CN116537750A CN202310211463.1A CN202310211463A CN116537750A CN 116537750 A CN116537750 A CN 116537750A CN 202310211463 A CN202310211463 A CN 202310211463A CN 116537750 A CN116537750 A CN 116537750A
Authority
CN
China
Prior art keywords
water
sand
cation
control
production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202310211463.1A
Other languages
Chinese (zh)
Other versions
CN116537750B (en
Inventor
史浩贤
谢文卫
曾志国
于彦江
卢秋平
李星辰
李博
李晶
钟奕昕
张熙
王偲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Marine Geological Survey
Original Assignee
Guangzhou Marine Geological Survey
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Marine Geological Survey filed Critical Guangzhou Marine Geological Survey
Priority to CN202310211463.1A priority Critical patent/CN116537750B/en
Publication of CN116537750A publication Critical patent/CN116537750A/en
Application granted granted Critical
Publication of CN116537750B publication Critical patent/CN116537750B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E21—EARTH OR ROCK DRILLING; MINING
    • E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/02—Subsoil filtering
    • E—FIXED CONSTRUCTIONS
    • E21—EARTH OR ROCK DRILLING; MINING
    • E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E—FIXED CONSTRUCTIONS
    • E21—EARTH OR ROCK DRILLING; MINING
    • E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/02—Subsoil filtering
    • E21B43/08—Screens or liners
    • E21B43/086—Screens with preformed openings, e.g. slotted liners

Landscapes

  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Physics & Mathematics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Chemical & Material Sciences (AREA)
  • Dispersion Chemistry (AREA)
  • Separation Of Solids By Using Liquids Or Pneumatic Power (AREA)
  • Cyclones (AREA)

Abstract

本发明公开了一种水平井控水排砂方法,所述方法包括:对流入筛管中的流体,利用旋流沉砂和阳离子聚集的方式,以实现控水排砂的目的;所述流体包括水和泥砂。本发明创新性地对流入筛管中的水和泥砂,利用旋流沉砂和阳离子聚集的方式,将难度更大的水和砂进行分时段、分层位控制,达到了不同开采周期,对气、水、砂的控制,对边底水高度进行合理调节,实时调整水平井的产液剖面,实现中期限流、后期排砂的全寿命产水产砂控制,确保近井带产气通道的顺畅,最大化的挖掘产能,确保稳产周期。

The invention discloses a method for water control and sand removal in a horizontal well. The method includes: using swirl sand settling and cationic aggregation for the fluid flowing into the screen to achieve the purpose of water control and sand removal; the fluid Including water and mud and sand. The present invention innovatively controls the water and sand flowing into the screen by using the method of swirling sand settling and cation aggregation to control the more difficult water and sand by time intervals and layers, achieving different mining cycles, and Control of gas, water and sand, reasonably adjust the height of edge and bottom water, adjust the liquid production profile of horizontal wells in real time, realize the life-span water production and sand production control of mid-term flow limitation and later sand discharge, and ensure the gas production channels near the wellbore Smooth and maximized mining capacity to ensure a stable production cycle.

Description

一种水平井控水排砂方法A method for water control and sand removal in horizontal wells

技术领域technical field

本发明涉及涉及水合物及高含泥气井开采技术,具体涉及一种水平井控水排砂方法The invention relates to the exploitation technology of hydrate and high-mud gas wells, in particular to a method for water control and sand removal in horizontal wells

背景技术Background technique

在水合物及高含泥气井开采过程中极易因孔隙水运移造成地层出砂,甚至沟通含水层,造成短期内井筒巨量产水出砂,掩埋井筒。目前针对水合物开采、高含泥砂层气体资源开采,尚无相关控水排砂方法。现有油气藏及煤层气等领域的控水技术,大多用于解决油井开采过程面临的水淹水涌等复杂情况,开发出疏油控水装置,或者在煤层气等领域采用直接下入分段封隔器进行注水泥封堵水的方式。During the production of gas hydrate and high-mud gas wells, it is very easy to cause sand in the formation due to the migration of pore water, and even communicate with the aquifer, resulting in a large amount of water and sand in the wellbore in a short period of time, which will bury the wellbore. At present, there is no relevant water control and sand removal method for hydrate mining and gas resource mining in high-silt sand layers. Existing water control technologies in the fields of oil and gas reservoirs and coalbed methane are mostly used to solve complex situations such as water flooding and surges faced in the oil well production process, and oil-repelling and water-controlling devices have been developed, or in fields such as coalbed methane, direct drop-in analysis The section packer performs cement injection to seal the water.

采用控水装置或采用注水泥封堵水等方式,或利用油水性质差异控水产油,都具有一个相同的特点,即针对特定石油开采领域开展的控水设计,但是天然气水合物或其他含泥水气藏的开采不涉及油层,进入井筒的物质分别有地层泥砂、地层水、天然气水合物分解气,此外还有少量的施工残渣等。因此也就无法利用油-水的粘滞系数差异设计控水机构,现有的油藏控水方式在上述资源开发中不适用。Using water control devices or using cement injection to block water, or using oil-water properties to control water and oil production, all have the same feature, that is, water control design for specific oil exploration fields, but natural gas hydrate or other muddy water The exploitation of gas reservoirs does not involve oil layers, and the substances entering the wellbore include formation mud sand, formation water, natural gas hydrate decomposition gas, and a small amount of construction residues. Therefore, it is impossible to design the water control mechanism by utilizing the viscosity difference between oil and water, and the existing reservoir water control methods are not applicable to the above-mentioned resource development.

发明内容Contents of the invention

本发明的目的在于克服上述现有技术的不足,提供一种水平井控水排砂方法,以实现实现控水排砂的目的。The object of the present invention is to overcome the shortcomings of the above-mentioned prior art, and provide a method for water control and sand removal in horizontal wells, so as to realize the purpose of water control and sand removal.

为实现上述目的,本发明的技术方案是:For realizing the above object, technical scheme of the present invention is:

一种水平井控水排砂方法,所述方法包括:A method for controlling water and removing sand from a horizontal well, said method comprising:

对流入筛管中的流体,利用旋流沉砂和阳离子聚集的方式,以实现控水排砂的目的;所述流体包括水和泥砂。For the fluid flowing into the screen, the purpose of water control and sand removal is achieved by means of cyclone sand settling and positive ion aggregation; the fluid includes water and mud sand.

进一步地,所述旋流沉砂的方式包括:将流入筛管中的水和泥砂汇聚至一螺旋管。Further, the method of swirling sand settling includes: converging the water and mud sand flowing into the screen pipe into a spiral pipe.

进一步地,所述阳离子聚集的方式包括:在所述螺旋管的长度方向间隔布置有控水排砂装置,所述控水排砂装置包括两阳离子聚集板聚集板,两阳离子聚集板相对而设,当阳离子聚集板通电时,阴离子接地消散,阳离子则聚集在阳离子聚集板,以对流经螺旋管内的泥砂进行吸附。Further, the method of cation aggregation includes: arranging water and sand control and sand discharge devices at intervals in the length direction of the spiral tube, the water and sand control and sand discharge device includes two cation gathering plates, and the two cation gathering plates are arranged opposite to each other. , when the cation gathering plate is energized, the anions are grounded and dissipated, and the cations are gathered in the cation gathering plate to adsorb the mud and sand flowing through the spiral tube.

进一步地,开采初期,所述阳离子聚集板不通电,进入筛管的气、水、泥砂则通过筛管的生产口进入井筒,产出至地面收集。Furthermore, at the initial stage of mining, the cation gathering plate is not powered on, and the gas, water, and mud entering the screen enter the wellbore through the production port of the screen, and the output is collected on the ground.

进一步地,开采中期,当需要要进行控水排砂作业时,所述阳离子聚集板通电,流经螺旋管内的泥砂被吸附,并逐渐聚集,则水在螺旋管内的流通通道会逐渐减小,水量随之降低。Further, in the mid-mining stage, when water control and sand removal operations are required, the cation gathering plate is energized, and the mud sand flowing through the spiral tube is absorbed and gradually aggregated, and the water circulation channel in the spiral tube will gradually decrease. The water volume decreases accordingly.

进一步地,当水量降低后,在螺旋管内内的含泥砂液体流速降低,泥砂有充分时间发生沉淀反应,沉淀后的泥砂也会降低螺旋沉淀器的流通空间,使得产水流压力增加,实现控水目的。Furthermore, when the water volume decreases, the flow rate of the mud-sand-containing liquid in the spiral tube decreases, and the mud-sand has sufficient time for sedimentation reaction, and the settled mud-sand will also reduce the circulation space of the spiral settler, increasing the pressure of the produced water flow and realizing water control. Purpose.

进一步地,在开采后期,停止阳离子聚集板的供电或降低供电功率,则阳离子聚集板对泥砂失去或减少吸附力,聚集在阳离子聚集板上的泥砂开始分解,并随水流运移,螺旋管的产能通道逐渐释放,水流增加,螺旋管内的液体流速增加,泥砂也被随着携带进入井筒,含水剖面将井筒周围的气藏驱替至井筒。Furthermore, in the later stage of mining, if the power supply of the cation gathering plate is stopped or the power supply is reduced, the cation gathering plate will lose or reduce the adsorption force on the mud and sand, and the mud and sand gathered on the cation gathering plate will start to decompose and migrate with the water flow. The productivity channel is gradually released, the water flow increases, the liquid flow rate in the spiral tube increases, and the mud and sand are also carried into the wellbore, and the water-bearing profile displaces the gas reservoir around the wellbore into the wellbore.

本发明与现有技术相比,其有益效果在于:Compared with the prior art, the present invention has the beneficial effects of:

本发明创新性地对流入筛管中的水和泥砂,利用旋流沉砂和阳离子聚集的方式,将难度更大的水和砂进行分时段、分层位控制,达到了不同开采周期,对气、水、砂的控制,对边底水高度进行合理调节,实时调整水平井的产液剖面,实现中期限流、后期排砂的全寿命产水产砂控制,确保近井带产气通道的顺畅,最大化的挖掘产能,确保稳产周期。The present invention innovatively controls the water and sand flowing into the screen by using the method of swirling sand settling and cationic aggregation to control the more difficult water and sand by time intervals and layers, achieving different mining cycles, and Control of gas, water and sand, reasonably adjust the height of edge and bottom water, adjust the liquid production profile of horizontal wells in real time, realize the life-span water production and sand production control of mid-term flow limitation and later sand discharge, and ensure the gas production channels near the wellbore Smooth and maximized mining capacity to ensure a stable production cycle.

附图说明Description of drawings

图1为本发明实施例提供的水平井控水排砂方法的操作使用示意图;Figure 1 is a schematic diagram of the operation and use of the horizontal well water control and sand removal method provided by the embodiment of the present invention;

图2为图1中的局部放大示意图;Fig. 2 is the partially enlarged schematic diagram in Fig. 1;

图中:1、筛管;1-1、生产口;2、螺旋管;3、阳离子聚集板;100、地层;200、套管。In the figure: 1, screen pipe; 1-1, production port; 2, spiral pipe; 3, cation gathering plate; 100, formation; 200, casing.

具体实施方式Detailed ways

实施例:Example:

下面结合附图和实施例对本发明的技术方案做进一步的说明。The technical solutions of the present invention will be further described below in conjunction with the accompanying drawings and embodiments.

在进行高含泥水气藏、水合物藏的开发时,地层100中的套管200提供稳定的井筒结构,在常规情况下井筒结构为水平井沿水平方向延伸,由于水合物、气体等分解的水会携带地层产出水和砂进入近井筒地带,受到孔隙结构和排砂能力的限制,泥砂在微孔隙中架桥堆积后,造成水堵-砂堵的复合堵塞,导致原有通道气相渗透率大幅降低,致使产能下降;此外在水合物分解过程中,进入井筒的主要物质包括:甲烷气体、分解水和原有孔隙水、地层泥砂颗粒,以这三种物质为主。其中,气体运移阻力较小,对渗透率要求较低,但随着开采进行,不同水平段面临的产水速率出现差异,如果不进行控水,井筒周围的孔隙结构将在短期内水淹,微观孔隙结构的水锁效应明显,会影响气体的产出。During the development of high muddy water gas reservoirs and hydrate reservoirs, the casing 200 in the formation 100 provides a stable wellbore structure. Under normal circumstances, the wellbore structure is a horizontal well extending along the horizontal direction. Due to the decomposition of hydrates and gases, etc. Water will carry formation water and sand into the near-wellbore area, limited by the pore structure and sand discharge capacity, after the mud and sand bridge and accumulate in the micropores, it will cause a composite blockage of water plugging and sand plugging, resulting in gas phase penetration of the original channel In addition, during the hydrate decomposition process, the main substances entering the wellbore include: methane gas, decomposed water and original pore water, and formation mud and sand particles, mainly these three substances. Among them, the resistance to gas migration is small, and the requirements for permeability are low. However, as the mining progresses, the water production rate faced by different horizontal sections will be different. If the water is not controlled, the pore structure around the wellbore will be flooded in a short time. , the water locking effect of the microscopic pore structure is obvious, which will affect the gas output.

因此,在不同开采期,应该结合边底水脊进问题,进行控水排砂作业,从而调整产液剖面均衡,延长稳产周期。Therefore, in different mining periods, water control and sand discharge operations should be carried out in combination with the problem of edge-bottom water ridge ingress, so as to adjust the balance of the liquid production profile and prolong the stable production period.

由于粘土主要由硅酸盐、碳酸盐岩等组成,其颗粒整体呈负电性,主要由:①粘土晶格内同晶置换所产生,部分硅氧四面体中Si(四价)被铝(三价)取代,部分铝氧八面体中,铝(三价)被镁、铁(二价)取代,从而产生剩余负电荷。②还可以由海底一些腐殖质所含的羧基产生离解,解离出H+而产生负电荷,羧基上的H+解离出来后,羧基就变成负电的离子团。③随着pH值改变,碱性环境有利于H+离解产生更多负电荷,而目已知的水合物储层孔隙水pH值一般在7~9之间,为弱碱性,有利于粘土表现出较强的负电荷性,即阴离子电性。粘土在外电场作用下容易被正电荷吸引聚集,而储层水则不呈现正负电荷吸附特性,因此,本发明将利用水和粘土的密度、电荷性差异,实现控水排砂的目的。基于此,本发明创新性地对流入筛管1中的水和泥砂,利用旋流沉砂和阳离子聚集的方式,将难度更大的水和砂进行分时段、分层位控制,达到了不同开采周期,对气、水、砂的控制,对边底水高度进行合理调节,实时调整水平井的产液剖面,实现中期限流、后期排砂的全寿命产水产砂控制,确保近井带产气通道的顺畅,最大化的挖掘产能,确保稳产周期。筛管1是套设在套管200中。Since clay is mainly composed of silicate, carbonate rock, etc., its particles are negatively charged as a whole, which is mainly caused by: ① Isomorphic replacement in the clay lattice, Si (tetravalent) in some silicon-oxygen tetrahedrons is replaced by aluminum ( Trivalent) substitution, in part of the aluminum oxygen octahedron, aluminum (trivalent) is replaced by magnesium, iron (divalent), resulting in a residual negative charge. ② It can also be dissociated from the carboxyl group contained in some humus on the seabed, and the H+ is dissociated to generate a negative charge. After the H+ on the carboxyl group is dissociated, the carboxyl group becomes a negatively charged ion group. ③As the pH value changes, the alkaline environment is conducive to the dissociation of H+ to generate more negative charges. However, the pH value of the pore water of known hydrate reservoirs is generally between 7 and 9, which is weakly alkaline and is conducive to the performance of clay. A strong negative charge, that is, anion charge. Clay is easily attracted and aggregated by positive charges under the action of an external electric field, while reservoir water does not exhibit positive and negative charge adsorption characteristics. Therefore, the present invention will use the differences in density and charge between water and clay to achieve the purpose of water control and sand discharge. Based on this, the present invention innovatively controls the water and sand flowing into the screen tube 1 by means of swirling sand settling and positive ion aggregation to control the more difficult water and sand by time intervals and layers, achieving different Production cycle, control of gas, water and sand, reasonable adjustment of the height of edge and bottom water, real-time adjustment of the liquid production profile of the horizontal well, and the control of water production and sand production in the middle period and later sand discharge in the whole life, ensuring the near-well zone The smoothness of the gas production channel maximizes the mining capacity and ensures a stable production cycle. The screen pipe 1 is sheathed in the casing pipe 200 .

在一具体实施例中,如图1-2所示,上述旋流沉砂的方式包括:将流入筛管1中的水和泥砂汇聚至一螺旋管2,通过螺旋的方式,对进入该螺旋管2的水、砂进行分选,由于泥砂密度>水,因此在流速较小的情况下,泥水通过该螺旋管2后,会在曲率较大区域形成沉砂,而产出水。图1中所示的箭头为流体的流动方向,流体包括气、水、砂。In a specific embodiment, as shown in Fig. 1-2, the method of swirling sand settling includes: converging the water and mud and sand flowing into the screen pipe 1 into a spiral pipe 2, through the spiral way, The water and sand in the pipe 2 are sorted. Since the density of mud and sand is greater than water, when the flow velocity is small, after the muddy water passes through the spiral pipe 2, sand settling will be formed in the area with a large curvature, and water will be produced. The arrows shown in Figure 1 indicate the flow direction of the fluid, which includes gas, water, and sand.

在一具体实施例中,上述的阳离子聚集的方式包括:在该螺旋管2的长度方向间隔布置有控水排砂装置,该控水排砂装置包括两阳离子聚集板聚集板3,两阳离子聚集板3相对而设,两阳离子聚集板3为一块金属,当阳离子聚集板3通电时,阴离子接地消散,阳离子则聚集在阳离子聚集板3,以对流经螺旋管2内的泥砂进行吸附。如此,而当阳离子聚集板不释放阳离子(不通电)后,泥砂失去附着力,统一排出井筒,螺旋管2内的流速也会增大,从而使螺旋管2内部沉淀泥砂排出,实现泥砂缓排或全排的目的。In a specific embodiment, the above-mentioned cation aggregation method includes: a water control and sand discharge device is arranged at intervals in the length direction of the spiral tube 2, and the water control and sand discharge device includes two cation accumulation plates 3, and the two cation accumulation The plates 3 are opposite to each other, and the two cation gathering plates 3 are a piece of metal. When the cation gathering plates 3 are electrified, the anions are grounded and dissipated, and the cations are gathered in the cation gathering plates 3 to adsorb the mud and sand flowing through the spiral tube 2 . In this way, when the cation collecting plate does not release cations (no electricity), the mud and sand lose their adhesion and are discharged uniformly from the wellbore, and the flow rate in the spiral tube 2 will also increase, so that the sedimented mud and sand inside the spiral tube 2 will be discharged to realize the slow discharge of mud and sand or whole row of purposes.

故而,在水合物开采的不同时期,通过控制阳离子聚集板通电与否即可以实现泥砂缓排或全排的目的。Therefore, in different stages of hydrate mining, the purpose of slow or full discharge of mud and sand can be achieved by controlling whether the cation gathering plate is powered on or not.

开采初期,阳离子聚集板3不通电,进入筛管1的气、水、泥砂则通过筛管1的生产口1-1进入井筒,产出至地面收集。In the early stage of mining, the cation gathering plate 3 is not powered on, and the gas, water, and mud entering the screen 1 enter the wellbore through the production port 1-1 of the screen 1, and the output is collected on the ground.

开采中期,根据生产数据判断不同层段的产水、出砂情况,部分层段边底水脊进严重,出现水淹的风险,运移至井筒附近的泥砂开始增多,需要进行控水排砂作业,阳离子聚集板3通电,流经螺旋管2内的泥砂被吸附,并逐渐聚集,则水在螺旋管2内的流通通道会逐渐减小,水量随之降低;当水量降低后,在螺旋管2内内的含泥砂液体流速降低,泥砂有充分时间发生沉淀反应,沉淀后的泥砂也会降低螺旋管2的流通空间,使得产水流压力增加,实现控水目的。In the middle stage of mining, the water production and sand production of different layers are judged according to the production data. In some layers, the edge and bottom water ridges are serious, and there is a risk of water flooding. The mud and sand migrating to the vicinity of the wellbore begins to increase, and water control and sand removal are required. operation, the cationic gathering plate 3 is electrified, and the mud and sand flowing through the spiral tube 2 are absorbed and gradually gathered, then the circulation channel of the water in the spiral tube 2 will gradually decrease, and the water volume will decrease accordingly; The flow rate of the mud-sand-containing liquid in the pipe 2 is reduced, and the mud-sand has sufficient time for sedimentation reaction, and the sedimented mud-sand will also reduce the circulation space of the spiral pipe 2, so that the pressure of the produced water flow increases, and the purpose of water control is realized.

在开采后期,停止阳离子聚集板3的供电或降低供电功率,则阳离子聚集板3对泥砂失去或减少吸附力,聚集在阳离子聚集板3上的泥砂开始分解,并随水流运移,螺旋管2的产能通道逐渐释放,水流增加,螺旋管2内的液体流速增加,泥砂也被随着携带进入井筒,含水剖面将井筒周围的气藏驱替至井筒。In the later stage of mining, if the power supply of the cation gathering plate 3 is stopped or the power supply power is reduced, the cation gathering plate 3 loses or reduces its adsorption force on the mud and sand, and the mud and sand gathered on the cation gathering plate 3 begin to decompose and migrate with the water flow, and the spiral pipe 2 The productivity channels in the well are gradually released, the water flow increases, the liquid velocity in the spiral tube 2 increases, and the mud and sand are also carried into the wellbore, and the water-bearing profile displaces the gas reservoir around the wellbore into the wellbore.

上述实施例只是为了说明本发明的技术构思及特点,其目的是在于让本领域内的普通技术人员能够了解本发明的内容并据以实施,并不能以此限制本发明的保护范围。凡是根据本发明内容的实质所做出的等效的变化或修饰,都应涵盖在本发明的保护范围内。The above-mentioned embodiments are only to illustrate the technical concept and characteristics of the present invention, and its purpose is to enable those of ordinary skill in the art to understand the content of the present invention and implement it accordingly, and cannot limit the protection scope of the present invention. All equivalent changes or modifications made according to the essence of the content of the present invention shall fall within the protection scope of the present invention.

Claims (7)

1. A horizontal well water control sand removal method, the method comprising:
the fluid flowing into the sieve tube is treated by cyclone sand setting and cation aggregation to realize the purpose of water control and sand discharge; the fluid includes water and silt.
2. The horizontal well water control sand removal method as set forth in claim 1, wherein the rotational flow sand setting mode comprises: the water and silt flowing into the screen pipe are collected into a spiral pipe.
3. The horizontal well control water sand removal method as set forth in claim 2, wherein said means for cation aggregation comprises: the water control sand discharging device is arranged at intervals in the length direction of the spiral pipe and comprises two cation collecting plate collecting plates, the two cation collecting plates are arranged oppositely, anions are grounded and dissipated when the cation collecting plates are electrified, and cations are collected on the cation collecting plates so as to adsorb mud sand flowing into the spiral pipe.
4. The horizontal well control water sand removal method as set forth in claim 3 wherein said cationic accumulation plate is not energized at the beginning of production and water and silt entering the screen are then introduced into the well bore through the production port of the screen and produced to surface for collection.
5. The horizontal well water control and sand removal method as set forth in claim 3 or 4, wherein the cation aggregation plate is energized when water control and sand removal operation is required during the production period, mud sand flowing through the spiral pipe is adsorbed and gradually aggregated, and the circulation passage of water in the spiral pipe is gradually reduced, and the water amount is reduced.
6. The method for water control and sand removal of horizontal well as set forth in claim 5, wherein when the water quantity is reduced, the flow rate of the liquid containing the muddy sand in the spiral pipe is reduced, the muddy sand has sufficient time for precipitation reaction, and the precipitated muddy sand also reduces the circulation space of the spiral precipitator, so that the pressure of the produced water is increased, and the purpose of water control is achieved.
7. The horizontal well control water discharging method as claimed in claim 3 or 4, wherein in the later period of production, the power supply of the cation aggregation plate is stopped or the power supply power is reduced, so that the cation aggregation plate loses or reduces the adsorption force on the muddy sand, the muddy sand aggregated on the cation aggregation plate starts to decompose and moves along with the water flow, the capacity channel of the spiral pipe is gradually released, the water flow is increased, the liquid flow rate in the spiral pipe is increased, the muddy sand is also carried into the well bore along with the water flow, and the water-containing profile drives the gas reservoir around the well bore to the well bore.
CN202310211463.1A 2023-03-07 2023-03-07 Horizontal well water control and sand discharge method Active CN116537750B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310211463.1A CN116537750B (en) 2023-03-07 2023-03-07 Horizontal well water control and sand discharge method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310211463.1A CN116537750B (en) 2023-03-07 2023-03-07 Horizontal well water control and sand discharge method

Publications (2)

Publication Number Publication Date
CN116537750A true CN116537750A (en) 2023-08-04
CN116537750B CN116537750B (en) 2025-08-15

Family

ID=87445889

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310211463.1A Active CN116537750B (en) 2023-03-07 2023-03-07 Horizontal well water control and sand discharge method

Country Status (1)

Country Link
CN (1) CN116537750B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1542040A (en) * 1977-06-21 1979-03-14 Akae Kikai Kogyo Co Wet-type sand classifier
US20100193418A1 (en) * 2009-01-29 2010-08-05 David Belasco Storm water treatment system, modular drain vault, tube cleaning tool and methods
CN202531037U (en) * 2012-03-09 2012-11-14 中国石油天然气股份有限公司 Segmented Completion Strings for Horizontal Wells in Tight Gas Reservoirs with Bottom Water
CN106639990A (en) * 2016-11-14 2017-05-10 北京国泰通源技术有限公司 Intelligent sand-prevention and water-controlling sieve tube
CN207507065U (en) * 2017-10-27 2018-06-19 江西大忙人实业有限公司 A kind of desanding filter of refined instant kudzu vine powder process equipment
US20190106973A1 (en) * 2017-10-05 2019-04-11 Saudi Arabian Oil Company Downhole centrifugal separation and removal of sand from wells using progressing cavity pump
CN113529691A (en) * 2021-07-06 2021-10-22 江苏科技大学 Device for solidifying river sludge on site and construction method
CN215595554U (en) * 2021-06-07 2022-01-21 中国石油大学(北京) Sand-carrying screen at toe end of horizontal well
CN116378609A (en) * 2023-03-07 2023-07-04 广州海洋地质调查局 A water control and sand removal system for horizontal wells

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1542040A (en) * 1977-06-21 1979-03-14 Akae Kikai Kogyo Co Wet-type sand classifier
US20100193418A1 (en) * 2009-01-29 2010-08-05 David Belasco Storm water treatment system, modular drain vault, tube cleaning tool and methods
CN202531037U (en) * 2012-03-09 2012-11-14 中国石油天然气股份有限公司 Segmented Completion Strings for Horizontal Wells in Tight Gas Reservoirs with Bottom Water
CN106639990A (en) * 2016-11-14 2017-05-10 北京国泰通源技术有限公司 Intelligent sand-prevention and water-controlling sieve tube
US20190106973A1 (en) * 2017-10-05 2019-04-11 Saudi Arabian Oil Company Downhole centrifugal separation and removal of sand from wells using progressing cavity pump
CN207507065U (en) * 2017-10-27 2018-06-19 江西大忙人实业有限公司 A kind of desanding filter of refined instant kudzu vine powder process equipment
CN215595554U (en) * 2021-06-07 2022-01-21 中国石油大学(北京) Sand-carrying screen at toe end of horizontal well
CN113529691A (en) * 2021-07-06 2021-10-22 江苏科技大学 Device for solidifying river sludge on site and construction method
CN116378609A (en) * 2023-03-07 2023-07-04 广州海洋地质调查局 A water control and sand removal system for horizontal wells

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
周福建;熊春明;宗贻平;杨贤友;张守良;孙凌云;李江涛;汪君臣;吴学安;: "纤维复合无筛管防细粉砂技术在涩北气田的应用", 石油勘探与开发, no. 01, 28 February 2006 (2006-02-28), pages 116 - 119 *
王晓莉;聂申健;刘昌虎;王鹰;: "油井复合化学防砂技术在文明寨油田的应用", 广州化工, no. 04, 15 April 2010 (2010-04-15), pages 211 - 213 *

Also Published As

Publication number Publication date
CN116537750B (en) 2025-08-15

Similar Documents

Publication Publication Date Title
US5964289A (en) Multiple zone well completion method and apparatus
CN102094586B (en) How to use sand flushing device for horizontal well
CN111950175B (en) A method for automatic optimization of fracturing fluid blowout working system after oil well fracturing
CN104895537B (en) Water Injection Production Method Applicable to Fracture-cavity Carbonate Condensate Gas Reservoirs
CN104314540B (en) A method for preventing steam channeling in steam injection reservoir
CN103967473B (en) A kind of apparatus and method of exploiting ocean natural gas hydrates well desanding
CN112664164B (en) High-water-content later-stage multi-stage stable long-acting sand prevention process method for sandstone oil reservoir
CN107489412B (en) Submarine shallow natural gas hydrate underground in-situ real-time separation backfill system
CN207315343U (en) A kind of sea-bottom shallow gas hydrates underground separates backfill system in real time on the spot
CN108952630A (en) A method of utilizing ultrahigh-power ultrasonic de-plugging anatonosis
CN105443095B (en) A kind of single channel reservoir model of heavy crude heat extraction well to be onstructed and application
CN110905469A (en) Sandstone thermal storage geothermal tail water efficient recharge method based on simulation
CN116378609A (en) A water control and sand removal system for horizontal wells
Wang et al. Ternary wetting modification technology: A remedy for water blockage and prevention sand in unconsolidated sandstone gas reservoirs
CN109879465B (en) An underground filtration-sedimentation device for loose sandstone thermal storage geothermal production wells
CN105134151B (en) Hot nitrogen energization Viscosity Reduction And Stimulation
CN116537750B (en) Horizontal well water control and sand discharge method
CN203145870U (en) Energy-saving solid control system
CN105257248A (en) A negative pressure back-vomiting and plugging removal method for sewage reinjection wells in low-permeability oilfields
Rezaei Abiz et al. A simulation study of nanoparticle transport in porous media: effects of salinity and reservoir parameters
CN111608584A (en) A construction method of downhole filter chamber suitable for weakly consolidated sandstone thermal storage
CN120373167A (en) Water injection well water injection pressure rising prediction and control method
CN114370253B (en) Water-blocking and oil-increasing tool for stabilizing pressure during gravel packing and stratum blocking removal
CN115961926B (en) A method for integrating tight reservoir reconstruction with injection, flooding and production
CN110174291B (en) A device for collecting water samples from underground mine seepage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant