CN116163213A - Translation type aerial temporary operation platform for integrally assembling bridge steel structure sections and method thereof - Google Patents
Translation type aerial temporary operation platform for integrally assembling bridge steel structure sections and method thereof Download PDFInfo
- Publication number
- CN116163213A CN116163213A CN202211400936.4A CN202211400936A CN116163213A CN 116163213 A CN116163213 A CN 116163213A CN 202211400936 A CN202211400936 A CN 202211400936A CN 116163213 A CN116163213 A CN 116163213A
- Authority
- CN
- China
- Prior art keywords
- platform
- truss
- steel structure
- bridge
- aerial
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/30—Metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种用于桥梁钢结构节段整体拼装的平移式空中临时作业平台及其方法,搭建在已完工的桥梁钢结构上所设置的当前施工工位的悬臂端,包括平台前移设备、临时连接体系以及空中作业平台,临时连接体系包括锚固横梁;平台前移设备包括自移式横梁结构、轨道以及履带吊,而自移式横梁结构则包括悬挂横梁、顶升设备以及移动小车;空中作业平台包括平台固定端以及位于平台固定端前端的平台悬臂端;平台固定端能够分别与悬挂横梁、锚固钢梁择一固定连接。由此可见,本发明将主桥钢结构节段的地面作业转移到空中,整合了节段整体拼装的优势,保证施工质量的前提下,有效地降低了海事、港航的影响。
The invention discloses a translational aerial temporary work platform for the overall assembly of bridge steel structure segments and a method thereof. Equipment, temporary connection system and aerial work platform. The temporary connection system includes anchor beams; platform forward equipment includes self-moving beam structures, tracks and crawler cranes, and self-moving beam structures includes suspension beams, jacking equipment and mobile trolleys The aerial work platform includes a fixed end of the platform and a cantilever end of the platform located at the front end of the fixed end of the platform; It can be seen that the present invention transfers the ground work of the steel structure section of the main bridge to the air, integrates the advantages of the overall assembly of the section, and effectively reduces the impact of maritime affairs, ports and shipping on the premise of ensuring the construction quality.
Description
技术领域technical field
本发明涉及一种平移式空中临时作业平台及其方法,属于桥梁施工技术领域。The invention relates to a translational aerial temporary operation platform and a method thereof, belonging to the technical field of bridge construction.
背景技术Background technique
钢结构拼装施工前,施工方案的选择,需要着重考虑如下几个方面:施工方案的水利防洪评估、施工方案所采用的临时措施对航道的影响、施工临时措施的安全性。Before the steel structure assembly construction, the selection of the construction plan needs to focus on the following aspects: the water conservancy and flood control assessment of the construction plan, the impact of the temporary measures adopted in the construction plan on the waterway, and the safety of the temporary construction measures.
桥梁拼装主要有两种方式,一种为节段整体吊装工艺,另一种则为支架拼装工艺。There are two main methods of bridge assembly, one is the segmental overall hoisting process, and the other is the bracket assembly process.
通常地,节段整体吊装工艺通常指在临时拼装场地内完成组装后通过运输船水上运输,将整体节段运至桥位正上方,采用桥面吊机安装主跨整体节段。该工艺最大的优点是工艺成熟,临时设施投入少,经济效益最佳,有利于钢结构整体焊接质量及线性的控制,在全国各地均由施工先例,如宁波三官堂大桥等。Generally, the overall segmental hoisting process usually means that after the assembly is completed in the temporary assembly site, the entire segment is transported to the top of the bridge position by a transport ship after being assembled on the water, and the overall segment of the main span is installed by a bridge deck crane. The biggest advantage of this process is that it is mature, requires less investment in temporary facilities, and has the best economic benefits. It is beneficial to the control of the overall welding quality and linearity of the steel structure. It has construction precedents throughout the country, such as Ningbo Sanguantang Bridge.
但是,节段整体吊装工艺存在以下困难:节段江上运输问题,航道清淤工作,大节段构件运输及下水困难,占用主要航道,造成航道封航。However, the overall hoisting process of the segment has the following difficulties: transportation problems on the river for the segment, dredging of the channel, difficulty in transporting and launching components of the large segment, occupying the main channel, and causing the channel to be closed.
支架拼装工艺即在江中设置临时支撑体系,完成节段拼装,然后再进行整体拼装。这种工法的主要难题在于,在航道转弯区域,尤其是大角度的航道转弯区域采用支架拼装工艺时,为了保证施工临时措施的安全性,临时支撑结构设计难度极大,原因在于,为保证转弯区域两侧的航道底边线错位,因此,临时支撑结构的横梁跨径大,而横梁跨径过大又会影响通航净高。再有,还存在运输船只碰撞临时支架的水上运输交通事故的安全隐患。The bracket assembly process is to set up a temporary support system in the river, complete the segmental assembly, and then proceed to the overall assembly. The main difficulty of this construction method is that in the turning area of the waterway, especially when the bracket assembly process is used in the turning area of the waterway with a large angle, in order to ensure the safety of the temporary construction measures, the design of the temporary support structure is extremely difficult. The reason is that in order to ensure the turning The bottom edge of the channel on both sides of the area is misaligned. Therefore, the span of the beam of the temporary support structure is large, and the span of the beam is too large, which will affect the clear height of the navigation. Have again, also there is the potential safety hazard of the water transport traffic accident of transport ship collision temporary support.
发明内容Contents of the invention
本发明针对现有技术的不足,提供一种平移式空中临时作业平台及其方法。所述的平移式空中临时作业平台整体包括两部分,其中一部分为平台前移设备,另一部分则为空中作业平台。平台前移设备安装在已搭建好的上一节钢结构节段的上层桥面系上,而空中作业平台则呈悬臂安装并具有两种安装状态,以使得空中作业平台一方面可以作为平台前移设备步进式前移的支撑,另一方面则可以作为待施工主桥钢结构节段的临时作业场所,从而可以在空中作业平台完成钢结构节段的拼装,为桥梁钢结构的节段整体焊接拼装做准备。由此可见,本发明将主桥钢结构节段的地面作业转移到空中,整合了节段整体拼装的优势,保证施工质量的前提下,有效地降低了海事、港航的影响,且经过标高测算,空中作业平台对通航净高亦无影响。Aiming at the deficiencies of the prior art, the invention provides a translational aerial temporary operation platform and a method thereof. The translational aerial temporary work platform as a whole includes two parts, one of which is a platform forward moving device, and the other part is an aerial work platform. The platform forward moving equipment is installed on the upper bridge deck of the last steel structure section that has been built, while the aerial work platform is installed as a cantilever and has two installation states, so that on the one hand, the aerial work platform can be used as the front of the platform. On the other hand, it can be used as a temporary work place for the steel structure section of the main bridge to be constructed, so that the assembly of the steel structure section can be completed on the aerial work platform, which is the bridge steel structure section Prepare for overall welding assembly. It can be seen that the present invention transfers the ground work of the steel structure section of the main bridge to the air, integrates the advantages of the overall assembly of the section, and effectively reduces the influence of maritime affairs, ports and shipping on the premise of ensuring the construction quality, and after the elevation According to calculations, the aerial work platform has no effect on the clear height of navigation.
为实现上述的技术目的,本发明将采取如下的技术方案:For realizing above-mentioned technical purpose, the present invention will take following technical scheme:
一种用于桥梁钢结构节段整体拼装的平移式空中临时作业平台,搭建在已完工的桥梁钢结构上所设置的当前施工工位的悬臂端,包括平台前移设备、临时连接体系以及空中作业平台,其中:A translational aerial temporary work platform for the overall assembly of bridge steel structure segments, built on the cantilever end of the current construction station set on the completed bridge steel structure, including platform forward moving equipment, temporary connection system and aerial work platform Operating platform, of which:
所述的临时连接体系,包括锚固横梁;所述的锚固横梁至少包括两组,一组安装在当前施工工位对应的桥梁左侧桁架上,为左侧锚固横梁,另一组则安装在当前施工工位的对应的桥梁右侧桁架上,为右侧锚固钢梁;The temporary connection system includes anchoring beams; the anchoring beams include at least two groups, one group is installed on the left side truss of the bridge corresponding to the current construction station, and the other group is installed on the current On the truss on the right side of the bridge corresponding to the construction station, it is the anchoring steel beam on the right side;
所述的平台前移设备包括自移式横梁结构、轨道以及履带吊,而自移式横梁结构则包括悬挂横梁、顶升设备以及移动小车;悬挂横梁横跨当前施工工位的上层桥面系设置,移动小车包括两组,对称地安装在悬挂横梁的下表面;履带吊置于当前施工工位的上层桥面系上;轨道包括两条,分别通过左、右侧锚固横梁支撑并能够通过履带吊吊装至下一个施工工位对应侧的锚固横梁上;顶升设备悬挂安装在悬挂横梁下表面,并能够促使移动小车安装在对应位置处的轨道中或者促使移动小车脱离对应位置处的轨道;The platform moving forward equipment includes a self-moving beam structure, a track and a crawler crane, while the self-moving beam structure includes a suspension beam, jacking equipment and a mobile trolley; the suspension beam spans the upper deck system of the current construction station. Setting, the mobile trolley consists of two groups, which are symmetrically installed on the lower surface of the suspension beam; the crawler is placed on the upper deck of the current construction station; The crawler crane is hoisted to the anchor beam on the corresponding side of the next construction station; the jacking equipment is suspended and installed on the lower surface of the suspension beam, and can make the mobile trolley install on the track at the corresponding position or make the mobile trolley break away from the track at the corresponding position ;
所述的空中作业平台,包括平台固定端以及位于平台固定端前端的平台悬臂端;所述的平台固定端能够分别与悬挂横梁、锚固钢梁择一固定连接。The aerial work platform includes a fixed end of the platform and a cantilever end of the platform located at the front end of the fixed end of the platform; the fixed end of the platform can be respectively fixedly connected with a suspension beam or an anchoring steel beam.
优选地,所述的空中作业平台包括平台桁架体系、平台底联以及端部平联;所述的平台桁架体系包括两根,对应为左侧平台桁架体系以及右侧平台桁架体系;左侧平台桁架体系与右侧平台桁架体系结构一致并相互平行设置;左侧平台桁架体系与右侧平台桁架体系两者的尾端之间通过端部平联连接成一体,且左侧平台桁架体系与右侧平台桁架体系两者的下弦杆之间在紧靠着端部平联的位置处通过平台底联连接。Preferably, the aerial work platform includes a platform truss system, a platform bottom connection and an end connection; the platform truss system includes two, corresponding to the left platform truss system and the right platform truss system; the left platform The truss system is consistent with the structure of the right platform truss system and arranged parallel to each other; The lower chords of the two side platform truss systems are connected through the platform bottom link at the position close to the end parallel link.
优选地,所述的平台桁架体系包括平台桁架上弦杆、平台桁架直腹杆、平台桁架斜腹杆以及平台桁架下弦杆;平台桁架上弦杆、平台桁架下弦杆相互平行设置,且平台桁架上弦杆、平台桁架下弦杆之间通过若干根平台桁架直腹杆连接,相邻的两根平台桁架直腹杆之间通过所述的平台桁架斜腹杆连接。Preferably, the platform truss system includes platform truss upper chord, platform truss straight web, platform truss oblique web and platform truss lower chord; 1. The bottom chords of the platform truss are connected by several platform truss straight webs, and two adjacent platform truss straight webs are connected by the platform truss diagonals.
优选地,平台桁架下弦杆在靠近尾端的位置处设置有若干块平台横梁连接板,平台底联的一侧与左侧平台桁架体系的下弦杆上的平台横梁连接板连接,另一侧则与右侧平台桁架体系的下弦杆上的平台横梁连接板连接。Preferably, the lower chord of the platform truss is provided with several platform beam connecting plates near the tail end, one side of the platform bottom link is connected with the platform beam connecting plate on the lower chord of the platform truss system on the left side, and the other side is connected with The platform beam connecting plate on the lower chord of the right platform truss system is connected.
优选地,所述的平台底联包括支撑横梁以及底部平联;所述支撑横梁的数量为三根,对应为第一至第三支撑横梁,且第二支撑横梁处于第一、第三支撑横梁之间,三根支撑横梁相互平行并等距布置;所述的底部平联包括两根对拼的V形架,V形架的两个端点分别与第二支撑横梁连接,而顶点则与第一支撑横梁或第三支撑横梁连接;Preferably, the platform bottom link includes a support beam and a bottom parallel link; the number of the support beam is three, corresponding to the first to third support beams, and the second support beam is located between the first and third support beams In between, the three supporting beams are arranged parallel to each other and equidistant; the bottom parallel connection includes two pairs of V-shaped frames, the two ends of the V-shaped frames are respectively connected with the second supporting beams, and the top points are connected with the first supporting Beam or third support beam connection;
平台横梁连接板的数量也为三个;所述三根支撑横梁的两端分别与相应侧的平台横梁连接板对应连接。The number of platform beam connecting plates is also three; the two ends of the three supporting beams are respectively connected to the corresponding side platform beam connecting plates.
优选地,所述的端部平联包括矩形外框以及分别对应地将矩形外框的两对角线连接的连接斜撑;矩形外框通过四根杆件相互围接而形成;每个围接点均设置有一块节点板。Preferably, the end parallel connection includes a rectangular outer frame and connecting braces correspondingly connecting two diagonal lines of the rectangular outer frame; the rectangular outer frame is formed by surrounding four rods; The joints are all provided with a gusset plate.
优选地,所述的左侧锚固横梁包括两排,其中一排安装在桥梁左侧桁架的上弦杆上,为第一左侧锚固横梁,另一排则安装在桥梁左侧桁架的下弦杆上,为第二左侧锚固横梁;Preferably, the left anchor beam includes two rows, one of which is installed on the upper chord of the left truss of the bridge, which is the first left anchor beam, and the other row is installed on the lower chord of the bridge left truss , is the second left anchor beam;
所述的右侧锚固横梁包括两排,其中一排安装在桥梁右侧桁架的上弦杆上,为第一右侧锚固横梁,另一排则安装在桥梁右侧桁架的下弦杆上,为第二右侧锚固横梁;The right anchor beam includes two rows, one of which is installed on the upper chord of the right truss of the bridge, which is the first right anchor beam, and the other row is installed on the lower chord of the bridge right truss, which is the first Two right anchor beams;
两条轨道分别通过第一左侧锚固横梁、第一右侧锚固横梁对应支撑。The two rails are respectively supported by the first left anchor beam and the first right anchor beam.
优选地,左侧平台桁架体系与右侧平台桁架体系两者的前端之间缺口设置或者通过防护栏杆连接。Preferably, gaps are provided between the front ends of the left platform truss system and the right platform truss system or are connected by protective railings.
本发明的另一个技术目的是提供一种上述的用于桥梁钢结构节段整体拼装的平移式空中临时作业平台的平移方法,包括如下步骤:Another technical purpose of the present invention is to provide a translation method for the above-mentioned translational aerial temporary work platform for the overall assembly of bridge steel structure segments, including the following steps:
步骤一、作业准备Step 1. Homework preparation
为在空中作业平台中进行待拼接桥梁钢结构节段的拼装以及与已完工的桥梁钢结构之间的整体拼装做准备,具体包括如下步骤:Prepare for the assembly of bridge steel structure segments to be spliced in the aerial work platform and the overall assembly with the completed bridge steel structure, including the following steps:
步骤1.1、将空中作业平台的两侧平台桁架体系与当前施工工位两侧的锚固横梁焊接固定,实现空中作业平台在桥梁钢结构上的悬吊;Step 1.1. Weld and fix the platform truss system on both sides of the aerial work platform and the anchor beams on both sides of the current construction station to realize the suspension of the aerial work platform on the bridge steel structure;
步骤1.2、解除空中作业平台与悬挂横梁之间的联系;Step 1.2, release the connection between the aerial work platform and the suspension beam;
步骤1.3、顶升气缸顶出;Step 1.3, the jacking cylinder is ejected;
步骤二、移位准备Step 2. Preparation for shifting
在当前施工工位完成待拼接桥梁钢结构节段的整体拼装后,为空中作业平台前移至下一个施工工位做准备,具体包括如下步骤:After the current construction station completes the overall assembly of the bridge steel structure segments to be spliced, prepare for the aerial work platform to move forward to the next construction station, including the following steps:
步骤2.1、在下一个施工工位对应的桥梁钢结构两侧分别安装有一组锚固横梁;每组锚固横梁均包括两层,对应地安装在同侧桁架体系的上、下弦杆上;每层锚固横梁均至少包括两根,每层锚固横梁所包含的各锚固横梁均沿着桥梁钢结构的纵桥向间隔分布;Step 2.1. Install a set of anchor beams on both sides of the bridge steel structure corresponding to the next construction station; each set of anchor beams includes two layers, which are installed on the upper and lower chords of the truss system on the same side; each layer of anchor beams Each includes at least two anchor beams, and the anchor beams included in each layer are distributed at intervals along the longitudinal bridge direction of the bridge steel structure;
步骤2.2、采用履带吊将轨道吊装至下一个施工工位对应的上层锚固横梁上进行铺设;Step 2.2, use the crawler crane to hoist the track to the upper anchor beam corresponding to the next construction station for laying;
步骤2.3、顶升气缸回缩,以将悬挂横梁下的移动小车嵌装在相应侧的轨道中;Step 2.3, the jacking cylinder is retracted to embed the mobile trolley under the suspension beam in the track on the corresponding side;
步骤2.4、将左侧平台桁架体系、右侧平台桁架体系紧靠着尾端的上弦杆分别固定到悬挂横梁的对应位置处,以使得空中作业平台悬吊在悬挂横梁上;Step 2.4, fix the upper chords of the left platform truss system and the right platform truss system close to the tail end to the corresponding positions of the suspension beams, so that the aerial work platform is suspended on the suspension beams;
步骤2.5、解除空中作业平台与当前施工工位两侧的锚固横梁之间的连接;Step 2.5, release the connection between the aerial work platform and the anchor beams on both sides of the current construction station;
步骤三、平移Step three, translation
启动移动小车,促使移动小车前移,直至带动空中作业平台平移至下一个施工工位;Start the mobile trolley to move the mobile trolley forward until it drives the aerial work platform to move to the next construction station;
重复步骤一至步骤三,直至完成整个桥梁钢结构节段的整体拼装。Repeat steps 1 to 3 until the overall assembly of the entire bridge steel structure segment is completed.
基于上述的技术目的,相对于现有技术,本发明具有如下的优势:Based on above-mentioned technical purpose, with respect to prior art, the present invention has following advantage:
本发明所述的施工方法对海事、港航的影响最小,且经过标高测算,空中作业平台对通航净高亦无影响,同时空中节段吊装拼接完成之后,形成整体节段进行焊接拼装可以确保与整体节段吊装工艺相同的施工质量。The construction method described in the present invention has the least impact on maritime affairs and port and navigation, and after the elevation measurement, the aerial work platform has no influence on the clear height of the navigation. Same construction quality as integral segment hoisting process.
附图说明Description of drawings
图1是本发明所述的平移式空中临时作业平台的结构示意图;Fig. 1 is a structural representation of the translational aerial temporary work platform of the present invention;
图2是本发明图1中所示的空中作业平台悬挂安装在桥梁钢结构上的结构示意图;Fig. 2 is a structural schematic diagram of the aerial work platform shown in Fig. 1 of the present invention being suspended and installed on a bridge steel structure;
图3是图1中空中作业平台的平台侧面桁架体系的结构示意图;Fig. 3 is a schematic structural view of the platform side truss system of the aerial work platform in Fig. 1;
图4是图1中空中作业平台的底部平联的结构示意图;Fig. 4 is a schematic structural view of the bottom parallel connection of the aerial work platform in Fig. 1;
图5是图1中空中作业平台的端部平联的结构示意图;Fig. 5 is a schematic structural view of the end parallel connection of the aerial work platform in Fig. 1;
图6是采用履带吊吊装当前钢结构节段至空中作业平台的示意图;Fig. 6 is a schematic diagram of using a crawler crane to hoist the current steel structure segment to the aerial work platform;
图7是当前钢结构节段在空中作业平台完成拼装并安装至主桥钢结构上的结构示意图;Figure 7 is a structural schematic diagram of the current steel structure segment being assembled on the aerial work platform and installed on the steel structure of the main bridge;
图8是主桥钢结构节段的结构示意图;Fig. 8 is a structural schematic diagram of the steel structure section of the main bridge;
图中:1-1、上层桥面系;1-2、下层桥面系;1-3、桥梁左侧桁架的上弦杆;1-4、桥梁左侧桁架的下弦杆;1-5、桥梁右侧桁架的上弦杆;1-6、桥梁右侧桁架的下弦杆;2-1、下锚固横梁;2-2、上锚固横梁;3-1、平台右侧桁架体系;3-1-1、平台桁架上弦杆;3-1-2、平台桁架直腹杆;3-1-3、平台桁架斜腹杆;3-1-4、平台桁架下弦杆;3-1-5、平台横梁连接板; 3-2、平台左侧桁架体系;3-3、平台底联;3-4、防护栏杆;3-5、端部平联;3-6、底部平联;3-7、支撑横梁;4-1、悬挂横梁;4-2、轨道运输体系;5-上一节主桥桁架节段;6-1、下弦杆锚固点;6-2、上弦杆锚固点;7-待施工主桥桁架节段;8-履带吊履带。In the figure: 1-1, the upper deck system; 1-2, the lower deck system; 1-3, the upper chord of the left truss of the bridge; 1-4, the lower chord of the left truss of the bridge; 1-5, the bridge The upper chord of the right truss; 1-6, the lower chord of the right truss of the bridge; 2-1, the lower anchor beam; 2-2, the upper anchor beam; 3-1, the right truss system of the platform; 3-1-1 , platform truss upper chord; 3-1-2, platform truss straight web; 3-1-3, platform truss inclined web; 3-1-4, platform truss lower chord; 3-1-5, platform beam connection 3-2, truss system on the left side of the platform; 3-3, platform bottom connection; 3-4, protective railing; 3-5, end flat connection; 3-6, bottom flat connection; 3-7, support beam ;4-1. Suspension beam; 4-2. Rail transportation system; 5-The truss section of the last main bridge; 6-1. The anchor point of the lower chord; 6-2. The anchor point of the upper chord; Bridge truss segment; 8-crawler crawler.
具体实施方式Detailed ways
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。以下对至少一个示例性实施例的描述实际上仅仅是说明性的,决不作为对本发明及其应用或使用的任何限制。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。除非另外具体说明,否则在这些实施例中阐述的部件和步骤的相对布置、表达式和数值不限制本发明的范围。对于相关领域普通技术人员已知的技术、方法和设备可能不作详细讨论,但在适当情况下,所述技术、方法和设备应当被视为授权说明书的一部分。在这里示出和讨论的所有示例中,任何具体值应被解释为仅仅是示例性的,而不是作为限制。因此,示例性实施例的其它示例可以具有不同的值。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. The following description of at least one exemplary embodiment is merely illustrative in nature and in no way taken as limiting the invention, its application or uses. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention. The relative arrangements, expressions and numerical values of components and steps set forth in these embodiments do not limit the scope of the present invention unless specifically stated otherwise. Techniques, methods and devices known to those of ordinary skill in the relevant art may not be discussed in detail, but where appropriate, such techniques, methods and devices should be considered part of the Authorized Specification. In all examples shown and discussed herein, any specific values should be construed as illustrative only, and not as limiting. Therefore, other examples of the exemplary embodiment may have different values.
如图1至8所示,本发明所述的用于桥梁钢结构节段整体拼装的平移式空中临时作业平台,搭建在已完工的桥梁钢结构上所设置的当前施工工位的悬臂端。所述的平移式空中临时作业平台整体包括两部分,其中一部分为平台前移设备,另一部分则为空中作业平台。平台前移设备安装在已搭建好的上一节钢结构节段5的上层桥面系1-1上,而空中作业平台则呈悬臂安装并具有两种安装状态,以使得空中作业平台一方面可以作为平台前移设备步进式前移的支撑,另一方面则可以作为待施工钢结构节段7的临时作业场所,从而可以在空中作业平台完成钢结构节段的拼装,为桥梁钢结构的节段整体焊接拼装做准备。由此可见,本发明将主桥钢结构节段的地面作业转移到空中,整合了节段整体拼装的优势,保证施工质量的前提下,有效地降低了海事、港航的影响,且经过标高测算,空中作业平台对通航净高亦无影响。As shown in Figures 1 to 8, the translational aerial temporary work platform for the overall assembly of bridge steel structure segments according to the present invention is built on the cantilever end of the current construction station set on the completed bridge steel structure. The translational aerial temporary work platform as a whole includes two parts, one of which is a platform forward moving device, and the other part is an aerial work platform. The platform moving equipment is installed on the upper bridge deck system 1-1 of the previous
本发明中,平移式空中临时作业平台包括平台前移设备、临时连接体系以及空中作业平台,其中:In the present invention, the translational aerial temporary work platform includes platform forward equipment, temporary connection system and aerial work platform, wherein:
所述的临时连接体系,包括锚固横梁;所述的锚固横梁至少包括两组,一组安装在当前施工工位的左侧桁架体系上,为左侧锚固横梁,另一组则安装在当前施工工位的右侧桁架体系上,为右侧锚固钢梁;The temporary connection system includes anchoring beams; the anchoring beams include at least two groups, one group is installed on the left truss system of the current construction station, which is the left anchoring beam, and the other group is installed on the current construction site. On the truss system on the right side of the station, it is the right anchoring steel beam;
所述的平台前移设备包括自移式横梁结构、轨道以及履带吊,而自移式横梁结构则包括悬挂横梁4-1、顶升设备以及移动小车4-2;悬挂横梁4-1横跨当前施工工位的上层桥面系1-1设置,移动小车4-2包括两组,对称地安装在悬挂横梁4-1的下表面;履带吊置于当前施工工位的上层桥面系1-1上;轨道包括两条,分别通过左、右侧锚固横梁支撑并能够通过履带吊吊装至下一个施工工位对应侧的锚固横梁上;顶升设备悬挂安装在悬挂横梁4-1下表面,并能够促使移动小车4-2安装在对应位置处的轨道中或者促使移动小车4-2脱离对应位置处的轨道;The platform forward moving equipment includes a self-moving beam structure, a track and a crawler crane, while the self-moving beam structure includes a suspension beam 4-1, jacking equipment and a mobile trolley 4-2; the suspension beam 4-1 spans The upper deck system 1-1 of the current construction station is set, and the mobile trolley 4-2 includes two groups, which are symmetrically installed on the lower surface of the suspension beam 4-1; the crawler belt is placed on the upper deck system 1 of the current construction station -1 above; two rails are supported by the left and right anchor beams respectively and can be hoisted to the anchor beams on the corresponding side of the next construction station by crawler cranes; the jacking equipment is suspended and installed on the lower surface of the suspension beam 4-1 , and can impel the mobile trolley 4-2 to be installed in the track at the corresponding position or impel the mobile trolley 4-2 to break away from the track at the corresponding position;
所述的空中作业平台,包括平台固定端以及位于平台固定端前端的平台悬臂端;所述的平台固定端能够分别与悬挂横梁4-1、锚固钢梁择一固定连接。The aerial work platform includes a fixed end of the platform and a cantilever end of the platform located at the front end of the fixed end of the platform; the fixed end of the platform can be respectively fixedly connected with one of the suspension beam 4-1 and the anchoring steel beam.
优选地,所述的空中作业平台包括平台桁架体系、平台底联3-3以及端部平联3-5;所述的平台桁架体系包括两根,对应为左侧平台桁架体系3-2以及右侧平台桁架体系3-1;左侧平台桁架体系3-2与右侧平台桁架体系3-1结构一致并相互平行设置;左侧平台桁架体系3-2与右侧平台桁架体系3-1两者的尾端之间通过端部平联3-5连接成一体,且左侧平台桁架体系3-2与右侧平台桁架体系3-1两者的下弦杆之间在紧靠着端部平联3-5的位置处通过平台底联3-3连接。Preferably, the aerial work platform includes a platform truss system, a platform bottom connection 3-3 and an end parallel connection 3-5; the platform truss system includes two, corresponding to the left platform truss system 3-2 and The right platform truss system 3-1; the left platform truss system 3-2 and the right platform truss system 3-1 have the same structure and are arranged parallel to each other; the left platform truss system 3-2 and the right platform truss system 3-1 The tail ends of the two are connected into one body through the end parallel connection 3-5, and the bottom chords of the left platform truss system 3-2 and the right platform truss system 3-1 are close to the ends The position of the flat joint 3-5 is connected by the bottom joint 3-3 of the platform.
优选地,所述的平台桁架体系包括平台桁架上弦杆3-1-1、平台桁架直腹杆3-1-2、平台桁架斜腹杆3-1-3以及平台桁架下弦杆3-1-4;平台桁架上弦杆3-1-1、平台桁架下弦杆3-1-4相互平行设置,且平台桁架上弦杆3-1-1、平台桁架下弦杆3-1-4之间通过若干根平台桁架直腹杆3-1-2连接,相邻的两根平台桁架直腹杆3-1-2之间通过所述的平台桁架斜腹杆3-1-3连接。Preferably, the platform truss system includes platform truss upper chord 3-1-1, platform truss straight web 3-1-2, platform truss diagonal 3-1-3 and platform truss lower chord 3-1- 4. The upper chord 3-1-1 of the platform truss and the lower chord 3-1-4 of the platform truss are arranged parallel to each other, and several The platform truss straight webs 3-1-2 are connected, and two adjacent platform truss straight webs 3-1-2 are connected through the platform truss diagonals 3-1-3.
优选地,平台桁架下弦杆3-1-4在靠近尾端的位置处设置有若干块平台横梁连接板3-1-5,平台底联3-3的一侧与左侧平台桁架体系3-2的下弦杆上的平台横梁连接板3-1-5连接,另一侧则与右侧平台桁架体系3-1的下弦杆上的平台横梁连接板3-1-5连接。Preferably, the lower chord 3-1-4 of the platform truss is provided with several platform beam connecting plates 3-1-5 near the tail end, and one side of the platform bottom link 3-3 is connected to the left platform truss system 3-2. The platform beam connecting plate 3-1-5 on the lower chord of the platform truss system 3-1 is connected, and the other side is connected with the platform beam connecting plate 3-1-5 on the lower chord of the right platform truss system 3-1.
优选地,所述的平台底联3-3包括支撑横梁3-7以及底部平联3-6;所述支撑横梁3-7的数量为三根,对应为第一至第三支撑横梁3-7,且第二支撑横梁3-7处于第一、第三支撑横梁3-7之间,三根支撑横梁3-7相互平行并等距布置;所述的底部平联3-6包括两根对拼的V形架,V形架的两个端点分别与第二支撑横梁3-7连接,而顶点则与第一支撑横梁3-7或第三支撑横梁3-7连接;Preferably, the platform bottom link 3-3 includes a supporting beam 3-7 and a bottom connecting beam 3-6; the number of the supporting beams 3-7 is three, corresponding to the first to third supporting beams 3-7 , and the second support beam 3-7 is between the first and third support beams 3-7, the three support beams 3-7 are arranged parallel to each other and equidistant; The V-shaped frame, the two end points of the V-shaped frame are respectively connected with the second support beam 3-7, and the apex is connected with the first support beam 3-7 or the third support beam 3-7;
平台横梁连接板3-1-5的数量也为三个;所述三根支撑横梁3-7的两端分别与相应侧的平台横梁连接板3-1-5对应连接。The number of platform beam connecting plates 3-1-5 is also three; the two ends of the three supporting beams 3-7 are respectively connected with the corresponding side platform beam connecting plates 3-1-5.
优选地,所述的端部平联3-5包括矩形外框以及分别对应地将矩形外框的两对角线连接的连接斜撑;矩形外框通过四根杆件相互围接而形成;每个围接点均设置有一块节点板。Preferably, the end parallel connection 3-5 includes a rectangular outer frame and connecting braces correspondingly connecting two diagonal lines of the rectangular outer frame; the rectangular outer frame is formed by surrounding four rods; Each enclosure point is provided with a gusset plate.
优选地,所述的左侧锚固横梁包括两排,其中一排安装在桥梁左侧桁架的上弦杆1-3上,为第一左侧锚固横梁2-1,另一排则安装在桥梁左侧桁架的下弦杆1-4上,为第二左侧锚固横梁2-2;所述的右侧锚固横梁包括两排,其中一排安装在桥梁右侧桁架的上弦杆1-5上,为第一右侧锚固横梁,另一排则安装在桥梁右侧桁架的下弦杆1-6上,为第二右侧锚固横梁;此时,两条轨道分别通过第一左侧锚固横梁2-1、第一右侧锚固横梁对应支撑。具体地,桥梁左侧桁架的上弦杆1-3的对应位置处设置有上弦杆锚固点6-2,用于安装第二左侧锚固横梁2-2,桥梁左侧桁架的下弦杆1-4的对应位置处设置有下弦杆锚固点6-1,用于安装第一左侧锚固横梁2-1,同理,桥梁右侧桁架的对应位置处也设置相应的锚固点,用于安装相应的锚固横梁。Preferably, the left anchoring beams include two rows, one of which is installed on the upper chord 1-3 of the left truss of the bridge, which is the first left anchoring beam 2-1, and the other row is installed on the left side of the bridge. On the lower chord 1-4 of the side truss, it is the second left anchor beam 2-2; the right anchor beam includes two rows, one of which is installed on the upper chord 1-5 of the bridge right truss, which is The first right anchor beam, and the other row is installed on the lower chord 1-6 of the right truss of the bridge, which is the second right anchor beam; at this time, the two tracks respectively pass through the first left anchor beam 2-1 1. The first right side anchor beam corresponds to the support. Specifically, an upper chord anchorage point 6-2 is provided at the corresponding position of the upper chord 1-3 of the left truss of the bridge for installing the second left anchor beam 2-2, and the lower chord 1-4 of the left truss of the bridge A lower chord anchorage point 6-1 is set at the corresponding position of the bridge for installing the first left anchor beam 2-1. Similarly, a corresponding anchor point is also set at the corresponding position of the bridge right truss for installing the corresponding Anchor beams.
优选地,左侧平台桁架体系3-2与右侧平台桁架体系3-1两者的前端之间缺口设置或者通过防护栏杆3-4连接。Preferably, a gap is set between the front ends of the left platform truss system 3-2 and the right platform truss system 3-1 or is connected by a protective railing 3-4.
基于上述的用于桥梁钢结构节段整体拼装的平移式空中临时作业平台,本发明提供了该平移式空中临时作业平台的平移方法,包括如下步骤:Based on the above-mentioned translational temporary aerial work platform for the overall assembly of bridge steel structure segments, the present invention provides a translation method for the translational aerial temporary work platform, comprising the following steps:
步骤一、作业准备Step 1. Homework preparation
为在空中作业平台中进行待拼接桥梁钢结构节段的拼装以及与已完工的桥梁钢结构之间的整体拼装做准备,具体包括如下步骤:Prepare for the assembly of bridge steel structure segments to be spliced in the aerial work platform and the overall assembly with the completed bridge steel structure, including the following steps:
步骤1.1、将空中作业平台的两侧平台桁架体系与当前施工工位两侧的锚固横梁焊接固定,实现空中作业平台在桥梁钢结构上的悬吊;Step 1.1. Weld and fix the platform truss system on both sides of the aerial work platform and the anchor beams on both sides of the current construction station to realize the suspension of the aerial work platform on the bridge steel structure;
步骤1.2、解除空中作业平台与悬挂横梁4-1之间的联系;Step 1.2, release the connection between the aerial work platform and the suspension beam 4-1;
步骤1.3、顶升气缸顶出;Step 1.3, the jacking cylinder is ejected;
步骤二、移位准备Step 2. Preparation for shifting
在当前施工工位完成待拼接桥梁钢结构节段的整体拼装后,为空中作业平台前移至下一个施工工位做准备,具体包括如下步骤:After the current construction station completes the overall assembly of the bridge steel structure segments to be spliced, prepare for the aerial work platform to move forward to the next construction station, including the following steps:
步骤2.1、在下一个施工工位对应的桥梁钢结构两侧分别安装有一组锚固横梁;每组锚固横梁均包括两层,对应地安装在同侧桁架体系的上、下弦杆上;每层锚固横梁均至少包括两根,每层锚固横梁所包含的各锚固横梁均沿着桥梁钢结构的纵桥向间隔分布;Step 2.1. Install a set of anchor beams on both sides of the bridge steel structure corresponding to the next construction station; each set of anchor beams includes two layers, which are installed on the upper and lower chords of the truss system on the same side; each layer of anchor beams Each includes at least two anchor beams, and the anchor beams included in each layer are distributed at intervals along the longitudinal bridge direction of the bridge steel structure;
步骤2.2、采用履带吊将轨道吊装至下一个施工工位对应的上层锚固横梁上进行铺设;Step 2.2, use the crawler crane to hoist the track to the upper anchor beam corresponding to the next construction station for laying;
步骤2.3、顶升气缸回缩,以将悬挂横梁4-1下的移动小车4-2嵌装在相应侧的轨道中;Step 2.3, the jacking cylinder is retracted, so that the mobile trolley 4-2 under the suspension beam 4-1 is embedded in the track on the corresponding side;
步骤2.4、将左侧平台桁架体系3-2、右侧平台桁架体系3-1紧靠着尾端的上弦杆分别固定到悬挂横梁4-1的对应位置处,以使得空中作业平台悬吊在悬挂横梁4-1上;Step 2.4, fix the upper chords of the left platform truss system 3-2 and the right platform truss system 3-1 close to the tail end to the corresponding positions of the suspension beam 4-1, so that the aerial work platform is suspended on the suspension On beam 4-1;
步骤2.5、解除空中作业平台与当前施工工位两侧的锚固横梁之间的连接;Step 2.5, release the connection between the aerial work platform and the anchor beams on both sides of the current construction station;
步骤三、平移Step three, translation
启动移动小车4-2,促使移动小车4-2前移,直至带动空中作业平台平移至下一个施工工位;Start the mobile trolley 4-2, prompting the mobile trolley 4-2 to move forward until the aerial work platform is moved to the next construction station;
重复步骤一至步骤三,直至完成整个桥梁钢结构节段的整体拼装。Repeat steps 1 to 3 until the overall assembly of the entire bridge steel structure segment is completed.
实施例1Example 1
本实施例主要阐释空中作业平台的结构设计,具体如下:This embodiment mainly explains the structural design of the aerial work platform, specifically as follows:
(1)结构设计原则(1) Structural Design Principles
1)满足竖向荷载下的承载能力要求1) Meet the bearing capacity requirements under vertical load
主桥钢结构主跨高度梁高为6米,为满足钢结构节段构件空中拼装要求,空中作业平台的结构高度将会接近8米,选择桁架结构体系增强结构整体承载能力。同时参考悬臂浇筑混凝土连续梁施工挂篮结构进行结构设计,但是空中作业平台因节段构件吊装需求,悬挑端正上方位置无法设置水平向横向联系,因此桁架整体结构设计时需考虑平台施工过程中的整体稳定性。The steel structure of the main bridge has a main span height of 6 meters. In order to meet the requirements for aerial assembly of steel structure segments, the structural height of the aerial work platform will be close to 8 meters. The truss structure system is selected to enhance the overall bearing capacity of the structure. At the same time, refer to the hanging basket structure of cantilever pouring concrete continuous beam construction for structural design, but due to the hoisting requirements of segmental components on the aerial work platform, the position directly above the cantilever end cannot be provided with horizontal and horizontal connections. Therefore, the overall structure design of the truss needs to consider the platform during construction. overall stability.
2)满足横向荷载下的承载能力要求2) Meet the bearing capacity requirements under lateral load
悬臂空中作业平台钢结构焊接需设置防风措施,因此平台悬臂端将会承受较大的横向风荷载,对整体作业平台的稳定性和结构受力存在较大影响,控制作业平台设计、计算时需充分考虑横向风荷载的影响。The steel structure welding of the cantilever aerial work platform needs to be equipped with windproof measures. Therefore, the cantilever end of the platform will bear a large transverse wind load, which will have a great impact on the stability of the overall work platform and the structural force. It is necessary to control the design and calculation of the work platform. Fully consider the influence of lateral wind load.
3)适应桥梁横坡的影响3) To adapt to the influence of bridge cross slope
特大桥结构横断面存在2%的横坡,造成左右桁架空间标高不同,从而影响空中作业平台的锚固结构设置,因此空中作业平台设计时需考虑平台锚固措施在横坡影响下的合理性。There is a 2% cross-slope in the cross-section of the super-large bridge structure, which causes the space elevation of the left and right trusses to be different, which affects the anchoring structure setting of the aerial work platform. Therefore, the rationality of platform anchorage measures under the influence of cross-slope must be considered in the design of the aerial work platform.
(2)结构构件设计(2) Design of structural components
空中作业平台主要承重结构采用桁架结构,主桁弦杆采用HW400×400×13×21,其中上弦杆两侧外附10mm钢板形成矩形截面,主桁直腹杆采用HW300×300×10×15,斜腹杆采用交叉拉杆设计,采用下前支点前方位置斜腹杆采用双拼25a槽钢(肢背相向),其余位置采用双拼20a槽钢(肢背相向)体系。The main load-bearing structure of the aerial work platform adopts a truss structure, and the main truss chord adopts HW400×400×13×21, of which 10mm steel plates are attached to both sides of the upper chord to form a rectangular section, and the main truss straight web adopts HW300×300×10×15. The oblique web bar is designed with cross tie rods, and the oblique web bar in the front position of the lower front fulcrum adopts a double-piece 25a channel steel (legs and backs facing each other), and the rest of the position adopts a double-piece 20a channel steel (legs and backs facing each other) system.
桁架前三根竖杆下方设置双拼HW400工字钢节段构件支撑横梁3-7,同时作为操作平台分配梁的支撑横梁3-7使用,支撑横梁3-7之间设置菱形平联,同时为增加左右桁架间的整体稳定,在桁架端部设置左右桁架横向联系(双拼20a槽钢),空中作业平台的结构设计图详见图3-5所示。Under the first three vertical bars of the truss, the supporting beams 3-7 of the double HW400 I-shaped steel segment members are set, and they are also used as the supporting beams 3-7 of the distribution beam of the operation platform. To increase the overall stability between the left and right trusses, the left and right trusses are connected horizontally at the ends of the trusses (double 20a channel steel). The structural design of the aerial work platform is shown in Figure 3-5.
(3)结构锚固设计(3) Structural anchor design
主桥采用全焊钢结构体系,故不额外设置施工用临时螺栓体系。因此,空中作业平台通过焊缝与主桥主桁体系连接。The main bridge adopts an all-welded steel structure system, so there is no additional temporary bolt system for construction. Therefore, the aerial work platform is connected to the main truss system of the main bridge through welds.
空中作业平台的边界约束通过“HM700型钢”提供:The boundary constraints of the aerial work platform are provided by "HM700 steel":
1)连接用型钢(即为上述的锚固横梁)位于主桥主桁体系弦杆的顶板,其中,上弦采用楔形垫块调平,下弦采用30mm钢板调平;1) The section steel for connection (that is, the above-mentioned anchor beam) is located on the top plate of the chord of the main truss system of the main bridge, wherein the upper chord is leveled with wedge-shaped pads, and the lower chord is leveled with 30mm steel plates;
2)空中作业平台依据腹杆的外挑加劲与连接用型钢连接,不仅平衡纵坡对安装精度的影响,而且可以适应主桁结构2%的横坡要求;2) The aerial work platform is connected with the connecting section steel according to the external stiffening of the web, which not only balances the influence of the longitudinal slope on the installation accuracy, but also can adapt to the 2% transverse slope requirement of the main truss structure;
3)上弦反力相对较小(不足300kN),故楔形垫块采用双侧角焊缝连接,型钢与上弦间不设置额外焊缝;3) The upper chord reaction force is relatively small (less than 300kN), so the wedge block is connected by double-sided fillet welds, and no additional welds are set between the profile steel and the upper chord;
4)下弦反力较大,型钢与下弦腹杆焊接,以承担竖向反力作用,型钢与下弦顶板间设置30mm垫块找平,采用双侧角焊缝连接,以抵抗水平反力;4) The reaction force of the lower chord is relatively large, and the section steel is welded to the lower chord web bar to bear the vertical reaction force. A 30mm pad is set between the section steel and the lower chord top plate for leveling, and the double-sided fillet weld is used to resist the horizontal reaction force;
5)上、下弦杆每个节段端部设置1道连接型钢,上弦型钢可在现场焊接,亦可在工厂制作,但下弦型钢必须在工厂焊接,否则仰焊连接难度较大。5) A connection section steel is provided at the end of each segment of the upper and lower chords. The upper chord section steel can be welded on site or manufactured in the factory, but the lower chord section steel must be welded in the factory, otherwise it is more difficult to connect by overhead welding.
此外,上弦顶板焊缝清理后浇筑沥青铺装,对外观质量要求相对较低;下弦的腹杆与连接用型钢间、下弦顶板与找平垫块间均采用角焊缝连接。其中,内侧腹板角焊缝与顶板角焊缝为俯焊清理,相对容易,外侧腹板角焊缝需仰焊清理,难度较高,平台锚固设计如图2所示。In addition, the asphalt pavement is poured after cleaning the welds of the upper chord roof, which has relatively low requirements on the appearance quality; fillet welds are used to connect the web members of the lower chord and the connecting steel, and between the lower chord roof and leveling pads. Among them, the fillet welds of the inner web and the top plate are cleaned by downward welding, which is relatively easy, and the fillet welds of the outer web need to be cleaned by overhead welding, which is more difficult. The platform anchorage design is shown in Figure 2.
(4)结构构件验算(4) Check calculation of structural components
根据截面设计情况利用迈达斯软件进行结构验算,进行计算时外部荷载按照1600KN进行考虑,同时考虑垂直平台的横向风荷载,并按照事情情况施加锚固荷载。各个杆件中,双拼槽钢结构采用肢背相向构造,结构外边距270mm,即HW300×300×10×15工字钢顶底板净距。According to the cross-section design, Midas software is used to check the structure. When calculating, the external load is considered as 1600KN. At the same time, the transverse wind load of the vertical platform is considered, and the anchor load is applied according to the situation. Among the various rods, the double channel steel structure adopts the structure with the limbs and the back facing each other, and the outer margin of the structure is 270mm, that is, the net distance between the top and bottom plates of HW300×300×10×15 I-shaped steel.
迈达斯计算内力计算结果表示,空中作业平台各杆件最大应力为139Mpa,满足容许应力法控制值140Mpa。同时利用迈达斯计算软件对空中作业平台整体稳定性进行验算,计算结果表明空中作业平台的稳定系数为4.3,满足结构稳定要求。The internal force calculation results of Midas show that the maximum stress of each member of the aerial work platform is 139Mpa, which meets the allowable stress method control value of 140Mpa. At the same time, Midas calculation software is used to check the overall stability of the aerial work platform. The calculation results show that the stability coefficient of the aerial work platform is 4.3, which meets the structural stability requirements.
实施例2Example 2
本实施例主要阐释空中作业平台在桥梁施工过程中的前移,具体内容如下:This embodiment mainly explains the forward movement of the aerial work platform during the bridge construction process, and the specific content is as follows:
空中作业平台在一个节段施工完成之后,将作业平台移动至下一个节段进行施工,作业平台的前移设备是平台整体结构的重要组成部分。平台整体重量将会超过60吨,因此桥面使用的履带吊无法完成平台的前移工作,项目部整体考虑设计了一种轨道驼移设备(即指前移设备),完成平台的整体前移。After the construction of one section of the aerial work platform is completed, the work platform is moved to the next section for construction. The forward moving equipment of the work platform is an important part of the overall structure of the platform. The overall weight of the platform will exceed 60 tons, so the crawler crane used on the bridge deck cannot complete the forward movement of the platform. The project department has considered and designed a track camel movement equipment (referred to as forward movement equipment) to complete the overall forward movement of the platform .
如图1所示,轨道驼移设备设置在锚固横梁位置,轨道铺设前增设1-2道横梁,同时利用楔形钢板垫平轨道横坡,抬升千斤顶设置在悬挂横梁4-1下方,将作业平台整体抬升后安装轨道和横移小车,利用前面移动动力装置向前移动,到达指定位置后下方。As shown in Figure 1, the track moving equipment is set at the anchoring beam position, and 1-2 beams are added before the track is laid. After the overall lifting, install the track and the traversing trolley, and use the front moving power device to move forward and reach the designated position.
实施例3Example 3
本实施例主要阐释基于上述空中作业平台的主跨节段拼装工艺,具体内容如下:This embodiment mainly explains the main span segment assembly process based on the above-mentioned aerial work platform, and the specific content is as follows:
3.1.主跨钢结构节段划分3.1. Segment division of main span steel structure
(1)节段划分确定(1) Determination of segment division
项目部根据主桥钢结构空中作业平台施工情况,进行主桥钢结构节段划分,主桥钢结构节段的结构如图8所示,包括主桥节段上弦9-1、主桥节段下弦,主桥钢结构节段尾端与已完成的主桥结构之间能够形成矩形空间9-3,可有效的控制节段拼装过程中拼装误差的累计,确保钢结构整体线型。上弦杆支撑点落于已完成的主桥结构,在分摊空中作业平台荷载同时,有利于整体节段的位置调整。According to the construction situation of the steel structure aerial work platform of the main bridge, the project department divided the steel structure sections of the main bridge. The structure of the steel structure sections of the main bridge is shown in Figure 8, including the upper chord 9-1 of the main bridge section, In the lower chord, a rectangular space 9-3 can be formed between the end of the main bridge steel structure segment and the completed main bridge structure, which can effectively control the accumulation of assembly errors during the segment assembly process and ensure the overall line shape of the steel structure. The support point of the upper chord falls on the completed main bridge structure, which is conducive to the position adjustment of the whole segment while sharing the load of the aerial work platform.
(2)横断面形式确定(2) Determination of cross-sectional form
当上层桥面、下层桥面以及上下弦杆均为2%横坡时,考虑到空中作业平台安装锚固需求,维持原有上层、下层桥面板2%横坡外,将上弦杆底板、下弦杆上下顶板调整为水平,同时为满足空中作业平台使用要求,上层桥面系1-1中悬臂板后装。调整完成之后大桥主跨空中作业平台施工时,下层锚固横梁位于下弦杆顶面(水平设置),同时下弦杆底面调整为水平,以保证桁架安装前期的临时稳定。When the upper deck, the lower deck, and the upper and lower chords are all 2% transverse slopes, considering the installation and anchoring requirements of the aerial work platform, the original upper and lower deck decks are maintained with a 2% transverse slope, and the upper chord bottom plate and lower chord The upper and lower roof plates are adjusted to be horizontal. At the same time, in order to meet the requirements for the use of aerial work platforms, the upper deck is installed after the 1-1 middle cantilever plate. After the adjustment is completed, when the aerial work platform of the main span of the bridge is constructed, the lower anchor beam is located on the top surface of the lower chord (horizontal setting), and the bottom surface of the lower chord is adjusted to be horizontal to ensure the temporary stability of the truss installation in the early stage.
3.2.履带吊节段拼装3.2. Segment assembly of crawler crane
空中作业平台完成安装之后履带起重机就位,桥面锚固横梁间距空隙设置为7米,100吨履带吊最大外形尺寸为7780×6350(长×宽)mm,7米宽的履带吊行车空间可满足履带吊的行走,同时在一定程度上锚固横梁可作为履带起重机的限位装置(端部锚固横梁加长),可保证履带吊使用安全。而节段构件通过桥面运输设备(限位轨道+运输平板车)送至履带吊后方,由履带吊完成节段吊装。After the aerial work platform is installed, the crawler crane is in place, and the gap between the anchor beams on the bridge deck is set to 7 meters. The maximum external dimension of the 100-ton crawler crane is 7780×6350 (length×width) mm, and the space for the crawler crane with a width of 7 meters can meet The crawler crane is moving, and the anchor beam can be used as a limit device for the crawler crane to a certain extent (the anchor beam at the end is lengthened), which can ensure the safety of the crawler crane. The segmental components are sent to the rear of the crawler crane through the bridge deck transportation equipment (limiting track + transport flatbed truck), and the segmental hoisting is completed by the crawler crane.
3.3.步履式千斤顶调整3.3. Walking jack adjustment
整体节段在空中作业平台完成拼装后立业步履式千斤顶完成最后的位置调整,步履式千斤顶可利用“顶”、“推”的两个步骤实现整体节段标高和平面位置的调整,以保证主桥整体线型的准确。After the whole segment is assembled on the aerial work platform, the Liye walking jack completes the final position adjustment. The walking jack can use the two steps of "lifting" and "push" to realize the adjustment of the overall segment elevation and plane position to ensure that the main The overall alignment of the bridge is accurate.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211400936.4A CN116163213B (en) | 2022-11-09 | 2022-11-09 | A translational aerial temporary work platform and its method for the integral assembly of bridge steel structure segments. |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211400936.4A CN116163213B (en) | 2022-11-09 | 2022-11-09 | A translational aerial temporary work platform and its method for the integral assembly of bridge steel structure segments. |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN116163213A true CN116163213A (en) | 2023-05-26 |
| CN116163213B CN116163213B (en) | 2026-04-21 |
Family
ID=86417066
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211400936.4A Active CN116163213B (en) | 2022-11-09 | 2022-11-09 | A translational aerial temporary work platform and its method for the integral assembly of bridge steel structure segments. |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116163213B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116586876A (en) * | 2023-07-07 | 2023-08-15 | 张立新 | A steel structure three-dimensional reference working platform |
| CN117587706A (en) * | 2023-11-21 | 2024-02-23 | 宁波市政工程建设集团股份有限公司 | Part-piece assembly method of main bridge main span steel structure segments based on cantilever bridge erecting machine |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101806053A (en) * | 2010-05-17 | 2010-08-18 | 大连船舶重工集团有限公司 | Integral installation method of cantilever beams of self lifting type well drilling platform |
| CN106906756A (en) * | 2017-04-26 | 2017-06-30 | 武汉二航路桥特种工程有限责任公司 | Can Fast Installation remove maintenance operation platform and its construction method |
| CN110130230A (en) * | 2019-06-24 | 2019-08-16 | 中铁二局集团有限公司 | A kind of automatic traveling lifting lane-change formula trolley installation sound barrier construction method |
| CN211498464U (en) * | 2019-11-08 | 2020-09-15 | 中交二航局第四工程有限公司 | A steel truss girder maintenance vehicle track high-altitude transportation and installation platform |
| WO2021078310A1 (en) * | 2019-10-21 | 2021-04-29 | 宁波市政工程建设集团股份有限公司 | Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor |
| CN114476962A (en) * | 2022-01-21 | 2022-05-13 | 中铁十一局集团有限公司 | A steel-concrete composite beam erection system based on bridge deck crane |
-
2022
- 2022-11-09 CN CN202211400936.4A patent/CN116163213B/en active Active
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101806053A (en) * | 2010-05-17 | 2010-08-18 | 大连船舶重工集团有限公司 | Integral installation method of cantilever beams of self lifting type well drilling platform |
| CN106906756A (en) * | 2017-04-26 | 2017-06-30 | 武汉二航路桥特种工程有限责任公司 | Can Fast Installation remove maintenance operation platform and its construction method |
| CN110130230A (en) * | 2019-06-24 | 2019-08-16 | 中铁二局集团有限公司 | A kind of automatic traveling lifting lane-change formula trolley installation sound barrier construction method |
| WO2021078310A1 (en) * | 2019-10-21 | 2021-04-29 | 宁波市政工程建设集团股份有限公司 | Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor |
| CN211498464U (en) * | 2019-11-08 | 2020-09-15 | 中交二航局第四工程有限公司 | A steel truss girder maintenance vehicle track high-altitude transportation and installation platform |
| CN114476962A (en) * | 2022-01-21 | 2022-05-13 | 中铁十一局集团有限公司 | A steel-concrete composite beam erection system based on bridge deck crane |
Non-Patent Citations (1)
| Title |
|---|
| 陈旭;: "大跨连续钢箱梁驮移安装施工技术研究", 城市道桥与防洪, no. 10, 15 October 2016 (2016-10-15), pages 104 - 106 * |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116586876A (en) * | 2023-07-07 | 2023-08-15 | 张立新 | A steel structure three-dimensional reference working platform |
| CN117587706A (en) * | 2023-11-21 | 2024-02-23 | 宁波市政工程建设集团股份有限公司 | Part-piece assembly method of main bridge main span steel structure segments based on cantilever bridge erecting machine |
Also Published As
| Publication number | Publication date |
|---|---|
| CN116163213B (en) | 2026-04-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US11634877B2 (en) | Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor | |
| CN202936736U (en) | Cable-stayed bridge composite beam construction bridge floor crane | |
| CN115748513A (en) | Construction method of ultra-small high-span-ratio all-welded steel truss girder bridge based on cantilever aerial work platform | |
| CN115821798A (en) | Spare part type cantilever assembly aerial work platform for all-welded steel truss girder bridge and construction method thereof | |
| CN113957793A (en) | Construction method for prefabricating box girder support in complex urban environment | |
| CN201102544Y (en) | Hanging train traffic system of hanging rail | |
| CN116163213B (en) | A translational aerial temporary work platform and its method for the integral assembly of bridge steel structure segments. | |
| CN115058957A (en) | Dual-purpose trestle support structure | |
| CN114476962B (en) | A steel-concrete composite beam erection system based on bridge crane | |
| CN115748512A (en) | Main bridge main span steel structure segment construction method based on cantilever aerial work platform | |
| CN116427283A (en) | A construction method for erecting prefabricated girders of small-radius bridges in mountainous areas | |
| CN205205685U (en) | Span wire pier is function portal device at most | |
| CN117166341A (en) | System and method for installing under-supported steel box arch rib tie arch bridge across water bodies | |
| CN112211112A (en) | Steel box girder installation method adopting double-guide-girder erection machine on existing bridge | |
| CN108222051A (en) | A kind of contact net upright post basic of railway steel reinforced concrete bondbeam and steel reinforced concrete combination bridge | |
| CN206800173U (en) | Floorings Prestressed Concrete I Beams are poured after a kind of railway | |
| CN111705682B (en) | Construction method and equipment for dismantling and reconstructing upper structure of widening bridge across electrified railway | |
| CN221142500U (en) | Steel truss girder falling construction tool | |
| CN219637728U (en) | Aerial working platform for cantilever assembly ultra-small high span ratio all-welded steel truss bridge | |
| CN219637691U (en) | Aerial temporary operation platform for integrally assembling bridge steel structure sections | |
| CN115748468B (en) | Overall assembly method of bridge steel structure segments based on aerial segment assembly | |
| CN219637692U (en) | Rail camel moving equipment of aerial operation platform | |
| CN214733976U (en) | Lifting station device for lifting overweight cable of cable-stayed bridge | |
| CN116657476A (en) | Middle-small span corrugated web I-shaped steel girder bridge and installation method | |
| CN116949946A (en) | Construction method for bridge bridging of small-radius curve bridge |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |
