CN116591296A - Steel corridor and steel corridor installation method - Google Patents
Steel corridor and steel corridor installation method Download PDFInfo
- Publication number
- CN116591296A CN116591296A CN202310569920.4A CN202310569920A CN116591296A CN 116591296 A CN116591296 A CN 116591296A CN 202310569920 A CN202310569920 A CN 202310569920A CN 116591296 A CN116591296 A CN 116591296A
- Authority
- CN
- China
- Prior art keywords
- rotating column
- layer
- steel corridor
- steel
- rotating
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑施工技术领域,尤其涉及一种钢连廊及钢连廊安装方法。The invention relates to the technical field of building construction, in particular to a steel corridor and a method for installing the steel corridor.
背景技术Background technique
随着城市的不断建设和发展,人们对于建筑使用功能和外观造型的设计要求越来越高。钢连廊作为建筑物外部的一种构筑物,能够起到扩充空间、提高空间利用率的作用,被越来越多地应用在建筑物上。在进行一些大跨度钢连廊的安装时,通常采用整体提升安装法对钢连廊进行安装,即在地面的胎架上将钢连廊整体拼装完成后,再将拼装好的钢连廊提升至连接位置,并与建筑物进行连接安装,该施工方法主要包括钢连廊整体拼装、钢连廊整体提升以及提升就位后的连接等主要施工步骤。With the continuous construction and development of cities, people have higher and higher requirements for the design of building functions and appearance. As a structure outside the building, the steel corridor can expand the space and improve the utilization rate of the space, and is increasingly used in buildings. When installing some long-span steel corridors, the overall lifting installation method is usually used to install the steel corridors, that is, after the overall assembly of the steel corridors is completed on the tire frame on the ground, the assembled steel corridors are lifted The construction method mainly includes the overall assembly of the steel corridor, the overall lifting of the steel corridor, and the connection after the lifting is in place.
现有的钢连廊安装方法如申请号为CN 201610921790.6的专利中提供的一种多层钢结构连廊整体提升施工方法及装置,在对下层连廊结构进行安装时,通过将顶部钢结构连廊提升至下一层的层高高度,之后锁止并安装下层连廊结构,从而实现各层钢连廊结构由上到下的逆行安装,安装效率高且安全性好;但是该钢连廊整体提升施工方法存在以下问题:在拼装下层钢连廊结构时,上下层之间的连接梁需要逐个吊至上层钢连廊下,步骤繁琐、降低了施工效率,同时连接梁在吊运过程中不稳定,增大了施工难度。Existing installation methods for steel corridors, such as the overall lifting construction method and device for multi-layer steel structure corridors provided in the patent application number CN 201610921790.6, when installing the lower corridor structure, connect the top steel structure The corridor is lifted to the floor height of the next floor, and then the lower corridor structure is locked and installed, so as to realize the retrograde installation of the steel corridor structure on each floor from top to bottom, with high installation efficiency and good safety; however, the steel corridor structure The overall lifting construction method has the following problems: When assembling the lower steel corridor structure, the connecting beams between the upper and lower floors need to be hoisted one by one under the upper steel corridor, which is cumbersome and reduces construction efficiency. Stability increases the difficulty of construction.
发明内容Contents of the invention
本发明的目的在于提供一种钢连廊及钢连廊安装方法,能够降低施工难度和施工成本,同时提高施工的安全性。The object of the present invention is to provide a steel corridor and a steel corridor installation method, which can reduce construction difficulty and construction cost, and improve construction safety at the same time.
为达此目的,本发明采用以下技术方案:For reaching this purpose, the present invention adopts following technical scheme:
钢连廊,包括:Steel corridors, including:
横梁,所述横梁有多层,多层所述横梁沿所述钢连廊的高度方向层叠设置;A crossbeam, the crossbeam has multiple layers, and the multi-layer crossbeams are stacked along the height direction of the steel corridor;
桁架层,所述桁架层设置在最上层的所述横梁上,所述桁架层用于与提升机构连接;A truss layer, the truss layer is arranged on the uppermost beam, and the truss layer is used to connect with the lifting mechanism;
转动立柱,相邻的两层所述横梁之间设置有所述转动立柱,所述转动立柱具有第一端部和第二端部,所述第一端部转动设置在上层的所述横梁上,所述转动立柱在所述横梁上能够在叠放位置和拼装位置之间转动;当所述转动立柱转动到所述叠放位置时,所述转动立柱的长度方向与所述横梁的长度方向平行,所述转动立柱沿长度方向抵压在下层的所述横梁上,上层的所述横梁沿所述转动立柱的长度方向抵压在所述转动立柱上;所述桁架层能够带动上层的所述横梁上升,以使所述转动立柱在重力的作用下转动至所述拼装位置;当所述转动立柱转动到所述拼装位置时,所述转动立柱的长度方向与所述横梁的长度方向形成夹角,所述第一端部能够与上层的所述横梁固定连接,所述第二端部能够与下层的所述横梁固定连接。A rotating column, the rotating column is arranged between the two adjacent beams, the rotating column has a first end and a second end, and the first end is rotatably arranged on the upper beam , the rotating column can rotate between the stacked position and the assembled position on the beam; when the rotating column is rotated to the stacked position, the length direction of the rotating column and the length direction of the beam Parallel, the rotating column is pressed against the beam of the lower layer along the length direction, and the beam of the upper layer is pressed against the rotating column along the length direction of the rotating column; the truss layer can drive all the beams of the upper layer The beam rises so that the rotating column rotates to the assembled position under the action of gravity; when the rotating column rotates to the assembled position, the length direction of the rotating column and the length direction of the beam form a The included angle is that the first end can be fixedly connected to the beam on the upper floor, and the second end can be fixedly connected to the beam on the lower floor.
作为优选地,所述横梁的底部设置有铰接支座,所述第一端部通过销轴与所述铰接支座铰接连接。Preferably, a hinged support is provided at the bottom of the beam, and the first end is hingedly connected to the hinged support through a pin.
作为优选地,所述销轴上设有螺纹,所述销轴的一端设置有止挡板,所述销轴伸出所述铰接支座的另一端与螺母螺纹配合。Preferably, threads are provided on the pin shaft, a stop plate is provided at one end of the pin shaft, and the other end of the pin shaft protruding from the hinged support is threadedly engaged with a nut.
钢连廊安装方法,使用上述的钢连廊,包括以下步骤:The steel corridor installation method, using the above-mentioned steel corridor, includes the following steps:
S1、将多层所述横梁沿所述钢连廊的高度方向层叠放置,将所述转动立柱设置在相邻的两层所述横梁之间,并将所述转动立柱的所述第一端部与上层的所述横梁转动连接,使所述转动立柱位于所述叠放位置;S1. Lay multiple layers of the crossbeams along the height direction of the steel corridor, arrange the rotating columns between the two adjacent layers of the crossbeams, and place the first ends of the rotating columns The upper part is rotatably connected with the beam on the upper floor, so that the rotating column is located at the stacking position;
S2、将所述桁架层固定连接在最上层的所述横梁上,并与所述提升机构连接;S2. Fixing the truss layer to the uppermost beam and connecting it to the lifting mechanism;
S3、通过所述提升机构带动所述桁架层上升,使上层的所述横梁远离下层的所述横梁,直至上层的所述横梁上的所述转动立柱转动至安装位置;S3. Drive the truss layer up through the lifting mechanism, so that the beam on the upper floor is away from the beam on the lower floor until the rotating column on the beam on the upper floor is rotated to the installation position;
S4、将所述转动立柱与所述横梁固定连接;S4, fixedly connecting the rotating column with the beam;
S5、重复步骤S3和步骤S4,直至每层的所述转动立柱均与所述横梁固定连接。S5. Steps S3 and S4 are repeated until the rotating uprights on each floor are fixedly connected to the beams.
作为优选地,步骤S4中将所述转动立柱与所述横梁固定连接包括:Preferably, in step S4, the fixed connection between the rotating column and the beam includes:
将所述转动立柱的所述第一端部与上层的所述横梁固定连接;Fixing the first end of the rotating upright to the crossbeam on the upper floor;
将所述转动立柱的所述第二端部与下层的所述横梁固定连接。The second end of the rotating upright is fixedly connected to the crossbeam on the lower floor.
作为优选地,所述转动立柱的所述第二端部与下层的所述横梁焊接连接。Preferably, the second end of the rotating upright is welded to the lower beam.
作为优选地,将每层的所述转动立柱均与所述横梁固定连接后还包括:Preferably, after the rotating column of each floor is fixedly connected to the crossbeam, it further includes:
通过所述提升机构带动所述钢连廊提升至连接位置,将所述钢连廊与两侧的建筑物连接。The lifting mechanism drives the steel corridor to be lifted to the connecting position, and connects the steel corridor to the buildings on both sides.
作为优选地,将所述钢连廊与两侧的建筑物连接后还包括:Preferably, after connecting the steel corridor with the buildings on both sides, it also includes:
拆除所述提升机构。Remove the lifting mechanism.
作为优选地,步骤S3中所述提升机构带动所述桁架层上升的高度不超过所述转动立柱的长度。Preferably, in step S3, the lifting mechanism drives the truss layer up to a height not exceeding the length of the rotating column.
作为优选地,步骤S1中将多层所述横梁沿所述钢连廊的高度方向层叠放置包括:Preferably, in step S1, stacking the multi-layer beams along the height direction of the steel corridor includes:
将最底层的所述横梁放置在胎架上;placing the lowermost beam on the tire frame;
将其余的所述横梁沿所述钢连廊的高度方向层叠放置在最底层的所述横梁上。The rest of the beams are stacked on the bottom beam along the height direction of the steel corridor.
本发明的有益效果在于:The beneficial effects of the present invention are:
本发明提供的钢连廊,相邻的两层横梁之间设置有转动立柱,当转动立柱转动至叠放位置时,多层横梁按照由下往上的顺序堆叠放置在一起,转动立柱的长度方向与横梁的长度方向平行,即转动立柱呈水平状态夹设在相邻的两层横梁中间,降低了前期的拼装高度,无需采用脚手架或梯架等设备即能够对各层横梁进行拼装,从而降低了施工成本;当转动立柱转动至拼装位置时,转动立柱为与横梁存在夹角的竖直或倾斜状态,便于施工人员将转动立柱的两端分别与上下层的横梁固定连接,从而无需将转动立柱从地面逐一吊至作业高度,且由于转动立柱的第一端部已与上层的横梁转动连接,因此相较于现场临时吊运转动立柱,极大地提高了转动立柱与横梁连接的稳定性,降低了施工难度、提高了安全性。最上层横梁上的桁架层与提升机构连接,提升机构通过桁架层带动横梁上升,由于转动立柱的第一端部转动设置在横梁上,因此上层横梁上升时转动立柱在重力的作用下即可转动至拼装位置,便于施工人员进行拼装,无需另外设置驱动设备,施工人员也无需更换作业高度,操作方便且安装速度快。In the steel corridor provided by the present invention, a rotating column is arranged between adjacent two-layer beams. When the rotating column is rotated to the stacking position, the multi-layer beams are stacked together in order from bottom to top, and the length of the rotating column The direction is parallel to the length direction of the beam, that is, the rotating column is sandwiched between the two adjacent beams in a horizontal state, which reduces the assembly height in the early stage, and the beams of each layer can be assembled without using scaffolding or ladder frames. The construction cost is reduced; when the rotating column is rotated to the assembled position, the rotating column is in a vertical or inclined state with an angle with the beam, which is convenient for construction personnel to fix the two ends of the rotating column to the beams on the upper and lower floors respectively, so that there is no need to install The rotating columns are hoisted one by one from the ground to the working height, and since the first end of the rotating column has been rotationally connected with the upper beam, the stability of the connection between the rotating column and the beam is greatly improved compared with the temporary lifting of the rotating column on site , reducing the difficulty of construction and improving safety. The truss layer on the uppermost beam is connected to the lifting mechanism, and the lifting mechanism drives the beam to rise through the truss layer. Since the first end of the rotating column is rotated and arranged on the beam, the rotating column can rotate under the action of gravity when the upper beam rises To the assembly position, it is convenient for construction personnel to assemble, no need to set up additional driving equipment, and construction personnel do not need to change the working height, the operation is convenient and the installation speed is fast.
使用该钢连廊安装方法,提升机构通过桁架层带动横梁上升,能够使得转动设置在横梁上的转动立柱在重力的作用下转动至拼装位置,从而以由上到下的顺序进行拼装,降低了施工高度和施工成本;同时由于转动立柱在安装前已转动设置在横梁上,因此后续拼装时无需临时吊装转动立柱进行悬空连接,极大地提高了转动立柱与横梁连接的稳定性,降低了施工难度、提高了安全性;此外,转动立柱能够在重力的作用下自动转动至拼装位置,无需另外设置驱动设备,节省了人力物力。Using this steel corridor installation method, the lifting mechanism drives the beam to rise through the truss layer, which can make the rotating column on the beam rotate to the assembly position under the action of gravity, so that the assembly can be performed from top to bottom, reducing the Construction height and construction cost; at the same time, since the rotating column has been rotated and set on the beam before installation, there is no need to temporarily hoist the rotating column for suspended connection during subsequent assembly, which greatly improves the stability of the connection between the rotating column and the beam and reduces the difficulty of construction , Improve safety; in addition, the rotating column can automatically rotate to the assembly position under the action of gravity, without additional driving equipment, saving manpower and material resources.
附图说明Description of drawings
图1是本发明具体实施方式提供的转动立柱位于叠放位置时的结构示意图;Fig. 1 is a schematic structural view of a rotating column provided in a specific embodiment of the present invention when it is in a stacked position;
图2是本发明具体实施方式提供的钢连廊的拼装过程示意图;Fig. 2 is a schematic diagram of the assembly process of the steel corridor provided by the specific embodiment of the present invention;
图3是本发明具体实施方式提供的转动立柱位于拼装位置时的结构示意图。Fig. 3 is a schematic structural view of the rotating column provided by the specific embodiment of the present invention when it is in the assembled position.
图中:In the picture:
100-提升机构;200-胎架;300-连接件;100-lifting mechanism; 200-tire frame; 300-connector;
1-横梁;1 - Beam;
2-桁架层;2-truss layer;
3-转动立柱。3-Turn the upright.
具体实施方式Detailed ways
下面结合附图和实施例对本发明作进一步的详细说明。可以理解的是,此处所描述的具体实施例仅仅用于解释本发明,而非对本发明的限定。另外还需要说明的是,为了便于描述,附图中仅示出了与本发明相关的部分而非全部结构。The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, but not to limit the present invention. In addition, it should be noted that, for the convenience of description, only some structures related to the present invention are shown in the drawings but not all structures.
在本发明的描述中,除非另有明确的规定和限定,术语“相连”、“连接”、“固定”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected" and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integrated ; It can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediary, and it can be the internal communication of two components or the interaction relationship between two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention in specific situations.
在本发明中,除非另有明确的规定和限定,第一特征在第二特征之“上”或之“下”可以包括第一和第二特征直接接触,也可以包括第一和第二特征不是直接接触而是通过它们之间的另外的特征接触。而且,第一特征在第二特征“之上”、“上方”和“上面”包括第一特征在第二特征正上方和斜上方,或仅仅表示第一特征水平高度高于第二特征。第一特征在第二特征“之下”、“下方”和“下面”包括第一特征在第二特征正下方和斜下方,或仅仅表示第一特征水平高度小于第二特征。In the present invention, unless otherwise clearly specified and limited, a first feature being "on" or "under" a second feature may include direct contact between the first and second features, and may also include the first and second features Not in direct contact but through another characteristic contact between them. Moreover, "above", "above" and "above" the first feature on the second feature include that the first feature is directly above and obliquely above the second feature, or simply means that the first feature is horizontally higher than the second feature. "Below", "beneath" and "under" the first feature to the second feature include that the first feature is directly below and obliquely below the second feature, or simply means that the first feature has a lower level than the second feature.
在本实施例的描述中,术语“上”、“下”、“右”、“左”等方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述和简化操作,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。此外,术语“第一”、“第二”仅仅用于在描述上加以区分,并没有特殊的含义。In the description of this embodiment, the terms "up", "down", "right", "left" and other orientations or positional relationships are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of description and simplification of operations. It is not intended to indicate or imply that the referred device or element must have a particular orientation, be constructed in a particular orientation, and operate in a particular orientation, and thus should not be construed as limiting the invention. In addition, the terms "first" and "second" are only used to distinguish in description, and have no special meaning.
如图1所示,本发明提供了一种钢连廊,该钢连廊包括横梁1、桁架层2以及转动立柱3,横梁1有多层,多层横梁1沿钢连廊的高度方向层叠设置,桁架层2设置在最上层的横梁1上,桁架层2用于与提升机构100连接,相邻的两层横梁1之间设置有转动立柱3,转动立柱3具有第一端部和第二端部,第一端部转动设置在上层的横梁1上,转动立柱3在横梁1上能够在叠放位置和拼装位置之间转动;当所述转动立柱3转动到叠放位置时,转动立柱3的长度方向与横梁1的长度方向平行,转动立柱3沿长度方向抵压在下层的横梁1上,上层的横梁1沿转动立柱3的长度方向抵压在转动立柱3上;桁架层2能够带动上层的横梁1上升,以使转动立柱3在重力的作用下转动至拼装位置;当转动立柱转动到拼装位置时,转动立柱3的长度方向与横梁1的长度方向形成夹角,第一端部能够与上层的横梁1固定连接,第二端部能够与下层的横梁1固定连接。于本实施例中,每层钢连廊由上下两层横梁1、连接上下层横梁1的转动立柱3以及最顶面的桁架层2组成,其中横梁1起横向的连接和承载作用,人员在每层钢连廊底层的横梁1上通过,该层钢连廊顶层的横梁1同时又作为上层钢连廊的底层;转动立柱3则连接上下相邻两层横梁1,加强钢连廊的整体稳定性和连接强度;在其他实施例中,桁架层2也可由横梁1或其他顶部提升架代替,只要是能够起到与该钢连廊的下层结构连接且能够在提升机构100的提升下带动下层结构上升的作用即可,在此对桁架层2的结构形式不做限定。As shown in Figure 1, the present invention provides a steel corridor, which includes a beam 1, a truss layer 2 and a rotating column 3, the beam 1 has multiple layers, and the multi-layer beam 1 is stacked along the height direction of the steel corridor Set, the truss layer 2 is arranged on the uppermost beam 1, the truss layer 2 is used to connect with the lifting mechanism 100, and a rotating column 3 is arranged between adjacent two layers of beams 1, and the rotating column 3 has a first end and a second Two ends, the first end is rotated and arranged on the beam 1 on the upper floor, and the rotating column 3 can rotate between the stacked position and the assembled position on the beam 1; when the rotating column 3 is rotated to the stacked position, the rotation The length direction of the column 3 is parallel to the length direction of the beam 1, the rotating column 3 is pressed against the lower beam 1 along the length direction, and the upper beam 1 is pressed against the rotating column 3 along the length direction of the rotating column 3; the truss layer 2 The crossbeam 1 on the upper floor can be driven to rise so that the rotating column 3 rotates to the assembly position under the action of gravity; The end portion can be fixedly connected with the beam 1 of the upper layer, and the second end portion can be fixedly connected with the beam 1 of the lower layer. In this embodiment, each steel corridor is composed of upper and lower beams 1, rotating columns 3 connecting the upper and lower beams 1, and the topmost truss layer 2. The beam 1 on the bottom floor of the steel corridor on each floor passes through, and the beam 1 on the top floor of the steel corridor on this floor also serves as the bottom floor of the steel corridor on the upper floor; the rotating column 3 connects the beams 1 on the upper and lower adjacent floors to strengthen the overall structure of the steel corridor Stability and connection strength; in other embodiments, the truss layer 2 can also be replaced by a beam 1 or other top lifting frame, as long as it can be connected to the lower structure of the steel corridor and can be driven by the lifting mechanism 100 The function of raising the lower structure is sufficient, and the structural form of the truss layer 2 is not limited here.
具体地,在进行该钢连廊的安装之前,施工人员按照从下往上的放置顺序将多层横梁1放置在地面的胎架200上,其中相邻的两层横梁1之间设置有转动立柱3;此时转动立柱3位于叠放位置,转动立柱3的长度方向与横梁1的长度方向平行,即转动立柱3呈水平状态夹设在相邻的两层横梁1中间,降低了前期的拼装高度,无需采用脚手架或梯架等设备即能够对各层横梁1进行拼装,从而降低了施工成本。之后施工人员启动提升机构100,提升机构100通过桁架层2带动横梁1上升,由于转动立柱3的第一端部转动设置在横梁1上,因此上层横梁1上升时转动立柱3在重力的作用下即可转动至拼装位置,便于施工人员进行拼装,无需另外设置驱动设备,结构简单、操作方便;当该层的转动立柱3转动至拼装位置后,转动立柱3为与横梁1存在夹角的竖直或倾斜状态,便于施工人员将转动立柱3的两端分别与上下层的横梁1固定连接,从而无需将转动立柱3从地面逐一吊至作业高度,且由于转动立柱3的第一端部已与上层的横梁1转动连接,因此相较于吊运转动立柱3,极大地提高了转动立柱3与横梁1连接的稳定性,降低了施工难度、提高了安全性;于本实施例中,转动立柱3可以与横梁1垂直连接,也可以倾斜连接,只要能够保证转动立柱3与横梁1连接稳定即可,在此不做限定。Specifically, before the installation of the steel corridor, the construction personnel placed the multi-layer beams 1 on the tire frame 200 on the ground according to the order of placement from bottom to top, wherein a rotation mechanism is provided between adjacent two-layer beams 1 . Column 3; at this time, the rotating column 3 is in the stacked position, and the length direction of the rotating column 3 is parallel to the length direction of the beam 1, that is, the rotating column 3 is sandwiched in the middle of the adjacent two-layer beam 1 in a horizontal state, which reduces the previous stage. Assembling height, each layer of beams 1 can be assembled without using equipment such as scaffolding or ladder frames, thereby reducing construction costs. Afterwards, the construction workers start the lifting mechanism 100, and the lifting mechanism 100 drives the beam 1 to rise through the truss layer 2. Since the first end of the rotating column 3 is rotated and arranged on the beam 1, when the upper beam 1 rises, the rotating column 3 is under the action of gravity. It can be rotated to the assembly position, which is convenient for construction personnel to assemble, without additional driving equipment, simple structure and convenient operation; The straight or inclined state is convenient for construction personnel to fix the two ends of the rotating column 3 with the beams 1 on the upper and lower floors respectively, so that there is no need to lift the rotating column 3 from the ground to the working height one by one, and because the first end of the rotating column 3 has been It is rotatably connected with the beam 1 on the upper floor, so compared with hoisting the moving column 3, the stability of the connection between the rotating column 3 and the beam 1 is greatly improved, construction difficulty is reduced, and safety is improved; in this embodiment, the rotating The column 3 can be connected vertically or obliquely to the beam 1, as long as the connection between the rotating column 3 and the beam 1 can be ensured to be stable, there is no limitation here.
在提升机构100通过桁架层2带动横梁1上升的过程中,当转动立柱3转动至拼装位置时,此时施工人员关停提升机构100,在将本层的转动立柱3与上下层的横梁1固定连接之后继续启动提升机构100,从而能够将下层的转动立柱3升至施工人员所在的高度便于施工人员继续固定转动立柱3,如此重复作业,从而完成该钢连廊的整体拼装。When the lifting mechanism 100 drives the beam 1 to rise through the truss layer 2, when the rotating column 3 rotates to the assembly position, the construction personnel shuts down the lifting mechanism 100 at this time, and the rotating column 3 of this floor and the beam 1 on the upper and lower floors After the fixed connection, continue to start the lifting mechanism 100, so that the rotating column 3 on the lower floor can be raised to the height where the construction personnel are convenient for the construction personnel to continue to fix the rotating column 3, and the operation is repeated, thereby completing the overall assembly of the steel corridor.
进一步地,横梁1的底部设置有铰接支座,第一端部通过销轴与铰接支座铰接连接。具体地,第一端部上开设有通孔,铰接支座上设置有两个耳板,两个耳板之间开设有能够容纳第一端部的容纳通道,且两个耳板上均开设有销孔;第一端部插入两个耳板之间的容纳通道中且通孔与两侧耳板上的销孔对准,之后使用销轴依次穿过一侧耳板的销孔、第一端部的通孔以及另一侧耳板的销孔,从而将转动立柱3转动连接在铰接支座上。Further, the bottom of the beam 1 is provided with a hinged support, and the first end is hingedly connected to the hinged support through a pin. Specifically, a through hole is opened on the first end, two ear plates are provided on the hinged support, and a receiving channel capable of accommodating the first end is opened between the two ear plates, and both ear plates are provided with There are pin holes; the first end is inserted into the accommodation channel between the two ear plates and the through hole is aligned with the pin holes on both ear plates, and then the pin shaft is used to pass through the pin holes of one ear plate, the first end The through hole of the upper part and the pin hole of the ear plate on the other side, so that the rotating column 3 is rotatably connected to the hinged support.
具体地,销轴上设有螺纹,销轴的一端设置有止挡板,销轴伸出铰接支座的另一端与螺母螺纹配合。于本实施例中,当转动立柱3转动至拼装位置后,施工人员需要将转动立柱3的第一端部与上层的横梁1固定,在固定时可以采用可拆卸的锁定装置将第一端部与铰链支座固定连接,也可以直接将第一端部与铰链支座焊接固定;相比较于焊接连接,采用可拆卸的锁定装置便于对转动立柱3的安装角度和位置进行调整,同时也便于后期对转动立柱3进行拆卸与更换。具体地,锁定装置包括带止挡板的销轴以及螺母,销轴上设有螺纹,当转动立柱3转动到拼装位置后,施工人员将销轴上的螺母拧紧,通过螺母和止挡板的锁紧,第一端部两侧的耳板会发生形变并贴靠在转动立柱3上,从而将转动立柱3固定、避免继续转动;该锁定装置无需设置复杂的固定装置,仅需要通过旋拧螺母即可实现转动立柱3与上层横梁1的固定与解锁,结构简单、操作方便,不仅能够降低该锁定装置的故障率,还能够降低该钢连廊的制造成本。Specifically, the pin shaft is provided with threads, one end of the pin shaft is provided with a stop plate, and the other end of the pin shaft protruding from the hinged support is threadedly engaged with the nut. In this embodiment, after the rotating column 3 is rotated to the assembled position, construction personnel need to fix the first end of the rotating column 3 with the upper beam 1, and a detachable locking device can be used to fix the first end It is fixedly connected with the hinge support, and the first end can also be directly welded and fixed with the hinge support; compared with the welding connection, the detachable locking device is used to facilitate the adjustment of the installation angle and position of the rotating column 3, and it is also convenient In the later stage, the rotating column 3 is disassembled and replaced. Specifically, the locking device includes a pin with a stop plate and a nut, and the pin is provided with threads. When the rotating column 3 is rotated to the assembled position, the construction personnel will tighten the nut on the pin, and through the connection between the nut and the stop plate Locking, the ear plates on both sides of the first end will deform and lean against the rotating column 3, thereby fixing the rotating column 3 and avoiding further rotation; The fixing and unlocking of the upright column 3 and the upper beam 1 can be realized by turning the nut. The structure is simple and the operation is convenient, which can not only reduce the failure rate of the locking device, but also reduce the manufacturing cost of the steel corridor.
如图2所示,本实施例还提供了一种钢连廊安装方法,使用上述的钢连廊,包括以下步骤:As shown in Figure 2, this embodiment also provides a method for installing a steel corridor, using the above-mentioned steel corridor, including the following steps:
S1、将多层横梁1沿钢连廊的高度方向层叠放置,将转动立柱3设置在相邻的两层横梁1之间,并将转动立柱3的第一端部与上层的横梁1转动连接,使转动立柱3位于叠放位置;具体地,施工人员按照从下往上的放置顺序将多层横梁1放置在地面的胎架200上,其中相邻的两层横梁1之间设置有转动立柱3;此时转动立柱3位于叠放位置,转动立柱3的长度方向与横梁1的长度方向平行,即转动立柱3呈水平状态夹设在相邻的两层横梁1中间,降低了前期的拼装高度,无需采用脚手架或梯架等设备即能够对各层横梁1进行拼装,从而降低了施工成本。S1. Lay the multi-layer beams 1 along the height direction of the steel corridor, arrange the rotating column 3 between the two adjacent beams 1, and rotate the first end of the rotating column 3 to the upper beam 1 , so that the rotating column 3 is located in the stacking position; specifically, the construction personnel place the multi-layer beams 1 on the tire frame 200 on the ground according to the order of placement from bottom to top, wherein a rotating Column 3; at this time, the rotating column 3 is in the stacked position, and the length direction of the rotating column 3 is parallel to the length direction of the beam 1, that is, the rotating column 3 is sandwiched in the middle of the adjacent two-layer beam 1 in a horizontal state, which reduces the previous stage. Assembling height, each layer of beams 1 can be assembled without using equipment such as scaffolding or ladder frames, thereby reducing construction costs.
S2、将桁架层2固定连接在最上层的横梁1上,并与提升机构100连接;具体地,桁架层2由多组三角形钢结构焊接而成,结构强度大、承载力强,桁架层2固定连接在最上层的横梁1上方,桁架层2上设置有起吊钩,从而便于提升机构100提升。S2. The truss layer 2 is fixedly connected to the uppermost beam 1, and connected to the lifting mechanism 100; specifically, the truss layer 2 is welded by multiple sets of triangular steel structures, with high structural strength and strong bearing capacity. The truss layer 2 It is fixedly connected above the uppermost beam 1 , and the truss layer 2 is provided with a lifting hook, so as to facilitate the lifting of the lifting mechanism 100 .
S3、通过提升机构100带动桁架层2上升,使上层的横梁1远离下层的横梁1,直至上层的横梁1上的转动立柱3转动至拼装位置;为便于识别和理解,本实施例中按照从上往下的高度将多层横梁1分别命名为第一层横梁、第二层横梁、第三层横梁……同样也将与每层横梁1转动连接的转动立柱3命名为第一层转动立柱、第二层转动立柱、第三层转动立柱……具体地,施工人员启动提升机构100,提升机构100通过桁架层2带动第一层横梁上升,由于横梁1与转动立柱3转动连接,因此第一层横梁下的第一层转动立柱在重力和提升力的作用下会慢慢直立,直到转动至拼装位置。S3. Drive the truss layer 2 to rise through the lifting mechanism 100, so that the upper beam 1 is away from the lower beam 1 until the rotating column 3 on the upper beam 1 rotates to the assembly position; for easy identification and understanding, in this embodiment, according to For the height from top to bottom, the multi-layer crossbeams 1 are respectively named as the first floor crossbeam, the second floor crossbeam, the third floor crossbeam... and also the rotating column 3 connected with each floor beam 1 is named the first floor rotating column , the second layer of rotating columns, the third layer of rotating columns... Specifically, the construction personnel start the lifting mechanism 100, and the lifting mechanism 100 drives the first layer of beams to rise through the truss layer 2. Since the beams 1 and the rotating columns 3 are rotationally connected, the second layer The first layer of rotating columns under the first layer of beams will slowly stand upright under the action of gravity and lifting force until they are rotated to the assembled position.
S4、将转动立柱3与横梁1固定连接;具体地,当第一层转动立柱转动至拼装位置后,施工人员关停提升机构100,将第一层转动立柱与第一层横梁和第二层横梁固定连接,从而实现上下层横梁1的连接。S4. Fixedly connect the rotating column 3 to the crossbeam 1; specifically, when the first layer of rotating column is rotated to the assembly position, the construction personnel shut down the lifting mechanism 100, and connect the first layer of rotating column with the first layer of beam and the second layer The beams are fixedly connected, so as to realize the connection of the upper and lower beams 1 .
S5、重复步骤S3和步骤S4,直至每层的转动立柱3均与横梁1固定连接;具体地,当固定完第一层转动立柱后,施工人员再次启动提升机构100,此时第一层横梁会通过第一层转动立柱带动第二层横梁上升,而第二层转动立柱在第二层横梁的带动下和重力的作用下也会慢慢直立,直到转动至拼装位置;当第二层转动立柱转动至拼装位置后,施工人员关停提升机构100,并将第二层转动立柱与第二层横梁和第三层横梁进行固定连接;完成第二层转动立柱的固定连接后,施工人员便启动提升机构100,进行第三层转动立柱的固定连接,如此重复,直至每层的转动立柱3均与横梁1固定连接。S5. Repeat step S3 and step S4 until the rotating column 3 of each layer is fixedly connected with the beam 1; specifically, after the first layer of rotating column is fixed, the construction personnel start the lifting mechanism 100 again, and the first layer of beam The first layer of rotating columns will drive the second layer of beams to rise, and the second layer of rotating columns will slowly stand upright under the drive of the second layer of beams and the action of gravity until they are rotated to the assembled position; when the second layer rotates After the column rotates to the assembly position, the construction workers shut down the lifting mechanism 100, and fix the second-layer rotating column with the second-layer beam and the third-layer beam; after completing the fixed connection of the second-layer rotating column, the construction personnel will Start the lifting mechanism 100 to perform the fixed connection of the third layer of rotating columns, and repeat this until the rotating columns 3 of each layer are fixedly connected to the beams 1 .
进一步地,步骤S4中将转动立柱3与横梁1固定连接包括:将转动立柱3的第一端部与上层的横梁1固定连接;将转动立柱3的第二端部与下层的横梁1固定连接。于本实施例中,施工人员将转动立柱3的两端分别与上、下层的横梁1固定连接,从而使得转动立柱3与上、下层横梁1连接成稳定的整体结构。Further, in step S4, the fixed connection of the rotating column 3 to the beam 1 includes: fixedly connecting the first end of the rotating column 3 to the upper beam 1; fixedly connecting the second end of the rotating column 3 to the lower beam 1 . In this embodiment, construction personnel fixedly connect the two ends of the rotating column 3 to the upper and lower beams 1 respectively, so that the rotating column 3 is connected to the upper and lower beams 1 to form a stable overall structure.
具体地,转动立柱3的第二端部与下层的横梁1焊接连接。于本实施例中,第二端部与下层的横梁1焊接连接,无需提前设置其他结构,维护方便且连接紧密;于其他实施例中,也可以采用螺栓连接等可拆卸连接方式,只要是能够保证转动立柱3与横梁1连接稳定即可,在此对具体连接方式不做限定。Specifically, the second end of the rotating column 3 is welded to the lower beam 1 . In this embodiment, the second end is welded to the beam 1 on the lower floor, no other structures need to be arranged in advance, and the maintenance is convenient and the connection is tight; in other embodiments, detachable connection methods such as bolt connection can also be used, as long as it can It only needs to ensure the stable connection between the rotating column 3 and the crossbeam 1, and the specific connection method is not limited here.
进一步地,如图3所示,将每层的转动立柱3均与横梁1固定连接后还包括:通过提升机构100带动钢连廊提升至连接位置,将钢连廊与两侧的建筑物连接。于本实施例中,两侧的建筑物上设置有连接件300,施工人员启动提升机构100将拼装完的钢连廊提升至连接位置,之后将钢连廊与连接件300连接,从而将钢连廊稳固地安装在建筑物上。Further, as shown in Figure 3, after the rotating column 3 on each floor is fixedly connected to the beam 1, it also includes: driving the steel corridor to the connection position through the lifting mechanism 100, and connecting the steel corridor to the buildings on both sides . In this embodiment, the buildings on both sides are provided with connectors 300, and the construction workers start the lifting mechanism 100 to lift the assembled steel corridor to the connection position, and then connect the steel corridor with the connectors 300, so that the steel The corridor is firmly installed on the building.
进一步地,将钢连廊与两侧的建筑物连接后还包括:拆除提升机构100。于本实施例中,钢连廊安装完成后,施工人员将提升机构100拆除,避免提升机构100对钢连廊的顶部产生破坏。Further, after connecting the steel corridor with the buildings on both sides, it also includes: dismantling the lifting mechanism 100 . In this embodiment, after the installation of the steel corridor is completed, construction personnel remove the lifting mechanism 100 to avoid damage to the top of the steel corridor by the lifting mechanism 100 .
进一步地,步骤S3中提升机构100带动桁架层2上升的高度不超过转动立柱3的长度。于本实施例中,当提升机构100带动桁架层2上升时,其抬升的高度不超过不超过转动立柱3的长度,避免上、下层横梁1之间的间隔太大而导致转动立柱3的第二端部无法与下层的横梁1连接。Further, in step S3 , the lifting mechanism 100 drives the truss layer 2 up to a height not exceeding the length of the rotating column 3 . In this embodiment, when the lifting mechanism 100 drives the truss layer 2 to rise, the height of its lift does not exceed the length of the rotating column 3, so as to avoid the gap between the upper and lower beams 1 being too large and causing the first rotation of the rotating column 3. The two ends cannot be connected with the beam 1 of the lower floor.
进一步地,如图1所示,步骤S1中将多层横梁1沿钢连廊的高度方向层叠放置包括:将最底层的横梁1放置在胎架200上;将其余的横梁1沿钢连廊的高度方向层叠放置在最底层的横梁1上。于本实施例中,胎架200是起承重作用的高度较低的脚手架,作业场地放置有多个胎架200,胎架200能够调节高度,最底层的横梁1放置在胎架200上后能够进行找平,从而保证了后续安装的稳定性。Further, as shown in FIG. 1 , stacking the multi-layer beams 1 along the height direction of the steel corridor in step S1 includes: placing the lowest beam 1 on the tire frame 200; placing the remaining beams 1 along the steel corridor The height direction is stacked on the bottom beam 1. In this embodiment, the tire frame 200 is a low-height scaffold that plays a load-bearing role. There are multiple tire frames 200 placed on the work site. The tire frame 200 can adjust the height, and the bottom beam 1 can be placed on the tire frame 200 Leveling is carried out to ensure the stability of the subsequent installation.
显然,本发明的上述实施例仅仅是为了清楚说明本发明所作的举例,而并非是对本发明的实施方式的限定。对于所属领域的普通技术人员来说,能够进行各种明显的变化、重新调整和替代而不会脱离本发明的保护范围。这里无需也无法对所有的实施方式予以穷举。凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明权利要求的保护范围之内。Apparently, the above-mentioned embodiments of the present invention are only examples for clearly illustrating the present invention, rather than limiting the implementation of the present invention. Various obvious changes, readjustments, and substitutions will occur to those skilled in the art without departing from the scope of the present invention. It is not necessary and impossible to exhaustively list all the implementation manners here. All modifications, equivalent replacements and improvements made within the spirit and principles of the present invention shall be included within the protection scope of the claims of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310569920.4A CN116591296A (en) | 2023-05-19 | 2023-05-19 | Steel corridor and steel corridor installation method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310569920.4A CN116591296A (en) | 2023-05-19 | 2023-05-19 | Steel corridor and steel corridor installation method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116591296A true CN116591296A (en) | 2023-08-15 |
Family
ID=87611140
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310569920.4A Pending CN116591296A (en) | 2023-05-19 | 2023-05-19 | Steel corridor and steel corridor installation method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116591296A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117286790A (en) * | 2023-09-22 | 2023-12-26 | 中铁广州工程局集团有限公司 | A method for installing and dismantling overweight beams of cable suspension towers in steep terrain |
| CN119352638A (en) * | 2024-12-10 | 2025-01-24 | 中国建筑第八工程局有限公司 | Large-span multi-layer steel truss corridor and its construction method |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109779272A (en) * | 2019-03-18 | 2019-05-21 | 济南四建(集团)有限责任公司 | A kind of high-altitude steel structure corridor construction method |
| CN113494127A (en) * | 2021-07-09 | 2021-10-12 | 上海宝冶集团有限公司 | Construction method for layered lifting of large-span open-web corridor steel platform |
| CN115341661A (en) * | 2022-08-29 | 2022-11-15 | 天津大学 | Assembled concrete-filled steel tube truss column, truss column assembly and construction method |
| CN115653111A (en) * | 2022-10-28 | 2023-01-31 | 河北佳强节能科技有限公司 | Fast hoisting folding box house and its quick hoisting method |
| CN115749299A (en) * | 2022-09-22 | 2023-03-07 | 河北佳强节能科技有限公司 | Quickly-hoisted foldable box house and quick hoisting method thereof |
-
2023
- 2023-05-19 CN CN202310569920.4A patent/CN116591296A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109779272A (en) * | 2019-03-18 | 2019-05-21 | 济南四建(集团)有限责任公司 | A kind of high-altitude steel structure corridor construction method |
| CN113494127A (en) * | 2021-07-09 | 2021-10-12 | 上海宝冶集团有限公司 | Construction method for layered lifting of large-span open-web corridor steel platform |
| CN115341661A (en) * | 2022-08-29 | 2022-11-15 | 天津大学 | Assembled concrete-filled steel tube truss column, truss column assembly and construction method |
| CN115749299A (en) * | 2022-09-22 | 2023-03-07 | 河北佳强节能科技有限公司 | Quickly-hoisted foldable box house and quick hoisting method thereof |
| CN115653111A (en) * | 2022-10-28 | 2023-01-31 | 河北佳强节能科技有限公司 | Fast hoisting folding box house and its quick hoisting method |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117286790A (en) * | 2023-09-22 | 2023-12-26 | 中铁广州工程局集团有限公司 | A method for installing and dismantling overweight beams of cable suspension towers in steep terrain |
| CN119352638A (en) * | 2024-12-10 | 2025-01-24 | 中国建筑第八工程局有限公司 | Large-span multi-layer steel truss corridor and its construction method |
| CN119352638B (en) * | 2024-12-10 | 2025-10-14 | 中国建筑第八工程局有限公司 | Large-span multi-story steel truss corridor and its construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106760451B (en) | Assembled architecture construct it is collapsible operation and discharging platform and tool type stairs lifting combination constructing method thereof | |
| CN215291318U (en) | Mounting structure of attached lifting scaffold | |
| CN116591296A (en) | Steel corridor and steel corridor installation method | |
| CN114150857A (en) | Construction method of attached type automatic climbing elevator shaft safety protection platform | |
| CN1625517A (en) | Scaffold system | |
| JP7657261B2 (en) | Truss and truss construction method | |
| CN114737722A (en) | A kind of indoor rotating steel ladder and installation method thereof | |
| CN212151270U (en) | Moving platform type hanging basket platform | |
| CN213418443U (en) | Self-climbing type elevator shaft operation platform | |
| CN113494127A (en) | Construction method for layered lifting of large-span open-web corridor steel platform | |
| CN115538752B (en) | Attached lifting scaffold and construction method thereof | |
| CN116201348A (en) | Frame structure is climbed in outer wall construction and health safety monitoring system thereof | |
| CN116876841A (en) | An integral hoisting construction method for multi-layered steel corridors and its hoisting device | |
| CN216810895U (en) | An elevator shaft operation platform | |
| CN221741957U (en) | Elevator well scaffold system | |
| CN114370152B (en) | Suspension type operation platform for elevator shaft construction | |
| CN223793853U (en) | Attached lifting scaffold system | |
| CN221253693U (en) | Large modular unit lifting device | |
| CN224063878U (en) | Self-locking type concrete well supporting platform | |
| CN222757791U (en) | A lifting device | |
| CN222743836U (en) | A vertical transport lifting device installed using an indoor elevator shaft | |
| CN223018135U (en) | A construction platform suitable for various occasions | |
| CN219343914U (en) | Low-altitude maintenance platform | |
| CN218778575U (en) | Steel structure derrick of elevator | |
| CN121273077B (en) | Movable mounting platform for inverted cone-shaped glass curtain wall |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |