CN116537159A - Pipeline reinforcement anti-sedimentation method adjacent to foundation pit - Google Patents

Pipeline reinforcement anti-sedimentation method adjacent to foundation pit Download PDF

Info

Publication number
CN116537159A
CN116537159A CN202310453540.4A CN202310453540A CN116537159A CN 116537159 A CN116537159 A CN 116537159A CN 202310453540 A CN202310453540 A CN 202310453540A CN 116537159 A CN116537159 A CN 116537159A
Authority
CN
China
Prior art keywords
grouting
reinforced
foundation pit
pipeline
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310453540.4A
Other languages
Chinese (zh)
Inventor
何均
吴祥飞
荣国强
江帅
徐银鹏
杜江宇
陈明洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Zhejiang Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Zhejiang Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202310453540.4A priority Critical patent/CN116537159A/en
Publication of CN116537159A publication Critical patent/CN116537159A/en
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C09DYES; PAINTS; POLISHES; NATURAL RESINS; ADHESIVES; COMPOSITIONS NOT OTHERWISE PROVIDED FOR; APPLICATIONS OF MATERIALS NOT OTHERWISE PROVIDED FOR
    • C09KMATERIALS FOR MISCELLANEOUS APPLICATIONS, NOT PROVIDED FOR ELSEWHERE
    • C09K17/00Soil-conditioning materials or soil-stabilising materials
    • C09K17/02Soil-conditioning materials or soil-stabilising materials containing inorganic compounds only
    • C09K17/12Water-soluble silicates, e.g. waterglass
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • CCHEMISTRY; METALLURGY
    • C09DYES; PAINTS; POLISHES; NATURAL RESINS; ADHESIVES; COMPOSITIONS NOT OTHERWISE PROVIDED FOR; APPLICATIONS OF MATERIALS NOT OTHERWISE PROVIDED FOR
    • C09KMATERIALS FOR MISCELLANEOUS APPLICATIONS, NOT PROVIDED FOR ELSEWHERE
    • C09K2103/00Civil engineering use

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Soil Sciences (AREA)
  • Agronomy & Crop Science (AREA)
  • Organic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Inorganic Chemistry (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a pipeline reinforcement and sedimentation prevention method adjacent to a foundation pit, wherein a side, close to the foundation pit, of a pipeline is reinforced by adopting a back-type grouting method, a plurality of reinforcement supports are formed by grouting reinforcement from the top of a pipeline of a section to be reinforced, and the depth from the ground surface to the bottom of a reinforcement area is not lower than the depth of the foundation pit. The back grouting method is reinforced by a back grouting method of a grouting pipeline, and grout is injected into a stratum in the modes of extrusion, penetration and splitting, so that the strength and elastic deformation modulus of soil are improved. Grouting adopts the mode of adopting sodium silicate and grout to consolidate the soil body below the pipeline, can effectively reduce the pipeline subsidence, guarantees foundation ditch construction smoothly simultaneously, and is effectual, and the influence is little, with low costs. The invention solves the problem that the pipeline is easy to subside in the construction process of the newly-built foundation pit when the newly-built foundation pit is adjacent to the pipeline.

Description

临近基坑的管道加固防沉降方法Pipeline reinforcement and anti-subsidence method near foundation pit

技术领域technical field

本发明涉及建筑施工技术领域,具体涉及一种临近基坑的管道加固防沉降方法。The invention relates to the technical field of building construction, in particular to a method for reinforcing and preventing settlement of pipelines adjacent to foundation pits.

背景技术Background technique

目前,市区施工常常面临新建基坑临近管道的工况。新建基坑在开挖过程中,管道往往可能出现沉降现象,沉降过大则容易造成管道的破坏。At present, construction in urban areas often faces the situation that the new foundation pit is adjacent to the pipeline. During the excavation of a new foundation pit, the pipeline may often settle, and if the settlement is too large, it will easily cause damage to the pipeline.

公开于该背景技术部分的信息仅仅旨在增加对本发明的总体背景的理解,而不应当被视为承认或以任何形式暗示该信息构成已为本领域一般技术人员所公知的现有技术。The information disclosed in this Background section is only for enhancing the understanding of the general background of the present invention and should not be taken as an acknowledgment or any form of suggestion that the information constitutes the prior art that is already known to those skilled in the art.

发明内容Contents of the invention

为克服现有技术所存在的缺陷,现提供一种临近基坑的管道加固防沉降方法,以解决新建基坑临近管道,在新建基坑施工过程中,管道容易发生沉降现象的问题。In order to overcome the defects of the existing technology, a method for strengthening and preventing settlement of pipelines adjacent to foundation pits is provided to solve the problem that pipelines are prone to subsidence during the construction process of new foundation pits adjacent to pipelines.

为实现上述目的,提供一种临近基坑的管道加固防沉降方法,包括以下步骤:In order to achieve the above purpose, a pipeline reinforcement anti-settlement method near a foundation pit is provided, which includes the following steps:

确定管道的临近基坑的待加固段的位置;Determine the position of the section to be reinforced near the foundation pit of the pipeline;

查明所述待加固段所处的土层的分布范围、含水量、土的颗粒级配、地下水和孔隙率等物理力学性质指标;Find out the physical and mechanical property indicators such as the distribution range, water content, particle gradation of soil, groundwater and porosity of the soil layer where the section to be reinforced is located;

于所述待加固段的下方的土体中注浆固结形成多个加固支撑体,所述加固支撑体的上部包覆于所述待加固段,所述加固支撑体的上方的覆盖土的厚度大于2m,所述注浆的浆液包括水泥、水玻璃和水,所述浆液的水灰比为1:1,所述水与所述水玻璃的质量比为4:1,在注浆固结形成所述加固支撑体时,将所述待加固段所处的土层分为多个注浆段,自上而下注浆施工每个注浆段,在施工每个注浆段时采用后退式注浆法进行注浆,所述加固支撑体的底部标高低于所述临近基坑的坑底标高。Grouting and consolidating in the soil below the section to be reinforced to form a plurality of reinforcement supports, the upper part of the reinforcement supports covers the section to be reinforced, and the covering soil above the reinforcement supports The thickness is greater than 2m. The grout for grouting includes cement, water glass and water. The water-cement ratio of the grout is 1:1, and the mass ratio of the water to the water glass is 4:1. When forming the reinforced support body, the soil layer where the section to be reinforced is located is divided into multiple grouting sections, and each grouting section is grouted from top to bottom, and each grouting section is constructed using Grouting is carried out by a retreating grouting method, and the bottom elevation of the reinforced support body is lower than the bottom elevation of the adjacent foundation pit.

进一步的,多个所述加固支撑体沿所述待加固段的长度方向间隔设置。Further, a plurality of reinforcing supports are arranged at intervals along the length direction of the section to be reinforced.

进一步的,相邻的两个所述加固支撑体的之间的间距为2.5m。Further, the distance between two adjacent reinforcement supports is 2.5m.

进一步的,在注浆过程中,当所述土层的土体为砂性土时,注浆压力为0.2~0.5MPa。Further, during the grouting process, when the soil body of the soil layer is sandy soil, the grouting pressure is 0.2-0.5 MPa.

进一步的,在注浆过程中,当所述土层的土体为粘性土时,注浆压力为0.2~0.3MPa。Further, during the grouting process, when the soil body of the soil layer is cohesive soil, the grouting pressure is 0.2-0.3 MPa.

本发明的有益效果在于,本发明的临近基坑的管道加固防沉降方法,于管道靠近基坑一侧采用后退式注浆法加固,从待加固段的管顶处开始注浆加固形成多个加固支撑体,地表至加固区域底部深度为不低于基坑深度。后退式注浆法即通过注浆管道后退式注浆法加固,利用浆液以挤压、渗透、劈裂的形式注入地层,从而提高土体的强度和弹性变形模量。注浆采用采用水玻璃和水泥浆的方式对管道下方土体进行加固,既能有效减少管道沉降,同时保证基坑顺利施工,效果好,影响小,成本低。The beneficial effect of the present invention is that, in the pipeline reinforcement and anti-settlement method near the foundation pit of the present invention, the side of the pipeline close to the foundation pit is reinforced by the backward grouting method, and the grouting reinforcement is started from the top of the pipe in the section to be reinforced to form multiple Reinforce the support body, the depth from the ground surface to the bottom of the reinforced area shall not be lower than the depth of the foundation pit. The retreating grouting method is reinforced by the retreating grouting method of the grouting pipe, and the grout is injected into the formation in the form of extrusion, penetration, and splitting, so as to improve the strength and elastic deformation modulus of the soil. The grouting uses water glass and cement slurry to reinforce the soil below the pipeline, which can effectively reduce the settlement of the pipeline and ensure the smooth construction of the foundation pit. The effect is good, the impact is small, and the cost is low.

附图说明Description of drawings

通过阅读参照以下附图所作的对非限制性实施例所作的详细描述,本申请的其它特征、目的和优点将会变得更明显:Other characteristics, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:

图1为本发明实施例的临近基坑的管道加固的示意图。Fig. 1 is a schematic diagram of pipeline reinforcement near a foundation pit according to an embodiment of the present invention.

具体实施方式Detailed ways

下面结合附图和实施例对本申请作进一步的详细说明。可以理解的是,此处所描述的具体实施例仅仅用于解释相关发明,而非对该发明的限定。另外还需要说明的是,为了便于描述,附图中仅示出了与发明相关的部分。The application will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain related inventions, rather than to limit the invention. It should also be noted that, for ease of description, only parts related to the invention are shown in the drawings.

需要说明的是,在不冲突的情况下,本申请中的实施例及实施例中的特征可以相互组合。下面将参考附图并结合实施例来详细说明本申请。It should be noted that, in the case of no conflict, the embodiments in the present application and the features in the embodiments can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and embodiments.

参照图1所示,本发明提供了一种临近基坑的管道加固防沉降方法,包括以下步骤:Referring to Fig. 1, the present invention provides a pipeline reinforcement anti-settlement method near a foundation pit, comprising the following steps:

S1:确定管道的临近基坑A的待加固段1的位置。S1: Determine the position of the section 1 to be reinforced near the foundation pit A of the pipeline.

通过勘察管道的临近基坑的待加固段的位置,确定待加固段的长度。Determine the length of the section to be reinforced by surveying the position of the section to be reinforced near the foundation pit of the pipeline.

S2:查明待加固段1所处的土层的分布范围、含水量、土的颗粒级配、地下水和孔隙率等物理力学性质指标。S2: Find out the physical and mechanical property indicators such as the distribution range, water content, particle gradation of soil, groundwater and porosity of the soil layer where the section 1 to be reinforced is located.

确定注浆加固方案前,查明待加固段1所处的土层的分布范围、含水量、土的颗粒级配、地下水和孔隙率等土体的物理力学性质指标。同时,必须通过调查究,确定注浆的有效范围,注浆材料的选择、初凝时间、注浆量和压力、注浆孔布置和注浆顺序等。Before determining the grouting reinforcement scheme, find out the physical and mechanical properties of the soil such as the distribution range, water content, soil particle gradation, groundwater, and porosity of the soil layer to be reinforced. At the same time, the effective range of grouting, the selection of grouting materials, the initial setting time, the amount and pressure of grouting, the arrangement of grouting holes and the sequence of grouting must be determined through investigation and research.

S3:于待加固段1的下方的土体中注浆固结形成多个加固支撑体2,加固支撑体2的上部包覆于待加固段1,加固支撑体2的上方的覆盖土的厚度大于2m,注浆的浆液包括水泥、水玻璃和水,浆液的水灰比为1:1,水与水玻璃的质量比为4:1,在注浆固结形成加固支撑体2时,将待加固段1所处的土层分为多个注浆段,自上而下注浆施工每个注浆段,在施工每个注浆段时采用后退式注浆法进行注浆,加固支撑体2的底部标高低于临近基坑A的坑底标高。S3: Grouting and consolidation in the soil below the section to be reinforced 1 to form a plurality of reinforcement supports 2, the upper part of the reinforcement supports 2 is covered on the section 1 to be reinforced, and the thickness of the covering soil above the reinforcement support 2 If it is larger than 2m, the grout for grouting includes cement, water glass and water. The water-cement ratio of the grout is 1:1, and the mass ratio of water to water glass is 4:1. When the grouting is consolidated to form a reinforced support body 2, the The soil layer where the section to be reinforced 1 is located is divided into multiple grouting sections, each grouting section is grouted from top to bottom, and the retreat grouting method is used for grouting during the construction of each grouting section to reinforce the support The bottom elevation of the body 2 is lower than that of the adjacent foundation pit A.

在本实施例中,在待加固段的长度确认后,可基于待加固段的长度确定加固支撑体的数量。In this embodiment, after the length of the section to be reinforced is confirmed, the number of reinforcement supports may be determined based on the length of the section to be reinforced.

作为一种较佳的实施方式,多个加固支撑体2沿待加固段1的长度方向间隔设置。进一步的,相邻的两个加固支撑体2的之间的间距为2.5m。As a preferred embodiment, a plurality of reinforcement supports 2 are arranged at intervals along the length direction of the section 1 to be reinforced. Further, the distance between two adjacent reinforcement supports 2 is 2.5m.

在注浆过程中,当土层的土体为砂性土时,注浆压力为0.2~0.5MPa。During the grouting process, when the soil body of the soil layer is sandy soil, the grouting pressure is 0.2-0.5MPa.

在注浆过程中,当土层的土体为粘性土时,注浆压力为0.2~0.3MPa。During the grouting process, when the soil layer is cohesive soil, the grouting pressure is 0.2-0.3MPa.

注浆工艺和有效范围应根据工程不同要求,必须充分满足防渗堵漏,提高土体强度和模量、充填空隙及托换等目的加以确定。注浆点的覆盖土应大于2m。The grouting process and effective range should be determined according to the different requirements of the project, and must fully meet the purposes of anti-seepage and plugging, improving soil strength and modulus, filling voids and underpinning. The covering soil at the grouting point should be greater than 2m.

选定浆液及其配比的设计,必须考虑注浆的目的、地质情况、地基土的孔隙大小、地下水的状态,在满足所需目的范围内选定最佳配比。The design of the selected grout and its ratio must consider the purpose of grouting, geological conditions, pore size of the foundation soil, and the state of groundwater, and select the best ratio within the scope of meeting the required purpose.

注浆法处理软土的浆液材料可选用以水泥为主剂的悬浊液。The grout material for grouting treatment of soft soil can be a suspension with cement as the main agent.

用作提高土体强度的注浆液可选用以水泥为主剂的悬浊液。The grouting fluid used to improve the strength of the soil can be a suspension with cement as the main agent.

初凝时间必须根据地基土质条件和注浆目的决定。在砂土地基注浆中,一般使用的浆液初凝时间为5~20分钟,在粘性土劈裂注浆时,一般浆液初凝时间为1~2小时。The initial setting time must be determined according to the soil condition of the foundation and the purpose of grouting. In sandy foundation grouting, the initial setting time of the grout generally used is 5 to 20 minutes, and in the splitting grouting of cohesive soil, the general grouting initial setting time is 1 to 2 hours.

注浆量取决于地基土性质和浆液的渗透性等因素。在进行大规模注浆施工过程中,宜在施工现场进行试验性注浆以决定注浆量,一般粘性土中的浆液注入率为15~20%。The amount of grouting depends on factors such as the nature of the foundation soil and the permeability of the grout. In the process of large-scale grouting construction, it is advisable to carry out experimental grouting on the construction site to determine the amount of grouting. Generally, the grouting rate in cohesive soil is 15-20%.

注浆压力主要取决于浆液材料的稠度和注浆深度及土层性质,一般情况下,砂性土为0.2~0.5MPa,粘性土为0.2~0.3MPa。The grouting pressure mainly depends on the consistency of the grout material, the grouting depth and the properties of the soil layer. Generally, the sandy soil is 0.2-0.5MPa, and the clayey soil is 0.2-0.3MPa.

注浆孔的布置原则应能使被加固土体在平面和深度内连成一个整体。The layout principle of the grouting hole should be able to make the soil to be reinforced integrated into a whole in plane and depth.

注浆顺序必须采用适合于地基土质条件、现场环境及注浆目的进行,一般采用间隔跳排跳孔的方式进行,以防串浆,提高注浆孔内浆液的强度与约束性。对有地下动水流的特殊情况,应考虑在动水流下的迁移效应,应自水头高的一端注浆。The grouting sequence must be carried out in accordance with the foundation soil conditions, site environment and grouting purpose. Generally, it is carried out by skipping rows and holes at intervals to prevent grouting and improve the strength and restraint of the grout in the grouting holes. For the special case of underground dynamic water flow, the migration effect under dynamic water flow should be considered, and the grout should be injected from the end with high water head.

注浆时应采用先外围,后内部的施工方式。注浆范围以外有边界约束条件时,也可采用自内侧开始顺次往外侧注浆方法。When grouting, the construction method of the periphery first and then the interior should be adopted. When there are boundary constraints outside the grouting range, the method of grouting from the inside to the outside in sequence can also be used.

当采用水泥浆进行注浆时,宜采用标号不低于425号的普通硅酸盐水泥。When cement slurry is used for grouting, it is advisable to use ordinary Portland cement with a grade of not less than 425.

注浆使用的原材料及制成的浆体应符合下列要求:The raw materials used for grouting and the prepared slurry shall meet the following requirements:

制成的浆体应能在设计要求的时间内凝固并且有一定强度,其本身的防渗性和耐久性应能满足设计要求。The prepared slurry should be able to solidify within the time required by the design and have a certain strength, and its own impermeability and durability should meet the design requirements.

浆体在凝固后其体积不应有较大的收缩率,一般应小于3‰的体量。After solidification, the volume of the slurry should not have a large shrinkage rate, generally less than 3‰.

所制成的浆液在一小时内不发生析水现象。The prepared slurry does not undergo water separation within one hour.

注浆法施工的步骤如下:The steps of grouting construction are as follows:

孔位偏差不得大于6cm,垂直度偏差应小于1%,当注浆孔有设计角度时,倾角偏差不大于5°。The deviation of the hole position shall not be greater than 6cm, and the deviation of the verticality shall be less than 1%. When the grouting hole has a design angle, the deviation of the inclination angle shall not be greater than 5°.

注浆根据设计要求配制浆液,并按设计的注浆压力、注浆流量、单位米的注浆量、提管速率、等参数控制注浆。Grouting Prepare the grout according to the design requirements, and control the grouting according to the designed grouting pressure, grouting flow rate, grouting volume per meter, pipe lifting speed, and other parameters.

注浆结束后,对注浆管进行清洗。After the grouting is finished, clean the grouting pipe.

注浆开始前的准备工作包括机械器具、仪表、管路、注浆材料、水、电等检查及必要的试验。The preparatory work before grouting includes inspection of mechanical appliances, instruments, pipelines, grouting materials, water, electricity, etc. and necessary tests.

插管过程的操作控制及要求:Operational control and requirements of the intubation process:

插管前先配置好注浆管,一般采用1~5m的1寸镀锌管或直径大于30mm的钢管,所使用的注浆管必须事先进行检查管内是否有杂物堵塞,丝扣是否完好,注浆管底部堵头是否灵活,花管上胶皮松紧是否合适。Configure the grouting pipe before intubation. Generally, a 1-inch galvanized pipe with a diameter of 1-5m or a steel pipe with a diameter greater than 30mm is used. The grouting pipe used must be checked in advance whether there is any debris in the pipe and whether the thread is intact Whether the plug at the bottom of the grouting pipe is flexible, and whether the rubber on the flower pipe is tight or not.

采用机械设备钻孔、钻头直径宜选用Φ56合金钻头,插管后,应注意做好孔口密封工作。When using mechanical equipment to drill holes, the diameter of the drill bit should be Φ56 alloy drill bit. After intubation, care should be taken to seal the hole well.

采用震动器插管及使用死堵头,插管深度应超过设计孔深10~20cm,震动插管孔深到位后,应立即上拔注浆管10~20cm,使堵头脱落。Use a vibrator for intubation and use a dead plug. The depth of the intubation should exceed the design hole depth by 10-20cm. After the depth of the intubation hole is in place, the grouting pipe should be pulled up by 10-20cm immediately to make the plug fall off.

插管后应做好管口的封口工作,防止杂物掉入管内堵塞注浆管。After intubation, the mouth of the nozzle should be sealed to prevent debris from falling into the pipe and blocking the grouting pipe.

注浆过程的操作控制及要求:Operation control and requirements of grouting process:

注浆主要材料为水泥与水玻璃,分别配置浆液等比例同时进行注浆,其中水灰比为1:1,水:水玻璃为4:1。The main materials for grouting are cement and water glass, and grouting is performed at the same time with equal proportions of grout. The water-cement ratio is 1:1, and the water: water glass is 4:1.

注浆流量一般为7~10L/min,对充填型灌浆,流量可适当加快但不宜大于20L/min。The grouting flow rate is generally 7-10L/min. For filling type grouting, the flow rate can be appropriately accelerated but should not be greater than 20L/min.

为确保注浆段均匀吃浆,注浆时应根据每米设计注浆量上拔注浆管,每次上拔高度为通过注浆管末端出浆时为330mm,通过50cm长花管出浆时为500mm。In order to ensure that the grouting section eats grout evenly, the grouting pipe should be pulled up according to the designed grouting amount per meter, and the height of each pull-up is 330mm when the grout is discharged through the end of the grouting pipe, and the grout is discharged through a 50cm long flower pipe When it is 500mm.

注浆过程中,应对地表和附近建(构)筑物进行变形监测。During the grouting process, deformation monitoring of the ground surface and nearby buildings (structures) should be carried out.

注浆过程中,当发现注浆压力突然下降、流量突然增大时,应立即停注,检查是否冒浆、跑浆,当出现冒浆跑浆时,应采取下列措施:During the grouting process, when it is found that the grouting pressure suddenly drops and the flow rate suddenly increases, the injection should be stopped immediately to check whether the grout is leaking or running out. When the grouting and running out occur, the following measures should be taken:

a.停止注浆进行封堵;a. Stop grouting for plugging;

b.减小压力、加浓浆液或采用间歇注浆;b. Reduce the pressure, thicken the slurry or use intermittent grouting;

c.采用水玻璃、水泥浆进行交替注浆,使注入浆液速凝。c. Use water glass and cement slurry for alternate grouting to make the injected grout quick-set.

注浆中断时间较长或双液注浆中断时,应及时冲洗泵和管路。When the grouting is interrupted for a long time or the double-liquid grouting is interrupted, the pump and pipeline should be flushed in time.

采用交替注浆时,应根据设计严格掌握注浆交替量和交替频率。When alternate grouting is used, the alternate amount and frequency of grouting should be strictly controlled according to the design.

注浆过程中要经常对比相邻注浆孔流量、压力和注入量,分析注浆中存在的问题,并及时解决。During the grouting process, the flow rate, pressure and injection volume of adjacent grouting holes should be compared frequently to analyze the problems existing in the grouting and solve them in time.

达到注浆结束标准后,双液注浆应按管路占浆量定时压水。注浆结束后,应暂时封闭孔口阀,及时冲洗泵和管路,待孔内压释放后,拔出注浆管,全孔注浆结束应用注浆液或水泥砂浆封孔。After the grouting end standard is reached, the double liquid grouting should press water regularly according to the amount of grout in the pipeline. After the grouting is completed, the orifice valve should be closed temporarily, and the pump and pipeline should be flushed in time. After the internal pressure of the hole is released, the grouting pipe should be pulled out. After the grouting of the whole hole, the hole should be sealed with grouting liquid or cement mortar.

施工过程中,做好详细的施工记录、分析和整理工作。During the construction process, do a good job of detailed construction records, analysis and arrangement.

注浆施工顺序控制Grouting construction sequence control

注浆施工应按分序加密的原则。多排孔注浆时,在排序上应遵循先边排,后中排的原则;由多排孔组成的帷幕,宜先进行上游排的注浆,后进行下游排的注浆;在同一排上的注浆孔,应采用间隔跳跃式或三个次序注浆。The grouting construction should follow the principle of sequential densification. When grouting multiple rows of holes, the principle of rowing at the side first and then the middle row should be followed in order; for curtains composed of multiple rows of holes, it is advisable to perform grouting on the upstream row first, and then on the downstream row; The grouting holes on the top should be grouted in interval jumping or three sequential grouting.

同一次序的孔可以同时施工,不同次序的孔,应按照规定的次序进行。Holes in the same sequence can be constructed at the same time, and holes in different sequences should be carried out in accordance with the specified sequence.

已有建筑物进行地基加固时,应采用大间隔跳跃式的施工顺序。When the foundation of the existing building is reinforced, the construction sequence with large intervals and jumps should be adopted.

(4)注浆施工质量控制(4) Quality control of grouting construction

加固注浆的检查方法宜采用:开挖、钻探、触探、标贯、载荷试验、沉降观测、取样强度检查等,对重要工程应做载荷试验。加固体外形轮廓可采用触探法检验,加固体强度宜取试块做无限抗压试验,也可采用触探法或标贯法试验评价。Inspection methods for reinforcement grouting should be adopted: excavation, drilling, penetrating, standard penetration, load test, settlement observation, sampling strength inspection, etc. Load test should be done for important projects. The contour of the reinforced body can be inspected by the penetrating sounding method, and the strength of the reinforced body should be tested by taking a test block for infinite compression, or it can be evaluated by the penetrating sounding method or the standard penetration method.

检查孔应用所注浆液或水泥浆封孔。The inspection hole shall be sealed with grout or cement slurry.

本发明的临近基坑的管道加固防沉降方法,于管道靠近基坑一侧采用后退式注浆法加固,从待加固段的管顶处开始注浆加固形成多个加固支撑体,地表至加固区域底部深度为不低于基坑深度。后退式注浆法即通过注浆管道后退式注浆法加固,利用浆液以挤压、渗透、劈裂的形式注入地层,从而提高土体的强度和弹性变形模量。注浆采用采用水玻璃和水泥浆的方式对管道下方土体进行加固,既能有效减少管道沉降,同时保证基坑顺利施工,效果好,影响小,成本低。The pipeline reinforcement and anti-subsidence method near the foundation pit of the present invention adopts a retreating grouting method on the side of the pipeline close to the foundation pit, and starts grouting from the top of the pipe to be reinforced to form a plurality of reinforcement supports, from the surface to the reinforcement. The depth of the bottom of the area shall not be lower than the depth of the foundation pit. The retreating grouting method is reinforced by the retreating grouting method of the grouting pipe, and the grout is injected into the formation in the form of extrusion, penetration, and splitting, so as to improve the strength and elastic deformation modulus of the soil. The grouting uses water glass and cement slurry to reinforce the soil below the pipeline, which can effectively reduce the settlement of the pipeline and ensure the smooth construction of the foundation pit. The effect is good, the impact is small, and the cost is low.

以上描述仅为本申请的较佳实施例以及对所运用技术原理的说明。本领域技术人员应当理解,本申请中所涉及的发明范围,并不限于上述技术特征的特定组合而成的技术方案,同时也应涵盖在不脱离所述发明构思的情况下,由上述技术特征或其等同特征进行任意组合而形成的其它技术方案。例如上述特征与本申请中公开的(但不限于)具有类似功能的技术特征进行互相替换而形成的技术方案。The above description is only a preferred embodiment of the present application and an illustration of the applied technical principle. Those skilled in the art should understand that the scope of the invention involved in this application is not limited to the technical solution formed by the specific combination of the above-mentioned technical features, but should also cover the technical solution formed by the above-mentioned technical features without departing from the inventive concept. Other technical solutions formed by any combination of or equivalent features thereof. For example, a technical solution formed by replacing the above-mentioned features with technical features with similar functions disclosed in (but not limited to) this application.

Claims (5)

1. The pipeline reinforcement sedimentation prevention method adjacent to the foundation pit is characterized by comprising the following steps of:
determining the position of a section of the pipeline adjacent to the foundation pit to be reinforced;
ascertaining physical and mechanical property indexes such as distribution range, water content, grain composition of soil, groundwater and porosity of a soil layer where the section to be reinforced is positioned;
grouting consolidation is performed in soil below the section to be reinforced to form a plurality of reinforced supports, the upper portions of the reinforced supports are coated on the section to be reinforced, the thickness of the covering soil above the reinforced supports is greater than 2m, grouting slurry comprises cement, water glass and water, and the water-cement ratio of the slurry is 1:1, the mass ratio of the water to the water glass is 4:1, when grouting consolidation is carried out to form the reinforced support body, dividing a soil layer where the section to be reinforced is positioned into a plurality of grouting sections, grouting each grouting section from top to bottom, grouting by adopting a back grouting method when constructing each grouting section, and enabling the bottom elevation of the reinforced support body to be lower than the pit bottom elevation of the adjacent foundation pit.
2. The method of claim 1, wherein a plurality of the reinforcing supports are disposed at intervals along the length of the section to be reinforced.
3. A method of reinforcing a pipe against sedimentation adjacent to a foundation pit as set forth in claim 2, wherein the spacing between adjacent ones of the reinforcing supports is 2.5m.
4. The method for reinforcing and preventing sedimentation of a pipe adjacent to a foundation pit according to claim 1, wherein in the grouting process, when the soil body of the soil layer is sandy soil, the grouting pressure is 0.2-0.5 MPa.
5. The method for reinforcing and preventing sedimentation of a pipe adjacent to a foundation pit according to claim 4, wherein in grouting, when the soil body of the soil layer is clay, grouting pressure is 0.2-0.3 MPa.
CN202310453540.4A 2023-04-21 2023-04-21 Pipeline reinforcement anti-sedimentation method adjacent to foundation pit Pending CN116537159A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310453540.4A CN116537159A (en) 2023-04-21 2023-04-21 Pipeline reinforcement anti-sedimentation method adjacent to foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310453540.4A CN116537159A (en) 2023-04-21 2023-04-21 Pipeline reinforcement anti-sedimentation method adjacent to foundation pit

Publications (1)

Publication Number Publication Date
CN116537159A true CN116537159A (en) 2023-08-04

Family

ID=87449846

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310453540.4A Pending CN116537159A (en) 2023-04-21 2023-04-21 Pipeline reinforcement anti-sedimentation method adjacent to foundation pit

Country Status (1)

Country Link
CN (1) CN116537159A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118880852A (en) * 2024-09-09 2024-11-01 中国建筑第八工程局有限公司 Backward segmental grouting method for strengthening soil in sewage pipes
CN120174871A (en) * 2025-03-05 2025-06-20 北京市市政工程设计研究总院有限公司 Construction method of deep foundation pit structure near pressure pipeline and deep foundation pit structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120811A (en) * 2016-08-24 2016-11-16 中天建设集团有限公司天津分公司 A kind of foundation ditch periphery distortion preventing and deviation rectification construction method
CN109162722A (en) * 2018-10-11 2019-01-08 中国石油大学(华东) It is applicable in the advanced compacting grouting and reinforcing method in loose weak stratum of shallow-depth-excavation tunnel
CN111734448A (en) * 2020-06-22 2020-10-02 上海隧道工程有限公司 Structure and method for reinforcing vertical channel between underground space structure and shield tunnel
CN113389555A (en) * 2021-07-30 2021-09-14 中铁十二局集团有限公司 Construction protection method suitable for high-risk pipeline penetrating under underground excavation tunnel
CN115573725A (en) * 2022-09-28 2023-01-06 中铁二十五局集团有限公司盾构工程分公司 Stratum reinforcing method for comprehensive pipe gallery tunnel to penetrate existing subway shield

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120811A (en) * 2016-08-24 2016-11-16 中天建设集团有限公司天津分公司 A kind of foundation ditch periphery distortion preventing and deviation rectification construction method
CN109162722A (en) * 2018-10-11 2019-01-08 中国石油大学(华东) It is applicable in the advanced compacting grouting and reinforcing method in loose weak stratum of shallow-depth-excavation tunnel
CN111734448A (en) * 2020-06-22 2020-10-02 上海隧道工程有限公司 Structure and method for reinforcing vertical channel between underground space structure and shield tunnel
CN113389555A (en) * 2021-07-30 2021-09-14 中铁十二局集团有限公司 Construction protection method suitable for high-risk pipeline penetrating under underground excavation tunnel
CN115573725A (en) * 2022-09-28 2023-01-06 中铁二十五局集团有限公司盾构工程分公司 Stratum reinforcing method for comprehensive pipe gallery tunnel to penetrate existing subway shield

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118880852A (en) * 2024-09-09 2024-11-01 中国建筑第八工程局有限公司 Backward segmental grouting method for strengthening soil in sewage pipes
CN120174871A (en) * 2025-03-05 2025-06-20 北京市市政工程设计研究总院有限公司 Construction method of deep foundation pit structure near pressure pipeline and deep foundation pit structure

Similar Documents

Publication Publication Date Title
CN104453913B (en) A kind of Shaft Stopes front pre-grouting method
CN101638987B (en) Tunnel construction method for crossing high-pressure water-enriched fracture zone with curtain grouting and grout stopping wall
CN1193141C (en) Combined grouting construction process of reinforcing foundation
CN104846810B (en) Self-circulating posterior grouting bored pile construction method
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN107513995A (en) A kind of bridge struction pile post grouting construction method
CN114108609B (en) A construction method for multi-stage and segmental precise filling deep piles in goaf
CN104452793B (en) Foam concrete process overhead road of city Bridge Foundation place discards sewage conduct construction technology
CN116537159A (en) Pipeline reinforcement anti-sedimentation method adjacent to foundation pit
CN102296621B (en) Construction method of ground sectional water-stop curtain
CN107245989A (en) Bear the tunnel structure and its construction technology of external water pressure in height
CN107339108A (en) The layer of sand location subway pipe shed construction method of underground water enrichment
CN110469332B (en) Advanced support consolidation method for tunnel penetrating through debris flow accumulation body
CN114183170A (en) Karst grouting construction method
CN104947723A (en) Presplitting grouting method for pile bottom of rock-socketed grouting pile
CN108571330A (en) Method for treating leakage water of post-cast strip of subway bottom plate
CN204570696U (en) Viaduct foundation place discards sewage conduct construction system
CN102433887A (en) Construction method of sand replacement type mixing pile diaphragm wall
CN207277295U (en) Bear the tunnel structure of external water pressure in height
CN206052770U (en) A kind of use cast-in-situ bored pile combines the retaining wall of compaction grouting
CN205224019U (en) Stake of reinforcing bar fiber cement soil
CN112523272B (en) Anti-floating blind ditch for strongly weathered rock stratum and construction method thereof
CN109183800A (en) Preparation grouting system construction technology
CN115369785A (en) Existing pile foundation bearing capacity improving method
CN115977057A (en) Pile end post-grouting reinforcement structure of stratum foundation pile with overlying gap and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20230804