CN116607548A - Side slope supporting structure and side slope supporting method - Google Patents

Side slope supporting structure and side slope supporting method Download PDF

Info

Publication number
CN116607548A
CN116607548A CN202310802446.5A CN202310802446A CN116607548A CN 116607548 A CN116607548 A CN 116607548A CN 202310802446 A CN202310802446 A CN 202310802446A CN 116607548 A CN116607548 A CN 116607548A
Authority
CN
China
Prior art keywords
slope
cast
foot
foundation pit
toe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310802446.5A
Other languages
Chinese (zh)
Inventor
温忠义
刘伟
彭卫平
刘志方
肖淑君
陈倩岚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Urban Planning Survey and Design Institute
Original Assignee
Guangzhou Urban Planning Survey and Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Urban Planning Survey and Design Institute filed Critical Guangzhou Urban Planning Survey and Design Institute
Priority to CN202310802446.5A priority Critical patent/CN116607548A/en
Publication of CN116607548A publication Critical patent/CN116607548A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

本申请公开了一种边坡支护结构及边坡支护方法,应用于需要在边坡坡脚开挖基坑的工程,包括:灌注桩组件,包括坡脚灌注桩和基坑灌注桩,坡脚灌注桩的上半部分贴附坡脚设置,下半部分插入地下;基坑灌注桩插入地下,且贴附基坑靠近坡脚一侧的侧壁设置;坡脚灌注桩和基坑灌注桩间隔设置从而形成坡脚平台;锚固组件,包括多个坡脚锚固件和多个基坑锚固件,多个坡脚锚固件设置于坡脚灌注桩远离基坑灌注桩一侧,且倾斜插入边坡,多个基坑锚固件设置于基坑灌注桩和坡脚灌注桩之间,并且倾斜插入坡脚平台下方。如此,本申请解决了边坡结合基坑的工程中,因为二者相互影响导致的容易滑坡的问题。

The application discloses a side slope support structure and a side slope support method, which are applied to projects that need to excavate foundation pits at the slope foot of the slope, including: cast-in-place pile components, including cast-in-place piles at the foot of the slope and cast-in-place piles in the foundation pit, The upper part of the cast-in-place pile at the foot of the slope is attached to the foot of the slope, and the lower part is inserted into the ground; the cast-in-situ pile of the foundation pit is inserted into the ground, and is attached to the side wall of the foundation pit near the foot of the slope; the cast-in-situ pile at the foot of the slope and the pouring of the foundation pit The piles are arranged at intervals to form the toe platform; the anchor components include multiple toe anchors and multiple foundation pit anchors, and the multiple toe anchors are arranged on the side of the toe pouring pile away from the foundation pit pouring pile, and inserted oblique For a side slope, a plurality of foundation pit anchors are arranged between the cast-in-place piles of the foundation pit and the cast-in-place piles at the foot of the slope, and are obliquely inserted under the platform of the foot of the slope. In this way, the present application solves the problem of easy landslides caused by the interaction between the slope and the foundation pit.

Description

一种边坡支护结构及边坡支护方法A slope support structure and a slope support method

技术领域technical field

本发明涉及建筑技术领域,特别是涉及一种边坡支护结构及边坡支护方法。The invention relates to the technical field of buildings, in particular to a slope support structure and a slope support method.

背景技术Background technique

在施工过程中,永久边坡与坡脚临时基坑相结合的工程案例越来越多,一般上部为永久边坡,底部为临时基坑。深厚填土的高陡边坡,一般采用放坡、抗滑桩、格构梁结合锚杆(锚索)等多种支护方案。而对于临时基坑,一般采用支护桩加锚索或内支撑等支护方法。由于规划和建筑方案的影响,山体永久边坡坡脚的临时基坑往往开挖较大,且基坑边线距离坡脚线较近,边坡与基坑两者相互制约。若设计和施工时单独考虑顶部永久边坡或者底部临时基坑的设计,而不考虑二者的相互影响,容易导致基坑或边坡失稳的现象发生。具体的,在许多项目中,开挖坡脚临时基坑这一步骤是在永久边坡施工完成后发生的,由于基坑支护结构较弱或永久边坡支护方案缺陷,导致坡脚基坑失稳,进而引起已施工边坡发生滑坡,形成牵引式浅层滑坡或推移式深层滑坡。总而言之,现有的永久边坡与坡脚临时基坑相结合的工程存在容易滑坡的问题。During the construction process, there are more and more engineering cases combining permanent slope and temporary foundation pit at the foot of the slope. Generally, the upper part is a permanent slope and the bottom is a temporary foundation pit. For high and steep slopes with deep and thick fill, various support schemes such as grading, anti-slide piles, lattice beams combined with anchor rods (cables) are generally adopted. For temporary foundation pits, support methods such as support piles plus anchor cables or internal supports are generally used. Due to the influence of planning and construction schemes, the temporary foundation pits at the foot of the permanent slope of the mountain are often excavated relatively large, and the sideline of the foundation pit is relatively close to the footline of the slope, and the slope and the foundation pit are mutually restricted. If the design and construction of the permanent slope at the top or the temporary foundation pit at the bottom are considered separately, without considering the mutual influence of the two, it is easy to cause the foundation pit or slope to become unstable. Specifically, in many projects, the step of excavating the temporary foundation pit at the foot of the slope occurs after the construction of the permanent slope is completed. Due to the weak support structure of the foundation pit or the defect of the permanent slope support plan, the The instability of the pit will cause landslides on the constructed side slopes, forming traction-type shallow landslides or pushing-type deep landslides. All in all, the existing permanent slope combined with the temporary foundation pit at the foot of the slope is prone to landslides.

发明内容Contents of the invention

本发明提出一种边坡支护结构及边坡支护方法,旨在解决现有的边坡与基坑相结合的工程存在的容易滑坡的问题。The invention proposes a side slope support structure and a side slope support method, aiming at solving the problem of easy landslide existing in the existing engineering combining side slope and foundation pit.

为解决上述问题,本申请提出一种边坡支护结构,应用于需要在边坡坡脚开挖基坑的工程,包括灌注桩组件,包括坡脚灌注桩和基坑灌注桩,所述坡脚灌注桩的上半部分贴附所述坡脚设置,下半部分插入地下;所述基坑灌注桩插入地下,且贴附所述基坑靠近所述坡脚一侧的侧壁设置;所述坡脚灌注桩和所述基坑灌注桩间隔设置从而形成坡脚平台;锚固组件,包括多个坡脚锚固件和多个基坑锚固件,多个所述坡脚锚固件设置于所述坡脚灌注桩靠近所述边坡的一侧,且倾斜插入所述边坡,多个所述基坑锚固件设置于所述基坑灌注桩和所述坡脚灌注桩之间,并且倾斜插入所述坡脚平台下方。In order to solve the above problems, this application proposes a slope support structure, which is applied to the project that needs to excavate a foundation pit at the foot of the slope, including cast-in-place pile components, including cast-in-place piles at the foot of the slope and cast-in-situ piles in the foundation pit, the slope The upper part of the cast-in-place pile is attached to the foot of the slope, and the lower part is inserted into the ground; the cast-in-place pile of the foundation pit is inserted into the ground, and is attached to the side wall of the foundation pit near the foot of the slope; The cast-in-place piles at the foot of the slope and the cast-in-situ piles of the foundation pit are arranged at intervals to form a toe platform; the anchor assembly includes a plurality of toe anchors and a plurality of foundation pit anchors, and a plurality of the toe anchors are arranged on the toe The cast-in-place pile at the foot of the slope is close to the side of the slope, and is inserted obliquely into the slope, and a plurality of foundation pit anchors are arranged between the cast-in-place pile at the foundation pit and the cast-in-place pile at the foot of the slope, and are inserted obliquely Below the toe platform.

在一实施例中,所述边坡由坡顶至坡脚向下倾斜设置,所述灌注桩组件还包括至少一个坡中灌注桩,所述锚固组件还包括多个坡中锚固件,所述坡中灌注桩设置于所述边坡的坡顶和坡脚之间,所述坡脚锚固件设置于所述坡脚灌注桩和所述坡中灌注桩之间,所述坡中锚固件设置于所述坡中灌注桩靠近坡顶的一侧,且倾斜插入所述边坡。In one embodiment, the slope is arranged downwardly from the top of the slope to the foot of the slope, the cast-in-place pile assembly further includes at least one cast-in-place pile in the slope, and the anchor assembly also includes a plurality of anchor pieces in the slope, the The cast-in-place pile in the slope is arranged between the top and the foot of the slope, the anchor at the foot of the slope is arranged between the cast-in-place pile at the foot of the slope and the cast-in-place pile in the slope, and the anchor in the slope is arranged In the slope, the cast-in-place pile is close to the side of the top of the slope, and inserted obliquely into the side slope.

在一实施例中,所述边坡支护结构还包括多个注浆管,所述注浆管用于插入边坡内并注浆从而加固土体,所述坡中灌注桩、所述坡脚灌注桩靠近坡顶的一侧均设置有所述注浆管。In one embodiment, the slope support structure further includes a plurality of grouting pipes, the grouting pipes are used to insert into the slope and grout to reinforce the soil, the cast-in-place piles in the slope, the slope toe The grouting pipes are provided on the side of the cast-in-situ pile near the top of the slope.

在一实施例中,所述基坑锚固件和所述坡脚灌注桩之间存在间隙。In one embodiment, there is a gap between the foundation pit anchor and the cast-in-situ pile at the slope toe.

在一实施例中,所述基坑灌注桩和所述坡脚灌注桩之间的间距为a,其中15m≤a≤30m。In one embodiment, the distance between the cast-in-place piles in the foundation pit and the cast-in-place piles at the foot of the slope is a, where 15m≤a≤30m.

在一实施例中,所述坡脚平台为硬化结构。In one embodiment, the toe platform is a hardened structure.

在一实施例中,所述边坡支护结构还包括坡顶排水沟、坡脚排水沟,所述坡顶排水沟设置于所述边坡的坡顶,所述坡脚排水沟设置于所述坡脚平台,所述坡顶排水沟、坡脚排水沟接入外界排水系统。In one embodiment, the slope support structure further includes a slope top drainage ditch and a slope foot drainage ditch, the slope top drainage ditch is arranged at the slope top of the slope, and the slope foot drainage ditch is arranged at the slope top The platform at the foot of the slope is described, and the drainage ditch at the top of the slope and the drainage ditch at the foot of the slope are connected to the external drainage system.

在一实施例中,所述边坡的破面上还设置有至少一个马道平台,所述马道平台远离所述坡脚的一侧设置有硬化段,所述马道平台靠近所述坡脚的一侧连接有挡水板,所述硬化段、所述马道平台、所述挡水板共同围合形成坡中排水沟,所述坡中排水沟接入外界排水系统。In one embodiment, at least one horse path platform is further provided on the broken surface of the slope, a hardened section is provided on the side of the horse path platform away from the slope toe, and a side of the horse path platform close to the slope toe The side is connected with a water retaining plate, and the hardened section, the horseway platform, and the water retaining plate are jointly enclosed to form a drainage ditch in the slope, and the drainage ditch in the slope is connected to the external drainage system.

本申请还提出一种边坡支护方法,应用了上文所述的边坡支护结构,包括如下步骤:The application also proposes a slope support method, which uses the above-mentioned slope support structure, including the following steps:

S1,由坡顶至坡脚逐层开挖边坡,在开挖每层土体的过程中,完成每层土体中的锚固组件或者灌注桩组件的安装之后,再开挖下一层土体。S1, Excavate the side slope layer by layer from the top of the slope to the foot of the slope. In the process of excavating each layer of soil, after completing the installation of anchor components or cast-in-situ pile components in each layer of soil, excavate the next layer of soil body.

在一实施例中,所述边坡支护方法还包括如下步骤:In one embodiment, the slope support method also includes the following steps:

S2,在所述坡脚灌注桩施工完成后,对所述边坡进行检验,检验边坡的稳定性合格后,再硬化坡脚平台,进行坡脚锚固件和坡脚灌注桩的施工。S2, after the construction of the cast-in-situ piles at the foot of the slope is completed, the slope is inspected, and after the stability of the slope is qualified, the platform at the foot of the slope is hardened, and the anchors at the foot of the slope and the cast-in-situ piles at the foot of the slope are constructed.

如此,本申请提出了一种边坡支护结构及边坡支护方法,具体的,所述边坡支护结构包括坡脚灌注桩、基坑灌注桩、坡脚锚固件、基坑锚固件,其中,坡脚灌注桩和坡脚锚固件加固了坡脚,基坑灌注桩加固了基坑靠近坡脚的一侧,且坡脚灌注桩、基坑灌注桩间隔设置,二者之间形成有坡脚平台,坡脚平台下方为基坑锚固件提供了安装空间,进一步提高了靠近坡脚处的基坑的稳定性,从而解决了边坡结合基坑的工程中容易滑坡的问题。In this way, the present application proposes a slope support structure and a slope support method. Specifically, the slope support structure includes cast-in-place piles at the foot of the slope, cast-in-place piles for the foundation pit, anchors at the foot of the slope, and anchors for the foundation pit , wherein, the cast-in-place piles at the toe of the slope and the anchors at the toe of the slope reinforce the toe of the slope, and the cast-in-place piles at the foundation pit reinforce the side of the foundation pit near the toe of the slope, and the cast-in-place piles at the toe of the slope and the cast-in-place piles of the foundation pit are arranged at intervals, forming a There is a platform at the foot of the slope, and the installation space for the foundation pit anchor is provided under the platform of the foot of the slope, which further improves the stability of the foundation pit near the foot of the slope, thereby solving the problem of easy landslides in the engineering of the slope combined with the foundation pit.

附图说明Description of drawings

图1是本发明实施例边坡支护结构的结构示意图;Fig. 1 is the structural representation of the slope support structure of the embodiment of the present invention;

图2是本发明实施例的边坡开挖前的原始坡面的结构示意图。Fig. 2 is a structural schematic diagram of the original slope before excavation of the slope according to the embodiment of the present invention.

具体实施方式Detailed ways

下面接合附图和实施例,对本发明的具体实施方式作进一步详细描述。以下实施例用于说明本发明,但不用来限制本发明的范围。The specific implementation manner of the present invention will be described in further detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

在本发明的描述中,应当理解的是,“前”、“后”、“上”、“下”、“左”、“右”、“纵”、“横”、“竖直”、“水平”、“顶”、“底”、“内”、“外”、“头”、“尾”等指示的方位或位置关系为基于附图所示的方位或位置关系、以特定的方位构造和操作,仅是为了便于描述本技术方案,而不是指示所指的装置或元件必须具有特定的方位,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that "front", "rear", "upper", "lower", "left", "right", "longitudinal", "horizontal", "vertical", " The orientation or positional relationship indicated by "horizontal", "top", "bottom", "inner", "outer", "head", "tail", etc. is based on the orientation or positional relationship shown in the drawings and constructed in a specific orientation and operation are only for the convenience of describing the technical solution, but do not indicate that the device or element referred to must have a specific orientation, so it should not be construed as a limitation of the present invention.

在本发明中,除非另有明确的规定和限定,术语“吊装”、“绑扎”、“固定”等术语应做广义理解,例如,可以是绑扎连接,也可以是固定连接,或成一体;可以是机械连接,也可以是电焊连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。In the present invention, unless otherwise clearly specified and limited, terms such as "hoisting", "binding", and "fixing" should be interpreted in a broad sense, for example, it can be a binding connection, a fixed connection, or an integral body; It can be a mechanical connection or an electric welding connection; it can be a direct connection or an indirect connection through an intermediary, and it can be the internal communication of two components or the interaction relationship between two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention according to specific situations.

随着城市发展,永久边坡与坡脚临时基坑相结合的工程案例越来越多,一般上部为永久边坡,底部为临时基坑。工程上永久高陡边坡一般采用放坡、抗滑桩、格构梁+锚杆(锚索)等多种支护方案,临时基坑一般采用支护桩+锚索后内支撑等支护方法。由于规划和建筑方案的影响,山体永久边坡坡脚的临时基坑往往开挖较大,且基坑边线距离坡脚线较近,边坡与基坑两者相互制约。若设计和施工时单独考虑顶部永久边坡和底部临时基坑,则往往引起基坑或边坡而发生失稳,许多项目施工永久边坡结合临时基坑的工程时,由于基坑支护结构较弱或永久边坡支护方案缺陷,导致坡脚基坑失稳,进而引起已施工边坡发生滑坡,形成牵引式浅层滑坡或推移式深层滑坡。With the development of the city, there are more and more engineering cases combining permanent slopes and temporary foundation pits at the foot of the slope. Generally, the upper part is a permanent slope and the bottom is a temporary foundation pit. For permanent high and steep slopes in engineering, various support schemes such as grading, anti-slide piles, lattice beams + anchor rods (cables) are generally used, and temporary foundation pits are generally supported by support piles + anchor cables and rear internal supports. method. Due to the influence of planning and construction schemes, the temporary foundation pits at the foot of the permanent slope of the mountain are often excavated relatively large, and the sideline of the foundation pit is relatively close to the footline of the slope, and the slope and the foundation pit are mutually restricted. If the permanent slope at the top and the temporary foundation pit at the bottom are considered separately during design and construction, it will often cause instability of the foundation pit or slope. Weak or defective permanent slope support schemes lead to the instability of the foundation pit at the foot of the slope, which in turn causes landslides on the constructed slope, forming traction-type shallow landslides or pushing-type deep landslides.

对于场地条件复杂,存在深厚填土或软弱土层的高陡边坡与临时基坑相结合的工程实践较少,特别是永久边坡坡脚的临时基坑靠山顶侧开挖深度比靠近坡脚侧的深,基坑无法采用内支撑形成对称支护体系,故永久边坡需考虑基坑开挖的影响,同时基坑开挖也需考虑边坡的影响。For complex site conditions, high and steep slopes with deep fill or weak soil layers, there are few engineering practices for combining temporary foundation pits. The foot side is deep, and the foundation pit cannot use internal support to form a symmetrical support system. Therefore, the influence of the excavation of the foundation pit must be considered for the permanent slope, and the influence of the slope must also be considered for the excavation of the foundation pit.

因此,在深厚填土高陡边坡和基坑相结合工程项目中,特别是在基坑开挖至坑底未及时回填法人最不利工况下,为确保两者支护结构均安全,迫切需求一种永临结合的支护方法。Therefore, it is urgent to ensure the safety of both supporting structures in deep fill, high steep slope and foundation pit projects, especially when the foundation pit is excavated to the bottom of the pit and is not backfilled in time, which is the most unfavorable working condition. There is a need for a permanent combined support method.

请参阅图1,为解决上述问题,本申请提出一种边坡支护结构,应用于需要在边坡坡脚开挖基坑的工程,包括灌注桩组件10,包括坡脚灌注桩12和基坑灌注桩11,所述坡脚灌注桩12的上半部分贴附所述坡脚设置,下半部分插入地下;所述基坑灌注桩11插入地下,且贴附所述基坑靠近所述坡脚一侧的侧壁设置;所述坡脚灌注桩12和所述基坑灌注桩11间隔设置从而形成坡脚平台300;锚固组件20,包括多个坡脚锚固件22和多个基坑锚固件21,多个所述坡脚锚固件22设置于所述坡脚灌注桩12靠近所述边坡的一侧,即多个所述坡脚锚固件22设置于所述坡脚灌注桩12远离所述基坑灌注桩11一侧,且倾斜插入所述边坡,多个所述基坑锚固件21设置于所述基坑灌注桩11和所述坡脚灌注桩12之间,并且倾斜插入所述坡脚平台300下方。Please refer to Fig. 1, in order to solve the above-mentioned problems, this application proposes a kind of side slope support structure, is applied to the engineering that needs to excavate foundation pit at the foot of slope slope, comprises cast-in-place pile assembly 10, comprises cast-in-place pile 12 and foundation Pit cast-in-place pile 11, the upper half of the slope toe cast-in-place pile 12 is attached to the slope toe, and the lower half is inserted into the ground; the foundation pit cast-in-place pile 11 is inserted into the ground, and attached to the foundation pit close to the The side wall on one side of the slope toe is set; the toe cast-in-situ piles 12 and the foundation pit poured piles 11 are arranged at intervals to form a slope toe platform 300; the anchor assembly 20 includes a plurality of slope toe anchors 22 and a plurality of foundation pits Anchor 21, a plurality of toe anchors 22 are arranged on the side of the toe cast-in-place pile 12 close to the slope, that is, a plurality of toe anchors 22 are arranged on the toe cast-in-place pile 12 A side away from the cast-in-place pile 11 of the foundation pit, and inserted into the slope obliquely, a plurality of anchors 21 of the foundation pit are arranged between the cast-in-place pile 11 and the cast-in-place pile 12 at the foot of the slope, and are inclined Inserted below the toe platform 300 .

具体的,在边坡支护的过程中,灌注桩常常被用来加固边坡,抵抗土方侧压力,防止土方位移。本申请所提出的边坡支护结构,设置了位于坡脚的坡脚灌注桩12,以及设置了位于基坑靠近坡脚一侧的基坑灌注桩11。用于分别加固坡脚和基坑二者相互靠近的部分,从而减小边坡和基坑二者之间的影响。与此同时,本申请还在坡脚和基坑之间设置一坡脚平台300,坡脚平台300的设置在满足设计要求的前提下,在坡脚和基坑之间设置一定缓冲,进一步避免了二者的相互制约。Specifically, in the process of slope support, cast-in-situ piles are often used to reinforce the slope, resist the lateral pressure of the earth, and prevent the displacement of the earth. The slope support structure proposed in this application is provided with cast-in-place piles 12 at the toe of the slope, and with cast-in-place piles 11 at the side of the foundation pit near the toe of the slope. It is used to respectively reinforce the parts where the slope toe and the foundation pit are close to each other, so as to reduce the influence between the slope and the foundation pit. At the same time, this application also sets a toe platform 300 between the toe of the slope and the foundation pit. The setting of the toe platform 300 meets the design requirements, and a certain buffer is set between the toe of the slope and the foundation pit to further avoid mutual restriction of the two.

为了进一步加固土体,边坡支护结构还常设置有各种锚固件,如锚杆、锚索等。锚杆、锚索是岩土体加固的杆件体系结构。通过锚杆锚固体在岩土体内的锚固作用,克服岩土体抗拉能力远远低于抗压能力的缺点,确保锚杆能充分发挥抗拉强度。其实质上锚杆位于岩土体内的锚杆锚固体与岩土体形成一个新的复合体。这个复合体的可靠性是解决围岩体的抗拉能力低的关键。从而使得岩土体自身的承载能力大大加强。在一实施例中,锚杆一般采用直径25~32钢筋,间距2.0m,长9~15m,成孔直径130mm,锚索采用4束1x7 s/15.2钢绞线,间距2.0m,长24~36m,成孔直径180mm,打入角度20度。在另一实施例中。施工坡脚灌注桩12后,在坡脚灌注桩12处还另行设置一灌注桩锚索,该锚索为永久结构,用于稳固坡脚灌注桩12。可选的,此处的永久锚索采用6束1x7 s15.2钢绞线,间距2.0m,长36~42m,成孔直径180mm,应进入,且进入全强风化花岩不少于14m。In order to further strengthen the soil, the slope support structure is often equipped with various anchors, such as anchor rods, anchor cables, etc. Anchor rod and anchor cable are the rod system structure of rock and soil reinforcement. Through the anchoring effect of the bolt and anchor body in the rock and soil body, it overcomes the shortcoming that the tensile capacity of the rock and soil body is far lower than the compressive capacity, and ensures that the anchor rod can fully exert its tensile strength. In fact, the anchor rod and the rock-soil body form a new complex with the anchor rod located in the rock-soil body. The reliability of this complex is the key to solving the low tensile capacity of the surrounding rock mass. As a result, the bearing capacity of the rock and soil itself is greatly enhanced. In one embodiment, the anchor rod generally adopts steel bars with a diameter of 25-32mm, a distance of 2.0m, a length of 9-15m, and a hole diameter of 130mm. 36m, the hole diameter is 180mm, and the penetration angle is 20 degrees. In another embodiment. After constructing the cast-in-situ pile 12 at the foot of the slope, an anchor cable of the cast-in-situ pile is also set at the foot of the slope pile 12, and the anchor cable is a permanent structure for stabilizing the cast-in-situ pile 12 at the foot of the slope. Optionally, the permanent anchor cables here use 6 bundles of 1x7 s15.2 steel strands with a spacing of 2.0m, a length of 36-42m, and a hole diameter of 180mm, which should enter the fully weathered rock for no less than 14m.

请参阅图1,在一实施例中,所述边坡由坡顶至坡脚向下倾斜设置,所述灌注桩组件10还包括至少一个坡中灌注桩13,所述锚固组件20还包括多个坡中锚固件23,所述坡中灌注桩13设置于所述边坡的坡顶和坡脚之间,所述坡脚锚固件22设置于所述坡脚灌注桩12和所述坡中灌注桩13之间,所述坡中锚固件23设置于所述坡中灌注桩13靠近坡顶的一侧,且倾斜插入所述边坡。Please refer to Fig. 1, in one embodiment, the slope is set downwards from the top of the slope to the foot of the slope, the cast-in-situ pile assembly 10 also includes at least one cast-in-place pile 13 in the slope, and the anchor assembly 20 also includes multiple An anchor 23 in the slope, the cast-in-place pile 13 in the slope is arranged between the slope crest and the foot of the slope, and the anchor 22 of the slope foot is arranged in the cast-in-place pile 12 and the slope at the foot of the slope Between the cast-in-place piles 13, the in-slope anchors 23 are arranged on the side of the in-slope cast-in-place piles 13 close to the top of the slope, and are obliquely inserted into the side slope.

根据边坡的规模,所述坡中灌注桩13可以设置一排或者设置多排。在一实施例中,多个所述坡中灌注桩13由坡顶至坡脚间隔设置。而坡中锚固件23所采用的锚杆、锚索的规格、型号和坡脚锚固件22相似。而在施工过程中,坡中锚固件23、坡脚锚固件22在分层开挖土体的过程中分层间隔打入,并且在达到设计强度要求后张拉锁定。可选的,坡中灌注桩13、坡脚灌注桩12均采用大直径灌注桩。其灌注桩孔成孔采用旋挖成孔、冲击成孔、长螺旋成孔或全套筒全回转钻机成孔施工工艺。可选的,直径为1500mm,间距为2.0m,桩底应穿过填土与原状土之间的滑移带并进入全强风化岩不少于5m。According to the scale of the slope, one or more rows of cast-in-place piles 13 can be arranged in the slope. In one embodiment, a plurality of cast-in-place piles 13 are arranged at intervals from the top of the slope to the foot of the slope. And the specification, model of the anchor rod that the anchor 23 adopts in the slope, the anchor cable are similar to the anchor 22 at the foot of the slope. In the construction process, the mid-slope anchors 23 and the slope toe anchors 22 are driven in layers and at intervals in the process of excavating the soil layer by layer, and are stretched and locked after reaching the design strength requirements. Optionally, the cast-in-situ piles 13 in the slope and the cast-in-place piles 12 at the foot of the slope are all made of large-diameter cast-in-situ piles. The hole forming of the cast-in-place pile adopts the construction technology of rotary digging, impact hole, long spiral hole or full-sleeve full-rotary drilling rig. Optionally, with a diameter of 1500mm and a spacing of 2.0m, the bottom of the pile should pass through the slip zone between the fill and the undisturbed soil and enter the fully weathered rock for no less than 5m.

在一实施例中,所述边坡支护结构还包括多个注浆管,所述注浆管用于插入边坡内并注浆从而加固土体,所述坡中灌注桩13、所述坡脚灌注桩12靠近坡顶的一侧均设置有所述注浆管。In one embodiment, the slope support structure further includes a plurality of grouting pipes, which are used for inserting into the slope and injecting grout to reinforce the soil, the cast-in-place piles 13 in the slope, the The grouting pipes are provided on one side of the foot cast-in-place pile 12 near the top of the slope.

可选的,所述注浆管采用袖阀管。袖阀注浆管是一种用于岩土工程地基加固、压实、充填和防渗等工程的注浆管。它由膨胀软管、固定接头、注浆芯管和注水管组成。值得注意的是,在施工坡中灌注桩13和坡脚灌注桩12之前,需在已开挖边坡侧紧贴灌注桩设置4排袖阀管注浆,防治应施工大直径灌注桩引起已施工边坡和坡顶重要构建筑物的安全。Optionally, the grouting pipe adopts a sleeve valve pipe. Sleeve valve grouting pipe is a kind of grouting pipe used in geotechnical engineering foundation reinforcement, compaction, filling and anti-seepage and other projects. It consists of expansion hose, fixed joint, grouting core pipe and water injection pipe. It is worth noting that, before constructing the cast-in-place piles 13 in the slope and the cast-in-place piles 12 at the foot of the slope, it is necessary to install 4 rows of sleeve valve tubes for grouting on the side of the excavated slope close to the cast-in-place piles, so as to prevent the large-diameter cast-in-place piles from causing severe damage. The construction side slope and the top of the slope are important to ensure the safety of the building.

在另一实施例中,袖阀管的注浆孔采用岩芯钻机成孔,开孔孔径76mm,采用钢套管护孔至基岩面或黏性土一定深度(约200mm),如难以钻孔成孔,应采用双层或多层钢套管护孔。而且袖阀管注浆孔成孔后,采用套壳料封孔(套壳料可采用膨润土和水泥掺合制作,固结强度不大于0.5MPa,应根据现场试验做好配料),灌注42.5R普通硅酸盐水泥浆,水灰比0.5~1.0,注浆压力1.2~1.5MPa,注浆量500kg/m,出浆孔设置在地表以下1m至孔底。In another embodiment, the grouting hole of the sleeve valve pipe is drilled with a core drilling machine, the hole diameter is 76mm, and the steel casing is used to protect the hole to a certain depth (about 200mm) on the bedrock surface or cohesive soil. If it is difficult to drill Holes formed into holes shall be protected by double-layer or multi-layer steel casings. Moreover, after the grouting hole of the sleeve valve pipe is formed, the hole is sealed with casing material (the casing material can be made by mixing bentonite and cement, and the consolidation strength is not greater than 0.5MPa, and the ingredients should be prepared according to the field test), pouring 42.5R For ordinary Portland cement slurry, the water-cement ratio is 0.5-1.0, the grouting pressure is 1.2-1.5MPa, the grouting volume is 500kg/m, and the grouting hole is set 1m below the surface to the bottom of the hole.

请参阅图1,在一实施例中,所述基坑锚固件21和所述坡脚灌注桩12之间存在间隙。具体的,称由坡顶至坡脚的水平方向为长度方向,由坡脚向下的方向为高度方向,沿边坡的截面延伸的方向为宽度方向。其中,宽度方向与高度方向、长度方向均垂直设置。在同一高度,所述基坑灌注桩11、所述坡脚灌注桩12、所述坡中灌注桩13均沿着宽度方向设置有多个。可选的,相邻两坡脚灌注桩12之间还设置有泄水孔,用于排出边坡内的积水。Please refer to FIG. 1 , in one embodiment, there is a gap between the foundation pit anchor 21 and the cast-in-place pile 12 at the slope foot. Specifically, the horizontal direction from the top of the slope to the foot of the slope is called the length direction, the direction downward from the foot of the slope is called the height direction, and the direction extending along the section of the slope is called the width direction. Wherein, the width direction, the height direction, and the length direction are all set vertically. At the same height, there are multiple cast-in-place piles 11 in the foundation pit, cast-in-place piles 12 at the foot of the slope, and cast-in-place piles 13 in the slope along the width direction. Optionally, a drain hole is also provided between two adjacent cast-in-place piles 12 at the foot of the slope, for draining accumulated water in the slope.

而基坑锚固件21是倾斜插入坡脚平台300的,为了避免基坑锚固件21的设置对坡脚灌注桩12造成干扰,而影响其稳定性,所述基坑锚固件21和坡脚灌注桩12之间应存在间隙。在一实施例中,可通过控制基坑锚固件21的位置,使得基坑锚固件21从相邻两坡脚灌注桩12之间穿过以实现这一效果。但是,由于施工过程中存在误差,常采用另一避免干扰的方式。即控制坡脚平台300的长度,以及基坑锚固件21的位置、规格型号。使得基坑锚固件21插入坡脚平台300内的末端和坡脚灌注桩12之间在长度方向上仍然存在一定间隙。The foundation pit anchor 21 is obliquely inserted into the toe platform 300. In order to avoid the setting of the foundation pit anchor 21 from interfering with the toe pouring pile 12 and affecting its stability, the foundation pit anchor 21 and the toe pouring There should be a gap between the piles 12 . In one embodiment, this effect can be achieved by controlling the position of the foundation pit anchors 21 so that the foundation pit anchors 21 pass between two adjacent cast-in-place piles 12 at the foot of the slope. However, due to errors in the construction process, another way to avoid interference is often used. That is to control the length of the toe platform 300 , and the position, specification and model of the foundation pit anchor 21 . There is still a certain gap in the length direction between the end of the foundation pit anchor 21 inserted into the toe platform 300 and the toe cast-in-place pile 12 .

请参阅图1,在一实施例中,所述基坑灌注桩11和所述坡脚灌注桩12之间的间距为a,其中15m≤a≤30m。所述基坑灌注桩11和所述坡脚灌注桩12之间的间距即为所述坡脚平台300的长度。由于坡脚平台300的长度受实际施工环境所限制,长度过长,可能会占用过多施工空间。长度过短,则基坑锚固件21的施工可能会对坡脚锚固桩产生干扰,进而影响边坡的稳定性。在一实施例中,所述基坑灌注桩11和所述坡脚灌注桩12之间的间距为20m。Please refer to Fig. 1 , in one embodiment, the distance between the cast-in-place piles 11 for the foundation pit and the cast-in-place piles 12 for the slope foot is a, where 15m≤a≤30m. The distance between the cast-in-place pile 11 of the foundation pit and the cast-in-place pile 12 at the toe is the length of the toe platform 300 . Since the length of the toe platform 300 is limited by the actual construction environment, if the length is too long, it may occupy too much construction space. If the length is too short, the construction of the foundation pit anchor 21 may interfere with the anchor pile at the foot of the slope, thereby affecting the stability of the slope. In one embodiment, the distance between the cast-in-place pile 11 for the foundation pit and the cast-in-place pile 12 at the foot of the slope is 20m.

请参阅图1,在一实施例中,所述坡脚平台300为硬化结构。如此,为后续基坑的施工流程提供了一个硬化的施工平台,工作人员不需要在泥浆地上施工,进而提高了施工效率。Please refer to FIG. 1 , in one embodiment, the toe platform 300 is a hardened structure. In this way, a hardened construction platform is provided for the subsequent construction process of the foundation pit, and the staff does not need to construct on the mud ground, thereby improving the construction efficiency.

请参阅图1,在一实施例中,所述边坡支护结构还包括坡顶排水沟33、坡脚排水沟31,所述坡顶排水沟33设置于所述边坡的坡顶,所述坡脚排水沟31设置于所述坡脚平台300,所述坡顶排水沟33、坡脚排水沟31接入外界排水系统。坡顶排水沟33起到边坡和基坑施工过程中的截水作用,同时在施工完成后保留,成为永久边坡排水系统中一部分。Please refer to Fig. 1 , in one embodiment, the slope support structure also includes a slope top drainage ditch 33 and a slope foot drainage ditch 31, and the slope top drainage ditch 33 is arranged on the slope top of the slope, so The toe drainage ditch 31 is arranged on the toe platform 300, and the top drainage ditch 33 and the toe drainage ditch 31 are connected to the external drainage system. The drainage ditch 33 at the top of the slope plays the role of intercepting water during the construction of the slope and the foundation pit, and it is retained after the construction is completed to become a part of the permanent slope drainage system.

请参阅图1,在一实施例中,所述边坡的破面上还设置有至少一个马道平台,所述马道平台靠近所述坡顶的一侧设置有硬化段,所述马道平台靠近所述坡脚的一侧连接有挡水板,所述硬化段、所述马道平台、所述挡水板共同围合形成坡中排水沟32,所述坡中排水沟32接入外界排水系统。在一实施例中,马道平台宽度在1500mm至3000mm之间,厚度在100mm至200mm之间,硬化段宽度在0.5m至2m之间,挡水板宽度在100mm至200mm之间,高度在1至1.5米范围内,随着马道平台一起浇筑。可选的,马道平台宽度2000mm,厚150mm,硬化段的宽度为1m,挡水板宽度150mm,高度1.2m,与马道平台一起浇筑。Please refer to Fig. 1, in one embodiment, at least one horse track platform is also provided on the broken surface of the slope, the side of the horse track platform near the top of the slope is provided with a hardened section, and the horse track platform is close to the One side of the foot of the slope is connected with a water retaining plate, and the hardened section, the horseway platform, and the water retaining plate together form a mid-slope drainage ditch 32, and the mid-slope drainage ditch 32 is connected to an external drainage system. In one embodiment, the width of the horseway platform is between 1500mm and 3000mm, the thickness is between 100mm and 200mm, the width of the hardened section is between 0.5m and 2m, the width of the water barrier is between 100mm and 200mm, and the height is between 1 and 200mm. Within 1.5 meters, it will be poured together with the horse track platform. Optionally, the width of the horseway platform is 2000mm, the thickness is 150mm, the width of the hardened section is 1m, the width of the water retaining plate is 150mm, and the height is 1.2m, and it is poured together with the horseway platform.

请参阅图1、图2,本申请还提出一种边坡支护方法,应用了上文所述的边坡支护结构,包括如下步骤:Please refer to Fig. 1, Fig. 2, this application also proposes a kind of side slope support method, has applied the side slope support structure described above, comprises the steps:

S1,由坡顶至坡脚逐层开挖边坡,在开挖每层土体的过程中,完成每层土体中的锚固组件20或者灌注桩组件10的安装之后,再开挖下一层土体。S1, excavate the side slope layer by layer from the top of the slope to the foot of the slope, in the process of excavating each layer of soil, after completing the installation of the anchor assembly 20 or cast-in-situ pile assembly 10 in each layer of soil, excavate the next layer layer of soil.

请参阅图2,图2为(现状)边坡的结构示意图。即在开挖之前,边坡的坡面为现状坡面500,原始坡面400为坡积或残积土的原状坡面,现状坡面500和原始坡面400之间为深厚填土层100。步骤S1即是对具有现状坡面500的边坡进行开挖,在深厚填土层100形成开挖面。使得上文所述的边坡的开挖面,位于原始坡面400和现状坡面500之间,后续支护结构的施工也在该开挖面上进行。Please refer to Fig. 2, Fig. 2 is the structural schematic diagram of (current situation) slope. That is, before excavation, the slope surface of the side slope is the current slope surface 500 , the original slope surface 400 is the original slope surface of slope accumulation or residual soil, and the deep filling layer 100 is between the current slope surface 500 and the original slope surface 400 . Step S1 is to excavate the side slope with the existing slope 500 to form an excavation surface in the deep and thick filling layer 100 . The above-mentioned excavation surface of the slope is located between the original slope surface 400 and the current slope surface 500, and the construction of the subsequent support structure is also carried out on the excavation surface.

具体的,所述边坡支护结构的施工过程包括边坡的施工部分和基坑的施工部分。在对边坡进行施工时,并安装对应的灌注桩和锚固件。值得注意的是,在施工之间,在边坡进行填土形成具有原始坡面400的边坡,再对此边坡进行开挖施工。具体的,在施工过程中,按设计坡率分层分段分级放坡。在一实施例中,分层厚度为1500mm,分段长度为20m,分级高度为10m。施工上一层的锚固件(锚杆或者锚索)或者灌注桩并达到设计强度要求后,方可进行下一层的土方开挖,并且在开挖一级边坡后施工格构梁,并与已施工的锚固件和灌注桩形成放坡段的永久边坡支护体系。Specifically, the construction process of the slope support structure includes the construction part of the slope and the construction part of the foundation pit. When constructing the slope, install the corresponding cast-in-place piles and anchors. It should be noted that, between constructions, soil filling is carried out on the side slope to form a side slope with an original slope surface 400, and then the side slope is excavated for construction. Specifically, during the construction process, slopes are graded layer by layer according to the design slope rate. In one embodiment, the layer thickness is 1500mm, the section length is 20m, and the classification height is 10m. After the anchors (bolts or cables) or cast-in-situ piles of the previous layer are constructed and the design strength requirements are met, the earthwork excavation of the next layer can be carried out, and the lattice beams are constructed after excavating the first-level slope, and Form a permanent slope support system for the grading section with the constructed anchors and cast-in-place piles.

在一实施例中,所述边坡支护方法还包括如下步骤:In one embodiment, the slope support method also includes the following steps:

S2,在所述坡脚灌注桩12施工完成后,对所述边坡进行检验,检验边坡的稳定性合格后,再硬化坡脚平台300,进行基坑锚固件21和基坑灌注桩11的施工。如此设置,坡脚平台300的硬化在坡脚灌注桩12和坡脚锚固件22施工完成并通过安全验收后进行。避免施工过程中,两部分同时进行从而影响结构的稳定性。进一步减少了边坡结构和基坑结构的相互影响。S2, after the construction of the cast-in-situ piles 12 at the foot of the slope is completed, the slope is inspected, and after the stability of the slope is qualified, the toe platform 300 is hardened, and the foundation pit anchors 21 and the cast-in-situ piles 11 of the foundation pit are carried out. construction. In this way, the hardening of the toe platform 300 is carried out after the construction of the toe cast-in-situ piles 12 and the toe anchors 22 is completed and passed the safety inspection. Avoid the construction process, the two parts at the same time to affect the stability of the structure. The interaction between the slope structure and the foundation pit structure is further reduced.

在一实施例中,本申请所提出的边坡支护结构采用包括如下步骤的边坡支护方法施工:In one embodiment, the slope support structure proposed in the present application is constructed using a slope support method comprising the following steps:

(1)施工坡顶排水沟33,并接入外界排水系统。(1) Construct the drainage ditch 33 at the top of the slope and connect it to the external drainage system.

(2)按设计坡率分层分级放坡,施工坡中锚固件23和格构梁,各个锚固件分层间隔打入,达设计强度要求后张拉锁定。(2) According to the design slope rate, the slope is graded and graded. The anchors 23 and the lattice beams in the construction slope are driven in layers and intervals. After reaching the design strength requirements, they are tensioned and locked.

(3)在边坡开挖的过程中,坡面设置马道平台、挡水板和硬化段,并把其形成的坡中排水沟32接入外界排水系统。(3) During the excavation process of the slope, set up a horse track platform, a water retaining plate and a hardening section on the slope surface, and connect the drainage ditch 32 formed in the slope to the external drainage system.

(4)开挖至坡中灌注桩13安装位置时,施工袖阀管注浆加固坡中灌注桩13靠已开挖边坡侧的松散填土,设置稳定的灌注桩施工平台,施工坡中灌注桩13和坡中灌注桩13锚索。(4) When excavating to the installation position of the cast-in-situ pile 13 in the slope, the construction sleeve valve pipe grouting reinforces the cast-in-situ pile 13 in the slope against the loose fill soil on the side of the excavated slope, and a stable construction platform for the cast-in-situ pile is set up, and the cast-in-situ pile in the construction slope The cast-in-situ pile 13 and the anchor cable of the cast-in-place pile 13 in the slope.

(5)按照步骤(2)的方法施工坡脚锚固件22,直至开挖至坡脚灌注桩12安装位置时,施工袖阀管注浆加固灌注桩靠已开挖边坡侧的松散填土,设置稳定的灌注桩施工平台,施工坡脚灌注桩12、坡脚锚固件22,其中坡脚锚固件22包括锚索和冠梁,并且在达设计强度要求后,张拉锁定锚固件后,开挖土方至坡脚平台300。(5) According to the method of step (2), construct the anchor 22 at the foot of the slope until the excavation reaches the installation position of the cast-in-place pile 12 at the foot of the slope. , set a stable cast-in-place pile construction platform, construct cast-in-place piles 12 at the foot of the slope, and anchors at the foot of the slope 22, wherein the anchor at the foot of the slope 22 includes anchor cables and crown beams, and after reaching the design strength requirements, tension and lock the anchors, Excavate the earthwork to the slope toe platform 300.

(6)施工坡脚平台300,并且开挖坡脚排水沟31,并且将坡脚排水沟31接入外界排水系统。(6) Construction of the slope toe platform 300, excavation of the slope toe drainage ditch 31, and connection of the slope toe drainage ditch 31 to the external drainage system.

(7)上述施工完成后,对其进行安全检验,检验合格后,坡脚平台300硬化,施工基坑锚固件21和基坑灌注桩11、以及基坑的主体结构工程桩,按照基坑施工要求,由上至下分层开挖基坑。(7) After the above-mentioned construction is completed, carry out safety inspection on it. After passing the inspection, the toe platform 300 is hardened, and the foundation pit anchors 21 and foundation pit pouring piles 11, as well as the main structure engineering piles of the foundation pit, are constructed according to the foundation pit construction. It is required to excavate the foundation pit layer by layer from top to bottom.

(8)通过基坑进行地下室的施工,地下室施工完成后,回填基坑,进行上部结构的施工。(8) Construction of the basement is carried out through the foundation pit. After the construction of the basement is completed, the foundation pit is backfilled to carry out the construction of the superstructure.

以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明技术原理的前提下,还可以做出若干改进和替换,这些改进和替换也应视为本发明的保护范围。The above is only a preferred embodiment of the present invention, it should be pointed out that for those of ordinary skill in the art, without departing from the technical principle of the present invention, some improvements and replacements can also be made, these improvements and replacements It should also be regarded as the protection scope of the present invention.

Claims (10)

1.一种边坡支护结构,应用于需要在边坡坡脚开挖基坑的工程,其特征在于,包括:1. A slope support structure, which is applied to the engineering that needs to excavate a foundation pit at the foot of the slope, is characterized in that, comprising: 灌注桩组件,包括坡脚灌注桩和基坑灌注桩,所述坡脚灌注桩的上半部分贴附所述坡脚设置,下半部分插入地下;所述基坑灌注桩插入地下,且贴附所述基坑靠近所述坡脚一侧的侧壁设置;所述坡脚灌注桩和所述基坑灌注桩间隔设置从而形成坡脚平台;The cast-in-place pile assembly includes the cast-in-place pile at the foot of the slope and the cast-in-situ pile for the foundation pit. The upper half of the cast-in-situ pile at the foot of the slope is attached to the foot of the slope, and the lower part is inserted into the ground; the cast-in-situ pile for the foundation pit is inserted into the ground, and The side wall of the foundation pit is set close to the side of the slope foot; the slope foot filling pile and the foundation pit filling pile are arranged at intervals to form a slope foot platform; 锚固组件,包括多个坡脚锚固件和多个基坑锚固件,多个所述坡脚锚固件设置于所述坡脚灌注桩靠近所述边坡的一侧,且倾斜插入所述边坡,多个所述基坑锚固件设置于所述基坑灌注桩和所述坡脚灌注桩之间,并且倾斜插入所述坡脚平台下方。An anchoring assembly, including a plurality of toe anchors and a plurality of foundation pit anchors, the plurality of toe anchors are arranged on the side of the toe cast-in-place pile close to the slope, and inserted obliquely into the side slope A plurality of said foundation pit anchors are arranged between said foundation pit cast-in-place pile and said slope toe cast-in-place pile, and are obliquely inserted under said slope toe platform. 2.如权利要求1所述的边坡支护结构,其特征在于,所述边坡由坡顶至坡脚向下倾斜设置,所述灌注桩组件还包括至少一个坡中灌注桩,所述锚固组件还包括多个坡中锚固件,所述坡中灌注桩设置于所述边坡的坡顶和坡脚之间,所述坡脚锚固件设置于所述坡脚灌注桩和所述坡中灌注桩之间,所述坡中锚固件设置于所述坡中灌注桩靠近坡顶的一侧,且倾斜插入所述边坡。2. The side slope support structure as claimed in claim 1, wherein the side slope is inclined downward from the top of the slope to the foot of the slope, and the cast-in-place pile assembly also includes at least one cast-in-place pile in the slope, the said cast-in-place pile The anchor assembly also includes a plurality of mid-slope anchors, the mid-slope cast-in-place piles are arranged between the slope crest and the slope toe of the slope, and the slope toe anchors are arranged between the slope toe cast-in-place piles and the slope Between the mid-slope cast-in-place piles, the mid-slope anchor is arranged on a side of the mid-slope mid-slope near the top of the slope, and is obliquely inserted into the side slope. 3.如权利要求2所述的边坡支护结构,其特征在于,所述边坡支护结构还包括多个注浆管,所述注浆管用于插入边坡内并注浆从而加固土体,所述坡中灌注桩、所述坡脚灌注桩靠近坡顶的一侧均设置有所述注浆管。3. The slope support structure as claimed in claim 2, characterized in that, the slope support structure also comprises a plurality of grouting pipes, and the grouting pipes are used for inserting into the slope and injecting grout to reinforce the soil body, the side of the cast-in-place pile in the slope and the cast-in-place pile at the foot of the slope is provided with the grouting pipe near the top of the slope. 4.如权利要求1所述的边坡支护结构,其特征在于,所述基坑锚固件和所述坡脚灌注桩之间存在间隙。4. The slope support structure according to claim 1, characterized in that there is a gap between the foundation pit anchor and the cast-in-place pile at the foot of the slope. 5.如权利要求1所述的边坡支护结构,其特征在于,所述基坑灌注桩和所述坡脚灌注桩之间的间距为a,其中15m≤a≤30m。5. The slope support structure according to claim 1, characterized in that, the distance between the cast-in-place piles in the foundation pit and the cast-in-place piles at the foot of the slope is a, wherein 15m≤a≤30m. 6.如权利要求1所述的边坡支护结构,其特征在于,所述坡脚平台为硬化结构。6. The slope support structure according to claim 1, wherein the slope toe platform is a hardened structure. 7.如权利要求1所述的边坡支护结构,其特征在于,所述边坡支护结构还包括坡顶排水沟、坡脚排水沟,所述坡顶排水沟设置于所述边坡的坡顶,所述坡脚排水沟设置于所述坡脚平台,所述坡顶排水沟、坡脚排水沟接入外界排水系统。7. The slope support structure according to claim 1, characterized in that, the slope support structure also includes a slope top drainage ditch and a slope foot drainage ditch, and the slope top drainage ditch is arranged on the slope The slope top, the slope foot drainage ditch is arranged on the slope foot platform, and the slope top drainage ditch and the slope foot drainage ditch are connected to the external drainage system. 8.如权利要求7所述的边坡支护结构,其特征在于,所述边坡的破面上还设置有至少一个马道平台,所述马道平台远离所述坡脚的一侧设置有硬化段,所述马道平台靠近所述坡脚的一侧连接有挡水板,所述硬化段、所述马道平台、所述挡水板共同围合形成坡中排水沟,所述坡中排水沟接入外界排水系统。8. The slope support structure according to claim 7, characterized in that, at least one horse track platform is also provided on the breaking surface of the slope, and the side of the horse track platform away from the slope toe is provided with a hardened Section, the side of the bridleway platform close to the foot of the slope is connected with a water retaining plate, and the hardened section, the bridleway platform, and the water dam are jointly enclosed to form a drainage ditch in the slope, and the drainage ditch in the slope Access to external drainage system. 9.一种边坡支护方法,其特征在于,应用了如权利要求1至8任意一项所述的边坡支护结构,包括如下步骤:9. A slope support method, characterized in that the slope support structure as claimed in any one of claims 1 to 8 is applied, comprising the steps of: S1,由坡顶至坡脚逐层开挖边坡,在开挖每层土体的过程中,完成每层土体中的锚固组件或者灌注桩组件的安装之后,再开挖下一层土体。S1, Excavate the side slope layer by layer from the top of the slope to the foot of the slope. In the process of excavating each layer of soil, after completing the installation of anchor components or cast-in-situ pile components in each layer of soil, excavate the next layer of soil body. 10.如权利要求9所述的边坡支护方法,其特征在于,还包括如下步骤:10. slope support method as claimed in claim 9, is characterized in that, also comprises the steps: S2,在所述坡脚灌注桩施工完成后,对所述边坡进行检验,检验边坡的稳定性合格后,再硬化坡脚平台,进行基坑锚固件和基坑灌注桩的施工。S2. After the construction of the cast-in-situ piles at the foot of the slope is completed, the side slope is inspected, and after the stability of the slope is qualified, the platform at the foot of the slope is hardened, and the foundation pit anchors and the cast-in-situ piles of the foundation pit are constructed.
CN202310802446.5A 2023-06-30 2023-06-30 Side slope supporting structure and side slope supporting method Pending CN116607548A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310802446.5A CN116607548A (en) 2023-06-30 2023-06-30 Side slope supporting structure and side slope supporting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310802446.5A CN116607548A (en) 2023-06-30 2023-06-30 Side slope supporting structure and side slope supporting method

Publications (1)

Publication Number Publication Date
CN116607548A true CN116607548A (en) 2023-08-18

Family

ID=87674916

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310802446.5A Pending CN116607548A (en) 2023-06-30 2023-06-30 Side slope supporting structure and side slope supporting method

Country Status (1)

Country Link
CN (1) CN116607548A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118375158A (en) * 2024-05-22 2024-07-23 深圳市勘察测绘院(集团)有限公司 Deep-layer easily-softened weathered rock surface layer fragmentation loose body landslide drainage treatment method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118375158A (en) * 2024-05-22 2024-07-23 深圳市勘察测绘院(集团)有限公司 Deep-layer easily-softened weathered rock surface layer fragmentation loose body landslide drainage treatment method

Similar Documents

Publication Publication Date Title
CN106223989B (en) Excavate safeguard structure and construction method in unsymmetrial loading tunnel hole
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN101476466B (en) Construction method of anti-sliding tunnel with prestressed anchor cable and new structure for prevention and control of huge thick landslide
CN103898916B (en) Mini stake Composite Braced Retaining Structure and construction method
CN110685286A (en) A deep foundation pit support construction technology adjacent to the road under complex geological conditions
CN103321246B (en) Underground diaphragm wall based foundation pit construction method
CN104196014A (en) Combined rock-embedded anchor cable slide-resistant pile where round steel is implanted and construction method thereof
CN102966356A (en) Method for controlling upward flotation and deformation of liquefiable ground operating tunnel under action of earthquake
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN110055973A (en) Construction space foundation pit enclosure structure and water-stopping method under by high metal bridge in limited time
CN217419613U (en) Protection structure for excavating and unloading existing underground structure
CN116607548A (en) Side slope supporting structure and side slope supporting method
CN109577322A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN111560964B (en) Construction method of rear anti-seepage system of foundation pit
CN105484270B (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN104499489A (en) Foundation pit construction method
CN104480945A (en) Inversed construction method for foundation pit
CN216999773U (en) A kind of road cutting widening support structure
CN105951874A (en) Retaining wall reinforcing structure and construction method thereof
CN106337418A (en) Supporting structure and supporting method of deep foundation pit in narrow area
CN216194845U (en) Pebble covering layer steel sheet pile cofferdam system
KR20130073336A (en) Pile structure and construction methods
CN113882195B (en) A construction method for preventing slippage of roadbed for operating railways
CN217974507U (en) Protection system of subway tunnel structure crouches down during soft soil foundation ditch excavation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination