CN116556204A - A construction method of V-shaped pier prestressed rods - Google Patents
A construction method of V-shaped pier prestressed rods Download PDFInfo
- Publication number
- CN116556204A CN116556204A CN202310506476.1A CN202310506476A CN116556204A CN 116556204 A CN116556204 A CN 116556204A CN 202310506476 A CN202310506476 A CN 202310506476A CN 116556204 A CN116556204 A CN 116556204A
- Authority
- CN
- China
- Prior art keywords
- pier
- layer
- height
- concrete
- pull rods
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/28—Concrete reinforced prestressed
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本发明属于涉及桥梁施工技术领域,涉及一种V型墩预应力拉杆施工方法,主要作用是用于平衡V墩及0号块施工期间产生的水平分力,防止V墩根部裂缝产生。The invention belongs to the technical field of bridge construction, and relates to a V-shaped pier prestressed rod construction method, which is mainly used to balance the horizontal component forces generated during the construction of the V-shaped pier and No. 0 block, and prevent cracks at the root of the V-shaped pier.
背景技术Background technique
预应力混凝土V型墩连续刚构桥比连续梁桥和T型刚构桥具有更为合理的力学性能,由于V型墩的支撑,可以有效减小计算跨度,降低主梁的弯矩,进而可以减少一定的梁部工程数量,且V型墩刚构桥线条活泼、造型美观。但由于墩身倾斜,墩身施工过程中会产生较大的竖向荷载及水平荷载,对支架承载能力要求较高,目前广泛采用的支架法、T型吊架法施工方法,仅适用于体量较小的V型墩,且要求周边地质情况良好,对大体积V型墩或承载能力较弱的地质条件下,墩身产生的水平分力会导致墩底根部与承台连接部分出现裂缝。Prestressed concrete V-shaped piers continuous rigid frame bridges have more reasonable mechanical properties than continuous girder bridges and T-shaped rigid frame bridges. Due to the support of V-shaped piers, the calculation span can be effectively reduced, and the bending moment of the main girder can be reduced. A certain number of beam projects can be reduced, and the V-shaped pier rigid frame bridge has lively lines and beautiful appearance. However, due to the inclination of the pier body, large vertical loads and horizontal loads will be generated during the construction of the pier body, and the requirements for the bearing capacity of the support are relatively high. Currently, the widely used construction methods of the support method and the T-shaped hanger method are only applicable to V-shaped piers with a small volume, and the surrounding geological conditions are required to be good. For large-volume V-shaped piers or geological conditions with weak bearing capacity, the horizontal component force generated by the pier body will cause cracks to appear at the connection between the root of the pier and the cap .
为解决上述问题,CN202954299U公开了一种“用于连续刚构桥的大角度V型墩及0#块模板的支撑结构”,其在V型墩两侧模板间设置了多层拉杆,在一定程度上可抵抗V型墩浇筑时产生的水平分力,但施工过程中,尤其是浇筑墩顶0号块时,由于水平分力过大,拉杆本身也会产生一定的拉伸量,无法完全避免V型墩根部开裂现象。In order to solve the above problems, CN202954299U discloses a kind of "supporting structure for large-angle V-shaped piers and 0# block templates used in continuous rigid frame bridges". To a certain extent, it can resist the horizontal component force generated when the V-shaped pier is poured, but during the construction process, especially when pouring the No. Avoid cracking at the root of the V-shaped pier.
发明内容Contents of the invention
本发明的目的是针对上述问题,提供一种V型墩预应力拉杆施工方法,可抵抗V型墩施工过程中较大水平分力,防止V型墩根部产生裂缝。The object of the present invention is to address the above problems and provide a V-shaped pier prestressed rod construction method, which can resist the large horizontal component force during the construction of the V-shaped pier and prevent cracks at the root of the V-shaped pier.
本发明的技术方案如下:Technical scheme of the present invention is as follows:
一种V型墩预应力拉杆施工方法,其特征在于,包括以下步骤:A V-shaped pier prestressed rod construction method is characterized in that it comprises the following steps:
(1)在V型墩两侧分别搭设一组钢管支架,每组钢管支架朝向墩身一侧横桥向搭设多根承重梁,在承重梁上沿墩身倾斜方向搭设多根分配梁,将V型墩的外模板支撑在分配梁上,安装墩身钢筋及内模板;在墩身两侧模板间穿设3层拉杆,每层拉杆至少5根,其中第一层拉杆设置在V型墩1/3高度以下,第二层拉杆设置在V型墩1/3高度以上、2/3高度以下,第三层拉杆设置在V型墩2/3高度以上、顶部高度以下,每根拉杆一端锚固在一组支架的分配梁外侧,另一端在另一组支架的分配梁外侧安装一张拉千斤顶;(1) Set up a set of steel pipe supports on both sides of the V-shaped pier, each set of steel pipe supports is set up with multiple load-bearing beams facing the side of the pier body, and multiple distribution beams are set up on the load-bearing beams along the inclined direction of the pier body. The outer formwork of the pier is supported on the distribution beam, and the pier body reinforcement and inner formwork are installed; 3 layers of tie rods are installed between the formwork on both sides of the pier body, with at least 5 tie rods in each layer, and the first layer of tie rods is set on the V-shaped pier 1/ Below the height of 3, the second layer of tie rods is set above 1/3 of the height of the V-shaped pier and below 2/3 of the height, and the third layer of tie rods is set above 2/3 of the height of the V-shaped pier and below the height of the top, and one end of each tie rod is anchored on The outside of the distribution beam of one group of brackets, and the other end is installed on the outside of the distribution beam of the other group of brackets with a pulling jack;
(2)分层浇筑墩身混凝土,具体按以下步骤进行:(2) Pour the pier body concrete in layers, specifically according to the following steps:
(21)张拉第一层拉杆,浇筑墩身混凝土至1/3墩身高度;(21) Stretch the first layer of tie rods, and pour the pier body concrete to 1/3 of the pier body height;
(22)张拉第二层拉杆,浇筑墩身混凝土至2/3墩身高度;(22) Stretch the second layer of tie rods, and pour the pier body concrete to 2/3 pier body height;
(23)张拉第三层拉杆,浇筑墩身混凝土至墩身顶标高;(23) Stretch the third layer of pull rods and pour the concrete of the pier body to the elevation of the top of the pier body;
上述每层拉杆张拉时,从中间向两侧对称张拉,张拉至拉杆最大张拉值的20%;When the above-mentioned tie rods of each layer are stretched, they are stretched symmetrically from the middle to both sides, and the tension reaches 20% of the maximum tension value of the tie rods;
(3)分层浇筑墩顶0号块混凝土,具体按以下步骤进行:(3) Concrete No. 0 on the top of the pier is poured in layers, specifically as follows:
(31)从下往上依次张拉3层拉杆,张拉至最大张拉值的40%,浇筑0号块底板混凝土;(31) Stretch 3 layers of tie rods sequentially from bottom to top, stretch to 40% of the maximum tension value, and pour No. 0 block bottom slab concrete;
(32)从下往上依次张拉3层拉杆,张拉至最大张拉值的60%,浇筑0号块横隔墙及腹板至1/2高度;(32) Stretch the 3-layer tie rods sequentially from bottom to top to 60% of the maximum tension value, and pour No. 0 block transverse partition wall and web to 1/2 height;
(33)从下往上依次张拉3层拉杆,张拉至最大张拉值的80%,浇筑0号块剩余横隔墙及腹板混凝土;(33) Stretch 3 layers of tie rods sequentially from bottom to top, stretch to 80% of the maximum tension value, and pour the remaining transverse partition wall and web concrete of No. 0 block;
(34)从下往上依次张拉3层拉杆,张拉至最大张拉值的100%,浇筑0号块顶板混凝土;(34) Stretch 3 layers of pull rods sequentially from bottom to top, stretch to 100% of the maximum tension value, and pour No. 0 block roof concrete;
(35)0号块预应力施工完成后,拆除拉杆。(35) After the prestressing construction of block No. 0 is completed, remove the tie rods.
本发明在墩身内沿高度方向设置3道预应力拉杆,并通过不同施工阶段施加不同的预应力以达到平衡墩身水平分力的效果,能保证V型墩身施工质量及施工安全。In the present invention, three prestressed tie rods are arranged along the height direction in the pier body, and different prestressing forces are applied in different construction stages to achieve the effect of balancing the horizontal component force of the pier body, which can ensure the construction quality and safety of the V-shaped pier body.
附图说明Description of drawings
图1是本发明的支架及拉杆布设方式立面图;Fig. 1 is the elevation view of support and pull rod arrangement mode of the present invention;
图2是本发明的拉杆布设方式侧视图;Fig. 2 is a side view of the layout of the tie rods of the present invention;
图3是本发明的拉杆施工方法流程图。Fig. 3 is a flowchart of the tie rod construction method of the present invention.
具体实施方式Detailed ways
本发明的具体实施方式如下:The specific embodiment of the present invention is as follows:
步骤一、支架及拉杆设置:如图1、图2所示,在V型墩10两侧分别搭设一组钢管支架1,每组钢管支架朝向墩身一侧横桥向搭设多根承重梁2,在承重梁上沿墩身倾斜方向搭设多根分配梁3,将V型墩的外模板4支撑在分配梁上,安装墩身钢筋及内模板5;在墩身两侧模板间穿设3层拉杆6,每层拉杆至少5根,其中第一层拉杆设置在V型墩1/3高度以下,第二层拉杆设置在V型墩1/3高度以上、2/3高度以下,第三层拉杆设置在V型墩2/3高度以上、顶部高度以下,每根拉杆一端锚固在一组支架的分配梁外侧,另一端在另一组支架的分配梁外侧安装一张拉千斤顶7。Step 1. Bracket and pull rod setting: As shown in Figure 1 and Figure 2, a set of steel pipe supports 1 are erected on both sides of the V-shaped pier 10, and each set of steel pipe supports faces the side of the pier body and sets up multiple load-bearing beams 2 in the direction of the bridge. , set up multiple distribution beams 3 along the inclined direction of the pier body on the load-bearing beam, support the outer formwork 4 of the V-shaped pier on the distribution beam, and install the pier body reinforcement and inner formwork 5; install three layers of tie rods between the formwork on both sides of the pier body 6. At least 5 tie rods for each layer, among which the first layer of tie rods is set below 1/3 of the height of the V-shaped pier, the second layer of tie rods is set above 1/3 of the height of the V-shaped pier and below 2/3 of the height, and the third layer of tie rods Set above the 2/3 height of the V-shaped pier and below the height of the top, one end of each pull rod is anchored on the outside of the distribution beam of one group of supports, and the other end is installed on the outside of the distribution beam of another group of supports.
步骤二、如图3中所示,浇V型墩10墩身混凝土:墩身混凝土采用分层浇筑,每层配合拉杆6张拉,具体按以下步骤进行:Step 2. As shown in Figure 3, pour the V-shaped pier 10 pier body concrete: the pier body concrete is poured in layers, and each layer is equipped with 6 tension rods. The specific steps are as follows:
(1)张拉第一层拉杆,浇筑墩身混凝土至1/3墩身高度;(1) Stretch the tie rods of the first layer, and pour the concrete of the pier body to 1/3 of the height of the pier body;
(2)张拉第二层拉杆,浇筑墩身混凝土至2/3墩身高度;(2) Stretch the second layer of tie rods and pour the pier body concrete to 2/3 of the height of the pier body;
(2)张拉第三层拉杆,浇筑墩身混凝土至墩身顶标高。(2) Stretch the tie rods of the third layer, and pour the concrete of the pier body to the elevation of the top of the pier body.
上述每层拉杆张拉时,从中间向两侧对称张拉,张拉至拉杆最大张拉值的20%;When the above-mentioned tie rods of each layer are stretched, they are stretched symmetrically from the middle to both sides, and the tension reaches 20% of the maximum tension value of the tie rods;
步骤三、如图3中所示,浇筑墩顶0号块20混凝土:采用分层浇筑,每层配合拉杆6张拉,具体按以下步骤进行:Step 3. As shown in Figure 3, pour the concrete of No. 0 block 20 on the top of the pier: adopt layered pouring, each layer is equipped with 6 tension rods, and the specific steps are as follows:
(1)从下往上依次张拉3层拉杆,张拉至最大张拉值的40%,浇筑0号块底板混凝土;(1) Stretch the 3-layer tie rods sequentially from bottom to top to 40% of the maximum tension value, and pour the No. 0 bottom slab concrete;
(2)从下往上依次张拉3层拉杆,张拉至最大张拉值的60%,浇筑0号块横隔墙及腹板至1/2高度;(2) Stretch the 3-layer tie rods sequentially from bottom to top to 60% of the maximum tension value, and pour the No. 0 block transverse partition wall and web to 1/2 height;
(3)从下往上依次张拉3层拉杆,张拉至最大张拉值的80%,浇筑0号块剩余横隔墙及腹板混凝土;(3) Stretch the 3-layer tie rods sequentially from bottom to top to 80% of the maximum tension value, and pour the remaining transverse partition wall and web concrete of Block 0;
(4)从下往上依次张拉3层拉杆,张拉至最大张拉值的100%,浇筑0号块顶板混凝土;(4) Stretch 3 layers of tie rods sequentially from bottom to top to 100% of the maximum tension value, and pour No. 0 block roof concrete;
(5)0号块预应力施工完成后,拆除拉杆。(5) After the prestressing construction of No. 0 block is completed, remove the tie rods.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310506476.1A CN116556204A (en) | 2023-05-06 | 2023-05-06 | A construction method of V-shaped pier prestressed rods |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310506476.1A CN116556204A (en) | 2023-05-06 | 2023-05-06 | A construction method of V-shaped pier prestressed rods |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116556204A true CN116556204A (en) | 2023-08-08 |
Family
ID=87495885
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310506476.1A Pending CN116556204A (en) | 2023-05-06 | 2023-05-06 | A construction method of V-shaped pier prestressed rods |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116556204A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117230722A (en) * | 2023-09-28 | 2023-12-15 | 中交三公局第一工程有限公司 | A construction method of V-pier near water |
| CN117248454A (en) * | 2023-09-28 | 2023-12-19 | 中交三公局第一工程有限公司 | A large-volume bridge deck construction method |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2837507A1 (en) * | 2002-03-25 | 2003-09-26 | Jean Muller | Arched span concrete bridge has inverted delta supports and center sections with expansion joints between cantilevered ends |
| CN101481902A (en) * | 2009-01-21 | 2009-07-15 | 中铁三局集团有限公司 | V type pier inclined leg combined type support for continuous rigid frame bridge and layered cast-in-situ construction method |
| CN102888815A (en) * | 2012-10-16 | 2013-01-23 | 上海城建市政工程(集团)有限公司 | Pouring construction method of wide-angle V-shaped pier and 0# box girder |
| CN103388308A (en) * | 2013-08-06 | 2013-11-13 | 中铁八局集团市政工程有限公司 | Secondary temporary pull rod structure protective construction method in large-sized symmetrical oblique pier construction |
| CN115928606A (en) * | 2023-02-08 | 2023-04-07 | 中交路桥建设有限公司 | Construction method of high pier "Y" type cover beam and its construction bracket |
| CN116065492A (en) * | 2023-01-04 | 2023-05-05 | 中铁十九局集团有限公司 | A construction method of cable-stayed support system for Y-shaped bridge piers |
| CN219793664U (en) * | 2023-05-06 | 2023-10-03 | 中交路桥华东工程有限公司 | V-shaped pier construction bent frame system |
-
2023
- 2023-05-06 CN CN202310506476.1A patent/CN116556204A/en active Pending
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2837507A1 (en) * | 2002-03-25 | 2003-09-26 | Jean Muller | Arched span concrete bridge has inverted delta supports and center sections with expansion joints between cantilevered ends |
| CN101481902A (en) * | 2009-01-21 | 2009-07-15 | 中铁三局集团有限公司 | V type pier inclined leg combined type support for continuous rigid frame bridge and layered cast-in-situ construction method |
| CN102888815A (en) * | 2012-10-16 | 2013-01-23 | 上海城建市政工程(集团)有限公司 | Pouring construction method of wide-angle V-shaped pier and 0# box girder |
| CN103388308A (en) * | 2013-08-06 | 2013-11-13 | 中铁八局集团市政工程有限公司 | Secondary temporary pull rod structure protective construction method in large-sized symmetrical oblique pier construction |
| CN116065492A (en) * | 2023-01-04 | 2023-05-05 | 中铁十九局集团有限公司 | A construction method of cable-stayed support system for Y-shaped bridge piers |
| CN115928606A (en) * | 2023-02-08 | 2023-04-07 | 中交路桥建设有限公司 | Construction method of high pier "Y" type cover beam and its construction bracket |
| CN219793664U (en) * | 2023-05-06 | 2023-10-03 | 中交路桥华东工程有限公司 | V-shaped pier construction bent frame system |
Non-Patent Citations (1)
| Title |
|---|
| 王春;邱建军;李伟平;: "南翔桥V形墩施工方案关键技术研究", 中外公路, no. 06, 31 December 2014 (2014-12-31), pages 171 - 173 * |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117230722A (en) * | 2023-09-28 | 2023-12-15 | 中交三公局第一工程有限公司 | A construction method of V-pier near water |
| CN117248454A (en) * | 2023-09-28 | 2023-12-19 | 中交三公局第一工程有限公司 | A large-volume bridge deck construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110331668B (en) | Construction method of bidirectional inclined V-shaped bridge tower of cable-stayed bridge without back cables | |
| CN102888815B (en) | The pouring construction method of a kind of wide-angle V-type pier and 0# block case beam | |
| CN106702910A (en) | Main girder construction process for extradosed cable-stayed bridge with double towers and double cable planes | |
| CN110700105A (en) | Synchronous construction method for high pier column and tie beam and template used in same | |
| CN102691266B (en) | Construction Method of Superelevation Composite Support in Cast-in-place Section of Side Span of Bridge | |
| CN105672134A (en) | Through concrete-filled steel tube tied-arch bridge erection construction method | |
| CN114781026B (en) | A construction control method for a single-tilted-tower cable-stayed bridge | |
| CN104153284A (en) | Partial filling type steel box concrete continuous composite girder bridge and construction method thereof | |
| CN105821750B (en) | A kind of precast prestressed T plate and its application method | |
| CN116556204A (en) | A construction method of V-shaped pier prestressed rods | |
| CN211815595U (en) | Lower tower column tension and compression structure for cable tower | |
| CN115387234A (en) | Template system of lower beam of ultrahigh rhombic tower pier and construction method | |
| CN116065492A (en) | A construction method of cable-stayed support system for Y-shaped bridge piers | |
| CN104314013A (en) | Double suspension arm construction method of ultra-asymmetry combined beam | |
| CN101691813B (en) | Device and method for elevation synchronous compensation for super-high structure construction | |
| CN107905115A (en) | Through Steel pipe concrete truss combination beamss bridge construction method | |
| CN111877129B (en) | Arch ring construction method of continuous arch bridge | |
| CN111058381A (en) | Construction method for side-span cast-in-place section of continuous rigid frame bridge | |
| CN102561199A (en) | Method of vertical crack resistance of hogging moment tension zone of single-column concrete bridge pier | |
| CN114016434B (en) | Construction method of double-arch bridge with large-span space torsion cross section | |
| CN102747678B (en) | Unequal-height V-shaped bridge pier | |
| CN208039060U (en) | A kind of steel box arch rib bowstring arch bridge binder steel skeleton external wrapping concrete hangs die body system | |
| CN115387239A (en) | Formwork structure for side-span cast-in-place section and closure section of rigid frame bridge and construction method of formwork structure | |
| CN102518041B (en) | Construction method of support system for overhead continuous beam form-erecting falsework | |
| CN106758855B (en) | Arc-shaped pier cap construction arch support component and arc-shaped pier cap construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |