CN116241112A CN202310346373.3A CN202310346373A CN116241112A CN 116241112 A CN116241112 A CN 116241112A CN 202310346373 A CN202310346373 A CN 202310346373A CN 116241112 A CN116241112 A CN 116241112A
Authority
CN
China
Prior art keywords
box body
joint
steel plate
waterproof
wall surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310346373.3A
Other languages
Chinese (zh)
Inventor
蒋学东
李述庭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Yangdi Steel Assembly Building Technology Co ltd
Original Assignee
Suzhou Yangdi Steel Assembly Building Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Yangdi Steel Assembly Building Technology Co ltd filed Critical Suzhou Yangdi Steel Assembly Building Technology Co ltd
Priority to CN202310346373.3A priority Critical patent/CN116241112A/en
Publication of CN116241112A publication Critical patent/CN116241112A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/12Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles
    • E04H1/1205Small buildings erected in the open air
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/665Sheets or foils impervious to water and water vapor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/12Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles
    • E04H2001/1283Small buildings of the ISO containers type
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A50/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE in human health protection, e.g. against extreme weather
    • Y02A50/30Against vector-borne diseases, e.g. mosquito-borne, fly-borne, tick-borne or waterborne diseases whose impact is exacerbated by climate change

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention provides a sanitary joint waterproof construction process for assembled joint boxes, which solves the problems of cracking, water-proof integrity damage and the like caused by displacement and settlement between boxes. The process comprises the following steps: welding a galvanized water retaining steel plate; splicing the box body and filling pearl cotton; filling structural adhesive; covering the inverted U-shaped folding piece; brushing a polymerized waterproof coating; brushing a polyester non-woven fabric cement-based polymer waterproof layer; paving a cement mortar bonding layer; paving the anti-slip brick veneer. Wherein, the water retaining steel plate is 2.5 cm higher than the frame, the width of the convex steel plate is 1.2 cm, the width of the splice is 2.5 cm, and the diameter of the pearl cotton is 3 cm. The inverted U-shaped folded piece is galvanized. The polymeric waterproof coating is painted at least twice, and is painted to the wall surface of the box body 1 meter higher than the wall surface of the box body, and the thickness of the polymeric waterproof coating is 2 mm. The waterproof layer of the polyester non-woven fabric cement-based polymer is coated on the wall surface of the box body, and the height of the wall surface of the box body is 20 cm. The thickness of the veneering surface of the anti-slip brick is 1 cm.

Description

一种装配式拼缝箱体卫生间接缝防水施工工艺A waterproof construction technology for the seams of toilets with prefabricated patchwork boxes

技术领域technical field

本发明涉及装配式建筑技术领域,特别涉及一种箱体卫生间接缝防水施工工艺。The invention relates to the technical field of prefabricated buildings, in particular to a waterproof construction process for joints in box toilets.

背景技术Background technique

装配式拼装箱体卫生间是一种将独立式卫生间为一体化钢结构模块化单体建筑,大都为单箱体下沉式箱体设计结构,卫生间全部(洁具除外)施工均在工厂作业完成,运输到装配现场直接吊装组合成型,安装洁具即可。这种方式可以提高施工效率和质量,节约材料和人力资源,减少现场污染和噪音。但是,由于装配式拼装箱体卫生间需要分开吊装,拼缝处需要吊装完成后才能进行施工。由于箱体之间产生位移、沉降所产生的开裂、破坏防水完整性等问题,独立箱体防水再好,拼缝处理不好,后期都有漏水隐患。Prefabricated assembled box toilet is a kind of independent toilet as an integrated steel structure modular single building, most of which are single box sunken box design structure, and all toilets (except sanitary ware) are constructed in the factory. It is transported to the assembly site and directly hoisted and combined to form, and the sanitary ware can be installed. This way can improve construction efficiency and quality, save materials and human resources, and reduce on-site pollution and noise. However, because the prefabricated assembled box toilet needs to be hoisted separately, the joints need to be hoisted before construction can be carried out. Due to problems such as displacement between boxes, cracks caused by settlement, and damage to waterproof integrity, no matter how waterproof the independent box is, if the joints are not handled well, there will be hidden dangers of water leakage in the later stage.

现有的拼缝处理方法主要有以下几种:The existing patchwork processing methods mainly include the following types:

1. 在两个相邻的箱体之间填充珍珠棉或其他柔性材料,并在表面涂抹结构胶或其他密封材料。这种方法的缺点是:珍珠棉下没有支撑结构,当箱体发生位移时空隙变大,珍珠棉因自重掉落下沉导致表面打胶部分下沉出现裂缝;结构胶或其他密封材料不能有效防止水分渗透到内部。1. Fill pearl cotton or other flexible materials between two adjacent boxes, and apply structural glue or other sealing materials on the surface. The disadvantages of this method are: there is no supporting structure under the pearl cotton, and when the box is displaced, the gap becomes larger, and the pearl cotton falls and sinks due to its own weight, causing cracks to sink in the glued part of the surface; structural glue or other sealing materials cannot be effective Prevents moisture from penetrating inside.

2. 箱体表层未做活动位移连接板及弹性无纺布防水层,当箱体发生形变时没有可变空间结构,作用力完全在结构胶上面,结构胶发生形变导致裂缝塌陷,表层就有出现裂缝漏水的风险。2. There is no movable displacement connecting plate and elastic non-woven waterproof layer on the surface of the box. When the box is deformed, there is no variable space structure, and the force is completely on the structural adhesive. The deformation of the structural adhesive causes cracks to collapse, and the surface layer has Risk of water leakage from cracks.

因此,在现有技术中还没有一种能够有效解决上述问题的拼缝处理方法。Therefore, in the prior art, there is no seam patching method that can effectively solve the above problems.

发明内容Contents of the invention

本发明的目的在于提供本发明的目的是提供一种装配式拼缝箱体卫生间接缝防水施工工艺,以解决箱体之间产生位移、沉降所产生的开裂、破坏防水完整性等问题。The purpose of the present invention is to provide a waterproof construction process for the bathroom joints of assembled jointed cabinets to solve problems such as displacement between the cabinets, cracking caused by settlement, and damage to waterproof integrity.

本发明通过以下技术方案实现:The present invention is realized through the following technical solutions:

一种装配式拼缝箱体卫生间接缝防水施工工艺,包括以下步骤:A waterproofing construction process for joints in bathrooms with prefabricated jointed cabinets, comprising the following steps:

步骤1:钢结构箱体框架边缘焊接高出框架的镀锌挡水钢板,在挡水钢板的一侧预留外凸钢板;Step 1: The edge of the frame of the steel structure box is welded with a galvanized water-retaining steel plate that is higher than the frame, and a protruding steel plate is reserved on one side of the water-retaining steel plate;

步骤2:将箱体拼合,箱体的挡水钢板之间留出拼缝,箱体拼缝处用珍珠棉填充密实,珍珠棉压实在外凸钢板上;Step 2: Assemble the cabinets, leaving seams between the water-retaining steel plates of the cabinets, filling the joints of the cabinets with pearl cotton, and pressing the pearl cotton on the convex steel plates;

步骤3:在珍珠棉上填涂结构胶,直至结构胶填满至挡水钢板平齐部位;Step 3: Fill and apply structural glue on the pearl cotton until the structural glue is filled to the level of the water-retaining steel plate;

步骤4:在拼缝处盖上倒U型折件,结构胶将倒U型折件粘接在拼缝处,封闭挡水钢板;Step 4: Cover the inverted U-shaped folded parts at the joints, and glue the inverted U-shaped folded parts to the joints with structural adhesive to seal the water-retaining steel plate;

步骤5:涂刷聚合防水涂料至箱体墙面,阴角拼缝处用防水涂料填满;Step 5: Apply polymeric waterproof paint to the wall of the cabinet, and fill the joints in the inner corners with waterproof paint;

步骤6:再涂刷一层聚酯无纺布水泥基聚合物防水层至箱体墙面;Step 6: Apply another layer of polyester non-woven cement-based polymer waterproof layer to the wall of the box;

步骤7:铺设水泥砂浆结合层;Step 7: laying cement mortar bonding layer;

步骤8:铺设防滑砖贴面,干水泥擦缝。Step 8: Lay the non-slip brick veneer and dry the cement to wipe the joints.

进一步的:步骤1中的挡水钢板高出框架2.5厘米。Further: The water retaining steel plate in step 1 is 2.5 cm higher than the frame.

进一步的:所述步骤1中的外凸钢板宽度为1.2厘米,步骤2中的拼缝宽度为2.5厘米,所使用的珍珠棉直径为3厘米。Further: the width of the protruding steel plate in step 1 is 1.2 cm, the width of the seam in step 2 is 2.5 cm, and the diameter of the pearl cotton used is 3 cm.

进一步的:所述步骤4倒U型折件经过镀锌处理。Further: the inverted U-shaped folded part in step 4 is galvanized.

进一步的:所述步骤5中涂刷至箱体墙面的聚合防水涂料涂刷至少两道,涂至箱体墙面1米高出,所形成的聚合防水涂层厚2毫米;阴角拼缝处用的防水涂料为堵漏王。Further: in the step 5, the polymeric waterproof coating applied to the wall of the box is painted at least twice, until the wall of the box is 1 meter above, and the formed polymeric waterproof coating is 2 mm thick; The waterproof paint used at the joints is the king of leak blocking.

进一步的:所述步骤6中聚酯无纺布水泥基聚合物防水层涂至箱体墙面高20厘米处。Further: in the step 6, the polyester non-woven cement-based polymer waterproof layer is applied to a height of 20 cm on the wall of the box body.

进一步的:所述步骤7中水泥砂浆结合层的水泥砂浆比例为1:3,水泥砂浆结合层厚度为5-8厘米。Further: the cement mortar ratio of the cement mortar bonding layer in the step 7 is 1:3, and the thickness of the cement mortar bonding layer is 5-8 cm.

进一步的:所述防滑砖贴面厚1厘米。Further: the thickness of the anti-slip brick veneer is 1 cm.

本发明和现有技术相比有以下优点:Compared with the prior art, the present invention has the following advantages:

箱体边缘焊接了挡水钢板,即使有漏水现象也不会很快蔓延至隔壁箱体。外凸钢板很好地解决了珍珠棉因自重产生的重力脱落问题,防止珍珠棉因自重掉落下沉导致表面打胶部分下沉出现裂缝;The edge of the box is welded with water-retaining steel plates, even if there is water leakage, it will not quickly spread to the next box. The convex steel plate solves the gravity shedding problem of the pearl cotton due to its own weight, and prevents the pearl cotton from falling and sinking due to its own weight, causing cracks to appear on the surface of the rubberized part;

使用镀锌的倒U型折件倒扣在拼缝上,镀锌折件具有活动性,对聚酯无纺布水泥基聚合物防水层起到一定的承托作用,错开了不同箱体间沉降不一致时对聚酯无纺布水泥基聚合物防水层的拉力,防止其开裂。The galvanized inverted U-shaped folding parts are used to buckle on the joints. The galvanized folding parts are movable and play a certain role in supporting the waterproof layer of polyester non-woven cement-based polymers, staggering the space between different boxes. Tensile force on the polyester non-woven cement-based polymer waterproofing layer during inconsistent settlement, preventing it from cracking.

聚酯无纺布水泥基聚合物防水层具有一定弹性空间,可以规避解决细微沉降带来的漏水风险。The polyester non-woven cement-based polymer waterproof layer has a certain elastic space, which can avoid the risk of water leakage caused by fine settlement.

附图说明Description of drawings

图1为装配式公共卫生间结构图;Figure 1 is a structural diagram of a prefabricated public toilet;

图2为图1中A处放大图。Figure 2 is an enlarged view of A in Figure 1 .

图中:In the picture:

框架;2、挡水钢板;2.1、外凸钢板;3、珍珠棉;4、结构胶;5、倒U型折件;6、聚合防水涂层;7、聚酯无纺布水泥基聚合物防水层;8、水泥砂浆结合层;8.1、防滑砖;9、马桶;10、楼梯间;11、卫生间。Frame; 2. Water-retaining steel plate; 2.1. Convex steel plate; 3. Pearl cotton; 4. Structural glue; Waterproof layer; 8. Cement mortar bonding layer; 8.1. Anti-skid brick; 9. Toilet; 10. Stairwell; 11. Toilet.

实施方式Implementation

下面将结合附图对本发明的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions of the present invention will be clearly and completely described below in conjunction with the accompanying drawings. Apparently, the described embodiments are part of the embodiments of the present invention, but not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

在本发明的描述中,需要说明的是,术语“中心”、“上”、“下”、“左”、“右”、“竖 直”、“水平”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。此外,术语“第一”、“第二”、“第三”仅用于描述目的,而不能理解为指示或暗示相对重要性。In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer" etc. The indicated orientation or positional relationship is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, or in a specific orientation. construction and operation, therefore, should not be construed as limiting the invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and should not be construed as indicating or implying relative importance.

本发明通过以下技术方案实现:The present invention is realized through the following technical solutions:

参见附图1与附图2,附图2为图1中A处放大图,图1中的马桶9,带水封,10mm以上的沥青或油毡等弹性材料;装配式公共卫生间结构图由如图1中的楼梯间10和卫生间11组成。Referring to accompanying drawing 1 and accompanying drawing 2, accompanying drawing 2 is the enlarged view of place A in Fig. 1, the toilet 9 in Fig. 1, band water seal, elastic materials such as asphalt or linoleum above 10mm; Stairwell 10 and toilet 11 among Fig. 1 are formed.

本发明公开了一种装配式拼缝箱体卫生间接缝防水施工工艺,包括以下步骤:The invention discloses a construction technique for waterproofing seams of bathrooms with assembly-type joint-jointed boxes, which comprises the following steps:

步骤1:钢结构箱体框架1边缘焊接高出框架2.5厘米的镀锌挡水钢板2,在挡水钢板2的一侧预留外凸钢板2.1,外凸钢板2.1宽度为1.2厘米;Step 1: The edge of steel structure box frame 1 is welded with galvanized water-retaining steel plate 2 that is 2.5 cm higher than the frame, and a convex steel plate 2.1 is reserved on one side of water-retaining steel plate 2, and the width of convex steel plate 2.1 is 1.2 cm;

步骤2:将箱体拼合,箱体的挡水钢板2之间留出宽度为2.5厘米的拼缝,箱体拼缝处用珍珠棉3填充密实,珍珠棉3直径为3厘米,将珍珠棉3压实在外凸钢板2.1上;Step 2: Assemble the cabinet, leave a seam with a width of 2.5 cm between the water-retaining steel plates 2 of the cabinet, fill the joints of the cabinet with pearl cotton 3, and the diameter of pearl cotton 3 is 3 cm. 3 compacted on the convex steel plate 2.1;

步骤3:在珍珠棉3上填涂结构胶4,直至结构胶4填满至挡水钢板2平齐部位;Step 3: Fill and apply structural adhesive 4 on the pearl cotton 3 until the structural adhesive 4 is filled to the level of the water-retaining steel plate 2;

步骤4:在拼缝处盖上镀锌处理后的倒U型折件5,结构胶将倒U型折件5粘接在拼缝处,封闭挡水钢板2;Step 4: Cover the galvanized inverted U-shaped folded part 5 at the seam, and bond the inverted U-shaped folded part 5 to the joint with structural glue, and seal the water-retaining steel plate 2;

步骤5:涂刷至少两道聚合防水涂料至箱体墙面1米高出,所形成的聚合防水涂层6厚2毫米,阴角拼缝处用堵漏王填满;Step 5: Apply at least two coats of polymeric waterproof paint to the height of 1 meter above the wall of the box body. The formed polymeric waterproof coating 6 is 2 mm thick, and fill the joints at the inner corners with plugging king;

步骤6:再涂刷一层聚酯无纺布水泥基聚合物防水层7至箱体墙面高20厘米处;Step 6: Apply another layer of polyester non-woven cement-based polymer waterproof layer 7 to a height of 20 cm on the wall of the box;

步骤7:铺设水泥砂浆结合层8,水泥砂浆结合层8的水泥砂浆比例为1:3,水泥砂浆结合层8厚度为5-8厘米;Step 7: laying cement mortar bonding layer 8, the cement mortar ratio of cement mortar bonding layer 8 is 1:3, and the thickness of cement mortar bonding layer 8 is 5-8 centimeters;

步骤8:铺设厚1厘米的防滑砖8.1贴面,干水泥擦缝。Step 8: Lay non-slip brick 8.1 veneer with a thickness of 1 cm, and wipe the joints with dry cement.

本发明有如下优点:The present invention has following advantage:

1、箱体框架1边缘焊接了挡水钢板2,即使有漏水现象也不会很快蔓延至隔壁箱体。外凸钢板2.1很好地解决了珍珠棉3因自重产生的重力脱落问题,防止珍珠棉3因自重掉落下沉导致表面打胶部分下沉出现裂缝;1. The water-retaining steel plate 2 is welded on the edge of the box frame 1, even if there is water leakage, it will not quickly spread to the next box. The convex steel plate 2.1 well solves the gravity shedding problem of the pearl cotton 3 due to its own weight, and prevents the pearl cotton 3 from falling and sinking due to its own weight, causing cracks to appear on the glued part of the surface;

2、使用镀锌的倒U型折件6倒扣在拼缝上,镀锌折件6具有活动性,对聚酯无纺布水泥基聚合物防水层7起到一定的承托作用,错开了不同箱体间沉降不一致时对聚酯无纺布水泥基聚合物防水层7的拉力,防止其开裂。2. Use the galvanized inverted U-shaped folding part 6 to buckle upside down on the seam. The galvanized folding part 6 has mobility and plays a certain role in supporting the polyester non-woven cement-based polymer waterproof layer 7. The pulling force to the polyester non-woven cement-based polymer waterproof layer 7 when the settlement between different boxes is inconsistent is prevented to prevent it from cracking.

3、聚酯无纺布水泥基聚合物防水层7具有一定弹性空间,可以规避解决细微沉降带来的漏水风险。3. The polyester non-woven cement-based polymer waterproof layer 7 has a certain elastic space, which can avoid and solve the risk of water leakage caused by fine settlement.

上述实施方式只为说明本发明的技术构思及特点,其目的在于让熟悉此项技术的人能够了解本发明的内容并据以实施,并不能以此限制本发明的保护范围。凡根据本发明精神实质所做的等效变换或修饰,都应涵盖在本发明的保护范围之内。The above-mentioned embodiments are only for illustrating the technical concept and characteristics of the present invention, and its purpose is to enable those skilled in the art to understand the content of the present invention and implement it accordingly, and not to limit the scope of protection of the present invention. All equivalent changes or modifications made according to the spirit of the present invention shall fall within the protection scope of the present invention.

Claims (8)

1. A sanitary joint waterproof construction process for an assembled joint box body is characterized in that: the method comprises the following steps:
step 1: the edge of the steel structure box body frame (1) is welded with a galvanized water retaining steel plate (2) higher than the frame, and an outer convex steel plate (2.1) is reserved at one side of the water retaining steel plate (2);
step 2: the box body is spliced, a splice is reserved between water retaining steel plates (2) of the box body, pearl wool (3) is filled and compacted at the splice of the box body, and the pearl wool (3) is compacted on the outer protruding steel plates (2.1);
step 3: filling structural adhesive (4) on the pearl cotton (3) until the structural adhesive (4) is filled up to the level part of the water retaining steel plate (2);
step 4: covering an inverted U-shaped folded piece (5) at the joint, bonding the inverted U-shaped folded piece (5) at the joint by structural adhesive, and sealing the water retaining steel plate (2);
step 5: brushing a polymerized waterproof coating to the wall surface of the box body, wherein the joint of the internal corners is filled with the waterproof coating;
step 6: coating a layer of polyester non-woven fabric cement-based polymer waterproof layer (7) to the wall surface of the box body;
step 7: paving a cement mortar bonding layer (8);
step 8: paving the anti-slip bricks (8.1) for facing and wiping the joints with dry cement.
2. The sanitary joint waterproof construction process for the assembled joint box body, according to claim 1, is characterized in that: the water retaining steel plate (2) in the step 1 is 2.5 cm higher than the frame (1).
3. The sanitary joint waterproof construction process for the assembled joint box body, according to claim 1, is characterized in that: the width of the convex steel plate (2.1) in the step 1 is 1.2 cm, the width of the splice seam in the step 2 is 2.5 cm, and the diameter of the used pearl cotton (3) is 3 cm.
4. The sanitary joint waterproof construction process for the assembled joint box body, according to claim 1, is characterized in that: and (3) the inverted U-shaped folded piece (5) in the step (4) is galvanized.
5. The sanitary joint waterproof construction process for the assembled joint box body, according to claim 1, is characterized in that: the polymeric waterproof coating painted to the wall surface of the box body in the step 5 is painted at least twice, and is painted to the wall surface of the box body 1 m higher, and the thickness of the formed polymeric waterproof coating (6) is 2 mm; the waterproof paint used at the joint of the internal corners is a plugging king.
6. The sanitary joint waterproof construction process for the assembled joint box body, according to claim 1, is characterized in that: and in the step 6, the polyester non-woven fabric cement-based polymer waterproof layer (7) is coated on the position 20 cm higher than the wall surface of the box body.
7. The sanitary joint waterproof construction process for the assembled joint box body, according to claim 1, is characterized in that: in the step 7, the proportion of the cement mortar combined layer (8) is 1:3, and the thickness of the cement mortar combined layer (8) is 5-8 cm.
8. The sanitary joint waterproof construction process for the assembled joint box body, according to claim 1, is characterized in that: the anti-slip brick (9) is faced with a thickness of 1 cm.
CN202310346373.3A 2023-04-03 2023-04-03 A waterproof construction technology for the seams of toilets with prefabricated patchwork boxes Pending CN116241112A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310346373.3A CN116241112A (en) 2023-04-03 2023-04-03 A waterproof construction technology for the seams of toilets with prefabricated patchwork boxes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310346373.3A CN116241112A (en) 2023-04-03 2023-04-03 A waterproof construction technology for the seams of toilets with prefabricated patchwork boxes

Publications (1)

Publication Number Publication Date
CN116241112A true CN116241112A (en) 2023-06-09

Family

ID=86633356

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310346373.3A Pending CN116241112A (en) 2023-04-03 2023-04-03 A waterproof construction technology for the seams of toilets with prefabricated patchwork boxes

Country Status (1)

Country Link
CN (1) CN116241112A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0044055A1 (en) * 1980-07-10 1982-01-20 Frank Huster Toilet cabin constructed from prefabricated elements
CN210439474U (en) * 2019-06-18 2020-05-01 深圳广田集团股份有限公司 Waterproof chassis concatenation structure of assembled bathroom
CN112240108A (en) * 2020-09-17 2021-01-19 上海宝冶集团有限公司 Construction method of assembly type building integrated bathroom system
CN216476571U (en) * 2021-12-31 2022-05-10 舍尔特中加(天津)钢木结构工程有限公司 Rain-proof structure of container room butt joint entrance to a cave
CN217630559U (en) * 2022-05-13 2022-10-21 深圳市中集建筑设计院有限公司 A modular splicing waterproof structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0044055A1 (en) * 1980-07-10 1982-01-20 Frank Huster Toilet cabin constructed from prefabricated elements
CN210439474U (en) * 2019-06-18 2020-05-01 深圳广田集团股份有限公司 Waterproof chassis concatenation structure of assembled bathroom
CN112240108A (en) * 2020-09-17 2021-01-19 上海宝冶集团有限公司 Construction method of assembly type building integrated bathroom system
CN216476571U (en) * 2021-12-31 2022-05-10 舍尔特中加(天津)钢木结构工程有限公司 Rain-proof structure of container room butt joint entrance to a cave
CN217630559U (en) * 2022-05-13 2022-10-21 深圳市中集建筑设计院有限公司 A modular splicing waterproof structure

Similar Documents

Publication Publication Date Title
CN110607809A (en) A construction method for basement waterproofing in construction engineering
CN107190844A (en) The waterproof and water drainage system and construction method of a kind of basement bottom board and exterior wall
CN106284425A (en) Basement in high rise building roof deformation seam water proof structure construction method
CN212926506U (en) Bathroom threshold stone waterproof construction
CN110273490A (en) A kind of embedded lightweight wall plate steel building construction and construction method
CN110185135A (en) A kind of basement bottom board and external wall waterproof structure and construction method
CN115538625A (en) A waterproof structure construction method for basement exterior wall bottom
CN114197524A (en) Waterproof construction method for civil air defense basement
CN107514016A (en) A kind of concavo-convex folded plate biting connecions deformation joint structure
CN209114658U (en) A kind of precast concrete partition plate structure for staircase
CN114411635B (en) Large deformation water-stop structure and installation method of asphalt concrete panel and concrete panel joint
CN116241112A (en) A waterproof construction technology for the seams of toilets with prefabricated patchwork boxes
CN216196849U (en) Waterproof construction of new and old building concrete bottom plate linking department
CN212001695U (en) An exterior wall waterproof structure
CN211080883U (en) Waterproof structure for toilet
CN115949097B (en) Construction method for preventing water from sinking and basement outer wall from falling off and construction structure
CN217128760U (en) Roof waterproof structure
CN214272795U (en) Waterproof floor structure of bathroom
CN214614653U (en) Combined toilet waterproof system
CN211286458U (en) Decorative surface paving structure of ground heating area
CN211421423U (en) Basement waterproof structure
CN115787745A (en) A waterproof membrane pre-laid structure and anti-adhesive construction method
CN209369099U (en) A kind of ultra-thin heat-insulating shield exterior-wall heat insulation construction of STP
CN221799353U (en) A junction structure between an acrylic swimming pool and a reinforced concrete structure
CN206581553U (en) An assembly for realizing ground water leakage prevention

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination