CN116378356A - A construction method for continuous construction of a large-area floor with separate warehouse joints - Google Patents
A construction method for continuous construction of a large-area floor with separate warehouse joints Download PDFInfo
- Publication number
- CN116378356A CN116378356A CN202310398189.3A CN202310398189A CN116378356A CN 116378356 A CN116378356 A CN 116378356A CN 202310398189 A CN202310398189 A CN 202310398189A CN 116378356 A CN116378356 A CN 116378356A
- Authority
- CN
- China
- Prior art keywords
- floor
- terrace
- channel steel
- construction
- thickening layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/12—Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/12—Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
- E04F15/14—Construction of joints, e.g. dividing strips
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/12—Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
- E04F15/14—Construction of joints, e.g. dividing strips
- E04F15/142—Dividing strips or boundary strips
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
Description
技术领域technical field
本发明属于建筑施工中地面工程施工技术领域,具体涉及一种大面积地坪可连续施工的分仓缝施工方法。The invention belongs to the technical field of ground engineering construction in building construction, and in particular relates to a construction method for sub-storage joints that can be continuously constructed on large-area floors.
背景技术Background technique
随着近年来新能源、医药、生物科技、装配式建造等新兴产业的迅猛发展,大面积地坪在工业厂房、停车楼、商业广场等建筑领域中广泛应用。大面积地坪对裂缝控制及平整度要求较高,在施工过程中采取有效的技术措施,避免地面裂缝、确保平整度和满足使用功能要求显得尤为重要。With the rapid development of emerging industries such as new energy, medicine, biotechnology, and prefabricated construction in recent years, large-area floors are widely used in construction fields such as industrial plants, parking buildings, and commercial plazas. Large-area floors have high requirements for crack control and flatness. It is particularly important to take effective technical measures during the construction process to avoid ground cracks, ensure flatness, and meet functional requirements.
针对大面积地坪混凝土易发生温度收缩裂缝的问题,传统工艺主要采取延长间隔时间或“跳仓施工”的方法,使用模板将大面积地坪进行分隔,隔仓进行浇筑,待混凝土养护一段时间后再进行相邻仓格混凝土的浇筑;采用模板不仅无法连续施工,还易在拆模过程中导致边角的损坏,在浇筑相邻仓格前还需进行凿毛处理,凿除的混凝土渣难以清理干净,相邻仓格之间仍存在先浇混凝土与后浇混凝土之间产生的施工缝;存在影响混凝土成型质量、增加人工成本及施工周期较长等不足之处。In view of the problem that large-area floor concrete is prone to temperature shrinkage cracks, the traditional technology mainly adopts the method of extending the interval time or "jumping warehouse construction", using formwork to separate large-area floors, pouring in separate warehouses, and waiting for the concrete to cure for a period of time Then pour the concrete of the adjacent cells; the use of formwork not only cannot be used for continuous construction, but also easily causes damage to the corners during the form removal process. It is difficult to clean up, and there are still construction joints between the first poured concrete and the second poured concrete between adjacent storage cells; there are shortcomings such as affecting the quality of concrete molding, increasing labor costs, and long construction periods.
申请号为“201910738222 .6”、名称为“一种建筑工程地坪施工方法”,该专利采用的是“跳仓施工”(隔跨浇筑)的方式,该方式采用木方用做模板隔成条形区段,存在拆模时导致边角损坏以及产生施工缝等缺点。The application number is "201910738222 .6" and the name is "a construction method for construction engineering floor". The strip section has disadvantages such as corner damage and construction joints when the formwork is removed.
发明内容Contents of the invention
基于上述现有技术的不足,本发明的目的是提供一种大面积地坪可连续施工的分仓缝施工方法,该方法中,相邻仓格无需等待混凝土养护达到规定时间,可保证大面积地坪混凝土结构连续,无需拆模,可避免先浇混凝土与后浇混凝土之间因温度变化产生的裂缝。Based on the deficiencies of the above-mentioned prior art, the purpose of the present invention is to provide a continuous construction method for large-area floors with sub-storage joints. The concrete structure of the floor is continuous without formwork removal, which can avoid cracks caused by temperature changes between the first poured concrete and the latter poured concrete.
为了实现上述目的,本发明提供了如下技术方案:一种大面积地坪可连续施工的分仓缝施工方法,步骤如下:In order to achieve the above object, the present invention provides the following technical proposal: a construction method for continuous construction of a large-area floor with separate warehouse joints, the steps are as follows:
步骤1:根据地坪分块尺寸和面积大小,规划出分仓缝的位置;Step 1: According to the floor block size and area size, plan the position of the warehouse joint;
步骤2:在地坪的分仓缝位置设置地坪加厚层,并在地坪加厚层和地坪区域内交错铺设加厚层配筋;在地坪以及地坪加厚层上交错配置有横向筋和纵向筋;Step 2: Set the floor thickening layer at the position of the sub-storey joint of the floor, and lay the reinforcement of the thickening layer alternately in the floor thickening layer and the floor area; staggered arrangement on the floor and the floor thickening layer There are transverse ribs and longitudinal ribs;
步骤3:地坪加厚层施工完成后,采用与地坪厚度相同的一对槽钢对地坪进行分隔处理;槽钢通过钢筋斜撑固定;Step 3: After the construction of the thickening layer of the floor is completed, a pair of channel steel with the same thickness as the floor is used to separate the floor; the channel steel is fixed by a steel bar brace;
步骤4:调整槽钢的平整度及顺直度保证地坪混凝土平整度和边角顺直度;Step 4: Adjust the flatness and straightness of the channel steel to ensure the flatness and straightness of the floor concrete;
步骤5:分仓缝设置好槽钢后,相邻仓格混凝土可实现连续浇筑;浇筑完成后分仓缝间采用柔性高强环氧树脂填缝,减少相互之间的约束力。Step 5: After the channel steel is set in the joints of the warehouses, the concrete of the adjacent warehouses can be poured continuously; after the pouring is completed, the joints between the warehouses are filled with flexible high-strength epoxy resin to reduce the binding force between them.
进一步地,在地坪与槽钢之间通过砂浆进行找平。Further, leveling is carried out with mortar between the floor and the channel steel.
进一步地,钢筋斜撑由斜撑和两根支撑杆组成,两根支撑杆平行设置,其中一根支撑杆竖直设置在槽钢一侧,另一根支撑杆竖直设置在地坪加厚层上,两根支撑杆之间倾斜固定斜撑。Further, the steel bar diagonal brace is composed of a diagonal brace and two support rods, and the two support rods are arranged in parallel, one of which is vertically arranged on one side of the channel steel, and the other vertically arranged on the thickened floor. On the first floor, the oblique braces are fixed obliquely between the two support rods.
进一步地,加厚层配筋为Z字型结构,且加厚层配筋的两端设有固定钩。Further, the reinforcement of the thickened layer has a Z-shaped structure, and the two ends of the reinforcement of the thickened layer are provided with fixing hooks.
进一步地,横向筋的两端设有固定钩。Further, fixing hooks are provided at both ends of the transverse rib.
本发明一方面通过调整槽钢的平整度及顺直度来保证地坪混凝土平整度和边角顺直度,另一方面,通过在分仓缝处用槽钢包裹,避免地坪分仓交接处的边角损坏,延长地坪混凝土使用寿命。本发明能够保证混凝土成型质量、节约成本,大大缩短施工工期。On the one hand, the present invention ensures the flatness and straightness of the floor concrete by adjusting the flatness and straightness of the channel steel; Damage to the corners of the floor and prolong the service life of the floor concrete. The invention can ensure the quality of concrete molding, save costs and greatly shorten the construction period.
附图说明Description of drawings
图1为本发明分仓缝的位置图;Fig. 1 is the position diagram of the sub-storey seam of the present invention;
图2为钢筋斜撑与槽钢的连接关系图。Figure 2 is a diagram of the connection relationship between the steel bar brace and the channel steel.
实施方式Implementation
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.
本领域技术人员将会理解,下列实施例仅用于说明本发明,而不应视为限定本发明的范围。实施例中未注明具体技术、连接关系或条件者,按照本领域内的文献所描述的技术、连接关系、条件或者按照产品说明书进行。所用材料、仪器或设备未注明生产厂商者,均为可以通过购买获得的常规产品。Those skilled in the art will understand that the following examples are only for illustrating the present invention and should not be considered as limiting the scope of the present invention. If no specific technology, connection relationship or condition is indicated in the embodiment, it shall be carried out according to the technology, connection relationship and condition described in the literature in this field or according to the product specification. The materials, instruments or equipment used are not indicated by the manufacturer, and they are all conventional products that can be obtained through purchase.
结合图1和图2所示,本发明提供的一种大面积地坪可连续施工的分仓缝施工方法,步骤如下:As shown in Fig. 1 and Fig. 2, the present invention provides a continuous construction method for sub-storage joints on large-area floors. The steps are as follows:
步骤1:根据地坪分块尺寸和面积大小,提前规划出分仓缝的位置;Step 1: According to the floor block size and area size, plan the position of the warehouse joint in advance;
步骤2:在地坪3的分仓缝位置设置地坪加厚层1(地坪加厚层1位于分仓缝下方),并在地坪加厚层1和地坪3区域内交错铺设加厚层配筋2;加厚层的配筋及厚度同地坪,保证地坪结构连续;在地坪3以及地坪加厚层1上交错配置有横向筋4和纵向筋5;Step 2: Set the
步骤3:地坪加厚层1施工完成后,采用与地坪3厚度相同的一对槽钢6对地坪3进行分隔处理(槽钢对称设置),并预先在地坪3与槽钢6之间通过砂浆10进行找平;槽钢6通过钢筋斜撑8固定,在浇筑混凝土时可起到支撑作用,同时可与混凝土连为整体,避免脱空;分仓缝处用槽钢包裹后,可避免地坪分仓交接处的边角损坏,延长地坪混凝土使用寿命,成型效果好,美观实用;Step 3: After the construction of the
步骤4:调整槽钢6的平整度及顺直度保证地坪混凝土平整度和边角顺直度;Step 4: Adjust the flatness and straightness of the
步骤5:分仓缝设置好槽钢后,相邻仓格混凝土可实现连续浇筑;浇筑完成后分仓缝间采用柔性高强环氧树脂7填缝,减少相互之间的约束力,在保证地坪结构连续的同时有效减少因混凝土发生应变产生的裂缝。Step 5: After the channel steel is set in the joints of the warehouses, the concrete of the adjacent warehouses can be poured continuously; after the pouring is completed, the joints of the warehouses are filled with flexible high-
具体地,钢筋斜撑8由斜撑和两根支撑杆组成,两根支撑杆平行设置,其中一根支撑杆竖直设置在槽钢6一侧,另一根支撑杆竖直设置在地坪加厚层1上,两根支撑杆之间倾斜固定斜撑。Specifically, the reinforced
进一步优化方案,加厚层配筋2为Z字型结构,且加厚层配筋2的两端设有固定钩9;横向筋4的两端也设有固定钩9,固定钩9钩在纵向筋上,增加整体的稳定性。To further optimize the scheme, the thickened
以上所述仅为本发明的较佳实施方式,本发明并不局限于上述实施方式,在实施过程中可能存在局部微小的结构改动,如果对本发明的各种改动或变型不脱离本发明的精神和范围,且属于本发明的权利要求和等同技术范围之内,则本发明也意图包含这些改动和变型。The above description is only a preferred embodiment of the present invention, the present invention is not limited to the above embodiment, there may be local minor structural changes during the implementation process, if the various changes or modifications of the present invention do not depart from the spirit of the present invention and scope, and belong to the claims and equivalent technical scope of the present invention, the present invention also intends to include these changes and modifications.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310398189.3A CN116378356B (en) | 2023-04-14 | 2023-04-14 | Construction method for dividing seam capable of continuously constructing large-area terrace |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310398189.3A CN116378356B (en) | 2023-04-14 | 2023-04-14 | Construction method for dividing seam capable of continuously constructing large-area terrace |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN116378356A true CN116378356A (en) | 2023-07-04 |
| CN116378356B CN116378356B (en) | 2025-05-02 |
Family
ID=86973049
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310398189.3A Active CN116378356B (en) | 2023-04-14 | 2023-04-14 | Construction method for dividing seam capable of continuously constructing large-area terrace |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116378356B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN118461851A (en) * | 2024-07-09 | 2024-08-09 | 玉田县致泰钢纤维制造有限公司 | Non-cracking terrace construction method with three-dimensional steel fiber skeleton |
| CN119195432A (en) * | 2024-10-23 | 2024-12-27 | 中国五冶集团有限公司 | A large area floor cutting-free construction method |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101265749A (en) * | 2008-04-29 | 2008-09-17 | 上海交通大学 | Elevation-adjustable super-flat floor partition seam protection formwork system |
| CN105239495A (en) * | 2015-10-30 | 2016-01-13 | 中国建筑第八工程局有限公司 | Concrete side mold and mold support method thereof |
| CN207609126U (en) * | 2017-11-30 | 2018-07-13 | 中建六局第三建筑工程有限公司 | Armor for the super flat one-pass molding load bearing heat preserving terrace of super large stitches |
| CN110173090A (en) * | 2019-06-20 | 2019-08-27 | 陕西建工集团有限公司 | Zinc-plated plate integrated form parting seam and construction method |
| JP2020169463A (en) * | 2019-04-02 | 2020-10-15 | 株式会社竹中工務店 | Floor construction method |
-
2023
- 2023-04-14 CN CN202310398189.3A patent/CN116378356B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101265749A (en) * | 2008-04-29 | 2008-09-17 | 上海交通大学 | Elevation-adjustable super-flat floor partition seam protection formwork system |
| CN105239495A (en) * | 2015-10-30 | 2016-01-13 | 中国建筑第八工程局有限公司 | Concrete side mold and mold support method thereof |
| CN207609126U (en) * | 2017-11-30 | 2018-07-13 | 中建六局第三建筑工程有限公司 | Armor for the super flat one-pass molding load bearing heat preserving terrace of super large stitches |
| JP2020169463A (en) * | 2019-04-02 | 2020-10-15 | 株式会社竹中工務店 | Floor construction method |
| CN110173090A (en) * | 2019-06-20 | 2019-08-27 | 陕西建工集团有限公司 | Zinc-plated plate integrated form parting seam and construction method |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN118461851A (en) * | 2024-07-09 | 2024-08-09 | 玉田县致泰钢纤维制造有限公司 | Non-cracking terrace construction method with three-dimensional steel fiber skeleton |
| CN119195432A (en) * | 2024-10-23 | 2024-12-27 | 中国五冶集团有限公司 | A large area floor cutting-free construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN116378356B (en) | 2025-05-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN206245209U (en) | A kind of bridge floor attachment means for continuous deck simply supported girder bridge | |
| CN105256713B (en) | Semi-assembly type steel concrete composite beam and construction method thereof | |
| CN116378356A (en) | A construction method for continuous construction of a large-area floor with separate warehouse joints | |
| CN102121227B (en) | Combined bridge deck of arched corrugated steel plates and concrete | |
| CN101851984A (en) | A prefabricated steel-concrete composite beam | |
| CN105178203B (en) | A kind of method utilizing polyurethane cement composite and bar-mat reinforcement reinforcement bridge component | |
| CN106480818A (en) | Simply supported girder bridge composite connection board construction and its construction method | |
| CN106906841A (en) | One kind is used for lateral wall form bracing system construction | |
| CN108252504A (en) | Tube shear wall concrete structure large form hoisting type construction method and constructing device | |
| CN108316120A (en) | It can rapidly-assembled precast bridge and its construction method | |
| CN206109960U (en) | Steel that can be under construction fast concrete integrated configuration bridge | |
| CN108240038A (en) | Super plane concrete structure and construction method based on multi-level network form post-cast strip | |
| CN114892511A (en) | A wet seam construction method | |
| CN106285721B (en) | A kind of railway culvert method of construction based on sliding mode system | |
| CN111255227A (en) | Thermal insulation composite formwork and construction method applied to concrete in strong wind forest area | |
| CN105926657B (en) | A construction method for prefabricated concrete foundation slabs | |
| CN206722216U (en) | A kind of prefabricated girder of laminated floor slab | |
| CN211142848U (en) | A UHPC composite structure of corrugated steel plates for strengthening hollow slab girder bridges | |
| CN209907616U (en) | Cast-in-place floor construction joint side keeps off structure | |
| CN207672389U (en) | Roadbed concrete curb cast-in-place mould | |
| CN214246715U (en) | Box type steel pipe reinforced concrete frame beam | |
| CN211655696U (en) | Precast concrete cable trench | |
| CN110348142B (en) | Method of forming curved bridge with combined formwork support technology based on BIM | |
| CN211899624U (en) | A reinforced concrete beam and slab post-cast belt temporary support system | |
| CN211691048U (en) | Composite heat-bridge-free self-insulation building block |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| PP01 | Preservation of patent right | ||
| PP01 | Preservation of patent right |
Effective date of registration: 20251231 Granted publication date: 20250502 |