CN116357062A - scaffolding support structure - Google Patents
scaffolding support structure Download PDFInfo
- Publication number
- CN116357062A CN116357062A CN202310391749.2A CN202310391749A CN116357062A CN 116357062 A CN116357062 A CN 116357062A CN 202310391749 A CN202310391749 A CN 202310391749A CN 116357062 A CN116357062 A CN 116357062A
- Authority
- CN
- China
- Prior art keywords
- rod
- positioning
- supporting
- pipe
- scaffold
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/02—Scaffold feet, e.g. with arrangements for adjustment
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/24—Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/16—Struts or stiffening rods, e.g. diagonal rods
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/24—Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
- E04G2001/242—Scaffolds movable on wheels or tracks
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A40/00—Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
- Y02A40/10—Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture
- Y02A40/25—Greenhouse technology, e.g. cooling systems therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Movable Scaffolding (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑施工技术领域,尤其涉及一种脚手架斜支撑结构。The invention relates to the technical field of building construction, in particular to a scaffolding inclined support structure.
背景技术Background technique
现有的脚手架一般是由方形框架及其下方的竖直支撑腿组成,其底部仅仅依靠竖直支撑腿支撑。在脚手架的搭建高度较高的情况下,尤其是在不平坦的地面上作业施工时,整个脚手架难以进行稳定支撑,甚至存在倾斜或倒塌的危险。Existing scaffolding generally is made up of square frame and the vertical support leg below it, and its bottom is only supported by the vertical support leg. In the case of a high scaffolding height, especially when working on uneven ground, the entire scaffolding is difficult to support stably, and there is even a danger of tilting or collapsing.
公开号为CN114396918A的专利提出了建筑施工脚手架偏移检测装置,通过斜撑梁与检测机构和定位机构的配合,提高了脚手架本体在使用时的抗倾覆性能、稳定性以及支撑效果。但是该装置在使用过程中,若转动手轮盘时受力向一侧倾斜,那么最终容易造成各个支撑柱整体向一侧倾斜,从而无法提供稳定支撑。The patent with the publication number CN114396918A proposes a construction scaffold offset detection device. Through the cooperation of the diagonal brace beam, the detection mechanism and the positioning mechanism, the anti-overturning performance, stability and support effect of the scaffold body during use are improved. However, during use of the device, if the handwheel is turned to one side by force, it is easy to cause each supporting column to tilt to one side as a whole, thereby failing to provide stable support.
发明内容Contents of the invention
有鉴于此,本发明的目的在于提出一种脚手架斜支撑结构,以解决上述问题。In view of this, the purpose of the present invention is to propose a scaffolding inclined support structure to solve the above problems.
基于上述目的,本发明提供了一种脚手架斜支撑结构,包括:固定管、转动管、安装筒、固定环、定位杆、斜撑架、螺纹管、支撑螺杆、手轮、支撑底盘、套筒和支撑杆;脚手架的立柱的下部分别固定套装有固定管,固定管上转动套装有转动管,转动管侧壁连接有安装筒;脚手架的立柱上分别连接有固定环,固定环位于转动管上方,固定环内穿装有定位杆,转动管上表面开设有第一定位槽,定位杆端部插接在第一定位槽中;斜撑架内端固定穿装在安装筒内,斜撑架外端连接有螺纹管,螺纹管内螺纹连接有支撑螺杆,支撑螺杆顶端连接有手轮,支撑螺杆底端转动连接有支撑底盘,支撑底盘下表面设置有抗滑凸块;螺纹管两侧分别连接有套筒,套筒内穿装有支撑杆,支撑杆与套筒内壁之间设置有防滑胶垫,支撑杆底端连接在支撑底盘上。Based on the above purpose, the present invention provides a scaffolding inclined support structure, including: fixed pipe, rotating pipe, installation cylinder, fixed ring, positioning rod, diagonal brace, threaded pipe, supporting screw, hand wheel, supporting chassis, sleeve and support rods; the lower part of the scaffolding column is respectively fixed with a fixed tube, the fixed tube is rotated with a rotating tube, and the side wall of the rotating tube is connected with a mounting tube; the scaffolding column is respectively connected with a fixed ring, and the fixed ring is located above the rotating tube , the fixed ring is equipped with a positioning rod, the upper surface of the rotating tube is provided with a first positioning groove, and the end of the positioning rod is inserted into the first positioning groove; the inner end of the diagonal brace is fixed and mounted in the installation tube, and the diagonal The outer end is connected with a threaded pipe, the inner thread of the threaded pipe is connected with a support screw, the top of the support screw is connected with a hand wheel, the bottom of the support screw is connected with a support chassis, and the lower surface of the support chassis is provided with anti-slip bumps; the two sides of the thread pipe are respectively connected There is a sleeve, a support rod is installed in the sleeve, an anti-slip rubber pad is arranged between the support rod and the inner wall of the sleeve, and the bottom end of the support rod is connected to the support chassis.
与现有技术相比,本发明的有益效果在于:在脚手架的各个立柱上分别连接斜撑架,实现对脚手架的稳定支撑。且斜撑架与立柱之间能够相对转动,提高了使用过程的灵活性,并通过固定环和定位杆对斜撑架的角度进行定位,该定位方式结构简单,便于操作。套筒和支撑杆起到导向作用,转动手轮调节支撑螺杆进行上下移动时,避免了因受力不均导致的倾斜问题,保证了支撑的稳定性。Compared with the prior art, the beneficial effect of the present invention lies in that: the diagonal bracing frames are respectively connected to each upright column of the scaffolding, so as to realize stable support for the scaffolding. Moreover, the diagonal bracing frame and the column can be relatively rotated, which improves the flexibility of the use process, and the angle of the diagonal bracing frame is positioned through the fixing ring and the positioning rod. This positioning method has a simple structure and is easy to operate. The sleeve and the support rod play a guiding role. When turning the hand wheel to adjust the support screw to move up and down, it avoids the problem of inclination caused by uneven force and ensures the stability of the support.
进一步地,套筒包括第一半圆筒、第二半圆筒、连接片和螺栓,第一半圆筒连接在螺纹管外壁上,第一半圆筒一端与第二半圆筒一端铰接,第一半圆筒另一端和第二半圆筒另一端分别连接有连接片,螺栓分别穿过两个连接片将两个连接片连接在一起。Further, the sleeve includes a first half cylinder, a second half cylinder, a connecting piece and a bolt, the first half cylinder is connected to the outer wall of the threaded pipe, one end of the first half cylinder is hinged to one end of the second half cylinder, and the first half cylinder is in addition One end and the other end of the second semi-cylinder are respectively connected with connecting pieces, and the bolts respectively pass through the two connecting pieces to connect the two connecting pieces together.
进一步地,支撑杆顶端连接有限位板。Further, the top end of the support rod is connected with a limiting plate.
进一步地,支撑转盘上连接有定位螺栓,定位螺栓垂直于支撑螺杆设置,支撑螺杆上开设有第二定位槽,定位螺栓端部插接在第二定位槽中。Further, positioning bolts are connected to the supporting turntable, and the positioning bolts are arranged perpendicular to the supporting screw rod, and a second positioning groove is opened on the supporting screw rod, and the ends of the positioning bolts are inserted into the second positioning groove.
进一步地,定位杆上套装有橡胶套,固定环内壁设置有抗滑胶套。Further, a rubber sleeve is set on the positioning rod, and an anti-slip rubber sleeve is provided on the inner wall of the fixing ring.
进一步地,本装置还包括固定螺栓,固定螺栓依次穿入安装筒和斜撑架,将安装筒和斜撑架固定连接在一起。Further, the device further includes fixing bolts, which are sequentially penetrated into the installation cylinder and the diagonal brace, and fixedly connect the installation cylinder and the diagonal brace together.
附图说明Description of drawings
图1为本发明实施例提供的脚手架斜支撑结构示意图;Fig. 1 is the schematic diagram of the inclined support structure of scaffold provided by the embodiment of the present invention;
图2为本发明实施例提供的脚手架斜支撑结构局部剖视图。Fig. 2 is a partial cross-sectional view of the diagonal support structure of the scaffold provided by the embodiment of the present invention.
图中标记为:1、脚手架;2、加固杆;3、固定管;4、转动管;5、安装筒;6、固定环;7、定位杆;8、斜撑架;9、螺纹管;10、支撑螺杆;11、手轮;12、支撑底盘;13、套筒;14、支撑杆;15、限位板;16、定位螺栓;17、固定螺栓。The marks in the figure are: 1. Scaffolding; 2. Reinforcing rod; 3. Fixed pipe; 4. Rotating pipe; 5. Installing cylinder; 6. Fixed ring; 7. Positioning rod; 10. Support screw; 11. Hand wheel; 12. Support chassis; 13. Sleeve; 14. Support rod; 15. Limit plate; 16. Positioning bolt; 17. Fixing bolt.
实施方式Implementation
为使本发明的目的、技术方案和优点更加清楚明白,以下结合具体实施例,对本发明进一步详细说明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with specific examples.
如图1和图2所示,本发明提出的一种脚手架1斜支撑结构,由固定管3、转动管4、安装筒5、固定环6、定位杆7、斜撑架8、螺纹管9、支撑螺杆10、手轮11、支撑底盘12、套筒13和支撑杆14等组成。斜撑架8由斜杆、竖杆、加固杆2和连接杆组成,竖杆的两端分别连接有斜杆,两个斜杆的端部分别连接有连接杆,连接杆平行于竖杆设置。两个斜杆之间连接有若干根加固杆2,加固杆2之间呈W字结构排列,用于提高斜撑架8整体的支撑强度和承载力。As shown in Fig. 1 and Fig. 2, a kind of scaffolding 1 oblique support structure that the present invention proposes, is made up of fixed pipe 3,
脚手架1的四个立柱的下部分别固定套装有固定管3,在本实施例中,每个立柱上分别套装两个固定管3。固定管3上转动套装有转动管4,转动管4侧壁固定连接有安装筒5。脚手架1的两个连接杆分别穿装在两个安装筒5中,固定螺栓17依次穿入安装筒5和连接杆,将安装筒5和斜撑架8固定连接在一起。The lower parts of the four uprights of the scaffold 1 are respectively fitted with fixed tubes 3 , and in this embodiment, two fixed tubes 3 are respectively set on each upright. The fixed pipe 3 is rotatably fitted with a
脚手架1的立柱上分别固定连接有固定环6,固定环6内壁设置有抗滑胶套。固定环6位于转动管4上方,也可以再一个立柱上连接两个固定环6,两个固定环6分别位于两个转动管4上方。固定环6内穿装有定位杆7,定位杆7上套装有橡胶套,从而避免定位杆7在固定环6内任意移动。转动管4上表面开设有若干个均匀分布的第一定位槽,定位杆7端部插接在第一定位槽中,从而实现对斜撑架8的定位。The columns of the scaffolding 1 are respectively fixedly connected with fixed
斜撑架8的竖杆上固定连接有螺纹管9,螺纹管9内螺纹连接有支撑螺杆10,支撑螺杆10顶端固定连接有手轮11,支撑螺杆10底端转动连接有支撑底盘12。支撑底盘12下表面设置有若干个梯形结构的抗滑凸块,用于防滑。螺纹管9两侧分别连接有套筒13,套筒13由第一半圆筒、第二半圆筒、连接片和螺栓组成。第一半圆筒固定连接在螺纹管9外壁上,第一半圆筒一端与第二半圆筒一端通过合页铰接在一起。第一半圆筒另一端和第二半圆筒另一端分别固定连接有连接片,螺栓分别穿过两个连接片将两个连接片连接在一起。套筒13内穿装有支撑杆14,支撑杆14与套筒13内壁之间设置有防滑胶垫,支撑杆14底端固定连接在支撑底盘12上,支撑杆14顶端固定连接有限位板15。The vertical bar of the
支撑转盘上连接有定位螺栓16,定位螺栓16垂直于支撑螺杆10设置。支撑螺杆10底部外壁沿圆周方向开设有若干个等间距分布的第二定位槽,定位螺栓16端部插接在第二定位槽中,从而实现对支撑螺杆10的定位。Positioning
使用过程:首先将定位杆7提起,使定位杆7的底端从第一定位槽中脱离,然后便能够转动斜撑架8使其偏转展开。将斜撑架8转动展开至合适位置后,将定位杆7的底端重新下插进对应位置的第一定位槽内,从而对展开后的斜撑架8进行限位固定。将支撑底盘12上的定位螺栓16旋拧退出支撑螺杆10的第二定位槽外,转动手轮11带动支撑螺杆10下降。支撑底盘12与地面接触后,支撑底盘12不跟随支撑螺杆10转动,继续转动手轮11,向下压紧支撑底盘12。将定位螺栓16进行旋拧复位,使支撑螺杆10与支撑底盘12之间不能进行相对转动。因此,通过本支撑结构有效避免了脚手架1在使用时出现倾斜的情况,大幅提高脚手架1的稳定性和安全性能。Use process: firstly lift the
本发明的实施例旨在涵盖落入所附权利要求的宽泛范围之内的所有这样的替换、修改和变型。因此,凡在本发明的精神和原则之内,所做的任何省略、修改、等同替换、改进等,均应包含在本发明的保护范围之内。Embodiments of the present invention are intended to embrace all such alterations, modifications and variations that fall within the broad scope of the appended claims. Therefore, any omissions, modifications, equivalent replacements, improvements, etc. within the spirit and principles of the present invention shall be included within the protection scope of the present invention.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310391749.2A CN116357062A (en) | 2023-04-13 | 2023-04-13 | scaffolding support structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310391749.2A CN116357062A (en) | 2023-04-13 | 2023-04-13 | scaffolding support structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116357062A true CN116357062A (en) | 2023-06-30 |
Family
ID=86904670
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310391749.2A Pending CN116357062A (en) | 2023-04-13 | 2023-04-13 | scaffolding support structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116357062A (en) |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU37128U1 (en) * | 2003-11-24 | 2004-04-10 | Латрыгина Надежда Алексеевна | CONSTRUCTION SCAFFOLDING, NODE FOR FASTENING ROD ELEMENTS OF CONSTRUCTION SCAFFOLDING AND SUPPORT ELEMENT FOR CONSTRUCTION SCAFFOLDING |
| CN214462613U (en) * | 2021-03-02 | 2021-10-22 | 孙志军 | A building steel pipe frame for high formwork operation |
| CN114396918A (en) * | 2022-01-24 | 2022-04-26 | 安徽华之语建筑工程有限公司 | Building construction scaffold frame skew detection device |
| CN217631502U (en) * | 2022-06-01 | 2022-10-21 | 中国水利水电第三工程局有限公司 | Prestressing force bearing structure of large-span steel construction factory building |
| CN218438449U (en) * | 2022-10-09 | 2023-02-03 | 重庆东群建筑工程有限公司 | Assembled building strutting arrangement |
| CN218623500U (en) * | 2022-11-07 | 2023-03-14 | 保定优杰人力资源服务有限公司 | Building construction bearing structure |
| CN219431335U (en) * | 2023-04-13 | 2023-07-28 | 中国二十二冶集团有限公司 | Scaffold inclined support structure |
-
2023
- 2023-04-13 CN CN202310391749.2A patent/CN116357062A/en active Pending
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU37128U1 (en) * | 2003-11-24 | 2004-04-10 | Латрыгина Надежда Алексеевна | CONSTRUCTION SCAFFOLDING, NODE FOR FASTENING ROD ELEMENTS OF CONSTRUCTION SCAFFOLDING AND SUPPORT ELEMENT FOR CONSTRUCTION SCAFFOLDING |
| CN214462613U (en) * | 2021-03-02 | 2021-10-22 | 孙志军 | A building steel pipe frame for high formwork operation |
| CN114396918A (en) * | 2022-01-24 | 2022-04-26 | 安徽华之语建筑工程有限公司 | Building construction scaffold frame skew detection device |
| CN217631502U (en) * | 2022-06-01 | 2022-10-21 | 中国水利水电第三工程局有限公司 | Prestressing force bearing structure of large-span steel construction factory building |
| CN218438449U (en) * | 2022-10-09 | 2023-02-03 | 重庆东群建筑工程有限公司 | Assembled building strutting arrangement |
| CN218623500U (en) * | 2022-11-07 | 2023-03-14 | 保定优杰人力资源服务有限公司 | Building construction bearing structure |
| CN219431335U (en) * | 2023-04-13 | 2023-07-28 | 中国二十二冶集团有限公司 | Scaffold inclined support structure |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN209585567U (en) | A kind of height-adjustable overturn-preventing scaffold | |
| CN208965998U (en) | Scaffold | |
| CN219431335U (en) | Scaffold inclined support structure | |
| CN207377093U (en) | A kind of scaffold | |
| CN209653345U (en) | A kind of scaffold for different level ground | |
| CN220747742U (en) | Temporary supporting device for building assembled wall | |
| CN219386329U (en) | Assembled detachable waist beam supporting structure | |
| CN116357062A (en) | scaffolding support structure | |
| CN214942467U (en) | Combined type inclined supporting device for building construction | |
| CN107288329B (en) | Scaffold frame that can level | |
| CN211447896U (en) | A kind of support for civil engineering construction | |
| CN107268963B (en) | Scaffold capable of being built on inclined plane and provided with movable platform | |
| CN218815101U (en) | Elevator shaft operating platform | |
| CN211114797U (en) | Hydraulic climbing formwork device and system with adjustable climbing angle | |
| CN210067523U (en) | Umbrella-type ground storehouse roof reinforcing apparatus that backs to | |
| CN107386619B (en) | Scaffold frame that can level and take movable platform | |
| CN217680429U (en) | Support device for climbing frame | |
| CN212613656U (en) | An elevator shaft bracket | |
| CN222375918U (en) | Stable reinforcing structure for bottom of construction frame | |
| CN212926994U (en) | A high-performance fastening device | |
| RU2322558C2 (en) | Rotary hoisting device base | |
| CN211597633U (en) | Scaffold for building engineering that can install fast | |
| CN208105867U (en) | A kind of large span hanging structure shuttering supporting adjustable jack | |
| CN115324202A (en) | A lifting device and construction method for a building supported by a column | |
| CN217872044U (en) | Stage facility building stabilizing device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |