CN116446385A - Karst filling-free filling pile structure and construction method thereof - Google Patents

Karst filling-free filling pile structure and construction method thereof Download PDF

Info

Publication number
CN116446385A
CN116446385A CN202310152380.XA CN202310152380A CN116446385A CN 116446385 A CN116446385 A CN 116446385A CN 202310152380 A CN202310152380 A CN 202310152380A CN 116446385 A CN116446385 A CN 116446385A
Authority
CN
China
Prior art keywords
pile
reinforcement cage
karst
additional
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310152380.XA
Other languages
Chinese (zh)
Inventor
张志伟
卜良桃
侯琦
卜志宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Hongli Civil Engineering Testing Co ltd
Hunan University Design Institute Co ltd
Hunan University
Hunan No6 Engineering Co Ltd
Original Assignee
Hunan Hongli Civil Engineering Testing Co ltd
Hunan University Design Institute Co ltd
Hunan University
Hunan No6 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Hongli Civil Engineering Testing Co ltd, Hunan University Design Institute Co ltd, Hunan University, Hunan No6 Engineering Co Ltd filed Critical Hunan Hongli Civil Engineering Testing Co ltd
Priority to CN202310152380.XA priority Critical patent/CN116446385A/en
Publication of CN116446385A publication Critical patent/CN116446385A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional [3D] extent, e.g. lattice girders

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Architecture (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种岩溶无填充灌注桩结构及其施工方法,该岩溶无填充灌注桩,包括置于桩孔内的设计钢筋笼,所述设计钢筋笼上增设贯穿岩溶分布段的附加钢筋笼,所述附加钢筋笼外全覆盖镀锌钢丝网和密目尼龙网,所述附加钢筋笼与所述设计钢筋笼之间存在环形充填间隙;所述设计钢筋笼由多根桩身主筋、桩身螺旋箍筋、桩身加劲环构成;所述附加钢筋笼由多根附加纵向钢筋、附加螺旋箍筋、附加加劲环构成。本申请其成桩工艺技术简单,具有安全可靠性、质量可控性、经济合理性与现场可实施性等显著性特点,能保障施工现场的生产安全、提高灌注桩的质量控制,降低工程成本与增加工程效益等。

The invention discloses a karst unfilled cast-in-situ pile structure and a construction method thereof. The karst unfilled cast-in-place pile includes a designed steel reinforcement cage placed in the pile hole, and an additional steel reinforcement cage penetrating through the karst distribution section is added to the designed steel reinforcement cage , the outside of the additional reinforcement cage is fully covered with galvanized steel wire mesh and dense mesh nylon mesh, and there is an annular filling gap between the additional reinforcement cage and the design reinforcement cage; The pile body is composed of spiral stirrups and pile body stiffening rings; the additional reinforcement cage is composed of multiple additional longitudinal reinforcements, additional spiral stirrups, and additional stiffening rings. The pile-forming technology of this application is simple, with remarkable features such as safety and reliability, quality controllability, economic rationality and on-site implementability, etc., which can ensure production safety on the construction site, improve quality control of cast-in-place piles, and reduce engineering costs And increase engineering benefits, etc.

Description

一种岩溶无填充灌注桩结构及其施工方法A karst non-filled cast-in-place pile structure and its construction method

技术领域technical field

本发明属于灌注桩领域,尤其涉及一种岩溶无填充灌注桩结构及其施工方法。The invention belongs to the field of cast-in-place piles, in particular to a karst unfilled cast-in-place pile structure and a construction method thereof.

背景技术Background technique

岩溶也称喀斯特(karst),是指水对可溶性岩石(碳酸盐岩、石膏、岩盐等)进行以化学溶蚀作用为主,流水的冲蚀、潜蚀和崩塌等机械作用为辅的地质作用,经岩溶作用而形成的地貌,在桂、黔和滇东部地区分布最广,湘西、鄂西、川东、鲁、晋等地分布也较广。岩溶的发育和形成多数对建筑物的地基或场地造成极大影响,因此,在岩溶地区进行工程建设的难点在于施工和稳定性评价,因此必须对岩溶地貌进行研究,预测和解决因岩溶地貌引起各种工程地质问题。Karst, also known as karst, refers to the geological action of water on soluble rocks (carbonate rock, gypsum, rock salt, etc.), mainly by chemical dissolution, supplemented by mechanical actions such as erosion, latent erosion and collapse of flowing water. , the landforms formed by karstification are most widely distributed in Guangxi, Guizhou and eastern Yunnan, and are also widely distributed in western Hunan, western Hubei, eastern Sichuan, Shandong, and Jin. Most of the development and formation of karst have a great impact on the foundation or site of buildings. Therefore, the difficulty of engineering construction in karst areas lies in construction and stability evaluation. Therefore, it is necessary to study karst landforms, predict and solve the problems caused by karst landforms. Various engineering geological problems.

在岩溶发育区的地质情况复杂多变,常见的岩溶地貌形态主要有:溶沟、石芽;岩溶漏斗;落水洞;干谷;峰从、峰林;溶烛洼地及坡立谷;溶洞;伏流、暗河。岩溶地区从事各种工程建设面临的地质问题:岩溶地基不稳定;岩溶地表塌陷;岩溶地面变形;岩溶地面开裂;岩溶渗漏突水;水资源流失等。The geological conditions in the karst development area are complex and changeable, and the common karst landforms mainly include: karst ditch, stone bud; karst funnel; sinkhole; dry valley; ,underground river. Geological problems faced by various engineering constructions in karst areas: karst foundation instability; karst surface subsidence; karst ground deformation; karst ground cracking; karst seepage water inrush;

目前,岩溶地区的桩基施工,通常采用桩基成孔设备成孔,如旋挖钻机、冲击钻机。桩基施工过程中遇到斜岩,常发生钻孔偏斜、卡钻、漏浆及塌孔等问题,为确保成桩质量等主要从两方面着手:一方面通过调整设计方案,优化或尽量规避岩溶不良地质,在一定程度上降低施工风险,如基础结构形式、结构形式等优化方式;另一方面在施工方面,通过现有技术措施处理为:根据地质情况不同,常采用诸如钢护筒加泥浆护壁、预注浆、抛填片石或回填低强度等级混凝土等措施,再机械成孔与成桩等。At present, pile foundation construction in karst areas usually uses pile foundation hole-forming equipment to form holes, such as rotary drilling rigs and impact drilling rigs. In the process of pile foundation construction, when inclined rock is encountered, problems such as drilling deviation, drill sticking, slurry leakage and hole collapse often occur. In order to ensure the quality of the pile, we mainly start from two aspects: on the one hand, by adjusting the design plan, optimizing or trying to Avoid karst bad geology and reduce construction risks to a certain extent, such as optimization methods such as foundation structure form and structure form; Add mud retaining wall, pre-grouting, throwing rubble or backfilling with low-strength concrete, etc., and then mechanically form holes and piles.

但以上方式存在诸如工程进度推进缓慢、注浆材料或混凝土的消耗、浪费严重,且回填混凝土初凝时间难以控制,影响机械成孔效益及磨损设备等不足,还存在泥浆护壁渗透岩溶可能造成岩溶上部已经完成桩孔的岩土体扩散流失形成塌孔等,导致桩孔周围土体整体塌陷,影响工作面的生产安全,以及周围已成桩的质量问题等。However, the above methods have shortcomings such as slow progress of the project, serious consumption and waste of grouting materials or concrete, and difficulty in controlling the initial setting time of backfill concrete, which affects the efficiency of mechanical pore formation and wear equipment, and there is also the possibility of karst caused by the seepage of mud retaining wall The rock and soil mass in the upper part of the pile hole that has been completed diffuses and loses to form a collapse hole, which leads to the overall collapse of the soil around the pile hole, affecting the production safety of the working face, and the quality problems of the surrounding piles.

发明内容Contents of the invention

本发明的主要目的在于提供一种岩溶无填充灌注桩结构及其施工方法,旨在有效地解决现有技术中岩溶等不良地质影响灌注桩成桩质量,及存在成本较高、施工效率较低等问题。。The main purpose of the present invention is to provide a karst non-filled cast-in-place pile structure and its construction method, aiming to effectively solve the problem of poor geological conditions such as karst affecting the quality of cast-in-place piles in the prior art, as well as high cost and low construction efficiency. And other issues. .

为此,本发明实施例一方面提供的岩溶无填充灌注桩结构,包括设于桩孔的设计钢筋笼以及增设在所述设计钢筋笼外并贯穿盖桩孔岩溶分布段的附加钢筋笼;For this reason, the karst non-filled cast-in-situ pile structure provided by the embodiment of the present invention includes a designed reinforcement cage arranged in the pile hole and an additional reinforcement cage installed outside the designed reinforcement cage and running through the karst distribution section of the pile hole;

所述设计钢筋笼由多根桩身主筋、桩身螺旋箍筋、桩身加劲环构成;The design reinforcement cage is composed of multiple pile body main reinforcements, pile body spiral stirrups, and pile body stiffening rings;

所述附加钢筋笼由多根附加纵向钢筋、附加螺旋箍筋、附加加劲环构成。The additional reinforcement cage is composed of multiple additional longitudinal reinforcements, additional spiral stirrups, and additional stiffening rings.

所述附加钢筋笼与所述设计钢筋笼之间存在环形充填间隙;There is an annular filling gap between the additional reinforcement cage and the design reinforcement cage;

所述附加钢筋笼外全覆盖有镀锌钢丝网和密目尼龙网;或者是,The outside of the additional reinforcement cage is fully covered with galvanized steel wire mesh and dense mesh nylon mesh; or,

所述附加钢筋笼外套设镀锌钢护筒。A galvanized steel casing is arranged outside the additional reinforcement cage.

具体的,所述附加钢筋笼中的多根附加纵向钢筋两端弯折后锚固在所述设计钢筋笼内,所述附加纵向钢筋在弯折处与端头采用附加加劲环焊接固定。Specifically, the two ends of multiple additional longitudinal reinforcements in the additional reinforcement cage are bent and anchored in the design reinforcement cage, and the additional longitudinal reinforcements are welded and fixed to the ends at the bends with additional stiffening rings.

具体的,所述镀锌钢丝网采用类似螺旋箍筋的方式重叠搭接设置,并用铁丝以梅花状方式固定在所述附加钢筋笼上,所述密目尼龙网全覆盖在镀锌钢丝网的外侧,并采用铁丝以一定间距牢靠固定。Specifically, the galvanized steel wire mesh is overlapped and overlapped in a manner similar to spiral stirrups, and is fixed on the additional reinforcement cage in a quincunx-shaped manner with iron wires, and the dense mesh nylon mesh is completely covered on the galvanized steel wire mesh. The outer side is firmly fixed with iron wire at a certain distance.

具体的,所述镀锌钢护筒由镀锌钢板现场焊接而成,首先以全覆盖的方式包裹在附加钢筋笼,再焊接成圆钢管,镀锌钢板的可靠性、耐腐蚀性好与镀层韧性强,可作为桩身的材料。Specifically, the galvanized steel casing is welded on-site by galvanized steel sheets, first wrapped in an additional reinforcement cage in a fully covered manner, and then welded into a round steel pipe. The reliability and corrosion resistance of galvanized steel sheets are as good as those of the coating Strong toughness, can be used as the material of the pile body.

具体的,所述附加纵向钢筋的直径,在有水环境一般为灌注桩的设计桩径(5)的基础上增加100mm,在无水环境则增加70mm。Specifically, the diameter of the additional longitudinal steel bar is increased by 100 mm on the basis of the designed pile diameter (5) of the cast-in-place pile in a water environment, and by 70 mm in an anhydrous environment.

具体的,所述桩孔的的直径比灌注桩的设计桩径大,岩溶分布段及以上部位的桩孔直径为长钢护筒内径,且不小于设计桩径+2倍[设计钢筋笼保护层厚度(35mm(无水环境)/50mm(有水环境)+附加钢筋笼保护层厚度(35mm(无水环境)/50mm(有水环境)];在岩溶分布段以下部位的桩孔直径,基于长钢护筒跟进与否确认,若不跟进长钢护筒,则桩孔直径一般为设计桩径,反之则同岩溶分布段及以上部位的桩孔直径。具体的,所述镀锌钢护筒外增设的螺旋加强箍筋以螺旋形式焊接方式固定。Specifically, the diameter of the pile hole is larger than the designed pile diameter of the cast-in-situ pile, and the diameter of the pile hole in the karst distribution section and above is the inner diameter of the long steel casing, and is not less than the design pile diameter + 2 times [design reinforced cage protection Layer thickness (35mm (without water environment)/50mm (with water environment) + additional steel cage protective layer thickness (35mm (without water environment)/50mm (with water environment)]; the pile hole diameter below the karst distribution section, Based on whether the long steel casing is followed up or not, if the long steel casing is not followed up, the diameter of the pile hole is generally the designed pile diameter, otherwise it is the same as the diameter of the pile hole at the karst distribution section and above. Specifically, the plating The spiral reinforcement stirrup added outside the zinc-steel casing is fixed by spiral welding.

具体的,所述设计钢筋笼与所述附加钢筋笼采用支撑钢筋焊接固定构成组合钢筋笼。Specifically, the design reinforcement cage and the additional reinforcement cage are welded and fixed by supporting reinforcement to form a combined reinforcement cage.

本发明实施例另一方面提供的一种岩溶无填充灌注桩结构施工方法,包括:Another aspect of the embodiment of the present invention provides a construction method for a karst unfilled cast-in-situ pile structure, including:

场地平整、定位,泥浆制备,长钢护筒制作,材料准备等;Site leveling, positioning, mud preparation, long steel casing production, material preparation, etc.;

桩基成孔设备与长钢护筒配套,开挖灌注桩至嵌岩深度,开挖过程中配合地勘报告,记录岩溶起始位置,终孔验收与清渣,所述长钢护筒内形成桩孔,长钢护筒底标高低于岩溶分布段最低位置一定深度;The pile foundation hole-forming equipment is matched with the long steel casing, and the cast-in-situ piles are excavated to the depth of the rock-socketed. During the excavation, the geological survey report is used to record the starting position of the karst, the final hole acceptance and slag removal. Pile holes are formed, and the elevation of the bottom of the long steel casing is lower than a certain depth at the lowest position of the karst distribution section;

根据岩溶无填充等不良地层起始位置,确定设计钢筋笼上需要增加附加钢筋笼的位置与长度;According to the starting position of unfavorable formations such as karst without filling, determine the position and length of the additional reinforcement cage on the design reinforcement cage;

设计钢筋笼制作,附加钢筋笼制作;Design reinforcement cage fabrication, additional reinforcement cage fabrication;

附加钢筋笼安装,外侧覆盖镀锌钢丝网与密目尼龙网或套设镀锌钢护筒,形成灌注桩的组合钢筋笼结构;Additional reinforcement cage installation, the outside is covered with galvanized steel wire mesh and dense mesh nylon mesh or set with galvanized steel casing to form a combined reinforcement cage structure of cast-in-situ piles;

桩孔内灌注桩组合钢筋笼吊放,沉渣厚度测量与二次清孔;Hanging and placement of cast-in-place pile composite reinforcement cage in the pile hole, measurement of sediment thickness and secondary hole cleaning;

导管安装,向桩孔内灌注桩身混凝土形成灌注桩;Conduit installation, pouring pile body concrete into the pile hole to form a pouring pile;

机械设备(起重机械、振动锤)起拔长钢护筒。Mechanical equipment (hoisting machinery, vibratory hammer) pulls out long steel casings.

具体的,附加钢筋笼与原设计钢筋笼之间的净距应≥35mm(无水环境)/50mm(有水环境),浇灌混凝土时,长钢护筒(沉入末端位置除外)底端位置一般低于混凝土浇筑面标高≮10m。Specifically, the net distance between the additional reinforcement cage and the original design reinforcement cage should be ≥35mm (without water environment)/50mm (with water environment). Generally lower than the concrete pouring surface elevation ≮10m.

具体的,所述长钢护筒的内径比灌注桩的设计桩径大140(无水环境)/200mm(有水环境),壁厚一般为20mm。Specifically, the inner diameter of the long steel casing is 140 mm larger than the designed pile diameter of the cast-in-situ pile (in an environment without water)/200 mm (in an environment with water), and the wall thickness is generally 20 mm.

上述施工方法具体包括:The above construction methods specifically include:

第一步:场地准备、桩位放样、材料准备等Step 1: site preparation, pile stake out, material preparation, etc.

第二步:长钢护简埋设和泥浆制备Step 2: Embedding of long steel sheathing and mud preparation

第三步:钻孔,终孔验收与一次清孔The third step: Drilling, final hole acceptance and one-time cleaning

第四步:组合钢筋笼安装Step 4: Combined reinforcement cage installation

第五步:沉渣指标检查与二次清孔Step 5: Sediment index inspection and secondary hole cleaning

将附件钢筋笼安装在设计钢筋笼上后,将组合钢筋笼整体吊装至桩孔内,并根据设计标高等要求控制好钢筋笼位置,同时在钢筋笼顶部采取相应措施予以固定,防止混凝土灌注过程中钢筋笼上升;After installing the accessory reinforcement cage on the design reinforcement cage, hoist the combined reinforcement cage into the pile hole as a whole, and control the position of the reinforcement cage according to the design elevation and other requirements, and at the same time take corresponding measures to fix it on the top of the reinforcement cage to prevent concrete pouring process The middle reinforcement cage rises;

提前设置好混凝土保护层垫块,用以控制钢筋笼与孔壁的净距。Set up the concrete cover block in advance to control the net distance between the reinforcement cage and the hole wall.

第六步:水下灌注混凝土Step 6: Pouring Concrete Underwater

在灌注过程中,应时常探测桩孔内的混凝土面位置,及时调整导管的埋深,连续灌注桩基混凝土,完成后及时机械拔出长钢护筒;During the pouring process, the position of the concrete surface in the pile hole should be detected frequently, the buried depth of the conduit should be adjusted in time, the pile foundation concrete should be poured continuously, and the long steel casing should be mechanically pulled out in time after completion;

第七步:成桩Step Seven: Pile

与现有技术相比,本发明至少一个实施例具有如下有益效果:Compared with the prior art, at least one embodiment of the present invention has the following beneficial effects:

应用本发明的技术方案能够有效地解决现有技术中岩溶无填充灌注桩的成孔、成桩质量及施工效率低下等问题,同时,施工工艺技术简单,具有安全可靠、质量可控、技术可行、经济合理、现场可实施性等显著性特点,能保障生产安全、提高质量控制、降低施工成本、增加工程效益。Applying the technical scheme of the present invention can effectively solve the problems of karst non-filled cast-in-situ piles in the prior art such as hole formation, pile formation quality, and low construction efficiency. At the same time, the construction technology is simple, safe, reliable, quality controllable, and technically feasible. , economical and reasonable, on-site implementability and other remarkable features can ensure production safety, improve quality control, reduce construction costs, and increase project benefits.

安全可靠:所采用的岩溶无填充灌注桩结构,采用长钢护筒配套施工,所增加的附加钢筋笼能有效阻隔桩身混凝土进入附近桩位(孔),不增加周边未施工桩位的施工难度的同时,泥浆护壁一定程度上较少渗透岩溶造成已经完成桩孔的土体流失与桩孔周围土体整体塌陷,不影响生产安全以及周围已成桩的质量问题等。Safe and reliable: the karst non-filled cast-in-place pile structure adopted is constructed with long steel casings, and the additional reinforcement cage can effectively prevent the concrete of the pile body from entering the nearby pile positions (holes), without increasing the construction of surrounding unconstructed pile positions At the same time as the difficulty, the mud retaining wall is less permeable to a certain extent, and the karst causes the soil loss of the completed pile hole and the overall collapse of the soil around the pile hole, which does not affect the production safety and the quality of the surrounding piles.

质量可控性:对比目前岩溶地区的灌注桩处理措施,采用岩溶无填充灌注桩结构,克服了目前处理措施的不足。桩身贯穿岩溶分布段时,在设计钢筋笼外侧增设附加钢筋笼,确保设计钢筋笼的保护层符合设计要求的同时,有效阻隔桩身混凝土扩散流失,以及泥浆或桩周岩土体进入桩身的同时,灌注桩质量容易得到保证;Quality controllability: Compared with the current cast-in-place pile treatment measures in karst areas, the use of karst unfilled cast-in-situ pile structure overcomes the shortcomings of the current treatment measures. When the pile body runs through the karst distribution section, an additional reinforcement cage is added outside the design reinforcement cage to ensure that the protective layer of the design reinforcement cage meets the design requirements and effectively prevent the diffusion and loss of pile concrete and the entry of mud or rock and soil around the pile into the pile body At the same time, the quality of cast-in-situ piles can be easily guaranteed;

技术可行:所采用的岩溶无填充灌注桩结构,适用于岩溶等不良地质条件,在技术上具有领先优势,同时经过丰富的工程实践检验了技术的成熟性和实用性;Technically feasible: the karst non-filled cast-in-place pile structure adopted is suitable for karst and other adverse geological conditions, and has a leading edge in technology. At the same time, the maturity and practicability of the technology have been tested through rich engineering practice;

经济合理:相较于当前的岩溶地区施工的措施措施,采用岩溶无填充灌注桩结构,能确保生产安全和质量控制的要求下,在工期与成本方面有显著性优势:①成本方面。不需要考虑填充等处理措施,如低等级的混凝土回填,无须考虑材料消耗与浪费,确保桩身混凝土的超灌量,能有效控制成本费用的投入;②工期方面。无回填等措施,岩溶无填充灌注桩结构,在设计上无须考虑优化,缩短设计时间。在施工上无回填等措施,无须考虑岩溶处理工期,无须考虑回填处理对机械成孔效益与设备磨损的影响,桩基施工的效率较高,工期容易得到保障。综合分析,所采用岩溶无填充灌注桩结构,在安全、工期、质量和施工成本等方面,均占有有一定的优势,尤其在安全和成本方面的优势较明显。Economical and reasonable: Compared with the current construction measures in karst areas, the use of karst unfilled cast-in-situ pile structure can ensure production safety and quality control requirements, and has significant advantages in terms of construction period and cost: ① In terms of cost. There is no need to consider filling and other treatment measures, such as backfilling with low-grade concrete, without considering material consumption and waste, ensuring the overfilling of concrete in the pile body, and effectively controlling the cost of investment; ② In terms of construction period. There is no backfilling and other measures, and the karst non-filling cast-in-place pile structure does not need to consider optimization in design, which shortens the design time. There is no backfilling and other measures in the construction, no need to consider the karst treatment period, no need to consider the impact of backfilling treatment on mechanical pore forming benefits and equipment wear, the efficiency of pile foundation construction is high, and the construction period is easy to be guaranteed. Comprehensive analysis shows that the karst non-filled cast-in-situ pile structure has certain advantages in terms of safety, construction period, quality and construction cost, especially in terms of safety and cost.

现场可实施性:所采用岩溶无填充灌注桩结构,与通常施工工艺流程区别不大,仅在岩溶分布段增加附加钢筋笼,并在附加钢筋笼上全覆盖镀锌钢丝网与密目尼龙网工序或套设镀锌钢护筒。成桩工艺技术与方法简单,施工现场容易组织施工,桩身混凝土质量易控制,有利于生产安全的同时,减少岩溶地区桩基施工的人、材、机等费用投入,符合低碳环保要求。On-site implementability: The karst non-filled cast-in-place pile structure adopted is not much different from the usual construction process. Only additional reinforcement cages are added in the karst distribution section, and the additional reinforcement cages are fully covered with galvanized steel wire mesh and dense mesh nylon mesh. process or set galvanized steel casing. The pile forming technology and method are simple, the construction site is easy to organize construction, and the quality of the pile concrete is easy to control, which is conducive to production safety and at the same time reduces the cost of manpower, materials, and machinery for pile foundation construction in karst areas, and meets the requirements of low-carbon environmental protection.

附图说明Description of drawings

为了更清楚地说明本发明实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings that need to be used in the description of the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present invention. For those skilled in the art, other drawings can also be obtained based on these drawings without creative effort.

图1为本发明实施例的岩溶无填充灌注桩结构示意图;Fig. 1 is the structural representation of the karst non-filling cast-in-place pile of the embodiment of the present invention;

图2为本发明实施例的岩溶分布段以上部位灌注桩身剖面结构示意图;Fig. 2 is a schematic diagram of the cross-sectional structure of the cast-in-place pile above the karst distribution section of the embodiment of the present invention;

图3为本发明实施例的岩溶分布段部位灌注桩身剖面结构示意图;Fig. 3 is a schematic diagram of the cross-sectional structure of the cast-in-place pile at the karst distribution section of the embodiment of the present invention;

图4为本发明实施例的岩溶分布段以下部位灌注桩身剖面结构示意图;Fig. 4 is a schematic diagram of the cross-sectional structure of the cast-in-place pile below the karst distribution section of the embodiment of the present invention;

图中:1、岩溶分布段;2、桩身主筋;3、桩身螺旋箍筋;4、桩身加劲环;5、设计桩径;6、桩孔;7、附加纵向钢筋;8、附加螺旋箍筋;9、附加加劲环;10、支撑钢筋;11、镀锌钢丝网和密目尼龙网;12、环形充填间隙;13、长钢护筒;14、施工桩径。In the figure: 1. Karst distribution section; 2. Main reinforcement of pile body; 3. Spiral stirrup of pile body; 4. Stiffening ring of pile body; 5. Design pile diameter; 6. Pile hole; 7. Additional longitudinal reinforcement; 8. Additional Spiral stirrup; 9. Additional stiffening ring; 10. Supporting steel bar; 11. Galvanized steel wire mesh and dense mesh nylon mesh; 12. Ring filling gap; 13. Long steel casing; 14. Construction pile diameter.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention.

在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”、“顺时针”、“逆时针”、“轴向”、“径向”、“周向”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In describing the present invention, it should be understood that the terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "front", " Back", "Left", "Right", "Vertical", "Horizontal", "Top", "Bottom", "Inner", "Outer", "Clockwise", "Counterclockwise", "Axial", The orientation or positional relationship indicated by "radial", "circumferential", etc. is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying the referred device or element Must be in a particular orientation, be constructed in a particular orientation, and operate in a particular orientation, and therefore should not be construed as limiting the invention.

参见图1-图4,本发明实施例提供的岩溶无填充灌注桩结构,包括插设于桩孔6的设计钢筋笼以及固定套设在设计钢筋笼外并覆盖桩孔6岩溶分布段1的附加钢筋笼,设计钢筋笼由多根桩身主筋2、桩身螺旋箍筋3、桩身加劲环4构成,附加钢筋笼由多根附加纵向钢筋7、附加螺旋箍筋8、附加加劲环9构成,附加钢筋笼与设计钢筋笼之间存在环形充填间隙12,桩孔6位于岩溶分布段1及以上部分的直径比灌注桩的设计桩径5大,附加钢筋笼外全覆盖有镀锌钢丝网和密目尼龙网11。Referring to Fig. 1-Fig. 4, the karst non-filled cast-in-situ pile structure provided by the embodiment of the present invention includes a designed reinforcement cage inserted in the pile hole 6 and a steel cage fixedly sleeved outside the designed reinforcement cage and covering the karst distribution section 1 of the pile hole 6. Additional reinforcement cage, the design reinforcement cage is composed of multiple pile body main reinforcement 2, pile body spiral stirrup 3, and pile body stiffening ring 4, and the additional reinforcement cage is composed of multiple additional longitudinal reinforcement 7, additional spiral stirrup 8, and additional stiffening ring 9 Composition, there is an annular filling gap 12 between the additional reinforcement cage and the design reinforcement cage, the diameter of the pile hole 6 located in the karst distribution section 1 and above is larger than the design pile diameter 5 of the cast-in-place pile, and the additional reinforcement cage is fully covered with galvanized steel wire Mesh and dense mesh nylon mesh11.

施工时,桩基成孔设备与长钢护筒配套,施工灌注桩至嵌岩深度,开挖过程中配合地勘报告,记录岩溶起始标高位置,终孔验收与清渣,之后根据岩溶无填充等不良地质起始位置,确定设计钢筋笼上需要增加附加钢筋笼的标高位置与长度,将灌注桩的组合钢筋笼整体吊装至桩孔6内,并再次进行沉渣厚度测量与二次清孔,并根据设计标高等要求控制好组合钢筋笼位置,同时在钢筋笼顶部采取相应措施予以固定,防止混凝土灌注过程中钢筋笼上升,组合钢筋笼提前设置好混凝土保护层垫块,用以控制钢筋笼与孔壁的净距;利用导管向桩孔6内灌注桩身混凝土形成灌注桩,利用机械设备(起重机械、振动锤)起拔长钢护筒13。During the construction, the pile foundation hole-forming equipment is matched with the long steel casing, and the cast-in-situ piles are constructed to the depth of the rock-socketed. During the excavation, the geological survey report is used to record the initial elevation of the karst, the final hole acceptance and slag removal, and then according to the karst Filling and other unfavorable geological starting positions, determine the elevation position and length of additional reinforcement cages that need to be added to the design reinforcement cages, hoist the combined reinforcement cages of cast-in-place piles as a whole into the pile hole 6, and conduct sediment thickness measurement and secondary hole cleaning again , and control the position of the combined reinforcement cage according to the design elevation and other requirements, and at the same time take corresponding measures to fix it on the top of the reinforcement cage to prevent the reinforcement cage from rising during the concrete pouring process. The net distance between the cage and the hole wall; use the conduit to pour the pile body concrete into the pile hole 6 to form a cast-in-situ pile, and use mechanical equipment (hoisting machinery, vibrating hammer) to pull out the long steel casing 13.

本实施例中,在灌注的过程中,岩溶分布段的桩身混凝土在镀锌钢丝网和密目尼龙网11的限制作用下,有效阻隔岩溶分布段的桩身混凝土向四周扩散流失,以及泥浆或桩周岩土体进入桩身,取代熔岩地区灌注桩施工预先处理地基的常规方法,降低成本,缩短工期,确保桩基施工质量。此外,即使岩溶分布段的附加钢筋笼外侧混凝土全部向四周扩散流失,位于附加钢筋笼与设计钢筋笼之间的混凝土可以作为设计钢筋笼的保护层,避免设计钢筋笼直接与桩周岩土体接触后所导致的设计钢筋笼加速锈蚀问题。In this embodiment, during the pouring process, the pile body concrete in the karst distribution section is restricted by the galvanized steel wire mesh and the dense mesh nylon mesh 11, effectively blocking the diffusion and loss of the pile body concrete in the karst distribution section to the surroundings, and the mud Or the rock and soil around the pile enter the pile body, replacing the conventional method of pre-treating the foundation for the construction of cast-in-situ piles in lava areas, reducing costs, shortening the construction period, and ensuring the construction quality of pile foundations. In addition, even if all the concrete outside the additional reinforcement cage in the karst distribution section diffuses and loses to the surroundings, the concrete between the additional reinforcement cage and the design reinforcement cage can be used as the protective layer of the design reinforcement cage to prevent the design reinforcement cage from directly contacting the rock and soil around the pile. Accelerated corrosion of design reinforcement cages caused by contact.

该灌注桩结构,适用范围较广,在设计方面无须过多考虑不良地质对桩基的影响,在施工方面没有机械钻孔设备等限制要求,配套长钢护筒13施工,在岩溶等不良地质分布段施工,能确保成孔顺利,工作效率较高,灌注桩身混凝土对组合结构的侧压力较小,实现在岩溶分布段1无填充施工灌注桩。The cast-in-situ pile structure has a wide range of applications, and there is no need to consider too much the influence of bad geology on the pile foundation in terms of design. There is no mechanical drilling equipment and other restrictions on construction, and it is equipped with long steel casing 13 for construction. The construction of the distribution section can ensure smooth hole formation and high work efficiency. The lateral pressure of the concrete of the poured pile body on the composite structure is small, and the construction of the poured pile without filling in the karst distribution section 1 can be realized.

需要解释说明的是,在实际设计中,岩溶分布段1及以上部位的桩孔6直径为长钢护筒13的内径,且不小于设计桩径+2倍[设计钢筋笼保护层(35mm(无水环境)/50mm(有水环境)+附加钢筋笼保护层(35mm(无水环境)/50mm(有水环境)];岩溶分布段1的附加钢筋笼直径一般比所述设计钢筋笼直径大2倍[35mm(无水环境)/50mm(有水环境)];岩溶分布段1以下部位桩孔6直径,基于长钢护筒跟进与否确认,如不跟进桩孔6直径则为设计桩径,反之则同岩溶分布段1及以上部位的桩孔6直径。镀锌钢丝网采用类似螺旋箍筋方式重叠搭接设置,并用铁丝以梅花状方式固定在附加钢筋笼上,密目尼龙网全覆盖在镀锌钢丝网的外侧,并采用铁丝以一定间距牢靠固定。What needs to be explained is that in the actual design, the diameter of the pile hole 6 in the karst distribution section 1 and above is the inner diameter of the long steel casing 13, and is not less than the design pile diameter + 2 times [the design reinforcement cage protective layer (35mm( No water environment)/50mm (with water environment) + additional reinforcement cage protection layer (35mm (without water environment)/50mm (with water environment)]; the diameter of the additional reinforcement cage in karst distribution section 1 is generally larger than the diameter of the design reinforcement cage 2 times larger [35mm (without water environment)/50mm (with water environment)]; 6 diameters of pile holes below the karst distribution section 1, based on whether the long steel casing is followed up or not, if the diameter of pile holes 6 is not followed up In order to design the pile diameter, otherwise it is the same as the diameter of the pile hole 6 in the karst distribution section 1 and above. The galvanized steel wire mesh is overlapped and overlapped in a manner similar to spiral stirrups, and is fixed on the additional steel cage in a plum blossom shape with iron wires. The mesh nylon mesh is fully covered on the outside of the galvanized steel mesh, and is firmly fixed with iron wires at a certain distance.

参见图1-图4,一种岩溶无填充的灌注桩结构的施工方法,包括以下步骤:Referring to Fig. 1-Fig. 4, a kind of construction method of the cast-in-place pile structure without filling in karst comprises the following steps:

第一步:场地准备Step 1: Site Preparation

施工场地应符合如下要求,避免桩基成孔设备在施工过程中,发生倾斜、倾倒或沉陷等情况,造成生产安全事故:The construction site should meet the following requirements to prevent the pile foundation hole-forming equipment from tilting, toppling or sinking during the construction process, causing production safety accidents:

1)为旱地施工场地,应清除地表杂物,置换软土,夯实整平等;1) It is a dry land construction site, surface sundries should be removed, soft soil should be replaced, compacted and leveled, etc.;

2)为斜坡或较厚淤泥层施工场地,应搭设工作平台;2) For construction sites with slopes or thick silt layers, a working platform should be erected;

3)为浅水区域施工场地,宜采用筑岛法施工,一般采用围堰;3) It is a construction site in a shallow water area, and the island construction method should be adopted for construction, and cofferdams are generally used;

4)为深水区域施工场地,可搭设贝雷梁工作平台。4) It is a construction site in a deep water area, and a Bailey beam working platform can be erected.

第二步:长钢护简埋设和泥浆制备Step 2: Embedding of long steel sheathing and mud preparation

长钢护筒13作用有:固定桩位、保护孔口、钻孔护壁、引导钻头方向、成孔垂直度、斜岩处理、维持泥浆液面高度、清孔、避免岩溶无填充造成泥浆渗漏与混凝土扩散流失,塌孔缩孔。The functions of the long steel casing 13 are: fixing the pile position, protecting the hole, drilling the wall, guiding the direction of the drill bit, verticality of the hole, treating inclined rock, maintaining the height of the mud level, clearing the hole, and avoiding mud leakage caused by karst non-filling Diffusion and loss of concrete, collapse and shrinkage cavities.

1)长钢护筒13一般用厚约20mm的钢板,在工厂加工制作,护筒内径一般与长钢护筒、地质条件、定额、成桩工艺等有关。1) The long steel casing 13 is generally made of a steel plate with a thickness of about 20mm, which is processed and manufactured in a factory. The inner diameter of the casing is generally related to the long steel casing, geological conditions, quota, and pile-forming technology.

2)长钢护筒13顶端高程应高出地下水位或孔外水位1.5m~2.0m,且还应高出作业面0.3m。2) The elevation of the top of the long steel casing 13 should be 1.5m to 2.0m higher than the groundwater level or the water level outside the hole, and should be 0.3m higher than the working surface.

3)长钢护筒13底端埋置深度:应贯穿岩溶分布段1,且低于最下层标高1m,但在岩溶分布段1浇灌混凝土时,长钢护筒13(沉入末端位置除外)底端位置一般低于混凝土面标高≮10m,避免过早起拔护筒,这是因为在岩溶分布段1,桩身混凝土对组合钢筋笼的侧压力过大,破坏组合钢筋笼上的镀锌钢丝网与密目尼龙网11,造成两方面影响:一方面灌注桩缩颈,以及钢筋笼保护层缺失;另一方面桩身混凝土扩散流失、塌陷带动上部混凝土面整体下降等现象,以及泥浆与桩身混凝土混合,影响灌注桩的质量等。3) Embedding depth of the bottom end of the long steel casing 13: it should run through the karst distribution section 1 and be 1m lower than the lowest level. The bottom end is generally lower than the concrete surface elevation ≮10m, so as to avoid pulling out the casing prematurely, this is because in the karst distribution section 1, the lateral pressure of the pile body concrete on the composite reinforcement cage is too large, which will damage the galvanized steel wire on the composite reinforcement cage Net and dense mesh nylon mesh 11, resulting in two effects: on the one hand, the necking of the cast-in-place pile and the lack of the protective layer of the steel cage; body concrete mixing, affecting the quality of cast-in-place piles, etc.

4)长钢护筒13平面位置的偏差不得大于50mm,长钢护筒13垂直度的偏差不得大于1%。4) The deviation of the plane position of the long steel casing 13 shall not be greater than 50mm, and the deviation of the verticality of the long steel casing 13 shall not be greater than 1%.

5)泥浆由水、粘土(或澎润土)和添加剂组成。泥浆的作用是将钻孔内不同土层的空隙渗填密实,使孔内渗漏水达最低限度,并维持桩孔6内一定压力以稳定没有设置长钢护筒段的孔壁。因此在成孔过程中应严格控制泥浆的配合比。5) The mud consists of water, clay (or bentonite) and additives. The effect of the mud is to infiltrate and fill the gaps in different soil layers in the borehole, so that the leakage of water in the hole reaches the minimum, and maintain a certain pressure in the pile hole 6 to stabilize the hole wall without the long steel casing section. Therefore, the mixing ratio of the mud should be strictly controlled during the hole forming process.

第三步:钻孔Step Three: Drilling

1)桩基成孔设备安装就位后,底座和顶部应平稳,在施工过程中不应产生倾斜、倾倒或沉陷。同时,成孔设备顶部中心或钻杆、钻头(锤头)和桩孔6中心三者应在同一铅垂线上。1) After the pile foundation hole-forming equipment is installed in place, the base and top should be stable, and there should be no inclination, dumping or subsidence during the construction process. At the same time, the top center of the hole-forming equipment or the drill rod, drill bit (hammer) and pile hole 6 centers should be on the same plumb line.

2)成孔作业应连续施工,注意地质变化并捞渣取样,判明地质状态与标高位置,尤其是岩溶等不良地质,及时记录以便与地质剖面图核对,用来确定组合钢筋笼的参数。2) The hole-forming operation should be carried out continuously, pay attention to geological changes and take slag samples to determine the geological state and elevation position, especially the unfavorable geology such as karst, and record it in time for checking with the geological profile to determine the parameters of the combined reinforcement cage.

3)在无长钢护筒13段钻孔作业时,需确保泥浆量及液面规定高度,方可继续钻孔施工。3) When drilling without long steel casing 13, it is necessary to ensure the amount of mud and the specified height of the liquid level before continuing the drilling construction.

4)中途暂停钻孔作业时,应保持桩孔6内的水位高度和泥浆相对密度及粘度,防止无长钢护筒塌孔或缩孔。4) When the drilling operation is suspended midway, the water level in the pile hole 6 and the relative density and viscosity of the mud should be maintained to prevent the collapse or shrinkage of the long steel casing.

第四步:组合钢筋笼Step Four: Assemble the Reinforcement Cage

1)组合钢筋笼由设计钢筋笼与附加钢筋笼构成。1) The composite reinforcement cage is composed of a design reinforcement cage and an additional reinforcement cage.

2)附加钢筋笼由附加纵向钢筋7、附加螺旋箍筋8、附加加劲环9等构成。2) The additional reinforcement cage is composed of additional longitudinal reinforcement 7, additional spiral stirrup 8, additional stiffening ring 9 and so on.

3)附加钢筋笼采用支撑钢筋10焊接在设计钢筋笼上。3) The additional reinforcement cage is welded on the design reinforcement cage with support reinforcement 10.

4)附加纵向钢筋7采用弯折锚固在设计钢筋笼内,锚固长度不小于LaE。4) The additional longitudinal reinforcement 7 is anchored in the design reinforcement cage by bending, and the anchorage length is not less than LaE.

5)设计桩径≯1200mm时,支撑钢筋10设置的位置,应避免影响导管与灌注桩基混凝土;设计桩径≥1200mm时,增设三角支撑钢筋,确保组合钢筋笼在吊运与安装过程中不易变形,增加钢筋笼整体稳定性等。5) When the design pile diameter is ≯1200mm, the location of the support reinforcement 10 should avoid affecting the conduit and the poured pile foundation concrete; when the design pile diameter is ≥1200mm, add triangular support reinforcement to ensure that the combined reinforcement cage is not easy to lift during lifting and installation. Deformation, increase the overall stability of the reinforcement cage, etc.

6)设计钢筋笼与附加钢筋笼组合安装时,先焊接支撑钢筋,再焊接附加钢筋笼的附加纵向钢筋7及附加螺旋箍筋8等,确保设计钢筋笼与附加钢筋笼之间的净距一致。6) When the design reinforcement cage and the additional reinforcement cage are installed in combination, the support reinforcement is first welded, and then the additional longitudinal reinforcement 7 and the additional spiral stirrup 8 of the additional reinforcement cage are welded to ensure that the clear distance between the design reinforcement cage and the additional reinforcement cage is consistent .

7)附加纵向钢筋7弯折后,弯折处与末端采用加劲环焊接成整体,弯折角度不应过大,以免影响导管的安装与混凝土的灌注。7) After the additional longitudinal steel bar 7 is bent, the bending part and the end are welded into a whole with a stiffening ring, and the bending angle should not be too large, so as not to affect the installation of the conduit and the pouring of concrete.

第五步:组合钢筋笼设计处理Step 5: Combined reinforcement cage design and processing

1)附加钢筋笼外表按里到外的顺序全覆盖设置镀锌钢丝网与密目尼龙网。1) The appearance of the additional reinforcement cage is fully covered with galvanized steel wire mesh and dense mesh nylon mesh in the order from inside to outside.

2)镀锌钢丝网,应具有良好的柔韧性和可塑性,即使局部受到过大的混凝土侧压力,不发生脱焊等现象,依然可以阻隔混凝土的塌陷以及泥浆进入桩内;其次钢丝网镀锌后,耐腐蚀性与耐久性较好,可作为桩身材料的同时,镀锌钢丝网覆盖在附加钢筋笼外,即使附加钢筋笼外侧混凝土扩散流失导致,也不影响设计桩身的截面尺寸、设计纵向钢筋的保护层等要求,这也是为何要求附加钢筋笼的直径为设计桩径5及岩溶无填充段及以上扩径的原由。因此,一般采用热镀锌钢丝网,网孔呈菱形,丝径≮1.0mm。2) Galvanized steel wire mesh should have good flexibility and plasticity. Even if it is partially subjected to excessive concrete lateral pressure and no desoldering occurs, it can still block the collapse of concrete and the entry of mud into the pile; secondly, the steel wire mesh is galvanized Finally, it has good corrosion resistance and durability. It can be used as the material of the pile body. At the same time, the galvanized steel wire mesh is covered outside the additional reinforcement cage. Design requirements for the protective layer of longitudinal reinforcement, which is why the diameter of the additional reinforcement cage is required to be the diameter of the designed pile diameter 5 and the expansion diameter of the karst unfilled section and above. Therefore, hot-dip galvanized steel wire mesh is generally used, the mesh is diamond-shaped, and the wire diameter is ≮1.0mm.

3)镀锌钢丝网采用类似螺旋箍筋的方式缠绕固定在附加钢筋笼上,钢丝网以重叠方式搭接≮200mm,再采用铁丝梅花状固定在附加钢筋笼上。3) The galvanized steel wire mesh is wound and fixed on the additional reinforcement cage in a manner similar to spiral stirrups. The wire mesh overlaps ≮ 200mm in an overlapping manner, and then is fixed on the additional reinforcement cage with iron wire plum blossoms.

4)镀锌钢丝网一般采用双层错位布设,错位距离为1/2钢丝网宽度,固定方式同样采用铁丝梅花状固定在附加钢筋笼上。4) The galvanized steel wire mesh is generally arranged in a double-layer dislocation, the dislocation distance is 1/2 the width of the steel wire mesh, and the fixing method is also fixed on the additional steel cage by iron wire plum blossom.

5)密目尼龙网的材质一般采用网目密度为2000目/100cm2的HDPE高密度聚乙烯,同时应具有韧性高、弹性好、耐腐蚀等特点。5) The material of dense-mesh nylon mesh is generally HDPE high-density polyethylene with a mesh density of 2000 mesh/100cm2, and it should have the characteristics of high toughness, good elasticity, and corrosion resistance.

6)密目尼龙网的全覆盖安装在镀锌钢丝网表面,一般采用铁丝@1500mm绑扎安装,尼龙网的安装长度为附加钢筋笼的长度。6) The full coverage of the dense-mesh nylon mesh is installed on the surface of the galvanized steel mesh. Generally, iron wire @1500mm is used for binding installation. The installation length of the nylon mesh is the length of the additional steel cage.

7)安装镀锌钢丝网与密目尼龙网后的附加钢筋笼,与长钢护筒13净距一般不小于35mm(无水环境)/50mm(有水环境),确保长钢护筒13顺利插拔等。7) Install the additional reinforcement cage after installing galvanized steel wire mesh and dense mesh nylon mesh, and the net distance between the long steel casing 13 and the long steel casing 13 is generally not less than 35mm (without water environment)/50mm (with water environment), so as to ensure that the long steel casing 13 runs smoothly. plugging etc.

第六步:清孔Step 6: Clear the hole

成孔达到图纸入岩深度要求后,应立即进行清孔。清孔的方式与桩基成孔设备、成桩工艺、地质条件等有关,如旋挖钻机应选择捞渣钻头。清孔应满足《建筑桩基技术规范》JGJ94规定与设计图纸要求。After the hole reaches the depth requirement of the drawing, the hole should be cleaned immediately. The method of hole cleaning is related to the pile foundation hole-forming equipment, pile-forming technology, and geological conditions. For example, a rotary drilling rig should choose a slag-removing drill bit. Clearing holes should meet the requirements of JGJ94 and design drawing requirements of "Technical Specifications for Building Pile Foundations".

清孔时,长钢护筒内水位应维持并高于地下水位或孔外水位1.5~2.0m以上,以防止未设置长钢护筒段的孔壁坍塌。When cleaning the hole, the water level inside the long steel casing should be maintained and 1.5-2.0m higher than the groundwater level or the water level outside the hole to prevent the hole wall without the long steel casing section from collapsing.

1)泥浆正循环清孔法:在终孔后提升钻头或钻锥距孔底10cm~20cm,钻头(锤头)的直径与长钢护筒之间应存在一定的间隙,避免与护筒直接接触,将相对密度较低(1.1~1.2)的泥浆中速压入,把钻孔内悬浮钻渣较多的泥浆换出。1) Positive mud circulation hole cleaning method: After the final hole, lift the drill bit or drill cone to 10cm to 20cm from the bottom of the hole. There should be a certain gap between the diameter of the drill bit (hammer) and the long steel casing to avoid direct contact with the casing. Contact, press in the mud with a low relative density (1.1-1.2) at a medium speed, and replace the mud with more suspended drilling slag in the borehole.

2)泥浆反循环清孔法:一般适应于各种桩基成孔设备,分泵吸反循环、气举反循环两种:①泵吸反循环。依据泵的安装位置又分孔底潜水泥浆泵直接抽吸或地面负压抽吸,一般适用于大直径桩、深桩。泵吸反循环清孔具有抽吸能力强、清孔时间短、孔底干净的优点,但泵吸反循环的泥浆量使用较大,需控制好泥浆性能和参数的同时,做好废浆废渣的处理。②气举反循环工艺压力差大,流速快,清渣能力强,但气举反循环设备的较复杂,清渣效率易受到空压机的选型、进气管长度和管道接头的影响。同时,气举反循环会引起桩孔6底部产生抽吸负压,以及保持泥浆的水头高度,控制好难泥浆回流入孔内的泥浆量与抽吸平衡,避免塌孔。2) Mud reverse circulation hole cleaning method: generally suitable for various pile foundation hole forming equipment, divided into two types: pump suction reverse circulation and gas lift reverse circulation: ① pump suction reverse circulation. According to the installation position of the pump, it can be divided into direct suction by submersible mud pump at the bottom of the hole or negative pressure suction on the ground. It is generally suitable for large-diameter piles and deep piles. Pump suction reverse circulation hole cleaning has the advantages of strong suction capacity, short hole cleaning time, and clean hole bottom. However, the amount of mud used by pump suction reverse circulation is relatively large. It is necessary to control the performance and parameters of the mud and at the same time do a good job of waste slurry and residue processing. ②The gas lift reverse circulation process has large pressure difference, fast flow rate and strong slag removal ability, but the gas lift reverse cycle equipment is more complicated, and the slag removal efficiency is easily affected by the selection of the air compressor, the length of the intake pipe and the pipe joint. At the same time, gas lift reverse circulation will cause suction negative pressure at the bottom of the pile hole 6, and maintain the head height of the mud, so as to control the amount of mud that is difficult to flow back into the hole and the suction balance to avoid hole collapse.

3)捞渣无泥浆循环清孔,一般用于旋挖钻机,终孔后利用专用的捞渣钻斗清除孔底的沉渣,孔底钻渣厚度满足要求后,再采用专门的泥浆调制措施,使桩孔6底部形成高黏度的泥浆,即能保护孔壁不坍塌与稳定和沉渣悬浮孔底上方,保持孔底的沉渣符合设计与规范要求。3) Slag removal without mud circulation for hole cleaning, which is generally used for rotary drilling rigs. After the hole is completed, use a special slag removal drill bucket to remove the sediment at the bottom of the hole. After the thickness of the drilling slag at the bottom of the hole meets the requirements, special mud preparation measures are adopted Making the bottom of the pile hole 6 form high-viscosity mud, which can protect the hole wall from collapsing and stabilizing and suspend the sediment above the bottom of the hole, and keep the sediment at the bottom of the hole to meet the design and specification requirements.

4)沉渣局部悬浮法:适应于旋挖钻孔机设备,离终孔还剩2m左右(两个回次终孔),将配制好的CMC(梭甲基纤维素)溶液,通过管道输送至孔底,经过旋挖钻孔机在终孔前的两个回次中搅动,与下面局部段泥浆混合,提高赫度和悬浮沉渣的能力,达到局部的沉渣处于悬浮效果。4) Sediment partial suspension method: suitable for rotary drilling equipment, about 2m away from the final hole (two secondary final holes), the prepared CMC (Shuttle methyl cellulose) solution is transported to the The bottom of the hole is stirred by the rotary drilling machine in the two rounds before the final hole, and mixed with the mud in the lower part of the hole to improve the degree of density and the ability to suspend the sediment, so as to achieve the effect that the local sediment is in suspension.

5)沉淀捞取法,适应于旋挖钻孔机,比沉渣局部悬浮法多一道工序,一般用沉渣桶来实现捞渣,根据不同地层的钻渣在泥浆内的沉降速度及一定时间内沉降厚度与时间段的相关关系,确定捞渣时间,同时彩虹沉渣检测设备进行检测。5) The sedimentation fishing method is suitable for rotary drilling machines. It has one more process than the partial suspension method of sediment. Generally, the sedimentation bucket is used to realize the removal of slag. According to the sedimentation speed of drilling slag in different strata in the mud and the sedimentation thickness within a certain period of time The correlation with the time period determines the slag removal time, and the rainbow sediment detection equipment conducts detection at the same time.

6)不得以加深桩底深度的方法来替代清孔。6) The method of deepening the depth of the pile bottom shall not be used as a substitute for clearing the hole.

第七步:水下灌注混凝土Step 7: Pouring Concrete Underwater

1)在灌注水下混凝土前,应将灌注桩的组合钢筋笼整体吊装至桩孔6内,并根据设计标高等要求控制好钢筋笼位置,同时在钢筋笼顶部采取相应措施予以固定,防止混凝土灌注过程中钢筋笼上升。1) Before pouring underwater concrete, the combined reinforcement cage of the cast-in-situ pile should be hoisted into the pile hole 6 as a whole, and the position of the reinforcement cage should be controlled according to the design elevation and other requirements, and corresponding measures should be taken to fix it on the top of the reinforcement cage to prevent concrete The reinforcement cage rises during the filling process.

2)组合钢筋笼提前设置好混凝土保护层垫块,用以控制钢筋笼与孔壁的净距。保护层垫块应牢固可靠的设置(捆绑)在钢筋笼上,一般梅花状布置,间隔距离不超过4m。2) The concrete protective layer pads are set in advance for the combined reinforcement cage to control the net distance between the reinforcement cage and the hole wall. The protective layer pads should be firmly and reliably set (bundled) on the steel cage, generally arranged in a plum blossom shape, and the distance between them should not exceed 4m.

3)水下混凝土的灌注。3) pouring of underwater concrete.

a.灌注混凝土前,孔底的成渣厚度指标应符合《建筑桩基技术规范》JGJ94规定与设计图纸要求,如有不符合要求应再次根据第六步清孔方法予以二次清孔。a. Before pouring concrete, the slag thickness index at the bottom of the hole should comply with the "Technical Specifications for Pile Foundations" JGJ94 and the requirements of the design drawings. If it does not meet the requirements, the hole should be cleaned a second time according to the hole cleaning method in the sixth step.

b.严格按配合比配制混凝土,控制好细石粗骨料的用量和粒径,现场必须对每车混凝土进行检查,降低水下灌注混凝土的离析等施工风险,以及确保成桩质量。b. Concrete is prepared strictly according to the mix ratio, and the amount and particle size of fine stone and coarse aggregate are well controlled. Every truck of concrete must be inspected on site to reduce construction risks such as segregation of underwater poured concrete and ensure the quality of pile formation.

c.混凝土可适量添加速凝剂,减少混凝土的流动对镀锌钢丝网和密目尼龙网的侧压力。c. Concrete can be added with an appropriate amount of quick-setting agent to reduce the lateral pressure of the flow of concrete on galvanized steel wire mesh and dense mesh nylon mesh.

d.灌注混凝土时,混凝土的温度不应低于5℃,当气温低于0℃时,灌注混凝土后应采取保温措施。d. When pouring concrete, the temperature of the concrete should not be lower than 5°C. When the temperature is lower than 0°C, insulation measures should be taken after pouring concrete.

e.灌注水下混凝土选用直径200~250mm导管,导管下口至孔底的距离应有300~500mm,导管埋入混凝土中的深度宜为2~6m,当灌注速度较快,有足够提升导管能力时,可适当加大导管的埋深。注意事项,各桩孔1初灌混凝土储备量应根据孔径、导管埋设深度等要求计算,确保导管一次埋入混凝土面以下深度≮0.8m。初灌混凝土用量计算公式:e. Conduits with a diameter of 200-250mm are used for pouring underwater concrete. The distance from the lower opening of the conduit to the bottom of the hole should be 300-500mm. The depth of the conduit buried in the concrete should be 2-6m. When the pouring speed is fast, there is enough to lift the conduit When the capacity is limited, the buried depth of the conduit can be appropriately increased. Matters needing attention, the reserve amount of primary poured concrete in each pile hole 1 should be calculated according to the requirements of hole diameter and conduit embedding depth, so as to ensure that the conduit is buried below the concrete surface at a depth of ≮0.8m. The formula for calculating the amount of concrete poured at the beginning of pouring:

HC=HD+HE H C =H D +H E

式中:HC—首批混凝土要求浇灌深度(m);In the formula: H C — the required pouring depth of the first batch of concrete (m);

HD—管底至桩孔底的高度(m);H D — the height from the bottom of the pipe to the bottom of the pile hole (m);

HE—导管的埋设深度(m);H E — the buried depth of the conduit (m);

D—灌注桩直径(m);D—diameter of cast-in-place pile (m);

h1—桩孔内混凝土达到HC时,导管内混凝土与导管外水压平衡所需高度(m);h 1 — When the concrete in the pile hole reaches HC, the required height of the concrete in the conduit and the hydraulic pressure outside the conduit (m);

Hw—初灌混凝土后桩孔内混凝土距孔口泥浆面高度,即桩孔内泥浆深度(m); Hw — the height of the concrete in the pile hole from the mud surface of the hole after the initial pouring of concrete, that is, the depth of the mud in the pile hole (m);

γw—桩孔内泥浆比重;γ w — specific gravity of mud in the pile hole;

γC—混凝土重度;γ C - concrete weight;

d—导管内径(m);d—the inner diameter of the catheter (m);

f.在灌注过程中,应时常探测桩孔6内的混凝土面位置,及时调整导管的埋深,连续灌注桩基混凝土,完成后及时起重机械或振动锤拔出长钢护筒13。f. During the pouring process, the position of the concrete surface in the pile hole 6 should be detected from time to time, the buried depth of the conduit should be adjusted in time, and the pile foundation concrete should be poured continuously. After completion, the long steel casing 13 should be pulled out in time by a lifting machine or a vibrating hammer.

g.成型后的桩顶标高应高出设计标高0.5m~1.0m,以保证质量,同时凿除浮浆与打毛后,确保桩顶混凝土强度等级、标高等符合规范与设计要求。g. The elevation of the formed pile top should be 0.5m~1.0m higher than the design elevation to ensure the quality. At the same time, after removing the laitance and roughening, ensure that the strength level and elevation of the pile top concrete meet the specifications and design requirements.

第八步:成桩Step Eight: Pile

如图3所示,岩溶无填充灌注桩结构,是在岩溶等不良地质分布段,增加附加钢筋笼,及覆盖表面的镀锌钢丝网与密目尼龙网,起到无须处理岩溶等不良地质的作用,确保设计钢筋笼的保护层厚度和控制灌注桩成本要求。As shown in Figure 3, the karst non-filled cast-in-situ pile structure is to add additional steel cages, galvanized steel wire mesh and dense nylon mesh covering the surface in the unfavorable geological distribution section such as karst, so as not to need to deal with unfavorable geology such as karst To ensure the thickness of the protective layer of the design reinforcement cage and control the cost requirements of cast-in-place piles.

参阅图2-4所示,在岩溶等不良地质分布段(岩溶分布段1)以上,采用图2方式设置钢筋笼;在岩溶等不良地质分布段,采用图3方式设置设计钢筋笼;在岩溶等不良地质分布段以下,采用图4方式设置钢筋笼,同时长钢护筒13的埋置深度应低于最下层岩溶分布段1标高下一定深度,共同构成岩溶等不良地质条件的灌注桩结构。该灌注桩结构在岩溶分布段1的附加钢筋笼长度应不小于多层不良地质的厚度,且附加钢筋笼的顶端与低端位置应超过岩溶等不良地质分布段总厚度一定距离,从而在岩溶不良地质分布段无须采用填充等处理措施,实现灌注桩的施工,达到提质降本增效的目的。Referring to Figure 2-4, above the unfavorable geological distribution section (karst distribution section 1) such as karst, adopt the method of Figure 2 to set the reinforcement cage; Below the unfavorable geological distribution section, adopt the method shown in Figure 4 to set the reinforcement cage, and at the same time, the embedding depth of the long steel casing 13 should be lower than a certain depth below the level of the lowest karst distribution section 1, which together constitute the cast-in-place pile structure with unfavorable geological conditions such as karst . The length of the additional reinforcement cage in the karst distribution section 1 of the cast-in-situ pile structure should not be less than the thickness of multi-layer unfavorable geology, and the top and bottom positions of the additional reinforcement cage should exceed the total thickness of the karst and other unfavorable geological distribution sections by a certain distance, so that There is no need to take filling and other treatment measures for the unfavorable geological distribution section, so as to realize the construction of cast-in-situ piles and achieve the purpose of improving quality, reducing cost and increasing efficiency.

注意事项:Precautions:

1)附加钢筋笼与原设计钢筋笼之间的净距应≥35mm(无水环境)/50mm(有水环境),以确保设计钢筋笼的保护层厚度符合设计要求,因此,在岩溶分布段1以及上部,成孔直径与长钢护筒有关,至少应扩大2倍[35mm(无水环境)/50mm(有水环境)],岩溶分布段1以下部位桩孔直径,基于长钢护筒跟进与否确认,如不跟进桩孔直径则为设计桩径,反之则同岩溶分布段1及以上部位的桩孔直径。施工岩溶分布段1以下部位且未设置长钢护筒段时,需要更换与设计桩径配套的钻头(锤头)。1) The net distance between the additional reinforcement cage and the original design reinforcement cage should be ≥ 35mm (without water environment) / 50mm (with water environment), to ensure that the thickness of the protective layer of the design reinforcement cage meets the design requirements. Therefore, in the karst distribution section 1 and the upper part, the diameter of the hole is related to the long steel casing, and should be enlarged by at least 2 times [35mm (without water environment)/50mm (with water environment)], the diameter of the pile hole below the karst distribution section 1 is based on the long steel casing Whether to follow up or not to confirm, if not followed up, the diameter of the pile hole is the design pile diameter, otherwise, it is the same as the diameter of the pile hole in the karst distribution section 1 and above. When constructing parts below the karst distribution section 1 and no long steel casing section is installed, the drill bit (hammer) matching the designed pile diameter needs to be replaced.

2)附加钢筋笼的参数,应根据桩径、桩长、岩溶分布段的位置等,进行相应的设计计算,在确保成桩质量、生产安全的前提下,控制成本投入,提升经济效益。2) The parameters of the additional reinforcement cage should be designed and calculated according to the pile diameter, pile length, and the location of the karst distribution section. On the premise of ensuring the pile quality and production safety, the cost input can be controlled and the economic benefit can be improved.

3)成桩后,泥浆液面保持至混凝土初凝后,防止泥水压与混凝土对镀锌钢丝网与密目尼龙网的侧压力不平衡,造成组合钢筋笼支护结构被破坏,混凝土未被阻隔等塌陷及进入岩溶无填充内,造成两方面影响:一方面灌注桩缩颈或桩身空洞,以及钢筋笼保护层缺失;另一方面塌陷带动上部混凝土面整体下降等现象,以及泥浆、土层与桩身混凝土混合,进一步影响灌注桩的质量等。3) After the pile is formed, the mud liquid level is maintained until the initial setting of the concrete, so as to prevent the mud water pressure and the lateral pressure of the concrete on the galvanized steel wire mesh and the dense mesh nylon mesh from being unbalanced, resulting in the destruction of the combined steel cage support structure, and the concrete is not The subsidence of blocking and entry into the karst without filling will cause two effects: on the one hand, the necking of the cast-in-situ pile or the cavity of the pile body, and the lack of the protective layer of the steel cage; Layer and pile body concrete mixing, further affect the quality of cast-in-place piles and so on.

另外,本发明的岩溶无填充灌注桩施工方法,还可以应用于土洞、采空区、湿陷性黄土等地质结构。其施工方法的机械成孔设备方面,可为旋挖钻机、全套管全回转钻机、正反循环钻机、冲击钻机、潜孔钻机等常见桩基成孔设备,但需要综合考虑环保、施工速度、实用性与自动化等影响指标。In addition, the construction method of karst non-filled cast-in-situ piles of the present invention can also be applied to geological structures such as soil caves, goafs, and collapsible loess. In terms of mechanical hole-forming equipment in its construction method, it can be common pile foundation hole-forming equipment such as rotary drilling rig, full-casing full-rotary drilling rig, positive and negative circulation drilling rig, impact drilling rig, down-the-hole drilling rig, etc., but it needs to comprehensively consider environmental protection, construction speed, Impact indicators such as usability and automation.

可以理解的是,附加钢筋笼外的镀锌钢丝网和密目尼龙网11也可以替换为镀锌钢护筒,并套设固定在附加钢筋笼外,在附加钢筋笼与设计钢筋笼之间存在环形充填间隙。为防止镀锌钢护筒在混凝土施工时侧压力作用下产生变形或破坏,在镀锌钢护筒外还可以增设螺旋加强箍筋,以螺旋形式焊接方式固定。It can be understood that the galvanized steel wire mesh and dense-mesh nylon mesh 11 outside the additional reinforcement cage can also be replaced with a galvanized steel casing, and set and fixed outside the additional reinforcement cage, between the additional reinforcement cage and the designed reinforcement cage There is an annular fill gap. In order to prevent the galvanized steel casing from being deformed or damaged under the lateral pressure during concrete construction, a spiral reinforcement stirrup can be added outside the galvanized steel casing and fixed by spiral welding.

上述实施例仅仅是清楚地说明本发明所作的举例,而非对实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里也无需也无法对所有的实施例予以穷举。而由此所引申出的显而易见的变化或变动仍处于本发明的保护范围之中。The above-mentioned embodiments are only examples for clearly illustrating the present invention, rather than limiting the implementation. For those of ordinary skill in the art, other changes or changes in different forms can be made on the basis of the above description. It is not necessary and impossible to exhaustively list all the embodiments here. However, the obvious changes or variations derived therefrom are still within the protection scope of the present invention.

Claims (10)

1.一种岩溶无填充灌注桩结构,其特征在于:包括置于桩孔(6)的设计钢筋笼以及增设在所述设计钢筋笼外并贯穿桩孔(6)岩溶分布段(1)的附加钢筋笼;1. A kind of karst cast-in-place pile structure without filling, is characterized in that: comprise the design reinforcement cage that is placed in pile hole (6) and set up outside described design reinforcement cage and run through pile hole (6) karst distribution section (1) Additional reinforcement cage; 所述设计钢筋笼由多根桩身主筋(2)、桩身螺旋箍筋(3)、桩身加劲环(4)构成;The design reinforcement cage is composed of a plurality of pile body main reinforcements (2), pile body spiral stirrups (3), and pile body stiffening rings (4); 所述附加钢筋笼由多根附加纵向钢筋(7)、附加螺旋箍筋(8)、附加加劲环(9)构成。The additional reinforcement cage is composed of multiple additional longitudinal reinforcements (7), additional spiral stirrups (8) and additional stiffening rings (9). 所述附加钢筋笼与所述设计钢筋笼之间存在环形充填间隙(12);There is an annular filling gap (12) between the additional reinforcement cage and the design reinforcement cage; 所述附加钢筋笼外全覆盖有镀锌钢丝网和密目尼龙网(11);或者是,The outside of the additional reinforcement cage is fully covered with galvanized steel wire mesh and dense mesh nylon mesh (11); or, 所述附加钢筋笼外套设镀锌钢护筒。A galvanized steel casing is arranged outside the additional reinforcement cage. 2.根据权利要求1所述的岩溶无填充灌注桩结构,其特征在于:所述附加钢筋笼中的多根附加纵向钢筋(7)两端弯折后锚固在所述设计钢筋笼内,所述附加纵向钢筋(7)在弯折处与端头采用附加加劲环(9)焊接固定。2. The karst unfilled cast-in-place pile structure according to claim 1, characterized in that: the two ends of the multiple additional longitudinal reinforcements (7) in the additional reinforcement cage are bent and anchored in the design reinforcement cage, and the The above-mentioned additional longitudinal reinforcement (7) adopts additional stiffening ring (9) to weld and fix at the bend and the end. 3.根据权利要求1所述的岩溶无填充灌注桩结构,其特征在于:所述镀锌钢丝网采用类似螺旋箍筋的方式重叠搭接设置,并用铁丝以梅花状方式固定在所述附加钢筋笼上,所述密目尼龙网全覆盖在镀锌钢丝网的外侧,并采用铁丝以一定间距牢靠固定。3. The karst non-filled cast-in-situ pile structure according to claim 1, characterized in that: the galvanized steel wire mesh is overlapped and overlapped in a manner similar to spiral stirrups, and is fixed on the additional steel bar in a quincunx-shaped manner with iron wires On the cage, the dense-mesh nylon mesh is completely covered on the outside of the galvanized steel wire mesh, and is firmly fixed with iron wires at a certain distance. 4.根据权利要求1所述的岩溶无填充灌注桩结构,其特征在于:所述附加纵向钢筋笼的直径,在有水环境一般为灌注桩的设计桩径(5)的基础上增加100mm,无水环境则增加70mm。4. The karst cast-in-place pile structure without filling according to claim 1, characterized in that: the diameter of the additional longitudinal reinforcement cage is generally increased by 100mm on the basis of the designed pile diameter (5) of the cast-in-place pile in a water environment, Anhydrous environment will increase by 70mm. 5.根据权利要求1所述的岩溶无填充灌注桩结构,其特征在于:所述桩孔(6)直径比灌注桩的设计桩径(5)大,岩溶分布段(1)及以上部位的桩孔(6)直径为长钢护筒(13)内径,且不小于设计桩径(5)+2倍设计钢筋笼保护层厚度+2倍附加钢筋笼保护层厚度;在岩溶分布段(1)以下部位的桩孔(6)直径,基于长钢护筒(13)跟进与否确认,若不跟进长钢护筒(13),则桩孔(6)直径一般为设计桩径(5),反之则同岩溶分布段(1)及以上部位的桩孔(6)直径。5. The karst unfilled cast-in-situ pile structure according to claim 1, characterized in that: the diameter of the pile hole (6) is larger than the designed pile diameter (5) of the cast-in-place pile, and the karst distribution section (1) and above parts The diameter of the pile hole (6) is the inner diameter of the long steel casing (13), and is not less than the design pile diameter (5) + 2 times the thickness of the design reinforcement cage protective layer + 2 times the thickness of the additional reinforcement cage protection layer; in the karst distribution section (1 ) diameter of the pile hole (6) is based on whether the long steel casing (13) is followed up or not. If the long steel casing (13) is not followed up, the diameter of the pile hole (6) is generally the design pile diameter ( 5), otherwise it is the same as the pile hole (6) diameter of the karst distribution section (1) and the above position. 6.根据权利要求1所述的岩溶无填充灌注桩结构,其特征在于:所述镀锌钢护筒外增设螺旋加强箍筋。6. The karst non-filled cast-in-situ pile structure according to claim 1, characterized in that: spiral reinforcement stirrups are added outside the galvanized steel casing. 7.根据权利要求1所述的岩溶无填充灌注桩结构,其特征在于:所述设计钢筋笼与所述附加钢筋笼采用支撑钢筋(10)焊接固定构成组合钢筋笼。7. The karst unfilled cast-in-place pile structure according to claim 1, characterized in that: the design reinforcement cage and the additional reinforcement cage are welded and fixed by supporting reinforcement bars (10) to form a combined reinforcement cage. 8.一种岩溶无填充灌注桩施工方法结构,其特征在于,包括:8. A karst non-filled cast-in-situ pile construction method structure, characterized in that it includes: 场地平整、桩位放样、泥浆制备、长钢护筒(13)制作、材料准备等;Site leveling, stake setting, mud preparation, long steel casing (13) production, material preparation, etc.; 桩基成孔设备与长钢护筒(13)配套,开挖灌注桩至嵌岩深度,开挖过程中配合地勘报告,记录岩溶起始位置,终孔验收与一次清孔,所述长钢护筒(13)内形成桩孔(6),长钢护筒(13)底标高低于岩溶分布段(1)最低位置一定深度;The pile foundation hole-forming equipment is matched with the long steel casing (13), and the cast-in-situ piles are excavated to the depth of the rock-socketed. A pile hole (6) is formed in the steel casing (13), and the bottom elevation of the long steel casing (13) is lower than a certain depth at the lowest position of the karst distribution section (1); 根据岩溶无填充等不良地层起始位置,确定设计钢筋笼上需要增设附加钢筋笼的位置与长度;According to the starting position of unfavorable formations such as karst without filling, determine the position and length of the additional reinforcement cage on the design reinforcement cage; 设计钢筋笼制作,附加钢筋笼制作;Design reinforcement cage fabrication, additional reinforcement cage fabrication; 附加钢筋笼安装,外侧覆盖镀锌钢丝网与密目尼龙网(11)或套设镀锌钢护筒,形成灌注桩组合钢筋笼结构;Additional reinforcement cage installation, the outer side is covered with galvanized steel wire mesh and dense mesh nylon mesh (11) or set with galvanized steel casing to form a composite reinforcement cage structure for cast-in-situ piles; 桩孔(6)内灌注桩组合钢筋笼吊放,沉渣厚度测量与二次清孔;The cast-in-place pile combination reinforcement cage in the pile hole (6) is hoisted, the thickness of the sediment is measured and the hole is cleaned for the second time; 导管安装,向桩孔(6)内灌注桩身混凝土形成灌注桩;The conduit is installed, pouring pile body concrete into the pile hole (6) to form a cast-in-situ pile; 机械设备起拔长钢护筒。Mechanical equipment pulls out the long steel casing. 9.根据权利要求8所述的岩溶无填充灌注桩结构施工方法,其特征在于:附加纵向钢筋笼与原设计钢筋笼之间的净距应≥D mm;9. The construction method of karst unfilled cast-in-situ pile structure according to claim 8, characterized in that: the net distance between the additional longitudinal reinforcement cage and the originally designed reinforcement cage should be ≥ D mm; 其中,针对无水环境,D的取值为35,针对有水环境,D的取值为50;Among them, for an anhydrous environment, the value of D is 35, and for a water environment, the value of D is 50; 浇灌混凝土时,长钢护筒底端位置一般低于混凝土浇筑面标高≮10m。When pouring concrete, the bottom end of the long steel casing is generally ≮10m below the level of the concrete pouring surface. 10.根据权利要求8所述的岩溶无填充灌注桩结构施工方法,其特征在于:所述长钢护筒的直径比灌注桩的设计桩径(5)至少大S mm;10. karst no-fill cast-in-place pile structure construction method according to claim 8, is characterized in that: the diameter of described long steel casing is at least larger than the design pile diameter (5) of cast-in-place pile by 8 mm; 其中,针对无水环境,S的取值为140,针对有水环境,S的取值为200。Wherein, for an anhydrous environment, the value of S is 140, and for a water environment, the value of S is 200.
CN202310152380.XA 2023-02-22 2023-02-22 Karst filling-free filling pile structure and construction method thereof Pending CN116446385A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310152380.XA CN116446385A (en) 2023-02-22 2023-02-22 Karst filling-free filling pile structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310152380.XA CN116446385A (en) 2023-02-22 2023-02-22 Karst filling-free filling pile structure and construction method thereof

Publications (1)

Publication Number Publication Date
CN116446385A true CN116446385A (en) 2023-07-18

Family

ID=87134500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310152380.XA Pending CN116446385A (en) 2023-02-22 2023-02-22 Karst filling-free filling pile structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN116446385A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116892203A (en) * 2023-08-14 2023-10-17 中建海峡建设发展有限公司 A steel cage structure suitable for adverse geological environments and its construction method
CN117702722A (en) * 2023-12-13 2024-03-15 中交建筑集团有限公司 A steel mesh formwork cast-in-place pile structure and construction method suitable for high-rise buildings in karst areas

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108894214A (en) * 2018-08-27 2018-11-27 孙德明 A kind of solution cavity geological environment bored concrete pile and its bore forming method
CN111851478A (en) * 2020-07-13 2020-10-30 深圳市工勘岩土集团有限公司 Pile-forming construction method for light corrugated steel pile casing isolation non-filling karst cave filling pile
CN113356190A (en) * 2021-05-08 2021-09-07 深圳市工勘岩土集团有限公司 Pile forming method for cast-in-place pile in karst development area
US20210292987A1 (en) * 2020-03-19 2021-09-23 Guangzhou Institute Of Building Science Co.,Ltd. Construction method for pouring concrete in karst cave
CN219343149U (en) * 2023-02-22 2023-07-14 湖南省第六工程有限公司 A kind of karst non-filling cast-in-place pile structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108894214A (en) * 2018-08-27 2018-11-27 孙德明 A kind of solution cavity geological environment bored concrete pile and its bore forming method
US20210292987A1 (en) * 2020-03-19 2021-09-23 Guangzhou Institute Of Building Science Co.,Ltd. Construction method for pouring concrete in karst cave
CN111851478A (en) * 2020-07-13 2020-10-30 深圳市工勘岩土集团有限公司 Pile-forming construction method for light corrugated steel pile casing isolation non-filling karst cave filling pile
CN113356190A (en) * 2021-05-08 2021-09-07 深圳市工勘岩土集团有限公司 Pile forming method for cast-in-place pile in karst development area
CN219343149U (en) * 2023-02-22 2023-07-14 湖南省第六工程有限公司 A kind of karst non-filling cast-in-place pile structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116892203A (en) * 2023-08-14 2023-10-17 中建海峡建设发展有限公司 A steel cage structure suitable for adverse geological environments and its construction method
CN117702722A (en) * 2023-12-13 2024-03-15 中交建筑集团有限公司 A steel mesh formwork cast-in-place pile structure and construction method suitable for high-rise buildings in karst areas
CN117702722B (en) * 2023-12-13 2025-01-28 中交建筑集团有限公司 A steel mesh cast-in-place pile structure and construction method suitable for high-rise buildings in karst areas

Similar Documents

Publication Publication Date Title
JP7266228B2 (en) Ultra-long and small-diameter borehole pile construction method
CN110106872A (en) A kind of super thick mud head of district casing concrete pouring of punched hole piles method
CN107724383B (en) Rotary digging cast-in-place pile construction method
CN112392400B (en) Hole forming construction process for slope protection pile in complex geological environment
CN102720186B (en) Underwater once pouring method for variable cross-section bored cast-in-place pile
CN112502139A (en) Construction method for excavation of deep pit by three-axis stirring pile curtain water stop and rotary digging cast-in-place pile support
CN104631438B (en) Long auger guncreting uplift pile construction method
CN110939303B (en) Semi-reverse construction method of cyclone pool
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN108894214A (en) A kind of solution cavity geological environment bored concrete pile and its bore forming method
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN110629747A (en) Full-casing full-rotation construction process for pile foundation under complex geological conditions
CN114703831A (en) Construction method of reinforced concrete cast-in-place pile under complex geological condition
CN103015429A (en) Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN114875972A (en) Open-cut top-down foundation pit main structure construction method
CN206721870U (en) A kind of long auger guncreting pile steel reinforcement cage
CN219343149U (en) A kind of karst non-filling cast-in-place pile structure
CN103215958A (en) Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area
CN114837213A (en) Tower crane foundation structure and construction method thereof
CN110777775A (en) Foundation pit structure and construction method thereof
CN110080779A (en) Tunnel tunnel bottom karst cave treatment construction method
CN114875898A (en) Construction method for bored cast-in-place pile by rotary excavation of steel long pile casing and arm guard in soft soil layer
CN114635450A (en) Construction method for permanent steel pipe structural column of covered and excavated station
CN108179759A (en) The underwater drill core slotting of driftway is without bottom sealing method
CN114439024A (en) A kind of steel pipe curtain auxiliary pile foundation hole forming construction technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination