR WINGS; WING FITTINGS NOT OTHERWISE PROVIDED FOR, CONCERNED WITH THE FUNCTIONING OF THE WING
    • E05F15/00Power-operated mechanisms for wings
    • E05F15/70Power-operated mechanisms for wings with automatic actuation
    • E05F15/72Power-operated mechanisms for wings with automatic actuation responsive to emergency conditions, e.g. fire
    • EFIXED CONSTRUCTIONS
    • E05LOCKS; KEYS; WINDOW OR DOOR FITTINGS; SAFES
    • E05YINDEXING SCHEME ASSOCIATED WITH SUBCLASSES E05D AND E05F, RELATING TO CONSTRUCTION ELEMENTS, ELECTRIC CONTROL, POWER SUPPLY, POWER SIGNAL OR TRANSMISSION, USER INTERFACES, MOUNTING OR COUPLING, DETAILS, ACCESSORIES, AUXILIARY OPERATIONS NOT OTHERWISE PROVIDED FOR, APPLICATION THEREOF
    • E05Y2900/00Application of doors, windows, wings or fittings thereof
    • E05Y2900/10Application of doors, windows, wings or fittings thereof for buildings or parts thereof
    • E05Y2900/13Type of wing
    • E05Y2900/148Windows
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B10/00Integration of renewable energy sources in buildings
    • Y02B10/10Photovoltaic [PV]

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

本发明公开了一种预制折板式采光发电排烟的屋面结构,包括:预制折板包括上部水平结构、中间倾斜结构及下部水平结构,中间倾斜结构的上下端与上部水平结构和下部水平结构成一定夹角连接,上部水平结构和下部水平结构与建筑物屋顶的底部钢梁或预制混凝土结构连接;电动排烟窗呈竖立状态的设置在中间倾斜结构的对面,且位于上部水平结构的下方,电动排烟窗能够与消防联动控制,且烟气能够从电动排烟窗排出,自然光能够通过电动排烟窗射入建筑物内;防水兼保护层、保温层、粘结层、防水卷材及防水涂膜从外至内依次设置在屋面结构除去电动排烟窗以外的区域上;光伏发电板铺设在中间倾斜结构的防水兼保护层上。可同时兼具满足自然采光等多项优点。

The invention discloses a roof structure of prefabricated folded plate type lighting, power generation and smoke exhaust, comprising: the prefabricated folded plate includes an upper horizontal structure, a middle inclined structure and a lower horizontal structure, and the upper and lower ends of the middle inclined structure are formed with the upper horizontal structure and the lower horizontal structure. A certain angle connection, the upper horizontal structure and the lower horizontal structure are connected with the bottom steel beam or prefabricated concrete structure of the building roof; the electric smoke exhaust window is erected on the opposite side of the middle inclined structure, and is located under the upper horizontal structure. The electric smoke exhaust window can be controlled in conjunction with fire protection, and the smoke can be discharged from the electric smoke exhaust window, and natural light can be injected into the building through the electric smoke exhaust window; waterproof and protective layer, insulation layer, adhesive layer, waterproof membrane and The waterproof coating film is arranged sequentially on the roof structure except for the electric smoke exhaust window from the outside to the inside; the photovoltaic power generation panel is laid on the waterproof and protective layer of the middle inclined structure. It can meet many advantages such as natural lighting at the same time.

Description

预制折板式采光发电排烟的屋面结构Prefabricated folding roof structure for daylighting, power generation and smoke exhaust

技术领域technical field

本发明是关于装配式建筑物领域,特别是关于一种预制折板式采光发电排烟的屋面结构。The invention relates to the field of prefabricated buildings, in particular to a prefabricated folded plate roof structure for daylighting, generating electricity, generating smoke and exhausting smoke.

背景技术Background technique

在建筑领域,对装配式建筑及被动式超低能耗建筑的探索愈加深入。In the field of construction, the exploration of prefabricated buildings and passive ultra-low energy buildings has become more and more in-depth.

装配式建筑能够将工序前置,实现建筑工业化,像建汽车一样建房子,将零部件在现场进行拼装,辅以少量的现浇结构进行连接。为了最大化利用自然资源,降低能耗,建筑也愈加推广主动优化、被动设计。对于一些公共建筑,为降低能耗,以及增加建筑外观特色,会将屋顶设计为采光屋顶,但是大面积玻璃天窗可能会造成冬冷夏热的结果;若直接设计为混凝土楼板,则需使用照明提供亮度。同时大空间结构施工机电系统也具有一定难度,需从地面搭设脚手架进行高空作业,因此需要设计一种方式既方便施工也满足消防需求。综上,对采光、降低能耗、满足消防要求、施工便捷等多因素的协调统一十分重要。The prefabricated building can advance the process to realize the industrialization of construction, build a house like building a car, assemble the parts on site, and connect them with a small amount of cast-in-place structures. In order to maximize the use of natural resources and reduce energy consumption, buildings are increasingly promoting active optimization and passive design. For some public buildings, in order to reduce energy consumption and increase the appearance of the building, the roof will be designed as a daylighting roof, but the large glass skylight may cause the result of cold winter and hot summer; if it is directly designed as a concrete floor, it is necessary to use lighting to provide brightness. At the same time, the mechanical and electrical system of the large-space structure construction is also difficult. Scaffolding needs to be erected from the ground for high-altitude operations. Therefore, it is necessary to design a method that is convenient for construction and meets fire protection requirements. To sum up, it is very important to coordinate and unify multiple factors such as daylighting, energy consumption reduction, meeting fire protection requirements, and convenient construction.

现有屋面施工技术存在以下缺陷:There are following defects in existing roof construction technology:

1、目前屋面采用全封闭结构或平铺式天窗结构,前者无采光、后者建筑内温度自主调节能力差。1. At present, the roof adopts a fully enclosed structure or a tiled skylight structure. The former has no lighting, and the latter has poor ability to independently adjust the temperature in the building.

2、公建一般设计为大空间结构,十几至几十米高度进行现浇结构施工,需搭设满堂支撑架,此种方式浪费人工,且现浇结构施工工序繁琐、施工周期长,不满足绿色施工要求。2. Public buildings are generally designed as large-space structures. For cast-in-place structure construction at a height of more than ten to tens of meters, a full hall of support frames needs to be erected. Green construction requirements.

3、大空间结构的机电系统施工也具有一定难度,高空作业安全隐患大,不利于安全文明施工。3. The construction of the electromechanical system of the large-space structure is also difficult, and the high-altitude operation has great potential safety hazards, which is not conducive to safe and civilized construction.

4、在正常保温层施工完成后进行光伏板安装,安装光伏板需要打胀栓固定,但是打胀栓会破坏保温及防水层,普通保温层不适于这类安装。4. Install the photovoltaic panels after the construction of the normal insulation layer is completed. The installation of the photovoltaic panels requires expansion bolts to fix them, but the expansion bolts will damage the insulation and waterproof layers. Ordinary insulation layers are not suitable for this type of installation.

公开于该背景技术部分的信息仅仅旨在增加对本发明的总体背景的理解,而不应当被视为承认或以任何形式暗示该信息构成已为本领域一般技术人员所公知的现有技术。The information disclosed in this Background section is only for enhancing the understanding of the general background of the present invention and should not be taken as an acknowledgment or any form of suggestion that the information constitutes the prior art that is already known to those skilled in the art.

发明内容Contents of the invention

本发明的目的在于提供一种预制折板式采光发电排烟的屋面结构,其兼具满足自然采光、通风、温度调节、消防要求以及发电等多项功能。The purpose of the present invention is to provide a prefabricated folded-plate roof structure for daylighting, power generation, and smoke exhaust, which has many functions such as natural lighting, ventilation, temperature regulation, fire protection requirements, and power generation.

为实现上述目的,本发明提供了一种预制折板式采光发电排烟的屋面结构,包括预制折板、电动排烟窗、防水兼保护层、保温层、粘结层、防水卷材及防水涂膜以及光伏发电板;预制折板包括上部水平结构、中间倾斜结构及下部水平结构,中间倾斜结构的上下端与上部水平结构和下部水平结构成一定夹角连接,上部水平结构和下部水平结构与建筑物屋顶的底部钢梁或预制混凝土结构连接;电动排烟窗呈竖立状态的设置在中间倾斜结构的对面,且位于上部水平结构的下方,电动排烟窗能够与消防联动控制,且烟气能够从电动排烟窗排出,自然光能够通过电动排烟窗射入建筑物内;防水兼保护层、保温层、粘结层、防水卷材及防水涂膜从外至内依次设置在屋面结构除去电动排烟窗以外的区域上;光伏发电板铺设在中间倾斜结构的防水兼保护层上。In order to achieve the above purpose, the present invention provides a roof structure of prefabricated folding panels for daylighting, power generation and smoke exhaust, including prefabricated folding panels, electric smoke exhaust windows, waterproof and protective layer, thermal insulation layer, adhesive layer, waterproof coiled material and waterproof coating membrane and photovoltaic power generation panels; prefabricated folded panels include an upper horizontal structure, a middle inclined structure and a lower horizontal structure, the upper and lower ends of the middle inclined structure are connected at a certain angle with the upper The bottom steel beam or precast concrete structure of the roof of the building is connected; the electric smoke exhaust window is set upright on the opposite side of the middle inclined structure, and is located below the upper horizontal structure. The electric smoke exhaust window can be linked with the fire control, and the smoke It can be exhausted from the electric smoke exhaust window, and natural light can be injected into the building through the electric smoke exhaust window; waterproof and protective layer, insulation layer, adhesive layer, waterproof coiled material and waterproof coating film are arranged on the roof structure from outside to inside. On the area other than the electric smoke exhaust window; photovoltaic power generation panels are laid on the waterproof and protective layer of the middle inclined structure.

在一优选的实施方式中,预制折板还包括多个预留销键孔、多个吊环以及凹槽;多个预留销键孔与上部水平结构和下部水平结构垂直地设置在上部水平结构和下部水平结构上,预留销键孔充填柔性灌浆料;多个吊环预埋在上部水平结构、中间倾斜结构以及下部水平结构上;凹槽预留在每个吊环处,凹槽用于待预制折板安装完毕后切除吊环的露出部分,并且补平;In a preferred embodiment, the prefabricated folding plate also includes a plurality of reserved pin keyholes, a plurality of suspension rings and grooves; the plurality of reserved pin keyholes are vertically arranged on the upper horizontal structure with the upper horizontal structure and the lower horizontal structure and the lower horizontal structure, the reserved pin hole is filled with flexible grouting material; multiple lifting rings are pre-embedded on the upper horizontal structure, middle inclined structure and lower horizontal structure; the groove is reserved at each lifting ring, and the groove is used After the prefabricated folding plate is installed, the exposed part of the suspension ring is cut off and filled up;

在一优选的实施方式中,预制折板还包括多个预留销键孔以及外露钢筋;多个预留销键孔与上部水平结构垂直地设置在上部水平结构上;外露钢筋设置在未设置预留销键孔的下部水平结构上,外露钢筋为预制折板的内部钢筋从下部水平结构的端面处向外延伸的部分,外露钢筋用于与建筑物屋顶的预制混凝土结构进行现浇连接。In a preferred embodiment, the prefabricated folded plate also includes a plurality of reserved pin keyholes and exposed steel bars; a plurality of reserved pin keyholes are vertically arranged on the upper horizontal structure; On the lower horizontal structure where the pin hole is reserved, the exposed steel bar is the part of the internal steel bar of the prefabricated folded plate extending outward from the end face of the lower horizontal structure, and the exposed steel bar is used for in-situ connection with the precast concrete structure of the building roof.

在一优选的实施方式中,预留销键孔呈上大下小的漏斗形结构,每个预留销键孔套设在一个固定在底部钢梁或预制混凝土结构上的栓钉上,上部水平结构和下部水平结构通过预留销键孔、栓钉以及柔性灌浆料与建筑物屋顶的底部钢梁或预制混凝土结构形成柔性连接。In a preferred embodiment, the reserved keyholes have a funnel-shaped structure with a large top and a small bottom, and each reserved keyhole is sleeved on a peg fixed on the bottom steel beam or prefabricated concrete structure. The horizontal structure and the lower horizontal structure form a flexible connection with the bottom steel beam or prefabricated concrete structure of the building roof through reserved keyholes, pegs and flexible grouting materials.

在一优选的实施方式中,预制折板还包括预留甩筋、加强筋以及避位缺口;预留甩筋设置在下部水平结构上,预留甩筋的外漏部分与下部水平结构的上表面垂直设置,预留甩筋内置部分与下部水平结构的上表面平行设置,预留甩筋用于排烟窗支撑部的现场浇筑;加强筋设置在下部水平结构内,且与下部水平结构的上表面平行设置,加强筋与预留甩筋内置部分固定连接;避位缺口设置在上部水平结构和下部水平结构上,避位缺口用于避让建筑物屋顶的钢柱。In a preferred embodiment, the prefabricated folded plate also includes reserved ribs, reinforcing ribs and avoidance gaps; the reserved ribs are arranged on the lower horizontal structure, and the leaking part of the reserved ribs is connected to the upper part of the lower horizontal structure. The surface is set vertically, the built-in parts of the reserved ribs are set parallel to the upper surface of the lower horizontal structure, and the ribs are reserved for on-site pouring of the support part of the smoke exhaust window; the reinforcing ribs are set in the lower horizontal structure, and The upper surface is arranged in parallel, and the reinforcing rib is fixedly connected with the built-in part of the reserved rib; the avoidance gap is arranged on the upper horizontal structure and the lower horizontal structure, and the avoidance gap is used to avoid the steel column of the building roof.

在一优选的实施方式中,防水兼保护层为新型复合材料,新型复合材料分为柔性材料和硬性材料。In a preferred embodiment, the waterproof and protective layer is a new composite material, and the new composite material is divided into flexible materials and hard materials.

在一优选的实施方式中,柔性材料包括乳液Hff-1及粉料Hff-2,柔性材料的施工配比为乳液Hff-1:水:粉料Hff-2=1:2:3。In a preferred embodiment, the flexible material includes emulsion Hff-1 and powder material Hff-2, and the construction ratio of flexible material is emulsion Hff-1:water:powder material Hff-2=1:2:3.

在一优选的实施方式中,柔性材料的施工方法包括刮涂法、刷涂法或喷涂法。In a preferred embodiment, the construction method of the flexible material includes a scraping method, a brushing method or a spraying method.

在一优选的实施方式中,硬性材料包括粉料Hff-3,硬性材料的工方法包括刮涂法、刷涂法或喷涂法。In a preferred embodiment, hard material comprises powder material HW-3, and the working method of hard material comprises scraping method, brushing method or spraying method.

在一优选的实施方式中,硬性材料的施工配比包括以下比例:In a preferred embodiment, the construction ratio of hard materials includes the following ratios:

刮涂法的施工配比为粉料Hff-3:水=1:0.35±0.05;The construction proportioning of scraping method is powder material HW-3: water=1:0.35 ± 0.05;

刷涂法的施工配比为粉料Hff-3:水=1:0.4±0.05;以及The construction proportion of brushing method is powder material HW-3: water=1:0.4 ± 0.05; And

喷涂法的施工配比为粉料Hff-3:水=1:0.5±0.05。The construction proportion of spraying method is powder HW-3: water=1:0.5±0.05.

在一优选的实施方式中,光伏发电板与防水兼保护层之间采用粘结连接。In a preferred embodiment, the photovoltaic power generation panel is bonded to the waterproof and protective layer.

与现有技术相比,本发明的预制折板式采光发电排烟的屋面结构具有以下有益效果:本方案可以同时满足采光、温度调节与消防要求以及发电功能;预制折板呈倾斜状态,但发生火灾等意外情况时,斜板将烟挡住聚集,电动排烟窗自动打开,实现智慧化管控;窗户呈竖立状态,与周圈主体形成整体,气密性好,且满足采光要求。本方案属于装配式施工,施工便捷;传统施工工艺需要从地面搭设脚手架,尤其对于大型公建中大空间设计,需从地面搭设十几至几十余米的架体,耗时耗工,且具有安全隐患;而本方案采用装配式施工,直接辅以塔吊进行吊装即可,操作人员站立在既有屋面上,对此部分采光排烟屋面进行施工,安全系数高;且施工迅速便捷,工序前置,避免现场支模与浇筑混凝土。此外,由于该屋面坡道较大约60°,采用传统的防水卷材粘贴容易造成卷材粘贴不牢、空鼓下坠等问题,因此采用防水涂膜与一层自粘型防水卷材的防水层设计,自粘防水卷材依靠其自粘特性,可形成有效满粘防水效果,避免质量风险。在防水层上施工粘接层,聚氨脂发泡胶进行保温层粘贴,在保温板施工完成后进行挂防裂网及抗裂砂浆施工统一成为保温层。保温层施工完成后,在保温层上施工一种特殊防水材料,该防水材料具有防腐防火绝缘等特性,在该材料上粘贴光伏板,光伏板可发电,采用粘结方法不用打胀栓,因而不破坏防水以及保温层。本方案安全可靠,销键孔内浇灌柔性灌浆料,上部水平结构与下部水平结构和主体结构实现柔性铰连接,刚度适中,可以实现“小震不坏、中震可修、大震不脱落”的目标。Compared with the prior art, the roof structure of the prefabricated folded plate type lighting, power generation and smoke exhaust of the present invention has the following beneficial effects: this solution can meet the requirements of lighting, temperature regulation, fire protection and power generation at the same time; the prefabricated folded plate is inclined, but the occurrence of In the event of fire and other accidents, the slanting plate will block the smoke and gather, and the electric smoke exhaust window will automatically open to realize intelligent control; the window is in an upright state, forming an integral body with the main body of the surrounding circle, with good air tightness and meeting the lighting requirements. This scheme belongs to the prefabricated construction, and the construction is convenient; the traditional construction technology needs to build scaffolding from the ground, especially for the large space design of large public buildings, it is necessary to build a frame body of more than ten to tens of meters from the ground, which is time-consuming and labor-intensive. There are potential safety hazards; however, this scheme adopts prefabricated construction, which can be directly assisted by tower cranes for hoisting. The operator stands on the existing roof and constructs this part of the lighting and smoke exhaust roof, with a high safety factor; and the construction is fast and convenient. Front, to avoid on-site formwork and concrete pouring. In addition, since the slope of the roof is about 60°, the use of traditional waterproof membranes for pasting is likely to cause problems such as poor adhesion of the membranes, hollowing and falling. Therefore, a waterproof layer of waterproof coating and a layer of self-adhesive waterproof membrane Design, self-adhesive waterproof membrane relies on its self-adhesive characteristics, can form an effective full-adhesive waterproof effect, and avoid quality risks. The adhesive layer is constructed on the waterproof layer, and the polyurethane styrofoam glue is used to paste the insulation layer. After the construction of the insulation board is completed, the anti-cracking net and anti-cracking mortar construction are carried out to form a unified insulation layer. After the construction of the insulation layer is completed, a special waterproof material is constructed on the insulation layer. The waterproof material has the characteristics of anti-corrosion, fire-proof and insulation. Paste photovoltaic panels on this material, and the photovoltaic panels can generate electricity. The bonding method does not require expansion bolts, so Does not damage the waterproof and insulation layers. This scheme is safe and reliable. The flexible grouting material is poured in the pin hole, and the upper horizontal structure is connected with the lower horizontal structure and the main structure with a flexible hinge. The goal.

附图说明Description of drawings

图1是根据本发明一实施方式的采光排烟屋面结构的平面布置示意图;Fig. 1 is a schematic plan layout diagram of a daylighting and smoke exhaust roof structure according to an embodiment of the present invention;

图2是根据本发明一实施方式的采光排烟屋面结构的剖视结构示意图;Fig. 2 is a schematic cross-sectional structural view of a daylighting and smoke exhaust roof structure according to an embodiment of the present invention;

图3是根据本发明一实施方式的单片预制折板的复式结构示意图;Fig. 3 is a composite structure schematic diagram of a single prefabricated folded plate according to an embodiment of the present invention;

图4是图3的1—1处的剖视结构示意图;Fig. 4 is a schematic cross-sectional structure diagram at 1-1 of Fig. 3;

图5是根据本发明一实施方式的预留销键孔的放大结构示意图;Fig. 5 is a schematic diagram of an enlarged structure of a reserved pin hole according to an embodiment of the present invention;

图6是根据本发明一实施方式的吊环及凹槽的施工结构示意图;Fig. 6 is a schematic diagram of the construction structure of the suspension ring and the groove according to an embodiment of the present invention;

图7是根据本发明一实施方式的单片预制折板的内部钢筋结构示意图;Fig. 7 is a schematic diagram of the internal reinforcement structure of a single prefabricated folded plate according to an embodiment of the present invention;

图8是图7的2—2处的剖视结构示意图;Fig. 8 is a schematic cross-sectional structural view at 2-2 of Fig. 7;

图9是根据本发明一实施方式的单片预制折板的预留甩筋俯视示意图;Fig. 9 is a schematic top view of the reserved tendons of a single prefabricated folded plate according to an embodiment of the present invention;

图10是图7的Ⅰ处的局部放大结构示意图;Fig. 10 is a schematic diagram of a partially enlarged structure at I of Fig. 7;

图11是根据本发明一实施方式的避位缺口的俯视示意图;Fig. 11 is a schematic top view of an avoidance gap according to an embodiment of the present invention;

图12是根据本发明一实施方式的未设置下部销键孔单片预制折板的俯视结构示意图;Fig. 12 is a schematic top view of a single-piece prefabricated folded plate without lower pin keyholes according to an embodiment of the present invention;

图13是图12的3—3处的剖视结构示意图;Fig. 13 is a schematic cross-sectional structural view at 3-3 of Fig. 12;

图14是图13的Ⅱ处的局部放大结构示意图;Fig. 14 is a schematic diagram of a partially enlarged structure at II of Fig. 13;

图15是根据本发明一实施方式的未设置下部销键孔单片预制折板的侧视结构示意图;Fig. 15 is a schematic side view of a single-piece prefabricated folded plate without lower pin keyholes according to an embodiment of the present invention;

图16是根据本发明一实施方式的双排销键孔单片预制折板的俯视结构示意图;Fig. 16 is a top structural schematic diagram of a single-piece prefabricated folded plate with double-row pin keyholes according to an embodiment of the present invention;

图17是图16的4—4处的剖视结构示意图。Fig. 17 is a schematic cross-sectional structural view at 4-4 in Fig. 16 .

具体实施方式Detailed ways

下面结合附图,对本发明的具体实施方式进行详细描述,但应当理解本发明的保护范围并不受具体实施方式的限制。The specific embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings, but it should be understood that the protection scope of the present invention is not limited by the specific embodiments.

除非另有其它明确表示,否则在整个说明书和权利要求书中,术语“包括”或其变换如“包含”或“包括有”等等将被理解为包括所陈述的元件或组成部分,而并未排除其它元件或其它组成部分。Unless expressly stated otherwise, throughout the specification and claims, the term "comprise" or variations thereof such as "includes" or "includes" and the like will be understood to include the stated elements or constituents, and not Other elements or other components are not excluded.

如图1至图2所示,根据本发明优选实施方式的一种预制折板式采光发电排烟的屋面结构,包括预制折板、电动排烟窗、防水兼保护层、保温层、粘结层、防水卷材及防水涂膜以及光伏发电板;预制折板包括上部水平结构、中间倾斜结构及下部水平结构,中间倾斜结构的上下端与上部水平结构和下部水平结构成一定夹角连接,该夹角一般为60度左右,但本发明并不以此限。上部水平结构和下部水平结构与建筑物屋顶的底部钢梁或预制混凝土结构连接;电动排烟窗呈竖立状态的设置在中间倾斜结构的对面,且位于上部水平结构的下方,电动排烟窗能够与消防联动控制,且烟气能够从电动排烟窗排出,自然光能够通过电动排烟窗射入建筑物内;防水兼保护层、保温层、粘结层、防水卷材及防水涂膜从外至内依次设置在屋面结构除去电动排烟窗以外的区域上;光伏发电板铺设在中间倾斜结构的防水兼保护层上。由于国内的一次性能源储量远远低于世界的平均水平,大约只有世界总储量的10%,太阳能是人类取之不尽用之不竭的可再生能源,具有充分的清洁性、绝对的安全性、相对的广泛性、确实的长寿命和免维护性、资源的充足性及潜在的经济性等优点,在长期的能源战略中具有重要地位。As shown in Figures 1 to 2, a prefabricated folded panel roof structure for daylighting, power generation, and smoke exhaust according to a preferred embodiment of the present invention includes prefabricated folded panels, electric smoke exhaust windows, waterproof and protective layers, thermal insulation layers, and adhesive layers , waterproof coiled material and waterproof coating film, and photovoltaic power generation panels; prefabricated folded panels include an upper horizontal structure, a middle inclined structure and a lower horizontal structure. The upper and lower ends of the middle inclined structure are connected at a certain angle with the upper horizontal structure and the lower horizontal structure. The included angle is generally about 60 degrees, but the present invention is not limited thereto. The upper horizontal structure and the lower horizontal structure are connected with the bottom steel beam or prefabricated concrete structure of the building roof; the electric smoke exhaust window is erected on the opposite side of the middle inclined structure, and is located below the upper horizontal structure. The electric smoke exhaust window can Linkage control with fire protection, and smoke can be discharged from the electric smoke exhaust window, natural light can enter the building through the electric smoke exhaust window; waterproof and protective layer, insulation layer, adhesive layer, waterproof coiled material and waterproof coating film The interior is arranged sequentially on the area of the roof structure except for the electric smoke exhaust window; the photovoltaic power generation panel is laid on the waterproof and protective layer of the middle inclined structure. Since the domestic primary energy reserves are far below the world average level, only about 10% of the world's total reserves, solar energy is an inexhaustible renewable energy source for human beings, which is fully clean and absolutely safe The advantages of nature, relative universality, long life and maintenance-free, resource adequacy and potential economy play an important role in the long-term energy strategy.

请参阅图1,在一些实施方式中,单块预制折板的俯视投影一般为矩形或者不规则形状,因为屋顶的形状以及特殊结构决定,预制折板式采光发电排烟的屋面结构基本是一片一排的设置,每一排首先由多块预制折板并排拼接安装,遇到特殊情况就得需要不规则形状的预制折板,不规则形状的预制折板也是事先根据设置图纸在车间预制的。Please refer to Figure 1. In some embodiments, the top view projection of a single prefabricated folded plate is generally rectangular or irregular. Because of the shape and special structure of the roof, the roof structure of the prefabricated folded plate for daylighting, power generation and smoke exhaust is basically one piece. For the arrangement of rows, each row is first assembled and installed with multiple prefabricated folded panels side by side. In special cases, prefabricated folded panels with irregular shapes are required. The irregularly shaped prefabricated folded panels are also prefabricated in the workshop according to the set drawings.

如图3至图5所示,在一些实施方式中,预制折板还包括多个预留销键孔,预留销键孔与上部水平结构和下部水平结构垂直地设置在上部水平结构和下部水平结构上,预留销键孔充填柔性灌浆料。As shown in Figures 3 to 5, in some embodiments, the prefabricated folded plate further includes a plurality of reserved pin keyholes, and the reserved pin keyholes are vertically arranged on the upper horizontal structure and the lower horizontal structure. On the horizontal structure, the reserved pin hole is filled with flexible grouting material.

在一些实施方式中,预留销键孔呈上大下小的漏斗形结构,每个预留销键孔套设在一个固定在底部钢梁或预制混凝土结构上的栓钉上,上部水平结构和下部水平结构通过预留销键孔、栓钉以及柔性灌浆料与建筑物屋顶的底部钢梁或预制混凝土结构形成柔性连接。In some embodiments, the reserved pin keyholes are in a funnel-shaped structure with a large top and a small bottom, and each reserved pin keyhole is sleeved on a peg fixed on the bottom steel beam or prefabricated concrete structure, and the upper horizontal structure It forms a flexible connection with the lower horizontal structure and the bottom steel beam or prefabricated concrete structure of the building roof through reserved pin holes, pegs and flexible grouting materials.

如图6所示,同时参阅图3、图4,在一些实施方式中,预制折板还包括多个吊环,其预埋在上部水平结构、中间倾斜结构以及下部水平结构上。As shown in Fig. 6, referring to Fig. 3 and Fig. 4 at the same time, in some embodiments, the prefabricated folded plate further includes a plurality of lifting rings, which are pre-embedded on the upper horizontal structure, the middle inclined structure and the lower horizontal structure.

在一些实施方式中,预制折板还包括凹槽,凹槽预留在每个吊环处,凹槽用于待预制折板安装完毕后切除吊环的露出部分,并且补平。凹槽的设置主要是因为预制折板安装完毕后,吊环已经完成了吊装的功能,而且吊环会阻碍接下来的保温层等的施工,因此需要将吊环露出部分切除,再用水泥浆凹槽处补平。In some embodiments, the prefabricated folded plate further includes a groove, the groove is reserved at each suspension ring, and the groove is used to cut off the exposed part of the suspension ring after the prefabricated folded plate is installed, and fill it up. The setting of the groove is mainly because after the prefabricated folded plate is installed, the lifting ring has completed the lifting function, and the lifting ring will hinder the construction of the next insulation layer, etc., so it is necessary to cut off the exposed part of the lifting ring, and then fill the groove with cement slurry. flat.

如图16至图17所示,在一些实施方式中,多个预留销键孔至少在上部水平结构和下部水平结构上排列成一排。从另一个角度说,下部水平结构上有时候不设置预留销键孔,或者设置1到2排预留销键孔,具体的设置情况需要与实际的安装环境决定。As shown in FIGS. 16 to 17 , in some embodiments, a plurality of reserved pinholes are arranged in a row at least on the upper horizontal structure and the lower horizontal structure. From another point of view, sometimes no reserved pin hole is provided on the lower horizontal structure, or 1 to 2 rows of reserved pin hole are provided. The specific setting needs to be determined according to the actual installation environment.

如图12至图14所示,在一些实施方式中,预制折板的多个预留销键孔只设置在上部水平结构上,而下部水平结构上不设置预留销键孔,那么替代预留销键孔连接的是外露钢筋,外露钢筋设置在未设置预留销键孔的下部水平结构上,外露钢筋为预制折板的内部钢筋从下部水平结构的端面处向外延伸的部分,外露钢筋用于与建筑物屋顶的预制混凝土结构进行现浇连接。As shown in Figures 12 to 14, in some embodiments, the multiple reserved keyholes of the prefabricated folded plates are only provided on the upper horizontal structure, while no reserved keyholes are provided on the lower horizontal structure, then instead of the reserved The exposed steel bars are connected to the keyholes of the pins. The exposed steel bars are set on the lower horizontal structure without the reserved pin key holes. Rebar is used for the cast-in-place connection to the precast concrete structure of the building's roof.

如图7至图11所示,在一些实施方式中,预制折板还包括预留甩筋、加强筋以及避位缺口;预留甩筋设置在下部水平结构上,预留甩筋的外漏部分与下部水平结构的上表面垂直设置,预留甩筋内置部分与下部水平结构的上表面平行设置,预留甩筋用于排烟窗支撑部的现场浇筑;加强筋设置在下部水平结构内,且与下部水平结构的上表面平行设置,加强筋与预留甩筋内置部分固定连接;避位缺口设置在上部水平结构和下部水平结构上,避位缺口用于避让建筑物屋顶的钢柱。带有避位缺口预制折板一般都是事先根据设置图纸在车间预制好的。As shown in Figures 7 to 11, in some embodiments, the prefabricated folded plate also includes reserved ribs, reinforcing ribs and avoidance gaps; the reserved ribs are arranged on the lower horizontal structure, and the leakage of the reserved ribs The part is set vertically with the upper surface of the lower horizontal structure, and the built-in parts of the reserved ribs are arranged parallel to the upper surface of the lower horizontal structure, and the reserved ribs are used for on-site pouring of the support part of the smoke exhaust window; the reinforcing ribs are set in the lower horizontal structure , and set parallel to the upper surface of the lower horizontal structure, and the reinforcing ribs are fixedly connected to the built-in part of the reserved ribs; the avoidance gap is set on the upper horizontal structure and the lower horizontal structure, and the avoidance gap is used to avoid the steel columns on the roof of the building . Prefabricated folded panels with avoidance gaps are generally prefabricated in the workshop according to the set drawings.

请参阅图2,在一些实施方式中,电动排烟窗呈竖立状态的设置在中间倾斜结构的对面,且位于上部水平结构的下方,由于屋顶的结构不是统一不变的,所以排烟窗支撑部一般情况下需要现场浇筑。Please refer to Figure 2. In some embodiments, the electric smoke exhaust window is erected on the opposite side of the middle inclined structure, and is located below the upper horizontal structure. Since the structure of the roof is not uniform, the smoke exhaust window supports Under normal circumstances, the part needs to be poured on site.

在一些实施方式中,防水兼保护层为新型复合材料,新型复合材料分为柔性材料和硬性材料。新型复合材料兼具挥发固化和反应固化双重功能:液料和粉料配伍、搅拌、混合后,聚合物乳液即把矿物颗粒包裹起来,乳液被矿物颗粒脱水,形成连续的、具有一定强度和弹性的橡胶薄膜;而矿物颗粒吸收乳液水分,发生水化反应而固化,并与橡胶薄膜形成具有网络结构的防水涂膜。In some embodiments, the waterproof and protective layer is a new composite material, and the new composite material is divided into flexible materials and hard materials. The new composite material has dual functions of volatilization and reaction curing: after the liquid material and powder are mixed, stirred, and mixed, the polymer emulsion wraps the mineral particles, and the emulsion is dehydrated by the mineral particles to form a continuous, certain strength and elasticity. The rubber film; and the mineral particles absorb the water of the emulsion, undergo a hydration reaction and solidify, and form a waterproof coating film with a network structure with the rubber film.

在一些实施方式中,柔性材料主要包括乳液Hff-1及粉料Hff-2;柔性材料的各项技术性能都达到或超过行业标准,具有以下优势:In some embodiments, the flexible material mainly includes the emulsion Hff-1 and the powder Hff-2; each technical performance of the flexible material reaches or exceeds the industry standard, and has the following advantages:

(1)本防腐防水柔性材料涂层强度高(拉伸强度达2.8MPa)、韧性大(断裂伸长率达117%),具有优异的耐水性、耐候性、耐紫外线、耐辐射、耐氧化。在-40℃~160℃环境温度下涂层无变化。具有很好的化学稳定性。(1) This anti-corrosion and waterproof flexible material has high coating strength (tensile strength up to 2.8MPa), high toughness (elongation at break up to 117%), and excellent water resistance, weather resistance, UV resistance, radiation resistance, and oxidation resistance. . There is no change in the coating at ambient temperatures of -40°C to 160°C. Has good chemical stability.

(2)本品为水溶性环保型产品,无毒、无味,无任何污染。检测证明,其中甲醛、VOC释放量,重金属溶出量,低于仪器的检出限(即未检测出)。(2) This product is a water-soluble and environment-friendly product, non-toxic, tasteless, and without any pollution. The test proved that the amount of formaldehyde and VOC released and the amount of heavy metal dissolved were lower than the detection limit of the instrument (that is, not detected).

(3)粘接力强(粘接强度达1.5MPa),能与各种材料牢固粘接,如混凝土、石材、木材、玻璃、金属材料等。(3) Strong adhesion (bonding strength up to 1.5MPa), can be firmly bonded with various materials, such as concrete, stone, wood, glass, metal materials, etc.

(4)常温作业,涂覆简便,工期短,便于维修。(4) Normal temperature operation, easy coating, short construction period and easy maintenance.

(5)涂层随基面形状变化,无接缝。可刮涂、刷涂、喷涂。(5) The coating changes with the shape of the base surface without joints. Can be scraped, brushed and sprayed.

(6)抗腐蚀性强,可在pH值2~12范围内及任何含盐份的环境中使用。(6) It has strong corrosion resistance and can be used in the range of pH 2-12 and any saline environment.

(7)良好的力学特性,拉伸机械强度>2Mpa(刚性产品),>0.12Mpa(柔性产品)。并具有一定程度上的弹性。(7) Good mechanical properties, tensile mechanical strength >2Mpa (rigid product), >0.12Mpa (flexible product). And has a certain degree of flexibility.

(8)隔音减震,本材料为多孔材料,并具有相当好的弹性,是一种优秀的隔音减震材料(8) Sound insulation and shock absorption. This material is porous and has good elasticity. It is an excellent sound insulation and shock absorption material.

(9)优越的隔热性能,常温下(25℃)导热系数可达到0.015w/m·k。(9) Excellent thermal insulation performance, the thermal conductivity at room temperature (25°C) can reach 0.015w/m·k.

(10)在200℃以下长期使用整体疏水(10) Long-term use of overall hydrophobicity below 200°C

(11)涂层无需养护,只需在自然条件下自行干燥。(11) The coating does not need to be maintained, it only needs to dry itself under natural conditions.

(12)本产品阻燃、绝缘。(12) This product is flame retardant and insulating.

在一些实施方式中,柔性材料的基面处理需要做到:施工基面必须完整、坚固、干净,无积水、尘土、油渍及其它污物。In some embodiments, the treatment of the base surface of the flexible material needs to be as follows: the construction base surface must be complete, firm, and clean, without water, dust, oil stains and other dirt.

在一些实施方式中,柔性材料包括乳液Hff-1及粉料Hff-2,柔性材料的施工配比为乳液Hff-1:水:粉料Hff-2=1:2:3。具体配比流程大致为:先将乳液和水按比例稀释,再将粉料倒入液体内,充分搅拌均匀,其中不应有颗粒。机械搅拌一般为5分钟。每次配料量不宜过多,应以20~30分钟使用量为准。材料初凝后不得加水再用。In some embodiments, the flexible material includes emulsion Hff-1 and powder Hff-2, and the construction ratio of flexible material is emulsion Hff-1:water:powder Hff-2=1:2:3. The specific proportioning process is roughly as follows: firstly dilute the emulsion and water in proportion, then pour the powder into the liquid, stir well, and there should be no particles in it. Mechanical stirring is generally 5 minutes. The amount of ingredients should not be too much each time, and the amount used in 20 to 30 minutes should prevail. Do not add water to the material after initial setting.

在一些实施方式中,柔性材料的施工方法可以采用刮涂法、刷涂法或喷涂法,具体流程大致如下:In some embodiments, the construction method of the flexible material can be scraped, brushed or sprayed, and the specific process is roughly as follows:

(1)刮涂法:用抹子或刮板将混合均匀的防腐防水柔性材料刮抹到施工基面上。先刮边角和结构复杂部位,后刮平整表面。每遍刮涂方向要保持一致,使相互衔接厚度均匀。在一层实干后再刮涂下一层,后一层刮涂方向要与前一层相互垂直。每一遍的涂层要薄;一般刮涂4遍以上,使之达到要求的总厚度,材料实干后可进行下一道工序。(1) Scratch coating method: use a trowel or scraper to scrape the uniformly mixed anti-corrosion and waterproof flexible material onto the construction base surface. First scrape the corners and complex structures, and then scrape the smooth surface. The direction of scraping each time should be consistent, so that the joint thickness is uniform. After one layer is dry, scrape the next layer, and the direction of scraping the last layer should be perpendicular to the previous layer. Each coating should be thin; generally scrape coating more than 4 times to make it reach the required total thickness, and the next process can be carried out after the material is dry.

(2)刷涂法:用刷子刷涂。其他同刮涂法。(2) Brushing method: brush with a brush. Others are the same as scraping method.

(3)喷涂法:利用一般外墙涂料喷涂设备进行喷涂。其他同刮涂法。(3) Spraying method: use general exterior wall paint spraying equipment for spraying. Others are the same as scraping method.

在一些实施方式中,柔性材料的施工注意事项大致如下:In some embodiments, construction considerations for flexible materials are roughly as follows:

(1)最适宜的施工温度是20±10℃,尽量避免在5℃以下、35℃以上干燥炎热环境下施工。在0℃以下不得施工。(1) The most suitable construction temperature is 20±10°C, and try to avoid construction in dry and hot environments below 5°C and above 35°C. Do not apply below 0°C.

(2)涂层必须实干后,才能进行下一道施工工序,以免破坏防水层。(2) The coating must be dry before proceeding to the next construction process, so as not to damage the waterproof layer.

(3)施工过程中防止涂层受到雨淋。(3) Prevent the coating from being exposed to rain during construction.

(4)Hff-2粉料不能单独加水使用。(4) Hff-2 powder cannot be used alone with water.

在一些实施方式中,硬性材料主要包括粉料Hff-3,硬性材料具有类分子筛结构和渗透结晶作用。防水层具有呼吸、防水和防腐功能。能够与混凝土牢固粘结。材料含有活性物质,在它的催化作用下,促进了水化反应并产生不溶于水的结晶,堵塞水的通道并提高了基础结构的抗压、抗折强度和抗渗压力。当产生微小裂隙时,只要有水存在,能重新生成结晶,实现自我修复。可有效地保护金属并提高了它的耐久性。硬性材料的基面处理和应用领域与柔性材料大致相同。In some embodiments, the hard material mainly includes powder HW-3, and the hard material has a molecular sieve-like structure and osmotic crystallization. The waterproof layer has breathing, waterproof and anti-corrosion functions. Can be firmly bonded to concrete. The material contains active substances, under its catalysis, it promotes the hydration reaction and produces water-insoluble crystals, which block the water channel and improve the compression resistance, flexural strength and impermeability pressure of the basic structure. When tiny cracks are generated, as long as there is water, crystals can be regenerated to achieve self-healing. Can effectively protect the metal and improve its durability. The substrate preparation and fields of application for rigid materials are largely the same as for flexible materials.

在一些实施方式中,硬性材料的工方法同样可以采用刮涂法、刷涂法或喷涂法。硬性材料的施工配比包括以下比例:刮涂法的施工配比为粉料Hff-3:水=1:0.35±0.05;刷涂法的施工配比为粉料Hff-3:水=1:0.4±0.05;以及喷涂法的施工配比为粉料Hff-3:水=1:0.5±0.05。配比方法大致为:将防腐防水硬性材料倒入水中,每次配料量应以20~30分钟使用量为准,充分搅拌均匀,机械搅拌时间一般为5分钟,其中不应有颗粒。施工方法大致如下:In some embodiments, the hard material can also be processed by scraping, brushing or spraying. The construction ratio of hard material comprises following ratio: the construction ratio of scraping method is powder material Hff-3: water=1:0.35 ± 0.05; The construction proportion of brush coating method is powder material Hff-3: water=1: 0.4 ± 0.05; and the construction proportion of spraying method is powder material Hff-3: water=1:0.5 ± 0.05. The proportioning method is roughly as follows: Pour the anti-corrosion and waterproof hard material into the water. The amount of each batch should be based on the amount used in 20-30 minutes. Stir well and evenly. The mechanical stirring time is generally 5 minutes, and there should be no particles. The construction method is roughly as follows:

(1)刮涂法:用抹子或刮板将混合均匀的防腐防水硬性材料刮抹到施工基面上。先做边角和特殊部位,后做平整表面。每遍刮涂方向要保持一致,后一层刮涂方向要与前一层相互垂直。使相互衔接厚度均匀。在一层终凝后再刮涂下一层。涂层一般刮涂2~3遍,使之达到要求的总厚度。(1) Scratch coating method: Use a trowel or scraper to scrape the uniformly mixed anti-corrosion and waterproof hard material onto the construction base surface. Do the corners and special parts first, and then make the flat surface. The scraping direction of each pass should be consistent, and the scraping direction of the next layer should be perpendicular to the previous layer. Make the mutual connection thickness uniform. After one layer has finally set, apply the next layer. The coating is generally scraped 2 to 3 times to make it reach the required total thickness.

(2)刷涂法:除材料配比不同外,其他同刮涂法。(2) Brush coating method: except for the different material ratios, it is the same as the scraping method.

(3)喷涂法:除材料配比不同和利用专用喷涂设备外,其他同刮涂法。(3) Spraying method: except that the material ratio is different and the special spraying equipment is used, the others are the same as the scraping method.

在一些实施方式中,硬性材料的施工注意事项大致如下:In some embodiments, the construction precautions for hard materials are roughly as follows:

(1)和料加水量应严格按照规定执行,切忌多加水以免影响工程质量。(1) The amount of water added to the blended material should be strictly implemented in accordance with the regulations, and excessive water should not be added to avoid affecting the quality of the project.

(2)和好的料如果开始初凝,不得加水再用。(2) If the reconciled material starts to set, do not add water for reuse.

(3)施工的环境温度为5℃~35℃,最佳温度为20±10℃。(3) The ambient temperature for construction is 5°C to 35°C, and the optimum temperature is 20±10°C.

(4)露天施工温度较高时,施工建议安排在早、晚间进行。避免由于涂层脱水干燥过快,材料水化、石化不充分,影响工程质量。(4) When the temperature of open-air construction is high, it is recommended to arrange construction in the morning and evening. Avoid excessive dehydration and drying of the coating, insufficient hydration and petrification of the material, which will affect the quality of the project.

(5)防腐防水硬性材料涂层需养护24小时,才能进行下一道施工工序,以免破坏防水层。(5) The coating of anti-corrosion and waterproof hard materials needs to be cured for 24 hours before the next construction process can be carried out to avoid damage to the waterproof layer.

(6)防腐防水硬性材料是涂层材料,不得作为混凝土或灰膏的外加剂。(6) Anti-corrosion and waterproof hard materials are coating materials and cannot be used as admixtures for concrete or plaster.

在一些实施方式中,新型复合材料的各项性能指标参见表一:In some embodiments, the various performance indicators of the novel composite material are shown in Table 1:

在一些实施方式中,新型复合材料的各项技术指标参见表二:技术指标(硬性涂料)In some embodiments, the technical indicators of the novel composite material are referred to Table 2: Technical indicators (hard coating)

特殊技术指标(硬性涂料)Special technical indicators (hard coating)

技术指标(柔性涂料)Technical Index (Flexible Coating)

环保指标(柔性涂料)Environmental indicators (flexible coatings)

与现有技术相比,本发明的预制折板式采光发电排烟的屋面结构具有以下优点:本方案可以同时满足采光、温度调节与消防要求以及发电功能;预制折板呈倾斜状态,但发生火灾等意外情况时,斜板将烟挡住聚集,电动排烟窗自动打开,实现智慧化管控;窗户呈竖立状态,与周圈主体形成整体,气密性好,且满足采光要求。本方案属于装配式施工,施工便捷;传统施工工艺需要从地面搭设脚手架,尤其对于大型公建中大空间设计,需从地面搭设十几至几十余米的架体,耗时耗工,且具有安全隐患;而本方案采用装配式施工,直接辅以塔吊进行吊装即可,操作人员站立在既有屋面上,对此部分采光排烟屋面进行施工,安全系数高;且施工迅速便捷,工序前置,避免现场支模与浇筑混凝土。此外,由于该屋面坡道较大约60°,采用传统的防水卷材粘贴容易造成卷材粘贴不牢、空鼓下坠等问题,因此采用防水涂膜与一层自粘型防水卷材的防水层设计,自粘防水卷材依靠其自粘特性,可形成有效满粘防水效果,避免质量风险。在防水层上施工粘接层,聚氨脂发泡胶进行保温层粘贴,在保温板施工完成后进行挂防裂网及抗裂砂浆施工统一成为保温层。保温层施工完成后,在保温层上施工一种特殊防水材料,该防水材料具有防腐防火绝缘等特性,在该材料上粘贴光伏板,光伏板可发电,采用粘结方法不用打胀栓,因而不破坏防水以及保温层。本方案安全可靠,销键孔内浇灌柔性灌浆料,上部水平结构与下部水平结构和主体结构实现柔性铰连接,刚度适中,可以实现“小震不坏、中震可修、大震不脱落”的目标。Compared with the prior art, the prefabricated folded-plate roof structure for daylighting, power generation and smoke exhaust of the present invention has the following advantages: this solution can meet the requirements of daylighting, temperature regulation, fire protection and power generation at the same time; the prefabricated folded plate is inclined, but the fire In the event of an accident, the slanting plate will block the smoke and gather, and the electric smoke exhaust window will automatically open to realize intelligent control; the window is in an upright state, forming an integral body with the main body of the surrounding circle, with good airtightness and meeting the lighting requirements. This scheme belongs to the prefabricated construction, and the construction is convenient; the traditional construction technology needs to build scaffolding from the ground, especially for the large space design of large public buildings, it is necessary to build a frame body of more than ten to tens of meters from the ground, which is time-consuming and labor-intensive. There are potential safety hazards; however, this scheme adopts prefabricated construction, which can be directly assisted by tower cranes for hoisting. The operator stands on the existing roof and constructs this part of the lighting and smoke exhaust roof, with a high safety factor; and the construction is fast and convenient. Front, to avoid on-site formwork and concrete pouring. In addition, since the slope of the roof is about 60°, the use of traditional waterproof membranes for pasting is likely to cause problems such as poor adhesion of the membranes, hollowing and falling. Therefore, a waterproof layer of waterproof coating and a layer of self-adhesive waterproof membrane Design, self-adhesive waterproof membrane relies on its self-adhesive characteristics, can form an effective full-adhesive waterproof effect, and avoid quality risks. The adhesive layer is constructed on the waterproof layer, and the polyurethane styrofoam glue is used to paste the insulation layer. After the construction of the insulation board is completed, the anti-cracking net and anti-cracking mortar construction are carried out to form a unified insulation layer. After the construction of the insulation layer is completed, a special waterproof material is constructed on the insulation layer. The waterproof material has the characteristics of anti-corrosion, fire-proof and insulation. Paste photovoltaic panels on this material, and the photovoltaic panels can generate electricity. The bonding method does not require expansion bolts, so Does not damage the waterproof and insulation layers. This scheme is safe and reliable. The flexible grouting material is poured in the pin hole. The upper horizontal structure is connected with the lower horizontal structure and the main structure with a flexible hinge. The goal.

前述对本发明的具体示例性实施方案的描述是为了说明和例证的目的。这些描述并非想将本发明限定为所公开的精确形式,并且很显然,根据上述教导,可以进行很多改变和变化。对示例性实施例进行选择和描述的目的在于解释本发明的特定原理及其实际应用,从而使得本领域的技术人员能够实现并利用本发明的各种不同的示例性实施方案以及各种不同的选择和改变。本发明的范围意在由权利要求书及其等同形式所限定。The foregoing descriptions of specific exemplary embodiments of the present invention have been presented for purposes of illustration and description. These descriptions are not intended to limit the invention to the precise form disclosed, and obviously many modifications and variations are possible in light of the above teaching. The exemplary embodiments were chosen and described in order to explain the specific principles of the invention and its practical application, thereby enabling others skilled in the art to make and use various exemplary embodiments of the invention, as well as various Choose and change. It is intended that the scope of the invention be defined by the claims and their equivalents.

Claims (10)

1.一种预制折板式采光发电排烟的屋面结构,其特征在于,包括:1. A prefabricated folded-plate roof structure for daylighting, power generation, and smoke exhaust, characterized in that it comprises: 预制折板,其包括上部水平结构、中间倾斜结构及下部水平结构,所述中间倾斜结构的上下端与所述上部水平结构和所述下部水平结构成一定夹角连接,所述上部水平结构和所述下部水平结构与建筑物屋顶的底部钢梁或预制混凝土结构连接;The prefabricated folded plate includes an upper horizontal structure, an intermediate inclined structure and a lower horizontal structure, the upper and lower ends of the intermediate inclined structure are connected at a certain angle with the upper horizontal structure and the lower horizontal structure, and the upper horizontal structure and the lower horizontal structure are connected at a certain angle. The lower horizontal structure is connected to the bottom steel beam or precast concrete structure of the building roof; 电动排烟窗,其呈竖立状态的设置在所述中间倾斜结构的对面,且位于所述上部水平结构的下方,所述电动排烟窗能够与消防联动控制,且烟气能够从所述电动排烟窗排出,自然光能够通过所述电动排烟窗射入建筑物内;The electric smoke exhaust window is erected on the opposite side of the middle inclined structure, and is located below the upper horizontal structure. The electric smoke exhaust window can be controlled in conjunction with fire protection, and the smoke can flow from the electric smoke exhaust window. The smoke exhaust window is exhausted, and natural light can enter the building through the electric smoke exhaust window; 防水兼保护层、保温层、粘结层、防水卷材及防水涂膜,其从外至内依次设置在所述屋面结构除去电动排烟窗以外的区域上;以及Waterproof and protective layer, thermal insulation layer, adhesive layer, waterproof coiled material and waterproof coating film, which are sequentially arranged on the area of the roof structure except the electric smoke exhaust window from the outside to the inside; and 光伏发电板,其铺设在所述中间倾斜结构的所述防水兼保护层上。The photovoltaic power generation panel is laid on the waterproof and protective layer of the intermediate inclined structure. 2.如权利要求1所述的预制折板式采光发电排烟的屋面结构,其特征在于,所述预制折板还包括:2. The prefabricated folded panel roof structure for daylighting, power generation and smoke exhaust as claimed in claim 1, characterized in that, the prefabricated folded panel further comprises: 多个预留销键孔,其与所述上部水平结构和所述下部水平结构垂直地设置在所述上部水平结构和所述下部水平结构上,所述预留销键孔充填柔性灌浆料;A plurality of reserved key holes, which are vertically arranged on the upper horizontal structure and the lower horizontal structure, and the reserved key holes are filled with flexible grouting material; 多个吊环,其预埋在所述上部水平结构、所述中间倾斜结构以及所述下部水平结构上;以及a plurality of lifting rings, which are pre-embedded on the upper horizontal structure, the intermediate inclined structure and the lower horizontal structure; and 凹槽,其预留在每个所述吊环处,所述凹槽用于待所述预制折板安装完毕后切除所述吊环的露出部分,并且补平。A groove is reserved at each of the suspension rings, and the groove is used to cut off the exposed part of the suspension ring after the prefabricated folding plate is installed, and fill it up. 3.如权利要求1所述的预制折板式采光发电排烟的屋面结构,其特征在于,所述预制折板还包括:3. The prefabricated folded panel roof structure for daylighting, power generation and smoke exhaust as claimed in claim 1, characterized in that the prefabricated folded panel further comprises: 多个预留销键孔,其与所述上部水平结构垂直地设置在所述上部水平结构上;以及a plurality of reserved pinholes, which are arranged on the upper horizontal structure perpendicular to the upper horizontal structure; and 外露钢筋,其设置在未设置所述预留销键孔的所述下部水平结构上,所述外露钢筋为所述预制折板的内部钢筋从所述下部水平结构的端面处向外延伸的部分,所述外露钢筋用于与所述建筑物屋顶的预制混凝土结构进行现浇连接。The exposed steel bar is arranged on the lower horizontal structure without the reserved pin hole, and the exposed steel bar is the part where the internal steel bar of the prefabricated folded plate extends outward from the end surface of the lower horizontal structure , the exposed steel bars are used for in-situ connection with the prefabricated concrete structure of the roof of the building. 4.如权利要求2或3所述的预制折板式采光发电排烟的屋面结构,其特征在于,所述预留销键孔呈上大下小的漏斗形结构,每个所述预留销键孔套设在一个固定在所述底部钢梁或所述预制混凝土结构上的栓钉上,所述上部水平结构和所述下部水平结构通过所述预留销键孔、所述栓钉以及所述柔性灌浆料与建筑物屋顶的底部钢梁或预制混凝土结构形成柔性连接。4. The prefabricated folded-plate roof structure for daylighting, power generation, and smoke exhaust as claimed in claim 2 or 3, characterized in that, the keyholes of the reserved pins are funnel-shaped with a large top and a small bottom, and each of the reserved pins The keyhole is set on a peg fixed on the bottom steel beam or the prefabricated concrete structure, the upper horizontal structure and the lower horizontal structure pass through the reserved pin hole, the peg and The flexible grouting material forms a flexible connection with the bottom steel beam or prefabricated concrete structure of the roof of the building. 5.如权利要求1所述的预制折板式采光发电排烟的屋面结构,其特征在于,所述预制折板还包括:5. The prefabricated folded panel roof structure for daylighting, power generation and smoke exhaust as claimed in claim 1, characterized in that, the prefabricated folded panel further comprises: 预留甩筋,其设置在所述下部水平结构上,所述预留甩筋的外漏部分与所述下部水平结构的上表面垂直设置,所述预留甩筋内置部分与所述下部水平结构的上表面平行设置,所述预留甩筋用于排烟窗支撑部的现场浇筑;The reserved ribs are arranged on the lower horizontal structure, the leaking part of the reserved ribs is vertically arranged with the upper surface of the lower horizontal structure, and the built-in part of the reserved ribs is horizontal to the lower part The upper surface of the structure is arranged in parallel, and the reserved ribs are used for on-site pouring of the support part of the smoke exhaust window; 加强筋,其设置在所述下部水平结构内,且与所述下部水平结构的上表面平行设置,所述加强筋与所述预留甩筋内置部分固定连接;以及A reinforcing rib, which is arranged in the lower horizontal structure and arranged parallel to the upper surface of the lower horizontal structure, and the reinforcing rib is fixedly connected to the built-in part of the reserved rib; and 避位缺口,其设置在所述上部水平结构和所述下部水平结构上,所述避位缺口用于避让建筑物屋顶的钢柱。A shelter notch is arranged on the upper horizontal structure and the lower horizontal structure, and the shelter notch is used to avoid steel columns on the roof of the building. 6.如权利要求1所述的预制折板式采光发电排烟的屋面结构,其特征在于,所述防水兼保护层为新型复合材料,所述新型复合材料分为柔性材料和硬性材料。6. The prefabricated folded plate roof structure for daylighting, power generation and smoke exhaust as claimed in claim 1, characterized in that the waterproof and protective layer is a new type of composite material, and the new type of composite material is divided into flexible materials and hard materials. 7.如权利要求6所述的预制折板式采光发电排烟的屋面结构,其特征在于,所述柔性材料包括乳液Hff-1及粉料Hff-2,所述柔性材料的施工方法包括刮涂法、刷涂法或喷涂法,所述柔性材料的施工配比为乳液Hff-1:水:粉料Hff-2=1:2:3。7. The roof structure of prefabricated folded plate type daylighting, power generation and smoke exhaust as claimed in claim 6, wherein said flexible material comprises emulsion HW-1 and powder material HW-2, and the construction method of said flexible material comprises scraping coating method, brushing method or spraying method, the construction proportion of described flexible material is emulsion Hff-1: water: powder material Hff-2=1:2:3. 8.如权利要求6所述的预制折板式采光发电排烟的屋面结构,其特征在于,所述硬性材料包括粉料Hff-3,所述硬性材料的工方法包括刮涂法、刷涂法或喷涂法。8. the roof structure of prefabricated folded plate type daylighting, power generation and smoke exhaust as claimed in claim 6, is characterized in that, described hard material comprises powder material HW-3, and the working method of described hard material comprises scraping method, brushing method or spraying method. 9.如权利要求8所述的预制折板式采光发电排烟的屋面结构,其特征在于,所述硬性材料的施工配比包括以下比例:9. The prefabricated folded-plate roof structure for daylighting, power generation, and smoke exhaust as claimed in claim 8, wherein the construction ratio of the hard materials includes the following ratios: 所述刮涂法的施工配比为粉料Hff-3:水=1:0.35±0.05;The construction proportioning of described scraping method is powder material HW-3: water=1:0.35 ± 0.05; 所述刷涂法的施工配比为粉料Hff-3:水=1:0.4±0.05;以及The construction proportion of described brushing method is powder material HW-3: water=1:0.4±0.05; And 所述喷涂法的施工配比为粉料Hff-3:水=1:0.5±0.05。The construction proportion of described spraying method is powder material HW-3: water=1:0.5±0.05. 10.如权利要求1所述的预制折板式采光发电排烟的屋面结构,其特征在于,所述光伏发电板与所述防水兼保护层之间采用粘结连接。10. The prefabricated folded panel roof structure for daylighting, power generation and smoke exhaust according to claim 1, characterized in that the photovoltaic power generation panel and the waterproof and protective layer are connected by bonding.
CN202310618828.2A 2023-05-30 2023-05-30 Prefabricated folding roof structure for daylighting, power generation and smoke exhaust Pending CN116657812A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310618828.2A CN116657812A (en) 2023-05-30 2023-05-30 Prefabricated folding roof structure for daylighting, power generation and smoke exhaust

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310618828.2A CN116657812A (en) 2023-05-30 2023-05-30 Prefabricated folding roof structure for daylighting, power generation and smoke exhaust

Publications (1)

Publication Number Publication Date
CN116657812A true CN116657812A (en) 2023-08-29

Family

ID=87725485

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310618828.2A Pending CN116657812A (en) 2023-05-30 2023-05-30 Prefabricated folding roof structure for daylighting, power generation and smoke exhaust

Country Status (1)

Country Link
CN (1) CN116657812A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101787738A (en) * 2010-03-12 2010-07-28 南通建筑工程总承包有限公司 Stair connection joint device
CN206737293U (en) * 2017-04-12 2017-12-12 侯文红 A kind of prefabricated assembled stair attachment structure
CN111910816A (en) * 2020-07-09 2020-11-10 北京城建集团有限责任公司 Metal roof structure with smoke exhaust function and serging welding method
CN213978845U (en) * 2020-11-16 2021-08-17 南水北调中线干线工程建设管理局河北分局 Concrete lining board
CN215211805U (en) * 2021-01-25 2021-12-17 重庆鸡冠石建筑工程有限公司 Solar thermoelectric integrated roof
CN218952630U (en) * 2022-11-09 2023-05-02 青岛国信建设投资有限公司 Roofing cornice waterproof construction
CN220014166U (en) * 2023-05-30 2023-11-14 北京城建北方集团有限公司 Prefabricated folded plate type lighting and smoke discharging roof structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101787738A (en) * 2010-03-12 2010-07-28 南通建筑工程总承包有限公司 Stair connection joint device
CN206737293U (en) * 2017-04-12 2017-12-12 侯文红 A kind of prefabricated assembled stair attachment structure
CN111910816A (en) * 2020-07-09 2020-11-10 北京城建集团有限责任公司 Metal roof structure with smoke exhaust function and serging welding method
CN213978845U (en) * 2020-11-16 2021-08-17 南水北调中线干线工程建设管理局河北分局 Concrete lining board
CN215211805U (en) * 2021-01-25 2021-12-17 重庆鸡冠石建筑工程有限公司 Solar thermoelectric integrated roof
CN218952630U (en) * 2022-11-09 2023-05-02 青岛国信建设投资有限公司 Roofing cornice waterproof construction
CN220014166U (en) * 2023-05-30 2023-11-14 北京城建北方集团有限公司 Prefabricated folded plate type lighting and smoke discharging roof structure

Similar Documents

Publication Publication Date Title
WO2021253808A1 (en) Building technique for low-carbon society in high-technology era
CN201593248U (en) A composite insulation layer
CN106382023A (en) Archaistic building and manufacturing method thereof
CN101851994A (en) Inorganic sandwich composite external thermal insulation system
CN202787603U (en) Light-weight heat preservation house roof plate or floor plate
CN110821198A (en) High-rise building external wall thermal insulation mortar falling prevention method
CN111042362A (en) Gel non-combustible heat-insulation decorative plate external wall external heat-insulation system and construction method
CN203174810U (en) Bearing-and-leaning type installed assembly wall body
CN111042361A (en) Gel non-combustible heat insulation plate external wall external heat insulation system and construction method
CN105089290A (en) Method for repairing roof
CN110670827A (en) Heat-insulating waterproof construction method for building external wall
CN207484846U (en) A kind of modularization seaweed house roofing
CN207934332U (en) Assembled architecture with steel Special-Shaped Column
CN207017545U (en) Foam concrete heat-preserving roofing optimizes architectural construction and local structure
CN209145323U (en) Balcony is transformed in the low energy consumption of existing building
CN204112508U (en) A kind of in-situ concrete wall fire-retardant heat insulation structure
CN206189921U (en) Archaistic building
CN109797875A (en) A kind of low energy consumption energy saving building system
CN116657812A (en) Prefabricated folding roof structure for daylighting, power generation and smoke exhaust
CN210342386U (en) Steel construction heat preservation waterproof roofing
CN107476592A (en) A kind of construction material for installing high-strength durable fiber cloth or/and plastic sheeting
CN108018986B (en) Structure and energy-saving integrated semi-fabricated prefabricated external wall panel and construction method thereof
CN111254937A (en) Installation method of fabricated building
CN111287311A (en) Construction method of cold-formed thin-wall light steel structure building
CN206681418U (en) The industrialization commercial residential buildings of energy-conserving and environment-protective

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination