CN116220062A - Section steel supporting structure for trench excavation and construction method - Google Patents

Section steel supporting structure for trench excavation and construction method Download PDF

Info

Publication number
CN116220062A
CN116220062A CN202310130724.7A CN202310130724A CN116220062A CN 116220062 A CN116220062 A CN 116220062A CN 202310130724 A CN202310130724 A CN 202310130724A CN 116220062 A CN116220062 A CN 116220062A
Authority
CN
China
Prior art keywords
channel steel
trench
steel
dug
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310130724.7A
Other languages
Chinese (zh)
Inventor
汪路
贺明武
宋求明
蔚静雯
刘杰
姚志华
黄英杰
辛盼盼
严维
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangtze Ecology And Environment Co ltd
Original Assignee
Yangtze Ecology And Environment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangtze Ecology And Environment Co ltd filed Critical Yangtze Ecology And Environment Co ltd
Priority to CN202310130724.7A priority Critical patent/CN116220062A/en
Publication of CN116220062A publication Critical patent/CN116220062A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E02D17/083Shoring struts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • E02D5/765Anchorings for bulkheads or sections thereof in as much as specially adapted therefor removable

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention provides a section steel supporting structure for trench excavation and a construction method thereof, comprising channel steel pile structures arranged at two sides of a trench to be excavated, wherein the channel steel pile structures are composed of forward channel steel and reverse channel steel which are alternately arranged in a sleeved mode; the inner side walls of the forward channel steel and the reverse channel steel which are arranged on the same side in a row are fixedly provided with surrounding purlin structures which are arranged along the length direction of the groove to be excavated, and a plurality of groups of inner supports which are horizontally arranged are arranged at equal intervals between the surrounding purlin structures. The supporting structure can form an integral supporting system, and the integrity, stability and sliding resistance of the supporting structure are ensured; the anti-capsizing capability is enhanced, and a safe construction environment can be provided for trench excavation.

Description

沟槽开挖的型钢支护结构及施工方法Sectional Steel Support Structure and Construction Method for Trench Excavation

技术领域technical field

本发明涉及沟槽支护施工技术领域,具体涉及了沟槽开挖的型钢支护结构及施工方法。The invention relates to the technical field of trench support construction, in particular to a section steel support structure for trench excavation and a construction method.

背景技术Background technique

现有的小区沟槽开挖支护形式主要采用槽钢支护,通常由槽钢密排或者间距布置形成基坑临时支护结构。其缺点是:在土质情况不好或存在地下水的情况,未能有效防止沟槽坍塌或抗渗水,同时在支护的完整性、稳定性、抗滑动、倾覆能力上稍有不足;在土质坚硬段无法成功打入土体中,无法形成支护结构。The existing form of trench excavation and support in the residential area mainly adopts channel steel support, and channel steel is usually arranged closely or at intervals to form a temporary support structure for foundation pits. Its disadvantages are: in the case of poor soil quality or the presence of groundwater, it cannot effectively prevent the trench from collapsing or anti-seepage, and at the same time, it is slightly insufficient in the integrity, stability, anti-sliding, and overturning capabilities of the support; The section cannot be driven into the soil successfully, and the supporting structure cannot be formed.

发明内容Contents of the invention

本发明的目的是克服现有技术不足,提供沟槽开挖的型钢支护结构及施工方法,此支护结构能够形成整体支撑体系,保证了支护的完整性、稳定性、抗滑动性;增强了抗倾覆能力,能给沟槽开挖提供安全的施工环境。The purpose of the present invention is to overcome the deficiencies in the prior art and provide a steel support structure and construction method for trench excavation. This support structure can form an integral support system, which ensures the integrity, stability and sliding resistance of the support; Enhanced anti-overturning ability, can provide a safe construction environment for trench excavation.

为了实现上述的技术特征,本发明的目的是这样实现的:沟槽开挖的型钢支护结构,它包括设置在待挖沟槽两侧的槽钢桩结构,所述槽钢桩结构由正、反套合交替打设的正向槽钢和反向槽钢构成;位于同一侧成排布置的正向槽钢和反向槽钢的内侧壁上固定有沿着待挖沟槽长度方向布置的围檩结构,围檩结构之间等间距布置有多组呈水平布置的内部支撑。In order to realize above-mentioned technical characterictic, the object of the present invention is achieved like this: the section steel supporting structure of trench excavation, it comprises the channel steel pile structure that is arranged on the both sides of the trench to be dug, and described channel steel pile structure is formed by positive It is composed of forward channel steel and reverse channel steel which are laid alternately in reverse fit; the inner side walls of the forward channel steel and reverse channel steel which are arranged in rows on the same side are fixed with grooves arranged along the length direction of the groove to be dug The surrounding purlin structure has multiple groups of horizontally arranged internal supports arranged at equal intervals between the surrounding purlin structures.

所述正向槽钢的打设部位预先打设有预引孔,所述预引孔采用等间距布置;且所述预引孔采用只钻孔不取土的环孔结构。The drilling part of the forward channel steel is pre-drilled with pre-pilot holes, and the pre-pilot holes are arranged at equal intervals; and the pre-pilot holes adopt a ring hole structure that only drills holes and does not take soil.

所述正向槽钢和反向槽钢都分被采用槽钢材料制成,长度为4-9m。Both the forward channel steel and the reverse channel steel are made of channel steel material, and the length is 4-9m.

所述围檩结构包括平行布置的上层型钢和下层型钢,上层型钢和下层型钢都分别采用焊接方式焊接固定在槽钢桩结构的内壁上;所述上层型钢和下层型钢的另一端采用焊接方式与内部支撑焊接固定。The purlin structure includes an upper section steel and a lower section steel arranged in parallel, and the upper section steel and the lower section steel are respectively welded and fixed on the inner wall of the channel steel pile structure by welding; the other ends of the upper section steel and the lower section steel are welded to the The internal support is welded and fixed.

所述上层型钢和下层型钢都采用工字钢裁剪而成,所述下层型钢和槽钢桩结构之间设置有加强筋板。Both the upper section steel and the lower section steel are cut from I-shaped steel, and a reinforcement plate is arranged between the lower section steel and the channel steel pile structure.

所述待挖沟槽的底部在开挖结束之后通过换填层进行换填,换填层和槽钢桩结构的接触面之间通过油毡层进行隔离;所述换填层的顶部中心通过管道支撑座支撑有管道。The bottom of the trench to be dug is replaced by a replacement layer after the excavation is completed, and the contact surface between the replacement layer and the channel steel pile structure is isolated by a linoleum layer; the top center of the replacement layer is passed through a pipe The support seat supports the pipe.

待挖沟槽的地面基础上,并位于槽钢桩结构的外侧设置有截水沟。An intercepting ditch is arranged on the ground foundation of the trench to be dug and outside the channel steel pile structure.

所述围檩结构和内部支撑设置在距离地面基础以下0.5m~0.6m范围内。The purlin structure and internal support are arranged within the range of 0.5m~0.6m below the ground foundation.

所述沟槽开挖的型钢支护结构的施工方法,其特征在于,包括以下步骤:The construction method of the section steel supporting structure of described trench excavation is characterized in that, comprises the following steps:

步骤一,预引孔的打设:Step 1, drilling of pre-pilot holes:

根据正向槽钢和反向槽钢的宽度尺寸,在待挖沟槽的两侧打设等间距布置的预引孔;According to the width of the forward channel steel and the reverse channel steel, drill pre-pilot holes arranged at equal intervals on both sides of the trench to be excavated;

步骤二,正向槽钢和反向槽钢的打设:Step 2, punching of forward channel steel and reverse channel steel:

待预引孔打设完成之后,将正向槽钢和反向槽钢采用正、反套合交替打设的布置方式打入预引孔内部,进而形成整体式的槽钢桩结构;After the pre-pilot hole is drilled, the forward channel steel and the reverse channel steel are driven into the pre-pilot hole in the arrangement of forward and reverse nesting alternately, and then an integral channel steel pile structure is formed;

步骤三,待挖沟槽的表层土开挖:Step 3, excavation of the topsoil of the trench to be dug:

待两侧的槽钢桩结构初步打设完成之后,将两侧的槽钢桩结构之间的土层向下开挖至少0.9m-1.2m;After the preliminary laying of the channel steel pile structures on both sides is completed, the soil layer between the channel steel pile structures on both sides shall be excavated downward for at least 0.9m-1.2m;

步骤四,围檩结构的固定:Step 4, fixation of purlin structure:

在槽钢桩结构的内壁上,并距离地面基础以下0.5m~0.6m范围内焊接固定围檩结构;Weld and fix the purlin structure on the inner wall of the channel steel pile structure and within 0.5m~0.6m below the ground foundation;

步骤五,内部支撑的固定:Step five, fixation of internal support:

在两侧的围檩结构之间,并沿着待挖沟槽的长度方向等间距固定内部支撑,进而将槽钢桩结构、围檩结构和内部支撑构成整体支护体系;Between the surrounding purlin structures on both sides, and along the length direction of the trench to be dug, internal supports are fixed at equal intervals, and then the channel steel pile structure, surrounding purlin structure and internal supports constitute an overall support system;

步骤六,待挖沟槽的进一步开挖施工:Step 6, further excavation construction of the trench to be dug:

待整体支护体系构建完成之后,对待挖沟槽的剩余高度进行进一步的开挖,直到其设计高程;After the construction of the overall support system is completed, the remaining height of the trench to be excavated shall be further excavated until its design elevation;

步骤七,待挖沟槽底部的换填;Step 7, replace the bottom of the trench to be dug;

待挖沟槽挖掘完成之后,在待挖沟槽的底部进行换填,进而构成换填层,然后,在换填层的顶部通过管道支撑座支撑设置管道。After the excavation of the trench to be dug is completed, the bottom of the trench to be dug is replaced to form a replacement layer, and then the pipeline is supported and arranged on the top of the replacement layer by the pipe support seat.

所述换填层采用砂垫层、碎石垫层或者混凝土垫层。The replacement layer adopts sand cushion, crushed stone cushion or concrete cushion.

本发明有益效效果:The present invention has beneficial effects:

1、通过采用本发明的沟槽开挖的型钢支护结构能形成完整支护体系,在支护的完整性、稳定性、抗滑动、倾覆能力上更强,能给沟槽开挖提供安全的施工环境。1. By adopting the steel support structure for trench excavation of the present invention, a complete support system can be formed, which is stronger in the integrity, stability, anti-sliding and overturning capabilities of the support, and can provide safety for trench excavation. construction environment.

2、通过采用正、反套合交替打设的正向槽钢和反向槽钢,保证了其形成的槽钢桩结构的稳定性,增强了其抗渗性能。2. The stability of the channel steel pile structure formed by using the forward channel steel and the reverse channel steel which are alternately laid by positive and negative sleeves is ensured, and its impermeability performance is enhanced.

3、通过上述的预引孔能够方便后续对正向槽钢进行打设,能够有效防止其产生打歪或者打斜的问题。3. Through the above-mentioned pre-piercing holes, it is convenient to drill the forward channel steel in the future, and it can effectively prevent the problem of skewing or skewing.

4、通过围檩结构能够将位于同一侧的正向槽钢和反向槽钢构成稳定的支撑。4. Through the purlin structure, the forward channel steel and reverse channel steel on the same side can form a stable support.

附图说明Description of drawings

下面结合附图和实施例对本发明作进一步说明。The present invention will be further described below in conjunction with drawings and embodiments.

图1为本发明槽钢桩结构俯视图。Fig. 1 is a top view of the channel steel pile structure of the present invention.

图2为本发明支护结构的断面图。Fig. 2 is a sectional view of the supporting structure of the present invention.

图3为本发明围檩结构与槽钢桩结构连接的局部放大图。Fig. 3 is a partially enlarged view of the connection between the purlin structure and the channel steel pile structure of the present invention.

图中:正向槽钢1、预引孔2、反向槽钢3、地面基础4、截水沟5、围檩结构6、内部支撑7、管道8、管道支撑座9、换填层10、油毡层11、上层型钢12、待挖沟槽13、槽钢桩结构14、加强筋板15、下层型钢16。In the figure: forward channel steel 1, pre-pilot hole 2, reverse channel steel 3, ground foundation 4, intercepting ditch 5, purlin structure 6, internal support 7, pipe 8, pipe support seat 9, replacement layer 10 , linoleum layer 11, upper section steel 12, trench to be dug 13, channel steel pile structure 14, stiffener plate 15, lower section steel 16.

具体实施方式Detailed ways

下面结合附图对本发明的实施方式做进一步的说明。Embodiments of the present invention will be further described below in conjunction with the accompanying drawings.

实施例1:Example 1:

请参阅图1-3,沟槽开挖的型钢支护结构,它包括设置在待挖沟槽13两侧的槽钢桩结构14,所述槽钢桩结构14由正、反套合交替打设的正向槽钢1和反向槽钢3构成;位于同一侧成排布置的正向槽钢1和反向槽钢3的内侧壁上固定有沿着待挖沟槽13长度方向布置的围檩结构6,围檩结构6之间等间距布置有多组呈水平布置的内部支撑7。通过采用本发明沟槽开挖的型钢支护结构能形成完整支护体系,在支护的完整性、稳定性、抗滑动、倾覆能力上更强,能给沟槽开挖提供安全的施工环境。Please refer to Fig. 1-3, the section steel supporting structure of trench excavation, it comprises the channel steel pile structure 14 that is arranged on the both sides of trench 13 to be dug, and described channel steel pile structure 14 is driven alternately by positive and negative nesting The set forward channel steel 1 and the reverse channel steel 3 are formed; the inner side walls of the forward channel steel 1 and the reverse channel steel 3 arranged in rows on the same side are fixed with grooves arranged along the length direction of the trench 13 to be dug. Purlin structures 6, multiple sets of horizontally arranged internal supports 7 are arranged at equal intervals between the purlin structures 6 . By adopting the steel support structure for trench excavation of the present invention, a complete support system can be formed, which is stronger in the integrity, stability, anti-sliding and overturning capabilities of the support, and can provide a safe construction environment for trench excavation .

进一步的,所述正向槽钢1的打设部位预先打设有预引孔2,所述预引孔2采用等间距布置;且所述预引孔2采用只钻孔不取土的环孔结构。通过采用上述的预引孔2便于后续正向槽钢1的打设布置,提高了其后续的打设效率,防止产生打斜的问题。Further, the drilling position of the forward channel steel 1 is pre-drilled with pre-pilot holes 2, and the pre-pilot holes 2 are arranged at equal intervals; hole structure. By adopting the above-mentioned pre-piercing hole 2, it is convenient for the subsequent drilling arrangement of the forward channel steel 1, which improves the subsequent drilling efficiency and prevents the problem of skewing.

进一步的,所述正向槽钢1和反向槽钢3都分被采用槽钢材料制成,长度为4-9m。通过上述的槽钢能够形成稳定的沟槽支护,进而保证了支护的稳定性和可靠性。Further, the forward channel steel 1 and the reverse channel steel 3 are both made of channel steel material, with a length of 4-9m. The above-mentioned channel steel can form a stable groove support, thereby ensuring the stability and reliability of the support.

进一步的,所述围檩结构6包括平行布置的上层型钢12和下层型钢16,上层型钢12和下层型钢16都分别采用焊接方式焊接固定在槽钢桩结构14的内壁上;所述上层型钢12和下层型钢16的另一端采用焊接方式与内部支撑7焊接固定。通过上述的围檩结构6能够将同一侧的槽钢桩结构14连接成为整体结构。Further, the purlin structure 6 includes upper section steel 12 and lower section steel 16 arranged in parallel, and the upper section steel 12 and the lower section steel 16 are respectively welded and fixed on the inner wall of the channel steel pile structure 14 by means of welding; the upper section steel 12 And the other end of the lower section steel 16 is welded and fixed with the internal support 7 by welding. Through the purlin structure 6 mentioned above, the channel steel pile structures 14 on the same side can be connected to form an integral structure.

进一步的,所述上层型钢12和下层型钢16都采用工字钢裁剪而成,所述下层型钢16和槽钢桩结构14之间设置有加强筋板15。通过上述的上层型钢12和下层型钢16保证了对内部支撑7支撑的稳定性和可靠性。Further, both the upper profiled steel 12 and the lower profiled steel 16 are cut from I-shaped steel, and a stiffener plate 15 is arranged between the lower profiled steel 16 and the channel steel pile structure 14 . The stability and reliability of supporting the inner support 7 are ensured by the above-mentioned upper section steel 12 and lower section steel 16 .

进一步的,所述待挖沟槽13的底部在开挖结束之后通过换填层10进行换填,换填层10和槽钢桩结构14的接触面之间通过油毡层11进行隔离;所述换填层10的顶部中心通过管道支撑座9支撑有管道8。通过采用上述的换填层10保证了对待挖沟槽13底部的稳定性。Further, the bottom of the trench 13 to be dug is replaced by a replacement layer 10 after the excavation is completed, and the contact surface between the replacement layer 10 and the channel steel pile structure 14 is isolated by a linoleum layer 11; The top center of the replacement layer 10 is supported by a pipe 8 through a pipe support seat 9 . The stability of the bottom of the trench 13 to be dug is guaranteed by adopting the above-mentioned replacement layer 10 .

进一步的,待挖沟槽13的地面基础4上,并位于槽钢桩结构14的外侧设置有截水沟5。通过上述的截水沟5能够起到导水的目的,提高了防渗导流的效果。Further, on the ground foundation 4 of the trench 13 to be dug, and outside the channel steel pile structure 14, a water intercepting ditch 5 is provided. The above-mentioned intercepting ditch 5 can serve the purpose of water diversion, improving the effect of seepage prevention and diversion.

进一步的,所述围檩结构6和内部支撑7设置在距离地面基础4以下0.5m~0.6m范围内。通过上述的布置距离,能够对槽钢桩结构14的顶部形成稳定的支撑,进而保证了其形成的护壁结构的稳定性和可靠性。Further, the purlin structure 6 and the internal support 7 are arranged within a range of 0.5m~0.6m below the ground foundation 4 . Through the above arrangement distance, a stable support can be formed on the top of the channel steel pile structure 14, thereby ensuring the stability and reliability of the retaining wall structure formed by it.

实施例2:Example 2:

所述沟槽开挖的型钢支护结构的施工方法,包括以下步骤:The construction method of the section steel supporting structure of described trench excavation, comprises the following steps:

步骤一,预引孔2的打设:Step 1, drilling of pre-pilot hole 2:

根据正向槽钢1和反向槽钢3的宽度尺寸,在待挖沟槽13的两侧打设等间距布置的预引孔2;According to the width dimension of the forward channel steel 1 and the reverse channel steel 3, drill holes 2 arranged at equal intervals on both sides of the trench 13 to be dug;

步骤二,正向槽钢1和反向槽钢3的打设:Step 2, punching forward channel steel 1 and reverse channel steel 3:

待预引孔2打设完成之后,将正向槽钢1和反向槽钢3采用正、反套合交替打设的布置方式打入预引孔2内部,进而形成整体式的槽钢桩结构14;After the pre-pilot hole 2 is drilled, the forward channel steel 1 and the reverse channel steel 3 are drilled into the pre-pilot hole 2 in the way of forward and reverse nesting alternately, so as to form an integral channel steel pile Structure 14;

步骤三,待挖沟槽13的表层土开挖:Step 3, excavation of the topsoil of the trench 13 to be dug:

待两侧的槽钢桩结构14初步打设完成之后,将两侧的槽钢桩结构14之间的土层向下开挖至少0.9m-1.2m;After the preliminary setting of the channel steel pile structures 14 on both sides is completed, the soil layer between the channel steel pile structures 14 on both sides is excavated downward for at least 0.9m-1.2m;

步骤四,围檩结构6的固定:Step 4, fixation of purlin structure 6:

在槽钢桩结构14的内壁上,并距离地面基础4以下0.5m~0.6m范围内焊接固定围檩结构6;On the inner wall of the channel steel pile structure 14, the purlin structure 6 is welded and fixed within the range of 0.5m~0.6m below the ground foundation 4;

步骤五,内部支撑7的固定:Step 5, fix the inner support 7:

在两侧的围檩结构6之间,并沿着待挖沟槽13的长度方向等间距固定内部支撑7,进而将槽钢桩结构14、围檩结构6和内部支撑7构成整体支护体系;Between the surrounding purlin structures 6 on both sides, the internal support 7 is fixed at equal intervals along the length direction of the trench 13 to be dug, and then the channel steel pile structure 14, the surrounding purlin structure 6 and the internal support 7 form an overall support system ;

步骤六,待挖沟槽13的进一步开挖施工:Step 6, further excavation construction of the trench 13 to be dug:

待整体支护体系构建完成之后,对待挖沟槽13的剩余高度进行进一步的开挖,直到其设计高程;After the construction of the overall support system is completed, the remaining height of the trench 13 to be excavated is further excavated until its design elevation;

步骤七,待挖沟槽13底部的换填;Step 7, filling the bottom of the trench 13 to be dug;

待挖沟槽13挖掘完成之后,在待挖沟槽13的底部进行换填,进而构成换填层10,然后,在换填层10的顶部通过管道支撑座9支撑设置管道8。After the excavation of the trench to be dug 13 is completed, the bottom of the trench to be dug 13 is replaced to form a replacement layer 10 , and then the pipeline 8 is supported by the pipe support seat 9 on the top of the replacement layer 10 .

所述换填层10采用砂垫层、碎石垫层或者混凝土垫层。The replacement layer 10 adopts a sand cushion, gravel cushion or concrete cushion.

Claims (10)

1.沟槽开挖的型钢支护结构,其特征在于,它包括设置在待挖沟槽(13)两侧的槽钢桩结构(14),所述槽钢桩结构(14)由正、反套合交替打设的正向槽钢(1)和反向槽钢(3)构成;位于同一侧成排布置的正向槽钢(1)和反向槽钢(3)的内侧壁上固定有沿着待挖沟槽(13)长度方向布置的围檩结构(6),围檩结构(6)之间等间距布置有多组呈水平布置的内部支撑(7)。1. The section steel support structure for trench excavation is characterized in that it includes channel steel pile structures (14) arranged on both sides of the trench to be dug (13), and the channel steel pile structures (14) consist of positive, It is composed of forward channel steel (1) and reverse channel steel (3) which are laid alternately in reverse fit; it is located on the inner wall of the forward channel steel (1) and reverse channel steel (3) arranged in rows on the same side Purlin structures (6) arranged along the length direction of the trench to be excavated (13) are fixed, and multiple sets of horizontally arranged internal supports (7) are arranged at equal intervals between the purlin structures (6). 2.根据权利要求1所述沟槽开挖的型钢支护结构,其特征在于,所述正向槽钢(1)的打设部位预先打设有预引孔(2),所述预引孔(2)采用等间距布置;且所述预引孔(2)采用只钻孔不取土的环孔结构。2. The profiled steel support structure for trench excavation according to claim 1, characterized in that, the drilling part of the forward channel steel (1) is pre-drilled with a pre-pilot hole (2), and the pre-pilot hole (2) is drilled in advance. The holes (2) are arranged at equal intervals; and the pre-pilot holes (2) adopt a ring hole structure in which only holes are drilled and soil is not taken. 3.根据权利要求1所述沟槽开挖的型钢支护结构,其特征在于,所述正向槽钢(1)和反向槽钢(3)都分被采用槽钢材料制成,长度为4-9m。3. The profile steel support structure for excavating trenches according to claim 1, characterized in that, both the forward channel steel (1) and the reverse channel steel (3) are made of channel steel materials, and the length It is 4-9m. 4.根据权利要求1所述沟槽开挖的型钢支护结构,其特征在于,所述围檩结构(6)包括平行布置的上层型钢(12)和下层型钢(16),上层型钢(12)和下层型钢(16)都分别采用焊接方式焊接固定在槽钢桩结构(14)的内壁上;所述上层型钢(12)和下层型钢(16)的另一端采用焊接方式与内部支撑(7)焊接固定。4. The profile steel support structure for trench excavation according to claim 1, characterized in that, the purlin structure (6) comprises upper profile steel (12) and lower profile steel (16) arranged in parallel, and the upper profile steel (12 ) and the lower section steel (16) are respectively welded and fixed on the inner wall of the channel steel pile structure (14); the other ends of the upper section steel (12) and the lower section steel (16) are welded to the internal support (7 ) fixed by soldering. 5.根据权利要求4所述沟槽开挖的型钢支护结构,其特征在于,所述上层型钢(12)和下层型钢(16)都采用工字钢裁剪而成,所述下层型钢(16)和槽钢桩结构(14)之间设置有加强筋板(15)。5. The profiled steel support structure for trench excavation according to claim 4, characterized in that, both the upper profiled steel (12) and the lower profiled steel (16) are cut from I-shaped steel, and the lower profiled steel (16) ) and the channel steel pile structure (14) are provided with reinforcing ribs (15). 6.根据权利要求1所述沟槽开挖的型钢支护结构,其特征在于,所述待挖沟槽(13)的底部在开挖结束之后通过换填层(10)进行换填,换填层(10)和槽钢桩结构(14)的接触面之间通过油毡层(11)进行隔离;所述换填层(10)的顶部中心通过管道支撑座(9)支撑有管道(8)。6. The profiled steel support structure for trench excavation according to claim 1, characterized in that the bottom of the trench to be dug (13) is replaced by a replacement layer (10) after the excavation is completed, and the replacement The contact surface between the fill layer (10) and the channel steel pile structure (14) is isolated by a linoleum layer (11); the top center of the replacement layer (10) is supported by a pipe (8) through a pipe support seat (9) ). 7.根据权利要求1所述沟槽开挖的型钢支护结构,其特征在于,待挖沟槽(13)的地面基础(4)上,并位于槽钢桩结构(14)的外侧设置有截水沟(5)。7. The profiled steel support structure for trench excavation according to claim 1, characterized in that, on the ground foundation (4) of the trench to be dug (13) and on the outside of the channel steel pile structure (14), a Cutting ditch (5). 8.根据权利要求7所述沟槽开挖的型钢支护结构,其特征在于,所述围檩结构(6)和内部支撑(7)设置在距离地面基础(4)以下0.5m~0.6m范围内。8. The profiled steel support structure for trench excavation according to claim 7, characterized in that, the purlin structure (6) and internal support (7) are set at 0.5m~0.6m below the ground foundation (4) within range. 9.权利要求1-8任意一项所述沟槽开挖的型钢支护结构的施工方法,其特征在于,包括以下步骤:9. The construction method of the profiled steel support structure of trench excavation described in any one of claims 1-8, is characterized in that, comprises the following steps: 步骤一,预引孔(2)的打设:Step 1, drilling of pre-pilot holes (2): 根据正向槽钢(1)和反向槽钢(3)的宽度尺寸,在待挖沟槽(13)的两侧打设等间距布置的预引孔(2);According to the width of the forward channel steel (1) and the reverse channel steel (3), drill pre-pilot holes (2) at equal intervals on both sides of the trench to be dug (13); 步骤二,正向槽钢(1)和反向槽钢(3)的打设:Step 2, punching forward channel steel (1) and reverse channel steel (3): 待预引孔(2)打设完成之后,将正向槽钢(1)和反向槽钢(3)采用正、反套合交替打设的布置方式打入预引孔(2)内部,进而形成整体式的槽钢桩结构(14);After the pre-pilot hole (2) is drilled, the forward channel steel (1) and the reverse channel steel (3) are punched into the pre-pilot hole (2) in the arrangement of forward and reverse nesting alternately, Then an integral channel steel pile structure (14) is formed; 步骤三,待挖沟槽(13)的表层土开挖:Step 3, excavating the topsoil of the trench (13) to be dug: 待两侧的槽钢桩结构(14)初步打设完成之后,将两侧的槽钢桩结构(14)之间的土层向下开挖至少0.9m-1.2m;After the initial laying of the channel steel pile structures (14) on both sides is completed, excavate the soil layer between the channel steel pile structures (14) on both sides downward for at least 0.9m-1.2m; 步骤四,围檩结构(6)的固定:Step 4, fixation of purlin structure (6): 在槽钢桩结构(14)的内壁上,并距离地面基础(4)以下0.5m~0.6m范围内焊接固定围檩结构(6);on the inner wall of the channel steel pile structure (14), and weld and fix the purlin structure (6) within the range of 0.5m~0.6m below the ground foundation (4); 步骤五,内部支撑(7)的固定:Step five, fixing the internal support (7): 在两侧的围檩结构(6)之间,并沿着待挖沟槽(13)的长度方向等间距固定内部支撑(7),进而将槽钢桩结构(14)、围檩结构(6)和内部支撑(7)构成整体支护体系;Between the surrounding purlin structures (6) on both sides, and along the length direction of the trench to be dug (13), the internal supports (7) are fixed at equal intervals, and then the channel steel pile structure (14), the surrounding purlin structure (6 ) and internal support (7) constitute the overall support system; 步骤六,待挖沟槽(13)的进一步开挖施工:Step 6, further excavation construction of the trench to be dug (13): 待整体支护体系构建完成之后,对待挖沟槽(13)的剩余高度进行进一步的开挖,直到其设计高程;After the construction of the overall support system is completed, the remaining height of the trench to be excavated (13) is further excavated until its design elevation; 步骤七,待挖沟槽(13)底部的换填;Step 7, filling the bottom of the trench to be dug (13); 待挖沟槽(13)挖掘完成之后,在待挖沟槽(13)的底部进行换填,进而构成换填层(10),然后,在换填层(10)的顶部通过管道支撑座(9)支撑设置管道(8)。After the excavation of the trench to be dug (13) is completed, the bottom of the trench to be dug (13) is replaced to form the replacement layer (10), and then the pipe support seat ( 9) Support setting pipe (8). 10.根据权利要求9所述沟槽开挖的型钢支护结构的施工方法,其特征在于,所述换填层(10)采用砂垫层、碎石垫层或者混凝土垫层。10. The construction method of the sectioned steel support structure excavated by trenches according to claim 9, characterized in that, the replacement layer (10) adopts a sand cushion, a crushed stone cushion or a concrete cushion.
CN202310130724.7A 2023-02-17 2023-02-17 Section steel supporting structure for trench excavation and construction method Pending CN116220062A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310130724.7A CN116220062A (en) 2023-02-17 2023-02-17 Section steel supporting structure for trench excavation and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310130724.7A CN116220062A (en) 2023-02-17 2023-02-17 Section steel supporting structure for trench excavation and construction method

Publications (1)

Publication Number Publication Date
CN116220062A true CN116220062A (en) 2023-06-06

Family

ID=86574521

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310130724.7A Pending CN116220062A (en) 2023-02-17 2023-02-17 Section steel supporting structure for trench excavation and construction method

Country Status (1)

Country Link
CN (1) CN116220062A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN208633118U (en) * 2018-07-25 2019-03-22 中铁上海设计院集团有限公司 A kind of supporting construction that Subway Tunnel service channel pump house excavates
CN110306616A (en) * 2019-08-02 2019-10-08 中交上海航道局有限公司 A kind of construction method of sewage conduct
CN215562669U (en) * 2021-08-02 2022-01-18 武汉市政工程设计研究院有限责任公司 A kind of support structure for foundation pit of pipe jacking construction
CN115355360A (en) * 2022-09-16 2022-11-18 中建八局发展建设有限公司 Method for welding and laying large-diameter spiral steel pipes in different geological environments

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN208633118U (en) * 2018-07-25 2019-03-22 中铁上海设计院集团有限公司 A kind of supporting construction that Subway Tunnel service channel pump house excavates
CN110306616A (en) * 2019-08-02 2019-10-08 中交上海航道局有限公司 A kind of construction method of sewage conduct
CN215562669U (en) * 2021-08-02 2022-01-18 武汉市政工程设计研究院有限责任公司 A kind of support structure for foundation pit of pipe jacking construction
CN115355360A (en) * 2022-09-16 2022-11-18 中建八局发展建设有限公司 Method for welding and laying large-diameter spiral steel pipes in different geological environments

Similar Documents

Publication Publication Date Title
CN110004936A (en) A kind of excavation ramp and construction method based on deep foundation pit supporting structure
KR101041274B1 (en) Synthetic Grouting Fixture Structure and Construction Method
CN110777809A (en) A kind of deep foundation pit combined support adjacent to existing buildings and construction method thereof
CN211200426U (en) Anti-sliding supporting and retaining structure for miniature steel pipe pile retaining wall
CN207003421U (en) A kind of steel plate pilework for being seated hard rock top surface
CN211228523U (en) Deep foundation pit combined support adjacent to existing building
CN211057851U (en) Assembled steel-concrete combined square culvert structure based on gyro pile raft plate foundation
KR102195203B1 (en) Soil blocking method using horizontal Strut and slope Strut
CN212506300U (en) Soft clay stratum pipeline laying open cut supporting construction
CN101748735A (en) Foundation ditch excavation method for reducing pile deflection in soft soil area
CN116220062A (en) Section steel supporting structure for trench excavation and construction method
JP4888293B2 (en) Earth retaining wall made of parent pile sheet pile, water stop structure of earth retaining wall made of parent pile side sheet pile, construction method of earth retaining wall made of parent pile side sheet pile, and retaining wall of earth retaining wall made of parent pile side sheet pile Water method
CN204225101U (en) The construction equipment of concrete pile
CN218622256U (en) Double-row pile and inclined pile combined type foundation pit support structure
CN217460445U (en) Novel refute bank suitable for soft soil foundation
CN113668892B (en) Underground storey-adding method for downhill displacement of frame structure building
CN109972634A (en) A soil retaining method for the side wall of the open excavation foundation pit of the pipe gallery crossing the branch pipe trench
JP5375549B2 (en) How to construct a retaining wall
CN214116528U (en) Structure is restoreed to reverse osmotic pressure drainage system of panel
CN211312527U (en) Support stand bottom plate watertight fittings in ultra-deep foundation ditch
KR102122698B1 (en) Construction method of underground continuous walls for minimizing ground displacements during deep and vertical excavation in urban areas
CN210049221U (en) Foundation treatment structure for deep silt
CN102322063B (en) Method for secondary excavation and supporting construction of deep foundation pit
CN111827307A (en) A combined construction method pile supporting structure and its construction method
CN113668893B (en) Horizontal-position underground storey-adding method for frame structure building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination