CN116220747A - A large-scale underground space construction system and construction method based on underpinning and underground excavation - Google Patents
A large-scale underground space construction system and construction method based on underpinning and underground excavation Download PDFInfo
- Publication number
- CN116220747A CN116220747A CN202211720869.4A CN202211720869A CN116220747A CN 116220747 A CN116220747 A CN 116220747A CN 202211720869 A CN202211720869 A CN 202211720869A CN 116220747 A CN116220747 A CN 116220747A
- Authority
- CN
- China
- Prior art keywords
- pipe shed
- construction
- support
- underground space
- soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/15—Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
- E21D11/152—Laggings made of grids or nettings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本发明提供了一种基于托换暗挖的大型地下空间施工体系及施工方法,涉及建筑施工技术领域。该体系包括管棚支护体系和台模体系,管棚支护体系用于对遗址区土体的上部、下部和侧部进行加固,在管棚支护体系的下方设有管棚支撑结构,管棚支撑结构的顶部支撑在管棚支护体系的下方,管棚支撑结构的底部竖直向下延伸,台模体系能够移动设置在管棚支护体系的下方,并在台模体系移动到位后,在台模体系的顶部与管棚支护体系的底部之间形成浇筑混凝土的空间。从而利用管棚支撑体系和管棚支护体系的管棚完成浅埋暗挖施工,通过台模体系完成地下空间主体结构的施工。本发明的施工体系适用于地下室无法进行明挖,需进行主体结构施工的工程,施工安全、便捷。
The invention provides a large-scale underground space construction system and construction method based on underpinning and underground excavation, and relates to the technical field of building construction. The system includes a pipe shed support system and a formwork system. The pipe shed support system is used to reinforce the upper, lower and side parts of the soil in the ruins area, and a pipe shed support structure is provided below the pipe shed support system. The top of the pipe shed support structure is supported under the pipe shed support system, and the bottom of the pipe shed support structure extends vertically downwards. Finally, a space for pouring concrete is formed between the top of the table formwork system and the bottom of the pipe shed support system. Therefore, the shallow buried excavation construction is completed by using the pipe shed support system and the pipe shed of the pipe shed support system, and the construction of the main structure of the underground space is completed through the table formwork system. The construction system of the present invention is suitable for projects where the basement cannot be excavated and the construction of the main structure is required, and the construction is safe and convenient.
Description
技术领域technical field
本发明涉及建筑施工技术领域,尤其是涉及一种基于托换暗挖的大型地下空间施工体系及施工方法。The invention relates to the technical field of building construction, in particular to a large-scale underground space construction system and construction method based on underpinning and underground excavation.
背景技术Background technique
本申请人发现现有技术至少存在以下技术问题:现有的地下结构在穿越遗址区等无法进行明开挖的区域时,需进行地下暗挖施工,然而传统暗挖工程需进行上部土体加固,但遗址区域无法进行注浆加固,使得施工困难。The applicant found that there are at least the following technical problems in the prior art: when the existing underground structure passes through the area where open excavation cannot be carried out, such as the ruins area, underground excavation construction is required, but the traditional underground excavation project needs to carry out upper soil reinforcement , but the ruins area cannot be reinforced by grouting, making construction difficult.
发明内容Contents of the invention
本发明的目的在于提供一种基于托换暗挖的大型地下空间施工体系及施工方法,以解决现有技术中存在的有遗址区域施工过程中,无法进行上部土体加固的技术问题。本发明提供的诸多技术方案中的优选技术方案所能产生的诸多技术效果详见下文阐述。The purpose of the present invention is to provide a large-scale underground space construction system and construction method based on underpinning and underground excavation, so as to solve the technical problem in the prior art that the upper soil cannot be reinforced during the construction process in areas with ruins. The many technical effects that can be produced by the preferred technical solutions among the many technical solutions provided by the present invention are described in detail below.
为实现上述目的,本发明提供了以下技术方案:To achieve the above object, the present invention provides the following technical solutions:
本发明提供的一种基于托换暗挖的大型地下空间施工体系,包括管棚支护体系和台模体系,所述管棚支护体系用于对遗址区土体的上部、下部和侧部进行加固,在所述管棚支护体系的下方设有管棚支撑结构,所述管棚支撑结构的顶部支撑在所述管棚支护体系的下方,所述管棚支撑结构的底部竖直向下延伸,所述台模体系能够可移动的设置在所述管棚支护体系的下方,并在所述台模体系移动到位后,在所述台模体系的顶部与所述管棚支护体系的底部之间形成浇筑混凝土的空间。A large-scale underground space construction system based on underpinning and underground excavation provided by the present invention includes a pipe shed support system and a table formwork system. For reinforcement, a pipe shed support structure is provided below the pipe shed support system, the top of the pipe shed support structure is supported under the pipe shed support system, and the bottom of the pipe shed support structure is vertical Extending downwards, the table formwork system can be movably arranged under the pipe shed support system, and after the table formwork system is moved in place, the table formwork system and the pipe shed support A space for pouring concrete is formed between the bottom of the retaining system.
根据一种优选实施方式,所述管棚支护体系包括临时支护体系,其中,所述临时支护体系包括设置在遗址区土体两侧的微型支护桩以及位于遗址区土体上部的加固组件,所述加固组件包括铺设在所述遗址区土体上部的钢跳板,在所述钢跳板的上侧设置锁口工字钢,且所述锁口工字钢的两端分别与两侧的所述微型支护桩相连接。According to a preferred embodiment, the pipe shed support system includes a temporary support system, wherein the temporary support system includes micro-support piles arranged on both sides of the soil in the ruins area and micro-support piles located on the upper part of the soil in the ruins area. Reinforcement assembly, the reinforcement assembly includes a steel springboard laid on the upper part of the soil in the ruins area, a locking I-beam is set on the upper side of the steel springboard, and the two ends of the locking I-beam are respectively connected to two The micro support piles on the side are connected.
根据一种优选实施方式,所述管棚支护体系还包括管棚结构,所述管棚结构设置在所述遗址区土体的底部,用于对上部遗址区土体进行支撑;According to a preferred embodiment, the pipe shed support system further includes a pipe shed structure, which is arranged at the bottom of the soil in the ruins area, and is used to support the soil in the upper ruins area;
所述管棚支撑结构与所述管棚结构相垂直的设置在所述管棚结构的下部;且在所述管棚支撑结构与所述管棚结构之间通过双拼工字钢进行连接。The pipe shed support structure is vertically arranged at the lower part of the pipe shed structure; and the pipe shed support structure and the pipe shed structure are connected by double I-beams.
根据一种优选实施方式,在所述管棚结构的下方形成地下空间结构,在所述地下空间结构内安装结构柱和结构板,所述结构柱的上下侧分别连接有上结构板和下结构板,所述管棚支撑结构穿过所述结构板以使得所述上结构板和下结构板固定在地下室内。According to a preferred embodiment, an underground space structure is formed under the pipe shed structure, structural columns and structural plates are installed in the underground space structure, and the upper and lower sides of the structural columns are respectively connected with an upper structural plate and a lower structure The pipe shed supporting structure passes through the structural plate so that the upper structural plate and the lower structural plate are fixed in the basement.
根据一种优选实施方式,在所述上结构板上且对应所述结构柱的位置设有预留钢筋,所述预留钢筋的顶部垂直于所述上结构板的上表面向上延伸。According to a preferred embodiment, a reserved steel bar is provided on the upper structural plate at a position corresponding to the structural column, and the top of the reserved steel bar extends upward perpendicular to the upper surface of the upper structural plate.
根据一种优选实施方式,所述上结构板与所述管棚结构之间的高度大于所述台模体系的高度。According to a preferred embodiment, the height between the upper structural plate and the pipe shed structure is greater than the height of the table formwork system.
根据一种优选实施方式,所述台模体系包括台模平台、位于所述台模平台顶部的顶板以及位于所述台模平台底部的滑动支座,其中,所述滑动支座能够带动所述台模平台和所述顶板移动至管棚结构下方的预定位置。According to a preferred embodiment, the table form system includes a table form platform, a top plate located at the top of the table form platform, and a sliding support located at the bottom of the table form platform, wherein the sliding support can drive the The table form platform and the top plate are moved to a predetermined position under the pipe shed structure.
根据一种优选实施方式,所述台模平台为盘扣架。According to a preferred embodiment, the table form platform is a buckle frame.
根据一种优选实施方式,在所述顶板上且竖直向下的设有与预留钢筋位置相对应的梁钢筋,用以与所述预留钢筋进行绑扎。According to a preferred embodiment, a beam reinforcement corresponding to the position of the reserved reinforcement is arranged vertically downward on the top plate for binding with the reserved reinforcement.
本发明还提供了一种基于托换暗挖的大型地下空间施工方法,包括如下步骤:The present invention also provides a large-scale underground space construction method based on underpinning and underground excavation, which includes the following steps:
在遗址区土体两侧延长方向进行微型支护桩的施工;并在遗址区土体的顶部进行钢跳板的施工;Construction of micro support piles is carried out in the extension direction of both sides of the soil in the ruins area; construction of a steel springboard is carried out on the top of the soil in the ruins area;
待所述微型支护桩施工完成后,在所述微型支护桩上口处进行冠梁施工并使冠梁的顶部高于遗址区土体,将两侧的冠梁通过锁口工字钢进行连接;After the construction of the miniature support piles is completed, crown beam construction is carried out at the upper opening of the miniature support piles and the top of the crown beams is higher than the soil in the ruins area, and the crown beams on both sides pass through the I-beams of the locks. make a connection;
在遗址区土体下部进行管棚支撑结构的施工,在所述管棚支撑结构施工完成后,进行两侧土方开挖,开挖至管棚结构的施工标高后插入管棚结构进行施工,待管棚结构注浆完成并达到龄期后,挖出管棚结构下方的土方;The construction of the pipe shed support structure is carried out at the lower part of the soil in the site area. After the construction of the pipe shed support structure is completed, the earthwork excavation on both sides is carried out. After excavation reaches the construction elevation of the pipe shed structure, the pipe shed structure is inserted for construction. After the grouting of the pipe shed structure is completed and reaches the age, the earthwork under the pipe shed structure shall be excavated;
施工地下空间结构部分,在地下空间结构内施工结构柱和结构板,待施工到地下室顶板标高后,在上结构板上部搭设台模体系,在台模体系的顶板绑扎梁钢筋,并将台模体系滑动至预定位置进行固定,在台模体系的顶部与管棚结构之间浇筑混凝土;For the construction of the underground space structure, the structural columns and structural slabs are constructed in the underground space structure. After the construction reaches the elevation of the basement roof, a table formwork system is set up on the upper structural slab, beam steel bars are bound on the top slab of the table formwork system, and the table formwork The system slides to the predetermined position for fixing, and concrete is poured between the top of the formwork system and the pipe shed structure;
拆除台模体系,完成地下室结构施工。Remove the formwork system and complete the construction of the basement structure.
基于上述技术方案,本发明的一种基于托换暗挖的大型地下空间施工体系及施工方法至少具有如下技术效果:Based on the above-mentioned technical scheme, a large-scale underground space construction system and construction method based on underpinning and underground excavation of the present invention have at least the following technical effects:
本发明的基于托换暗挖的大型地下空间施工体系包括管棚支护体系和台模体系,管棚支护体系用于对遗址区土体的上部、下部和侧部进行加固,在管棚支护体系的下方设有管棚支撑结构,管棚支撑结构的顶部支撑在管棚支护体系的下方,管棚支撑结构的底部竖直向下延伸,台模体系能够可移动的设置在管棚支护体系的下方,并在台模体系移动到位后,在台模体系的顶部与管棚支护体系的底部之间形成浇筑混凝土的空间。从而本发明的大型地下空间施工体系利用管棚支护体系完成对遗址区土体的进行临时支护,管棚支撑体系和管棚支护体系的管棚完成浅埋暗挖施工,然后通过台模体系完成地下空间结构主体结构的施工。本发明的施工体系适用于地下室无法进行明挖,需进行主体结构施工的工程,施工安全、便捷。The large-scale underground space construction system based on underpinning and underground excavation of the present invention includes a pipe shed support system and a formwork system. The pipe shed support system is used to reinforce the upper, lower and side parts of the soil in the ruins area. There is a pipe shed support structure under the support system, the top of the pipe shed support structure is supported under the pipe shed support system, the bottom of the pipe shed support structure extends vertically downwards, and the table formwork system can be movably set on the Below the shed support system, and after the table formwork system is moved into place, a space for pouring concrete is formed between the top of the table formwork system and the bottom of the pipe shed support system. Therefore, the large-scale underground space construction system of the present invention utilizes the pipe shed support system to complete the temporary support of the soil in the ruins area, and the pipe shed support system and the pipe shed support system of the pipe shed support system complete the shallow buried excavation construction, and then pass the platform The formwork system completes the construction of the main structure of the underground space structure. The construction system of the present invention is suitable for projects where the basement cannot be excavated and the construction of the main structure is required, and the construction is safe and convenient.
另一方面,本发明实施例的施工方法中台模体系在搭设完成后可移动的设置在管棚支护体系的下方,能够在台模体系移动到预定位置之前,完成顶板梁钢筋的绑扎,解决了顶板梁钢筋无法绑扎的问题。On the other hand, in the construction method of the embodiment of the present invention, the table formwork system is movably arranged under the pipe shed support system after erection, so that the binding of the roof beam reinforcement can be completed before the table formwork system moves to a predetermined position. Solved the problem that the roof girder reinforcement could not be bound.
附图说明Description of drawings
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are only These are some embodiments of the present invention. Those skilled in the art can also obtain other drawings based on these drawings without creative work.
图1是本发明的基于托换暗挖的大型地下空间施工方法中微型支护桩的施工工况示意图;Fig. 1 is the construction mode schematic diagram of miniature support pile in the large-scale underground space construction method based on underpinning and underground excavation of the present invention;
图2是本发明的基于托换暗挖的大型地下空间施工方法中加固组件的顶部示意图;Fig. 2 is the top schematic view of the reinforcement assembly in the large-scale underground space construction method based on underpinning and underground excavation of the present invention;
图3是本发明的基于托换暗挖的大型地下空间施工方法中管棚支撑结构的施工工况示意图;Fig. 3 is a schematic diagram of the construction conditions of the pipe shed support structure in the large-scale underground space construction method based on underpinning and underground excavation of the present invention;
图4是本发明的基于托换暗挖的大型地下空间施工方法中管棚结构的施工工况示意图;Fig. 4 is a schematic diagram of the construction conditions of the pipe shed structure in the large-scale underground space construction method based on underpinning and underground excavation of the present invention;
图5是本发明的基于托换暗挖的大型地下空间施工方法中土方开挖施工工况示意图;Fig. 5 is a schematic diagram of earthwork excavation construction conditions in the large-scale underground space construction method based on underpinning and underground excavation of the present invention;
图6是本发明的基于托换暗挖的大型地下空间施工方法中地下室除顶板外结构工况示意图;Fig. 6 is a schematic diagram of the structure of the basement except the roof in the large-scale underground space construction method based on underpinning and underground excavation of the present invention;
图7是本发明的基于托换暗挖的大型地下空间施工方法中台模搭设及梁钢筋绑扎的施工工况示意图;Fig. 7 is a schematic diagram of the construction conditions of platform formwork erection and beam reinforcement binding in the large-scale underground space construction method based on underpinning and underground excavation of the present invention;
图8是本发明的基于托换暗挖的大型地下空间施工方法中台模行进至相应位置并浇筑混凝土的施工工况示意图;Fig. 8 is a schematic diagram of the construction conditions in which the formwork advances to the corresponding position and pours concrete in the large-scale underground space construction method based on underpinning and underground excavation of the present invention;
图9是本发明的基于托换暗挖的大型地下空间施工方法中地下结构施工完成工况示意图;Fig. 9 is a schematic diagram of the completion of underground structure construction in the large-scale underground space construction method based on underpinning and underground excavation of the present invention;
图10是本发明的基于托换暗挖的大型地下空间施工方法中钢管桩桩头工况示意图。Fig. 10 is a schematic diagram of the working conditions of the steel pipe pile head in the large-scale underground space construction method based on underpinning and underground excavation according to the present invention.
图中:1-微型支护桩;2-加固组件;3-管棚支撑结构;4-管棚结构;5-结构柱;6-上结构板;7-下结构板;8-预留钢筋;9-管口;10-顶板;11-台模平台;12-梁钢筋;13-滑动支座;14-双拼工字钢;21-锁口工字钢;22-钢跳板。In the figure: 1-miniature support pile; 2-reinforcement components; 3-tube shed support structure; 4-pipe shed structure; 5-structural column; 6-upper structural plate; 7-lower structural plate; 8-reserved steel ; 9-nozzle; 10-roof; 11-tableform platform;
具体实施方式Detailed ways
为使本发明的目的、技术方案和优点更加清楚,下面将对本发明的技术方案进行详细的描述。显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所得到的所有其它实施方式,都属于本发明所保护的范围。In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be described in detail below. Apparently, the described embodiments are only some of the embodiments of the present invention, but not all of them. Based on the embodiments of the present invention, all other implementations obtained by persons of ordinary skill in the art without making creative efforts fall within the protection scope of the present invention.
实施例1Example 1
本实施例提供了一种基于托换暗挖的大型地下空间施工体系,包括管棚支护体系和台模体系。管棚支护体系用于对遗址区土体的上部、下部和侧部进行加固,在管棚支护体系的下方设有管棚支撑结构3,管棚支撑结构3的顶部支撑在管棚支护体系的下方,管棚支撑结构3的底部竖直向下延伸。从而利用管棚支护体系和管棚支撑结构完成浅埋暗挖施工。台模体系能够可移动的设置在管棚支护体系的下方,并在台模体系移动到位后,在台模体系的顶部与管棚支护体系的底部之间形成浇筑混凝土的空间。从而通过台模体系平移完成主体结构的施工,本发明的施工体系能够用于地下室无法进行明挖,需要进行主体结构施工的工程,施工安全、便捷。This embodiment provides a large-scale underground space construction system based on underpinning and underground excavation, including a pipe shed support system and a table formwork system. The pipe shed support system is used to reinforce the upper, lower and side parts of the soil in the ruins area. A pipe
优选地,管棚支护体系包括临时支护体系。如图1或图2所示,其中,临时支护体系包括设置在遗址区土体两侧的微型支护桩1以及位于遗址区土体上部的加固组件2,加固组件2包括铺设在遗址区土体上部的钢跳板22,在钢跳板22的上侧设置锁口工字钢21,且锁口工字钢21的两端分别与两侧的微型支护桩1连接。从而利用工字钢作为拉结,使得土体两侧的微型支护桩形成整体。优选地,微型支护桩1为微型钢管桩。多个微型钢管桩沿遗址区土体两侧的延长方向依次间隔排列,并在施工完成后,在每列微型钢管桩的上口处设置冠梁,冠梁的顶部高于遗址区土体,以便将一整列微型钢管桩进行连接。锁口工字钢21的两端分别连接两侧的冠梁,以形成整体结构。在施工过程中,需保证微型钢管桩的垂直度,再利用横向锁口工字钢将两侧微型支护桩连接起来。Preferably, the pipe shed support system includes a temporary support system. As shown in Figure 1 or Figure 2, the temporary support system includes micro support piles 1 arranged on both sides of the soil in the ruins area and a
进一步优选地,如图4所示,管棚支护体系还包括管棚结构4。管棚结构4设置在遗址区土体的底部,用于对上部遗址区土体进行支撑;管棚结构为土体底部的加固部件。优选地,管棚结构4与两侧的微型支护桩1焊接形成整体,保证了土体的稳定。优选地,管棚支撑结构3与管棚结构4相垂直的设置在管棚结构4的下部;且在管棚支撑结构3与管棚结构4之间通过双拼工字钢14进行纵向连接。管棚支撑结构3为钢管桩,管棚支撑结构支撑在管棚结构下部,对管棚结构进行支撑,保证了下部土体开挖时管棚结构上部土体的稳定。Further preferably, as shown in FIG. 4 , the pipe shed support system further includes a pipe shed structure 4 . The pipe shed structure 4 is set at the bottom of the soil in the relics area, and is used to support the soil in the upper relics area; the pipe shed structure is a reinforcement component at the bottom of the soil. Preferably, the pipe shed structure 4 is welded with the micro support piles 1 on both sides to form a whole, which ensures the stability of the soil. Preferably, the pipe shed
进一步优选地,如图6所示,在管棚结构4的下方形成地下空间结构。在地下空间结构内安装结构柱5和结构板。结构柱5的上下侧分别连接有上结构板6和下结构板7,管棚支撑结构3穿过结构板以使得上结构板6和下结构板7固定在地下室内,以形成地下空间结构部分。进一步优选地,在上结构板6上且对应结构柱5的位置设有预留钢筋8,预留钢筋8的顶部垂直于上结构板6的上表面向上延伸。进一步优选地,上结构板6与管棚结构4之间的高度大于台模体系的高度。以使得台模体系能够沿上结构板滑动至管棚结构的下部指定位置。Further preferably, as shown in FIG. 6 , an underground space structure is formed under the pipe shed structure 4 .
如图7所示,进一步优选地,台模体系包括台模平台11、位于台模平台11顶部的顶板10以及位于台模平台11底部的滑动支座13。优选地,台模平台11为盘扣架。台模体系的搭设可以在基坑内根据图纸及施工方案进行搭设。在台模平台11的底部设置有滑动支座13。滑动支座13能够带动台模平台11和顶板10移动至管棚结构4下方的预定位置。在顶板10上且竖直向下的设有与预留钢筋8位置相对应的梁钢筋12,用以与预留钢筋8进行绑扎。其中,梁钢筋12在顶板10上的绑扎是在台模平台搭设完成在进行绑扎。在顶板的梁钢筋绑扎完成后,将台模平台利用滑动支座送至预定位置。待固定好后,进行顶板混凝土浇筑施工。优选地,滑动支座13可以为能够调节高度的滑轮移动系统,通过滑轮移动至预定位置后,通过调节高度液压系统将台模平台升高或降低以满足结构标高要求。As shown in FIG. 7 , further preferably, the table form system includes a table form platform 11 , a top plate 10 located on the top of the table form platform 11 , and a sliding
实施例2Example 2
本实施例还提供了一种基于托换暗挖的大型地下空间施工方法,施工的工艺流程为:This embodiment also provides a large-scale underground space construction method based on underpinning and underground excavation. The construction process is as follows:
准备材料----微型支护桩施工----管棚支撑桩施工----管棚施工----土方开挖----地下室结构施工(除地下室顶板外)----台模搭设、顶板梁钢筋绑扎----台模入位---混凝土浇筑----拆模。Preparation of materials----micro support pile construction----pipe shed support pile construction----pipe shed construction----earth excavation----basement structure construction (except the basement roof)--- -Establishment of table formwork, tying of roof girder steel bars----table formwork in place---concrete pouring----formwork removal.
具体包括如下步骤:Specifically include the following steps:
如图1所示,在需要保护的遗址区土体两侧延长方向进行微型支护桩1的施工;并在遗址区土体的顶部进行钢跳板22的施工;As shown in Figure 1, carry out the construction of
待微型支护桩1施工完成后,在微型支护桩1上口处进行冠梁施工并使冠梁的顶部高于遗址区土体,将两侧的冠梁通过锁口工字钢21进行连接;形成整体;优选地,在施工过程中需保证微型支护桩的垂直度,再利用横向工字钢将土体两侧微型支护桩连接起来。After the construction of the
如图3所示,同时在遗址区土体下部进行管棚支撑结构3的施工。如图4和图5所示,在管棚支撑结构3施工完成后,进行两侧土方开挖,开挖至管棚结构4的施工标高后插入管棚结构4进行施工,待管棚结构注浆完成并达到龄期后,挖出管棚结构下方的土方;优选地,在管棚结构施工完成后需采用双拼工字钢将管棚结构与管棚支撑结构纵向连接,置于管棚支撑结构上,保证上部土体的稳定性。在对管棚结构下方土体进行开挖施工时,开挖过程中应采用退台法进行开挖,挖机严禁碰触上部管棚结构及管棚支撑结构。As shown in Figure 3, at the same time, the construction of the pipe shed
如图6所示,施工地下空间结构部分,在地下室开挖完成后,进行除地下室顶板外的其他结构的施工,例如筏板、负二层结构等。在地下空间结构内施工结构柱和结构板,待施工到地下室顶板标高后,如图7所示,在上结构板上部搭设台模体系,台模体系根据施工图纸和方案进行搭设,在台模体系的顶板绑扎梁钢筋12。如图8所示,将台模体系滑动至预定位置进行固定,在台模体系的顶部与管棚结构4之间浇筑混凝土;As shown in Figure 6, for the construction of the underground space structure, after the excavation of the basement is completed, the construction of other structures other than the basement roof, such as rafts and negative second-floor structures, will be carried out. Structural columns and structural slabs are constructed in the underground space structure. After the construction reaches the elevation of the basement roof, as shown in Figure 7, a table formwork system is erected on the upper structural slab. The table formwork system is erected according to the construction drawings and plans. The top plate binding beam reinforcement 12 of the system. As shown in Figure 8, the table formwork system is slid to a predetermined position for fixing, and concrete is poured between the top of the table formwork system and the pipe shed structure 4;
如图9和图10所示,最后拆除台模体系,完成地下室结构施工。在完成拆除台模体系后完成地下室结构施工时,需对管棚支撑结构的管口9进行封堵。管口9位于与下结构板相连接处。As shown in Figures 9 and 10, the formwork system is finally removed to complete the construction of the basement structure. When the construction of the basement structure is completed after the removal of the table formwork system, the
本发明的施工方法适用于地下室无法进行明挖,需要进行主体结构施工的工程,施工安全、便捷。本发明提供了一种浅埋暗挖施工方法,解决了有遗址区域施工过程中,无法进行上部土体加固的技术问题。同时,本发明的施工方法在暗挖完成后,对于地下空间结构施工提供了一种台模平台平移的结构施工方案,用以解决了顶板钢筋无法绑扎的问题。The construction method of the present invention is suitable for the project where the basement cannot be cut open and requires the construction of the main structure, and the construction is safe and convenient. The invention provides a construction method for shallow burial and underground excavation, which solves the technical problem that the upper soil body cannot be reinforced during the construction process in the area with ruins. Simultaneously, the construction method of the present invention provides a structural construction plan for the translation of the formwork platform for the construction of the underground space structure after the underground excavation is completed, so as to solve the problem that the roof reinforcement cannot be bound.
在本发明的描述中,需要说明的是,除非另有说明,“多个”的含义是两5个或两个以上;术语“上”、“下”、“左”、“右”、“内”、“外”、“前In the description of the present invention, it should be noted that, unless otherwise specified, the meaning of "plurality" is two or more; the terms "upper", "lower", "left", "right", " Inner, Outer, Front
端”、“后端”、“头部”、“尾部”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不The orientation or positional relationship indicated by "end", "rear end", "head", "tail", etc. is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation and therefore not
能理解为对本发明的限制。此外,术语“第一”、“第二”、“第三”等仅用0于描述目的,而不能理解为指示或暗示相对重要性。It can be understood as a limitation of the present invention. In addition, the terms "first", "second", "third", etc. are used for descriptive purposes only and should not be construed as indicating or implying relative importance.
在本发明的描述中,还需要说明的是,除非另有明确的规定和限定,术语In the description of the present invention, it should also be noted that, unless otherwise clearly specified and limited, the terms
“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是"Installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be
直接相连,也可以通过中间媒介间接相连。对于本领域的普通技术人员而言,5可视具体情况理解上述术语在本发明中的具体含义。directly or indirectly through an intermediary. For those skilled in the art, 5 can understand the specific meanings of the above terms in the present invention according to specific situations.
以上所述,仅为本发明的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,可轻易想到变化或替换,都应涵盖在本发明的保护范围之内。因此,本发明的保护范围应以所述权利要求的保护范围为准。The above is only a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Anyone skilled in the art can easily think of changes or substitutions within the technical scope disclosed in the present invention. Should be covered within the protection scope of the present invention. Therefore, the protection scope of the present invention should be determined by the protection scope of the claims.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211720869.4A CN116220747B (en) | 2022-12-30 | 2022-12-30 | Large underground space construction system and construction method based on underpinning and underground excavation |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211720869.4A CN116220747B (en) | 2022-12-30 | 2022-12-30 | Large underground space construction system and construction method based on underpinning and underground excavation |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN116220747A true CN116220747A (en) | 2023-06-06 |
| CN116220747B CN116220747B (en) | 2025-08-19 |
Family
ID=86588296
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211720869.4A Active CN116220747B (en) | 2022-12-30 | 2022-12-30 | Large underground space construction system and construction method based on underpinning and underground excavation |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116220747B (en) |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2017084573A1 (en) * | 2015-11-16 | 2017-05-26 | 彭高培 | Upheaval-resisting support structure |
| CN108442943A (en) * | 2018-03-05 | 2018-08-24 | 北京市政建设集团有限责任公司 | A kind of branch-cut bridge section tunnel and Double side heading method construction method |
| CN110374633A (en) * | 2019-07-19 | 2019-10-25 | 中铁隧道集团二处有限公司 | The Portal Section Construction method of Tunnel Passing loose media |
| CN111911183A (en) * | 2020-07-01 | 2020-11-10 | 中铁二院重庆勘察设计研究院有限责任公司 | Tunnel hole entering construction method based on end wall type guide wall structure |
| CN113216249A (en) * | 2021-04-22 | 2021-08-06 | 北京城建设计发展集团股份有限公司 | Method for constructing underground space under narrow road condition |
| WO2021203625A1 (en) * | 2020-04-09 | 2021-10-14 | 山东建筑大学 | Composite supporting structure, and construction system and method |
| US20220106879A1 (en) * | 2020-05-28 | 2022-04-07 | China Construction Seventh Bureau Transportation Construction Co., Ltd. | Construction method for entering shallow-buried multi-arch tunnel under water-rich geological conditions |
-
2022
- 2022-12-30 CN CN202211720869.4A patent/CN116220747B/en active Active
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2017084573A1 (en) * | 2015-11-16 | 2017-05-26 | 彭高培 | Upheaval-resisting support structure |
| CN108442943A (en) * | 2018-03-05 | 2018-08-24 | 北京市政建设集团有限责任公司 | A kind of branch-cut bridge section tunnel and Double side heading method construction method |
| CN110374633A (en) * | 2019-07-19 | 2019-10-25 | 中铁隧道集团二处有限公司 | The Portal Section Construction method of Tunnel Passing loose media |
| WO2021203625A1 (en) * | 2020-04-09 | 2021-10-14 | 山东建筑大学 | Composite supporting structure, and construction system and method |
| US20220106879A1 (en) * | 2020-05-28 | 2022-04-07 | China Construction Seventh Bureau Transportation Construction Co., Ltd. | Construction method for entering shallow-buried multi-arch tunnel under water-rich geological conditions |
| CN111911183A (en) * | 2020-07-01 | 2020-11-10 | 中铁二院重庆勘察设计研究院有限责任公司 | Tunnel hole entering construction method based on end wall type guide wall structure |
| CN113216249A (en) * | 2021-04-22 | 2021-08-06 | 北京城建设计发展集团股份有限公司 | Method for constructing underground space under narrow road condition |
Non-Patent Citations (1)
| Title |
|---|
| 汪跃飞;: "长城遗址下浅埋暗挖双跨大断面矩形隧道方案比选及沉降控制", 四川建筑, no. 03, 28 June 2013 (2013-06-28), pages 163 - 167 * |
Also Published As
| Publication number | Publication date |
|---|---|
| CN116220747B (en) | 2025-08-19 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102995659B (en) | Method for constructing from central area to periphery of ultra-large type underground engineering | |
| CN107313431A (en) | Close on not contour foundation ditch method for synchronously constructing | |
| CN109610508B (en) | Pipe gallery construction method for penetrating built pipe gallery and support replacing structure thereof | |
| CN110017149A (en) | A kind of underground structure and construction method of underground excavation and construction of arch cover | |
| CN111236241B (en) | Reinforcement and excavation method of subway foundation pit in soft and water-rich stratum based on half-cover excavation method | |
| CN115110959A (en) | Restraint measure of pipe curtain and construction process thereof | |
| CN115324104A (en) | Permanent and temporary combined assembly type station and construction method thereof | |
| CN111809662A (en) | Subway station underground structure combination construction method | |
| CN213952237U (en) | Take a four corners supporting beam's underground structure | |
| CN213143117U (en) | An assembled keyway foundation retaining wall structure | |
| CN216586567U (en) | Pit-in-pit miniature pile supporting structure | |
| CN111827349B (en) | Method for quickly constructing underground structure of subway station by adopting combined structure technology | |
| CN113216209A (en) | Novel foundation pit supporting system and construction method | |
| CN116220747A (en) | A large-scale underground space construction system and construction method based on underpinning and underground excavation | |
| CN216193926U (en) | Construction site trestle structure | |
| CN216948299U (en) | Novel foundation pit supporting system | |
| JP3057466B2 (en) | How to build underground structures | |
| CN113266038B (en) | Construction method for excavating underground building in foundation pit | |
| CN213014316U (en) | Prefabricated post-cast skeleton slope protection structure of assembling of railway side slope | |
| CN212956547U (en) | Foundation ditch support tower crane basis integral type structure | |
| JPH07119465B2 (en) | Underground excavation construction method | |
| CN115198787A (en) | Steel pipe column type tower crane foundation, construction method thereof and cover-excavation top-down construction method | |
| CN221345616U (en) | Prefabricated self-sinking foundation pit enclosure wall board | |
| CN113585336A (en) | Quick construction method of sinking type concrete mixing station in soft foundation environment | |
| CN113668892A (en) | A method for downslope displacement of frame structure buildings and underground building-up method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |
