CN116446303B - A method for simultaneous construction of single cantilever tower and beam of a steel truss cable-stayed bridge - Google Patents

A method for simultaneous construction of single cantilever tower and beam of a steel truss cable-stayed bridge

Info

Publication number
CN116446303B
CN116446303B CN202310288532.9A CN202310288532A CN116446303B CN 116446303 B CN116446303 B CN 116446303B CN 202310288532 A CN202310288532 A CN 202310288532A CN 116446303 B CN116446303 B CN 116446303B
Authority
CN
China
Prior art keywords
tower
cable
bridge
steel truss
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202310288532.9A
Other languages
Chinese (zh)
Other versions
CN116446303A (en
Inventor
王俊平
李猛
赵大伟
贾晓峰
孙燕荣
王连同
周立业
亓泽霖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Urban Construction Group Co Ltd
Shandong Quanjian Engineering Testing Co Ltd
Jinan Municipal Engineering Construction Group Co Ltd
Shandong Huitong Construction Group Co Ltd
Shandong Huiyou Municipal Garden Group Co Ltd
Original Assignee
Jinan Urban Construction Group Co Ltd
Shandong Quanjian Engineering Testing Co Ltd
Jinan Municipal Engineering Construction Group Co Ltd
Shandong Huitong Construction Group Co Ltd
Shandong Huiyou Municipal Garden Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Urban Construction Group Co Ltd, Shandong Quanjian Engineering Testing Co Ltd, Jinan Municipal Engineering Construction Group Co Ltd, Shandong Huitong Construction Group Co Ltd, Shandong Huiyou Municipal Garden Group Co Ltd filed Critical Jinan Urban Construction Group Co Ltd
Priority to CN202310288532.9A priority Critical patent/CN116446303B/en
Publication of CN116446303A publication Critical patent/CN116446303A/en
Application granted granted Critical
Publication of CN116446303B publication Critical patent/CN116446303B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/04Bearings; Hinges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/16Suspension cables; Cable clamps for suspension cables ; Pre- or post-stressed cables

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及桥梁施工技术领域,具体涉及到一种钢桁梁斜拉桥单悬臂塔梁同步施工方法。本发明索塔中塔柱向上施工时,同步安装墩顶节间,设置顺桥向及横桥向限位;钢桁梁边跨段架设完成后,采用塔吊在边跨节间上安装全回转吊机,索塔施工至相应节段;随着索塔向上施工,继续向中跨侧单悬臂安装钢桁梁,对称安装、张拉中边跨侧斜拉索,至全桥合龙。本发明索塔与钢桁梁单侧悬臂施工同时进行,解决了传统施工方案造价高、进度慢的问题。

This invention relates to the field of bridge construction technology, specifically to a method for simultaneous construction of a single cantilever tower and girder of a steel truss cable-stayed bridge. In this invention, during the upward construction of the tower column, the pier top segment is installed simultaneously, with longitudinal and transverse bridge-direction limits set. After the side span of the steel truss girder is erected, a tower crane is used to install a full-rotation crane on the side span segment, and the tower is constructed to the corresponding segment. As the tower continues to be constructed upwards, the steel truss girder is installed on the single cantilever side of the middle span, and the cable stays on the middle and side spans are symmetrically installed and tensioned until the entire bridge is closed. This invention allows for simultaneous construction of the tower and the single cantilever of the steel truss girder, solving the problems of high cost and slow progress associated with traditional construction methods.

Description

Synchronous construction method for Shan Xuanbei tower beams of steel truss girder cable-stayed bridge
Technical Field
The invention relates to the technical field of bridge construction, in particular to a synchronous construction method for a Shan Xuanbei tower beam of a steel truss girder cable-stayed bridge.
Background
The steel truss girder cable-stayed bridge is the most common bridge type of the large-span highway-railway dual-purpose cable-stayed bridge, and is favored by vast engineers due to the advantages of stable structural system, mature construction method, noninterference between highway layer and railway layer subareas and the like. In recent years, a large number of large-span highway-railway dual-purpose cable-stayed bridges such as Shangsu Tong Yangtze river highway-railway bridge, shangji Hangzhou railway turnip Yangtze river highway-railway bridge, copper tomb Yangtze river highway-railway bridge, white house temple Yangtze river bridge and the like are built successively and realize traffic, and good economic and social benefits are created. The construction method of the steel truss girder cable-stayed bridge is greatly influenced by the modeling, structural characteristics, topography, construction site conditions and the like of a cable-stayed tower, the overall construction method of the girder comprises a double-cantilever whole-section installation method, a double-cantilever loose splicing method, a pushing method, a shore side pushing mid-span cantilever loose splicing method and the like, and the construction method of the steel truss girder pier top internode comprises a whole-section hoisting method, a loose splicing sliding method and the like.
When the double-cantilever split-splicing method is adopted, two rotary cranes are required to be simultaneously put into, and the top position of the pier is required to be set with stronger temporary consolidation, so that on one hand, the temporary consolidation measure cost is increased, on the other hand, the girder construction difficulty is increased, and the favorable topography of the side span on the beach and polo area is not fully utilized.
When the traditional steel truss cable-stayed bridge tower beams are synchronously constructed, when the middle-span side steel truss girder segments are installed and the stay cables are tensioned, the main tower is closed, and the main defects are that the middle-span side steel truss girder segments can be installed after the cable tower is closed, the steel truss girder installation operation can not be simultaneously carried out when the cable tower construction is not realized, and the construction period is long.
Aiming at a steel truss girder cable-stayed bridge crossing a non-navigable river and having a main pier positioned in a beach polder area, a new construction method is required to be found to reduce the construction cost and accelerate the construction progress.
Disclosure of Invention
The invention provides a synchronous construction method for a Shan Xuanbei tower beam of a steel truss girder cable-stayed bridge, which aims to solve the defects in the prior art.
The invention is realized by the following technical scheme:
A synchronous construction method for a Shan Xuanbei tower beam of a steel truss girder cable-stayed bridge comprises the following steps:
The method comprises the steps of constructing a lower tower column, concrete brackets, a lower beam, auxiliary piers and side piers of a main pier cable tower, installing a pier-side bracket embedded part on the concrete surface in advance during construction of a main pier bearing platform and a tower seat, synchronously constructing a main pier cable tower section and the pier-side bracket, installing a temporary buttress at a side span part, and installing a side span side gantry crane.
And secondly, constructing a tower column in the main pier by adopting a hydraulic climbing die, installing a lower chord member between pier tops by adopting a crawler crane, arranging a sliding rail in the bridge direction, a vertical adjusting jack and a temporary cushion block, installing the lower chord member and a lower bridge deck system on the temporary pier tops on the side of the side span along the bridge direction, connecting the lower chord member and the lower bridge deck system into a whole by adopting high-strength bolts, lifting the lower chord member and removing the sliding rail in the bridge direction after the horizontal dragging jack and the finish rolling screw steel are dragged to a designated position, dropping the lower chord member onto a permanent support, and bolting and fixing the lower chord member and an upper steel plate of the permanent support.
And step three, sequentially installing a pier top internode straight web member, an inclined web member, an upper chord member, an upper middle bridge surface system and an inclined strut, installing a transverse bridge direction sliding rail on a lower cross beam of a cable tower, sliding the auxiliary truss rod to a designated position along the transverse bridge direction by adopting a horizontal dragging jack and finish rolling screw steel, adjusting the position of the auxiliary truss rod by adopting a vertical adjusting jack, connecting with the inclined strut, and installing an upper bridge surface system to complete the installation of the whole pier top internode steel member.
And fourthly, sequentially installing the rest steel truss members at the middle span and the side span of the pier top internode by adopting a crawler crane, and installing forward limit and transverse limit on the forward and transverse sides of the pier top permanent support at the bottom surface of the lower chord of the steel truss.
And fifthly, constructing a tower column on the cable tower, installing a first-section steel anchor beam and a cable guide pipe, and adopting a gantry crane to install the steel truss beam from the middle span to the side span until the main bridge side span steel truss beam is completely installed.
And step six, continuing to construct the cable tower upwards, adopting a tower crane to install a rotary crane at the side span position, and installing a girder loading trolley on the upper bridge deck.
And when the hydraulic climbing formwork climbs and the outlet end of the cable duct is exposed and has the installation condition of the stay cable, the first section steel truss girder at the midspan side is installed by adopting a rotary crane, the first section stay cable at the midspan side and the first section stay cable at the side are symmetrically installed, and the pier bracket is tensioned and removed.
And eighth, along with the upward construction of the cable tower, continuously installing the steel truss girder on the mid-span side in a single cantilever method, symmetrically tensioning corresponding stay cables on the mid-span side and the side span side, removing the temporary buttress under the steel truss girder in advance before tensioning the side span side stay cables, and removing the hydraulic climbing formwork after the cable tower is capped.
And step nine, the main bridge continues cantilever construction until closure, the forward limit and the transverse limit of the main pier are released, the angle, the elevation and the plane deviation of the steel trusses at the two ends of the closure opening are adjusted by adjusting the cable force of the stay cable, and the closure section steel trusses are installed by using a bridge deck crane.
And step ten, adjusting the cable force of the stay cable, installing a steel truss girder damper, and applying the damper to a bridge deck system and an accessory structure.
As a preferable scheme:
In the second step, the forward-bridge-direction sliding track is made of profile steel, the forward-bridge-direction sliding track is arranged along the center of the lower chord member, the elevation of the top of the forward-bridge-direction sliding track is 5-10cm higher than that of the permanent support, the bottom of the forward-bridge-direction sliding track is supported on the top surface of a concrete bracket or a pier side support distribution beam by adopting a steel plate, both ends of the permanent support are provided with temporary cushion blocks and vertical adjusting jacks, a tensioning counterforce seat is arranged on the top of the middle-span side forward-bridge-direction sliding track, a fixed end of finish-rolling deformed steel bar is anchored on a customizing tool at the end part of the lower chord member, and the horizontal dragging jacks are used for tensioning the finish-rolling deformed steel bar to realize forward-bridge-direction sliding of the lower chord member and a lower bridge panel.
In the third step, the pier top central internode straight web member, the upper chord member, the upper bridge deck system and the diagonal brace are all hoisted in place through the crawler crane, and the auxiliary truss rod is in place through a transverse sliding and dragging method.
In the third step, transverse bridge direction sliding rails are respectively arranged on the top surface of the lower cross beam of the cable tower, after the cable tower slides to a designated position, the vertical adjusting jack is adopted to jack up the auxiliary truss rod, then the transverse bridge direction sliding rails are removed, and the cable tower falls down to be connected with the inclined stay bars.
In the fifth step, before the steel truss reaches the next temporary buttress, the steel truss needs to be lifted by using the vertical adjusting jacks on the previous temporary buttress, and the lifting height is consistent with the downwarping height of the steel truss between the two temporary buttresses, so that the steel truss can be smoothly penetrated.
In the seventh step, the installation condition of the stay cable is that the tower column section where the first section of the stay cable steel anchor beam on the side of the middle span and the side span is located has completed annular prestress construction, the concrete age of the tower column section meets the 28-day requirement, 2-3 tower column sections are constructed above the tower column section, and after the hydraulic climbing formwork is climbed, the cable guide pipe is exposed out of the outer surface of the tower column.
In the step nine, when the cable tower is capped, the cable is required to complete 1/3-1/2 of the total number of installation tensioning operations.
The cable tower and the steel truss single-side cantilever construction are simultaneously carried out, so that the problems of high construction cost and slow progress of the traditional construction scheme are solved, new designs are carried out at each construction stage, the construction cost can be obviously reduced, the construction progress is quickened, and the total construction cost of the engineering is saved.
Additional advantages, objects, and features of the invention will be set forth in part in the description which follows and in part will become apparent to those having ordinary skill in the art upon examination of the following or may be learned from practice of the invention.
Drawings
FIG. 1 is a longitudinal section layout view of a cable-stayed bridge with steel trusses according to the embodiment;
FIG. 2 is a schematic diagram of a cross-sectional structure of a cable tower of the cable-stayed bridge of the steel truss girder of the embodiment;
FIG. 3 is a schematic diagram of a longitudinal section structure of a cable tower of the cable-stayed bridge with steel truss girder according to the embodiment;
FIG. 4 is a schematic view of the structure of the steel truss girder according to the present embodiment;
FIG. 5 is a schematic diagram showing a construction step of the present embodiment;
FIG. 6 is a schematic view of a cross section of a bottom chord member and a bottom deck assembly of a center section of a second pier top in this embodiment;
FIG. 7 is a schematic view of a bottom chord and deck assembly of a second pier top center section in accordance with the present embodiment;
FIG. 8 is a schematic diagram of the step two pier top center internode lower chord and lower deck system slippage in this embodiment;
FIG. 9 is a schematic view of the adjustment of the lower chords and the lower deck system drop beams of the center section of the second pier top in this embodiment;
FIG. 10 is a schematic view of the mounting cross section of the center internode straight web member, upper chord, etc. of the three pier top in this embodiment;
FIG. 11 is a schematic view of a vertical section of a three pier top center section straight web member, an upper chord member, etc. in this embodiment;
FIG. 12 is a schematic cross-sectional view of a sliding installation of a center section of a side truss rod at a top of a three pier in the present embodiment;
FIG. 13 is a schematic view of a sliding installation longitudinal section of a center section auxiliary truss rod of a three pier top in the embodiment;
FIG. 14 is a step four schematic diagram of the present embodiment;
FIG. 15 is a schematic view of the mounting cross section of the remaining steel truss members between four pier top joints in the step of this embodiment;
FIG. 16 is a fifth step diagram of the present embodiment;
FIG. 17 is a diagram illustrating a sixth step of the present embodiment;
FIG. 18 is a seventh schematic diagram of the step of the present embodiment;
FIG. 19 is a schematic diagram of a step eight of the present embodiment;
FIG. 20 is a schematic view of a maximum cantilever state of a nine-steel truss girder according to the step of the present embodiment;
fig. 21 is a schematic construction diagram of a closure section of a nine-steel truss girder in the step of this embodiment.
In the figure, 1, a cable tower, 2, a lower tower column, 3, a concrete bracket, 4, a lower cross beam, 5, a middle tower column, 6, an upper tower column, 7, a permanent support, 8, a steel truss girder, 9, a cable guide, 10, a steel anchor beam, 11, a lower chord, 12, an upper chord, 13, a lower bridge deck system, 14, an upper middle bridge deck system, 15, a secondary truss rod, 16, an upper bridge deck system, 17, a straight web member, 18, a diagonal web member, 19, a diagonal brace, 20, an auxiliary pier, 21, a side pier, 22, a hydraulic climbing die, 23, a tower crane, 24, a pier side bracket, 25, a temporary pier, 26, a gantry crane, 27, a forward bridge sliding track, 28, a vertical adjusting jack, 29, a temporary cushion block, 30, a crawler crane, 31, a counter-force seat, 32, a horizontal drag jack, a finish rolling screw, 34, a transverse bridge sliding track, 35, a gyrator, 36, a girder trolley, 37, a diagonal bridge, 38, a forward bridge, 39, a transverse bridge girder, and a limit girder.
Detailed Description
The present invention is described in further detail below with reference to the drawings to enable those skilled in the art to practice the invention by referring to the description.
It should be noted that, in the following embodiments, unless otherwise specified, the experimental methods are conventional methods, and the reagents and materials are commercially available, unless otherwise specified, and in the description of the present invention, the terms "horizontal", "longitudinal", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are merely for convenience in describing the present invention and simplifying the description, and do not indicate or imply that the apparatus or elements to be referred to must have specific orientations, be configured and operated in specific orientations, and therefore are not to be construed as limiting the present invention.
As shown in fig. 1, the main bridge of the steel truss cable-stayed bridge of the embodiment is a double-tower five-span steel truss cable-stayed bridge, the main bridge is not navigable across a water area, and the main pier, the auxiliary pier 20 and the side pier 21 are all positioned in a shore side beach polepiece area and are not interfered by flood.
As shown in fig. 2-4, the cable-stayed bridge tower 1 of the steel truss girder 8 is in a bottle shape as a whole, and the cable tower 1 comprises a lower tower column 2, a concrete bracket 3, a lower cross beam 4, a middle tower column 5 and an upper tower column 6. The steel truss girder 8 is in an inverted trapezoid shape, and the steel truss girder 8 comprises a lower chord member 11, an upper chord member 12, a lower bridge deck system 13, an upper middle bridge deck system 14, an auxiliary truss rod 15, an upper bridge deck system 16, a straight web member 17, an inclined web member 18 and an inclined strut member 19. The lower tower column 2 of the cable tower 1 inclines outwards, the middle tower column 5 inclines inwards, the upper tower column 6 is vertically upwards after closure, and gradually upwards reaches the tower crown along the cross section. The inner side wall of the lower tower column 2 is provided with a concrete bracket 3, a permanent support 7 is arranged on the concrete bracket 3, and the concrete bracket 3 is a vertical main stress member of the steel truss girder 8. The number of the lower cross beams 4 of the cable towers 1 is 2, a certain interval exists between the cross beams, the steel truss beam 8 pier top section straight web members 17 penetrate through the lower cross beams 4 of the two cable towers 1, the upper chord member 12, the auxiliary truss rod 15, the upper middle bridge surface system 14 and the upper bridge surface system 16 are all positioned above the lower cross beams 4 of the cable towers 1, and the steel anchor beam 10 and the cable guide pipe 9 are arranged at the upper tower column 6 section of the cable tower 1.
The synchronous construction method of the Shan Xuanbei tower beams of the steel truss girder cable-stayed bridge comprises the following steps:
Step one, as shown in fig. 5, constructing a lower tower column 2, a concrete bracket 3, a lower cross beam 4, an auxiliary pier 20 and an edge pier 21 of a main pier cable tower 1, and installing a pier side bracket 24 embedded part on the concrete surface in advance during construction of a main pier bearing platform and a tower seat, synchronously constructing a main pier cable tower 1 section and the pier side bracket 24, installing an edge-span part temporary supporting pier 25 and installing an edge-span side gantry crane 26.
6-9, Constructing a tower column 5 in the main pier by adopting a hydraulic climbing die 22, adopting a crawler crane 30 to install a pier top internode lower chord 11 along a bridge-direction sliding rail 27, adopting a vertical adjusting jack 28 and adopting a temporary cushion block 29, installing the lower chord 11 and a lower bridge deck system 13 on the side span side temporary buttress 25 along the bridge-direction sliding rail 27, adopting high-strength bolts to connect the lower chord 11 and the lower bridge deck system into a whole, adopting a horizontal dragging jack 32 and finish rolling screw steel 33 to drag to a designated position, lifting the lower chord 11, removing the along bridge-direction sliding rail 27, dropping the lower chord 11 onto a permanent support 7, and bolting and fixing the lower chord 11 with an upper steel plate of the permanent support 7.
In the second step, the forward-bridge sliding rail 27 is made of profile steel, the forward-bridge sliding rail 27 is arranged along the center of the lower chord 11, the top elevation of the forward-bridge sliding rail 27 is 5-10cm higher than that of the permanent support 7, steel plates are adopted to support the bottom of the rail to be on the top surface of the concrete bracket 3 or a pier side support distribution beam, temporary cushion blocks 29 and vertical adjusting jacks 28 are arranged at two ends of the permanent support 7, a tensioning counterforce seat 31 is arranged at the top of the midspan side forward-bridge sliding rail 27, the fixed end of a finish-rolling deformed steel 33 is anchored on a custom-made tool at the end part of the lower chord 11, and the horizontal traction jack 32 is adopted to finish-roll deformed steel 33, so that the forward-bridge sliding of the lower chord 11 and a lower bridge panel is realized.
10-13, Sequentially installing a pier top internode straight web member 17, an inclined web member 18, an upper chord member 12, an upper middle bridge surface system 14 and an inclined strut 19, installing a transverse bridge direction sliding rail 34 on the lower beam 4 of the cable tower 1, sliding the auxiliary truss rod 15 to a designated position along the transverse bridge direction by adopting a horizontal dragging jack 32 and a finish rolling screw steel 33, adjusting the position of the auxiliary truss rod 15 by adopting a vertical adjusting jack 28, connecting with the inclined strut 19, installing an upper bridge surface system 16, and completing the installation of the whole pier top internode steel member.
In the third step, the pier top central internode straight web member 17, the inclined web member 18, the upper chord member 12, the upper bridge deck system, the inclined strut 19 and other components can be lifted and positioned through the crawler 30, the auxiliary truss rod 15 is affected by the inward inclination of the middle tower column 5, the lifting and the positioning cannot be realized, and the transverse sliding and dragging method is adopted for positioning.
In the third step, a transverse bridge direction sliding rail 34 is respectively arranged along the top surface of the lower cross beam 4 of the cable tower 1, after the cable tower is slid to a designated position, the vertical adjusting jack 28 is adopted to jack up the auxiliary truss rod 15, then the transverse bridge direction sliding rail 34 is removed, and the cable tower falls down to be connected with the diagonal brace 19.
And fourthly, as shown in figures 14-15, sequentially installing the rest steel truss beam 8 components on the middle span and the side span of the pier top by adopting a crawler crane 30. And the pier top permanent support 7 is arranged on the bottom surface of the lower chord 11 of the steel truss girder 8 along the bridge direction and at the two sides along the transverse bridge direction, and a forward bridge direction limit 38 and a transverse bridge direction limit 39 are arranged.
And fifthly, as shown in figure 16, constructing a tower column 6 on the cable tower 1, installing a first-section steel anchor beam 10 and a cable guide pipe 9, and installing the steel truss beam 8 from the middle span to the side span by adopting a gantry crane 26 until the main bridge side span steel truss beam 8 is completely installed.
In the fifth step, before the steel truss girder 8 reaches the next temporary buttress 25, the steel truss girder 8 needs to be lifted by using the vertical adjusting jacks 28 on the previous temporary buttress 25, and the lifting height is consistent with the downwarping height of the steel truss girder 8 between the two temporary buttresses 25, so that the steel truss girder 8 can be smoothly passed through holes.
Step six, as shown in fig. 17, the cable tower 1 continues to be constructed upwards, a rotary crane 35 is installed at the side span position by adopting a tower crane 23, and a girder loading trolley 36 is installed on the upper bridge deck.
And step seven, as shown in figure 18, the cable tower 1 continues to be constructed upwards by adopting the hydraulic climbing mould 22, and after entering an anchor cable area, the steel anchor beam 10 and the cable guide pipe 9 are sequentially installed from bottom to top, when the hydraulic climbing mould 22 climbs, the outlet end of the cable guide pipe 9 is exposed and has the installation condition of the stay cable 37, the first section steel truss beam 8 of the first section on the midspan side is installed by adopting the rotary crane 35, the first section stay cable 37 on the midspan side and the first section stay cable 37 on the side are symmetrically installed, and the pier-side bracket 24 is tensioned and removed.
In the seventh step, the first section stay cable 37 on the middle span side and the side span side is installed under the condition that the section of the tower column where the steel anchor beam 10 of the first section stay cable 37 on the middle span side and the side span side is located has completed the circumferential prestress construction, the concrete age of the section of the tower column meets the requirement of 28 days, 2-3 sections of the tower column have been constructed above the section of the tower column, and after the hydraulic climbing mould 22 climbs, the cable guide pipe 9 is exposed on the outer surface of the tower column. The first section of the stay cable 37 on the midspan and side of the side span is synchronously threaded and tensioned at 4 points on the upstream side and the downstream side.
And step eight, as shown in figure 19, along with the upward construction of the cable tower 1, continuously installing the steel truss girder 8 on the mid-span side in a single cantilever method, symmetrically tensioning corresponding stay cables 37 on the mid-span side and the side-span side, and removing the temporary buttress 25 under the steel truss girder 8 in advance before tensioning the side-span side stay cables 37, and removing the hydraulic climbing formwork 22 after capping the cable tower 1.
Step nine, as shown in figures 20-21, the cantilever construction of the main bridge is continued until closure, the forward limit 38 and the transverse limit 39 of the main pier are released, the angle, the elevation and the plane deviation of the steel trusses 8 at the two ends of the closure opening are adjusted by adjusting the cable force of the stay cable 37, and the bridge deck crane is used for installing the closure section steel trusses 40.
When the cable tower 1 is capped, the stay cables 37 are required to complete 1/3-1/2 of the total number of installation tensioning operations, and the installation of the rest stay cables 37 and the steel truss girder 8 is not affected by the construction of the cable tower 1.
And step ten, adjusting the cable force of the stay cable 37, installing a damper of the steel truss girder 8, and applying the damper to a bridge deck system and an accessory structure.
Although embodiments of the present invention have been disclosed above, it is not limited to the details and embodiments shown and described, it is well suited to various fields of use for which the invention would be readily apparent to those skilled in the art, and accordingly, the invention is not limited to the specific details and illustrations shown and described herein, without departing from the general concepts defined in the claims and their equivalents.

Claims (7)

1.一种钢桁梁斜拉桥单悬臂塔梁同步施工方法,包括以下步骤:1. A method for simultaneous construction of a single cantilever tower and beam of a steel truss cable-stayed bridge, comprising the following steps: 步骤一:施工主墩索塔(1)下塔柱(2)、混凝土牛腿(3)、下横梁(4)及辅助墩(20)、边墩(21);主墩承台及塔座施工时,提前在混凝土表面安装墩旁托架(24)预埋件,主墩索塔(1)节段与墩旁托架(24)同步施工,安装边跨部位临时支墩(25),安装边跨侧龙门吊机(26);Step 1: Construct the main pier tower (1), lower tower column (2), concrete corbel (3), lower crossbeam (4), auxiliary pier (20), and side pier (21); When constructing the main pier foundation and tower base, install the pre-embedded parts of the pier side bracket (24) on the concrete surface in advance. The main pier tower (1) segment and the pier side bracket (24) are constructed simultaneously. Install the temporary support pier (25) at the side span and install the side span gantry crane (26). 步骤二:采用液压爬模(22)施工主墩中塔柱(5),采用履带吊(30)安装墩顶节间下弦杆(11)顺桥向滑移轨道(27)、竖向调节千斤顶(28)、临时垫块(29),在边跨侧临时支墩(25)顶顺桥向滑移轨道(27)上安装下弦杆(11)及下桥面系(13),采用高强螺栓连接成一整体,采用水平拖拉千斤顶(32)及精轧螺纹钢(33)拖拉至指定位置后,顶升下弦杆(11)并拆除顺桥向滑移轨道(27),下落下弦杆(11)至永久支座(7)上,将下弦杆(11)与永久支座(7)上钢板栓接固定;Step 2: The main pier tower column (5) is constructed using hydraulic climbing formwork (22). The lower chord (11) of the pier top section is installed using crawler crane (30) along the bridge direction sliding track (27), vertical adjusting jacks (28), and temporary pads (29). The lower chord (11) and the lower bridge deck system (13) are installed on the bridge direction sliding track (27) on the top of the temporary support pier (25) on the side span. They are connected into a whole using high-strength bolts. After being dragged to the designated position using horizontal dragging jacks (32) and precision rolled threaded steel (33), the lower chord (11) is lifted and the bridge direction sliding track (27) is removed. The lower chord (11) is lowered to the permanent support (7) and the lower chord (11) is bolted to the steel plate on the permanent support (7). 步骤三:依次安装墩顶节间直腹杆(17)、斜腹杆(18)、上弦杆(12)、上中桥面系(14)、斜撑杆(19),在索塔(1)下横梁(4)上安装横桥向滑移轨道(34),采用水平拖拉千斤顶(32)及精轧螺纹钢(33)沿横桥向将副桁杆(15)滑移至指定位置,采用竖向调节千斤顶(28)调整副桁杆(15)位置,与斜撑杆(19)连接,安装上边桥面系(16),完成整个墩顶节间钢构件安装;Step 3: Install the straight web members (17), diagonal web members (18), upper chord members (12), upper and middle bridge deck system (14), and diagonal bracing members (19) in sequence at the top of the pier. Install the transverse sliding track (34) on the lower crossbeam (4) of the tower (1). Use horizontal drag jacks (32) and precision rolled threaded steel bars (33) to slide the secondary truss (15) to the designated position along the transverse direction. Use vertical adjustment jacks (28) to adjust the position of the secondary truss (15) and connect it with the diagonal bracing members (19). Install the upper bridge deck system (16) to complete the installation of the entire steel components at the top of the pier. 步骤四:采用履带吊(30)依次安装墩顶节间中跨及边跨侧剩余钢桁梁(8)构件;在钢桁梁(8)下弦杆(11)底面位置墩顶永久支座(7)顺桥向及横桥向两侧安装顺桥向限位(38)及横桥向限位(39);Step 4: Use a crawler crane (30) to install the remaining steel truss beams (8) on the middle and side spans of the pier top section in sequence; install the longitudinal limiters (38) and transverse limiters (39) on both sides of the permanent support (7) at the bottom of the lower chord (11) of the steel truss beam (8) in the longitudinal and transverse directions. 步骤五:施工索塔(1)上塔柱(6),安装首节钢锚梁(10)及索导管(9);采用龙门吊机(26)自中跨向边跨侧安装钢桁梁(8),至主桥边跨钢桁梁(8)全部安装完成;Step 5: Construct the upper tower column (6) of the cable tower (1), install the first section of steel anchor beam (10) and cable guide (9); use a gantry crane (26) to install the steel truss beam (8) from the middle span to the side span until all the steel truss beams (8) of the main bridge side span are installed; 步骤六:索塔(1)继续向上施工,采用塔吊(23)在边跨位置安装回转吊机(35),并在上桥面安装运梁小车(36);Step 6: The tower (1) continues to be constructed upwards. A slewing crane (35) is installed at the side span position using a tower crane (23), and a beam transport trolley (36) is installed on the upper bridge deck. 步骤七:索塔(1)继续采用液压爬模(22)向上施工,进入锚索区后,自下而上依次安装钢锚梁(10)及索导管(9);当液压爬模(22)爬升,索导管(9)出口端外露且具备斜拉索(37)安装条件时,采用回转吊机(35)安装中跨侧第一个节段钢桁梁(8),对称安装中跨侧第一个节段斜拉索(37)、边跨侧第一个节段斜拉索(37),并张拉,拆除墩旁托架(24);Step 7: The cable tower (1) continues to be constructed upward using hydraulic climbing formwork (22). After entering the anchor cable area, steel anchor beams (10) and cable guide pipes (9) are installed sequentially from bottom to top. When the hydraulic climbing formwork (22) is ascending, the outlet end of the cable guide pipe (9) is exposed and the conditions for installing the stay cables (37) are met, the first segment of the steel truss beam (8) on the middle span side is installed using a rotary crane (35), and the first segment of the stay cables (37) on the middle span side and the first segment of the stay cables (37) on the side span side are symmetrically installed and tensioned. The brackets (24) beside the pier are then removed. 步骤八:随着索塔(1)向上施工,继续以单悬臂方法向跨中侧安装钢桁梁(8),对称张拉中跨侧、边跨侧相应斜拉索(37),边跨侧斜拉索(37)张拉前,提前拆除钢桁梁(8)下临时支墩(25),索塔(1)封顶后,拆除液压爬模(22);Step 8: As the tower (1) is constructed upward, continue to install the steel truss beam (8) towards the mid-span side using the single cantilever method, and symmetrically tension the corresponding stay cables (37) on the mid-span side and the side span side. Before tensioning the stay cables (37) on the side span side, remove the temporary support pier (25) under the steel truss beam (8) in advance. After the tower (1) is capped, remove the hydraulic climbing formwork (22). 步骤九:主桥继续悬臂施工至合龙前,解除主墩顺桥向限位(38)及横桥向限位(39),通过调整斜拉索(37)索力,调整合龙口两端钢桁梁(8)角度及高程、平面偏差,利用桥面吊机安装合龙段钢桁梁(40);Step 9: Before the main bridge is closed, the longitudinal (38) and transverse (39) limit of the main pier is released. The angle, elevation and plane deviation of the steel truss beams (8) at both ends of the closure section are adjusted by adjusting the cable force of the stay cable (37). The steel truss beams (40) of the closure section are installed using the bridge deck crane. 步骤十:调整斜拉索(37)索力,安装钢桁梁(8)阻尼器,施作桥面系及附属结构。Step 10: Adjust the cable tension of the stay cables (37), install the damper of the steel truss (8), and construct the bridge deck system and ancillary structures. 2.根据权利要求1所述的钢桁梁斜拉桥单悬臂塔梁同步施工方法,其特征在于:所述步骤二中,顺桥向滑移轨道(27)采用型钢制作,顺桥向沿下弦杆(11)中心布置,顺桥向滑移轨道(27)顶标高高于永久支座(7)5-10cm,顺桥向滑移轨道(27)底部采用钢板支垫在混凝土牛腿(3)顶面或墩旁支架分配梁上,永久支座(7)两端均设置临时垫块(29)及竖向调节千斤顶(28);张拉反力座(31)设置于中跨侧顺桥向滑移轨道(27)顶部,精轧螺纹钢(33)固定端锚固于下弦杆(11)端部定制工装上,采用水平拖拉千斤顶(32)张拉精轧螺纹钢(33),实现下弦杆(11)及下桥面板顺桥向滑移。2. The method for synchronous construction of single cantilever tower beam of steel truss cable-stayed bridge according to claim 1, characterized in that: in step two, the sliding track (27) along the bridge direction is made of steel and is arranged along the center of the lower chord (11) along the bridge direction. The top elevation of the sliding track (27) along the bridge direction is 5-10cm higher than the permanent support (7). The bottom of the sliding track (27) along the bridge direction is supported by steel plates on the top surface of the concrete corbel (3) or the distribution beam of the support next to the pier. Temporary pads (29) and vertical adjustment jacks (28) are set at both ends of the permanent support (7). The tensioning reaction seat (31) is set on the top of the sliding track (27) along the bridge direction on the middle span side. The fixed end of the fine rolled threaded steel (33) is anchored to the customized tooling at the end of the lower chord (11). The fine rolled threaded steel (33) is tensioned by the horizontal drag jack (32) to realize the sliding of the lower chord (11) and the lower bridge deck along the bridge direction. 3.根据权利要求1所述的钢桁梁斜拉桥单悬臂塔梁同步施工方法,其特征在于:所述步骤三中,墩顶中心节间直腹杆(17)、上弦杆(12)、上桥面系、斜撑杆(19)均通过履带吊(30)实现吊装就位,副桁杆(15)采用横向滑移拖拉方法就位。3. The method for synchronous construction of single cantilever tower beam of steel truss cable-stayed bridge according to claim 1, characterized in that: in step three, the straight web member (17), upper chord member (12), upper bridge deck system and diagonal brace (19) of the central section of the pier top are all hoisted into place by crawler crane (30), and the secondary truss member (15) is placed in place by lateral sliding and dragging method. 4.根据权利要求1所述的钢桁梁斜拉桥单悬臂塔梁同步施工方法,其特征在于:所述步骤三中,沿索塔(1)下横梁(4)顶面各设置横桥向滑移轨道(34),滑移至指定位置后,采用竖向调节千斤顶(28)顶起副桁杆(15)后拆除横桥向滑移轨道(34),落梁并与斜撑杆(19)进行连接。4. The method for synchronous construction of single cantilever tower beam of steel truss cable-stayed bridge according to claim 1, characterized in that: in step three, a transverse bridge sliding track (34) is set on the top surface of the lower crossbeam (4) of the tower (1). After sliding to the designated position, the secondary truss (15) is lifted by a vertical adjusting jack (28) and then the transverse bridge sliding track (34) is removed, and the beam is lowered and connected with the diagonal brace (19). 5.根据权利要求1所述的钢桁梁斜拉桥单悬臂塔梁同步施工方法,其特征在于:所述步骤五中,钢桁梁(8)到达下一组临时支墩(25)前,需利用前一组临时支墩(25)上的竖向调节千斤顶(28)将钢桁梁(8)顶升,顶升高度与两临时支墩(25)间钢桁梁(8)下挠高度一致,确保钢桁梁(8)能顺利过孔。5. The method for synchronous construction of single cantilever tower beam of steel truss cable-stayed bridge according to claim 1, characterized in that: in step five, before the steel truss beam (8) reaches the next set of temporary supports (25), the vertical adjustment jacks (28) on the previous set of temporary supports (25) are used to lift the steel truss beam (8), and the lifting height is consistent with the downward deflection height of the steel truss beam (8) between the two temporary supports (25), so as to ensure that the steel truss beam (8) can pass through the hole smoothly. 6.根据权利要求1所述的钢桁梁斜拉桥单悬臂塔梁同步施工方法,其特征在于:所述步骤七中,斜拉索(37)安装条件为中跨及边跨侧第一个节段斜拉索(37)钢锚梁(10)所处塔柱节段已完成环向预应力施工,该塔柱节段混凝土龄期满足28天要求,且该塔柱节段以上已施工完成2-3个塔柱节段,液压爬模(22)爬升后,索导管(9)已外露于塔柱外表面。6. The method for synchronous construction of single cantilever tower beam of steel truss cable-stayed bridge according to claim 1, characterized in that: in step seven, the installation conditions of the cable stay (37) are that the circumferential prestressing construction of the tower column segment where the first segment of cable stay (37) steel anchor beam (10) is located on the middle span and side span has been completed, the concrete age of the tower column segment meets the requirement of 28 days, and 2-3 tower column segments above the tower column segment have been constructed. After the hydraulic climbing formwork (22) is raised, the cable guide (9) is exposed on the outer surface of the tower column. 7.根据权利要求1所述的钢桁梁斜拉桥单悬臂塔梁同步施工方法,其特征在于:所述步骤九中,索塔(1)封顶时,斜拉索(37)要完成总体数量的1/3~1/2安装张拉作业。7. The method for synchronous construction of single cantilever tower beam of steel truss cable-stayed bridge according to claim 1, characterized in that: in step nine, when the tower (1) is capped, the cable stays (37) need to complete 1/3 to 1/2 of the total number of installation and tensioning operations.
CN202310288532.9A 2023-03-23 2023-03-23 A method for simultaneous construction of single cantilever tower and beam of a steel truss cable-stayed bridge Active CN116446303B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310288532.9A CN116446303B (en) 2023-03-23 2023-03-23 A method for simultaneous construction of single cantilever tower and beam of a steel truss cable-stayed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310288532.9A CN116446303B (en) 2023-03-23 2023-03-23 A method for simultaneous construction of single cantilever tower and beam of a steel truss cable-stayed bridge

Publications (2)

Publication Number Publication Date
CN116446303A CN116446303A (en) 2023-07-18
CN116446303B true CN116446303B (en) 2026-02-13

Family

ID=87123006

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310288532.9A Active CN116446303B (en) 2023-03-23 2023-03-23 A method for simultaneous construction of single cantilever tower and beam of a steel truss cable-stayed bridge

Country Status (1)

Country Link
CN (1) CN116446303B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117286805B (en) * 2023-10-09 2026-02-17 中交二航局第四工程有限公司 An installation process for asymmetric steel-concrete composite beams under complex transportation conditions
CN117211193A (en) * 2023-10-26 2023-12-12 中交路桥建设有限公司 A construction method of reverse construction of truss beams in the tower area of large-span cable-stayed bridges in mountainous areas
CN119711347B (en) * 2024-12-17 2025-12-02 中铁建大桥工程局集团第四工程有限公司 Construction method of three-tensioning of cable stays for super-large bridge towers

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561208A (en) * 2012-03-28 2012-07-11 中铁二院工程集团有限责任公司 Method of tower-girder spontaneous construction for railway steel trussed cable-stayed bridge
CN112695649A (en) * 2020-12-18 2021-04-23 中铁大桥局集团有限公司 Method for erecting whole-segment symmetrical double cantilevers of steel truss girder of large-span cable-stayed bridge on beach

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100969005B1 (en) * 2009-11-06 2010-07-09 동아대학교 산학협력단 Constructing method of suspension bridge and temporary cable therefor
CN102121234B (en) * 2011-04-23 2012-04-04 中铁三局集团有限公司 Quick construction method of two-tower five-span steel truss girder cable-stayed bridge
CN112663507B (en) * 2020-12-23 2022-11-15 浙江省大成建设集团有限公司 Tower beam synchronous construction method for short-tower cable-stayed bridge

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561208A (en) * 2012-03-28 2012-07-11 中铁二院工程集团有限责任公司 Method of tower-girder spontaneous construction for railway steel trussed cable-stayed bridge
CN112695649A (en) * 2020-12-18 2021-04-23 中铁大桥局集团有限公司 Method for erecting whole-segment symmetrical double cantilevers of steel truss girder of large-span cable-stayed bridge on beach

Also Published As

Publication number Publication date
CN116446303A (en) 2023-07-18

Similar Documents

Publication Publication Date Title
CN116446303B (en) A method for simultaneous construction of single cantilever tower and beam of a steel truss cable-stayed bridge
CN110042769B (en) Auxiliary span full-cantilever assembling construction method for composite beam cable-stayed bridge
CN106702910B (en) A kind of main girder construction technique of the double rope face low-pylon cable-stayed bridges of double tower
CN216891927U (en) Large-span double-layer combined construction steel truss arch bridge
CN101220580A (en) Longitudinal multi-point continuous drag construction method for steel truss girders
CN114781026B (en) A construction control method for a single-tilted-tower cable-stayed bridge
CN109629439B (en) Construction method of single-tower cable-stayed bridge
CN111593665B (en) Bridge construction method integrating dismantling and construction
CN116892172B (en) Method for erecting sections of public rail co-construction multi-span continuous steel truss bridge
CN110344334B (en) Construction method of two-span continuous steel-concrete composite bridge using back-cable bridge erecting machine
CN116479781B (en) A construction method for large-span precast steel-concrete composite beams
CN115075143B (en) Bridge tower column construction method
CN110396942B (en) Steel arch frame assembling and traversing system and method for upper bearing arch bridge construction
CN110093862B (en) Three-working-face bridge girder erection machine capable of realizing longitudinal and transverse assembly and bent cap non-channel segment assembly construction method
CN111485500A (en) Transverse lengthening reinforcing construction method and structure for retreating and dismantling of rhombic hanging basket
CN116065500A (en) Synchronization system and construction method of cable-stayed bridge tower and girder
CN112267369A (en) Non-span upright post steel trestle structure, pushing installation device and construction method
CN114561875A (en) Steel box girder jacking and high-position girder falling method
CN210684480U (en) Steel arch assembling and transverse moving system for deck type arch bridge construction
CN115652768A (en) Arch rib support system and installation method of a continuous asymmetric non-thrust arch bridge
CN115961549A (en) Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge
CN110438907B (en) Deck type arch bridge construction method based on steel arch frame
CN110438906B (en) Arch rib construction method for deck box type arch bridge
CN110438908B (en) Deck-type box-type arch bridge reconstruction construction method
CN110593117B (en) Steel box girder installation system and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant