CN116220062A - Section steel supporting structure for trench excavation and construction method - Google Patents
Section steel supporting structure for trench excavation and construction method Download PDFInfo
- Publication number
- CN116220062A CN116220062A CN202310130724.7A CN202310130724A CN116220062A CN 116220062 A CN116220062 A CN 116220062A CN 202310130724 A CN202310130724 A CN 202310130724A CN 116220062 A CN116220062 A CN 116220062A
- Authority
- CN
- China
- Prior art keywords
- channel steel
- trench
- steel
- dug
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
- E02D17/083—Shoring struts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/76—Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
- E02D5/765—Anchorings for bulkheads or sections thereof in as much as specially adapted therefor removable
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- General Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
技术领域technical field
本发明涉及沟槽支护施工技术领域,具体涉及了沟槽开挖的型钢支护结构及施工方法。The invention relates to the technical field of trench support construction, in particular to a section steel support structure for trench excavation and a construction method.
背景技术Background technique
现有的小区沟槽开挖支护形式主要采用槽钢支护,通常由槽钢密排或者间距布置形成基坑临时支护结构。其缺点是:在土质情况不好或存在地下水的情况,未能有效防止沟槽坍塌或抗渗水,同时在支护的完整性、稳定性、抗滑动、倾覆能力上稍有不足;在土质坚硬段无法成功打入土体中,无法形成支护结构。The existing form of trench excavation and support in the residential area mainly adopts channel steel support, and channel steel is usually arranged closely or at intervals to form a temporary support structure for foundation pits. Its disadvantages are: in the case of poor soil quality or the presence of groundwater, it cannot effectively prevent the trench from collapsing or anti-seepage, and at the same time, it is slightly insufficient in the integrity, stability, anti-sliding, and overturning capabilities of the support; The section cannot be driven into the soil successfully, and the supporting structure cannot be formed.
发明内容Contents of the invention
本发明的目的是克服现有技术不足,提供沟槽开挖的型钢支护结构及施工方法,此支护结构能够形成整体支撑体系,保证了支护的完整性、稳定性、抗滑动性;增强了抗倾覆能力,能给沟槽开挖提供安全的施工环境。The purpose of the present invention is to overcome the deficiencies in the prior art and provide a steel support structure and construction method for trench excavation. This support structure can form an integral support system, which ensures the integrity, stability and sliding resistance of the support; Enhanced anti-overturning ability, can provide a safe construction environment for trench excavation.
为了实现上述的技术特征,本发明的目的是这样实现的:沟槽开挖的型钢支护结构,它包括设置在待挖沟槽两侧的槽钢桩结构,所述槽钢桩结构由正、反套合交替打设的正向槽钢和反向槽钢构成;位于同一侧成排布置的正向槽钢和反向槽钢的内侧壁上固定有沿着待挖沟槽长度方向布置的围檩结构,围檩结构之间等间距布置有多组呈水平布置的内部支撑。In order to realize above-mentioned technical characterictic, the object of the present invention is achieved like this: the section steel supporting structure of trench excavation, it comprises the channel steel pile structure that is arranged on the both sides of the trench to be dug, and described channel steel pile structure is formed by positive It is composed of forward channel steel and reverse channel steel which are laid alternately in reverse fit; the inner side walls of the forward channel steel and reverse channel steel which are arranged in rows on the same side are fixed with grooves arranged along the length direction of the groove to be dug The surrounding purlin structure has multiple groups of horizontally arranged internal supports arranged at equal intervals between the surrounding purlin structures.
所述正向槽钢的打设部位预先打设有预引孔,所述预引孔采用等间距布置;且所述预引孔采用只钻孔不取土的环孔结构。The drilling part of the forward channel steel is pre-drilled with pre-pilot holes, and the pre-pilot holes are arranged at equal intervals; and the pre-pilot holes adopt a ring hole structure that only drills holes and does not take soil.
所述正向槽钢和反向槽钢都分被采用槽钢材料制成,长度为4-9m。Both the forward channel steel and the reverse channel steel are made of channel steel material, and the length is 4-9m.
所述围檩结构包括平行布置的上层型钢和下层型钢,上层型钢和下层型钢都分别采用焊接方式焊接固定在槽钢桩结构的内壁上;所述上层型钢和下层型钢的另一端采用焊接方式与内部支撑焊接固定。The purlin structure includes an upper section steel and a lower section steel arranged in parallel, and the upper section steel and the lower section steel are respectively welded and fixed on the inner wall of the channel steel pile structure by welding; the other ends of the upper section steel and the lower section steel are welded to the The internal support is welded and fixed.
所述上层型钢和下层型钢都采用工字钢裁剪而成,所述下层型钢和槽钢桩结构之间设置有加强筋板。Both the upper section steel and the lower section steel are cut from I-shaped steel, and a reinforcement plate is arranged between the lower section steel and the channel steel pile structure.
所述待挖沟槽的底部在开挖结束之后通过换填层进行换填,换填层和槽钢桩结构的接触面之间通过油毡层进行隔离;所述换填层的顶部中心通过管道支撑座支撑有管道。The bottom of the trench to be dug is replaced by a replacement layer after the excavation is completed, and the contact surface between the replacement layer and the channel steel pile structure is isolated by a linoleum layer; the top center of the replacement layer is passed through a pipe The support seat supports the pipe.
待挖沟槽的地面基础上,并位于槽钢桩结构的外侧设置有截水沟。An intercepting ditch is arranged on the ground foundation of the trench to be dug and outside the channel steel pile structure.
所述围檩结构和内部支撑设置在距离地面基础以下0.5m~0.6m范围内。The purlin structure and internal support are arranged within the range of 0.5m~0.6m below the ground foundation.
所述沟槽开挖的型钢支护结构的施工方法,其特征在于,包括以下步骤:The construction method of the section steel supporting structure of described trench excavation is characterized in that, comprises the following steps:
步骤一,预引孔的打设:Step 1, drilling of pre-pilot holes:
根据正向槽钢和反向槽钢的宽度尺寸,在待挖沟槽的两侧打设等间距布置的预引孔;According to the width of the forward channel steel and the reverse channel steel, drill pre-pilot holes arranged at equal intervals on both sides of the trench to be excavated;
步骤二,正向槽钢和反向槽钢的打设:Step 2, punching of forward channel steel and reverse channel steel:
待预引孔打设完成之后,将正向槽钢和反向槽钢采用正、反套合交替打设的布置方式打入预引孔内部,进而形成整体式的槽钢桩结构;After the pre-pilot hole is drilled, the forward channel steel and the reverse channel steel are driven into the pre-pilot hole in the arrangement of forward and reverse nesting alternately, and then an integral channel steel pile structure is formed;
步骤三,待挖沟槽的表层土开挖:
待两侧的槽钢桩结构初步打设完成之后,将两侧的槽钢桩结构之间的土层向下开挖至少0.9m-1.2m;After the preliminary laying of the channel steel pile structures on both sides is completed, the soil layer between the channel steel pile structures on both sides shall be excavated downward for at least 0.9m-1.2m;
步骤四,围檩结构的固定:Step 4, fixation of purlin structure:
在槽钢桩结构的内壁上,并距离地面基础以下0.5m~0.6m范围内焊接固定围檩结构;Weld and fix the purlin structure on the inner wall of the channel steel pile structure and within 0.5m~0.6m below the ground foundation;
步骤五,内部支撑的固定:Step five, fixation of internal support:
在两侧的围檩结构之间,并沿着待挖沟槽的长度方向等间距固定内部支撑,进而将槽钢桩结构、围檩结构和内部支撑构成整体支护体系;Between the surrounding purlin structures on both sides, and along the length direction of the trench to be dug, internal supports are fixed at equal intervals, and then the channel steel pile structure, surrounding purlin structure and internal supports constitute an overall support system;
步骤六,待挖沟槽的进一步开挖施工:Step 6, further excavation construction of the trench to be dug:
待整体支护体系构建完成之后,对待挖沟槽的剩余高度进行进一步的开挖,直到其设计高程;After the construction of the overall support system is completed, the remaining height of the trench to be excavated shall be further excavated until its design elevation;
步骤七,待挖沟槽底部的换填;
待挖沟槽挖掘完成之后,在待挖沟槽的底部进行换填,进而构成换填层,然后,在换填层的顶部通过管道支撑座支撑设置管道。After the excavation of the trench to be dug is completed, the bottom of the trench to be dug is replaced to form a replacement layer, and then the pipeline is supported and arranged on the top of the replacement layer by the pipe support seat.
所述换填层采用砂垫层、碎石垫层或者混凝土垫层。The replacement layer adopts sand cushion, crushed stone cushion or concrete cushion.
本发明有益效效果:The present invention has beneficial effects:
1、通过采用本发明的沟槽开挖的型钢支护结构能形成完整支护体系,在支护的完整性、稳定性、抗滑动、倾覆能力上更强,能给沟槽开挖提供安全的施工环境。1. By adopting the steel support structure for trench excavation of the present invention, a complete support system can be formed, which is stronger in the integrity, stability, anti-sliding and overturning capabilities of the support, and can provide safety for trench excavation. construction environment.
2、通过采用正、反套合交替打设的正向槽钢和反向槽钢,保证了其形成的槽钢桩结构的稳定性,增强了其抗渗性能。2. The stability of the channel steel pile structure formed by using the forward channel steel and the reverse channel steel which are alternately laid by positive and negative sleeves is ensured, and its impermeability performance is enhanced.
3、通过上述的预引孔能够方便后续对正向槽钢进行打设,能够有效防止其产生打歪或者打斜的问题。3. Through the above-mentioned pre-piercing holes, it is convenient to drill the forward channel steel in the future, and it can effectively prevent the problem of skewing or skewing.
4、通过围檩结构能够将位于同一侧的正向槽钢和反向槽钢构成稳定的支撑。4. Through the purlin structure, the forward channel steel and reverse channel steel on the same side can form a stable support.
附图说明Description of drawings
下面结合附图和实施例对本发明作进一步说明。The present invention will be further described below in conjunction with drawings and embodiments.
图1为本发明槽钢桩结构俯视图。Fig. 1 is a top view of the channel steel pile structure of the present invention.
图2为本发明支护结构的断面图。Fig. 2 is a sectional view of the supporting structure of the present invention.
图3为本发明围檩结构与槽钢桩结构连接的局部放大图。Fig. 3 is a partially enlarged view of the connection between the purlin structure and the channel steel pile structure of the present invention.
图中:正向槽钢1、预引孔2、反向槽钢3、地面基础4、截水沟5、围檩结构6、内部支撑7、管道8、管道支撑座9、换填层10、油毡层11、上层型钢12、待挖沟槽13、槽钢桩结构14、加强筋板15、下层型钢16。In the figure: forward channel steel 1, pre-pilot hole 2,
具体实施方式Detailed ways
下面结合附图对本发明的实施方式做进一步的说明。Embodiments of the present invention will be further described below in conjunction with the accompanying drawings.
实施例1:Example 1:
请参阅图1-3,沟槽开挖的型钢支护结构,它包括设置在待挖沟槽13两侧的槽钢桩结构14,所述槽钢桩结构14由正、反套合交替打设的正向槽钢1和反向槽钢3构成;位于同一侧成排布置的正向槽钢1和反向槽钢3的内侧壁上固定有沿着待挖沟槽13长度方向布置的围檩结构6,围檩结构6之间等间距布置有多组呈水平布置的内部支撑7。通过采用本发明沟槽开挖的型钢支护结构能形成完整支护体系,在支护的完整性、稳定性、抗滑动、倾覆能力上更强,能给沟槽开挖提供安全的施工环境。Please refer to Fig. 1-3, the section steel supporting structure of trench excavation, it comprises the channel
进一步的,所述正向槽钢1的打设部位预先打设有预引孔2,所述预引孔2采用等间距布置;且所述预引孔2采用只钻孔不取土的环孔结构。通过采用上述的预引孔2便于后续正向槽钢1的打设布置,提高了其后续的打设效率,防止产生打斜的问题。Further, the drilling position of the forward channel steel 1 is pre-drilled with pre-pilot holes 2, and the pre-pilot holes 2 are arranged at equal intervals; hole structure. By adopting the above-mentioned pre-piercing hole 2, it is convenient for the subsequent drilling arrangement of the forward channel steel 1, which improves the subsequent drilling efficiency and prevents the problem of skewing.
进一步的,所述正向槽钢1和反向槽钢3都分被采用槽钢材料制成,长度为4-9m。通过上述的槽钢能够形成稳定的沟槽支护,进而保证了支护的稳定性和可靠性。Further, the forward channel steel 1 and the
进一步的,所述围檩结构6包括平行布置的上层型钢12和下层型钢16,上层型钢12和下层型钢16都分别采用焊接方式焊接固定在槽钢桩结构14的内壁上;所述上层型钢12和下层型钢16的另一端采用焊接方式与内部支撑7焊接固定。通过上述的围檩结构6能够将同一侧的槽钢桩结构14连接成为整体结构。Further, the purlin structure 6 includes
进一步的,所述上层型钢12和下层型钢16都采用工字钢裁剪而成,所述下层型钢16和槽钢桩结构14之间设置有加强筋板15。通过上述的上层型钢12和下层型钢16保证了对内部支撑7支撑的稳定性和可靠性。Further, both the upper profiled
进一步的,所述待挖沟槽13的底部在开挖结束之后通过换填层10进行换填,换填层10和槽钢桩结构14的接触面之间通过油毡层11进行隔离;所述换填层10的顶部中心通过管道支撑座9支撑有管道8。通过采用上述的换填层10保证了对待挖沟槽13底部的稳定性。Further, the bottom of the
进一步的,待挖沟槽13的地面基础4上,并位于槽钢桩结构14的外侧设置有截水沟5。通过上述的截水沟5能够起到导水的目的,提高了防渗导流的效果。Further, on the ground foundation 4 of the
进一步的,所述围檩结构6和内部支撑7设置在距离地面基础4以下0.5m~0.6m范围内。通过上述的布置距离,能够对槽钢桩结构14的顶部形成稳定的支撑,进而保证了其形成的护壁结构的稳定性和可靠性。Further, the purlin structure 6 and the
实施例2:Example 2:
所述沟槽开挖的型钢支护结构的施工方法,包括以下步骤:The construction method of the section steel supporting structure of described trench excavation, comprises the following steps:
步骤一,预引孔2的打设:Step 1, drilling of pre-pilot hole 2:
根据正向槽钢1和反向槽钢3的宽度尺寸,在待挖沟槽13的两侧打设等间距布置的预引孔2;According to the width dimension of the forward channel steel 1 and the
步骤二,正向槽钢1和反向槽钢3的打设:Step 2, punching forward channel steel 1 and reverse channel steel 3:
待预引孔2打设完成之后,将正向槽钢1和反向槽钢3采用正、反套合交替打设的布置方式打入预引孔2内部,进而形成整体式的槽钢桩结构14;After the pre-pilot hole 2 is drilled, the forward channel steel 1 and the
步骤三,待挖沟槽13的表层土开挖:
待两侧的槽钢桩结构14初步打设完成之后,将两侧的槽钢桩结构14之间的土层向下开挖至少0.9m-1.2m;After the preliminary setting of the channel
步骤四,围檩结构6的固定:Step 4, fixation of purlin structure 6:
在槽钢桩结构14的内壁上,并距离地面基础4以下0.5m~0.6m范围内焊接固定围檩结构6;On the inner wall of the channel
步骤五,内部支撑7的固定:Step 5, fix the inner support 7:
在两侧的围檩结构6之间,并沿着待挖沟槽13的长度方向等间距固定内部支撑7,进而将槽钢桩结构14、围檩结构6和内部支撑7构成整体支护体系;Between the surrounding purlin structures 6 on both sides, the
步骤六,待挖沟槽13的进一步开挖施工:Step 6, further excavation construction of the
待整体支护体系构建完成之后,对待挖沟槽13的剩余高度进行进一步的开挖,直到其设计高程;After the construction of the overall support system is completed, the remaining height of the
步骤七,待挖沟槽13底部的换填;
待挖沟槽13挖掘完成之后,在待挖沟槽13的底部进行换填,进而构成换填层10,然后,在换填层10的顶部通过管道支撑座9支撑设置管道8。After the excavation of the trench to be dug 13 is completed, the bottom of the trench to be dug 13 is replaced to form a replacement layer 10 , and then the
所述换填层10采用砂垫层、碎石垫层或者混凝土垫层。The replacement layer 10 adopts a sand cushion, gravel cushion or concrete cushion.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310130724.7A CN116220062A (en) | 2023-02-17 | 2023-02-17 | Section steel supporting structure for trench excavation and construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310130724.7A CN116220062A (en) | 2023-02-17 | 2023-02-17 | Section steel supporting structure for trench excavation and construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116220062A true CN116220062A (en) | 2023-06-06 |
Family
ID=86574521
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310130724.7A Pending CN116220062A (en) | 2023-02-17 | 2023-02-17 | Section steel supporting structure for trench excavation and construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116220062A (en) |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN208633118U (en) * | 2018-07-25 | 2019-03-22 | 中铁上海设计院集团有限公司 | A kind of supporting construction that Subway Tunnel service channel pump house excavates |
| CN110306616A (en) * | 2019-08-02 | 2019-10-08 | 中交上海航道局有限公司 | A kind of construction method of sewage conduct |
| CN215562669U (en) * | 2021-08-02 | 2022-01-18 | 武汉市政工程设计研究院有限责任公司 | A kind of support structure for foundation pit of pipe jacking construction |
| CN115355360A (en) * | 2022-09-16 | 2022-11-18 | 中建八局发展建设有限公司 | Method for welding and laying large-diameter spiral steel pipes in different geological environments |
-
2023
- 2023-02-17 CN CN202310130724.7A patent/CN116220062A/en active Pending
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN208633118U (en) * | 2018-07-25 | 2019-03-22 | 中铁上海设计院集团有限公司 | A kind of supporting construction that Subway Tunnel service channel pump house excavates |
| CN110306616A (en) * | 2019-08-02 | 2019-10-08 | 中交上海航道局有限公司 | A kind of construction method of sewage conduct |
| CN215562669U (en) * | 2021-08-02 | 2022-01-18 | 武汉市政工程设计研究院有限责任公司 | A kind of support structure for foundation pit of pipe jacking construction |
| CN115355360A (en) * | 2022-09-16 | 2022-11-18 | 中建八局发展建设有限公司 | Method for welding and laying large-diameter spiral steel pipes in different geological environments |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110004936A (en) | A kind of excavation ramp and construction method based on deep foundation pit supporting structure | |
| KR101041274B1 (en) | Synthetic Grouting Fixture Structure and Construction Method | |
| CN110777809A (en) | A kind of deep foundation pit combined support adjacent to existing buildings and construction method thereof | |
| CN211200426U (en) | Anti-sliding supporting and retaining structure for miniature steel pipe pile retaining wall | |
| CN207003421U (en) | A kind of steel plate pilework for being seated hard rock top surface | |
| CN211228523U (en) | Deep foundation pit combined support adjacent to existing building | |
| CN211057851U (en) | Assembled steel-concrete combined square culvert structure based on gyro pile raft plate foundation | |
| KR102195203B1 (en) | Soil blocking method using horizontal Strut and slope Strut | |
| CN212506300U (en) | Soft clay stratum pipeline laying open cut supporting construction | |
| CN101748735A (en) | Foundation ditch excavation method for reducing pile deflection in soft soil area | |
| CN116220062A (en) | Section steel supporting structure for trench excavation and construction method | |
| JP4888293B2 (en) | Earth retaining wall made of parent pile sheet pile, water stop structure of earth retaining wall made of parent pile side sheet pile, construction method of earth retaining wall made of parent pile side sheet pile, and retaining wall of earth retaining wall made of parent pile side sheet pile Water method | |
| CN204225101U (en) | The construction equipment of concrete pile | |
| CN218622256U (en) | Double-row pile and inclined pile combined type foundation pit support structure | |
| CN217460445U (en) | Novel refute bank suitable for soft soil foundation | |
| CN113668892B (en) | Underground storey-adding method for downhill displacement of frame structure building | |
| CN109972634A (en) | A soil retaining method for the side wall of the open excavation foundation pit of the pipe gallery crossing the branch pipe trench | |
| JP5375549B2 (en) | How to construct a retaining wall | |
| CN214116528U (en) | Structure is restoreed to reverse osmotic pressure drainage system of panel | |
| CN211312527U (en) | Support stand bottom plate watertight fittings in ultra-deep foundation ditch | |
| KR102122698B1 (en) | Construction method of underground continuous walls for minimizing ground displacements during deep and vertical excavation in urban areas | |
| CN210049221U (en) | Foundation treatment structure for deep silt | |
| CN102322063B (en) | Method for secondary excavation and supporting construction of deep foundation pit | |
| CN111827307A (en) | A combined construction method pile supporting structure and its construction method | |
| CN113668893B (en) | Horizontal-position underground storey-adding method for frame structure building |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |