CN116378356A - A construction method for continuous construction of a large-area floor with separate warehouse joints - Google Patents

A construction method for continuous construction of a large-area floor with separate warehouse joints Download PDF

Info

Publication number
CN116378356A
CN116378356A CN202310398189.3A CN202310398189A CN116378356A CN 116378356 A CN116378356 A CN 116378356A CN 202310398189 A CN202310398189 A CN 202310398189A CN 116378356 A CN116378356 A CN 116378356A
Authority
CN
China
Prior art keywords
floor
terrace
channel steel
construction
thickening layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202310398189.3A
Other languages
Chinese (zh)
Other versions
CN116378356B (en
Inventor
许扬威
何辉祥
赖建
李绍承
丁明忠
余波云
瞿士钦
魏义佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ycih No6 Construction Co ltd
Original Assignee
Ycih No6 Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ycih No6 Construction Co ltd filed Critical Ycih No6 Construction Co ltd
Priority to CN202310398189.3A priority Critical patent/CN116378356B/en
Publication of CN116378356A publication Critical patent/CN116378356A/en
Application granted granted Critical
Publication of CN116378356B publication Critical patent/CN116378356B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
    • E04F15/14Construction of joints, e.g. dividing strips
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
    • E04F15/14Construction of joints, e.g. dividing strips
    • E04F15/142Dividing strips or boundary strips
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a method for constructing a dividing seam of a large-area terrace, which comprises the steps of firstly planning the position of the dividing seam according to the size and the area of a terrace dividing block; arranging a terrace thickening layer at the position of a dividing seam of the terrace, and alternately paving thickened layer reinforcing bars in the terrace thickening layer and a terrace region; transverse ribs and longitudinal ribs are arranged on the terrace and the terrace thickening layer in a staggered mode; after the construction of the terrace thickening layer is completed, a pair of channel steels with the same thickness as the terrace is adopted to separate the terrace; the channel steel is fixed through a steel bar diagonal brace; the flatness and straightness of the channel steel are adjusted to ensure the flatness and the corner straightness of the terrace concrete; after the channel steel is arranged at the dividing seams, the adjacent concrete of the dividing seams can realize continuous pouring; and after pouring, the gap between the sub-warehouse joints is filled with flexible high-strength epoxy resin. According to the invention, the channel steel is wrapped at the dividing seam, so that the corner damage at the dividing junction of the terrace is avoided, and the service life of terrace concrete is prolonged.

Description

一种大面积地坪可连续施工的分仓缝施工方法A construction method for continuous construction of a large-area floor with separate warehouse joints

技术领域technical field

本发明属于建筑施工中地面工程施工技术领域,具体涉及一种大面积地坪可连续施工的分仓缝施工方法。The invention belongs to the technical field of ground engineering construction in building construction, and in particular relates to a construction method for sub-storage joints that can be continuously constructed on large-area floors.

背景技术Background technique

随着近年来新能源、医药、生物科技、装配式建造等新兴产业的迅猛发展,大面积地坪在工业厂房、停车楼、商业广场等建筑领域中广泛应用。大面积地坪对裂缝控制及平整度要求较高,在施工过程中采取有效的技术措施,避免地面裂缝、确保平整度和满足使用功能要求显得尤为重要。With the rapid development of emerging industries such as new energy, medicine, biotechnology, and prefabricated construction in recent years, large-area floors are widely used in construction fields such as industrial plants, parking buildings, and commercial plazas. Large-area floors have high requirements for crack control and flatness. It is particularly important to take effective technical measures during the construction process to avoid ground cracks, ensure flatness, and meet functional requirements.

针对大面积地坪混凝土易发生温度收缩裂缝的问题,传统工艺主要采取延长间隔时间或“跳仓施工”的方法,使用模板将大面积地坪进行分隔,隔仓进行浇筑,待混凝土养护一段时间后再进行相邻仓格混凝土的浇筑;采用模板不仅无法连续施工,还易在拆模过程中导致边角的损坏,在浇筑相邻仓格前还需进行凿毛处理,凿除的混凝土渣难以清理干净,相邻仓格之间仍存在先浇混凝土与后浇混凝土之间产生的施工缝;存在影响混凝土成型质量、增加人工成本及施工周期较长等不足之处。In view of the problem that large-area floor concrete is prone to temperature shrinkage cracks, the traditional technology mainly adopts the method of extending the interval time or "jumping warehouse construction", using formwork to separate large-area floors, pouring in separate warehouses, and waiting for the concrete to cure for a period of time Then pour the concrete of the adjacent cells; the use of formwork not only cannot be used for continuous construction, but also easily causes damage to the corners during the form removal process. It is difficult to clean up, and there are still construction joints between the first poured concrete and the second poured concrete between adjacent storage cells; there are shortcomings such as affecting the quality of concrete molding, increasing labor costs, and long construction periods.

申请号为“201910738222 .6”、名称为“一种建筑工程地坪施工方法”,该专利采用的是“跳仓施工”(隔跨浇筑)的方式,该方式采用木方用做模板隔成条形区段,存在拆模时导致边角损坏以及产生施工缝等缺点。The application number is "201910738222 .6" and the name is "a construction method for construction engineering floor". The strip section has disadvantages such as corner damage and construction joints when the formwork is removed.

发明内容Contents of the invention

基于上述现有技术的不足,本发明的目的是提供一种大面积地坪可连续施工的分仓缝施工方法,该方法中,相邻仓格无需等待混凝土养护达到规定时间,可保证大面积地坪混凝土结构连续,无需拆模,可避免先浇混凝土与后浇混凝土之间因温度变化产生的裂缝。Based on the deficiencies of the above-mentioned prior art, the purpose of the present invention is to provide a continuous construction method for large-area floors with sub-storage joints. The concrete structure of the floor is continuous without formwork removal, which can avoid cracks caused by temperature changes between the first poured concrete and the latter poured concrete.

为了实现上述目的,本发明提供了如下技术方案:一种大面积地坪可连续施工的分仓缝施工方法,步骤如下:In order to achieve the above object, the present invention provides the following technical proposal: a construction method for continuous construction of a large-area floor with separate warehouse joints, the steps are as follows:

步骤1:根据地坪分块尺寸和面积大小,规划出分仓缝的位置;Step 1: According to the floor block size and area size, plan the position of the warehouse joint;

步骤2:在地坪的分仓缝位置设置地坪加厚层,并在地坪加厚层和地坪区域内交错铺设加厚层配筋;在地坪以及地坪加厚层上交错配置有横向筋和纵向筋;Step 2: Set the floor thickening layer at the position of the sub-storey joint of the floor, and lay the reinforcement of the thickening layer alternately in the floor thickening layer and the floor area; staggered arrangement on the floor and the floor thickening layer There are transverse ribs and longitudinal ribs;

步骤3:地坪加厚层施工完成后,采用与地坪厚度相同的一对槽钢对地坪进行分隔处理;槽钢通过钢筋斜撑固定;Step 3: After the construction of the thickening layer of the floor is completed, a pair of channel steel with the same thickness as the floor is used to separate the floor; the channel steel is fixed by a steel bar brace;

步骤4:调整槽钢的平整度及顺直度保证地坪混凝土平整度和边角顺直度;Step 4: Adjust the flatness and straightness of the channel steel to ensure the flatness and straightness of the floor concrete;

步骤5:分仓缝设置好槽钢后,相邻仓格混凝土可实现连续浇筑;浇筑完成后分仓缝间采用柔性高强环氧树脂填缝,减少相互之间的约束力。Step 5: After the channel steel is set in the joints of the warehouses, the concrete of the adjacent warehouses can be poured continuously; after the pouring is completed, the joints between the warehouses are filled with flexible high-strength epoxy resin to reduce the binding force between them.

进一步地,在地坪与槽钢之间通过砂浆进行找平。Further, leveling is carried out with mortar between the floor and the channel steel.

进一步地,钢筋斜撑由斜撑和两根支撑杆组成,两根支撑杆平行设置,其中一根支撑杆竖直设置在槽钢一侧,另一根支撑杆竖直设置在地坪加厚层上,两根支撑杆之间倾斜固定斜撑。Further, the steel bar diagonal brace is composed of a diagonal brace and two support rods, and the two support rods are arranged in parallel, one of which is vertically arranged on one side of the channel steel, and the other vertically arranged on the thickened floor. On the first floor, the oblique braces are fixed obliquely between the two support rods.

进一步地,加厚层配筋为Z字型结构,且加厚层配筋的两端设有固定钩。Further, the reinforcement of the thickened layer has a Z-shaped structure, and the two ends of the reinforcement of the thickened layer are provided with fixing hooks.

进一步地,横向筋的两端设有固定钩。Further, fixing hooks are provided at both ends of the transverse rib.

本发明一方面通过调整槽钢的平整度及顺直度来保证地坪混凝土平整度和边角顺直度,另一方面,通过在分仓缝处用槽钢包裹,避免地坪分仓交接处的边角损坏,延长地坪混凝土使用寿命。本发明能够保证混凝土成型质量、节约成本,大大缩短施工工期。On the one hand, the present invention ensures the flatness and straightness of the floor concrete by adjusting the flatness and straightness of the channel steel; Damage to the corners of the floor and prolong the service life of the floor concrete. The invention can ensure the quality of concrete molding, save costs and greatly shorten the construction period.

附图说明Description of drawings

图1为本发明分仓缝的位置图;Fig. 1 is the position diagram of the sub-storey seam of the present invention;

图2为钢筋斜撑与槽钢的连接关系图。Figure 2 is a diagram of the connection relationship between the steel bar brace and the channel steel.

实施方式Implementation

为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.

本领域技术人员将会理解,下列实施例仅用于说明本发明,而不应视为限定本发明的范围。实施例中未注明具体技术、连接关系或条件者,按照本领域内的文献所描述的技术、连接关系、条件或者按照产品说明书进行。所用材料、仪器或设备未注明生产厂商者,均为可以通过购买获得的常规产品。Those skilled in the art will understand that the following examples are only for illustrating the present invention and should not be considered as limiting the scope of the present invention. If no specific technology, connection relationship or condition is indicated in the embodiment, it shall be carried out according to the technology, connection relationship and condition described in the literature in this field or according to the product specification. The materials, instruments or equipment used are not indicated by the manufacturer, and they are all conventional products that can be obtained through purchase.

结合图1和图2所示,本发明提供的一种大面积地坪可连续施工的分仓缝施工方法,步骤如下:As shown in Fig. 1 and Fig. 2, the present invention provides a continuous construction method for sub-storage joints on large-area floors. The steps are as follows:

步骤1:根据地坪分块尺寸和面积大小,提前规划出分仓缝的位置;Step 1: According to the floor block size and area size, plan the position of the warehouse joint in advance;

步骤2:在地坪3的分仓缝位置设置地坪加厚层1(地坪加厚层1位于分仓缝下方),并在地坪加厚层1和地坪3区域内交错铺设加厚层配筋2;加厚层的配筋及厚度同地坪,保证地坪结构连续;在地坪3以及地坪加厚层1上交错配置有横向筋4和纵向筋5;Step 2: Set the floor thickening layer 1 at the position of the sub-storage joint of the floor 3 (the floor thickening layer 1 is located below the sub-storage joint), and lay the thickening layer 1 and the floor 3 alternately in the area of the floor thickening layer 1 Thick layer reinforcement 2; the reinforcement and thickness of the thickened layer are the same as that of the floor to ensure the continuity of the floor structure; horizontal reinforcement 4 and longitudinal reinforcement 5 are arranged alternately on the floor 3 and the thickened layer 1 of the floor;

步骤3:地坪加厚层1施工完成后,采用与地坪3厚度相同的一对槽钢6对地坪3进行分隔处理(槽钢对称设置),并预先在地坪3与槽钢6之间通过砂浆10进行找平;槽钢6通过钢筋斜撑8固定,在浇筑混凝土时可起到支撑作用,同时可与混凝土连为整体,避免脱空;分仓缝处用槽钢包裹后,可避免地坪分仓交接处的边角损坏,延长地坪混凝土使用寿命,成型效果好,美观实用;Step 3: After the construction of the floor thickening layer 1 is completed, a pair of channel steel 6 with the same thickness as the floor 3 is used to separate the floor 3 (the channel steel is symmetrically arranged), and the floor 3 and the channel steel 6 are pre-installed. leveling by mortar 10; the channel steel 6 is fixed by the steel bar brace 8, which can play a supporting role when pouring concrete, and at the same time can be connected with the concrete as a whole to avoid emptying; It can avoid damage to the corners at the junction of the floor sub-warehouses, prolong the service life of the floor concrete, good molding effect, beautiful and practical;

步骤4:调整槽钢6的平整度及顺直度保证地坪混凝土平整度和边角顺直度;Step 4: Adjust the flatness and straightness of the channel steel 6 to ensure the flatness and straightness of the floor concrete;

步骤5:分仓缝设置好槽钢后,相邻仓格混凝土可实现连续浇筑;浇筑完成后分仓缝间采用柔性高强环氧树脂7填缝,减少相互之间的约束力,在保证地坪结构连续的同时有效减少因混凝土发生应变产生的裂缝。Step 5: After the channel steel is set in the joints of the warehouses, the concrete of the adjacent warehouses can be poured continuously; after the pouring is completed, the joints of the warehouses are filled with flexible high-strength epoxy resin 7 to reduce the binding force between them. While the flat structure is continuous, it can effectively reduce the cracks caused by the strain of the concrete.

具体地,钢筋斜撑8由斜撑和两根支撑杆组成,两根支撑杆平行设置,其中一根支撑杆竖直设置在槽钢6一侧,另一根支撑杆竖直设置在地坪加厚层1上,两根支撑杆之间倾斜固定斜撑。Specifically, the reinforced diagonal brace 8 is composed of a diagonal brace and two support rods, and the two support rods are arranged in parallel, one of which is vertically arranged on the side of the channel steel 6, and the other vertically arranged on the floor On the thickened layer 1, the oblique braces are fixed obliquely between the two support rods.

进一步优化方案,加厚层配筋2为Z字型结构,且加厚层配筋2的两端设有固定钩9;横向筋4的两端也设有固定钩9,固定钩9钩在纵向筋上,增加整体的稳定性。To further optimize the scheme, the thickened layer reinforcement 2 is a Z-shaped structure, and the two ends of the thickened layer reinforcement 2 are provided with fixed hooks 9; the two ends of the transverse reinforcement 4 are also provided with fixed hooks 9, and the fixed hooks 9 are hooked on The longitudinal ribs increase the overall stability.

以上所述仅为本发明的较佳实施方式,本发明并不局限于上述实施方式,在实施过程中可能存在局部微小的结构改动,如果对本发明的各种改动或变型不脱离本发明的精神和范围,且属于本发明的权利要求和等同技术范围之内,则本发明也意图包含这些改动和变型。The above description is only a preferred embodiment of the present invention, the present invention is not limited to the above embodiment, there may be local minor structural changes during the implementation process, if the various changes or modifications of the present invention do not depart from the spirit of the present invention and scope, and belong to the claims and equivalent technical scope of the present invention, the present invention also intends to include these changes and modifications.

Claims (5)

1.一种大面积地坪可连续施工的分仓缝施工方法,其特征在于,步骤如下:1. A kind of sub-cang joint construction method that large-area floor can be constructed continuously, it is characterized in that, the steps are as follows: 步骤1:根据地坪分块尺寸和面积大小,规划出分仓缝的位置;Step 1: According to the floor block size and area size, plan the position of the warehouse joint; 步骤2:在地坪(3)的分仓缝位置设置地坪加厚层(1),并在地坪加厚层(1)和地坪(3)区域内交错铺设加厚层配筋(2);在地坪(3)以及地坪加厚层(1)上交错配置有横向筋(4)和纵向筋(5);Step 2: Set the floor thickening layer (1) at the position of the sub-storey joint of the floor (3), and lay the reinforcement of the thickening layer alternately in the area of the floor thickening layer (1) and the floor (3) ( 2); transverse ribs (4) and longitudinal ribs (5) are alternately arranged on the floor (3) and the floor thickening layer (1); 步骤3:地坪加厚层(1)施工完成后,采用与地坪(3)厚度相同的一对槽钢(6)对地坪(3)进行分隔处理;槽钢(6)通过钢筋斜撑(8)固定;Step 3: After the construction of the floor thickening layer (1) is completed, use a pair of channel steel (6) with the same thickness as the floor (3) to separate the floor (3); Support (8) is fixed; 步骤4:调整槽钢(6)的平整度及顺直度保证地坪混凝土平整度和边角顺直度;Step 4: Adjust the flatness and straightness of the channel steel (6) to ensure the flatness and straightness of the corners of the floor concrete; 步骤5:分仓缝设置好槽钢后,相邻仓格混凝土可实现连续浇筑;浇筑完成后分仓缝间采用柔性高强环氧树脂(7)填缝,减少相互之间的约束力。Step 5: After the channel steel is set in the joints of the warehouses, the concrete of the adjacent warehouses can be poured continuously; after the pouring is completed, the joints of the warehouses are filled with flexible high-strength epoxy resin (7) to reduce the binding force between them. 2.根据权利要求1所述的一种大面积地坪可连续施工的分仓缝施工方法,其特征在于,在地坪(3)与槽钢(6)之间通过砂浆(10)进行找平。2. The construction method for continuous construction of a large-area floor according to claim 1, characterized in that, leveling is carried out between the floor (3) and the channel steel (6) by mortar (10) . 3.根据权利要求1所述的一种大面积地坪可连续施工的分仓缝施工方法,其特征在于,钢筋斜撑(8)由斜撑和两根支撑杆组成,两根支撑杆平行设置,其中一根支撑杆竖直设置在槽钢(6)一侧,另一根支撑杆竖直设置在地坪加厚层(1)上,两根支撑杆之间倾斜固定斜撑。3. A construction method for continuous construction of large-area floor joints according to claim 1, characterized in that the reinforced diagonal brace (8) is composed of a diagonal brace and two support rods, and the two support rods are parallel to each other. Setting, one of the support rods is vertically arranged on one side of the channel steel (6), the other support rod is vertically arranged on the floor thickening layer (1), and the diagonal brace is fixed obliquely between the two support rods. 4.根据权利要求1所述的一种大面积地坪可连续施工的分仓缝施工方法,其特征在于,加厚层配筋(2)为Z字型结构,且加厚层配筋(2)的两端设有固定钩(9)。4. A construction method for continuous construction of large-area floor joints according to claim 1, characterized in that the reinforcement of the thickened layer (2) is a Z-shaped structure, and the reinforcement of the thickened layer ( 2) Fixed hooks (9) are provided at both ends. 5.根据权利要求1所述的一种大面积地坪可连续施工的分仓缝施工方法,其特征在于,横向筋(4)的两端设有固定钩(9)。5. The construction method for continuous construction of a large-area floor with sub-storage joints according to claim 1, characterized in that, fixed hooks (9) are provided at both ends of the transverse ribs (4).
CN202310398189.3A 2023-04-14 2023-04-14 Construction method for dividing seam capable of continuously constructing large-area terrace Active CN116378356B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310398189.3A CN116378356B (en) 2023-04-14 2023-04-14 Construction method for dividing seam capable of continuously constructing large-area terrace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310398189.3A CN116378356B (en) 2023-04-14 2023-04-14 Construction method for dividing seam capable of continuously constructing large-area terrace

Publications (2)

Publication Number Publication Date
CN116378356A true CN116378356A (en) 2023-07-04
CN116378356B CN116378356B (en) 2025-05-02

Family

ID=86973049

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310398189.3A Active CN116378356B (en) 2023-04-14 2023-04-14 Construction method for dividing seam capable of continuously constructing large-area terrace

Country Status (1)

Country Link
CN (1) CN116378356B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118461851A (en) * 2024-07-09 2024-08-09 玉田县致泰钢纤维制造有限公司 Non-cracking terrace construction method with three-dimensional steel fiber skeleton
CN119195432A (en) * 2024-10-23 2024-12-27 中国五冶集团有限公司 A large area floor cutting-free construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101265749A (en) * 2008-04-29 2008-09-17 上海交通大学 Elevation-adjustable super-flat floor partition seam protection formwork system
CN105239495A (en) * 2015-10-30 2016-01-13 中国建筑第八工程局有限公司 Concrete side mold and mold support method thereof
CN207609126U (en) * 2017-11-30 2018-07-13 中建六局第三建筑工程有限公司 Armor for the super flat one-pass molding load bearing heat preserving terrace of super large stitches
CN110173090A (en) * 2019-06-20 2019-08-27 陕西建工集团有限公司 Zinc-plated plate integrated form parting seam and construction method
JP2020169463A (en) * 2019-04-02 2020-10-15 株式会社竹中工務店 Floor construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101265749A (en) * 2008-04-29 2008-09-17 上海交通大学 Elevation-adjustable super-flat floor partition seam protection formwork system
CN105239495A (en) * 2015-10-30 2016-01-13 中国建筑第八工程局有限公司 Concrete side mold and mold support method thereof
CN207609126U (en) * 2017-11-30 2018-07-13 中建六局第三建筑工程有限公司 Armor for the super flat one-pass molding load bearing heat preserving terrace of super large stitches
JP2020169463A (en) * 2019-04-02 2020-10-15 株式会社竹中工務店 Floor construction method
CN110173090A (en) * 2019-06-20 2019-08-27 陕西建工集团有限公司 Zinc-plated plate integrated form parting seam and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118461851A (en) * 2024-07-09 2024-08-09 玉田县致泰钢纤维制造有限公司 Non-cracking terrace construction method with three-dimensional steel fiber skeleton
CN119195432A (en) * 2024-10-23 2024-12-27 中国五冶集团有限公司 A large area floor cutting-free construction method

Also Published As

Publication number Publication date
CN116378356B (en) 2025-05-02

Similar Documents

Publication Publication Date Title
CN206245209U (en) A kind of bridge floor attachment means for continuous deck simply supported girder bridge
CN105256713B (en) Semi-assembly type steel concrete composite beam and construction method thereof
CN116378356A (en) A construction method for continuous construction of a large-area floor with separate warehouse joints
CN102121227B (en) Combined bridge deck of arched corrugated steel plates and concrete
CN101851984A (en) A prefabricated steel-concrete composite beam
CN105178203B (en) A kind of method utilizing polyurethane cement composite and bar-mat reinforcement reinforcement bridge component
CN106480818A (en) Simply supported girder bridge composite connection board construction and its construction method
CN106906841A (en) One kind is used for lateral wall form bracing system construction
CN108252504A (en) Tube shear wall concrete structure large form hoisting type construction method and constructing device
CN108316120A (en) It can rapidly-assembled precast bridge and its construction method
CN206109960U (en) Steel that can be under construction fast concrete integrated configuration bridge
CN108240038A (en) Super plane concrete structure and construction method based on multi-level network form post-cast strip
CN114892511A (en) A wet seam construction method
CN106285721B (en) A kind of railway culvert method of construction based on sliding mode system
CN111255227A (en) Thermal insulation composite formwork and construction method applied to concrete in strong wind forest area
CN105926657B (en) A construction method for prefabricated concrete foundation slabs
CN206722216U (en) A kind of prefabricated girder of laminated floor slab
CN211142848U (en) A UHPC composite structure of corrugated steel plates for strengthening hollow slab girder bridges
CN209907616U (en) Cast-in-place floor construction joint side keeps off structure
CN207672389U (en) Roadbed concrete curb cast-in-place mould
CN214246715U (en) Box type steel pipe reinforced concrete frame beam
CN211655696U (en) Precast concrete cable trench
CN110348142B (en) Method of forming curved bridge with combined formwork support technology based on BIM
CN211899624U (en) A reinforced concrete beam and slab post-cast belt temporary support system
CN211691048U (en) Composite heat-bridge-free self-insulation building block

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20251231

Granted publication date: 20250502